Clearance List EGHVO

S/S Name
Site Readiness for Commissioning ABB Ref. :

Pre checks
YES NO NA Remarks
1 Test Formats are available
2 Method of statements have been
Submitted and available
3 Calibration certificates are available
4 FAT reports are available
5 Visual Inspections have been
conducted
6 testing program schedule has been
submitted and approved
7 Availability of proper light and
ventilation around Testing are
8 Testing area is neat and clean
9 PTW is issued
10 Impact recorder reports have been
verified and results are satisfactory
11 Testing area free from dust which may
be effect the test results
12 Aggressive gases that will effect
personnel or equipment
13 Outlets powered up and suitable
for tooling and test equipment
14 lifting devices or material
transportation which may be needed
during commissioning
Installation clearance
1 Verify all shipping bracing is removed
2 installation of all equipment and their
accessories are completed and correct
according to the approved documents
3 All bolts and nuts are marked by
manufacture to enable detection of
loose connection, if these marking are
shifted re-tighten nuts
4 Proper eathing for Equipment has
been provided
5 Installation scaffoldings have been

Representative Commissioning Installation Safety Civil

Name

Signature

Date
Clearance List EGHVO
S/S Name
Site Readiness for Commissioning ABB Ref. :

Removed
6 Unwanted materials have been
removed
7 cable laying and termination of all
related cables are completed and
tagged.
Safety clearance
1 Risk assessment is available
2 Evacuation plan is fixed near testing
area
3 Ensure work only on de-energized
equipment. Always de-energize and
ground the
Equipment before performing any
tests
4 Presence of danger notice and other
warning notices
5 Tool box has been conducted
6 Safety induction has been conducted
7 Testing area has been identified and
barricading
8 Weather is not adverse
9 Confirm safety officer will be available
during commencing of testing
Civil clearance
1 Proper egress and access provided
to Testing area

2 Scaffoldings have been removed


3 Floor has been sealed and close
4 All openings around the testing area
have been closed
5 Confirm around the testing area
No other work is conducted such
as(Drill, painting , shifting material ,etc
)

Representative Commissioning Installation Safety Civil