RECITALS;
A. SCOPE OF WORK
The CONTRACTOR has agreed to perform and continue the remaining services
for the OWNER:
Furnish all labor, equipment, tools and administrative supervision and all other
incidentals necessary to complete the works as follows:
a) Supply & installation of toilet fixtures and tiles for the 3 rd floor
comfort room of House 1.
b) Supply & installation of analouk sliding windows and window grills
for all window openings of House 1.
c) Installation of flush door for front room at 2nd floor of House 1.
d) Tiling works for floorings at the following area within House 1:
i. 3rd floor family room
ii. 2nd floor back extension room
iii. Laundry area
e) Supply & installation of 1pc. Steel French door going out to 3 rd floor
comfort room of House 1.
f) Supply & installation of waterproofing works for all exterior walls of
House 1.
g) Supply & installation of overall interior and exterior paint works of
House 1.
h) Supply of labor only for modification works such as tiling,
replacement of fixtures for 1st floor comfort room of House 1.
i) Supply & installation of ceiling works for 2nd floor of House 1.
j) Provision of plant box in front of entrance door of House 1
k) Provision of wooden steps for spiral stairs of House 1.
l) Dismantling of wall between the gate area of House 1 and House 2.
m) Dismantling of wall between the laundry area of House 1 and House
2.
n) Dismantling of wall between the 2nd floor back room of House 1 and
House 2.
B. PLACE OF WORK
C. PAYMENT
1. The Total Contract Cost of the PROJECT including the completed works not
specified in the Scope of Work of this Agreement amounts to THREE
HUNDRED THOUSAND PESOS only (PHP 300,000.00).
5. All payments under this Agreement shall be subject to withholding tax and
other taxes and duties as may be provided for by law and to the usual and
regular government accounting and auditing rules and regulations.
2. CONTRACTOR shall furnish and provide for its account all the necessary
materials, labor, tools, supplies, equipment, plant and other facilities as
required for the satisfactory performance and accomplishment of the Project
according with and as directed by the OWNER and based on the Scope of
Work agreed upon.
The CONTRACTOR shall at all times be directly responsible and liable for
the enforcement of and compliance with all existing laws, rules and
regulation particularly in respect of any and all claims brought by its
personnel for the enforcement of the provisions of the Labor Code of the
Philippines and other related laws. The CONTRACTOR holds the OWNER
free and harmless from all such claims and liabilities.
5. CONTRACTOR shall likewise comply with all laws, rules and regulation
promulgated by the government or any of its instrumentalities applicable to
the Project and shall be personally and solely responsible for any violation
of the same.
6. CONTRACTOR shall hold the OWNER, free and harmless against any
claim, losses, damages, or injuries of whatever kind or nature that may be
filed or claimed against the OWNER by any third person, firm, or entity
arising out of or in connection with the construction undertaken by the
CONTRACTOR under this Agreement, or by the negligence of the
CONTRACTOR, its agents, servants, employees, and/or subcontractors.
7. CONTRACTOR shall finish and turn over the said Project at the said
contract price and in accordance with the directions of the OWNER and with
the herein Scope of Work.
2. However, the OWNER shall have the right to terminate this Agreement for
any just cause; provided that it notifies the CONTRACTOR of its intention
to terminate the Agreement.
G. CONTRACTORS GUARANTEE
H. MISCELLANEOUS
1. The failure of the OWNER to insist upon the strict performance of any of
the covenants, terms and conditions in this Agreement shall not be deemed
as relinquishment or waiver of any rights or remedies that the OWNER has.
Nor shall it be construed as a waiver for any subsequent breach or violation
of the covenants under this Agreement. No waiver by the OWNER of any
rights shall be deemed to have been made unless expressed in writing and
signed by the OWNER through its authorized representative.
2. Aside from the rights accorded to the OWNER in case of breach by the
CONTRACTOR, should the CONTRACTOR violate any of the terms and
conditions of this Agreement, the CONTRACTOR shall be liable to pay
liquidated damages in no less than the contract price.
8. Any notice/s required to be given or delivered to each party under the terms
of this Agreement shall be in writing and addressed to its respective
indicated address herein.
_____________________ _____________________
Mrs. Julieta S. Cisneros Mr. Vincent Pacpaco
Owner Contractor
_____________________
Mrs. Shavarra Pacpaco
Contractor
ACKNOWLEDGMENT
known to me and to me known to be the same persons who executed the foregoing
Compromise Agreement, consisting of ____ pages, including this page in which
this Acknowledgment is written, signed by the Parties on each page, and who
acknowledged to me that the same is their free and voluntary act and deed, as well
as the free and voluntary act of the entity represented in this instance.
NOTARY PUBLIC