You are on page 1of 12

twi= qe\o

&LAFHRMED 1997
IS 7349 : 1989

Indian Standard
BARRAGES AND WEIRS-OPERATION AND
:
__
--\
MAINTENANCE-GUIDELINES
(First Revision )
w3h WV5
3&r 37r3fq93- 5PZFld3 ?Q?VT~ - STk?i? fUgT=a

UDC 62782 + 627431/432004 [ 026 ]

0 BIS 1989

BUREAU OF INDIAN STANDARDS


MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002

November 1989 Price Group 4


Barrages and Weirs Sectional Committee, BDC 65

FOREWORD

This Indian Standard ( First Revision) was adopted by the Bureau of Indian Standards on 24 January
1989, after the draft finalized by the Barrages and Weirs Sectional Committee had been approved by the
Civil Engineering Division Council.

Proper operation and maintenance of barrages and weirs is of great importance. It is essential that the
drawings of works as executed and as amended from time to time are kept up to date and are maintained
as permanent record so as to be available readily for consultation. It is necessary that the engineers-in-
charge make themselves familiar with the basis of design and operation/regulation orders/manual of the
works/structures.

This standard was first published in 1974. With the experience gained from the prototype behaviour of
many barrages and the various remedial measures generally being adopted/suggested for overcoming the
difficulties faced in actual operation and maintenance of the barrages, it was considered necessary to revise
the standard and incorporate many of the measures currently being followed in various projects.
Accordingly, requirements of operation and regulation have been fully revised, providing detailed
clarifications/guidelines on many of the issues faced by the site engineers. The history of headworks has
also been revised with the addition of data on gate/shutter operation adopted from time to time.

For the purpose of deciding whether a particular requirement of this standard is complied with, the final
value, observed or calculated, expressing the result of a test or analysis, shall be rounded off in accordance
with IS 2, : 1960 Rules for rounding off numerical values ( revised). The number of significant places
retained in the rounded off value should be the same as that of the specified value in this standard.
IS 7349 : 1989

Indian Standard
BARRAGES AND WEIRS-OPERATION AND
MAINTENANCE-GUIDELINES
(First Revision )
1 SCOPE 3.1.6 Where the considerations given in 3.1.5 are
not governing, it would generally be desirable to
This standard lays down guidelines for the operation subject barrage gates to wedge operation commencing
and maintenance of hydro-mechanical installations to open from the centre and moving on either side
and civil structures connected with the barrages and till all the gates have been opened equally. The
weirs. gates shall be opened in instalments not exceeding
30 mm at a time. Gate opening shall be suitably
increased to allow passage of boulders.
2 REFERENCES
3.1.7 The operation shall be so done that the safety
The Indian Standards listed in Annex A are necess-
ary adjuncts to this standard. of the structure is not jeopardized at any time and
the permissible difference in static head on either
side of the divide walls is not exceeded beyond
3 OPERATION AND MAINTENANCE OF the safe limit, which shall be clearly specified.
HY DRO-MECHANICAL INSTALLATIONS
3.1.8 The gates operating silt/shingle excluding
All machinery at the works should be kept clean, devices should be closed very slowly to avoid water
tidy and in proper working order and care should hammer action which can otherwise damage the
be taken to ensure that it is properly handled in structure.
conformity with the manufacturers instructions.
The main mechanical items are generally the gates 3.2 Maintenance of Gates
and the winches.
. 3.2.1 All cavities and angles in the gates/shutters
should be kept clear of debris, driftwood, moss and
3.1 Operation of Gates and Falling Shutters silt accumulations. All drainage holes in the webs
of horizontal structural members should be kept
3.1.1 All lift gates should be operated at suitable open and no water allowed to remain entrapped.
intervals to free the mechanism and wash out ex- Green stains should not be allowed to form on the
traneous material. In low supplies when openings steel members at the back of the gates/shutters. The
are not desirable, raising of gates by 150 mm for a gates and counter balanced boxes should hang per-
few minutes should suffice. If the gates have not fectly level and plumb. This should be checked
been moved for a sufficiently long time, they should occasionally and adjustment made as needed. In
not be forcibly raised all at once but should be case of shutters, the chains/anchors holding them
lifted by about 30 mm or so and left at that position should be kept free from rust. IS 10096 ( Part I/
for about 10 to 15 minutes till the silt deposited Set 1 ) : 1983 and IS 7718 (Part 3 ) : 1975 may also
against the gates gets softened and water begins to be referred for the inspection/maintenance of the
ooze out. This is essential to avoid heavy strain on gates considering the type of gates provided on the
the machinery. barrages/weirs.

3.1.2 The speed of operation of the gates should be 3.2.2 No painting is required for machined surfaces
limited to the maximum speed indicated by the and surfaces of stainless steel, brass or bronze.
manufacturer. These surfaces shall be protected by a coating of
gasoline-soluble rust preventive non-corrosive
3.1.3 The head regulator gates shall be opened compound.
equally unless otherwise indicated by model studies
due to adverse local conditions. 3.2.3 The upstream face of the skin plate which
comes in contact with water should preferably be
painted with a suitable primer and subsequently with
3.1.4 The operation of under sluice gates shall be sanded aluminium paint for a long life. The other
based on model studies conducted for optimum parts of the gates/shutters which do not come in
silt exclusion, hydraulic efficiency and structural contact with water should be painted with paint
safety. conforming to IS 158 : 1981 or chlorinated rubber
based paint or epoxy coal tar paint ( cold applica-
3.1.5 Sequence of operation of barrage gates/weir tion ). The upstream face may also be painted
shutters shall be decided by the engineer-in-charge with any of these paints. These paints may be sub-
depending on river behaviour, shoal formation, stituted with decorative paint ( synthetic enamel )
scour, etc, both upstream and downstream. ( see IS 2932 : 1974 ) for better appearance.

1
IS 7349:1989

3.2.3.1 The application procedure for sanded 3.2.3.2 The application procedure for bituminous
aluminiutn paint on new work shall be as detailed black paint shall be as detailed below:
below: The surface cleaning should be done as for sanded
aluminium paint detailed in 3.2.3.1(a). The paint
a) Cleaning is then applied cold with brushes in 4 or 5 coats to
1) Weld spatter or other surface irregularity obtain a desirable thickness of 045 mm. Each coat
shall be removed by any suitable means; should be allowed to dry thoroughly before applying
the succeeding coat. The minimum drying time is
2) Oil, grease or dirt, if any, shall bc removed 24 h even under favorable conditions.
from the surface by the use of solvents,
that is, clean mineral spirits, naptha or 3.3 Gate Grooves and Seals
white gasoline;
Grooves and particularly their machined faces should
3) S1 No. (1) and (2) above shall be followed be kept clean and lubricated well and all sticky
by sand blasting for removal of rust or deposits should be scraped off before application of
mill scale, to present a uniform bright lubricant.
base metal. Any dust or grit remaining
from this cleaning operation should be 3.3.1 Seals
completely removed from the surface by
brushing or with dry air; and Efficiency of rubber seals should be tested initially
after construction and at the time of closures or
4) Painting shall be immediately commenced isolation of different portions for repairs. The
after cleaning in accordance with S1 No. horizontality and verticality of the seal seat and wall
(3) above. plates shall be checked with spirit level and seal
faces of the rubber seal should be tested to press
b) First Primer Coat uniformly both by light test and by use of paper-
strip inserts. Seals of the gate should be checked
)
The first primer coat- should be prepared by
for wear and tear and deterioration. These should
mixing 1 kg of aluminium paste ( see IS 289:
be adjusted/replaced as necessary. Few sets of
1963 ), 45 Iitres of zinc chromate mixing
spare seals should be kept in stock and stored for
paint and thinning it suitably with oil of emergency in such a way that these seals do not get
turpentine ( see IS 6646: 1972 ). This shall
damaged/withered with the passage of time while in
be applied by brushing at a coverage rate of
stores.
10 to 125 m2/1. Drying time shall be at
least 18 h unless otherwise specified by the 3.3.2 Stanching Pipes
paint manufacturer. Stanching pipes, where provided, should be checked
for their sealing efficiency and necessary repairs/
c) Second Primer Coat replacements carried out.
The paint shall be prepared in a similar
manner as in (b) except that no thinner shall 3.4 Steel Wire Ropes
be added. The paint shall be applied by All steel wire ropes must be cleaned to remove
brushing at a rate of approximately 725 m2/1. all dust accumulation and lubricated with suitable
Immediately after the application of the greases at least once a year. The portion of steel
second coat, clean and dry sand with rounded wire rope which is submerged in water should be
grains of 30-50 mesh size shall be sprayed lubricated frequently, preferably thrice a year.
with low air pressure of 35000 to 70000 Pa
( 035 to 07 kgf/cm ) so that the sand grains 3.4.1 The procedure laid down in IS 3973:1984
get embedded in the wet second priming coat should be followed. It is desirable that the inspection
and do not puncture the first coat. Drying and maintenance of wire clamps be also carried out
time shall be at least 24 hours. Sand spraying with the rope. The clamping devices should be
is omitted in the case of surface on the down- declamped and reclamped at least once in three
stream side not coming in contact with water. years.

d) Finish Coat 3.5 Roller Trains and Fixed Rollers


This is prepared by mixing 1 kg of aluminium The roller trains should be examined at least once
pigment paste with 45 litres of phenolic resin a year. Partially jammed rollers should be cleaned,
mixing varnish. The first coat shall be applied freed and greased but totally jammed railers should
by spraying at a coverage rate of approxima- be replaced. The bolts of roller guard should be
tely 57 m/l. The second finish coat shall checked and tightened. The sliding/fixed ro]]ers
be applied not earlier than 24 h after the should be extracted at the time of closure (unless
completion of the first finishing coat at a necessitated otherwise due to some defects which may
coverage of approximately 725 m/ 1. This need immediate repairs), and cleaned and greased
may be substituted by coal tar paint or properly. Worn out pins should be replaced and
decorative paint in case of downstream side. suitably held against rotation by filling the empty
The equipment shall be kept idle for 5 days space between the pin and the side plates through
after this treatment before it is put into welding or by other approved means. Spare rollers
service. should be kept in stores for ready replacement.
.
L

...___-.
-
. - .. .
IS 7349 : 1989

3.6 Winches/Hoist weirs before the onset of monsoon and after passing
the floods.
3.6.1 All winches and lifting drums should be
examined at least once a year to see if all the gears 4. INSPECTION, MAINTENANCE AND
and axles are clean and properly lubricated. All INSTRUMENTATION OF CIVIL WORK
grease-fed bearings should be cleaned, old grease
removed withkerosene oil and fresh grease applied. 4.1 Inspection of barrages and weirs is necessary to
The alignment of shafts should be checked and obviate the possibility of extension of damage. Such
coupling bolts tightened. inspection should usually be carried out annually
for all underwater works after monsoon by means of
3.6.2 All grease cups must be kept full of lubricants underwater lamps and sounding rods. In addition,
and covers tightened periodically to ensure lubricant detailed inspection in stages should be carried out
moving and causing an effective seal against dust after drying the upstream floor by isolating portions
getting into the bearings. For winches with ratios of of the barrage such that each portion is thoroughly
60 : 1 to 100 : 1, four men should be able to operate inspected against any crack or damage, once every
the hoist easily. If the working of any winch five years. While doing so, the embankment should
becomes hard and it requires more men to operate be placed suitably upstream of the impervious floor
it, it should be examined and the defect removed for pressure relief and the divide wall or pier and
before it is used. Winch gear covers should have adjacent floor provided with temporary strengthening
felt or rubber washers to check the entry of dust. to the extent required.
The winches should be operated in correct direction
and to ensure this, direction or operation should be 4.2 The repairs as necessary as a result of inspection
correctly marked and the limits of operation should be carried out well before the onset of the
indicated. next monsoon. Any serious defects noticed should
be reported to appropriate authorities and decisions
3.6.3 In case of electrically-operated hoists, all taken in time.
precautions necessary to ensure safety and, fault-
free operation of electric motors and switching 4.3 The inspection and maintenance may broadly be
devices such. as checking up of insulation of all classified under the following items:
electrical wirings, motor armature windings, etc,
should be taken. Mechanical upkeep of motor a>Aprons
bearings and reducing gears should be ensured
1) Upstream apron and area immediately
through proper inspection and lubrication. The upstream of it, and
arrangement for operation of hoists manually in
addition to the operation of hoists by electric means 2) Downstream apron and area immediately
should also be provided besides provision for downstream of it.
isolating the one from the other. The latest techni-
que of automatic gate lifting may also be provided b) Impervious Floors
if the project is equipped for such operation. 1) Upstream of the gates/falling shutters, and
2) Downstream of the gates/falling shutters.
3.7 Wooden planking, where provided in the deck-
ing of hoist bridge, should be checked to tighten up Sediment Excluding Devices
the loose holding down nuts and bolts and replace Canal Head Regulator
worn out planks. The wooden planking should
Instrumentation and Performance
receive at least two costs of creosote oil application
once in two years. River Training Works

3.8 The engineer-in-charge should test all lift gates, 4.3.1 Aprons
and chain and clips of falling shutters and submit a
certificate to the competent authority (as laid down The sounding and probing in the area shall be
in regulation orders) before the advent of the undertaken every year immediately after the monsoon
monsoon that all gates/falling shutters are in good in order to assess the scours and launching of aprons
operation condition. in the vicinity of structures. The non-launching
portion should be carefully examined, particularly
3.9 All flood lighting and barrage illumination on downstream, to ensure the effectiveness of
should be checked daily during flood season and inverted filter.
once in a week during slack season.
4.3.2 Impervious Floors
3.10 Where road bridge is provided, the bridge
bearings should be cleaned and greased once a year A thorough inspection of upstream and downstream
after the monsoon season. floors shall be done after the monsoon. The
upstream floor shall be inspected every year early in
3.11 The painting of supper structures should be the cold weather season by probing and the use of
done once in two years. underwater lamps. A careful inspection of joints of
the stone-sets should be done where such structures
3.12 IS 10096 ( Part l/Set 2 ) : 1986 may also be have been carried out in boulder reaches. Minor
referred for inspection/maintenance of hoists con- repairs can be done under water whereas major
sidering the type of hoist provided on the barrages/ repairs may be undertaken by isolating the area.

3
IS 7349 :1989

4.3.2.1 The downstream basin shall also be carefully local conditions. It may generally be enough to take
inspected in the cold weather season and the repairs observations once a month during monsoon period
carried out well in time before the onset of monsoon. and more frequently during the non-monsoon period.
In case of deep cisterns requiring expensive cleaning It shall be ensured that:
and dewatering, inspection of sandy river reaches
can be carried out by probing but in boulder reaches a) the mouths of all pipes are kept closed by
where this may not be possible, dewatering, cleaning caps to obviate the chances of foreign matter
finding its way into the pipes and clogging
and repairs may be carried out by rotation once in
three years. The condition of boulder-set or granite them;
block in the case of boulder stage river should be b) each pressure observation point is given a
carefully examined, and repairs and replacements distinct number; and
made, as found necessary. While dewatering deep c) each pipe is frequently tested to ensure that
downstream basins, care shall be taken to ensure its strainer is not choked. This can be best
that the design uplift for such condition is not done with the help of an ordinary hand pump,
exceeded. This shall be clearly specified in the by working it till water comes out freely.
regulation order.
4.3.5.2 Pressure release (drainage) pipes
4.3.3 Sediment Excluding Devices
Pressure release (drainage) pipes, where provided, in
A thorough inspection of roofs, ducts and mouth of the downstream floor should simultaneously be
the sediment excluders shall be carried out every checked for the quantity and quality (sediment
year in the cold weather with the help of divers and content) of the discharge. Such observations may be
underwater lamps. Minor repairs may be carried out possible only during the dry season when all the
under water and major repairs by local isolation. gates of the compartments are closed. This is necessary
to check the efficient working of the drainage system.
4.3.4 Canal Head Regulator A correlation between head of water and discharge
should be established and any large variations
The work shall be carefully examined every year in immediately taken notice of and suitable action
the cold weather by probing in case of upstream taken. As discharge of sediment in the e@luent could
floor and examination under dry condition of lead to undermining of the foundations, immediate
downstream floor during closure or isolating the remedial measures should be undertaken. In extreme
area where closure may not be possible. Visual cases it may become necessary even to completely
inspection of upstieam floor should also be carried block the sediment discharging pipe.
out once in three to five years by isolating the area.
All necessary repairs shall be carried out in time. 4.3.5.3 Hydraulic jump pro$le
4.3.5 Instrumentation and Performance Strip gauges should be painted every 10 m on the
wing walls and the long divide walls to observe the
It is essential that every year a performance report hydraulic jump profile in the prototype under
be prepared on the basis of instrument observations. different hydraulic conditions. The following obser-
The observations can be broadly classified under the vations shall be taken:
following sub-heads:
4 Upstream water level,
a) Uplift pressure,
b) Downstream water level,
b) Suspended sediment,
cl Shade temperature - maximum and minimum,
c) Settlement,
4 Temperature of the river water at a depth
d) Retrogression, from the surface below which it remains
e) Aggradation upstream, and approximately constarit,
f) Discharge distribution and crossflow. 4 Temperature of the sub-soil water in a few
selected observation pipes,
4.3.5.1 Uplift pressure f) Water level in all pipes may be observed by
using a bell sounder or by other suitable
The pressure observation pipes (see IS 6532 : 1972 ) means,
are embedded in the weir or barrage structure
generally in piers, and flank walls in such a manner s) Discharge from drainage pipes, and
as to give representative uplift pressure along and h) Depth of sediment on upstream and down-
immediately beneath the horizontal floor, at different stream floors.
points along the vertical cut-off. Additional pressure
pipes may be installed, if required, to determine 4.3.5.4 Suspended sediment
uplift pressure at critical points in stratified founda-
tions. The pipes shall be numbered and a permanent During the monsoon season, water sample should
record of observations shall be maintained. The be taken in accordance with IS 4890 : 1968
observed uplift pressure should be compared with simultaneously upstream and downstream of the
the design uplift pressures with the help of a undersluices and in the canal below the head
graphical plot and any needed remedial measures regulator to assess the suspended sediment therein.
adopted. Frequency of observation will depend upon Such observations should be taken at least once a

4
IS 7349 : 1989

week (closer intervals in case of high sediment side. Similarly, the survey on downstream side
concentration) to judge the efficiency of sediment should extend to a length up to which river bed
exclusion and to decide if any change in the mode changes occur. Sufficient number of permanent
of regulation and/or other remedial measures are reference marks should be established on both banks
required. to facilitate superimposition of old and new survey.
The changes in the river course shall be examined
4.3.5.5 Settlement and remedial measures taken.
Where appreciable foundation settlements are antici- 4.3.6.2 The afflux bunds, guide bunds and spurs
pated, particularly when the structure is founded shall be examined in the cold weather and necessary
partially or wholly on clay or other soft soil, surface repairs to the bunds, pitching and aprons carried
settlement of relatively heavily loaded parts of the out and completed well before the onset of monsoon.
structure should be observed early in the cold An adequate stock of boulder/stones shall be main-
weather every year and remedial measures under- tained close to the protection works for use in
taken, if necessary. This can be done by establishing emergency.
permanent observation points of steel on the
structure and doing precise levelling from permanent
bench marks established sufficiently away from the 5 OPERATION AND REGULATION
influence of any structure.
5.1 Adequate regulation staff should be provided
4.3.5.6 Retrogression and their duties should be clearly specified.
Adequate stocks of stores, tools and plants required
Retrogression of the river bed can be expected to meet emergencies should be maintained on all
downstream of the weir/barrage. In order that the barrages and weirs. These should be listed in detail
lowering of water level at any discharge condition in the regulation orders and their availability checked
does not exceed that provided for in the design, it periodically by the engineer-in-charge. The gauge
is necessary to establish gauges on both banks, one sites ( see 5.3.2.1 ) shall be linked by a telephone or
immediately downstream of the work and two more, telegraph or both with the headworks.
1 000 and 2 000 m downstream of the first and to
observe them simultaneously at least once a day. 5.2 In general, operation of the barrage gates should
Remedial measures should be undertaken as and ensure the following features:
when required to ensure the safety of the structure
a>The required pond level is maintained both
4.3.5.7 Aggradation upstream during the non-monsoon flows and the falling
flood periods.
The river bed upstream of the barrage of weir is
likely to aggradate resulting in increased afflux and b) The non-monsoon flows remain near the
reduction in freeboard provided in design. To undersluice bays so that feeding of the canal(s)
determine the increase in the afflux, if any, gauges through the head regulator(s) is not
should be established on the upstream, one immedia- affected.
tely upstream of the work and one each at 1 000 and
2 000 m upstream of the first, and observed regularly. cl A fair uniform distribution of discharge along
The afhux bunds may have to be raised, if found the width of the barrage is obtained, as far as
necessary, to restore the designed freeboard. practicable.
4 Parallel flows both on the upstream and the
4.3.5.8 Discharge distribution and crossflow downstream of the barrage is avoided at all
times, as far as practicable.
Observations should be taken to find the discharge
distribution through different bays of the barrage. 4 The risk of deep scours and shoal formations
If there is significant crossflow and/or difference in in the vicinity of the barrage both on the
discharge intensities through different bays, remedial upstream and the downstream is minimized,
measures should be taken to check this tendency for as far as possible.
which improved regulations may be of great help.
f) To evolve the operation of gates to exclude
maximum silt/debris deposits on the upstream
4.3.5.9 Pond capacity side and also to minimize the entry of same
Where the barrage is also providing balancing in canals/channels.
storage, soundings in the entire pond area may be
made at suitable intervals for periodic review of g) The hydraulic jump should not be allowed to
form beyond the toe of the downstream glacis
storage capacity.
in any case.
4.3.6 River Training Works h) A relatively high intensity of flow is avoided
in the deep scour zones, if formed.
4.3.6.1 A detailed river survey covering the barrage/
weir and river training works upstream and down- 3 If a shoal has formed on either upstream,or
stream shall be carried out every year. The suruey downstream, or both of the barrage, it is
should preferably extend about one metre above the washed out and kept away from the barrage,
design flood level on both the banks on upstream as far as practicable.

5
IS 7349:1989

k) The gate operation schedule should also as given below:


consider constraints regarding rates of lowering/
raising of ponds. It should also consider the a) Still pond operation
safe rate of filling of the canals.
In still pond operation, all the gates of the
m) Constant and regular supply in canals/ undersluice bays are to be kept closed so as
channels even during fluctuations in discharges to limit the discharge flowing into the pocket
from power houses located on the upstream to be equal to the canal supply. The specified
side. or required discharge only should be drawn
in the canal and the surplus river discharge
5.3 The operation and regulation can be divided into should be passed through the spillway bays
three distinct periods as given below: or river sluice bays, if provided. As the
a) Pre-monsoon, undersluice bays are kept closed, the low
velocity in the pocket causes the sediment to
b) During monsoon, ond settle down and relatively clear water enters
c) Post-monsoon. the canal. However, the pocket gets silted up
in this process after some time.
5.3.1 Pre-monsoon Operation
At that time, the canal head regulator gates
It is a low flow period and normally no wastages of should be closed and deposited silt should be
water shall be permitted during this period. The flushed out be opening the gates of the under-
barrage gates/falling shutters shall be regulated such sluice bays. The canal supply may be stopped
that all the available supplies are conserved and during this scouring operation which may
pond level is maintained. Any excess flow over take about 24 hours. After the silt deposits
and above the requirements through the head are flushed out sufficiently, the head regulator
regulator(s) shall be released through undersluice gates should be opened and undersluice
bays and silt excluder tunnels, wherever provided. closed. This operation is desirable where the
The release through the head regulator of the canal crest of the head regulator is at a sufficiently
shall be based on the discharge tables. The dis- higher level than that of the upstream floor of
charge tables shall be occasionally checked for the undersluice bays. This still pond operation
accuracy by actual measurements in the canal. should be continued till the river stage reaches
the pond level after which the undersluice
For any flashy hood, the canal may have to be gates should be opened to avoid overtopping.
closed temporarily, if the concentration of suspended
silt is in excess of the safe limit prescribed.
I b) Semi-Still Pond Operation
The discharge tables shall be occasionally checked In the semi-still pond operation, the gates of
for accuracy by actual measurements in the canal. the canal head regulator are not closed for
flushing of silt deposit in the pocket. The
5.3.2 Monsoon Operation gates of the undersluice bays should be kept
partially open to the minimum necessary so
5.3.2.1 Gauges to indicate flood stage shall be that the bed material in the pocket could be
installed sufficiently ( not less than 1 000 m ) upstream passed downstream. The discharge in excess
of the barrage at suitable locations so as to ensure of the canal requirement should be passed
adequate margin of time for operation of gates at through the undersluice bays and silt excluder
the weir/barrage site. tunnels also, wherever provided.

5.3.2.2 During low floods, the gauges shall be 5.3.2.5 Excluders, where provided, should be kept
signalled and recorded every three hours while in open and while doing so, the limitations imposed by
medium and high floods, these shall be recorded the safety of the structure should be kept in view.
every hour. The signaller at the headworks, on The required intensity of discharge, q, which may be
receiving the flood warning shall communicate the sufficient to flush the deposited silt in the pocket can
same to the official/officer-in-charge of the headworks be calculated from the Laceys scour equation
and other regulation points downstream and to the
district officers of the neighbouring districts.

5.3.2.3 The advisability of installation of wireless


R = 135 42
[ f 1 l/3

transmitting stations of headworks on major rivers where


for speedy transmission of flood warning should be
considered. R= scour depth in metres that is, between
the water level and the level of the pocket
5.3.2.4 In order to create most favourable conditions floor in this case;
for sediment exclusion from the canal, still-pond intensity of discharge, in mg/s per metre
4=
regulation should be resorted to, as far as possible. width; and
However, in locations where canals cannot be
closed for flushing, semi-still pond/regulation f= silt factor corresponding to the deposited
may be adopted ( as in the case of power channels ) material in the pocket.

6
IS 7349 : 1989

The required intensity of discharge thus calculated direction of current and vortex formation during low
may be generated by suitable gate openings when and medium tloods should be made. After critically
sufficient head is available in the pond. Under no observing the effects of different patterns of gate
circumstances shall the undersluice gates be allowed operation on the same, the engineer-in-charge should
to be overtopped. Silt ejectors in the canal should judiciously select the correct pattern which would
be operated as much as possible so that the chances cause only minimum scour or minimum shoaling.
of heavy siltation in the canal posing a problem of
flushing due to its compaction are minimized. 5.3.2.8 The engineer-in-charge should remain con-
versant with shoal formations, changing network of
5.3.2.6 During monsoon months, it is important to spill channels, etc, which cause unequal distribution
keep a constant watch over the sediment entering of flows through different bays, cross flow near the
the head, the portion thereof ejected by the extractor barrage floor ends, vortex formations, etc. He should
if any, and the sediment deposition taking place in try to wash away the shoal formations coming too
the canal and to ensure that sediment deposition close to the barrage/weir and otherwise improve
only to the extent that can be washed out early flow conditions at the work by judicious gate
in the cold weather before the full demand develops, operation.
is allowed. For this, the following actions shall be
taken: 5.3.2.9 The pond level shall be kept minimum
required to feed the canal with the required discharge
a) Sediment charge observations ( both suspend- by suitably opening the gates. It shall be ensured
ed sediment and bed load ) shall be made at that in a high flood, all falling shutters of weirs are
least once a day in low floods immediately lowered and all gates raised clear of the water level
below the head regulator, below the silt with adequate freeboard to clear floating debris.
ejector, if any, and at any other sensitive point
lower downy the canal.. The frequency of
5.3.2.10 The operation of barrage gates/weirs shutters
observations may be increased in medium and
shall preferably be based on model studies at various
high floods as required;
flood intensities, that is, low, medium and high, as
modified by observed river behaviour at site. In this
4 Cross section of the canal shall be taken connection, for major barrages it would be desirable
daily at a few sensitive points to watch the
extent of sediment deposition of the canal; to constitute a gate regulation committee for each
barrage comprising senior engineers of the project
Water surface slopes in the sensitive head design office and research station and engineer-in-
reach of the canal shall be kept under observa- charge of the Headworks Division. The committee
tion daily with the help of gauges; should hold meetings at least once during pre-
monsoon, monsoon (preferably twice) and after
The ponding upstream of power stations, if monsoon and should review the gate operation
any, in the canal shall be restricted to the pattern and modify wherever necessary on the basis
requisite extent so as to avoid harmful sedi- of the observed river cross section on the upstrean
ment deposition; and and downstream of the structure. After some years
when satisfactory flow conditions are established, all
4 The canal shall be closed from the head: the recommendations of the committee from time to
time should be compiled in the form of a manual
1) beyond a specified sediment charge during so that guidance could be obtained by the gate
medium/high flood and re-opened when operating personnel for future use in the project.
the sediment charge drops below the specified Generally with the rise in the flood discharge, a
limit. Since the silt carrying capacity of the step-by-step gate operation with gradual increase of
canal would govern this specified limit, it opening from ends towards the centre is sometimes
would vary from project to project and recommended.
should be estimated based on actual data/
experience. In so far as the power channels
are concerned, this would depend on the 5.3.2.11 In order to keep a close watch on the river
size of the particle carried down. behaviour and bed configuration both upstream and
downstream of the barrage, river surveys should be
2) when sediment deposition at the sensitive conducted regularly, once before the floods and
points has reached the maximum permis- another after the floods. For major structures,
sible bed level. This limit along with the powerful launches with echo-sounders may be
sediment charge in excess of which the desirable to take cross sections even during medium
canal is to be kept closed, may have to be flood stage. The survey shall be conducted over an
fixed for different months during the area close to the barrage for a distance of 1 000 m
monsoon period in order to be able to meet both on the upstream and downstream. The bed
the irrigation and power demand. levels shall be determined by use of echo-sounders
at close intervals of 10 m. Depending upon the bed
5.3.2.7 Since cross flows and vortex formations configuration, the pattern of gate regulation shall be
dangerously cause deep scours both on the upstream modified suitably to ensure safety and better
and downstream of the barrage leading to washing hydraulic performance of the barrage. Canals having
away or sinking of cement concrete blocks and hydro-electric power stations should be provided
loose stone aprons, and damages to the nose and with trash racks at the head regulator to check entry
shanks of guide bunds, visual observations of the of floating debris. The trash racks should be kept

7
IS 7349 : 1989

clean preferably by a mechanical or electrical downstream of the barrage inspite of judicial


operation device. Instances of collapse of trash racks operation of the gates, during normal and flushing
due to lack of cleaning and excessive pressure built operation of reservoir, the shoal shall be removed by
up has been on record. Where floating debris try dredging by the use of suitable dredgers to the
to enter the irrigation canal head regulators, trash extent possible so that satisfactory flow conditions
booms may be erected just upstream of the head are established and also desired capacity is restored.
regulators.
5.6 Landsat imageries obtainable from the National
5.3.2.12 The cranes for lifting weir shutters should Remote Sensing Agency may be helpful in the
be housed safely in the crane houses when not studies on variations of the bank lines, flow patterns,
in use. etc, taking place from year to year both on the
upstream approach and downstream exit of the
5.3.3 Post-Monsoon Operation barrage. Regular studies with landsat imageries may
be made and remedial measures for improving the
5.3.3.1 Sediment charge observations and cross river behaviour and flow pattern may be taken up
section of sensitive points on the canal shall be immediately if the studies so warrant. Wherever
continued at less frequent intervals till satisfactory erosion or damage to the protective works on the
conditions have been established. upstream and downstream banks close to the barrage
are observed, these should be immediately repaired
5.3.3.2 Still/semi-still pond operation, with sediment before the onset of the next monsoon.
excluders/ejectors operating, depending on the
surplus water availability should be continued till 6 HISTORY OF HEADWORKS
water becomes reasonably clear.
A continuous history of river behaviour and the
overall performance of the barrage/weir, head
5.4 When a canal is first opened, a low supply shall regulators and river training works should be
be run for a few hours at least and the depth should maintained on all major headworks. The history
gradually be raised according to the requirements. should include details of repairs carried out and river
The rate of filling and lowering of the canal should training measures adopted and their efficacy. It
be prescribed and these should not be transgressed. should also contain details of the gate/shutter opera-
Silt ejector hoppers and outlet pipes may be cleaned tion pattern adopted from time to time. Necessary
by pressure flow or back-jetting before, the canal is drawings should be appended in the history. Pre-
started for operation. monsoon and post-monsoon river bed contours may
be plotted, reduced in size and properly filed in
5.5 If a study of the survey data indicates that shoal serial order for comparison to understand the pattern
formation has occured -on the upstream and/or of shoals, scours, oblique flow, etc.

ANNEX A
( Clause 2 )
LIST OF REFERRED INDIAN STANDARDS

IS No. Title IS No. Title


IS 158 : 1981 Specification for ready mixed paint, IS 6646 : 1972 Specification for oil of turpentine,
brushing, bituminous, black, lead solvent grade
free, acid, alkali and heat resisting
( third revision ) IS 7718 Recommendations for inspection,
IS 289 : 1963 Specification for aluminium paste (Part 3) : 1975 testing and maintenance of fixed
for paints ( revised) wheeland slide gates: Part 3 After
erection
IS 2932 : 1974 Specification for enamel, synthetic,
exterior (a) undercoating, (b)
finishing (first revision ) IS 10096 Recommendations for inspection,
(Part I/ testing and maintenance of radial
IS 3973 : 1984 Code of practice for the selection, Set 1) : 1983 gates and their hoists: Part 1
installation and maintenance of Inspection, testing and assembly at
wire ropes (jirst revision ) the manufacturing stage, Section 1
IS 4890 : 1968 Methods for measurement of Gates
suspended sediment in open
channels IS 10096 Recommendations for inspection,
IS 6532 : 1972 Code of practice for design, in- (Part l/ testing and maintenance of radial
stallation, observation and main- Set 2) : 1986 gates and their hoists: Part 1
tenance of uplift pressure pipes for Inspection, testing and assembly at
hydraulic structures on permeable the manufacturing stage, Section 2
foundations Rope drum hoists
Standard Mark

The use of the Standard Mark is governed by the provisions of the Bureau of Indian
Standards Act, 1986 and the Rules and Regulations made thereunder. The Standard Mark on
products covered by an Indian Standard conveys the assurance that they have been produced
to comply with the requirements of that standard under a well defined system of inspection,
testing and quality control which is devised and supervised by BIS and operated by the
producer. Standard marked products are also continuously checked by BIS for conformity
to that standard as a further safeguard. Details of conditions under which a licence for the
use of the Standard Mark may be granted to manufacturers or producers may be obtained
from the Bureau of Indian Standards.
Bureau of Indian Standards

BIS is a statutory institution established under the Bureau of Indian Standards Act, 1986 to promote
harmonioug development of the activities of standardization, marking and quality certification of goods
and attending to connected matters in the country.

Copyright

BIS has the copyright of all its publications. No part of these publications may be reproduced in
any form without the prior permission in writing of BIS. This does not preclude the free use, in the
course of implementing the standard, of necessary details, such as symbols and sizes, type or grade
designations. Enquiries relating to copyright be addressed to the Director ( Publications), BIS.

Revision of Indian Standards

Indian Standards are reviewed periodically and revised, when necessary and amendments, if any, are
issued from time to time. Users of Indian Standards should ascertain that they are in possession of
the latest amendments or edition. Comments on this Indian Standard may be sent to BIS giving the
following reference:

Dot : No. BDC 65 (4469)

Amendments Issued Since Publication

Amend No. Date of Issue Text Affected

BUREAU OF INDIAN STANDARDS

Headquarters:

Manak Bhavan, 9 Bahadur Shah Zafar Marg, New Delhi 110002


Telephones : 331 01 31, 331 13 75 Telegrams : Manaksanstha
( Common to all Offices )

Regional Offices: Telephone

Central : Manak Bhavan, 9 Bahadur Shah Zafar Marg I 331 01


13 75
31
NEW DELHI 110002

Eastern : I/14 C. I. T. Scheme VII M, V. I. P. Road, Maniktola


CALCUTTA 700054 36 24 99

Northern : SC0 445-446, Sector 35-C, CHANDIGARH 160036 2 1843


( 3 16 41

Southern : C. I. T. Campus, IV Cross Road, MADRAS 600113 41 24 42


41 25 19
41 29 16
Western : Manakalaya, E9 MIDC, Marol, Andheri (East)
BOMBAY 400093 6 32 92 95

Branches : AHMADABAD. BANGALORE. BHOPAL. BHUBANESHWAR.


GUWAHATI. HYDERABAD. JAIPUR. KANPUR. PATNA.
TRIVANDRUM.

Printed at Printrade, New Delhi, India

You might also like