You are on page 1of 23

DOC. NO.

: PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 1 of 23

CONTENTS
1 - SCOPE

2 - APPLICATION
3 - INTRODUCTION OF THE WORK
4 - MANAGEMENT COMMITMENT
5 - ORGANIZATION
6 COMMUNICATION
7 ENGINEERING AND DESIGN
8 - DRAWING AND DOCUMENT CONTROL
9 PURCHASING
10 MANUFACTURING PROCESS
11 - SPECIAL PROCESSES
12 PRODUCT IDENTIFICATION AND TRACEABILITY
13 MARKING AND CUTTING PROCESS
14 BULD UP MEMBER AND FITTING PROCESS
15 WELDING PROCESS
16 FINISHING PROCESS
17 BLASTING PAINTING PROCESS
18 INSPECTION AND TESTING
19 CONTROL OF NONCONFORMING PRODUCT
20 CORRECTIVE AND PREVENTIVE ACTION
21-STORAGE, PACKING, AND DELIVERY
22 -QUALITY RECORDS

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 2 of 23

0. REVISION STATUS

Rev Description of Change Effective Date


No

0 Initial release

1 Additional processes and Organizational chart 20.08.08

Prepared by: Cc to: Approved by:

QUALITY DEPT. CUST. SERV. DEPT DIRECTOR


Department
Name Mark Nofuente Nanda Kumar Adib Kouteili

Date 23rd of Oct. 08 23rd of Oct. 08 23rd of Oct. 08

Signature

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 3 of 23

1. SCOPE

This quality plan describes the manufacturing details of pre-engineering


structures and the quality control requirements where all the respective
departments of PEB Steel Buildings Co., Ltd. need to demonstrate their ability to
consistently provide the service that meet customers and applicable regulatory
requirements.

2- APPLICATION

This quality plan is intended to be applicable to all the respective departments of


the manufacturing process of the PEB Steel Buildings Co., Ltd.

3- INTRODUCTION OF THE WORK

CUSTOMER :

NAME OF PROJECT :

JOB SITE LOCATION :

DESCRIPTION OF ITEMS:

WORK VOLUME:

PERIOD OF MANUFACTURING:

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 4 of 23

4. MANAGEMENT COMMITMENT

The management of PEB Steel Buildings Co. Ltd. has fully committed to
meeting all the specified requirements on time with high degree of quality.
The manufacturing and quality system requirement described in this
quality plan is based on PEB STEEL and international standards, design
and technical specification, and other contractual requirements.

All our employees are responsible for comply with this quality plan and for
the quality of work carried out on the manufacturing process of structures,
services and performance.

Operation Director, Mr. Adib Kouteili is responsible and has the authority
to organize, maintain and administer this quality plan and to ensure its
effective implementation.

Further all other key staff of our factory is given the responsibility and
authority to identify any problem and implement solutions to those
problems and to control the product quality at all stages of manufacturing.
This includes preventing dispatch defective, nonconforming and
unsatisfactory products to customer until satisfactory corrective action has
been taken.

Each process group is required to implement this quality plan in each area
of their responsibility.

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 5 of 23

5. ORGANIZATION

ENGINEERING MANAGER SUPERVISORS

QC SUPERVISOR &
QUALITY DEPT. HEAD INSPECTORS

SHIPPING /PURCHASING
SUPERVISOR &
LOGICSTIC & PURCHASING FOREMAN
MANAGER

CUSTOMER SERVICE
CUSTOMER SERVICE ENGINEER/SUPERVISOR
DIRECTOR
MANAGER
Mr. ADIB KOUTEILI

ACCOUNTANT
CHIEF ACCOUTANT

ADMIN & HR H.R.ASSISTANT

PLANT MANAGER PRODUCTION/PLANNING


ENGINEERING/SUPERVIS
MR. NABIL KHALAF OR

SITE ENGINEERS / EREC.


PROJ. MGMT. MANAGER COOR.

IT SUPERVISOR IT TECHNICIANS

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 6 of 23

6- COMMUNICATION

6.1 Management has ensured that the appropriate communication process by


defining interrelations between the departments within the organization by
means of documented internal communication instructions. It shall ensure the
effective communications take place regarding the effectiveness of the
quality control and manufacturing system.

6.2 All the communication shall be addressed to:

Mr.Adib Kouteili
Director
Ho Chi Minh City Office
Unit 701, 7th Floor, City Plaza,
60A Truong Son St.,
Tan Binh Dist, HCMC
Tel: (84) 8 847 5475 / 997 5975
Fax: (84) 8 847 6476 / 9975157

Vung Tau City Office


PEB Steel Buildings Co., Ltd.
Dong Xuyen Industrial zone, Ward 10, Vung Tau city Viet Nam
Tel: (84) 64 613 124 / 613126
Fax: (84) 64 613 125
Mobile: (84) 903 353 335
E-mail: adib@pebsteel.com.vn

7- ENGINEERING AND DESIGN

7.1 PEB design department shall take the responsibility of the following related to:
a. Design development
b. Identifying and documenting any statutory and regulatory requirements
c. Review of the selection of design input requirements
d. Resolving incomplete, ambiguous or conflicting requirements
e. Documenting the design output
f. Design calculations

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 7 of 23

g. Design analysis
h. Design reviews
i. Design verification
j. Design validation

7.2 Acceptance criteria and identifying any crucial design requirements for the main
frame and other structures shall be the responsibility of customer.

7.3 Any design modification required by design department or customer during the
manufacturing process, a written instruction shall need to be issued through
PEBs Customer Service Department so that the modification can be embodied
in the final product.

8. DRAWING AND DOCUMENT CONTROL

8.1 Planning Engineer shall establish and maintain a project document list showing
the latest revision status of the documents and it shall be readily available to
preclude the use of invalid/superseded documents.

8.2 Any superseded document retained for reference by the user and it shall be
communicated to the Planning Engineer. Planning Engineer shall identify those
documented to clearly differentiate from current version of documents by means
of stamp SUPERSEDED and RETAINED BY USER.

8.3 All the engineering documents which include PEB design, drawing and detailed
engineering drawings, connection details, engineering specifications and product
drawing or shop drawings shall be reviewed, controlled, managed, maintained,
issued revised and recalled by the Panning Engineer.

8.4 Design drawing list shall be based on drawing number and showing the status of
revision and date of receipt from the PEBs Customer service department. The
Engineer in-charge shall ensure that all the information provided in the design
drawings is very clear, complete and legible.

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 8 of 23

8.5 If any unclear, portion of the design drawing shall be clouded and marked as
HOLD in design drawing. No engineering work shall be carried out on
HOLD until it is released by PEBs design dept. with appropriate information.

8.6 Upon receipt of revised design drawing from PEBs design dept. the Planning
Engineer shall update the drawing list for new revision and he will ensure that
the revised portions have been clouded clearly, having the revision mark in a
triangle at every place of revision.

8.7 The new revised information shall be compared with existing drawing to identify
the changes or modification. If any discrepancy or conflict is found, it shall be
reported to PEBs design dept. immediately.

8.8 Upon receipt of new revision, the existing drawing shall be SUPERSEDED
and the new revision drawings shall be distributed to all the processes area
concerned and the old revision drawing shall be withdrawn from all the process
concern.

8.9 If any design revision received after issue of shop drawing to the production
process, the Planning Engineer shall communicate this information to the
production process and request them to hold the production process of such
items.

9. PURCHASING OF MATERIAL, CONSUMABLES AND PAINTING


MATERIAL

9.1 Purchasing department of PEB shall ensure all the materials, welding consumables
and paint material purchased from approved manufacturer/supplier to confirm the
specified requirements of design drawing and international standards.

9.2 All of the steel materials shall be procured for the main frame structure by PEB
STEEL purchasing department and delivered to the factory at Vung Tau city.
Purchasing department in-charge in Factory will coordinate with Head office to
procure other consumables such as: Welding electrode & Wire, Paint and thinner,
Tools, Safety devices and accessories etc.

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 9 of 23

9.3 Purchase order/Sales contracts shall be described and defined clearly the material
to be purchased. All the purchasing information shall be defined and documented
in the purchase order/sales contract.
9.4 Prior to order being placed to any supplier or manufacturer, purchasing
department Head shall ensure the adequacy of the specified purchase requirement
by communicating with the supplier or manufacturer.
9.5 Prior to release purchase order/sales contract to the supplier, the purchasing
Documents shall be verified by the end user in the company who made the
Requests and it shall be reviewed by the Planning.

9.6 All the materials, consumables and paints from the supplier or manufacturer
shall be verified and inspected to ensure that the materials meet specified
purchase requirements. All the verifications and inspection activities shall be in
accordance with the company in-coming material receiving inspection and test
procedure.

10. MANUFACTURING PROCESS

The company has identified various processes that involve in the manufacturing
of mainframe structures:
Marking / cutting
Build up of members
Fitting / assembly
Final Welding
Secondary and Sundry Parts
Sheeting, Panel and Trims
Surface Treatment and Painting
Buyouts
Loading /Delivery

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 10 of 23

11. SPECIAL PROCESSES

The following processes are considered as special processes where conformity of


product is totally depend upon the capability of personnel, equipment and
facilities used and where the resulting output cant be fully verified by
subsequent inspection and testing and where the deficiencies become apparent
only after the product is used:

Welding
Surface treatment and painting
NDT

12. PRODUCT IDENTIFICATION AND TRACEABILITY

12.1. Identification of parts shall be followed in accordance with PEB STEEL design
and shop detail drawings.
12.2 Planning and Production Manager in consultation with other concern
departments shall establish the identification of each item based on design and
contract requirement.
12.3 Upon completion of marking and prior to start cutting every parts, the
identification number of the particular parts shall be written by means of
crayons/paint in accordance with drawing and part list.
12.4 Prior to start blasting of items, blasting team shall prepare the metal tags with
hard punched identification number of the particular items and hang on the
product by mean of steel wire to avoid missing of the tags during blasting.
12.5 Identification of completed product and logo of company shall be stenciled by
paint on the surface of connecting parts so that it will not appear on the final l
structure.

13. MARKING AND CUTTING PROCESS

13.1 Prior to marking, bend or deformation of the material shall be corrected by


mechanical method or heat-cooling methods. On the heat-cooling method, the
heating temperature should be less than 4500C

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 11 of 23

13.2 Prior to start marking, cutting plan showing allotment of the component on the
ordered materials shall be made to minimize the losses and surpluses.

13.3 Application to the center punch in the marking shall be minimized except for
those areas where marking can be completely erased afterwards by means of
drilling, coping or welding.

13.4 As much as possible, original heat number which is stamped by mill must be
retained and marking should be avoided on the identification numbers. Only on
un-avoidable circumstances, the original plate heat numbers shall be transferred
by means of hard punch at unusable corner of the material.

13.5 The cutting face of each member shall be perpendicular to the axis line unless
otherwise specified on the drawing.

13.6 Cut face shall be free from remarkable uneven notch or slag attachment. In case
of occurrence of notch, such part shall be welded and finished to flatness by
means of grinder.

14. BULD UP MEMBER AND FITTING PROCESS

14.1 Fitter shall inspect the items visually for any surface damages, bends and
deformation. If so, it shall be properly corrected in accordance with shop detail
drawings.

14.2 It is the responsibility of fitter/QC Supervisor to verify the size, thickness, hole
details, hole diameter, spacing and number of holes. The contact surfaces of the
components shall be free of burrs and foreign materials that would prevent solid
seating of the part.

14.3 All the edge preparation and site assembly profile on both main members and
components shall be carried out prior to start fitting and in accordance with shop
drawing.

14.4 Assembly work shall be carried out with suitable tools and equipment, such as
surface plate, positioners, jacks, lever blocks, chain blocks and strong backs.

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 12 of 23

14.5 All full penetration weld joints of fitting shall have minimum root gap of 3mm
and the edge preparation strictly in accordance with shop drawing.

14.6 The fitter performing the tack welding shall be qualified for the process in
accordance with the applicable welding procedure specification.

14.7 Electrode for tack welding shall be in accordance with the specification and as
per the approved welding procedure.

15. WELDING PROCESS

15.1 All the welding process shall be in accordance with the approved welding
procedure specification (WPS) and procedure qualification record (PQR).

15.2 All the welders to be engaged in this work should have approved welder
performance qualification test certificates.

15.3 Prior to the welding, all welding joint surfaces shall be clean and dry condition.
Rust, paint, dust, grease or any other foreign particles shall be cleaned by
mechanically using wire brush or grinding.

15.4 When the pre-heat is required as per WPS, pre-heating temperature of the base
metal shall be of 100-1200C and shall be checked by temperature crayon.

15.5 Welding gaps or bevels must be accurately controlled over the entire joint during
welding operation.

15.6 Control prior to welding

15.6.1 Consumables such welding electrodes, flux etc. to be used shall be as per
standards. Deteriorated or spoiled consumables should not be used.

15.6.2 Welding equipment should be in satisfactory working condition and be able to


product right quality welds.

15.6.3 Weld testing equipment should be in good operating condition and be handled
by the well trained staff.

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 13 of 23

15.7 Control during welding

15.7.1 The weld groove should be free from dirt, rust, oil, slag or any other foreign
particles which affect the quality of the weld.

15.7.2 Job edge preparation should be as per approved welding procedure

15.7.3 The fit-up, gap, orientation, welding position, method and sequence of
assembly all should be as per approved welding procedure.
15.7.4 Tack welds should be of adequate size, length and pitch.

15.7.5 Fittings, clamps, fixtures, etc. should not interfere with welding

15.7.6 Methods should be adopted to minimize distortion

15.7.7 Slag should be thoroughly removed from each pass in multi-pass arc welds and
spot welding electrodes should be dresses periodically.

15.8 Control after welding

15.8.1 Cleaning and visual inspection of welding includes: Final weld appearance,
final weld size, extent of welding, dimensional of accuracy, amount of
distortion, surface cracks, undercut, overlap, exposed porosity, unacceptable
weld profile, and roughness of the weld face.

15.8.2 Check the welding conformity to the drawings and specification.

16. FINISHING PROCESS

16.1 Welding slag and spatter must be cleaned properly and use wire brush or power
brush as post cleaning operation.
16.2 If any undercutting or porosity found during cleaning, mark the spot by means of
crayons and report to welding supervisor for repair and ensure the repair has
been done in accordance with the standard and acceptable level.
16.3 If any crater observed, note down the welder identification number which is
written near the welding and call the same welder for repair.

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 14 of 23

16.4 All the bolt holes must be clean and trimming by means of grinder, round file
and reamer if in case necessary.
16.5 All the cutting edges must be grind smooth and all the sharp edges must be
radius and smooth.
16.6 All the gas notches must be rebuilt by (touch up) qualified welders and grind
smooth.
16.7 Any bend, deflection and deformation of member out of tolerance should be
corrected by means of heating and cooling methods.

17. BLASTING PAINTING PROCESS

17.1 Prior to start painting blasted surface shall be cleaned by dry compressed air and
ensure the surface is dust free.

17.2 The following area shall be covered by masking tape to avoid painting:

The parts to be metal to metal contact

Embedded steel in contact with concrete

The parts where field welding is to be applied

17.3 Each container of paint shall be clearly marked or labeled to show paint
identification date of manufacture, batch number, analysis of contents,
identification of all toxic substance and special instruction.

17.4 All ingredients in any container of paint shall be thoroughly mixed before use and
shall be agitated often enough during application to keep the paint uniform.

17.5 The type of thinner shall comply with paint manufacturers instructions. Correct
amount of thinner to be added to particular application when the use of thinner is
permissible, thinner shall be added slowly to paint during mixing process.

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 15 of 23

17.6 The equipment used for painting application shall be suitable for the appropriate
purpose and coating system and shall be capable of properly atomizing the paint
to be applied.

17.7 All the paint pot shall be equipped with suitable pressure regulators and gauges.

17.8 Paint shall be applied in a uniform layer with overlapping at the edges of the
pattern. During application, the painting spray gun shall be held perpendicular to
the surface which will ensure that a wet layer of paint is deposited on the surface.
The trigger of the gun should be released at the end of each stroke.

17.9 The air caps, nozzles and needles shall be those recommended by the paint
manufacturers of material being sprayed and equipment being used.

17.10 Traps or separators shall be provided to remove oil and condensed water from air. The
traps or separators must be of adequate size and must be drained periodically during
operations.

17.11 The pressure on the material in the pot and of the air at the gun shall be adjusted
for optimum spraying effectiveness.

17.12 The pressure on the material in the pot shall be adjusted when necessary for
changes in elevation of the gun above the pot. The atomizing air pressure

At the gun shall be high enough to properly atomize the paint.

17.13 When spraying the spray gun should be held from 250 mm to 350 mm from the
surface and maintained perpendicular to the surface throughout the stroke. At the
end of each pass, the gun trigger should be released.

17.14 For airless application, the distance should be from each spray pass should
overlap the previous one by 50%, and where possible, a cross hatch technique

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 16 of 23

should be used. This requires a duplicate series of pass at 90o to the first to
ensure complete and uniform coverage.

17.15 Paint shall not be applied when the temperature of steel or the paint is below 4o C.

17.16 Paint shall not be in rain, wind, fog, mist or when the steel surface temperature is
less than 3o C above the dew point.

17.17 Paint shall not be applied when the relative humidity is above 80%. The
manufacturers instructions shall be followed regarding the acceptable humidity
range for the particular paint.

17.18 Paint thickness shall be in accordance with the customer requirements.

18. INSPECTION AND TESTING

18.1 Material receiving inspection

18.1.1 All the materials shall be inspected against the specified material specification
and the mill certificate.

18.1.2 Upon receipt of materials/products, storekeeper shall verify the quantity, number
of packing, type of materials, general appearance of materials and conformance
against the requisition order, purchase documents, packing list and delivery
order. He shall also make arrangements to request Q.C Inspector for receiving
inspection.

18.1.3 Q.C Inspector shall carry out the following visual inspection upon receipt
Of materials:
General appearance
Corrosion or pitting conditions
Conformance to the purchase order
Material identification (heat number) conformance to the Mill certificate.

18.1.4 All the welding consumables shall be in inspected before use.

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 17 of 23

18.1.5 Material shall not be used for production until it has been inspected or verified as
conforming to specified requirements.

18.2 In-process inspection and testing

18.2.1 In-process inspection shall be carried out in all stages of process in order to verify
the conformance of the product against drawings and technical specification.
18.2.2 Product shall be hold until the required in process and test have been completed
and shall be released for next process, only after acceptance by QC inspector.
18.2.3 If any part or item found nonconformity during in-process inspection and test
shall be identified, segregated and hold until the items to be re-inspected and
accepted by QC inspector.

18.2.4 Marking and cutting process

a) The in- process inspection during marking and cutting process shall include:

Checking of full scale template


Verification of marking against the required dimension including any
cutting allowance
Verification of part number
Transfer of heat number, when necessary
Edge preparation in accordance to the drawing

b) In-process inspection during marking and cutting shall be carried out by the
marking/cutting group leader and the Q.C Supervisor / Engineer may
witness the transfer of heat number when necessary.

18.2.5 Fit up process

a) In process inspection during the fitting and assembly of the items


b) Any non-conformance observed during inspection, QC supervisor shall fix a
HOLD label and subsequently NCR to be raised.

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 18 of 23

c) Appropriate corrective action shall be carried out within the period stated in
the NCR reports. Upon completion of satisfactory corrective action, the
same item shall be re-inspected again in accordance with the requirements.
d) If any items are not in conformance with the requirements after necessary
repair and re-inspection, QC Engineer shall fix REJECT label and
separate the item from the assembly line and further investigation to be
conducted for the failure.

18.2.6 Welding process

a) QC Engineer shall verify the following conditions for conformity to the


applicable specification, AWS D1.1 Edition 2008.

Review of the welding procedure specification (WPS)


Review of welding procedure qualification record (PQR)
Review of welders performance test records
Verification of the welders against their qualification badge number
Verification of joint preparation, dimensions against design drawing
and cleanliness
Alignment and fit up of the pieces being welded.
Welding process and consumables
Condition of welding equipment and power sources
Preheat temperature
Condition of tack welding
b) QC Engineer/welding Supervisor shall inspect the following aspect during
the welding process
Treatment of tack welding
Verification of corrective usage of electrodes and classification
Verification of welder identification number written near the weld joint
Inspection of quality of the root pass and the succeeding weld layers
Ensure the sequence of welding

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 19 of 23

Ensure the adequate cleaning of welding


Verify the root pass penetration prior to welding a second side and ensure the
back chipping/grinding in accordance with the welding procedure specification.

c) Any welding defect noticed by the QC Engineer who shall mark the
defective area and subsequently the welding supervisor shall take necessary
corrective action.

18.2.7 Non-destructive Inspection


As applicable for jobs
NDT inspection shall be carried out by subcontractor.
Any non-conformance found through NDT test reports and the defects shall be
identified by the paint/chalk and subsequently HOLD label shall be fixed to
the defective area and NCR to be raised for necessary corrective action.
18.2.8 Painting inspection

a) QC Engineer shall perform random inspection on the profile of the surface


preparation. Surface profile comparator shall be used to verify the surface
profile conformance.
b) The following shall be inspected upon completion of painting:
Required dry film thickness
Dryness of the paint
Completeness of coverage
Brush mark, run sags etc.
Adhesion of dry paint
Specified number of coats
Blisters, pores etc.

18.2.9 Final inspection and testing

a) The equipment shall not be dispatched or handed over to customer until all
the activities specified in this work plan/quality plan, inspection & test plan
including applicable records and documents have been satisfactorily
completed.

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 20 of 23

b) The final inspection activities shall include:


Ensure all the previous inspection and tests have been performed
The as-built configuration is the same as the issued status of all parts, sub
assemblies, specified by the design standard.
All the documented non-conformities have been resolved and remedial
action taken and verified
All customers and Engineers concession if any, has been approved.
All the inspection and test records have been collected and complete the
final inspection records and documentation.
Any inspection and test result beyond the specified limit is either subject to
an approved concession, an approved specification change or re-inspection
which shows conformance with the requirements.

19. CONTROL OF NONCONFORMING PRODUCT

19.1 QC Engineer shall be responsible for review and disposition of non-conforming


report.

19.2 Al the non-conforming product shall be segregated from the routine process or
from the conforming items. If the parts or items are heavy and too big, a
HOLD label shall be fixed until the appropriate corrective action taken.

19.3 Any item or part number that has been repaired, reworked and modified shall be
re-inspected prior to it being released to further process or dispatch. Re-
inspection and test records shall indicate the original rejection, disposition and
the result of the re-inspection.

19.4 Upon completion of correction action, QC Engineer shall verify the effectiveness
of the corrective action and records in the non-conformance report. NCR shall be
closed once the corrective action is completed and satisfied.

19.5 QC Engineer shall ensure that product which does not conform to the specified
requirements is prevented from further processing or dispatch to the customer.

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 21 of 23

20. CORRECTIVE AND PREVENTIVE ACTION

20.1 The QC Engineer shall be responsible for the execution of proposed corrective
action for any customers complaint or comments and he is also responsible to
submit the appropriate corrective action reports to customers representative
when required.

20.2 Corrective action shall include the documenting/recording both cause and
proposed appropriate corrective action needed to eliminate the cause of non-
conformities.

20.3 The concerned action party shall report when the corrective action has been
completed and the QC Engineer shall verify it.

20.4 If QC Engineer determines the non-conformance is minor and the effect of non-
conformities does not affect the performance of the product, it shall be
recommended to use as it is without any corrective action.
20.5 In case of product non-conformity is considered as major the QC Engineer shall
recommend for repair the product to meet the requirements. In such case, the
repair method and acceptance criteria shall be documented in the non-
conformance report.

21. STORAGE, PACKING, PRESERVATION AND DELIVERY

21.1 Storage

21.1.1 Appropriate designated storage areas for raw materials and the equipment shall
be planned in advance in order to prevent damage or deterioration.

21.1.2 After painting, the product shall be kept in open yard on the stable steel skid
beams and there shall not be any deflection in the middle.

21.2. Preservation (protection)

21.2.1. Machined surfaces shall be coated with rust preventive grease

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 22 of 23

21.2.2. All threads of bolt and nuts including any exposed parts should be coated with
rust preventive grease or oil to prevent corrosion during storage.

21.3 Packing and marking

Marking and identification shall be done clearly on the equipment and other
packages and shall be in accordance with requirements, which is stated in
contract or technical specification.

21.4 Delivery

21.4.1 Products shall be delivered to the Project site based on schedule and instruction
to delivery from Customer Service Department (PEB STEEL).

21.4.2 Delivery/shipping documents as required shall be prepared by the Shipping


Manager, Reviewed by Factory Manager and submit to CSD for review and final
submission to customers/client.

22. QUALITY RECORDS

22.1 The following records shall be maintained to demonstrate to conformance of the


goods to the requirements:

Material Mill Certificate ( from the Manufacturer)


Appropriate Welding Procedure Specification (WPS)
Appropriate Procedure Qualification Record (PQR)
List of Qualified Welder Involved in Welding Process
Approved Welder Performance Qualification.
Incoming Material Inspection Report
In Process and Final Dimensional Inspection Report
Secondary Inspection Report
Final Welding Inspection Record
Appropriate NDT Inspection Report

PEB/ QC./Updated Quality plan


DOC. NO. : PEB-QP-J0B-

QUALITY PLAN REV. : 1

PAGE : Page 23 of 23

Surface Preparation Inspection Report


Painting Inspection Report
Appropriate Non-conformance Report
Pre Shipment Inspection Report
Final Release Inspection Report
22.2 All the quality records shall be stored in the place having the facilities that
provide a suitable environment to prevent damage or deterioration and to prevent
loss.

PEB/ QC./Updated Quality plan

You might also like