Incite Construction Lot Codes

Construction NSW & ACT


ROADS (& Water)
PROCESS SUB PROCESS
PRE Preliminary
SIES Site Establishment
SEDC Sedimentation Control
ACRO Access Roads/Tracks
WEED Weed Eradication
DEMO Demolition
PADJ Property Adjustments
DISH Dilapidation Surveys Housing
DISR Dilapidation Surveys Existing Road Systems
GEOT Geotechnical Investigation
TRST Traffic Staging
TRCO Traffic Control
QAEV Quality Event
CMDA Concrete Mix Design Approval
AMDA Asphalt Mix Design Approval
WLDQ Welding Qualifications
TRCP Traffic Control Plan Approval
SWMA Site Won Material Stockpiles and Approvals
BPMD Batch Plant Mobilisation/Demobilisation

UTS Utilities and Services


WATE Water Services
ELEC Electricty Services
TELE Telecommunication Services
SEWS Sewerage Services
GASS Gas Services
LOCS Locate Service

ELE Electrical
COM Communications
ECON Installation of Conduits
CBLI Cable Ladder Installation
CBPE Cable Pulling
ECOM Commissioning
SBDS Switchboard Supply
SBDI Switchboard Installation
DICL Installation of Ductile Iron Concrete Lined
IFLC Installation of Field Cabinet
ITDC Installation of Trenchless Ducts
IFOC Installation of Fibre Optic Cable
IEMT Installation of Emergency Telephones
AQMG Air Quality Monitoring
TTEE Test and Energise
FIRA Fire Rating

SSC Soft Soil Consolidation


DDSM Dry Deep Soil Mixing
WDSM Wet Deep Soil Mixing
DYCO Dynamic Compaction
WIDR Wick Drains
DRSC Dry Stone Columns
COIC Concrete Injected Columns
GEOI Geotechnical Instrumentation / Monitoring
LIWF Light Weight Fill
DCCL Driven Concrete Columns

EWK Earthworks
CLGR Clear and Grub

Leighton Contractors Pty Limited ACN 000 893 667 ABN 98 000 893 667 Page 1 of 6
369741051.xlsx Revised October 2010
TOPS Topsoil Stripping
BORW Borrow
CRSH Crushing of site won materials
DRBL Drilling and Blasting
FTRC Foundation Treatment Cutting
FTRE Foundation Treatment Embankment
CLNR Contaminated Land Remediation
ASST Acid Sulphate Soil Treatment
CWPS Construction Working Platforms
LEMS Low Embankment Strategy
SRPL Surcharge Placement
SURE Surcharge Removal
ECUT Earthworks Cut
CTFT Cut to Fill Transition
EDFL Excavation Cut - Design Floor Level
ROFL Rock Fill
EMGF Embankment General Fill
BACK Backfill
UPZF Upper Zone
ISON Installation of Soil Nails
SHCR Shotcreting
TMBT Trim Batters
VERG Verge
ROFC Rock Facing (Pitching)
SEMZ Select Material Zone
STBE Stabilisation of Earthwork

DRG Drainage
DRAB Drainage Blankets
SEDB Sediment Basin
ODRV Open Drains Vegetated
ODCL Open Drains Concrete Lined
CDRL Catch Drains Lined
CDRU Catch Drains Unlined
LEVB Levee Bank
SCPR Scour Protection
ICDS Insitu Concrete Drainage Structure
PCDS Precast Concrete Drainage Structure
RCBC Reinforced Concrete Box Culvert
RPCU Reinforced Concrete Pipe Installation and/or Culvert
DCWU Drainage Concrete Works under 1.8m High
DCWA Drainage Concrete Works above 1.8m High
TPIP Transverse Pipe Culverts
LPIP Longitudinal Pipe Culverts
PDPC Pavement Drainage - Pipe Culverts
PCPH Pre-cast Pits / Headwalls
SSDR Sub-Soil Drains
DRAI Drain (Transverse & Longitudinal)
TRDR Trench Drains
IPDR Intra Pavement Drainage
EGDR Edge Drains
HBDR Herring Bone Drains
FLGT Floodgates
FPIT Finishing Pits
CNBS Concrete Batter Shutes
SHBP Shotcreting Batter Protection

RWL Retaining Walls


DRPI Driven Piles
BOPI Bored Piles
BLIN Blinding
INRC Insitu Reinforced Concrete
SHOT Shotcrete
STEF Steel Fabrication
STER Steel Erection
INPA Install Panels
CAPP Capping Beams

Leighton Contractors Pty Limited ACN 000 893 667 ABN 98 000 893 667 Page 2 of 6
369741051.xlsx Revised October 2010
BOCU Box Culvert
RESW Reinforced Soil Walls
BLOW Block Walls
PILW Piled Walls
RWFF Retaining Wall Foundation and Footing
RGBW Rock Gabion Walls

NWL Noise Wall


DRIP Driven Piles
BORP Bored Piles
BLID Blinding
IRCO Insitu Reinforced Concrete
PRCP Pre-Cast RC Panel Manufacture
SFAB Steel Fabrication
STEE Steel Erection
INWC Install Noise Wall (E.g. Concrete Panels, Wood Panels, Steel Panel
INWH Install Noise Wall - Hebel
HTRE House Treatments
EMNW Earth Mound Noise Wall

PIP Pipeline
SSWR Supply Sewer Pipeline
ISWR Install Sewer Pipeline
SWTR Supply Water Pipeline
IWTR Install Water Pipeline
SREP Supply RE (Recycled Effluent) Pipieline
IREP Install RE (Recycled Effluent) Pipieline

STR Structures
BRG Bridges
PCC Precast Concrete
MOAU Manufacturing of Arch Units
MOGP Manufacturing of Girders / Planks
MPBR Manufacture of Precast Bridge Elements (E.g. parapets, pile caps, columns, piers, headstocks)
FBSS Fabrication of Structural Steel
FMSI Fabrication of Minor Steel Items (E.g. Bridge Furniture, Platforms, Stairways, etc)
SPIL Sheet Piling
RANC Rock Anchors
SCPL Screw Piles
DPCP Driven Prestressed Concrete Piles
DHSP Driven H Section Steel Piles
BCPP Bored Cast in Place Concrete Piles - Permanent Casing
BCCT Bored Cast in Place Concrete Piles Temporary Casing
CWKU Concrete Works under 1.8m High
CWKA Concrete Works above 1.8m High
CWBC Concrete Works Balanced Cantilever
PTEN Post Tensioning
IBBE Installation of Bridge Bearings and Mortar Pads
IEXJ Installation of Expansion Joints
EOAU Erection of Arch Units
EOGP Erection of Girders / Planks
EPBR Erection/Installation of Precast Bridge Elements (E.g. parapets, pile caps, columns, piers, headstocks)
ISCP Insitu Concrete Parapets
EOSS Erection of Structural Steel
EMSI Erection/Installation of Minor Steel Items
IBDR Installation of Bridge Drainage
IBRL Installation of Barrier Rails
ITHS Installation of Throw Screens
PPJS Parapet Joint Sealing
IBPP Installation of Batter Protection Panels
BFAS Backfill Around Structures
VFIN Voids Forms Installation
CFAP Continuous Flight Auger (CFA) Piles
DRCP Driven Reinforced Concrete Piles
INWM Install Waterproof Membrane (Bridge de-bonding)

Leighton Contractors Pty Limited ACN 000 893 667 ABN 98 000 893 667 Page 3 of 6
369741051.xlsx Revised October 2010
FPV Flexible Pavements
BFPV Bound Fexible Pavement
UFPV Unbound Flexible Pavement
DEGB Dense Grade Base
DEGS Dense Grade Sub-Base
PRSL Prime Seal
PRRS Primer Seal
AC10 Dense Graded Asphalt - AC10
AC14 Dense Graded Asphalt - AC14
AC20 Dense Graded Asphalt - AC20
OG14 Open Grade Asphalt - OG14
PM14 Dense Graded Asphalt with A15E Binder
FLSB Flexible Sub-Base
FLBA Flexible Base
SMAC Stone Mastic Asphalt

RPV Rigid Pavements


SUBB Subgrade Beams
DLMC Debonding (LMC)
COSA Concrete Slab Anchors
CSPT Concrete Subbase Paving Trial
CBPT Concrete Base Paving Trial
CSMP Concrete Subbase, Machine places
CSHP Concrete Subbase, Hand Placed
CBMP Concrete Base, Machine Placed
CBHP Concrete Base, Hand Placed
CBSH Concrete Base, Shoulder Hand Planced
CBSM Concrete Base, Shoulder Machine Planced
SFRM Steel Fibre Reinforced Concrete Machine Placed
SFRH Steel Fibre Reinforced Concrete Hand Placed
STSS Structural Shoulder Slab incl Precast
EDGE Edge Detail / No Fines
CRCM Continuous Reinforced Concrete Pavement Machine Placed
CRCH Continuous Reinforced Concrete Pavement Hand Placed
CRCS Continuous Reinforced Concrete Pavement Shoulder
REOP Reo for Continuosly Reinforced Concrete Pavement
CUTT Concrete Cutting
SEAL Concrete Sealing

SGN Signage
FSSS Fabrication of Strutural Steel Signage
FSFC Fabrication of Sign Faces
TSIN Temporary Signage
ISNP Installation of Sign Posting
SSFF Special Signage Foundation and Footing
SSER Special Signage Erection
GFFT Gantry Foundation and Footing
GNER Ganty Erection

FWK Finishing Works


FPPR Footpaths and Pram Ramps
ICTI Insitu Concrete Traffic Islands
ICDW Insitu Concrete Driveways
KGHP Kerb and Gutter - Hand Placed
KGSF Kerb and Gutter - Slipform
CBAR Concrete Barriers
GRSB Guard Rail Safety Barrier
WRSB Wire Rope Safety Barrier
GPST Guide Posts
CRAT Crash Attenuators
PVMK Pavement Marking
LINE Line Marking
RPMK Raised Pavement Markers
PAIN Application of Paint
PCOT Application of Protective Coating
ATGP Anti Graffiti Painting
AGTS Application of Granosite

Leighton Contractors Pty Limited ACN 000 893 667 ABN 98 000 893 667 Page 4 of 6
369741051.xlsx Revised October 2010
KGNF Kerb and Gutter No Fines
PITC Pit Completion

LSC Landscaping
SEED Seed Collection
PROP Plant Propagation
LSPL Landscaping and Planting
BUSH Bush Regeneration
WALK Walking Track
HYDM Hydromulching
HYDS Hydroseeding

FEN Fencing
PRPT Property Fencing
MPFE Manproof Fencing
SPFE Stock Proof Fencing
CGIN Cattle Grid Installation
FAUN Fauna Fencing
NOTE: Perm or Temp is indicated on INCITE Lot record
LGT Lighting
SLFF Street Lighting Foundation and Footings
ESLP Erection of Street Light Poles and Luminaries
LCON Installation of Conduits
CBPL Cable Pulling
TLFF Traffic Light Foundations and Footings
ITRL Installation of Traffic Lights
ILGF Installation of Light Fittings
LCOM Commissioning
SWSU Switchboard Supply
SWIN Switchboard Installation
EMLG Emergency Lighting
EMSS Emergency Signs
PHTR Photometer

MEC Mechanical
IJTF Installation of Jet Fans
ISWG Installation of Swing Gates
ISPP Installation of Sump Pumps
MCOM Commissioning

FIR Fire Systems


DFSI Dry Fire System Installation
IFSP Installation of Fire System Pipework
IAFS Installation of Automatic Fire Suppression
IFPU Installation of Fire Pumps
FPWS Tunnel Fire Protection - Water Supply
FPWD Tunnel Fire Protection - Water Distribution
TFPD Tunnel Fire Protection - Deluge
TFDN Tunnel Fire Detection
TEEC Tunnel Emergency Equipment Cabinets

TUN Tunneling
BRIW Barrette Infill Works
PBLI Placement of Blinding
BFAT Backfill Around Tunnel
EALP Erection of Alpolic
ITIS Installation of Tunnel Instrumentation
DIAW Diaphragm Walls
CEBA Central Barrettes
PDIW Preparation of Diaphragm Walls
FSPS Fabrication of Steel Pipe Struts
ESPS Erection of Steel Pipe Struts
IABD Installation of Architectural Board
CWTN Concrete Works Tunnel
ECTN Excavation Cut - Tunnel
ECTR Excavation Cut - Tunnel Ramp
ECTS Excavation Cut - Tunnel Sump

Leighton Contractors Pty Limited ACN 000 893 667 ABN 98 000 893 667 Page 5 of 6
369741051.xlsx Revised October 2010
WAPR Installation of Tunnel Waterproofing
VMTH Installation of Vermitex TH
GCJC Grouting Concrete Joints and Cracks
FUKO Fuko Injection
RBPR Rockbolt Procurement
RGMD Rockbolt Grout Mix Design
RBIN Rockbolt Installation
WHDR Weep Hole Drilling

SBU Service Buidlings


AFLR Access Floor
BLKW Blockwork
ROOF Installation of Roof
DOOR Installation of Doors
IPTL Installation of Partitions and Linings
ITWP Installation of Tiles and Waterproofing
IWTT Installation of Water Tank
FWTT Fabrication of Water Tank
IWTP Installation of Water Tank Pumps

ITS Intelligent Transport System


RRBC Installation of Radio Rebroadcast System
MCRS Installation of Microwave Radio System
CCTV Installation of CCTV
ICOM Commissioning
OHVD Installation of Overheight Vehicle Detectors
IVBA Installation of Vehicle Barrier Arms
LOOP Installation of Loop Detectors
IVMS Installation of Variable Message Boards
VMSS Variable Message Signs
VSLS Variable Speed Limit Signs
LUSS Lane Usage Signs
TMSS Tunnel Message Signs
CMSS Changeable Message Signs
LTFS Loops (Traffic Flow system)
SASM Security Access System
ITSC ITS Cabinets
TCSM Tunnel Closure System

Leighton Contractors Pty Limited ACN 000 893 667 ABN 98 000 893 667 Page 6 of 6