LAGOS STATE GOVERNMENT

LOCAL GOVERNMENT AND LOCAL COUNCIL DEVELOPMENT AREA


BILL OF ENGINEERING AND MEASUREMENT
LGA/LCDA: APAPA-IGANMU
CONSTRUCTION OF OBALE LN-KARIMU OPELOYERU ROAD AT APAPA
ROAD: ZONE:
IGANMU L.C.D.A
LOCATIONAPAPA L.G.A WARD
LENGTH: 253.00m AVERAGE WIDTH OF CARRIAGE: 8.00m

BILL NO. 1 : PRELIMINARIES NO OF CULVERTS


ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT(N)
Provide, furnish and maintain one site
1.10 office for the Project Engineer's LS 237,195.00
Representatives

Provide survey Equipment, assistance as


1.20 may be required by the Project Engineer's PS 33,207.30
Representative

Provide, furnish and maintain one site


1.30 PS 237,195.00
office for the Project Engineer's Staff

Allow for stationeries and other office


1.40 requirement for the Project Engineer's PS 61,670.70
Staff

1.50 Allow for the purchase of project vehicles PS 1,138,536.00


Allow for the repair, running cost and
1.60 PS 142,317.00
maintenance of the project vehicles

1.70 Allow for the cost of progress photographs PS 23,719.50

Allow for wages to project staff in training


1.80 PS 142,317.00
for the Project Engineer's Representative
1.90 Allow for laboratory testing of materials PS 75,902.40
Allow for services to Project Engineer's
1.10 PS 189,756.00
Representative

Allow for the construction and furnishing of


1.11 PS 170,780.40
a road camp in the Area

TOTAL BILL NO. 1 CARRIED TO SUMMARY 2,452,596.30


BILL NO. 2 : SITE CLEARANCE

ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT(N)

Clear carriage way and dispose as


2.10 3,036.00 SM 140.00 425,040.00
directed by the Project Engineer.

Demolish existing mud, timber, starter


2.20 foundation and other temporary structures PS 602,400.00
and dispose of materials as directed.

Demolish existing concrete surface for


2.30 CM
walkway and dispose of as directed.

Demolish concrete/ block walls including


2.40 CM
foundation and dispose as directed.

Scarify existing failed asphaltic surface


2.50 SM
and cart away as directed.

TOTAL BILL NO. 2 CARRIED TO SUMMARY 1,027,440.00

BILL NO. 3 : CULVERTS, DRAINS AND BRIDGES

ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT (N)

Clearing of existing drainage facilities and


3.10 LM
cart away.
Provide and construct Type 3A [0.75m x
3.40 LM
0.75m] drain to specification
Provide and construct Type 3B [0.75m x
3.50 506.00 LM 58,500.00 29,601,000.00
0.75m] drain to specification.
Provide and construct 1.20m x 1.20m Box
3.60 LM
culvert to specification.
Provide and construct 0.75m x 0.75m Box
3.70 24.00 LM 60,000.00 1,440,000.00
culvert to specification
Provide and construct Type 4B [1.00m x
3.80 LM
1.00m] drain to specification.
Provide and construct 0.9m ring culvert to
3.90 LM
specification.
3.10 Repair of concrete wall drain LM
Provide and construct Retaining Wall of
3.11 LM
1.2m heigth.
TOTAL BILL NO. 3 CARRIED TO SUMMARY 31,041,000.00

BILL NO. 4 : EARTHWORKS AND SURFACING

ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT(N)

Excavate top soil to a minimum thickness


4.10 2,024.00 SM 140.00 283,360.00
of 150mm and dispose.

Excavate all unsuitable materials except


4.20 rock along the road alignment and 1,214.40 CM 1,650.00 2,003,760.00
dispose.
Provide, spread, shape and compact to
100% West African Standard compaction
naturally occurring materials as sub base
4.30 607.20 CM 3,000.00 1,821,600.00
in compacted layers not exceeding
Provide, spread,
150mm thick andshape and compact
to an average to
thickness
100% West African Standard
of 300mm in Carriage width. compaction
naturally occurring materials as filling in
4.40 2,428.80 CM 3,000.00 7,286,400.00
compacted layers not exceeding 50mm
thick and to an average thickness of
1200mm in Carriage
Provide, spread width.
and compact approved
crushed stones ( all-in- aggregate ) as
4.50 2,024.00 SM 1,460.00 2,955,040.00
base course material to a compacted
thickness of 150mm as specified.

Provide, spread, shape and compact


4.60 Soil/Cement stabilization to 150mm SM
thickness.

Provide and lay concrete kerbs (0.3m x


4.70 0.15m) including hauling, blinding and 506.00 LM 1,850.00 936,100.00
hunching as specified for walkway.

Provide and compact sand bed to receive


4.80 interlocking stones on carriage way and 2,024.00 SM 1,000.00 2,024,000.00
walkway.

Grade, wet and roll final base to receive


4.90 2,024.00 SM 180.00 364,320.00
Asphaltic concrete or interlocking stones.

Provide and lay on sharp sand bed 60mm


thick interlocking stones, with min.crushing
4.10 506.00 SM 4,860.00 2,459,160.00
strength of 30N/mm2 and compact in
walkway area.
Provide and lay on sharp sand bed
100mm thick interlocking stones,with
4.11 2,024.00 SM 5,500.00 11,132,000.00
min.crushing strength of 30N/mm2 and
compact on carriageway.
Provide and sprread sand to fill interscites
4.12 on interlocking stones for carriageway and 2,024.00 SM 600.00 1,214,400.00
walkway
TOTAL BILL NO. 4 CARRIED TO SUMMARY 32,480,140.00

BILL NO. 5 : MISCELLANEOUS

ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT(N)

5.10 Allow for dewatering 72.00 DAYS 9,300.00 669,600.00


5.20 Allow for Lane Marking 253.00 LM 100.00 25,300.00
5.30 Provision of streetlight 3.00 NOS 395,000.00 1,185,000.00

5.40 Allow for Paint on Kerb surface 506.00 LM 650.00 328,900.00

5.50 Allow for surface dressing (2 coats) SM

Provide service duct @ 200m interval [ 4 -


5.60 36.00 LM 13,800.00 496,800.00
Way 100mm dia. PVC casing ]

Reconstruct demolished fences that have


5.70 PS 1,050,000.00
'Approved Building Plan'.

5.80 Relocation of services. PS 3,000,000.00


Provide for compensation of economic
5.90 crop, existing installation, demolition and PS
other utilities.
5.10 Allow for road diversion. PS 600,000.00
Allow for Soil Investigation and
5.11 PS 450,000.00
hydrological studies.
Provide aesthically shaped concrete flower
5.12 CM
pot on road median as specified.
5.13 Provide Greens on median as specified. SM
Supply and place reinforced concrete
median crash barriers (insitu concrete or
5.14 LM
precast elements) including foundation
and blinding to 800mm height.
TOTAL BILL NO. 5 CARRIED TO
7,805,600.00
SUMMARY

SUMMARY OF BILL OF ENGINEERING MEASUREMENT & EVALUATION


BILL NO. DESCRIPTION AMOUNT (N)
1.00 Preliminaries 2,452,596.30
2.00 Site Clearance 1,027,440.00
3.00 Culverts, Drains and Bridges 31,041,000.00
4.00 Earthworks and Surfacing 32,480,140.00
5.00 Miscellaneous 7,805,600.00
Sub Total 74,806,776.30
Add Contingency 5% 3,740,338.82
Total 78,547,115.12
Add 5% VAT 3,927,355.76
Grand Total 82,474,470.88