You are on page 1of 4

2 TECHNICAL

Budgets, standards and


simple variances
David Cornes is a Senior Lecturer at Bournemouth University

T
here is often understandable confu- from an assessment of the value of cost ele- control without standard costing, but standard
sion regarding the relationship be- ments...” costing without the additional management
tween budgets and budgetary control information provided by budgetary control is
The standard then goes on to define the uses of
on the one hand and standards and standard unlikely.The factor which links the topics
standards in measuring performance and in
costing on the other. Furthermore, variances irrevocably together is the fact that they are
valuing stock and providing control informa-
seem to pop up indiscriminately — sometimes both concerned with the calculation of
tion. So is there a link here with budgetary
when you least expect them! variances.
control? The Terminology definition of stand-
A good starting point to resolve the confusion ard costing helps to clarify this:
Variances
is the CIMA Terminology of Management
“A control technique which compares stand- Returning to the CIMA Terminology let us see
Accounting which defines a budget as:
ard costs and revenues with actual results to what the definition is for a variance:
“A plan expressed in money. It is prepared and obtain variances which are used to stimulate
“Difference between planned, budgeted or
approved prior to the budget period and may improved performance.”
standard cost and actual cost; and similarly for
show income, expenditure, and the capital to
So, yes there is a link, both standard costing revenue.”
be employed...”
and budgetary control are concerned with
So, a variance is the difference between what
The definition then goes on to outline how the comparing something with actual results
a cost (or revenue) ought to have been under
budget is prepared. Putting aside the question achieved in order to influence future perform-
standard circumstances, and what it actually
of whether a budget is only concerned with ance. The easiest way to consider them is to
was. If we are looking at the variance concern-
money, for example a production budget could regard the techniques as very closely related
ing a single item, then this is a variance against
be more meaningful to production personnel with substantial overlaps, however budgets
standard; and a variance for a department or
expressed in units rather than cost, the key and budgetary control are concerned with the
the company as a whole is a variance against
feature is that a budget is a future plan. comparison of the expected (budgeted) results
budget; but when we come down to the com-
with the actual results of the company as a
Budgetary control is defined thus in the Ter- putations the distinction becomes academic.
whole at a particular (budgeted) level of activ-
minology:
ity, broken down to individual managers’ level To illustrate the effect of standards and budg-
“The establishment of budgets relating the (i.e. departmental); and standards are prepared ets on the calculation of variances let us take a
responsibilities of executives to the require- at unit level i.e. individual products etc., aggre- straightforward example. We are examining
ments of a policy, and the continuous compari- gated to individual managers or departments the performance of a company which has a
son of actual with budgeted results, either to as required. Of course, the standards are used single product, the standard cost specification
secure by individual action the objectives of in the preparation of budgets; and, as will be for which is shown in Figure 1. The standard
that policy or to provide a basis for its revi- demonstrated shortly, the budgeted level of cost specification for the variable cost ele-
sion.” production is used to determine the standard ments (direct material, direct labour and vari-
fixed cost per unit. You can have budgetary able production overhead) are specified as the
This implies the use of the budgets to imple-
ment responsibility accounting, the Sales Man-
ager for example is responsible for the achieve-
ment of the sales that are budgeted to be made; Figure 1— Standard cost specification
the comparison of actual sales achieved with
the budget indicating what action must be Direct material Total Std £
taken to achieve the budget, or, if the budget 160 x kg mat @ £/kg £7.50 1,200
can no longer be achieved then the opportunity Direct labour
arises to decide the best course of action in the
25 hrs @ £/hr £6.00 150
light of circumstances that were not envisaged
when the budget was prepared. Variable production overhead
25 hrs @ £/hr £10.00 250
What about standards then? The Terminology
defines a standard as: Total standard variable cost 1,600
Fixed production overhead
“A predetermined measurable quantity set in Budgeted units/month 200 400
defined conditions.”
Total production standard cost 2,000
Standard cost is defined as: Standard gross profit 500
“A standard expressed in money. It is built up Standard selling price 2,500
TECHNICAL 5

cost behaviour patterns, is designed to change


Figure 2 — Budget as volume of output changes.”

Sales 200 @ £2,500 £500,000 Well, the volume of output has changed, from
Production 200 Units the budgeted 200 units to the actual 220.
Direct materials 200 @ £1,200 £240,000 What’s this about cost behaviour patterns?
Direct labour 200 @ £150 £30,000 The analysis of costs according to behaviour
Variable production overhead 200 @ £250 £50,000 gives us a distinction between variable and
Fixed production overhead 200 @ £400 £80,000 fixed costs. As can be seen in Figure 4 in the
flexed budget the variable items, direct mate-
Gross profit £100,000
rial, direct labour and variable production
overhead have changed from the original fixed
Figure 3 — Actuals budget (Figure 2), whereas fixed overhead
remains unaltered from the original budget
Sales were 220 units @ £2,450 per unit because fixed costs by definition should not
Sales revenue £539,000 change. That is, the budget has been flexed to
Production was 220 units the actual level of 220 units, evaluated at the
Direct materials purchased & issued 35,000 kgs £266,700 standard per-unit costs and selling price. You
Direct labour worked 6,000 hours £33,000 should notice in this example that the produc-
Variable production overhead £53,000 tion and sales units are the same so there are no
Fixed production overhead £79,300 complications due to stock increases or de-
creases, in other words the cost of production
Gross profit £107,000
and cost of sales are identical.
Selling and administration £32,000
Net profit £75,000 Comparing the flexed budget with the actual
performance results in the variances. When
standard quantity of the resource required (e.g. we consider these differences there is not only
penses like selling and administration. Unless
160 kg of material) multiplied by the standard the amount of the variance to be established
the question asks you to reconcile budgeted
cost per unit of that resource (i.e. £7.50 per kg). but also the sign of the variances. Variances
gross profit with actual net profit you can
The sum of the three variable cost elements is can be either favourable or adverse according
ignore this, if you are asked for such a recon-
the total standard variable cost. to their effect on profit. Take sales, with a
ciliation then the actual non-production cost
flexed budget of £550,000 compared with an
Fixed production overhead is of course differ- given is the final item on your reconciliation.
actual of £539,000, there is a difference of
ent. Fixed overhead in total is regarded as The second query, the fact that we are given
£11,000 less, so had the budgeted sales been
constant, it should not be altered by changes in the actual quantities of the resources used is in
achieved the profit would have been £11,000
the level of production, at least not over the fact required information when we come to
more, the variance is obviously adverse;
normal range of activity. Therefore, as fixed sub-divide the variances but can be ignored for
whereas direct materials have cost £2,700
production overhead per unit is calculated by: the moment. The principal problem is that the
more than budget, the effect on profit is again
total fixed overhead –: number of units, it will number of units produced and sold is different
adverse. Note also the convention that has
be a factor of the number of units chosen. In the from the budget. This means that we cannot
been adopted in this example to express whether
example in Figure 1 it can be seen that the directly compare the budget figures in Figure
the variances are favourable or adverse. This is
fixed overhead of £400 per unit has been based 2 with the actual results in Figure 3. If we do
stated at the head of the variances column and
on the budgeted production per month of 200 and, say, tell the Production Manager that he
tells us that the variances are in £ with favour-
units, so the budgeted amount of fixed produc- has overspent by (£266,700 – £240,000)
able variances in plain figures and adverse
tion overhead per month must have been 200 £26,700 on direct materials, his answer will be
variances within brackets. There are other
x £400 = £80,000. Also included in the stand- along the lines of “Well of course I have, I
conventions, for example the letters (F), (U) or
ard cost specification is the standard selling made twenty extra units”, but probably not
(A) standing for favourable, unfavourable or
price and therefore the standard gross profit expressed so politely! What we have to estab-
adverse; or favourable variances may be pre-
per unit that the company expects to achieve. lish first is what the results should have been
sented in one column and unfavourable ones
given that 220 units were produced and sold.
Given the budget of 200 units per month and in another. It does not matter what convention
So, for our last dip into the CIMA Terminol-
the standard cost specification per unit we can you adopt so long as you state what convention
ogy, let us see what the definition is for a
calculate the budget per month. This is shown you are using, and stick to it! If you are
flexible budget:
in Figure 2. This tells us what the revenue and presented with a question containing variances
costs per month should be. If we now look at “A budget which, by recognising different with some in brackets and some without where
the actual results for a period in Figure 3 a
number of queries arise. First, the budget was Figure 4 — Flexible budget
to sell 200 units and we actually produced and
sold 220. Secondly, we have the actual usage Flexed Actual Variances
of the direct material and labour in kilograms budget £Fav/(Adv)
and hours as well as the values and, thirdly, Sales 220 @ £2,500 £550,000 £539,000 (11,000)
there is another category of expense, selling Production 220 Units
and administration, to be deducted from gross Direct materials 220 @ £1,200 £264,000 £266,700 (2,700)
profit to finally arrive at net profit. Taking the Direct labour 220 @ £150 £33,000 £33,000 0
last of these problems first, it is not unusual in Variable production overhead 220 @ £250 £55,000 £53,000 2,000
variance analysis questions to find we are Fixed production overhead £80,000 £79,300 700
given the standard gross profit and the actual
Gross profit £118,000 £107,000 (11,000)
net profit after charging non-production ex-
4 TECHNICAL

the convention is not stated do not assume that question, what should it have cost in direct 35,000 kg means that 200 kg have been saved.
the bracketed figures are necessarily adverse, material to produce the 220 units that were This gives a favourable usage variance of 200
in at least one question under the old 2.4 produced, and what did it cost? Each unit kg, and it is a common mistake in variance
syllabus the reverse was the case. should have cost the standard direct material questions for students to stop right there and
cost of £1,200, so 220 units should have cost say the usage variance is 200 favourable. It is
What do these variances tell us? Well we can
£264,000, they did cost £266,700 so they cost not however the answer. We need to calculate
see that on the actual sales of 220 units the
£2,700 too much — the variance is adverse. the usage variance as a monetary value. 200 kg
profit should have been £118,000 and it was
Unless specifically asked for in the question it saved at the standard price of £7.50 gives a
only £107,000, a total adverse variance of
is not necessary to calculate the total variance, favourable usage variance of £1,500.
£11,000. Of this total, £11,000 adverse is the
simply to go straight to the sub-variances.
responsibility of sales and a net nil variance The adverse price variance of £4,200 com-
However until you feel competent with vari-
arose in production. This does not mean that bined with the favourable usage variance of
ance calculations I suggest that you do calcu-
the cost of production corresponded in detail £1,500 agrees with the total direct material
late the total variance first, it gives you the total
to the budget, but that there are compensating variance of £2,700 adverse that we calculated
that the sub-variances should sum to and thus
variances with £2,700 adverse due in some to begin with.
gives you a check on your calculations.
way to differences on direct materials, £2,000
You may be feeling slightly uneasy about one
being gained on variable production overhead So what are these sub-variances? We know
thing, we have evaluated the 200 kg favour-
and £700 underspend on fixed production that direct material has cost £2,700 more than
able usage variance at the standard price of
overhead. However although this analysis tells it should but we do not yet know the reasons
£7.50 when we know that we actually paid
us where the variances have arisen it gives why this is so. There are two possible causes:
£7.62. Has not the saving really been £1,524?
little help in establishing why. The purpose of either the material we used cost too much per
For the moment the answer has to be that as we
variance analysis is to give more information kilogram — a price variance; or too much
have evaluated the price variance on all the
to managers to enable them to understand and material was used — a usage variance. Or, of
material that was actually used then arithmeti-
control their operations. To find out more we course, some combination of both price and
cally the usage variance must be evaluated at
will have to analyse the variances further. usage variances. For reasons I shall return to
the standard price. This is why I suggested that
later always calculate the price variance first!
the price variance should always be calculated
Variance analysis The price variance calculates the effect of any first, there is no arithmetical reason for doing
For the moment I am going to consider only
difference from the standard price per unit on so but, having extracted the price variance on
the cost variances arising in the variable cost
all the material actually used. In the example all the material actually used, it feels more
elements; that is direct material, direct labour
in Figure 5 35,000 kg were used so we com- ‘comfortable’ to evaluate the usage variance at
and variable production overhead. There are
pare how much 35,000 kg should have cost at standard price. Variance calculations are al-
several methods of performing the variance
the standard price of £7.50 per kg, with how ways performed this way ‘by convention’.
calculations. They fall into two groups involv-
much 35,000 kg did cost. If instead we are
ing either the memorising of formulae as ad- Turning now to the other ‘variable cost ele-
given the actual price paid per kg (in this
vocated in Drury and also in the Students’ ments’ of direct labour and variable produc-
example it is £7.62) we can find the difference
Newsletter articles by Duncan Williamson tion overhead the pattern of variances is iden-
in price per kg and multiply by 35,000 kg to
and Mark Lee Inman, or the logical examina- tical to those for direct material that we have
obtain the price variance (35,000 x £0.12 =
tion of what each variance is trying to measure already examined. Only the names of the
£4,200). As the actual amount paid is more
by comparing what it should cost to what it did variances are different as shown in Figure 6.
than the standard amount the variance is obvi-
cost in the context of the factor in question. It The total variance can still be analysed into
ously adverse.
is the latter method that I will attempt to two elements, that part of the total variance
describe. Having calculated the price variance on the caused by the price of the resource being
actual quantity used, the usage variance now different from standard, called now either a
If you examine the direct material variances in
addresses the question of whether 35,000 kg rate or expenditure variance; and that part of
Figure 5 you will note that the total direct
should have been used. Remembering that we the total variance caused by the quantity of the
material variance is of course the direct mate-
are using flexible budgeting the question to resource differing from the standard allow-
rial variance that we obtained by comparing
ask is how much material should 220 units use ance, called now an efficiency variance.
the flexible budget with the actual results in
if each one is allowed 160 kgs. The answer of
Figure 4. It is obtained by asking the same Taking the total direct labour variance first, the
35,200 kg compared with the actual usage of
question is basically the same as for the total
material variance, given that production was
Figure 5 —Total direct material variance 220 units, how much should the direct labour
cost be at the standard of £150 per unit? This
Total direct material variance Variances is identical to the actual direct labour cost so
£Fav/(Adv) the total direct labour variance is nil. However
Production should cost 220 @ £1,200 £264,000 this does not mean that we do not have to
Production did cost £266,700 (£2,700) calculate the sub-variances. As can be seen
there are compensating variances for direct
Direct material price variance labour rate and direct labour efficiency. The
Material should cost 35,000 @ £7.50 £262,500 calculations for these variances are identical in
Material did cost £266,700 (£4,200) concept to those for direct material, again
Direct material usage variance calculate the rate variance first. The rate vari-
Production should use 220 @ 160 35,200 kg ance evaluates the difference between the stand-
Production did use 35,000 kg ard cost of the actual hours worked and the
Material variance in units 200 kg @ £7.50 £1,500 actual cost, the efficiency variance evaluates
the difference between the hours allowed for
Total direct material variance (£2,700) 220 units and the actual hours taken. Note
TECHNICAL 5

again that the rate variance can be calculated References ‘Management Accounting; Official Termi-
by multiplying the difference between the ‘Beyond traditional variance analysis’, Mark nology’, Chartered Institute of Management
£5.50 per hour actually paid and the standard Lee Inman, ACCA Students’ Newsletter, Au- Accountants: 1991.
of £6.00 per hour by the actual hours worked, gust 1993. ‘Standard costing made simple’, Duncan
and, like the usage variance, the efficiency
Costing: an introduction —3rd Edition, Colin Williamson, ACCA Students’ Newsletter,
variance is calculated first in units (hours in
Drury, Chapman and Hall, 1994. January 1990.
this case) and then evaluated at standard rate
per hour.
To calculate the variable production overhead Figure 6 —Total direct labour variance
variances the assumption is made that the
overhead is actually incurred in proportion to Total direct labour variance Variances
the direct labour hours worked. Thus the ex- £Fav/(Adv)
penditure variance ‘should cost’ value is cal- Production should cost 220 @ £150.00 £33,000
culated on the actual 6,000 direct labour hours Production did cost £33,000 £0
worked, and we do not need to recalculate the
Direct labour rate variance
efficiency variance in hours because this is the
Actual hrs should cost 6,000 @ £6.00 £36,000
same as the direct labour efficiency variance
Actual hrs did cost £33,000 £3,000
of 500 hours adverse but evaluated now at
£10.00 per hour. Direct labour efficiency variance
Production should take 220 @ 25 5,500 hrs
The fact that the same variance in hours ap- Production did take 6,000 hrs
plies both to the direct labour and variable
Variance in hours (500) hrs@ £6.00 (£3,000)
overhead variances emphasises the inter-rela-
tionship between variances. Suppose that the Total direct labour variance £0
direct labour variances show the effect of a Total variable overhead variance
deliberate decision by management to employ Production should cost 220 @ £250.00 £55,000
a lower grade of labour at £5.50 per hour Production did cost £53,000 £2,000
instead of the standard £6.00 per hour and as a
result the labour force took 500 extra hours to Variable overhead expenditure variance
complete the work. You might at first suppose Actual hrs should cost 6,000 @ £10.00 £60,000
that the decision had broken even as the fa- Actual hrs did cost £53,000 £7,000
vourable rate variance is exactly compensated Variable overhead efficiency variance
by the adverse efficiency variance. This is not Variance in hours (500) hrs @ £10.00 (£5,000)
the case as the extra 500 hours have also Total variable overhead variance £2,000
incurred an extra £5,000 of variable overhead
that would not otherwise have been incurred.
If asked to suggest causes for variances always
look for inter-relationships between them, for
example a cheap material purchased may give Figure 7 — Variable cost variances
a favourable price variance but cause not only Standard Actual
an adverse material usage variance but also
adverse labour efficiency and variable over- Price,or
head efficiency variances. Price £5 per kg rate or £6 per kg
The relationships between the sub-variances expenditure
for the variable cost elements of direct mate- Usage, or variance
rial, direct labour and variable overhead are efficiency
illustrated in Figure 7. Total cost is a factor of variance
both price and quantity; standard price and
quantity for total standard cost, and actual Qty 10 kg per unit 11 kg per unit
price and quantity for total actual cost. The Total Total
total variance is the difference between total std actual
actual cost and total standard cost. The price cost cost
(or rate, or expenditure) variance is the effect < Total variance >
of the difference between standard and actual Variable cost variances
price per unit on all the units actually used. The (Direct material, direct labour, variable production overhead)
usage (or efficiency) variance is the effect of
the difference between total actual usage and N.B. Budget is ‘flexed’ so unit quantity and price are multiplied by actual
total standard allowance evaluated at stand- quantity produced = 100 units
ard price. 100 units should use 100 x 10 kg = 1,000 kg each costing £5 per kg = £5,000
100 units did use 100 x 11 kg = 1,100 kg each costing £6 per kg = £6,600
A future article will discuss fixed overhead
variances, revenue (sales) variances and the Total direct material variance £(1,600)
further analysis of variances together with Price variance 1,100 kg x (£5 per kg – £6 per kg) £(1,100)
some more theoretical aspects concerning joint Usage variance 100 units x (10 kg –11 kg) = 100 kg at £5 per kg £(500)
variances and the timing of the extraction of £(1,600)
the material price variance.

You might also like