Shell Malaysia Exploration & Production

SSB / SSPC
Working at Height Rescue Plan Capabilities for Frontline Operations Procedure

6.0 APPENDICES

APPENDIX 1 - WORKING AT HEIGHT RESCUE PLAN

Site Address: PTW No:


Rescue Plan Ref No:
Work Location/Area:

JOB TASK
Job Reference No: Working at Heights Dates From: To:
What is the task to be done:

Work Crew:
Names of workers who are involved in the work at height:
1) 2)
3) 4)
5) 6)

The Rescuer is to check all individual suspension trauma straps and rescue equipment to verify that they are in good
working condition prior to proceeding with the work at height task and sign below.

7) Signature of Rescuer: Date


Note: Work plan for the day should clearly state all SERT members are notified of the WAH task and means to
communicate event is established. The SERT members can engaged other tasks but within 5 mins response as required.

RESCUE
The rescue plan should ensure that the potential for suspension trauma is minimized by affecting a rescue within 5 minutes.

Communication
What communication systems will be used between the suspended worker and supervisor / rescue team?
9 as appropriate
1) Direct Voice Communication
2) Two-way Radios/Headsets
3) Other Visual or Audible Communication:

Test Communication System Attendee (if required):


Attendee may be required to ensure timely reporting of a fall event
Emergency Contact
In the event of an emergency / fall from height the WAH supervisor should immediately alert the rescue team and first aid
assistance:

Rescue Team Name: Name:

First Aider(s) Name: Name:

Facility/Site Emergency Contact Number

Security Classification: Rev.: 1.0 Date: Custodian Ind: ECCN: Not subject to EAR Page:
Restricted 15/12/2016 UPO/L/MSD No US content 22 of 29
DIN: HSSE.PeS.PR.016 Printed copies are uncontrolled
Shell Malaysia Exploration & Production
SSB / SSPC
Working at Height Rescue Plan Capabilities for Frontline Operations Procedure

External Emergency Services Provider (If applicable):


Fire: ___________________ Police: __________________ Ambulance: _________________

Rescue Considerations:
9 as appropriate
Are Operators trained and competent to use of rescue equipment? Yes No
Are Rescuers trained and competent in the use of rescue equipment? Yes No
Are there sufficient numbers of rescuers available? Yes No
Is rescue equipment selected appropriate for nature of work? Yes No
Is rescue equipment in good condition, certified and inspected as required? Yes No
Have assessments including in date been made of anchor points for the rescue? Yes No

What equipment is needed to perform a rescue for this Job Task?


9 as appropriate
Self-rescue kits/descent devices Scaffold
Remote rescue kit / Gotcha Kit Crane personnel basket
Suspension trauma straps Climbing/abseiling rescue kit
Rescue ropes Crane personnel basket
MEWP Immobilization device (stretcher, sled, etc)
First aid-kit or trauma kit AED (automatic external defibrillator)
Rescue ladder Resuscitator
Life Ring Other:
Fast Rescue Boat / Fast Rescue Craft

What obstructions are in the way of reaching the suspended person? What additional controls or mitigations are to be
employed? (Detail): _________________________________________________________________________________________
___________________________________________________________________________________________________________
___________________________________________________________________________________________________________

How will rescuers get to person? (Detail):


___________________________________________________________________________________________________________
___________________________________________________________________________________________________________

How will rescuers perform the rescue using the above listed equipment? (Detail): _________________________________
___________________________________________________________________________________________________________
___________________________________________________________________________________________________________

What method will be used for attaching and if necessary immobilizing injured person? (Detail): ___________________
_______________________________________________________________________________________________________

Security Classification: Rev.: 1.0 Date: Custodian Ind: ECCN: Not subject to EAR Page:
Restricted 15/12/2016 UPO/L/MSD No US content 23 of 29
DIN: HSSE.PeS.PR.016 Printed copies are uncontrolled