Professional Documents
Culture Documents
Protection Schemes
Unit Scheme
Non-Unit Scheme
Distribution Protection
Non-Unit Scheme
Current
Time
Time & Current
1
Distribution Protection
e.g.
1
Distribution Protection
Unit Scheme
Costly
2
Distribution Protection
87
Distribution Protection
64
High Impedance
Relay
3
Distribution Protection
Overcurrent Protection
Distribution Protection
Overcurrent Protection
CO-ORDINATION PROCEDURE
ii. the impedances in ohms, per cent or per unit, of all power
transformers, rotating machine and feeder circuits
iii. the maximum and minimum values of short circuit currents that
are expected to flow through each protection device
4
Distribution Protection
Overcurrent Protection
CO-ORDINATION PROCEDURE (CONT.)
Distribution Protection
Overcurrent Protection
5
Distribution Protection
Discrimination by time
Distribution Protection
Discrimination By Currents
11 kV F
1
H F2 G F
250MVA J
11 103
For a fault at F1, I
ZL = 0.24 ohms
3 Z S Z L
6
Distribution Protection
Discrimination By Currents
Relay setting of 8800 amp at J would protect the whole of the cable
section between J and H.
However, the disadvantage :
1. It is not practical to distinguish between a fault at F1 and a fault at
F2, which is a short distance.
2. Variations in the source fault level would not protect the
section concerned.
Distribution Protection
Discrimination By
Both Time And Current
Xi Xi Xi Xi
150 A
0.36 PU 7.5 PU 1.98 PU 0.53
0.29 PU 17.5
132 kV 11 kV 3.3 kV
7
Discrimination By Both Time And Current
(cont.)
F1 F2
Time(second)
A
B A
B
1.0
0.6
0.5
Current (amp)
Distribution Protection
Relay Characteristics
Figure 2.5
8
Distribution Protection
Distribution Protection
K
t=
(I - 1)
9
Distribution Protection
Distribution Protection
10
IDMT Relay
Shaded
Pole
Unshaded
T 2 Pole
1
Moving
contact
Fixed
Coil contact
Disc
1 2
IC
E1
I1
Distribution Protection
They need only one electrical quantity for operation - the alternating
primary current.
11
Figure : Shaded pole type induction disc relay
Unshaded Pole
2 1
T
Moving contact
Fixed contact
Coil Disc
12
IDMT Relay
induction disc type
Unshaded Pole
2 1
T
Moving contact
Fixed contact
Coil Disc
13
There is phase shift between 1 and 2 T
1
1 induces voltage E1 2
2 induces voltan]ge E2
E1 and E2 lag flux by 90 E1
I1
I2
E1 and E2 E2
Eddy currents I1 & I2
Torque 1
2
T 1 2 Sin
So that
14
Distribution Protection
T 12 sin
but
I
Hence:
T = K I2
The current I1 from the line CTs, sets up a magnetic flux A and also
induces a current I2 in the secondary winding which in turn sets up a
flux in B. Fluxes A and B are out of phase thus producing a torque in
the disk causing it to rotate. Now, speed is proportional to braking
torque, and is proportional to driving torque. Therefore, speed is
proportional to I.
But,
Hence
15
Distribution Protection
Time-Current Characteristics
The larger current will produce the larger torque and, therefore, the
faster operating time to trip.
The plug setting multiplier (PSM), becomes the horizontal axis of this
relay characteristic while the vertical axis, is the operating time in
seconds.
The higher the fault current, the shorter the operating time. The
operating time then tends to be constant for high fault currents (the
definite minimum time).
IDMT Characteristic
16
Distribution Protection
Relay Adjustments
Distribution Protection
Current Plug Setting (PS)
Taps on the coil of the relay are used to adjust the current
setting which are called the current plug setting.
17
Distribution Protection
Current Plug Setting (PS)
Distribution Protection
Current Plug Setting (PS)
Usually the following ranges of nominal current are used,
giving a 1:4 ratio in seven steps:
18
Distribution Protection
Current Plug Setting (PS)
Distribution Protection
19
Choice of CT Transformer Ratio
1. I nom
20
Choice of CT Transformer Ratio
21
Choice of CT Transformer Ratio
22
Relay
Background
Electromechanical relays of various types have been
available from the earliest days of electrical power supply.
Some of these early designs have been improved over the
years. One of the most successful types of
electromechanical protection relays has been the
previously discussed inverse definite minimum time
(IDMT) overcurrent relay based on the induction disk.
Relay
What is a static protection relay?
Most modern overcurrent relays are of the digital type. There are many
reasons for this,
the main ones being associated with cost, accuracy, flexibility,
reliability, size, auxiliary power drain, etc. Many of these reasons will
become evident during the course of this chapter, which will
concentrate on relays of the digital type. Microprocessor relays are of
the digital type.
The main objective of using static relays is to improve the sensitivity,
speed and reliability of a protection system by removing the delicate
mechanical parts that can be subject to wear due to vibration, dust and
23
Relay
What is a microprocessor relay?
Where
T = operating time in seconds
K = time multiplier
I = current value
I> = set current value.
Relay
The unit includes four BS 142 specified characteristics with different
degrees of inverse. The degree of inverse is determined by the values
of the constants and .
24
Relay
Introduction to the numerical relay
Distribution Protection
25
Distribution Protection
Overshoot
When the driving torque is removed, the relay disc
continues to rotate.
The time of rotation after the relay is de-energised is
called the overshoot time.
Distribution Protection
Errors
All measuring devices, including the relay, are
subject to manufacturer's error.
A tolerance must be allowed.
Final Margin
Some extra allowance is required to ensure that a
satisfactory operation of the relay is obtained. This
is also called safety margin.
26
Distribution Protection
Recommended Discrimination
Time
Distribution Protection
Recommended Discrimination
Time
27
Industrial Power System Protection
J
K
A A
B B
C C
Ph/F 51
E/F 51 64 E/F
64 51
(a)
(b)
Ph/F
51 51 64 E/F
The simple connection is shown in
Figure(a).
(c)
Only on two phases are provided
overcurrent relays. (Figure c)
28
Distribution Protection
Operate for close up faults very quickly but should not operate even
for maximum fault currents at the remote end of the feeder.
Protecting long transmission lines or transformer feeders.
Distribution Protection
Determination Of
IDMT relay Settings
Two methods:
Graphical (template) method
Mathematical analysis.
29
Distribution Protection
RSI = CT x PS/100 A
(CT ratio x Relay rating x PS/100 )
PSM = FC/RSI
RCOT = f (PSM) S
ROT = RCOT x TSM S
RjOT = RnOT + DT S
Distribution Protection
A B C D
30
Distribution Protection
Max Max.
CT Plug Load
Relay
Fault
(A) Ratio Setting Current TSM
(%) (A)
Distribution Protection
At substation D:
CT ratio = 100/5A
Chosen relay plug setting, PS = 100% a primary current
RSI = CT x PS/100
= 100 x 100/100
= 100 A
The maximum fault at substation D = 1395 A (Table 2.1). Therefore :
PSM = FC/RSI
= 1395/100
= 13.95
31
Distribution Protection
Using this value of PSM (13.95), RCOT can be found (from characteristic
TSM = 1.0) as:
RCOT = 2.6 seconds
TSM = 1.0
The ROT is:
ROT = RCOT x TSM
= 2.6 x 0.05
= 0.13 second RCOT = 2.6
For substation C:
A grading margin of 0.5 is adopted in this example PSM=13.95
Distribution Protection
CT ratio = 200/5
Chosen relay plug setting, PS = 100% = 200A
RSI = 200 x 100/100
= 200A
The maximum fault current for grading relay C with relay D = 1395 A.
Therefore :
PSM = 1395/200
= 6.975
Using this value of PSM (6.975), the RCOT can be found as:
RCOT = 3.6 seconds
32
Distribution Protection
Therefore :
ROT
TSM
RCOT
= 0.63/3.6
= 0.175
Distribution Protection
The maximum fault current for a fault just outside the substation C
busbar is 2690A. Therefore:
2690
PSM
200
13.45
33
Distribution Protection
The results of these relay setting calculations are shown in Table 2.2.
PS=125%
PS=150%
Distribution Protection
34
Distribution Protection
Distribution Protection
Graphical Method
Moving the template vertically alters the time multiplier setting (TSM)
and horizontally the current setting (PS).
35
Distribution Protection
Computer Method
Exercise 1
36
Solution
RSI = CT x PS/100
= 500 x 150/100
= 750
PSM = 6000/750 = 8
RCOT = 3.35 seconds (from graph)
Exercise 2
It is given that fault current level at 33 kV
side is 2,700 A, CT ratio at 33 kV side is
200 : 1 and 132 kV side is 100 : 1. If both
relays R1 and R2 are set for 100% plug
setting, determine the operation time for
both relays when time grading margin of
0.6 second is given and TSM for relay R1 is
0.15. Calculate also TSM for R2.
37
33kV
132kV
100/1 132/33kV 200/1
IF = 2700A
R2 R1
Solution :
At R2
At R1
On 132 kV side
RSI = 200X100/100 = 200
IF = 2700 x 33/132 = 675 A
PSM = 2700/200 = 13.5
RSI = 100 x 100 /100 = 100
From graph : RCOT = 2.6 S PSM = 675/100 = 6.75
RCOT = 3.7 S
ROT = 2.6 x 0.15 = 0.39 s
TSM = (0.39 + 0.6)/3.7
= 0.26
Distribution Protection
Fuses
Simple
Can be very fast
Limit fault energy
Require Coordination
38
FUSE
FUSES
BS Standard
DIN Standard :
Deutches Institut fur
Normung
(German Standard)
39
DIN FUSES
Fuse Element
40
Industrial Power System Protection
Element of Fuse
Normal operation
Fuse is operating below its continuous current
rating
Electrical resistance of the link is low
Simply acts as a conductor
Overload current
Temperature of the link reaches a level that
causes
a restricted segment of the link to melt.
A gap is then formed.
An electric arc is established. (Figure 2.26(b))
Cut off
As the arc causes the link metal to burn back,
the gap width increases.
Arc cannot be sustained and it is extinguished
(Figure 2.26(c))
Figure 2.26
41
Fuse Classification
1. High-voltage fuses
For protection of devices 1000V AC and above
2. Low-voltage fuses
For protection of devices up to 1000V AC and 1500V DC
400A 250A
160A fuse
200A 160A 100A fuse 125A fuse not melted
operated arcing
Largest Largest
fuse fuse
100A 125A 160A
100A 100A
42
Distribution Protection
Peak asymmetrical
current
Prospective
current
Cut-off current
Zero current
Distribution Protection
I2t Rating
10000
Total I2t - Minor Fuse
Pre-arcing I t - Major Fuse
2 80A 100A 125A 160A
1000
To obtain positive discrimination between
fuses, the total value of the smaller fuse
must not exceed that of the pre-arcing value
of the larger.
43
Distribution Protection
Time / Characteristic
A family of time/characteristic
curves for a standard fuse is
shown in Figure.
Figure
44
Distribution Protection
45
Distribution Protection
415V
20 kW 30 kW 30 kW
LIGHTING HEATING MOTOR
Figure 2.30
Distribution Protection
10000
100
A 100A fuse, which would withstand
383A for longer than 10 seconds, would
10 be necessary.
6s
Time
(s)
1
80A
100A
125A
160A
0.1
0.01
100 1000 10000
Current (A)
Figure
46
Industrial Power System Protection
Fuse Application
It can be seen that fuses
H, J and K will Rating
1000A
G
47
Fuse Application
The solution illustrated G
Rating
in the abovr Figure is to 1000A
appropriate to the
remaining sub-circuit
Distribution Protection
Summary
48
Distribution Protection
Coordination
Between Relay And Fuse
Distribution Protection
Coordination
Between Relay And Fuse
49
COMPUTER METHOD
The use of digital computers has been revolutionized the
process of designing and analyzing electrical power systems
50
The manual method of calculation can be carried out
systematically as follows:-
(i) Study the single-line diagram of the system and
identify the system components required for modeling
according to the types of faults to be investigated, determine
an adequate representation of the power source especially if
the supply is taken from the supply company.
Distribution Protection
51
Distribution Protection
Local
Remote
Rr Substation
The substation from which the grading is
started and then carried out towards the
Adjacent relays at neighboring substations.
Substation
Ra
Adjacent
Local
Substation
Any substation which is directly connected to
Rj the local substation is defined as an adjacent
substation.
Remote
Any substation which is directly connected to
an adjacent substation is called a remote
substation.
Distribution Protection
52
Distribution Protection
Examples of
The Most Onerous Condition
Case A : To grade relay A with respect to relay D [Fig.
4.2] A B C
The Most Onerous Condition :
Three-phase fault at F one feeder in circuit
(To clear fault in the minimum time & to give a D
suitable discrimination time) F
Case B : To grade R1 with R2 [ Fig. 4.3 (i)] Load
Fig. 4.2
1 Adjacent 1
R1 R1
The Most Onerous
Condition :
Max fault flows through R1 2 Local
2
whilst, at the same time, the R2 R2
Local
minimum current flows through
R 2.
Fault at F. 3 3
R3 R3
Remove parallel feeder between 1
and 2 except R1, as Fig. 4.3 (ii). F
Examples of
The Most Onerous Condition (cont.)
Case C: To grade R1 with respect to R2 (refer Figure 4.4)
The Most Onerous Condition: Fault occurred at point F.
Maximum fault current flows through R1.
Exact circuit condition:Remove incoming lines to
busbar 2, including the line parallel to relay R1, except
the line containing R1, as shown in Figure 4.4(ii).
1 1
R1 R1
2 2
R2 R2
F F
3 3
53
Distribution Protection
IA Ia IF
A a IF
IF
IP 3
VA Van
Vab 3
2I F
B B IF IF
n b 3
3
IF
C
c 3
Figure 4.5: Transformer in Power System Figure 4.6: Line-line Fault on side of
transformer
Distribution Protection
54
Example of power system numbering
ASH6 7 SAL6 8
L1 L2 PS (4,2)
CT (4,2)
CB (4,2)
BAG3 6 11 4
BEN3 NOR3
BAG6 9 BEN6 12 10
NOR6
L3 L4 L5
Distribution Protection
55
The structural matrix MA for the network is :
2 1 1
2 1 1
1 4 1 20
1 4 20 1
1 1 5 1 20
1 1 5 20 1
20 2
20 2
20 2
20 2
1 1 3 10
10 1
Distribution Protection
56
Distribution Protection
Conflicting
settings.
Iteration.
The Largest Number of Substation
This critical path is defined as the route, or ring, from one source
(BSP) to any other source having the largest number of substations.
Distribution Protection
Example of
The Critical Path Approaches
1 2
3 5
7 8
6 11 4
9 12 10
57
Distribution Protection
Setting Procedure
Radial Circuits
In those parts of a network classified as radial circuits, each
group of branches is fed from only one end and therefore they
have only one busbar source. The other end is the load point
from where settings are started. Setting then progresses along
the radial circuit until the BSP or a bus on the critical path is
encountered.
Rings and Interconnected Ring Circuits
Each substation in a ring system has two infeeds. Such systems
are necessary to maintain continuity of supply to other
substations, in the event of a fault occurring on one line or
busbar. Even though the capital cost of providing such systems
is higher, the need to provide a continuous supply, such as to
hospitals, is more important.
Critical paths will be formed
Iterative procedure will be done, with the starting point is the lowest
setting.
Distribution Protection
PS Calculation
The minimum plug setting available on IDMT relay devices is 50% whilst the
maximum plug setting is 200%, in steps of 25%.
For each relay, starting with the minimum plug setting (50%), the relay
current setting in amperes is calculated.
The plant current rating for the feeder protected by the relay is then
compared with this relay setting.
If the plant rating is higher, the next increment of 25% is added to the relay
setting and the setting current recalculated.
This is repeated until the plant rating is less than the relay setting.
The plug setting is then calculated from:
PS = RSI x 100/CT
58
Time Setting (TSM)
The time settings for these relays are then calculated using the five
basic equations listed earlier. These five basic equations are:
Results
SALE
1
ASH3 2 SAL3 4
ASH6 6 SAL6 7
59
1 100 11 5 13 1 0 4
2 4
3 SALE 33
4 ASH3 33
5 NOR3 33
6 SAL3 33
7 BAG3 33
8 ASH6 6.6
9 SAL6 6.6
10 BAG6 6.6
11 NOR6 6.6
12 BEN3 33
13 BEN6 6.6
14 1 2 1 1
15 1 3 1 1
16 1 4 1 1
17 1 5 1 1
18 2 4 1 1
19 2 6 20 2
20 3 9 20 2
21 3 10 1 1
22 4 5 1 1
23 4 7 20 2
24 5 8 20 2
25 5 10 1 1
26 10 11 10 1
60
27 1 2 (0.0128, 0.0143) 800 800 600 600
28 1 3 (0.0472, 0.0517) 400 400 325 325
29 1 4 (0.0155, 0.0187) 800 800 600 600
30 1 5 (0.0504, 0.0560) 400 400 320 320
31 2 4 (0.0198, 0.0217) 800 800 600 600
32 3 10 (0.0270, 0.0296) 600 600 325 325
33 4 5 (0.0178, 0.0202) 600 600 600 600
34 5 10 (0.0193, 0.0322) 600 600 304 304
35 10 11 (0.0000, 0.5000) 600 80 262 1310
36 2 (2.0,6.0)
37 (0.0000, 0.9800) (0.0000, 0.9800)
38 400 604 400 604
39 80 3020 80 3020
40 2 (4.0,7.0)
41 (0.0000, 1.0000) (0.0000, 1.0000)
42 600 604 600 604
43 80 3020 80 3020
44 2 (5.0,8.0)
45 (0.0000, 1.0000) (0.0000, 1.0000)
46 400 367 400 367
47 80 1835 80 1835
48 2 (5.0,8.0)
49 (0.0000, 1.0000) (0.0000, 1.0000)
50 600 604 600 604
51 80 3020 80 3020
52 1 6 125 .40 80
53 2 7 125 .40 80
54 3 8 125 .40 80
55 4 9 125 .40 80
56 5 11 125 .40 80
61 0.5
62 ####S
61
CODE SUBSTATION kV
1 SALE 33.0
2 ASH3 33.0
3 NOR3 33.0
4 SAL3 33.0
5 BAG3 33.0
6 ASH6 6.6
7 SAL6 6.6
8 BAG6 6.6
9 NOR6 6.6
10 BEN3 33.0
11 BEN6 6.6
RADIAL(1) : 6 2
RADIAL(2) : 8 4
RADIAL(3) : 9 5
RADIAL(4) : 7 3
RADIAL(5) : 11 10
CRITICAL PATH(4) : 1 4 2 1
RESIDUAL RADIAL(5) : 4 5
CRITICAL PATH(10) : 1 3 10 5 1
62
PREDICTED SETTING OF RELAYS ARE:
Input
Critical Paths
Output
63
Distribution Protection
Distribution Protection
simple radial
64
Distribution Protection
TSM (a,b)
etc
Distribution Protection
65
Distribution Protection
Distribution Protection
Step 1
A fault calculation for a three-phase fault on the feeder side of the selected
circuit breaker, but adjacent to it, is carried out.
Step 2
The operating time of each IDMT relay is calculated by using the
following equation:
RSI = CT x PS / 100 amp
PSM = FC/RSI
RCOT = f(PSM) seconds
ROT = RCOT x TSM seconds
66
Distribution Protection
Step 3
In this stage, ordering of the substation is considered
A typical examples of this step for a fault at substation G for the power
shown in Fig 3.5a, is shown in Fig 3.5b. Only the relays looking in the
direction of the fault flow are ordered.
Step 4
Referring to step 3, a list of ordered substations with the operating times
of their IDMT relays is written. The list shows which relay will operate
first.
Distribution Protection
Step 5
67
Distribution Protection
Step 6
The procedure for this new situation is repeated starting from step 1 and
terminating at step 6 until all fault currents through the feeders are zero.
Step 7
Distribution Protection
A C D
(1) (3) (4)
F
L2
G
(7)
F
L1
L3 H
(8)
L4
68
Distribution Protection
3.92 s A
3.80 s B
3.65 s E
3.75 s
1.90 s F 3.62 s
D
0.81 s
G C A
1.40 s
F 3.40 s
Distribution Protection
C G 1.40
A C 3.40
D C e.g. 1.90
E D 3.65
B E 3.80
A B 3.92
F D 3.62
E F 3.75
E F 3.75
GT A 4.10
69
GT1B GT1A GT2A GT2B
30 MVA 45 MVA 45 MVA 30 MVA
SALE
B.S.P
(1)
ASH3
793MVA SAL3
(2) 793MVA
(4)
ASH6
162MVA SAL6
(10) 160MVA
(7)
Figure 4.5: Relay Operatingtimes for a bulk supply point feeder fault. e.g.SAL3
(SALE-SAL3 is seen to trip first)
70
RELAY DISCRIMINATION DISPLAY
71
RELAY DISCRIMINATION DISPLAY
FAULTED SUBSTATION SALE
FAULTED FEEDER SAL3
SUB CT PS TSM OPER. FAULT
FEEDER
STN. RATIO TIME MVA
SALE SAL3 800. 75.00 .00000 .00000 .00 1 4
SAL3 SALE 800. 50.00 .00000 .00000 .00 4 1
11kV
R1 R2 Z 1= R3 Z 1= R4
0.25 j 1.0 0.2 j 2.5 no other
protection
Figure Q1
72
Thank You
Thank You
73