Professional Documents
Culture Documents
81 IR
SWD
STEERING COMMITTEE
WIND ENERGY
DEVELOPING COUNTRIES
December 1981
IDH\f TWO
DHV Consulting Engineers Technical Working Group
for Developing Countries
2Q-\ Ifc-ty
2
CONTENTS PAGE
1. PREFACE 4
2.1. Introduction 5
2.2. Construction manual 5
2.2.1. Site clearance and preparation of foundations 5
2.2.2. Construction materials 6
2.2.2.1. Bricks 6
2.2.2.2. Cement 6
2.2.2.3. Sand 6
2.2.2.4. Water 6
2.2.2.5. Mortar mix 6
2.2.3. Construction 7
2.2.3.1. Instructions for bricklaying 7
2.2.4. Plaster 8
2.2.5. Tools 8
2.2.6 Plastic foil or lining 8
2.2.7. Bund earth wall 8
2.3. Work instructions, drawings 9
2.3.1. Watertank Type 1 10
2.3.2. Watertank type II 17
2.3.3. Watertank type III 25
2.3.4. Watertank type IV 33
2.3.5. Watertank type V 41
2.3.6. Typical details 49
2.4. Testing 54
2.4.1. Introduction 54
2.4.2. Testing construction materials 54
2.4.2.1. Choise of bricks 54
2.4.2.2. Simple field identification tests 55
2.4.3. Testing masonry construction 57
2.4.3.1. Testing of a brick wall 57
2.5. General starting points for the structural
calculations 61
2.5.1. Calculation of the tanks 63
2.5.1.1. Tank capacity of 30 m3 63
2.5.1.2. Tank capacity of 60 m3 64
2.5.1.3. Tank capacity of 90 m3 65
2.5.1.4. Tank capacity of 150 m3 67
2.5.1.5. Type III, IV, V 69
;
3
Annex 5 bibliography 76
/--
4
1. PREFACE
Designs for tanks made of bund walls, ferro cement, plastic foil tubes
with stabilized soil and a combination of ferro cement and masonry will
be prepared in a later stage.
The authors are grateful for the support, and critisism, that they
received from the SWD.
The authors:
J. Costa
J. de Lange
C. Pieck
2. IRRIGATION WATER STORAGE TANKS MADE OF BRICKWORK
2.1. Introduction
Descriptions and drawings have been made showing masonry tanks with a
capacity of 30-60-90 and 150 m3 with five several types. As shown,
several constructions are possible.
The site chosen for the tank should be cleared. At least the topsoil
with a layer of approx. 200 mm is to be excavated to be sure that all
vegetation, loose surface soil and black soil are removed.
If necessary the surface should be (roughly) levelled.
After clearance it is advisable to backfill a sand and/or gravel layer
of approx. 200 mm thick.
The ensuing compaction is done by means of ramming with (self-made)
tampers.
When for backfill sand is used compaction can also be done by sprinkling
with a little water and ramming.
2.2.2. Construction materials
2.2.2.1. Bricks
2.2.2.2. Cement
2.2.2.3. Sand
The first requirement for sand is that it should be free from organic
and chemical impurities which may weaken the mortar.
A coarse silica sand is probably the best for the purpose. The use of
coarse sand will lessen the workability of the mortar but its resistance
to shrinkage will be greater than that of a mortar made with fine sand.
2.2.2.4. Water
The water must be clean and free from acid chemicals, salt and organic
matters.
Salt water should never be used.
Mortars for brickwork are a mixture of cement, sand and water, each
ingredient having the correct proportion. For a maximum brickwork
resistance to water pressure the following cement mortar mixes are
advisable:
The portland cement should be fresh, old and/or wet bags with portland
cement are to be removed.
Water should be clean and free from harmfull matter, (see chapter "Testing")
Where tests can be carried out they should be in accordance with the
codes locally applicable. The aggregate (sand) should be free from
vegetable soil and black soil.
2.2.3. Constructions
When the site for the tank is cleared, its surface is levelled with a
200 mm thick layer of sand and/or gravel. The setting out can be done by
driving a post into the ground at the centre point of the tank site and
scribing a circle, while marking the ground at approx. 1 meter core to
core with pegs.
2.2.4. Plaster
2.2.5. Tools
The tools required are picks and shovels for levelling, spades, hammers
(and nails), bricklayer's tools and accessories like trowel, pegs, cord
wooden posts, mortar tub, plumb line, measuring tape, wheelbarrow and
buckets.
I
I
/
s
2.3. - Work instructions
Drawings
\
10 K
MASONRY CONSTRUCTION
SWD
TYPE I
dt aioi
4 1 I 1 GENERAL LAY OUT
cal* in mitrt TWO DHV
I
12
i
TYPE I
i
/
i
work sequence and description notes and recommandations
t
water and ramming
- If necessary the surface is to be
levelled
- Mark the circumference of the
tankslab with pegs (pegs core
to core 1 metre)
- Mix the cement and sand to a dry
i
mortar
- Add water to the dry mortar until
the mortar can be handled well
- Start bricklaying the tankslab - As indicated in the details
t
- On the bottom of the tankslab
the circumference of the tankwall
can be marked
(see page 52) the toplayer
of the bottom should be
started only after finishing
i
- Continue with bricklaying of the.
tankwall.
- On top of the tankwall a bricklayer
the first layer.
- The bonds are indicated in
the details as well (see
i
of edge coping is to be applied (see page 51.)
page 51 .)
- Refill the outer circumference with
soil
- When the bricks are of a good
quality and the sizes are
approx equal, joints of + 12
i
- The refill is to be compacted
- Scrape out the joints of the inside
of the wall and of the slab (approx
to 15 mm are preferred
- Take special care of the joint
between the tankslab and
i
t
20 mm) and apply a rendering (plaster) the tankwall.
to the inner surfaces of the tank - The joint should be cleaned
and moistened before brick-
laying of the tankwall starts.
- When heavy loads are ex-
pected on the foundation
part of the bottom outside
the wall a bond earth wall
is advisable (see also type II)
- Immediately after bricklaying
(after each day) the finished
i
parts of the tank are to be
protected against weather
influences.
I
Therefore these parts should
be moistened or covered during
at least the first three weeks.
I
13
10 M SO
f I i I t I
0 M 40
teal* in c a n t i m a t a r t
TYPE X capacity 30 m3
PRICE LEVEL
cement bag 19
(40 Itr)
sand m3 2
roarsn
excavation m3 16.5
materials
labour mandays
total cost
MASONRY CONSTRUCTION
SWD
TYPE X
data 810707
DETAIL AND DIMENSIONS
BILLOF QUANTITIES TWO QHV
14
p f tar
1
ground laval \
.Ullll.lllllll.lllf
falJH.Jtith toil
.1 1 1 .1. LL [
-'\. J s
I lay*
0 7820
W 30 30
4 I iIr*-
0 20 40
acala in cantimatara
TYPE I capacity 60 m 1
PRICI LIVIL
materials
labour mandaya
total cost
THIS OESIQN WAS RIAUSEO UMOtN AUSPICE! OF TNI STEERING COMMITTEE WINOENEROT
DEVELOPING COUNTRIES 1 * 0 0 SOI SS ANtRSPOORT THI NETHERLANDS
TYPE I IM COOPERATION * ITH - T WO AtttRSf OORT.
MASONRY CONSTRUCTION
SWD
TYPE I
! 810707
DETAIL AND DIMENSIONS
B I L L O F QUANTITIES OHV
TWO
15
1=
a.
ground lvt
a
f fMUaith toil i i i
_x~
i 4
220) fl so
I Imymi- T
0^ I
W 30 SO
*t 1 rI r-
0 *0 40
teal* in cntfmtft
TYPE X capacity 90 m3
PniCt LCVtL
cement bag 36
(40ltr)
3
sand m 3
coarse
excavation m3 41
materials
labour mtndiyt
total cost
THIS OCSIQM WAS RCAllSCD UNOCR AUtPICeS Of TMC STeiRIMQ COMMITTCI WIHDCMflQI
OIVELOflNO COUNTKIIS 1W0 PO 1 0 * IS AWERtfOOMT THI NETHERLANDS
TYPE I IN COOMRATION WITH TWO Ae*FOOIT.
MASONRY CONSTRUCTION
SWD
TYPE I
data 810707
DETAIL AND DIMENSIONS
8 I L L O F QUANTITIES TWO OMV
16
-*4-
4-
9tomm f N
JC T%f, T nRTTC
WHWl
A
1X0
0 K> 40
ae4* in e * * i t l m * t r i
cement b9 e4
(40 I * >
and S
coarse
excavation TO
sand layer 32
materials
labour
total cost
TYPE I
TMIt M l Mill M M A L I M O UHOI* AUlPtCEt 0 * TM< S T I I I U M CO*J<TTIf ttlNBCNiaOt
o t v i i o p i n c c o u w r m i i two PO a o t n A M P J P O O T TM N t T M i a L A N D S
Ut C O O M B J A J I O * WITH TWO A i n t 0 0 T .
I
Capacity 150 m3 IRRIGATION WATER STORAGE TANKS
TYPICAL DESIGN
MASONRY CONSTRUCTION
SWD .
TYPEI
diU 810707
DETAIL AND DIMENSIONS
OHV
BILL OF QUANTITIES TWO
17
Page
General lay-out 18
Work-instructions 19-20
Capacity 30 m3 21
Capacity 60 m3 22
Capacity 90 m3 23
Capacity 150 ra3 24
plans
if.
hMM&M
m !!> 41 t(W/t<
I - t.4. - 4 U-
sections
TYPE H
capacity 30 m' capacity 60 m 1 capacity 0 0 m' capacity 150 m 1
MASONRY CONSTRUCTION
SWD
maaaura* in mm
TYPEH
0 1 2 3 4 5 dau aioaia
GENERAL LAY OUT
seal* In mlrt
TWO | sn_._.
19
TYPE II
t , * i i i
0 K> 40
acala in cnttmlr
TYPE nr capacity 30 m3
PRICI n v i t
excavation m3 16.5
bund m3 20
materials
labour mandaya
total cost
THIS DCtlOll WAS Rf ALIStO UN01R AUSPICIt OF TMC 1TIIRIHQ COMM1TTII WINOftMIRQf
OfVILQEUia COUNTRIES IWO >0 SOI Bft AMtRtFOORT THI H I THIRL A M M
TYPE II LM COO* RAT ION W ITM TWO AMCRWOORT.
MASONRY CONSTRUCTION
SWD
TYPE H
dt B10707
DETAIL AND DIMENSIONS
B I L L O F QUANTITIES TWO OMV
O *)
| 1QHQ
LI S O J.".i.
I I
*"-
I I I I I I
0 tO 40
s e a l * in canlimatara
TYPE TT capacity 60 m 1
'"ICI LtVIl
cement bag 27
sand
I:O.II-S>-
excavation 29
bund 25.5
materials
labour mandaya
total cost
MASONRY CONSTRUCTION
SWD
TYPE I t
data 810707
DETAIL AND DIMENSIONS
B I L L O F QUANTITIES TWO OMV
O.. C < > ! ' >
23
plaaf r
--^v
., t<"rL arasao
tt as ao
I I I I I I
0 tO 40
calo in contlmotor*
TYPE Ot capacity 9 0 m3
flUCl LtVIL
cement bag 36
(40 I t r l
sand m 3
co;lr^.',
excavation m3 41
bund m3 35
materials
labour mindiyi
total cost
MASONRY CONSTRUCTION
SWD
TYPE H milium m mni
data 810707
DETAIL AND DIMENSIONS
B I L L O F QUANTITIES DMV
TWO
24
1 1 1 \ tend layer
J~330*L, 0 12360
10 30 90
0 20 40
seal* in c e n t i m e t e r s
! I
ITEM UNIT UNIT PRICE QUANTITY j PRICE
bricks piece 32700 ! ;
2 2 0 K 1 1 0 * 5 5 mm
cement bag 64
140 II r |
sand m3 5
rn.irj-
excavation m3 70
sand layer m3 32
materials ' \
I
| labour mandays -
total cost
i i
MASONRY CONSTRUCTION
SWD
TYPE3E measures m mm
date 810710
DETAIL AND DIMENSIONS
BILLOF QUANTITIES TWO 13 N V
1
I 25
t***fi
:fc_
ii
4
sections
TYPE UL
capacity 30 m' capacity 60 m1 capacity 9 0 m1 capacity ISO m>
MASONRY CONSTRUCTION
SWD
TYPE H I mturoi m RIM
0 1 2 3 4 5 di aioaia
H 1 ..}. i- - t - t - GENERAL LAY OUT
TWO 1 rr:
27
TYPE III
j{
Type III and type IV are variants.
Minor differences in respect of the quantities of materials
incorporated in the types III and IV are indicated in the schedule
of quantities.
29
ground le
x aand l a y t r
0
- i . . * - "
330 ^ ^ 5540
10 30 30
0 20 40
teal* in c e n t i m e t e r s
TYPE HL capacity 3 0 m3
PRICE LEVEL
I
ITEM UNIT I UNIT PRICE QUANTITY PRICE
bricks piece j 5400
220, 110iSS mm
cement bag 11
(40llr |
3
sand m
' i
3
excavation m 15
I
sand layer nv> 6.7 I
3 I
refill with soil m 1.7
bund m3 20
j
plaster ttmmi bag 1 i
I
sand m3 0.3
plastic foil m2 22 I
total cost
i MASONRY CONSTRUCTION
SWD
TYPE OH measure s in mm
dale 810707
DETAIL AND DIMENSIONS
I BILLOF QUANTITIES TWO
13 H V
30
__ I._
-I-
S
inb
440 I 0 7820
10 30 SO
0 20 40
cl in c*Mtmtrs
TYPE HE capacity 60 m3
PICE LEVEL
sand 1.8
excavation 28
sand layer 11
bund 24
impermeable soil 11
laterials
labour
total cost
MASONRY CONSTRUCTION
SWD
TYPE M.
flat* 810707
DETAIL AND DIMENSIONS
BILLOF QUANTITIES TWO OHV
31
T_
I-
O
to >o so n-~0-^-
0 30 40
scala m c a n t i m a t a r t
TYPE M capacity 9 0 m3
PRICE LEVEL
i
ITEM ! UNIT UNIT PRICE QUANTITY PRICE |
i
bricks " 1 piece 13000
2 2 0 . 11055 mm 1
i
cement bag 26
(40 It')
sand m3 2
ri\:\i -,t-
excavation m3 39
3
sand layer m 18
h
refill with soil " ~m 3 2.2
1
bund m3 36
i
impermeable soil m3 19
materials
!
labour mandayt
total cost
MASONRY CONSTRUCTION
SWD
TYP M. m i i u n & >n mm
data 3107D7
HETAIL AND DIMENSIONS
| BILLOF QUANTITIES TWO DHV
32
10 30 50
0 10 40
s e a l * in centimeters
bund m3 38
!
plaster cmnt bag 3
sand m1 0.6
-
plastic foil m* 54
impermeable soil nV 26
materials |
labour ! msndays
i
total cost
i
T H I S O C S I G N WAS R E A L I S E D UNOER A U S P I C E S OF THE S T E E R I N G C O M M I T T E E WINDENERQY
D E V E L O P I N G C O U N T R I E S swo PO sOx as AwensFOORT T H C NETHERLANDS
TYPE III IN COOPERATION WITH TWO AMERSFOORT.
MASONRY CONSTRUCTION
SWD
TYPE :nr mailuiti in mm
aat. 910710
DETAIL AND DIMENSIONS
BILL OF QUANTITIES TWO IJMV
i
33
Page
General lay-out 34
Work instructions 35-36
Capacity 30 m3 37
Capacity 60. m3 38
Capacity 90 m3 39
Capacity 150 m3 40
pln
ir
>J0
-4
3- CO
i:1
#M,IO
i-t- T ~"*"i n o i *
xctlont
TVPE EC
fHIt OttlON At MIALHIO UMD1M AUSFICIt 0 ' THf fTIIHIMQ COMM^'II WIHDfNtRGv
0(VIk.0PIHC COUNTMltt *WO HO M * * AMlHtfOOMT I M i NtlHiftLANDt
n coo*i"'ion WITH - t w o A M I u t r o o p i
MASONRY CONSTRUCTION
SWD
MIU(* in mm
TYPE J3Z
0 1 J 1 4 5
GENERAL LAV OUT
c a l * in > TWO |srr.-. |
35
TYPE IV
- - ? -
[ 220 l^iHO
220 1 I
100
660 i1 I
10 90 SO
0 20 40
<:* in cant>matrs
TYPE 31 capacity 30 m3
PRiCE LEVEL
bund m3 23
plastic foil m2 35
sand m3 0.5
impermeable soil m3 4.5
materials !
labour mandays
i
total cost
MASONRY CONSTRUCTION
SWD
TYPE 3 E m i l i u m irt mm
data 810707
DETAIL AND DIMENSIONS
OHV
BILLOF QUANTITIES TWO
I
38
1
\ Ui>d l a y r
220 Jg~ 7 8 2 0
T-^H-
10 30 M
O 20 0
teal* m cntmtt
TYPE HZ capacity 60 m3
ICi LlTVfl
I !
ITEM UNIT UNIT PRICE QUANTITY PRICE
bricks piece 8900
i
220 H O i S S mm
cement
- - H bag 18
140 I t t )
3
sand m 1.5
conrsR
i
-1 3 - -
excavation m 30
bund m3 26
plastic toil m2 65
.
plaster cimint bag 2
sand m3 0.5
impermeable soil m3 9.3 i
materials
labour ffllndlyi
L
total cost I
i i
' OISICN WAS M A l ' M O UNDID AUSIC O* TM| STffW'NG COMMlTTCI WIMOCNEHGT
O I v i l O H t t G COUNrlllS - 1WD 0 t O l IS AMCHSFOORT T N ( N E T M C H .NOS
TYPE IV IN COOfl RATION WMfM - r WO * H S * 0 0 " T
MASONRY CONSTRUCTION
SWD
TYPE 3E.
data 810707
DETAIL AND DIMENSIONS
B I L L O F QUANTITIES TWO
39
f__
fiii< with too.
pl*tlC
V^
toil
T-
0 9580
^ 1000
K> K M
0 30 40
cement bag 20
I4C ltd ; i
sand m3 1.5 !
coarse
. i
excavation ' 41
i '.
materials
--
labour mandayt
total cost \ \
i 1
TYPE I T millu'ti in mm
( 810707
DETAIL AND DIMENSIONS
OHV
B I L L O F QUANTITIES TWO
40
1 1
ITEM UNIT UNIT PRICE QUANTITY ! PRICE
bricks piece 17750
2 2 0 . 110.55 mm
cement bag 34 i
I40ltr) < |
sand m3 2.7 i |
i:o;irsf
excavation m3 70
sand layer m3 33 ; |
materials ; j
| labour mindiyt
I
total cost I
i I
MASONRY CONSTRUCTION
SWD
TYPETX m t i i u r t s in mm
d u e 810707
DETAIL AND DIMENSIONS
BILLOF QUANTITIES TWO DHV
i
41
page
General lay-out 42
work instructions 43-44
Capacity 30 m3 45
Capacity 60 m3 46
Capacity 90 m3 47
Capacity 150 ra3 48
f
I
plans
JJQ
IT
it 'HI 1
'TL-
n o r
sections
TYPE 3E
capacity 30m* capacity 60m' capacity 90nt 3 capacity 150 m'
MASONRY CONSTRUCTION
SWD
TYPE 3Z
0 1 2 3 4 4st tioaie
- t 4 t 1 -*- GENERAL LAY OUT
cal* in mtfs TWO | 5T.*l |
43
TYPE V
tiarods m a d * ol stealitrips
"I-
ground laval
to so so
0 20 40
s e a l * in c a n t i m a t a r t
TYPE IE capacity 30 m3
PKtCt LEVEL
I
ITEM UNIT UNIT PRICE QUANTITY PRICE I
bricks piece 5400
230 i 110 i 5 mm
cement bag 11
<40ltr)
3
sand m 1
ro.irsc
excavation m1 17
!
3
sand layer m a
i
i
refill with soil m3 1.8 i
i materials
|
labour . (Vi and ays
total cost
I
THIS D E S I G N WAS R E A L I S E O UNOSR AUSPICES OF T H i S T E E R I N G C O M M I T T E E WINOCNERGY
D E V E L O P I N G C O U N T R I E S SWO RO 1 0 1 * S A M C R S F O O R T THE N E T H E R L A N D S
TYPE V I N C O O P E R A T I O N W I T H - T WO A M C R S F O O R T .
MASONRY CONSTRUCTION
SWD
TYPE 3C
data 810707
! DETAIL AND DIMENSIONS
I 8 I L L 0 F QUANTITIES TWO
DHV
46
i C3Sr
ground !*!
ra Ml yil_n ton
m ji^7Tpi.}i,.i.i,i,iHii,i
>v
| plaatic loil \Mtui l y i f
> . 0 7820
Tfist
to JO o
o ao o
teal* in c*r*tim*t*ri
TYPE 3E capacity 60 m3
HCI LCVIL
-
! !
ITEM UNIT UNIT PRICE QUANTITY PRICE
materials !
labour mindiyi
i
i total cost i
1 I
TNlB OfSlON WAS RIALISIO UMOIR AUtPICtl OF TMI tTflRINC COM**ITT(f WIHOENIRO*
TYPE V OfVllORINQ COUftTNllt 0 PQ aOI AMMS'OORr TMfl NETM1RLAN0S
IN COOM NATION W I T M r WO A MERS'OORT
MASONRY CONSTRUCTION
SWD
TYPE 3C m t a l u r t i in mm
data 810707
DETAIL AND DIMENSIONS
! 8 I L L O F QUANTITIES TWO ST"-....._.
I
47
rods mads of t i t f s t r i p t
V-""T'
//A , n ,i i, C\ I,i i,i 11 i i 11 i l l n
istn_i_j*itr> toil ,-/M\ 1 I fV.r.-iv;.--\:w-::.:..::
W M> 5 0
*- *- i- t --*-
0 40
cat* in cnt<m*tr*
TYPE 3C capacity 90 m 1
lCl LtVH
cement bag 20 i
140 n o I
sand m3 1.5
CIW5P
excavation m3 41
i
sand layer m3 25.6
r
plastic foil "~'m2" 80
, plaster c.m.m
bag 3
sand m3 0.5
tierods 10,26 m' 6
i
materials !
labour mindiyi
total cost i
MASONRY CONSTRUCTION
SWD
TYPE 3C maij(*A " mm
dat* 810707
DETAIL AND DIMENSIONS
DNV
| BILLOF QUANTITIES TWO
48
tiarods mada of ttaalttripa .
r
-H+
3= -
0 40
cat* in cantlmatara
cement bag 34
(40ltr)
sand m5 3
coarse
excavation m3 70
sand layer m3 32
r e f i l l w i t h soil m3 4.5
materials
labour mandays
total cost
THtt Ottiate WAS M A I . 1*10 UWOIH AU*I . . _* Or TMC tTttHlHO COMMIT T * t VIMOtMCftQT
oiviLOPma court runs two PO I O I u AMCRSFOORT T M I M T M I U L A N D I
TYPE V IM C0O*IaA7tOM WITH-TWOAUfP-tPOOHT.
MASONRY CONSTRUCTION
SWD
TYPE I
data 810707
DETAIL AND DIMENSIONS
OMV
B I L L O F QUANTITIES TWO
49
Page
Details brickwork bond, for a wall 50
Details brickwork bond, brick on
edge coping 51
Details brickwork bond for the
floorslab 52
Details tierods made of steelstrips 53
< 220 mm
330 mm
T-
4 4 0 mm
IRRIGATION
TYPICAL DESIGN
MASONRY CONSTRUCTION
WATER STORAGE
SWD
TANKS
I
DETAILS
BRICKWORK BOND
m m u r a t in i
6 * t * 810715
TWO f
1
brick on edge coping for
a wall of 220 mm thickness
220 mm
440 mm
MASONRY CONSTRUCTION
SWD
DETAILS
oat* 810713
BRICKWORK BOND
OMV
TWO
brickwork bond for tha flooralab
Unp>fmbl toil
MASONRY CONSTRUCTION
SWD |
DETAILS > ' la 1
<! U07U 1
BRICKWORK BOND
mf
TWO
53
tierods mada
of steelsfrips
H=H^ T~
connecting detail
I: :~wsr:
'
mr
M 20 w-
M"20~"
MASONRY CONSTRUCTION
SWD
DETAILS
U 810715
BRICKWORK BOND
OHV
TWO
54
2.4. Testing
2.4.1. Introduction
The question arises how a brick wall in the field or on a farm should be
tested to obtain information about cracks and collapse. The critical
moment is the moment when the brick wall begins to crack, since in a
cracked wall leakage will occur and the tank will be unsuitable. In
developing countries test equipment is not always available.
Therefore it must be determined with limited means, whether the brick,
the mortar and the brick wall are of such quality that with a reasonable
certainty the watertank can be constructed without risk of collapse.
If test equipment is available, it is strongly recommended to make use
of it.
However, we assume that the only way to test a brick wall will be to use
local materials and local equipment.
Preliminary
a. Appearance
b. Feel
Sands and gravel feel coarse and gritty. Silts and clay are
hard or floury when dry and soft or sticky when wet. Clay when
wet will stain the fingers and can only be removed by washing.
c. Composition
Vibration test
If there are many different sizes between the largest and the smallest,
the sample is well-graded. This means it will compact well. If only a
few sizes can be seen, then it is single-sized or poorly graded.
Settling test
This test can also be used to determine the amount of soil (dirt) in
river sand used for masonry or concrete work.
Place a sample in a bottle or a glass jar with straight sides. Then put
it down to allow the mixture to settle. Gravel and coarse sand will
settle immediately. Fine sand and coarse silt will settle more slowly
taking about 30 seconds. Clay and fine silt fractions will not settle
for several hours.
\ f
<r C O A R S e .
Cohesion test
Test
An easy test can be carried out as described below. The working order is
as follows: (see also the drawing).
A suitable area is chosen.
'"Two wooden straight beams are dug into the top soil with a core to
core distance of 2.0 metre.
The surface is levelled.
The top of the levelled surface and the wooden beams are covered
with plastic foil.
A 220 mm thick wall of 1.10 metre height and approx. 2.3 m in
length is made on top of the plastic foil and supported by the two
wooden beams (the total weight of the brick wall is approx. 1000 kg).
The bricks and the mortar should be the same as those used for the
watertank to be executed.
The brickwork bond is indicated on the drawing below (the stretcher
joints run vertically over the 1.10 m height to enable the most
critical situation to be simulated).
S C t <= K W O R K
G^rz.E'C I , | x. - 2 , 3 X.<=>,22 M )
The first load case occurs when the brickwork slab is supported by the
wooden beams only (first test-step).
The bending moment due to self weight of the slab is then as follows:
60
g brickwork = 4 KN/m1
<=\ fef?.>^K.v*'(*-K
( t o be checked)
M i 4 4 4 + 4 4| M= | * 4 * 2 2
= 2 KNm/m
^
2.oM
W = \ * 1 * 0 . 2 2 2 = 0.0081 m3
O.lfeM O,I&H
2*10 6 =
a bending moment = _ OQi*ioa 2469N/mm2
To calculate the ring forces and the bending moments in the irriga-
tion tanks the cylinder theory has been used a.o. according to:
"Theorie und Berechnung rotations-symmetrischer Bauwerke" by Dr.
Gyula Markus
Where applicable, tables and coefficients from this book are added.
With the above theory the following formulaa are used:
- /3(1-M2) NQ = pa F N My = pah
ah
V
h
//////// ////// /r F~\
ah
K= yv 3d-o.2^) = 67
lal^M
2.77*0.22
= 1.25 m N
Q r
a = 2.77 m n
hw = 0.22 m My u FM
M = 0.2 Pan "w
pa = 10*1.25*2 11 = 34.6
pah = 7.62
J No. *_
i A A VZ | 6 < 2 O
A ._ it ,/*?
~ |i;'<-
O.l >i/d>9
\%hA
"? o/2
0,3 \4,Gx*
C2,6o
t 1-2, i
0,3
0,6> 11,13
<7 <5,aa
6&&
o<&
Of) 2.,/ 6 6
to O
N Q (KN/m') M (KNm/m')
. _ 12.6-no3 _ .... 2 . 0.54*106 cc. 12
A = HA i m = 55 mm'
Au = rr?; =115 mm* v 90x110
h 110
a brickwork (h) = ^ A ^ S o = 0.0573 N/mra2 (< 0.10)
220-1000
0.54 *106*6
a brickwork (v) = = 0.0669 N/mm2 (< 0.10)
1000*220*
= 1.25 m V
3.91*0.22 l w:>
'
a = 3.91 m
hw = 0.22 m Kl = 1.76
M = 0.2 m pa = 10*1.25*3.91 = 48.88
pah = = 10.75
N Q (KN)/ra' M (KNn)/m'
. 18.79*10* ,,n 2 A = 0.62*106 , 2
V = 62
= 17 90* 100 ^
\ no
18 7 9 * 1 0 3 ^r ---
a brickwork (h) = 220*1000
ooA-l^n = 0,085 N/mm* (< 0,10)
6
a brickwork (v) = 0.62*10 *6
^ = 0,077 N/mra2 (< 0.10)
1000*220
* non-reinforced, wall thickness 220 mm
65
bv/ M,
H*<
o,v% 0/22 / .* \,i O, 3 3 o.
1
11.
A <5 12 \C 1o 1A1&
1 ) z*.7* -24,11 o o
o, l J 1A& 25,6c 0 ( 0-< 0,0-;
i j
0,2 22,4
> . < o,i-s O . I 3
\
7 0,3
\J T.f/24 tt.JJ. 7 o2<5 o,2
O/A
Ji 1^.7 16,} 0,Xo
V >r
y A
.7 M , I < 5 \1fiS O.lC
0/Z&
7< 77 9 , " <3/S<>
o , < M o,-94
A,& A7*
o o o
\o o
N Q (KN)/m' My (KNn)/m*
3
. _ 24.11*10 oon ,. , 0.66*106
h flO =
mm /m1 v 90*110 = 67 mm22/m
/m
=
a brickwork (h) = 220*1000" -11 N/n2 (too high)
See Table -*
26.78*]LO3 2 . _ 0.71*106 _ , , _ , /.
V 110 = 243 mm /m' A = i in----, in =46.0 mnr/ro
v 140"110
26. 78"io3
a b rickwork (h) = 3 -3r\ = 0.0812 N/ram2 (< 0.10)
nn
=
a brickwork (v) = Q O O * 3 3 0 * 6 - 039 N/mm2 (<
- 1 0 )
1
a
=
1.25 m
6.18 m
K it/T(i-o.2)
6.18*0.33 *
= 0 91
hw = 0.33/0.44 m Kl 1.14
M = 0.2 pa 10-1.25*6.18 = 77.25
N^ pahw 10*1.25*6.18*0.33 = 25.49
V,^ 0.44 = 58.24
0.^.-4 Q / S 5
3.772 36,14
34.1e 33,05
So.lo
17,25
i<3,<$6 ^ , 7 3
\i,<yi ii.2-4
-4.H
o
(KN)/m'
NQ
. _ 36,25*10 3 _ 0<5 2
A
i. = \TR = 330 mnr
n 110
0.44 o3
0 0
0 | 0 5 0,0-4
o,,< o,l&
, a 0, 3
o,a ,.46
.*9 o,&*
o,<o o , 6 9
0,<*2
.7'
0,63
,7
o^ Ot<4o
0 O
My (KNn)/nT
0>71*1066
56 mm
v 140*90
68
CTEELSTRIP5 ottTlSllioOS
See Table *
. _ 37.72*103 _ ,, 2/ . " A - 5,82 E6 2
A 3 4 3 mra / m A 46 /m
h " ~TTo v " 200*90 - """
Ring foundation only at the bottom of the tank wall carried out in
brickwork, concrete or impermeable soil
Formule:
N = 5E2 n
capacity m- hw pw NQO(n = i )
Calculation of hw
thickness (hw)
48.87E3
Bottom of the wall a. = 0.089 N/mm2 550 mm
brickwork 550 * 1000
59.87E3
- Bottom of the wall a. = 0.109 N/mm2 550 mm
brickwork 550 * 1000
71
77 25E3
- Bottom of the wall a, . . . = -,-,,,*.<. ,nnn = 0.10 N/mm2 770 mm
brickwork 770 * 1000 '
*) Uneconomical solution.
72
ANNEX 1
/
/
/ 'Y
/ /
\f=X=> M 3
/ <
/
/
/
/ I /
C\0 M3
* " ' '
I /
j/7 I /
^ O M ' ' s / /
/ // ' / /
/
/
3 b M3 f i- l^Vy. =. *Z?.o MM
/
i 1 I 1 -I-
^ o 3*3 -AA<=> W o <<=>
i-
"2o a>oo -Aoo *=*o<?
MM MM2
^^^\-\- T H I C K N E S S W t^eiNFORcEMENT
f-
ANNEX 2
Type
I II III IV V
+ + D D + water-permeability
more more less less more quantity materials
D + + + + realization
+ + D n + durability
less less more more more sensity for maintenance
- - - - _- frost-resistance
D ++ ++ ++ D resistance against changes
in humidity and temperature
D D + + ++ quality of workmanship
= bad
= reasonable
+ = good
++ = very good
74
ANNEX 3
DESIGN TABLE
In accordance with:
\ ^ 1
0 0,1 0,1 o, 0,4 o. 0. 0.7 0,1 0,( 1.0 '
4 0,0038 +0,1184 +0,2402 +0,3595 +0,4698 +0,5590 +0,6079 +0,5922 + 0,4877 +0,2829 0
7 0,0002 +0,0970 +0,1985 +0,2985 +0,4073 + 0,5283 +0,6573 + 0,7618 +0.7581 + 0,5202 0
8 + 0,0008 +0,0997 +0,1983 + 0,2971 +0,3993 + 0,5120 +0,6407 + 0,7669 +0,8059 +0,5870 0
List of symbols
ANNEX 5
2.7. Bibliography
1. Watt S.B.
Ferrocement Water Tanks
London 1978
2. Markus Gyula
Theorie und Berechnung rotations syrametrischer Bauwerke
4. v. Oss J.F.
Warenkennis en Technologie
J.H. de Bussy 1956
6. F.W. Knipschild
Stand der Technik der Abdichtung von Deponien mit HDPE
CP/JdL/MBi/JeP/S24/M