Professional Documents
Culture Documents
IBIC-210-400-ENQ-0058
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R1
Enquiry Specification for Shop Fabricated Tanks Date of Rev 23/05/2017
REVISION CONTROL
Page 1
Project Documentation
IBIC-210-400-ENQ-0058
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R1
Enquiry Specification for Shop Fabricated Tanks Date of Rev 23/05/2017
Table of Contents
1 Introduction 3
2 Site Condition 3
3 Equipment list 4
4 Equipment Detail 4
5 Scope of supply 4
6 Technical Details 5
7 Enclosures 5
IV Price schedules
V Devition Form
Page 2
Project Documentation
IBIC-210-400-ENQ-0058
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R1
Enquiry Specification for Shop Fabricated Tanks Date of Rev 23/05/2017
1.0 INTRODUCTION
M/S Deepak Fertilizers and Petrochemicals Corporation Limited (DFPCL) is setting up Nitric Acid Complex
having capacity 450 MTPD of Weak Nitric Acid (WNA) & 2 140 MTPD of Concentrated Nitric Acid (CNA) at
Dahej, near Bharuch, Gujarat and M/S IBI Chematur (Engineering & Consultancy) Ltd.(is the Detailed
Engineering Consultant for the same Project.
General Information:
1 Ambient Temp in C
a Max DB C 48
b Max WB C 29
c Min DB C 5
d Design dry bulb temperature C 35
2 RH
a Winter % 45
b Summer % 85
c Design Humidity % 75
3 Barometric Pressure
a Winter psia 14.68
b Summer psia 14.43
c Design pressure psia 14.59
4 Rainfall
a Average rainfall per Year mm 1000
b Max rainfall intensity mm/hour 65
c June-Sept rainfall intensity mm 920
5 Wind data
a Maximum velocity m/s 47 as per IS-875
b Wind direction Rose diagram
6 Earth quake
a Zone 3 as per IS-1893-1984 and
Rookie Earth Quake School
Report for Bharuch
Page 3
Project Documentation
IBIC-210-400-ENQ-0058
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R1
Enquiry Specification for Shop Fabricated Tanks Date of Rev 23/05/2017
Page 4
Project Documentation
IBIC-210-400-ENQ-0058
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R1
Enquiry Specification for Shop Fabricated Tanks Date of Rev 23/05/2017
Fabrication
Inspection & Testing
Painting for CS tank
Pickling & passivation for SS tanks
5.2 The Fabricator shall guarantee that the mechanical design, materials and workmanship of all
items are in accordance with this specification and all applicable codes
5.3 Scope of the fabricator shall include design, manufacturing, Testing, Packing & Forwarding as
per the attached drawings & specifications.
5.4 Supply all material required for completion of work in vendors scope. This shall cover Design
Engineering, Fabrication, stage wise inspection and testing. The scope of vendors covers all services
and activities required to be carried out for the Shop fabrication of Stainless Steel tanks, carbon steel
tank & carbon steel tank with rubber lining. The services and activities to be carried out by the
contractor shall include, but not limited to following
Design calculation as per relevant code specified in drawing
Preparation of fabrication drawings , duly approved by IBIC/DFPCL
Fabrication of Structural work like monkey ladder ,hand railing, pipe support, platform cleats
,insulation ring/cleats
Rubber lining by hot vulcanized rubber & Testing for (91T-6962) as per IS 4682 (PART I)
Rubbers lining approved vendors are MIL, Lathia, Lebracs, Sriram Rub.
Surface preparation(Pickling & Passivation For SS) as per ASTM A 380.
All carbon steel parts shall be sand blasted as per SA 2 1/2 & painted with Protecto mastic
primer (dft 50 micron) with final coat as per Standard Specification for site fabricated Tank
Annexure-9.
Supply of foundation bolts as per drawing
Page 5
Project Documentation
IBIC-210-400-ENQ-0058
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R1
Enquiry Specification for Shop Fabricated Tanks Date of Rev 23/05/2017
Ongoing project
Last 3year turn over
5.6 The following items shall be constructed as part of fabricators scope of supply whether the
same is specially indicated in the drawings & datasheet or not.
a. Cleats of insulation
b. 3 sets of spare gaskets for manholes. Hand holes & connection where blind
flange is provided.
c. Blind flanges & extra 10% nut bolts for all manholes, hand holes & spare
nozzles.
d. Suitable flanged joints or otherwise removable designs in respect of all
internals to enable removal through manhole unless specifically noted
otherwise in the datasheets / drawings.
e. Stiffening of nozzles 40 NB & below by 3 gussets.
f. Lifting lugs
g. Test rings / flanges wherever required for testing of the unit.
h. Davit arms or hinge cover for man ways.
i. Name plates
j. Earthing cleats
k. Foundation bolts/ Foundation Template
l. Structural items like ladders, platforms etc.
Design Parameter
Design code Good Engineering Practice
Volume (Nom.) 6M
Fluid Absorber Feed Water
Density 994 Kg/M
Design Pressure (Int. / Ext.) Atmosphere
Design Temperature 95C
Hydrotest pressure Water fill
Page 6
Project Documentation
IBIC-210-400-ENQ-0058
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R1
Enquiry Specification for Shop Fabricated Tanks Date of Rev 23/05/2017
Design Parameter
Design code API650 LATEST EDITION
Volume (Nom.) 115 M
Fluid Weak Acid
Density 1340 Kg/M
Design Pressure (Int. / Ext.) 8 WC + LIQUID HEAD
Design Temperature 149C
Hydrotest pressure AS PER CODE
Corrosion Allowance Nil
Joint Efficiency(Shell / Dished End) 0.85
Wind Load max. 47 m/s
Seismic Zone Zone 3 acc. to IS 1893
Material of construction SS304L
Design Parameter
Design code ASME Sec VIII Div I
Volume (Nom.) 12 M
Fluid Condensate
Density 960 Kg/M
Design Pressure (Int. / Ext.) 0.8 Bar
Design Temperature 121 C
Hydrotest pressure 1.04 Bar
Corrosion Allowance Nil
Joint Efficiency (Shell / Dished End) 0.85/ 1
Wind Load max. 47 m/s
Seismic Zone Zone 3 acc. to IS 1893
Material of construction SS304L
Insulation Hot Insulation 60 mm
Page 7
Project Documentation
IBIC-210-400-ENQ-0058
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R1
Enquiry Specification for Shop Fabricated Tanks Date of Rev 23/05/2017
Design Parameter
Design code ASME Sec VIII Div I
Volume (Nom.) 15 M
Fluid Instrument Air
Density 7.7 Kg/M
Design Pressure (Int. / Ext.) 9.4 Bar
Design Temperature 70 C
Hydrotest pressure 12.22 Bar
Corrosion Allowance 3 mm
Joint Efficiency (Shell / Dished End) 0.85/ 1
Wind Load max. 47 m/s
Seismic Zone Zone 3 acc. to IS 1893
Material of construction Carbon steel
Design Parameter
Design code ASME Sec VIII Div I
Volume (Nom.) 8 M
Fluid Plant Air
Density 9.32 Kg/M
Design Pressure (Int. / Ext.) 9.4 Bar
Design Temperature 70 C
Hydrotest pressure 12.22 Bar
Corrosion Allowance 3mm
Joint Efficiency (Shell / Dished End) 0.85/1
Wind Load max. 47 m/s
Seismic Zone Zone 3 acc. to IS 1893
Material of construction Carbon steel
Design Parameter
Design code API650 LATEST EDITION
Volume (Nom.) 12M
Fluid 98% H2SO4
Density 1840 Kg/M @ 25 C
Design Pressure (Int. / Ext.) Atmosphere
Design Temperature 70C
Hydrotest pressure AS PER CODE
Page 8
Project Documentation
IBIC-210-400-ENQ-0058
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R1
Enquiry Specification for Shop Fabricated Tanks Date of Rev 23/05/2017
Design Parameter
Design code API650 LATEST EDITION
Volume (Nom.) 20 M
Fluid 44% CAUSTIC SOLN.
Density 1458 Kg/M
Design Pressure (Int. / Ext.) Atmosphere
Design Temperature 75C
Hydrotest pressure AS PER CODE
Corrosion Allowance Nil
Joint Efficiency(Shell / Dished End) 0.85
Wind Load max. 47 m/s
Seismic Zone Zone 3 acc. to IS 1893
Material of construction CS/RL
The contractor shall carry out mechanical design of the tanks as per specified codes and standard &
submit design calculation for IBIC/DFPCL approval
6.1 Equipment shall be designed as per ASME Sec VIII Div I edition 2015/API 650/ unless
otherwise indicated.
6.2 Equipment shall be fabricated as per attached Equipment general drawing.
6.3 Rubber lining thickness: 4.5 mm natural rubber, hardness 65-70 shore A for rubber lined
Tank (91T-6992).
6.4 Rubber lining & inspection shall be done as per IS4682 (part -I) for (91T-6992) Tank.
6.5 Vendor to use hot vulcanization method for curing rubber lining for (91T-6962) Tank.
6.6 All flanges opening shall be blanked off with 12thk plywood or steel disc to secure with 4 Nos
bolts minimum.
6.7 Carbon content in forging & plates shall not exceed 0.25%.
6.8 All R/F pad holes shall be plugged.
Page 9
Project Documentation
IBIC-210-400-ENQ-0058
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R1
Enquiry Specification for Shop Fabricated Tanks Date of Rev 23/05/2017
6.9 All carbon steel part shall be sand blasted 2 & 3 coat of zinc phosphate primer.
6.10 Vendor to mark the nozzle No. & orientation detail on equipment.
6.11 Water for hydro testing shall not have chorine content exceeding 25 ppm for SS 7 50 PPM for
CS.
6.12 Calibration of tank is in vendor's scope. Prepare calibration chart by ullage method & get it
duly Certified by local weight & measures authorities for 91T- 6962, 91T- 6952 & 16V-1675
Tanks.
1.0 ENCLOSURES
Page 10
NOZZLE DATA LIST DESIGN DATA
Flange DESIGN CODE GOOD ENGINEERING PRACTICE
ID ND SCH/THK Description Remarks
500 500 WASHER PLATE TO BE WELDED AFTER Type Face Rating CODE STAMP REQUIRED -
RAFTERS POSITIONING OF EQUIPMENT L01A 2" 80S SO RF CL 150 Level Transmitter
Volume (Nom.) 6.0
REFER DETAIL-'A' 5THK ROOF L01B 2" 80S SO RF CL 150 Level Transmitter
170 = 230 = Fluid ABSORBER FEED WATER
PLATE L02A 2" 80S SO RF CL 150 Level Transmitter
5THK. 88 82 L02B 2" 80S SO RF CL 150 Level Transmitter Density 994
PAD = 175 =
ANCHOR BOLT M01 24" - SO RF CL 150 Manway (Access) API 650 Design Pressure (Int. / Ext.) Bar g ATMOSPHERIC
= 100 =
HOLD
270
= 150 = N01 2" 80S SO RF CL 150 Waste water Inlet
300
Design Temperature 95
50
Thk.
N02 2" 80S SO RF CL 150 DEMN. Water Inlet
12
8 Operating Pressure Bar g ATM
HOLE N03 4" 40S SO RF CL 150 Drain
Operating Temperature 35
165
N04 3" 40S SO RF CL 150 Vent
250
N05 3" 40S SO RF CL 150 Water Outlet Hydrostatic Test Pressure Bar g WATER FILL
N06 4" 40S SO RF CL 150 Overflow Corrosion Allowance mm 0
10 N07 2" 80S SO RF CL 150 Spare + BF
Thk.
HOLE
12
Joint Efficiency (Shell / Dished End) 0.85
10
250
N08 1" 80S SO RF CL 150 Pump Recirculation
50
Radiography (Shell / Dished End) 10% + ALL T JOINT
180
N09 2" 80S SO RF CL 150 Spare + BF
T01 1 1/2" 80S SO RF CL 150 Temparature Indicator Insulation Type / Thk. mm NIL
EC - - - - - Earthing Conn. 2 Nos Impact Test -
HOLE
150
NP - - - - - Name Plate 1 No. -
P.W.H.T
- -
R25 LL - - - Lifting Lug 4 Nos
M.D.M.T -
50 EARTHING Wind Load max. 47 m/s
EC
CONN. 10 = 100 = 10 Zone 3 acc. to IS 1893
Notes continue...:- Seismic Zone
25
Thk. Thk.
3048 TOTAL HEIGHT
19. PIPING ROUTINE FOR OVERFLOW NOZZLE UP TO GROUND FLOOR WILL BE Fabrication Tolerances Refer Standard Specification
IN OTHER'S SCOPE. Painting -
20. VENDOR TO PROVIDE 200% GASKETS & 10% EXTRA BOLTING AS SPARES. Surface Preparation Pickling & Passivation
5 DETAIL OF ANCHOR CHAIR
THK 21. LIFTING LUGS, EARTHING LUGS & NAME PLATE TO BE PROVIDED BY FABRICATOR. Lethal Service YES
(4 NOS.)
Empty Weight kg ~ 1280
23. FOR NAME PLATE REFER STANDARD IBIC-400-STD-70 & IBIC-400-STD-74. Operating Weight kg ~ 4270
0
20
24. CALIBRATION OF TANK IS IN VENDOR'S SCOPE. PREPARE CALIBRATION CHART BY Hydrotest Weight kg ~ 7280
NORMAL METHOD & GET IT DULY CERTIFIED BY BY LOCAL
100 Location OUT DOOR
WEIGHT & MEASURES AUTHORITIES.
6 Inspection IBIC / DFPCL
THK. 100 Seismic Moment kg-m -
25
SHELL SA 240 GR.304L ANCHOR CHAIR IS 2062 GR.B
R40 ROOF SA 240 GR.304L ANCHOR BOLTS SA 193 GR B7
1000
100
225
150
BASE PLATE SA 240 GR.304L SUPPORT CLEATS SA240 GR304L
750
R1 P. 16 THK.
GASKET REFER NOTE 6 EARTHING LUG S.S.304
TY
Notes:-
FOR 4 NOS. DETAIL OF LIFTING LUGS 01. ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE STATED.
ANCHOR CHAIRS (4 NOS.) 02. ALL NOZZLES UP TO 1 1/2" NB SIZE PROVIDED WITH 3 NOS. OF STIFFENERS.
ELEVATION
05. MANHOLE FLANGE DIMENSIONS SHALL BE AS PER API 650.
06. GASKET - TYPE S.S. SPIRAL WOUND FLEXIBLE GRAPHITE FILLED S.S. INNER
150 RING & S.S. OUTER RING, AS PER ASME B16.20
07. ALL NON PRESSURE PARTS MIN. 5 MM THK. UNLESS OTHERWISE SPECIFIED.
10 Thk.
09. ALL T/T HOLES TO BE PLUGGED WITH METALLIC CAP.
= 30 =
LL LL
80
BY STRESS CALCULATION.
25
5
CONSULTANT Issued :
Project :
Site :
DETAIL 'A' Title :
Sheet No.: Rev
Doc. Type : 1 of 1 R1
A1
1630
NOZZLE DATA LIST DESIGN DATA
HOLD
I
Flange DESIGN CODE API 650 (LATEST EDITION)
C MH2 ID ND SCH/THK Description Remarks
P H A B HANDRAIL Type Face Rating CODE STAMP REQUIRED -
1150 1150 WASHER PLATE TO BE WELDED AFTER A 2" 80S SO RF CL 150
Volume (Nom.) 115
HOLD HOLD POSITIONING OF EQUIPMENT B 2" 80S SO RF CL 150
C 2" 80S SO RF CL 150 Fluid WEAK ACID
175
ROOF D 3" 40S SO RF CL 150 Density 1340
HOLD
E 2" 80S SO RF CL 150 Outlet Design Pressure (Int. / Ext.) Bar g 8" W.C + Liquid Head
515
REF. DETAIL 'B' PAD 125 F1A 3" 40S SO RF CL 150 L.L. Gauge Design Temperature 149
75 F1B 3" 40S SO RF CL 150 L.L. Gauge
ANCHOR BOLT Operating Pressure Bar g ATM
R1 G1A 3" 40S SO RF CL 150 L.L. Gauge
HOLD
HOLD
350
350
US
40S SO RF CL 150 L.L. Gauge Operating Temperature 42
500
G1B 3"
I
8
RAD
INS R365
F1B G1B H HOLD - - - CL 150 Pressure Relief Hydrostatic Test Pressure Bar g AS PER CODE
8
IDE
I HOLD - SO RF CL 150 Vac. Relief Corrosion Allowance mm NIL
20
J 2" 80S SO RF CL 150 Spare w/ B.F.
Joint Efficiency (Shell / Dished End) 0.85
20
MH-1 20" - - - API 650 Manway w / davit As per API 650
200
200
- - API 650 As per API 650 Radiography (Shell / Dished End) 10% + ALL 'T' JOINT
MH-2 20" -
Insulation Type / Thk. mm -
50
P 3" 40S WN RF CL 150 LT
EC - - - - - Earthing Conn. 2 Nos Impact Test -
150
NP - - - - - Name Plate 1 No. -
100 8 P.W.H.T
LL - - - - - Lifting Lug 4 Nos
EC M.D.M.T -
Wind Load max. 47 m/s
75
Notes continue...:- Zone 3 acc. to IS 1893
Seismic Zone
Fabrication Tolerances Refer Standard Engineering Specification
SHELL 50 20. VENDOR TO PROVIDE 200% GASKETS & 10% EXTRA BOLTING AS SPARES.
21. LIFTING LUGS, EARTHING LUGS & NAME PLATE TO BE PROVIDED BY FABRICATOR. Painting -
I.D.
DETAIL OF ANCHOR CHAIR ON BASE PLATE (8 NOS.) Surface Preparation Pickling & Passivation
DETAIL 'A' MIDDLE ON LADDER. Lethal Service -
Empty Weight kg ~ 8450
TOE GUARD - 100MM x 4 MM THICK MS PLATE.
Operating Weight kg ~ 162550
5THK 24. FOR NAME PLATE REFER STANDARD IBIC-400-STD-70 & IBIC-400-STD-74. kg ~ 124000
Hydrotest Weight
ROOF PLATE 25. CALIBRATION OF TANK IS IN VENDOR'S SCOPE. PREPARE CALIBRATION CHART BY
ULLAGE METHOD & GET IT DULY CERTIFIED BY BY LOCAL Location OUT DOOR
WEIGHT & MEASURES AUTHORITIES. Inspection IBIC / DFPCL
5
50x50x6THK 26. GASKET - 1/8" VIRGIN NONPOROUS TEFLON TFE Seismic Moment kg-m -
CURB ANGLE Wind Moment kg-m -
100 MATERIAL SPECIFICATION
5 1/4" NPT (1 NO.) SHELL SA240 GR304L ANCHOR CHAIR IS 2062 GR.B
100 TELL TALE HOLE
THK. ROOF / DISH END SA240 GR304L ANCHOR BOLTS SA 193 GR B7
RAFTERS BASE PLATE SA240 GR304L SUPPORT CLEATS SA240 GR304L
25
0 RAFTERS SA240 GR304L INTERNALS SS 304L
5 R4
1200
225
150
10973 TOTAL HEIGHT
R1
HO 150
LD
G1A F1A LADDER-2 R1 23.05.2017 Issued for Enquiry VYT SAS NAS
10 Thk. 150
R0 18.05.2017 Issued for Approval VYT SAS NAS
200
= 30 =
NP
J Rev. Date Description Rev. By Chkd. By Appd. By
CLIENT:
HOLD
500
230
750
15
TYP.
MID LANDING Nitric Acid Complex at Dahej, Gujarat.
E D
175
500
1 D LL EC (HOLD)
Approved
NAS Dept. No.
400
Detailed Engineering (SUB CONTRACTOR)
REFER DETAIL 'A' 120 DETAIL OF EARTHING CONN. Checked
SAS Scale
1:20
LADDER-1 NOZZLE DETAIL Created Date
Project No : VYT 25/04/2017
FOR N05
G1A G1B Client : Dwg.No.
Project :
ELEVATION NOZZLE ORIENTATION Site :
Title :
LADDER, PLATFORM ORIENTATION (HOLD) Sheet No.:
1 of 1
Rev
Doc. Type : R1
A1
N01 HANDRAIL NOZZLE DATA LIST DESIGN DATA
Flange
ID ND SCH/THK Description Remarks DESIGN CODE ASME Sec. VIII DIV.1
2:1 ELLIPTICAL DISH END Type Face Rating
6Thk. N01 4" 40 SO RF CL 150 Vent CODE STAMP REQUIRED Latest Edition, Code stamp required
NOM. 8THK.
N02 3" 40 SO RF CL 150 Cold Cond. Inlet Volume (Nom.) 12
MIN. 6THK. 125
12 12 N03 3" 40 SO RF CL 150 Inlet from Steam Cond.
THK
TYP.
THK
Fluid Condensate
655
12
12
N04 3" 40 SO RF CL 150 Hot Cond. Inlet
(TYP.)
90
S.F.
3 NOS. INSULATION
50
N05 4" 40 SO RF CL 150 Cond. Outlet Density 960
SUPPORT RING N06 4" 40 SO RF CL 150 Overflow
Design Pressure (Int. / Ext.) Bar g 0.8
T.L. 2" x 2" x 3/8" ANGLE N07 1 1/2" 160 SO RF CL 150 Pump Min. Flow
W.L. WELDED TO SHELL N08 1 1/2" 160 SO RF CL 150 - W/ B.F. Design Temperature 121
HOLD
HOLD
200
250
250
HOLD
N12 3" 40 SO RF CL 150 Spare W/ B.F. Hydrostatic Test Pressure Bar g -
350
100
N13 2" 160 SO RF CL 150 Pressure Indicator
THK.
N13 N09 Corrosion Allowance mm 3.0
24
N14 1 1/2" 160 SO RF CL 150 Temparature Indicator
LT
N14 M01 24" - SO RF CL 150 W/ B.F. Joint Efficiency (Shell / Dished End) 0.85/1
HOLD
HOLD
6
500
Seismic Zone Zone 3 acc. to IS 1893
THK
3840 T.L. TO T.L.
HOLD
400
200 NB SCH 40 200 Lethal Service -
150
RF
PIPE Empty Weight kg ~ 2700
1200
PA
6THK
1219 Operating Weight kg ~ 14220
D
RF PAD
(HOLD) EACH SIDES TOTAL 94 NOS. Hydrotest Weight kg ~ 16550
803 803
23 SPACES @ 35 23 SPACES @ 35 SEE SPARGER Location OUT DOOR
SUPPORT DETAIL Inspection
LT IBIC / DFPCL
Seismic Moment kg-m 776
N03 Wind Moment kg-m 4304
HOLD
1630
HOLD
305
10THK.
N04 SHELL SA 516 GR.70 BOLTS & NUTS
NP
VALID FOR ALL NOZZLES HEADS SA 516 GR.70 SUPPORT SA 516 GR.70
750 IF NOT OTHERWISE INDICATED BASE PLATE SA 516 GR.70 INTERNALS SS 304
610
250 (QTY. 2 NOS.) COIL / JACKET N.A REINFORCING PAD SA 516 GR.70
L01B BODY FLANGE N.A NAME PLATE SS 304
W.L.
T.L. GASKET N.A FITTINGS SA 234 WPB
BOLTS & NUTS - INSULATION CLEATS -
6NOS - 3" SKIRT REFER DETAIL 'B' PIPE NOZZLE PIPE SA 516 GR.70/ SA 106 Gr.B EARTHING LUG SS 304
SPARGER PIPE 22. FINISH CS : REMOVE ALL FUSED & LOOSE WELD SPATTER, SLAG, SCALE FOREIGN
VENT CAP
VORTEX BREAKER U-BOLT FOR 3" PIPE MATERIAL. SANDBLAST ALL OUTSIDE CARBON STEEL SURFACES TO NOZZLE FLANGE SA 105 FOUNDATION BOLTS SA 193 B7
4" STD. WT.PIPE W/NUTS SPEC-SP10 "NEAR WHITE FINISH" SHELL AND UPPER PORTION OF GASKET SEE NOTE 22 LAP RING -
38 SKIRT - PRIME W/ ONE (1) COAT OF INTERNATIONAL PROTECTIVE COATINGS
8" SCH. 40S PIPE SLEEVE
x 3"(76MM) LONG INTER ZINC 22. 2.0 MLS D.F.T. Notes
01. ALL DIMENSIONS ARE IN M.M. UNLESS OTHERWISE STATED.
(HOLD)
N05
2250
THK
6
02.
CL. OF 20" x 8" ACCESS 03.
OPENING 04. ALL T/T HOLES TO BE PLUGGED AFTER HYDROTEST.
(HOLD)
05. ALL BOLT HOLES OF FLANGES SHALL BE STRADDLE WITH PRINCIPLE C/L OF VESSEL.
1425
25
06. ALL NOZZLE FLANGES SHALL BE ASME B16.5 AND GASKET SEATING SURFACE SHALL
8"
730
185
6 6THK
07. LIFTING LUGS, EARTHING LUGS & NAME PLATE TO BE PROVIDED BY FABRICATOR.
08. WELD WHICH IS ACCESSIBLE FROM OTHER SIDE SHOULD BE BACK CHIP UP TO
SOUNDMETAL AND REWELD OR OTHER WISE TIG WELDED.
09. EQUIPMENT TO BE HYDROTESTED IN HORIZONTAL POSITION.
25 10. CLEATS FOR INSULATION SHALL BE PROVIDE BY EQUIPMENT SUPPLIER.
52 52 TYP. 11. ALL INSIDE WELDS SHALL BE FLUSH WITH SHELL I.D.
ELEVATION 6
REFER DETAIL 'A' 12. PRIMER PAINT SHALL BE PROVIDE ON ALL C.S PARTS.
185 13. PAD PLATE PROVIDED 3" NB & ABOVE NOZZLES.
CL. OF 20" ACCESS OPENING M01 N13
14. FOR NAME PLATE DETAILS REF. DRG. NO:-IBI-400-STD-70 / 71.
SPARGER SUPPORT DETAIL
FOR M-20 BOLTS (TYPICAL)
N09 16. VENDOR TO PROVIDE LADDER AND HANDRAIL WITH TOE PLATE.
N02 N10
N06 TOE GUARD - 100MM x 4 MM THICK MS PLATE.
N 17. VENDOR TO PROVIDE FOUNDATION BOLTS AND TEMPLATE
18. VENDOR TO REINFORCE ALL NOZZLES TO COMPLY WITH CODE.
19. VENDOR TO BE FURNISHED & INSTALLED MATERIAL UNLESS OTHERWISE SPECIFIED.
20. VENDOR TO PROVIDE DESIGN AND PROVIDE LIFTING TRUNION,
10 THK. 21. SUPPLY OF LADDER AND HANDRAIL IS IN VENDOR'S SCOPE.
LT N01 LT 6
N04 N11 N05 N08 R1 23.05.2017 Issued for Enquiry VYT SAS NAS
= 30 =
R0 12.05.2017 Issued for Approval VYT SAS NAS
N12 Rev. Date Description Rev. By Chkd. By Appd. By
CLIENT:
A1
NOZZLE DATA LIST DESIGN DATA
Flange
200 NB SCH 40 ID ND SCH/THK Description Remarks DESIGN CODE ASME Sec. VIII DIV.1
200 Type Face Rating
RF
PIPE N01 2" 160 WN RF CL 150 CODE STAMP REQUIRED -
PA
10THK N02 2" 160 WN RF CL 150 Volume (Nom.) 15
D
RF PAD N03 1 1/2" 160 WN RF CL 150
HAND RAIL Fluid INSTRUMENT AIR
N04 2" 160 WN RF CL 150 Pressure Safety valve
M01 24" 10THK WN RF CL 150 With Davit arm Density 7.7
P01 2" 160 WN RF CL 150 Pressure Transmitter
LT 2" 160 WN RF CL 150 Pressure Gauge
Design Pressure (Int. / Ext.) Bar g 9.4
P02
S01 2" 160 WN RF CL 150 Spare B.F. Design Temperature 70
S02 2" 160 WN RF CL 150 Spare B.F. Operating Pressure Bar g 7.0
S03 S03 2" 160 WN RF CL 150 Spare B.F.
EC - -- - - - Earthing Conn. 2 Nos Operating Temperature AMBIENT
NP - - - - - Name Plate 1 No. Hydrostatic Test Pressure Bar g 12.5
10THK.
LL - - - - - Lifting Lug 4 Nos
2:1 ELLIPTICAL DISH END Corrosion Allowance mm 3
ACH - - - - - Anchor Chair 8 Nos
NOM. THK. 14 MM DETAIL OF LIFTING TRUNION
MIN. THK. 12 MM Joint Efficiency (Shell / Dished End) 0.85/1
(QTY. 2 NOS.)
S.F.
50
TYP. Radiography (Shell / Dished End) 10% + ALL 'T' JOINT
T.L. Insulation Type / Thk. mm -
200
W.L. Impact Test -
N02 S01 10Thk.
500
P.W.H.T -
20 12 125 12 10 M.D.M.T -
200
EC Surface Preparation -
Lethal Service -
Empty Weight kg ~ 5800
20
100
10
THK.
24
Operating Weight kg ~ 5900
Hydrotest Weight kg ~ 22600
FOR M 20 F BOLTS. Location OUT DOOR
12 DETAIL OF ANCHOR CHAIR ON BASE PLATE SKIRT SHELL TO DISH JOINT Wind Moment N-m 889407
THK
MATERIAL SPECIFICATION
N04 SHELL SA 516 GR.70 BOLTS & NUTS
5300 T.L. TO T.L.
HEADS / ROOF SA 516 GR.70 SUPPORT SA 516 GR.70
BASE PLATE SA 516 GR.70 INTERNALS -
150 COIL / JACKET REINFORCING PAD
N.A SA 516 GR.70
06. ALL NOZZLE FLANGES SHALL BE ASME B16.5 AND GASKET SEATING SURFACE SHALL
N03 BOTTOM BE SERRATED TYPE UNLESS OTHERWISE SPECIFIED.
N01 N04 07. LIFTING LUGS, EARTHING LUGS & NAME PLATE TO BE PROVIDED BY FABRICATOR.
NP M01 M01 08. WELD WHICH IS ACCESSIBLE FROM OTHER SIDE SHOULD BE BACK CHIP UP TO
SOUNDMETAL AND REWELD OR OTHER WISE TIG WELDED.
S02 S01 VALID FOR ALL NOZZLES
09. EQUIPMENT TO BE HYDROTESTED IN HORIZONTAL POSITION.
IF NOT OTHERWISE INDICATE
800
NOZZLE ORIENTATION
750
FOR M 20 BOLTS. 16. VENDOR TO PROVIDE LADDER AND HANDRAIL WITH TOE PLATE.
V0 'B'
TOE GUARD - 100MM x 4 MM THICK MS PLATE.
350
17. VENDOR SHALL PROVIDE FOUNDATION BOLTS AND TEMPLATE (SA 36) WITHIN
V0 EC 10 THK. 3 MONTHS OF ORDER FOR FOUNDATION PREPARATION AT SITE
N03
1500
A0
= 30 =
THK
24
'A'
EC R0 03.05.2017 Issued for Approval VYT SAS NAS
Rev. Date Description Rev. By Chkd. By Appd. By
ACH CLIENT:
EC
50 Approved NAS Dept. No.
400
Detailed Engineering (SUB CONTRACTOR)
Checked Scale
SAS 1:18
Created Date
Project No : VYT 19/04/2017
ACH V0 Client : Dwg.No.
LT ACH DETAIL OF EARTHING CONN. Project :
ELEVATION (QTY. 2 NOS.) Site :
ORIENTATION Title :
Sheet No.: Rev
ANCHOR CHAIR DETAIL ON SKIRT SHELL (HOLD) Doc. Type : 1 of 1 R1
A1
HAND RAIL
NOZZLE DATA LIST DESIGN DATA
Flange
ID ND SCH/THK Description Remarks DESIGN CODE ASME Sec. VIII DIV.1
S03 Type Face Rating
N01 2" 160 WN RF CL 150 CODE STAMP REQUIRED -
N02 2" 160 WN RF CL 150 Volume (Nom.) 8
2:1 ELLIPTICAL DISH END 200 NB SCH 40 200 N03 1 1/2" 160 WN RF CL 150
RF
PIPE N04 2" 160 WN RF CL 150 Pressure Safety valve Fluid PLANT AIR
NOM. THK. 12 MM
P
10THK 10THK WN RF CL 150 With Davit arm Density
AD
S.F.
MIN. THK. 10 MM M01 24" 9.32
50
TYP. RF PAD P01 2" 160 WN RF CL 150 Pressure Transmitter
Design Pressure (Int. / Ext.) Bar g 9.4
T.L. P02 2" 160 WN RF CL 150 Pressure Gauge
S01 2" 160 WN RF CL 150 Spare B.F. Design Temperature 70
200
W.L. S02 2" 160 WN RF CL 150 Spare B.F. Operating Pressure Bar g 7.0
N02 S01 LT
500
S03 2" 160 WN RF CL 150 Spare B.F.
EC - -- - - - Earthing Conn. 2 Nos Operating Temperature AMBIENT
NP - - - - - Name Plate 1 No. Hydrostatic Test Pressure Bar g 12.22
LT LT - - - - - Lifting Trunion 2 Nos
- - Corrosion Allowance mm 3
ACH - - - Anchor Chair 8 Nos
Joint Efficiency (Shell / Dished End) 0.85/1
10THK.
Radiography (Shell / Dished End) 10% + ALL 'T' JOINT
Insulation Type / Thk. mm -
Impact Test -
P.W.H.T -
M.D.M.T -
Wind Load max. 47 m/s
DETAIL OF LIFTING TRUNION
Seismic Zone Zone 3 acc. to IS 1893
(QTY. 2 NOS.)
1500 I.D. 10 Fabrication Tolerances Refer Standard Engineering Specification
THK Painting Refer Note 12
Surface Preparation -
200
EC COIL / JACKET N.A REINFORCING PAD SA 516 GR.70
BODY FLANGE N.A NAME PLATE SS 304
NP M01 N01 N04
GASKET N.A FITTINGS SA 234 WPB
100
20
THK.
BOLTS & NUTS - INSULATION CLEATS -
20
NOZZLE PIPE SA 106 Gr.B EARTHING LUG SS 304
800
750
02.
DETAIL OF ANCHOR CHAIR ON BASE PLATE VALID FOR ALL NOZZLES
03.
V0 'B' IF NOT OTHERWISE INDICATE 04. ALL T/T HOLES TO BE PLUGGED AFTER HYDROTEST.
250
05. ALL BOLT HOLES OF FLANGES SHALL BE STRADDLE WITH PRINCIPLE C/L OF VESSEL.
N03 06. ALL NOZZLE FLANGES SHALL BE ASME B16.5 AND GASKET SEATING SURFACE SHALL
BE SERRATED TYPE UNLESS OTHERWISE SPECIFIED.
1500
150 07. LIFTING LUGS, EARTHING LUGS & NAME PLATE TO BE PROVIDED BY FABRICATOR.
1500 I.D. 10
THK 08. WELD WHICH IS ACCESSIBLE FROM OTHER SIDE SHOULD BE BACK CHIP UP TO
SOUNDMETAL AND REWELD OR OTHER WISE TIG WELDED.
09. EQUIPMENT TO BE HYDROTESTED IN HORIZONTAL POSITION.
A0 10. CLEATS FOR INSULATION SHALL BE PROVIDE BY EQUIPMENT SUPPLIER.
THK
20
350
'A' 11. ALL INSIDE WELDS SHALL BE FLUSH WITH SHELL I.D.
EC 12. PRIMER PAINT SHALL BE PROVIDE ON ALL C.S PARTS.
13. PAD PLATE PROVIDED 3" NB & ABOVE NOZZLES.
14. FOR NAME PLATE DETAILS REF. DRG. NO:-IBI-400-STD-70 / 71.
LT A0 V0
ACH 16. VENDOR TO PROVIDE LADDER AND HANDRAIL WITH TOE PLATE.
ELEVATION ACH 10 THK.
FOR M 20 BOLTS. TOE GUARD - 100MM x 4 MM THICK MS PLATE.
N04 17. VENDOR SHALL PROVIDE FOUNDATION BOLTS AND TEMPLATE (SA 36) WITHIN
V0 EC 3 MONTHS OF ORDER FOR FOUNDATION PREPARATION AT SITE
18. SUPPORT CLEATS FOR PLATFORMS AS REQUIRED SHALL BE
10 SUPPLIED BY VENDOR. LADDER, HANDRAILS SHALL BE SUPPLIED BY VENDOR.
= 30 =
N P01 P02 ACH
10 35 15 CLIENT:
ACH V0
50 Nitric Acid Complex at Dahej, Gujarat.
EC
CONSULTANT Issued :
A1
NOZZLE DATA LIST DESIGN DATA
N10 C02 N07
N03 WASHER PLATE TO BE WELDED AFTER Flange DESIGN CODE API 650 (LATEST EDITION)
POSITIONING OF EQUIPMENT ID ND SCH/THK Description Remarks
N05 C01 N01 Type Face Rating -
L02 CODE STAMP REQUIRED
REFER DETAIL-'A' 170 C01 3" 80 WN RF CL 150
= 230 = Volume (Nom.) 12
1000 800 C02 3" 80 WN RF CL 150
6THK. 88 82 L01 3" 80 WN RF CL 150 Fluid 98% H2SO4
= 175 =
PAD L02 4" 80 WN RF CL 150 Spare With B.F. Density
= 100 = = 150 = ANCHOR BOLT
M01 24" - - - API 650 Manhole w / Cover As per API 650 Design Pressure (Int. / Ext.) Bar g 0.06
50
Thk.
20
8 N01 2" 80 WN RF CL 150 H2SO4 Inlet Design Temperature 70
HOLE N02 3" 80 WN RF CL 150 H2SO4 Outlet
Operating Pressure Bar g ATM
65 x 65 x 6THK. HAND RAIL N03 2" 80 WN RF CL 150 Vent
80 WN RF CL 150 Drain Operating Temperature
CURB ANGLE N04 2"
N05 3" 80 WN RF CL 150 With B.F. Hydrostatic Test Pressure Bar g FULL OF WATER
6 THK
THK
10
Thk.
HOLE N06 3" 80 WN RF CL 150 Spare With B.F.
20
ROOF PLATE Corrosion Allowance mm 3 FOR SHELL & BOTTOM / 1 FOR ROOF
10
325
80 WN RF CL 150 Pump Recirculation
50
N07 2" Dip Pipe Joint Efficiency (Shell / Dished End) 0.85
300
REFER DETAIL-'D' N08 3" 80 WN RF CL 150 Overflow Nozzle
80 WN RF CL 150 Spare Radiography (Shell / Dished End) 10% + ALL T JOINT
N09 3" With B.F.
Insulation Type / Thk. mm NIL
HOLD
150
350
T01 1 1/2" 80 WN RF CL 150 Temperature Transmitter Impact Test -
N08 N09 R25 EC - - - - - Earthing Conn. 2 Nos P.W.H.T -
50 NP - - - - - Name Plate 1 No.
EARTHING M.D.M.T -
EC - -
25
CONN. 10 = 100 = 10 LL - - - Lifting Lug 4 Nos
Wind Load max. 47 m/s
Thk. Thk.
Seismic Zone Zone 3 acc. to IS 1893
Fabrication Tolerances Refer Standard Engineering Specification
25
Wind Moment N-m 17722
NP M01
MATERIAL SPECIFICATION
R2 R40
L01 SHELL IS:2062 GRB BOLTS & NUTS SA193 GRB7/SA194 GR2H
225
150
N06
700
100
500
ROOF / DISH END IS:2062 GRB SUPPORT IS 2062 GR.B
N02 HO
LE BASE PLATE IS:2062 GRB INTERNALS IS 2062 GR.B
240
150
R2
COIL / JACKET - REINFORCING PAD IS 2062 GR.B
12
5 BODY FLANGE - NAME PLATE SS.304
1 N04 5 R1 P. 16 THK. GASKET - FITTINGS SA213 GR WPB
120 TY
WEAR PLATE BOLTS & NUTS - INSULATION CLEATS IS 2062 GR.B
NOZZLE PIPE SA106 GRB EARTHING LUG S.S.304
DETAIL OF LIFTING LUGS
(4 NOS.) NOZZLE FLANGE SA350 GR.LF2 CL.1 FOUNDATION BOLTS
GASKET R.F. PTFE Rod / Bar -
250
ELEVATION 10 Thk.
= 30 =
C01
N 15
TYP.
M01
N01
N06 80
L01 EC VALID FOR ALL NOZZLES PROTECTO MASTIC PRIMER (DFT 50 MICRON)
LE N10 DETAIL OF EARTHING CONN.
T01 LE IF NOT OTHERWISE INDICATE
UP TO GROUND FLOOR WILL BE IN OTHER'S SCOPE. R2
26. SILICA GEL POT IS IN VENDOR'S SCOPE.
27. CALIBRATION OF TANK IS IN VENDOR'S SCOPE. PREPARE CALIBRATION CHART BY
N03 2 NOS. ULLAGE METHOD & GET IT DULY CERTIFIED BY BY LOCAL
T01
0
20
WEIGHT & MEASURES AUTHORITIES.
LADDER WITH FABRICATOR'S
CAGE
0
SCOPE
00
0
TOE GUARD - 100MM x 4 MM THICK MS PLATE.
75
LE N09 NP
500
N08
N05 CLAMP
160
N07 LE 6
CONSULTANT Issued :
A1
WASHER PLATE TO BE WELDED AFTER NOZZLE DATA LIST DESIGN DATA
POSITIONING OF EQUIPMENT Flange
ID ND SCH/THK Description Remarks DESIGN CODE API 650 (LATEST EDITION)
175 Type Face Rating CODE STAMP REQUIRED -
S03 N06 S02 N07 L01 3" 80 WN FF CL 150
6 THK. 55 45 150 R1
Volume (Nom.) 20
N01 S01 N04 M01 24" - - - API 650 Manhole cover / Davit As per API 650
PAD 125 Fluid 44% CAUSTIC SOLUTION (NaOH)
N01 2" 80 WN FF CL 150 Inlet
75 ANCHOR BOLT N02 2" 80 WN FF CL 150 Outlet Density 1458
350 950 REFER DETAIL-'B' N03 2" 80 WN FF CL 150 Drain Design Pressure (Int. / Ext.) Bar g ATM
HAND RAIL N04 2" 80 WN FF CL 150 Vent Goose neck With Bird Screen Design Temperature 75
8 N05 3" 80 WN FF CL 150 Overflow
EQUI-SPACE Operating Pressure Bar g ATM
N06 2" 80 WN FF CL 150 Pump Recirculation
20
RAFTERS 6 THK + 4.5THK 80 WN FF CL 150 Spare Operating Temperature AMB
N07 2" With B.F.
20
ISMC 75
200
200
RUBBER LINING N08 3" 80 WN FF CL 150 Spare With B.F. Hydrostatic Test Pressure Bar g FULL OF WATER
ROOF PLATE N09 80 WN FF CL 150 Spare
150
2" With B.F. Corrosion Allowance mm NIL
50
S01 3" 80 WN FF CL 150 Spare With B.F.
REFER DETAIL-'A' Joint Efficiency (Shell / Dished End) 0.85
S02 2" 80 WN FF CL 150 Spare With B.F.
150
80 WN FF CL 150 Spare nozzle for dip pipe Radiography (Shell / Dished End) 10% + ALL T JOINT
100 8 S03 4" With B.F.
T01 2" 80 WN FF CL 150 Temperature Transmitter Insulation Type / Thk. mm NIL
250
250
EC
350
EC - - - - - Earthing Conn. 2 Nos Impact Test -
N05 N08
75
NP - - - - - Name Plate 1 No. -
P.W.H.T
LL - - - - - Lifting Lug 4 Nos
M.D.M.T -
ACH - - - Anchor Chair
50 Wind Load max. 47 m/s
DETAIL OF ANCHOR CHAIR
ACH Seismic Zone Zone 3 acc. to IS 1893
(8 NOS.)
6 Fabrication Tolerances Refer Standard Engineering Specification
THK. Painting Refer note 23
2 NOS.
4.5THK. Surface Preparation -
75
AFTER RUBBER LINING RUBBER LINING T01 Lethal Service -
Empty Weight kg ~ 3590 (WITHOUT RUBBER LINING)
REFER DETAIL-'B1'
3000
0
20
Hydrotest Weight kg ~ 24790 (WITHOUT RUBBER LINING)
T01 Location OUT DOOR
Inspection IBIC / DFPCL
DETAIL-'B'
Seismic Moment kg-m -
Wind Moment kg-m -
1000
M01 NP
MATERIAL SPECIFICATION
CLAMP
1000
100
SHELL ANCHOR CHAIR IS 2062 GR.B
750
175
FOR TO1 13. RUBBER LINING THICKNESS :4.5 MM NATURAL RUBBER, HARDNESS 65-70 SHORE A COIL N.A. INTERNALS IS2062 GR.B
DETAIL-'B1' 14. RUBBER LINING & INSPECTION SHALL BE DONE AS PER IS4682 (PART -I).
160
CURB ANGLE IS2062 GR.B REINFORCING PAD IS2062 GR.B
1 N03 IS2062 GR.B
120 6 THK. ROOF PLATE RAFTERS NAME PLATE S.S 304
150 16. VENDOR TO USE HOT VULCANIZATION METHOD FOR CURING RUBBER LINING. NOZZLE PIPE FITTINGS SA 234 WPB
6 NOZZLE FLANGE INSULATION CLEATS N.A.
150
GASKET SOFT RUBBER EARTHING LUG SS304
12
INT. BOLTS & NUTS EXT. BOLTS & NUTS SA193 GR.B7,SA194 GR.2H
160
CURB ANGLE
6
N N03
ACH EC N01
ACH 6 THK. PROTECTO MASTIC PRIMER (DFT 50 MICRON)
L01 N08 500
DETAIL-`A' HOLD
LE
N03 NOZZLE DETAIL
T01 L01 LE FOR N03 27. VENDOR TO PROVIDE LADDER AND HANDRAIL WITH TOE PLATE.
LADDER 150
TOE GUARD - 100MM x 4 MM THICK MS PLATE.
10 Thk.
= 30 =
ACH
R1300
ACH
4.5 THK. 30. CALIBRATION OF TANK IS IN VENDOR'S SCOPE. PREPARE CALIBRATION CHART BY
N04 RUBBER LINED ULLAGE METHOD & GET IT DULY CERTIFIED BY BY LOCAL
R9
50 15 WEIGHT & MEASURES AUTHORITIES.
TYP.
80
S01 M01 N06 S02
NP DETAIL OF EARTHING CONN. VALID FOR ALL NOZZLES
IF NOT OTHERWISE INDICATE
100
ACH ACH
6 1/4" NPT (1 NO.)
100 TELL TALE HOLE
R1 23.05.2017 Issued for Enquiry VYT SAS NAS
THK. R0 03.05.2017 Issued for Approval VYT SAS NAS
N02 N05 Rev. Date Description Rev. By Chkd. By Appd. By
25
CLIENT:
0
R4
N07 S03 LE
LE
225
CONSULTANT Issued :
HO
ACH ACH EC LE Approved
NAS Dept. No.
400
12 Detailed Engineering (SUB CONTRACTOR)
Checked Scale
N09 SAS 1:20
5 5
R1 P. 16 THK. Created Date
Project No : VYT 25/04/2017
TY Client
Project
:
:
Dwg.No.
A1
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
REVISION CONTROL
Page 1
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
Table of Contents
1 Introduction 3
6 Painting 7
8 Documentation 8
9 Reference standards 8
10 Guarantee 8
Page 2
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
1.0 INTRODUCTION
This Specification together with the data sheets / drawings covers the general requirements for
materials, design, fabrication, inspection, testing and erection of unfired pressure vessels. The
requirements laid down herein are supplementary to the design/ fabrication code as specified.
2.1 Design, fabrication, inspection and testing of the vessels are as per ASME SEC VIII Div.1. (Latest
edition unless otherwise specified)/Good engineering practice.
2.2 The design information and overall dimensions etc. specified in the specification sheet drawing
are only in respect of major details like shell and dish end thickness, skirts, flanges etc.
Wherever such dimensions / thickness is not specified for minor parts such as nozzle
reinforcement etc., the same shall be designed and supplied by the Fabricator as to meet
all applicable provisions of the design code. Fabricator shall satisfy himself with the design and
on placing the order shall submit the complete design calculations for IBIC's approval prior to
fabrication.
2.3 Wherever Fabricator proposes to use materials either with a change in specification or in
thickness, it shall be his responsibility to furnish all calculations as may be required to establish
that the proposed change is in agreement with the overall provisions of design code.
2.4 In case of any class of work, which is not covered by the governing codes, the work should
be carried out as per the standard engineering practice submitted to and approved by
Purchaser.
2.5 All dimensions shown in the data sheets / drawings are in mm unless otherwise
specified. Thickness indicated for shell and formed heads are minimum specified after forming.
2.6 The minimum corrosion allowance for carbon steel shall be 3 mm unless otherwise specified
in the data sheet. The corrosion allowance for nozzles and manholes shall be at least equal to
that specified in vessel shell.
2.7 For austenitic steel the corrosion allowance shall be zero unless otherwise specified in the data
sheet. The corrosion allowance for nozzles and manholes shall be at least equal to that specified
in vessel shell.
2.8 All the materials shall be as per equipment data sheets and conform to ASME Sec II and
inspected to corresponding ASTM specifications or IS specifications of equal grade. Check
testing shall be performed for all the materials as per code.
2.9 Max. Carbon content of all weld able carbon steel shall be 0.25%.
Page 3
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
3.1 Scope of the fabricator shall include design wherever necessary, preparation of detailed
fabrication drawings furnish design calculations and taking approval for the same, supply of
materials as per the specifications or as agreed upon, fabrication, testing, cleaning,
transportation, getting any Statutory approval of the vessel, if required and all activities required
for the completion of the work.
3.2 All the work other than specifically mentioned above required in order completing the jobs as per
specifications in the data sheet, the Fabricator shall carry out Inspection Standard.
3.3 The following items shall be constructed as part of Fabricator's scope of supply whether the same
is specifically indicated in the drawings / data sheets or not.
4.1 The fabrication procedure shall confirm to all applicable requirements of specified code and
established Engineering Practices for manufacture of vessels.
4.2 As far as practicable, the shell sections shall be made out of a single plate with one longitudinal
weld seam only. The longitudinal seams of adjacent courses shall be staggered by a minimum of
five times the greater thickness of plate section and, as far as possible seams shall be positioned
clear of supports so as to be readily visible for examination. The weld seams shall be indicated on
the fabrication / as built drawing.
4.3 Nozzles shall be located, as far as possible, clear of the weld joints by a minimum of 50 mm, where
this is not possible, Fabricator shall obtain the necessary approval from Purchaser and shall
provide adequate reinforcement.
4.4 All carbon and low alloy steel plates shall be cut to size by flame cutting and machined.
Alternatively cold shearing of plates is acceptable up to 25 mm thick, provided the sheared edges
are cut back by machining, chipping or grinding for a depth of 3 mm. In case of plates higher than
20 mm thk DP of cut edges shall be carried out.
4.5 Austenitic Stainless Steel plates may be cut by either cold shear or Plasma arc, but in all cases
the edges should be ground by 3 mm.
Page 4
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
4.6 All nozzle / manhole projections shall be 150 mm minimum, unless otherwise specified in
the data sheet & drawings.
4.7 Rolling of plates shall be along longitudinal direction only. Re-rolling, after welding, which is
not normally allowed may be resorted to only with prior approval and should be carried out as
directed by Purchaser.
4.8 Welders qualified as per requirements of ASME Section IX may perform welding manually
or with semi-automatic or automatic machines according to qualified and approved
procedures.
4.9 Welding shall be done by any of the shielded arc welding process, either by TIG welding or
by MIG welding process. Single pass submerged arc welding of butt joints is prohibited. Root run
shall be done only by TIG welding for S.S.
4.10 Edges to be welded shall be free of foreign materials, moisture, oil, grease, paint, etc. to a
distance of 25 mm minimum.
4.11 All the butt welds shall be full penetration welds, chipped back to sound metal and re- welded
from other side.
4.12 As far as practicable jigs, fixtures and other suitable methods shall be used to avoid distortion
due to welding.
4.13 Temporary attachment welds on vessels shall be removed. The surface under such welds
and under backing rings, which have been removed, shall be properly conditioned to eliminate
surface stress raisers. Such surface shall be examined by MT / DPT for stainless steel, and for carbon steel
with a design temperature below 0 C.
4.14 Internal baffles, trays support beams or other internals spanning a chord or diametric of the vessel
shall be provided with a means for allowing differential expansion between the part and vessel shell.
4.15 Internal non-pressure piping for carbon steel vessels shall be fabricated either from seamless
or ERW pipes extra heavy as indicated in the drawings.
4.16 Unless stated otherwise on vessel drawing, baffles or weir plates shall not be welded directly
to the shell (or head) of vessels, but shall be bolted to support attachment, which are welded to
the shell.
4.17 Whenever a dished end is made of more than two plates it must have a crown plate.
Whenever a nozzle or manhole is positioned at the centre of the dished end, the crown plate
should be larger than the nozzle / manhole reinforcing pad.
4.18 Manholes shall be a minimum of 600 mm nominal diameter unless otherwise specified.
4.19 Manhole cover shall be provided with a davit or hinge as per standard code unless otherwise
stated in the drawing.
4.20 Inside edge of manholes shall be smooth and rounded off with a radius of 3 mm.
4.21 Vessels shall be heat treated when specified on the drawing. In no case shall the heat
treatment performed be less than that specified by the code.
Page 5
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
4.22 While heat-treating the materials, the fire and flame shall not contact the metal directly and the
heating on all the metal part shall be uniform.
4.23 For vessels handling hydrogen sulphide, amines, caustics or other fluids, which cause hydrogen
penetration, the annular space between welds on slip on flanges shall be vented to the
atmosphere by using a 6 mm dia hole.
4.24 For hot working, the most suitable working temperature for each material shall be
maintained strictly. Metalworking shall be made by cold working as far as practicable unless
otherwise specified. Hot working shall be made at a temperature within the range of 850 C 950
C and the heat treatments as specified in UHA-105 for austenitic steels & UCS-56 for carbon
steels as per ASME Section VIII Div.1 shall be made after hot working.
4.25 All flange faces shall be suitably protected against, during heat treatment.
4.26 All vessels, which are stress relieved, shall have all attachments including insulations, support
rings, welded prior to stress relieving.
4.27 If ring flanges are fabricated by butt-welding plate segments, the joints shall be fully heat
treated and tested ultrasonically. All shell flanges shall have their gasket faces machined
after welding and heat treatment.
4.28 The maximum allowable gap between nozzles and manhole reinforcing pads and the curvature
of the vessel shell or heads shall be 3 mm.
4.29 All nut sealing faces on flanges shall be either spot faced or machined.
4.30 All bolt holes shall straddle to the principal centre lines of the equipment for nozzles.
4.31 All flange facing when specified, as R.F. shall be serrated 0.5 mm deep and 0.8 mm wide over
gasket sealing surface.
4.32 All reinforcement pads / body flanges shall have two dia telltale holes 180o apart.
4.33 All internal weld seams for lined vessels shall be ground flush. Others shall be dressed and
finished smooth.
4.34 Stainless Steel surface shall be acid pickled and passivated in accordance with IBIC Standard.
4.35 All the internals shall be supplied and installed by the Fabricator unless otherwise stated
on the vessel drawing.
5.1 Purchaser or Third party shall carry out stage-wise inspection as mentioned in the equipment
data sheet. Inspection shall be carried out as per IBIC Standard and the applicable code.
5.2 Approval of work by the inspection agency or the release of vessels for shipment shall in no way
release or relieve the manufacturer of any responsibility for carrying out all the work as per the
data sheet / specifications.
5.3 The extent of radiography shall be as specified on the data sheets. In no case shall the
Page 6
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
5.4 Testing of the vessels shall be done as per the code requirements / IBIC Standard.
5.5 All nozzle-reinforcing plates shall be tested at 1 kg/Cm2 (g) with soap solution pneumatically.
5.6 If any structure or part of a structure were found not to comply with any of the provisions of this
standard, it shall be liable to rejection. No structure or part of structure once rejected shall be
accepted for re-test except in cases where it is considered that the defect is rectifiable.
5.7 Defects that may appear during fabrication shall be made good with the prior approval of IBIC.
5.8 Purchasers Inspector shall have the right to pass upon the qualification of erection personnel
engaged by the erector and shall ask for replacement if desirable.
5.9 Material damaged by defective workmanship or otherwise defective shall be rejected. The
Inspector in such cases shall ask the erector to furnish new material or correct defective
workmanship and/or replace workmen engaged in the work.
5.10 All leaks detected during testing shall be repaired to the satisfaction of Purchasers Inspector and
on completion the entire tank shall be right and free from leaks.
5.11 Lined vessels shall be inspected before lining is applied and again after installation of lining.
5.12 Dimensional tolerance shall be strictly as per Purchasers Standard and applicable codes.
6.0 PAINTING
6.1 Carbon steel vessels shall be thoroughly cleaned and shall be applied with two coats of protective
primer as per IS 2074 after inspection and testing and greased on exposed machined parts to
prevent rust, corrosion or damage due to bad weather.
7.1 All parts not assembled integral with the main body of the equipment shall be marked with the
order number and equipment number for their identification.
7.2 Vessels shall be identified by a nameplate as per IBIC Standard and shall be of stainless steel (300
series) or cast corrosion resistant material. The nameplate shall be attached near to the manhole
or a place where it is readily visible.
7.3 All internals shall be suitably supported from inside to prevent damage during transit.
7.4 All openings shall be blanked with wooden covers fastened with wires and welds end to be
closed with wooden plugs before dispatch.
Page 7
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
8.0 DOCUMENTATION
8.1 Fabricator shall forward the necessary documents as specified in the Annexure-1 Sheet
attached herewith.
Sr.
Reference Doc. No Description
No
1 ENGINEERING STANDARD FOR INSPECTION & TEST OF
ANNEXURE-2
PRESSURE VESSELS
10.0 GUARANTEE
10.1 The tank shall be guaranteed in accordance with the conditions given in the General
Conditions of Contract.
10.2 Any part of the tank found defective during the tests after installation or during operation, and
not having been submitted to faulty operation or incorrect service conditions, shall be
promptly replaced and re-assembled by the Contractor at his own cost.
Page 8
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
ANNEXURE-1
GENERAL INSTRUCTIONS
Page 9
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
1.0 Unpriced Bids and Technical parameters should be sent to M/s. IBIC office strictly on due date given in
enquiry.
2.0 Acceptance of L.D / Penalty clause wherever applicable should be incorporated as per enquiry
specifications in the Bid.
3.0 The Vendor should quote with respect to the specifications given. Any deviations with respect to the
Materials of Construction and process required will be discussed at the time of technical discussion. This
will ensure that there is no delay in sending the technical / commercial BIDs.
4.0 The Vendor can however mention their scope of supply wherever deviations along with the BIDs.
5.0 Raw material procurement status to be immediately furnished to IBIC / CLIENT office at the time of
receipt of LOI / Purchase Order within one / two weeks.
6.0 Design calculations and drawings should be sent to IBIC / CLIENT office for approval within two weeks of
receipt of LOI / Purchase Order.
7.0 Supply of required drawings and documents is the responsibility of the vendor. In the event of vendor's
failure to meet this requirement of submission of drawing and documents, the supply shall be considered
as incomplete and the purchase order is liable to be cancelled.
8.0 All drawings and documents shall show equipment number, order number, vendor's own title / reference
number / drawing number and revision number on the lower side of right hand corner in each drawing.
The first drawing shall have revision number as R0' and subsequently, First revision shall be mark as R1.
9.0 Fold all prints to A4 size and roll the transparencies. All documents shall be supplied in folders / files.
10.0 Vendor shall make drawings to maximum size A1 only. Vendor shall avoid preparing drawing an A0 size
due to handling problem.
11.0 Drawing or data returned, to be resubmitted within one week. Revised drawings and data must be
marked on the drawing.
12.0 The drawings which are returned to the vendor Without Comments, Vendor shall prepare and submit
three sets of final Assembly / detailed drawings to M/s. IBIC.
13.0 Within one week of shipment of each item vendor shall submit all drawings connected to it marked as
CERTIFIED AS BUILT DRAWING.
15.0 Duly filled Material Chart must be sent to IBIC / CLIENT office after drawing approval within seven days. A
format of MATERIAL chart will be sent along with the enquiry.
Page 10
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
16.0 Quality Assurance plan, Bar Chart of welding procedure specification wherever applicable to be sent to
IBIC / CLIENT office within two weeks of receipt of LOI / Purchase Order. All document drawings
approval will be given on a specified date intimated by M/s IBIC / CLIENT.
17.0 Procurement action of castings, forgings should be done by the Vendor wherever applicable immediately
after receipt of LOI / Purchase Order. Unpriced Purchase Order copies of all Bought Out items should be
sent by Vendor to IBIC / CLIENTs office immediately on placing the order.
18.0 For items like Gasket, Nuts & Bolts, Seal, Special Welding Rods, Gases and other required items Vendor
shall ensure that adequate stock is available. In case of delay, adequate action is to be initiated by the
vendor. The same is to be intimated to IBIC / CLIENTs office.
19.0 Prior approval of all Sub-vendors is to be obtained from IBIC / CLIENT at the time of Technical
Discussion, also sub-vendors list with contact person details (name, telephone etc) to be furnished to
IBIC during discussion.
20.0 Detailed progress report of the equipment order to be given to IBIC / CLIENT indicating the actual status
of the job to be submitted every fortnight.
21.0 Status pertaining to the job ordered should be available with at least two persons in the vendors shop
and contact persons name and telephone no., to be given at the time of Technical Discussion / Receipt of
LOI / Purchase Order.
22.0 Inspection call to be given in advance of a fortnight, after ensuring them the job is complete in all
respect.
23.0 Inspection will be carried out as per approved Quality Assurance plan. All internal check testing Report,
Radiographic, and other related certificates should be made available to IBIC / CLIENT pertaining to the
job by the Vendor.
24.0 Material test certificates should be furnished & given to IBIC / CLIENT representative at the time or
inspection. Check testing of main items to be carried out apart from mill test certificate.
25.0 Raw Material inspection at sub-vendor's workshop is solely the responsibility of the Vendor. IBIC / CLIENT
representative reserves the right to inspect the material at sub- vendors workshop.
26.0 All Final Revised drawings incorporating all comments made by IBIC should be received at IBIC
before final inspection.
28.0 Material Release Order once released by M/s. IBIC, the items furnishing in M.R.O. should be dispatched
immediately to Clients works without any delay.
29.0 A copy of dispatch Detail should be sent to M/s. IBIC office by fax immediately after dispatch.
30.0 The vendor has to submit acknowledgement receipt for all documents to the CLIENT, in order to receive
certificate from IBIC.
Page 11
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
Page 12
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
ANNEXURE-2
Page 13
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
1.0 GENERAL
1.1 SCOPE
This standard gives the guidelines to shop inspection and testing of pressure vessels,
shell and tube type heat exchangers etc. (generally referred as vessels henceforth)
fabricated accordance with Purchaser's design, drawings and standards carried out by
fabricator.
Specific job requirements, if any shall be provided separately and shall over rule any
contradictions.
The codes and standards shall be referred as needed, supplemented by this standard.
1.4.1 The inspection and testing shall be in accordance with the IBIC Specification and drawings
and fabricator's drawings or procedures as approved by Purchaser.
1.4.2 If there is any conflict, the same shall be brought to IBICs attention.
All the tests shall be performed according to the written and approved procedures only.
1.6 WITNESSING
1.6.2 Witness shall be either Purchasers Inspector or their designated representative & CCOE
authority.
1.6.3 At any time during fabrication is underway, Purchaser's Inspector shall have free access
to any of the fabricator's shop concerned with the fabrication of the vessels.
1.6.4 Fabricator shall provide necessary facilities to satisfy the Purchaser's Inspector that the
vessels are being furnished in accordance with the specifications.
1.6.5 The fabricator and the Purchasers shall reach into an agreement about the methods of
inspection and items to be witnessed.
1.7.1 All inspections and tests specified shall be carried out by the fabricator and shall keep all
the records of all the tests and inspections and the same shall be submitted to the
Purchaser for approval.
1.7.2 Witnessing by Purchaser's Inspector shall in no way relieve fabricator from his
Page 14
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
2.1 Fabricator shall submit to Purchaser the following records for each vessel.
d) Test procedures.
i) Dimensional Inspection.
2.2 The fabricator shall use the inspection formats provided by the Purchaser, if not, the fabricator
shall get their formats approved by the Purchaser
3.1 The inspection and test of vessel shall be done as specified in the design data sheets, code and
standards. Refer to Inspection programme and Inspection Chart also.
3.2 Inspection and test items specified in the codes and standards shall govern where applicable.
Page 15
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
4.1.1 Fabricator shall submit the mill test certificates and Laboratory test certificates of
Laboratories recognized by Lloyds or Bureau Veritas for the following: (Refer SA-370 of
ASME Sec. II).
4.1.2 Impact tests shall be done for materials for low temperature service. Refer sections 19 to
28 of SA 370 of ASME Sec. II Part A.
4.1.3 Repairs if any shall only be done with the concurrence of the Purchasers Inspector.
4.1.4 Welding Procedure qualification and welder or welding operators qualification shall be
done according to ASME Sec. IX.
4.1.5 Production weld test shall be done for all vessels in accordance with the standards and
codes .
4.1.6 Welded joint category shall be according to the code as in UW-3 of ASME Section
VIII Div. 1.
4.1.7 The following items shall be checked before starting off with production welding.
4.1.9 Plate edge alignment tolerance shall be generally taken, as t/4 for low thicknesses up to
20 mm and for thickness above 20 mm shall be t/8. But the maximum permissible
tolerance for circumferential joint shall be 3 mm and for longitudinal joint shall be 5 mm.
4.1.10 Welding procedure, welding rod (specification and make), baking temperature and time
of electrode if any, preheat temperature, welding machines, other welding
consumables etc.
4.1.11 Root run shall be cleaned and inspected by liquid penetrant method.
4.1.12 Any cracks or slag inclusions shall not be found in the welding passes.
4.1.13 Defects that are to be looked out in visual inspection in the finished weldment and their
acceptability.
Page 16
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
g) Add welding.
Insufficient toe length of fillet weld
h) Crater To be removed
4.1.14 Other internal defects detectable by non-destructive testing methods other than visual:
a) Not acceptable
Lack of root penetration
b) Lack of root fusion Not acceptable
c) Not acceptable
Cracks
d) Slag inclusion According to the codes
Page 17
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
4.7.3 The vessel and its parts to be assembled at the job site shall be temporarily assembled
and checked, where necessary, at the fabricator's shop.
4.7.4 Nozzles and other fittings of vessels shall be checked for direction and orientation.
4.8.1 Dimensions of the vessel and its parts shall be checked to meet IBIC data sheets,
drawings and specifications.
4.8.2 Dimensional tolerances for columns and vessels shall be as per tolerance for pressure
vessel specifications IBIC/ME 005 attached.
4.8.4 The inside diameter shall be measured at four or more positions for each section at a
distance of about 100 mm from each side of circumferential welded seam.
4.9.1 Radiographic examination shall be done when specified in the design data sheets
according to UW51 and UW 52 of ASME Sec. VIII Div.1.
4.9.3 When spot radiography is specified, at least one spot for each welded seam and every
cross-longitudinal to circumferential weldment shall be examined.
4.9.4 Acceptance Standard shall be according to code - Refer UW51 (b) and UW52 (d) of ASME
Sec. VIII Div.1.
4.10.1 Ultrasonic Testing shall be done according to UW53 of ASME Sec. VIII div.1, when
specified in the design data sheets.
4.10.2 Generally all the critical joints shall be ultrasonically tested in addition to radiography
especially for vessels for lethal use.
4.10.3 Acceptance shall be according to Appendix 12 of ASME Sec. VIII Div I, if not specified
otherwise.
Page 18
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
4.11.1 Both magnetic particle and liquid penetration testing shall be done according to the
codes and design data sheets.
4.11.2 Root of all butt welds shall be checked using liquid penetration method.
4.11.3 All finished welds shall be checked with magnetic particle testing / liquid penetrant
testing.
4.11.4 All bent and formed elements of the vessel shall be inspected using either magnetic
particle or liquid penetration testing.
4.11.5 Solvent washable fluorescent dye shall be used in checking elements of vessels designed
for high pressure.
4.12.1 Hydrostatic test shall be done according to UG-99 of ASME Sec. VIII Div. 1 when specified
in the design data sheets.
4.12.2 Pneumatic test shall be done according to UG-100 of ASME Sec. VIII Div.1 when specified
in the design data sheets.
4.13.1 Leak Testing shall be performed according to Article 10 of ASME Sec. V, when specified in
the design data sheets.
4.13.2 When leak test using Freon-12 gas and halogen detectors are specified, shall be
performed according to IBIC engineering standard for leak testing using Freon- 12.
4.14.1 Other tests like Ferrite Test, Micro Test, Macro Test, IGC Test, etc shall be done as and
when the same is specified in the data sheets or as per Codes and Standards.
5.1.1 Preheating shall be done wherever and whenever specified - Refer Table T1.
5.1.2 Preheat temperature shall be checked before commencing the welding using
temperature pencils or chalks.
5.2.1 Post weld heat treatment shall be done as per the design data sheets. Ref. Table T2.
5.2.2 Fabricator shall submit the time-temperature chart of post weld heat treatment.
5.2.3 As far as possible, welding on the vessels shall be avoided after heat treatment.
Page 19
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
Passivation / Pickling shall be done as per Standards, if required, as per data sheets.
7.0 RECORDS
7.1 Fabricator shall maintain test certificates, inspection reports, test reports, post weld heat
treatment report etc.
7.2 Fabricator shall submit all the records concerning the vessel for the purchaser's approval.
8.0 MARKING
9.0 PAINTING
9.1 Painting and Stenciling shall be done in accordance with the specification and drawings.
10.0 DESPATCH
10.1 The Fabricator shall get the final Inspection Report and Release Note from the concerned
Inspector before dispatch.
10.2 Make sure that the internal and external surfaces of vessel are free from loose scale or any other
foreign material.
10.3 All exposed machined surfaces shall be coated with removable rust preventive and be protected
against mechanical damage.
10.4 Nozzles shall be protected with bolted wooden covers and all threaded connections are to be
suitably plugged.
10.5 All parts not assembled integral with main body of the vessel shall be marked with equipment no.
and match marked to ensure proper fit-up.
Page 20
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
TABLE T1
PREHEAT REQUIREMENTS
Pre-heating is needed if the values of the variables
listed are more than the values given. Temp. in
Sr. P.No./ Group No.
No. Thickness of joint Tensile C.
Content Specified
mm strength ksi
3 3/1,2,3 16 70 79
5 4/1,2 13 60 121
9 6/1,2,3 204
10 7/1,2 None
11 8/1,2 None
12 9A/1 121
13 9B/1 149
Page 21
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
19 11A/4 121
TABLE T2
POST WELD HEAT TREATMENT
50 mm 50 mm
50 mm 50 mm
5 Hrs + 15 min
1hr/ 25mm for each additional
4 4/1, 2 650 1 Hr/ 25 mm
15 min minimum 25 mm over
125 mm
5 Hrs + 15 min
1hr/ 25mm for each additional
5 5A/1, 5B/1 675 1 Hr/ 25 mm
15 min minimum 25 mm over
& 5C/1
125 mm
Page 22
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
5 Hrs + 15 min
1hr/ 25mm for each additional
6 5B/2 705 1 Hr/ 25 mm
15 min minimum 25 mm over
125 mm
10C/1 &
10 540 1hr.min. + 15min/25 mm for thk. over 25mm
10F/1
Page 23
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
ANNEXURE-3
Page 24
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
6.0 Checking of long seam set up, profile and root matching.
8.0 Back chip and welding, profile check and radiography of long seam.
10.0 Welding circumferential seam of shell-to-shell, back chip and DP test, RT etc.
16.0 Welding of above mentioned, back chip and NDT (DPT / RT).
17.0 Inspection of welding of lugs, earthing boss, cleats, lifting hooks, name plate bracket and touch up.
Page 25
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
ANNEXURE-3A
Page 26
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
PROJECT:
RADIOGRAPHIC TEST
CHEMICAL ANALYSIS
DESCRIPTION:
VISUAL INSPECTION
HYDROSTATIC TEST
ULTRASONIC TEST
PNEUMATIC TEST
HARDNESS TEST
FERRITE TEST
IMPACT TEST
MACRO TEST
* IGC TEST *
MICRO TEST
LEAK TEST
REMARKS
ENQ. NO:
PART /
MATERIAL /
STAGE
SHELL DISH
END
MATERIAL.
R. F PLATE +
PAD PLATE
MATL.
NOZZLE PIPE
+ FLANGE
MATL.
TRAY/INTERN
ALS/ MATL.
LUGS, CLEATS,
LIFTING
HOOKS
STIFFENERS &
NAME PLATE
etc.
PROFILE AND
SET UP
WELDING
FASTENERS
GASKETS
HEAT AS PER STANDARD CODE
TREATMENT
FINAL
INSPECTION
Page 27
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
ANNEXURE-4
Page 28
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
Over 2700 8
2.0 Distance between top and bottom tangent line 1.5mm/m height, max. 12 mm.
6.0 Alignment of flange face of nozzle shall be as given in table (Refer detail A in attached drawing).
7.0 Rotation of flange holes with reference to nozzle axis 1.5 mm max (Refer detail A in the attached
drawing).
9.0 Alignment for flange face of manhole shall be 9 mm in both vertical & transverse planes.
12.0 Bottom of skirt base ring to the bottom tangent line of vessel + 0, -6 mm.
15.0 Distances of bolt holes from axis: up to 2000 dia. 3mm and for over 2000 dia 6 mm.
Page 29
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
21.0 Location of external clips and attachments from reference line 6 mm.
23.0 For nozzles located in heads distance from flange face of nozzle to reference plane shall be within
6 mm.
24.0 Bolt hole circle tolerance shall be
25.0 Height of weir above tray measured to the bottom of notches in notched weir within 1.5 mm.
27.0 Maximum lateral translation of nozzle or any other attachment max. 3 mm.
28.0 Down comer horizontal clearance measured from bottom edge of the down cover to seal pan or
inlet weir within 3 mm.
Tray Dia. (mm) Max. Diff. Between high and low points (mm)
Below 900 3
Over 1500 6
Page 30
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
27
THIS DIMENSION TO BE
FINALLY ADJUSTED TO
SUIT TOTAL HEIGHT
T.T.L.
1 23
22
10
6 10
3 31
29
30 9
21
5
4
26
2 5 17
28 20
6 25
7
12
4
14
8
9 19
24 BASE LINE
22
10
2
17 18
11
TOLERANCE FOR HORIZONTAL VESSEL
REF.L.
23
12
MAX
2
13
16 S . MAX
NOMINAL NOZZLE S.MAX
BASE- DETAIL -'A'
LINE 50-100 INCLUSIVE 1.5
15 150-300 INCLUSIVE 2.5
OVER 300 5
= =
PLUMB LINE
14
14
NOTES:
Page 31
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
ANNEXURE-5
Page 32
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
1.0 GENERAL
1.1 Material Design, Construction and Inspection shall be in accordance with Chapter XV of IBR.
1.2 Fabricator shall obtain approval of design calculations and fabrication drawings from IBR
authority.
1.3 This Vessels shall be designed as Class 1 vessels with efficiency of fusion welded shell, E=0.9.
1.4 Non-destructive testing shall be as per IBR Reg. 265 and 561. Certificates of manufacture & test
in required forms signed by the maker and IBR inspector shall be obtained for all materials prior
to fabrication.
1.5 All the plates used in fabrication shall be fully killed type and shall be the requirements in Chapter
II of IBR.
1.6 Carbon content shall not be more than the limit specified in Reg. 234(a) of IBR.
1.8 After completion of welding but before Hydro test, heat treatment shall be carried out as per
Reg. 267 of IBR.
1.9 General requirements of construction shall be met in accordance with Reg. 266 of IBR.
1.10 All dimensional tolerance for tubes and plates shall be as per regulations in IBR.
1.11 Method of making weld joints, mechanical fittings etc. shall be as per Chap. V & XII of IBR.
1.14 Inspection of the vessel shall be carried out by IBR / Purchaser. Fabricator on required forms as
per IBR code shall obtain stage wise and final inspection/ Approval from IBR authority.
1.15 Tube sheet shall be from forged material, and the same shall be ultrasonically tested.
1.16 Girth / body flange material shall be tested ultrasonically and by 100% radiography.
1.17 All flanges and tube sheets shall be LP tested after machining. Also all root run and fillet welds
shall be LP tested.
1.18 All flange facing shall be of smooth finish, where gaskets are of SS wound type and glass filled
PTFE.
1.19 All the tubes shall be tested by Eddy Current Testing method as per ASTM/ASME Specifications.
1.20 All tubes shall be hydro tested after bending and bend portion shall be tested using PT.
1.21 Hydro testing shall be carried out by the fabricator as per Reg.601 of IBR.
Page 33
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
ANNEXURE-6
Page 34
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
1.0 SCOPE
To provide guidelines towards achieving better quality in fabrication of Vessels, Heat Exchangers or
Storage tanks.
2.0 GENERAL
2.1 The fabricator should make sure that they have understood the design and requirements
properly and if there is any doubt, the same shall be cleared beforehand. Equipment data
sheet shall be referred along with this QA plan.
2.2 No deviation from drawings / standards shall be permitted without written approval by the
Purchaser.
2.3 Fabricator can in general refer to ASME Sec. VIII Div.1, ASME Sec V, ASME Sec II, ASME Sec IX,
TEMA, IS 803 and API 650 as applicable for the fabrication, inspection and testing.
3.0 MATERIAL
3.1 All the materials of construction should be strictly in accordance with the purchasers
drawings and specifications. Alternative materials shall be used only on written approval
by the purchaser.
3.2 The Fabricator should provide proper evidence to prove that the materials used in
fabrication are according to approved drawings and specifications and are acceptable.
3.2.1 Fabricator should submit Mill test certificate for the materials in their scope and
supply for both physical and chemical properties and also get the materials tested
for the same by a reputed laboratory approved by Lloyds or Bureau Veritas and
submit the certificate for the Purchasers approval.
3.2.2 All the materials if specified should be inspected and certified by a qualified
inspector using non- destructive testing methods as per ASME Sec.V and Sec. II.
General Ref: UW-26 to UW-42, UG-75 to UG-85, UG-90 to UG-103 and UW-11, UW-46 to UW-53. IS 803,
API 650.
4.1 The Fabricator shall furnish fabrication procedure / fabrication drawings for Purchaser's
approval.
4.2 All weld joints circumferential and longitudinal shall be marked on drawing. All longitudinal
Page 35
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
4.3 For fabrication tolerance, Fabricator can refer to TEMA F1, F2 & F3 for heat exchangers; for
vessels, fabricator can refer to the tolerance specification sheets attached to data sheets and API
650 or IS 803 for storage tanks.
4.4 Fabricator shall use electrodes of reputed brand names only and get the same approved
from Purchaser before beginning with any production welding.
4.5
4.5.1 It is advisable to make part drawings and get it approved if necessary.
4.5.2 Fabricator should prepare cutting diagrams for the materials for Purchasers
approval.
4.5.3 Markings on the plates etc are to be checked and get it approved.
4.5.4 The part identification should be punched before cutting - Plate identification,
Drg. No., Part No. refer to UG-77.
4.5.5 Cutting process should be referred to UG-76 and should also note that SS Plates
should either be sheared off or cut off by plasma arc.
4.5.6 Fabricator should make the welded connections with reference to UW-15 to UW-
19 and UW-27.
4.5.7 All precautions shall be taken to avoid distortion (use jigs, fixtures etc.).
4.6 The fit up at various stages shall be made in tack-welded condition and get the same
approved by the Purchasers Inspector. Ref: UG-94 to UG-97 & UW-31 to UW-33.
4.7
4.7.1 Fabricator shall use qualified and approved welding procedure and qualified
welders or welding operators. Also Fabricator should get the welders qualified
for tube-to-tube sheet joints separately. Refer: UW-27 to UW-29.
4.7.2 The weldment should be done with reference to UW- 35 to UW-39.
4.7.3 Non-destructive testing methods are to be employed for the inspection of
weldment with reference to UG-103, UW-11, and UW-51 to UW-53 and in
accordance with ASME Sec. V as indicated in data sheets.
4.7.4 Make repairs if any with Inspectors concurrence and get it retested. Ref UW-38.
4.8 Formed ends of vessels preferably be made in one piece. Larger heads which cannot be formed
in one piece shall be fabricated as follows:
4.8.1 In two pieces, with welding seam included in the middle third and preferably on
the central line.
4.8.2 In petal construction, with meridianal seams and central cap of diameter not
larger than 0.75 times the vessel OD.
4.9 As far as practicable, the shell sections shall be made out of a single plate with one
longitudinal weld seam only. The longitudinal seams of adjacent courses shall be
Page 36
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
staggered and, as far as possible, seams shall be positioned clear of supports / nozzles, so
as to be readily accessible for examination. Ref. UG-79.
4.10 Nozzles shall be located, as far as possible, clear of longitudinal weld joints. Where this cannot
be avoided, Purchasers prior approval shall be obtained, since increase of reinforcement
may be necessary.
4.11 All longitudinal and circumferential shell joints shall be full penetration double-welded butt
joints. The reverse side shall be welded after chipping, grinding or gouging out the rest of
first side to sound metal. Where sound back welding is not feasible, single welded joints with
backing strips or rings shall be used. Alternatively, root run shall be done with TIG or MIG welding
process to ensure proper penetration.
4.12
4.12.1 The Fabricator should get the stage wise and final inspection done to ensure the
dimensional accuracy and quality of workmanship - Ref: UG-84 to UG-90.
4.12.2 The Fabricator should get the equipments tested using hydro test / pneumatic
and leak tests as per data sheets. Refer UG-99 & UG-100 and Section V.
4.12.3 For storage tanks in addition to all the testing methods mentioned above, testing
with reference to API Standard 650 - 5.3.3 to 5.3.7 and Article 10 of ASME section
V shall be done.
Post weld heat treatment of the weldments should be done as per UW-40 and time temperature chart
should be submitted for Purchasers approval.
6.2 Formats for inspection reports should be same as that provided by the Purchaser or the
Fabricator should get their own alternative format approved from the Purchaser.
7.1 Make sure that the internal and external surfaces of vessel are free from loose scale or any
other foreign material.
7.1.1 All exposed machined surfaces shall be coated with removable rust preventive
and be protected against mechanical damage.
7.1.2 Nozzles shall be protected with bolted wooden covers and all threaded
connections are to be suitably plugged.
7.2 All parts not assembled integral with main body of the vessel shall be marked with
equipment number and match marked to ensure proper fit-up.
Page 37
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
ANNEXURE-7
Page 38
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
Page 40
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
ANNEXURE-8
Page 41
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
1.0 GENERAL
1.1 This specification covers requirements for cleaning, pickling and passivating all stainless
steel process equipment constructed of alloys containing more than 12% Cr.
1.2 In case of equipment / piping assemblies subjected to post weld heat treatment the
whole surface shall be given the pickling treatment. Otherwise, only the weld joints and
sealed surfaces are to be pickled. Passivation shall be the last operation before
equipment / piping is put into service after testing.
1.3 The pickling and passivating solutions shall not be allowed to contact ferrous surfaces
containing less than 12% Cr. or any non-ferrous surfaces.
2.0 PROCEDURES
2.1 Cleaning
2.1.1 All welding flux and weld spatter shall be removed by grinding or blasting.
2.1.2 All dirt, cinders, fly-ash or other extraneous matter shall be removed by brushing
with a hard fiber brush or stainless steel wire brush. Carbon steel wire brush
shall not be used.
2.1.3 All organic materials, paint, crayon marks, soaps, oils or grease shall be removed
by washing with any commercial paint remover (those containing HCl or H2SO4
are not permitted) light solvent naphtha, di-chlorcethane or benzene. Soap
solutions or similar detergents may also be used. Motor Petrol shall not be used.
2.2 Pickling
2.2.2 The material shall be exposed to the pickling solution only to an extent just
necessary and sufficient to remove residual scale. The maximum period for which
the pickling solution shall be allowed to remain on the surface is 30 minutes.
During pickling, the removal of the oxides may be hastened by brushing with a
hard fiber or S.S. wire brush together with clean sand. The pickling agent shall
finally be washed off with plenty of water so as to leave no trace behind.
2.3 Passivating
Page 42
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
2.3.2 Tanks, pipelines and other equipments shall be filled with the solution. Small
parts shall be immersed in a tank containing this solution. The solution shall be
held in the equipment for:
a) At least 24 hours at 25 C
Temperature Duration
35 C 15 hours
50 C 8 hours
65 C 4 hours
80 C 2 hours
2.4 Rinsing
Finally the surface shall be thoroughly washed with a jet of water. Rubbing and
brushing are prohibited during and after Passivation. Water used for rinsing shall
contain no more than 1-ppm chloride.
3.0 INSPECTION
3.2.2 The free iron test shall be used on accessible parts of the equipment to
avoid further contamination, unless the inspector has reasons to believe
failure has occurred on some inaccessible surfaces.
Page 43
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
3.2.5 The solution shall be mixed within 24 hours on use and shall be applied
by brush or spray on test area. Blood red color indicates presence of free
iron and equipment must be rejected. Light pink color is acceptable.
Page 44
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
ANNEXURE-9
Page 45
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
Page 46
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
WELDING NECK
When O. D is 24" or Less 1/16"*
Outside diameter
When O. D. is above 24" 1/8"*
10" and Smaller 1/32"
Inside Diameter 12" thru 18" 1/16"
20" and above + 1/8", -1/16"
1/16" Raised face 1/32"
Diameter of contact Face " Raised face Tongue & Groove
1/64"
Male, Female
When "X" is 24" or Smaller 1/16" *
Diameter of Hub at base (X)
When "X" is 24" & above 1/8 *
5" and Smaller + 3/32", -1/32"
Diameter Hub at point of Welding
6" & Larger + 5/32", - 1/32"
Bolt Circle diameter
1/16"
(1/2"- 24")
Bolt hole spacing 1/32"
Drilling
Eccentricity of bolt circle with respect to facing
2 and smaller 1/32" Max.
3 and larger 1/16" Max.
Eccentricity of bolt circle with
1/32 Max. *
respect to bore
Eccentricity of facing with respect
1/32 Max. *
to bore
18" and Smaller + 1/8", -0"
Flange Thickness
Over 18" + 3/16", -0"
10" and Smaller 1/16"
Overall length Through Hub
12" and above 1/8"
Page 47
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
ANNEXURE-10
Page 48
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
1.0 SCOPE
This specification describes the various aspects of painting of pressure vessels and related structure. This
specification also covers and defines the material specification, surface preparation, application of paints,
inspection and test.
Note: Stainless Steel and other alloys, Plastic and Aluminium should not be painted.
Finish paint type: Rich Silicone Finish - thickness (dry) min 3 mils
3.1 Dressing
A careful dressing shall be carried out to eliminate all foreign materials, particularly glyceroids,
hydrocarbon such as grease, oil naphtha and similar substances from the surface required to be painted.
Dressing shall be carried out as follows:
Dry sand blasting shall be carried out by skilled personnel, approved by the Engineer-in- charge, on
external plate surface unless otherwise specified.
Before sand blasting all greasy substances shall be removed by means of adequate washing. The portion
that appears to be still greasy after the sand blasting shall be cleaned with solvents and re-blasted. The
sand blasting operation shall obtain surface of uniform grayish-white color. Sand blasted surface shall be
rough enough to obtain the best condition for applying primer.
Page 49
General Engineering Documentation
IBIC -400-SS-0002
Standard Specification
400 Equipment Engineering Rev R0
Standard Specification for Pressure vessels Date of Rev 19/05/2017
The surface examined under naked eye, should be free from corrosions, scales, oxide, paints, oil
and other undesirable foreign matters. The compressed air used shall be free from moisture, oil
and liquid vapors. Sand blasting shall be restricted to daytime only, however, night sand blasting
may be permitted with the approval of the Engineer-in-charge.
The sand blasting operation shall be suspended whenever the treated surface appears to
be humid or the relative humidity of the environment exceeds 80%.
The primer must be supplied on the sand blasted surface on the same day before sunset
and in any case before any oxidation occurs. Any surface where primer has not beenapplied
after sand blasting and consequently appears to the humid or oxidized will be blasted again.
Mechanical cleaning shall be carried out on external structure and all internal surfaces
by means of equipment approved by the Engineer-in-charge. This operation shall be
restricted to daytime only unless approved by the Engineer-in-charge. Painting shall be
carried out on the same day the cleaning operation takes place. The surface not
promptly painted will have to be brushed again if they appear to be humid or rusty.
Greasy substances will have to be removed by solvent before the mechanical cleaning
starts. Engineer-in-charge resolves the right to modify any procedures.
5.1. All consumables products such as paints, solvents, thinners etc. can be brought inside the
work site only when they are supplied in sealed containers, as dispatched from the
manufacturer. Specimen of such product shall be handed over to the Engineer-in-charge
and will be kept separately to carry out a comparison if so desired by the Engineer-in- charge.
5.2. If, in the opinion of the Engineer-in-charge any tests are to be conducted for the paints, the
Contractor at his own cost will carry out the tests.
Item to be
Final colour Munsel No RAL No
painted
Bare surfaces
Medium
Frame works 7.5G7/2 6021
green
STRUCTURAL STEEL
Medium
Platforms, stairs, floor plate, support 7.5G7/2 6021
green
Bare surfaces
Pumps,
MACHINERY
Page 51
General Engineering Documentation
IBIC-400-SS-0004
Standard Specification
400 Static equipment Engineering Rev. R0
Standard Specification for Storage tanks Date of Rev. 02/03/2017
STANDARD SPECIFICATION
FOR STORAGE TANKS
Table of Contents
1 Introduction 4
6 Completion time 10
7 Measurement of work 10
9 Documentation 11
10 Guarantee 11
11 Reference standards 11
13 Scope of inspection 13
1.0 Introduction
This Specification together with the data sheets / drawings covers the general requirements for materials,
design, fabrication, inspection, testing and erection of Storage tanks. The requirements laid down herein
are supplementary to the design/ fabrication code as specified.
2.1 Design, fabrication, erection, inspection and testing of the site fabricated tanks shall be
generally as per API 650 (Latest Edition).
2.2 Thicknesses indicated in the drawing are minimum. Thickness indicated shall not be the basis
of offer.
2.3 Thickness shall be rechecked by vendor based on actual design calculation without any
time/cost implication and submit the firm offer.
3.1 The scope of work mainly consists of Supply, Design, Engineering, fabrication, erection,
inspection, testing and painting of tanks as per API 650 and drawing furnished by IBIC.
Fabrication / Erection of structural work like spiral stair case, hand railing, pipe supports etc.
3.2 The design, engineering, supply, fabrication, erection, inspection, testing and
commissioning of CS/SS tanks as per following options.
3.3 The contractor shall submit the following drawings and documents for approval as per
plate sizes procured by CLIENT within two weeks from date of LOI for both potions.
3.5 Fabrication and erection of carbon steel structural such as platforms, ladders, gratings,
railing, supports, clamps, fasteners etc. as applicable.
3.6 Calibration of the tank shall be carried out through govt. agency as soon as the job is
completed and documents in original shall be submitted to CLIENT.
3.7 Supply, Fabrication, erection, welding and testing of SS/CS LP steam piping and tracers
under IBR as per EGD of IBIC. Vendor shall carry out approval of drawings under IBR
authorities, if required. Contractor shall deploy IBR welders for IBR piping.(Applicable for
IBR JOB)
3.8 The plate flanges/ RF pads etc. for nozzles and manhole shall be fabricated in one
piece as required from the plate material. Any other special items require to be
fabricated to complete the tank and its system shall be a part of contractor's scope.
3.9 Welder qualification test shall be arranged by the contractor for tank as well as piping at
CLIENT site under IBICs Inspection.
3.10 For tank, contractor shall submit PQR and WPS for IBIC/CLIENT approval.
3.11 Testing shall be as per quality control plan (QAP) approved by IBIC/CLIENT. This includes IGC
testing, radiography, DP Test, vacuum box test for the bottom joints of tank base plate,
pneumatic leak test for reinforcement pads, hydro test for the tank. Air/vacuum test for
the tank roof. Norms followed shall be as per API 650 & ANSI standards.
3.11 All the SS weld joints of tank shall be pickled /passivated by solution/paste recommended
by IBIC/CLIENT and it shall be arranged by contractor.
3.12 Contractor shall carry out above mentioned tests and arrangement at his own cost. The
rates shall be inclusive of such tests
3.13 Contractor shall make all arrangement for hydro test /water fill up test of the tanks/
piping system including fabrication and laying of temporary piping.
3.14 Handling of materials like plates, pipes, flanges, valves, fittings, fasteners, gaskets and all
other miscellaneous items etc. as per the job requirement from CLIENT or Contractors
stores to the contractors workshop or to the point of erection. All the excess material
after the job is over shall be returned to the place indicated by the engineer in charge for
material supplied by CLIENT.
3.15 The necessary equipments for loading, unloading, handling and erection of
tanks/piping/Structure materials shall be arranged by contractor at his cost.
3.16 The procurement and supply of consumable materials, construction, erection and testing
equipment required for the completion of work except the material specifically included
in CLIENTs scope of supply shall be the contractors responsibility. These items are as
under but not limited to them;
1) All consumables such as electrodes, filler wires, industrial gases for cutting and
welding, grinding wheels, DP solution, pickling/ Passivation solution/paste, etc.
2) Hydraulic jacking system for tank erection.
3) Structural gratings for stairs and platforms.
4) Steel scaffolding material and safety appliances require during execution of
job.
5) All tools, tackles, slings, chain pulley blocks, rolling machine, cutting machine,
cutting sets, plasma cutting sets, welding generators, grinding machines,
vacuum box, hydraulic pumps, pressure gages, dial gages, shims etc for
fabrication, welding, erection, testing, leveling and alignment.
6) Arrangement for radiography of tank/piping weld joints including required
material, dark room and radioactive source, IGC testing arrangement for test
coupons.
3.17 Contractor shall strictly adhere to labor laws, ISO 14001 & OHSAS18001 norms and Safety
Guidelines applicable for this job provided by CLIENT during execution. Safety appliances
like safety belts, safety helmets, safety goggles, gloves, shoes, asbestos sheets etc. to the
workers on job shall be provided by contractor. Execution shall be carried out on receipt
of work permit issued by shift-in-charge of plant and shall be get renewed in each shift.
3.18 The contractor within their quoted rates and time schedule shall make any alteration,
omission and/or modification as per the instructions of engineer in charge during site
execution.
3.19 Co-ordination with inspection department and keeping records of inspections reports shall
be contractors responsibility.
3.20 Area cleaning and removal of debris after the job is over shall be the responsibility of the
contractor.
3.21 Completing the entire job in all respect as per drawings, specifications and instructions of
engineer in charge and keeping the system ready in all respect for further commissioning.
3.22 Contractor shall submit material reconciliation statement after the job is over.
3.23 The Contractor other than specifically mentioned above, though required in order to
complete the jobs as per specifications in data sheet and Inspection Standards of IBIC shall
carry out all the works.
CLIENT shall supply the following materials/Services free of cost to the contractor.
4.1 The scope of work mainly consists of Supply, Design, Engineering, fabrication,
erection, inspection, testing and painting of tanks as per API 650 and drawing
furnished by IBIC. Fabrication / Erection of structural work like spiral stair case,
hand railing, pipe supports etc.
4.2 Civil foundations for tanks and footing for pipe supports.
4.3 Electrical power at one point in the area of prefabrication /at erection will be arranged by
client further distribution shall be done by contractor.
a) HRC type fuses with isolation switch for individual welding
machine.
b) Earth leakage circuit breaker (ELCB) for each machine with extension board.
c) For further distribution from single point, required standard quality cables in
single piece within 200 meter.
5.0 Fabrication involving welding shall not be sublet to others without the prior approval of
the engineer-in-charge.
5.1 Nozzle necks 10 and above shall be fabricated from plates and shall be 100%
radiographed.
5.2 The cleats shall not be welded with shell plates for fixing temporary gratings (jails) for
welders/fitters/workmen but scaffolding shall be made from bottom, as the tank material
is special IGC tested for SS tanks. Hydraulic jack system shall be used for tank shell course/
roof construction so that unwanted welding cleats and huge scaffolding can be avoided.
5.3 All welders shall be qualified as per the specification. Contractor shall indicate brand
names of electrodes and filler wires proposed for the entire job for the approval of IBIC.
No welding shall be carried out without the approval of IBIC/CLIENT Engineer in charge at
site.
5.4 Contractor shall carry out various tests as per QA plan approved by IBIC/CLIENT at his own
cost including any other test required to complete the job in all respect as per the code /
API650 requirements.
5.6 All the tests either on the field or at outside works/laboratories concerning the execution
of the work and supply of materials shall be carried out by the contractor at his own cost.
5.7 The contractor shall provide for the purpose of inspection, all facilities such as access
ladders, lighting, necessary instruments etc. at his own cost.
5.8 Weld joints to be radio graphed shall be identified by inspection engineer and extent of
radiography shall be as per tender terms & EGD.
5.9 Any work not conforming to the execution drawing, specifications or codes shall be rejected
forthwith and contractor shall carry out rectifications at his own cost.
5.10 All results of inspection and tests will be recorded in the inspection reports, Performa of
which will be approved by engineer-in-charge. These reports shall form part of the
completion documents.
5.11 Inspection, testing and acceptance of the work shall not relieve the contractor from any of
his responsibilities under this contract.
5.12 The fabrication procedure shall conform to all applicable requirements of specified code
and established engineering practices for manufacture of storage tanks.
5.13 Shell vertical joints in adjacent courses shall be staggered as per the code. The weld seam
shall be indicated in the fabrication / as built drawings.
5.14 All the nozzle openings shall be a minimum of 50 mm away from the weld joints. All the
nozzles and manhole projections shall be as per EGD.
5.15 Prior to welding, the edges of plates and adjoining surfaces for at least 25 mm on either
side shall be dry and free from oil, grease or scale or other deposit that may be
detrimental to weld quality.
5.16 Welding shall not be carried out when the surface of the any part to be welded is wet by
any cause for e.g. during periods of rain and high winds unless the welder and work are
properly shielded.
5.17 Tack welds shall be considered as having no strength and shall not be used for any
purpose except for holding of weldments in proper alignment.
5.18 All nozzle bolt holes shall straddle with principal centre line of Equipment.
5.19 All external and internal welds to be left ungrind but in decaled condition. (Respect to the
requirement)
5.20 Temporary attachment welds on Tanks shall be removed. The surface under such welds
and under backing rings, which have been removed, shall be properly conditioned to
eliminate surface stress raisers. LPT shall be carried out for grinded area.
5.21 Roof shall not have depressions that will permit accumulation of water.
5.22 All the internals shall be supplied and installed by the Fabricator unless otherwise stated
in the drawing / data sheets.
5.23 Suitable setting markers shall be provided on the tank shell before beginning of water fill
up/ Hydro test.
5.24 If any structure or part of a structure were found not complying with any of the provisions
of this standard, it shall be liable to rejection. No structure or part of structure once
rejected shall be accepted for re-test except in cases where it is considered that the defect
is rectifiable.
5.25 Defects that may appear during fabrication shall be repair with the prior approval of
Purchaser.
5.26 Purchasers Inspector shall have the right to pass upon the qualification of erection
personnel engaged by the erector and shall ask for replacement if desirable.
5.27 All erection lugs and cleats shall be removed before hydro-test for tanks fabricated at site.
5.28 All leaks detected during testing shall be repaired to the satisfaction of Purchasers
Inspector and on completion the entire tank shall be right and free from leaks.
5.29 STORAGE:
The plates shall normally be deposited and stored outside in such a way as to minimize
contamination and corrosion. The prescribed storage symbols shall be observed. Bent
plates shall be stored in a vertical position to avoid distortion. For plates stored in a
horizontal position, provisions shall be made for adequate supports. Plates shall always be
placed on timber under lays. When storing the plates, even temporarily, their unprotected
bare or machined surfaces must not touch the ground. In the event of prolonged storage
periods and/or extreme ambient conditions (high or low temperatures, corrosive
atmosphere), adequate protective measures shall be taken.
6.2 The contractor and engineer-in-charge will prepare a joint program of execution of
the work. The program will take into account the time of completion mentioned in
6.1 above.
6.3 Daily construction targets will be drawn up by the engineer-in-charge with the contractor.
The contractor shall scrupulously adhere to these targets and program and shall deploy
adequate personnel, arrange construction equipments and aids
6.4 Daily work progress report shall be submitted by site In charge to the Engineer-in-
charge
6.5 Liquidated damages as per general conditions of contract shall be levied in case of
delay in completion.
7.0 Measurement of work
7.2 Measurement of weights will be in metric tons corrected to the nearest kilogram
and will be made based on the execution drawings. All other measurements will be
as per the actual work executed at site.
7.3 Weld metal weight will not be taken into consideration for measurement.
7.5 The following scrap allowances by weight are permissible for plates and pipe material.
The percentage allowance shall be accounted on the basis of erected weights as per
execution drawing as below:
a) Salvage 1.5%
b) Unaccountable scrap 0.5%.
8.1 Surface preparation and painting shall be as per IBIC Standard. All external surfaces
of the tanks shall be painted with Protecto Mastic Primer (DFT 50 micron) after
inspection and testing, except gasket contact faces. Gasket contact faces and studs /
bolts shall be protected with rust preventive compound.
9.0 Documentation
Fabricator shall forward the necessary documents / drawings as specified in enquiry document
10.0 Guarantee
10.1 The tank shall be guaranteed in accordance with the conditions given in the General
Conditions of Contract.
10.2 Any part of the tank found defective during the tests after installation or during
operation, and not having been submitted to faulty operation or incorrect service
conditions, shall be promptly replaced and re-assembled by the Contractor at his
own cost.
For reference standard drawing refer IBIC-400-STD-01 for standard drawing details.
12.1 Prerequisites :
All welding operations, the prescribed examinations of welded joints, the prescribed heat
treatment operations as well as repair work, if any, must be completed. The anchor bolts
must have been grouted. Fabrication tolerances must have been checked (refer to 12.3.2).
Tanks shall be cleaned before testing. All welds shall be free of coating or insulation
materials. During the time of pressure and leakage testing, no work shall be performed on
the object being tested. Referring to tanks without bottom insulation, the vacuum test of
bottom joints shall be performed after the pressure or leakage testing. For tanks with
bottom insulation, the vacuum test shall be performed both before and after the pressure
or leakage testing. The partial vacuum shall be at least 0.5 bar. If the vacuum test
performed after the pressure test or leak test reveals any leaks, refilling of the tank (after
repair of the leak) is not required. The filling level prescribed for testing with water need
not be identical with the maximum filling level of the fluid to be stored. In no case shall the
water fill penetrate across the top line of the shell.
periphery of the foundation shall be marked before filling. The location of the reference
point outside the foundation shall be agreed upon with site management. For
extraordinary soil conditions, an expert shall be entrusted with the continual supervision
of settlement.
If the readings indicate differences in foundation settlement of more than 15mm (referred
to 10m) or uniform settlement of more than 10mm in 24 hours, filling operation shall be
interrupted. It shall be resumed only after close examination by an expert and with due
consideration to special regulations while the procedure is permanently being watched.
12.3 Leakage testing:
Atmospheric-pressure tanks intended for the storage of liquid shall be filled with water.
Tanks of carbon steel shall normally be filled with portable water containing less than 100
ppm of chloride ions. Referring to tanks of stainless steel, the water shall normally contain
less than 25 ppm of chloride ions. The quality of the water shall be evidenced by analyses.
Check analyses shall be made if water is reused. Deviation from the specified chloride ions
concentrations may be admitted, provided that the ordered prepares a technical
specification with detailed data for the specific case.
tanks wall and water fill has taken place. The water used for filling should have a
temperature of at least 15 C. Attention shall be given to the influence of the outside
temperature. Pressure and vacuum shall be measured with the aid of a U-tube
manometer designed for a sufficient measuring range. The filling with water to the
prescribed level shall be performed in accordance with 12.3.1. The nuts of the anchor
bolts shall be checked and shall be retightened, if necessary. Air may then gradually be
admitted to the free space above the water fill until the pressure has risen to 50% of the
allowable working pressure. Shell and roof shall be examined for any distortion. After this
examination, the pressure shall gradually be raised to 1.1 times the allowable working
pressure and shall be held for approximately one hour. The pressure rise in the free space
above the water fill may also be achieved by further gradual filling (approximately
0.1m/hr) if this method is permissible. If stipulated, all welds in the area above the water
level shall be examined with the aid of forming liquids. Upon completion of the pressure
tests, gradually venting the air and lowering the water level shall equalize the pressure.
After removal of the blind flange from the safety valve, each safety valve shall be tested
individually by restoring the pressure. If a vacuum test is also stipulated, the vacuum shall
be produced by gradually lowering the water level to the prescribed marks or to the relief
pressure setting of the safety valve.
13.0 Scope of inspection
13.1 Approval of design calculations, Fabrication drawings and plate cutout drawings for shell,
roof and bottom for compliance with relevant code requirements and General Engineering
Practice.
13.2 Witness of Material inspection and Identification.
13.3 Witness of ultrasonic testing for plate material to be used for fabrication work.
13.4 Verification of material test certificates of Chemical Analysis and Mechanical testing of
material. In case if certificates are not clear or there is any doubt, check testing of the
material from NABL approved laboratory without any extra cost.
13.5 Verification of IGC test certificates for SS material & collection of sample pieces as per the
requirement for Chemical, Physical and IGC testing in case of SS material.
13.6 Verification of reports of supplementary test on material as applicable.
13.7 Approval of Welding Procedures and witnessing of Procedure Qualification tests.
13.8 Witness and approval of qualification tests for welders as per qualified WPS.
13.9 Verification of welding consumables certificates and qualification for compliance to code
requirements.
13.10 Stage inspection during fabrication including checking of shell, roof, forging, alignment
and fit up checks, to comply with the code requirements. .
13.11 Witness NDT examinations as required.
13.12 Witness Mechanical testing on coupons tensile, impact etc. as applicable.
13.13 Verification of Calibration Records for M/c. and testing gauges.
13.14 Witness of Air Soap Bubble Test for R.F. Pads.
13.15 Carry out Visual and Dimensional Checks as per the requirements.
13.16 Witness Hydrostatic testing tank in vertical position.
13.17 Witness Vacuum leak test for roof and bottom of the tank.
13.18 Checking of Nameplate and final stamping as per code requirements.
13.19 Verification of pickling Passivation / painting inspection as applicable.
13.20 Calibration of all the tanks shall be carried out by the vendor as per IS2009 and IS2008
(latest edition) for tanks fabricated at site. All the liaison work including arranging the visit
and witnessing the strapping of work etc. with the competent authority, approving the
calibration charts shall be the vendors responsibility.
GENERAL INSTRUCTIONS
ANNEXURE-1
a) Unpriced Bids and Technical parameters should be sent to M/s. IBIC office strictly on due date given in
enquiry.
b) Acceptance of L.D./ Penalty clause wherever applicable should be incorporated as per enquiry
specifications in the Bid.
c) The Vendor should quote with respect to the specifications given. Any deviations with respect to the
Materials of Construction and process required will be discussed at the time of technical discussion. This
will ensure that there is no delay in sending the technical / commercial BIDs. The Vendor can however
mention their scope of supply wherever deviations along with the BIDs.
d) Raw material procurement status to be immediately furnished to IBIC / CLIENT office at the time of receipt
of LOI / Purchase Order within one / two weeks.
e) Design calculations and drawings should be sent to IBIC / CLIENT office for approval within two weeks of
receipt of LOI / Purchase Order.
f) All drawings and documents shall show equipment number, order number, vendor's own title / reference
number / drawing number and revision number on the lower side of right hand corner in each drawing.
The first drawing shall have revision number as R0' and subsequently, First revision shall be mark as R1.
g) Fold all prints to A4 size and roll the transparencies. All documents shall be supplied in folders / files.
i) Drawing or data returned, to be resubmitted within one week. Revised drawings and data must be marked
on the drawing.
j) The drawings which are returned to the vendor "Without Comments", Vendor shall prepare and submit
three sets of final Assembly / detailed drawings to M/s. IBIC.
k) Within one week of completion of each tank, vendor shall submit all drawings connected to it marked as
CERTIFIED AS BUILT DRAWING.
l) Quality Assurance plan, Bar Chart of welding procedure specification wherever applicable to be sent to
IBIC / CLIENT office within two weeks of receipt of LOI / Purchase Order. All document drawings approval
will be given on a specified date intimated by M/s IBIC / CLIENT.
m) Procurement action of forgings should be done by the Vendor wherever applicable immediately after
receipt of LOI / Purchase Order. Unpriced Purchase Order copies of all Bought Out items should be sent by
Vendor to IBIC / CLIENTs office immediately on placing the order.
n) For items like Gasket, Nuts & Bolts, Seal, Special Welding Rods, Gases and other required items Vendor
shall ensure that adequate stock is available. In case of delay, adequate action is to be initiated by the
vendor. The same is to be intimated to IBIC / CLIENTs office.
o) Prior approval of all Sub-vendors is to be obtained from IBIC / CLIENT at the time of Technical Discussion,
also sub-vendors list with contact person details (name, telephone etc) to be furnished to IBIC during
discussion.
p) Detailed progress report of the equipment order to be given to IBIC / CLIENT indicating the actual status of
the job to be submitted every fortnight.
q) Material test certificates should be furnished & given to IBIC / CLIENT representative at the time or
inspection. Check testing of main items to be carried out apart from mill test certificate.
r) Raw Material inspection at sub-vendor's workshop is solely the responsibility of the Vendor. IBIC / CLIENT
representative reserves the right to inspect the material at sub- vendors workshop.
s) All Final Revised drawings incorporating all comments made by IBIC should be received at IBIC before final
inspection.
t) The vendor has to submit acknowledgement receipt for all documents to the CLIENT, in order to receive
certificate from IBIC.
1.0 Scope
2.0 General
2.1 This standard shall be consulted in conjunction with the job specification, data sheets and
drawings.
2.2 The standard generally refers to API 650 / IS 803 (Latest Edition) and the points reiterated
below should be followed.
2.3 If the fabricator feels that any item of this standard is impractical the same shall be
brought to Purchaser's attention prior to fabrication of tank, and get approved the
alternative procedure suggested, if any.
2.4 At any time during fabrication is underway, Purchaser's Inspector should have free access
to any of the fabricator's shop concerned with fabrication of tanks. Fabricator shall
provide necessary facilities to satisfy the Purchaser's Inspector that the fabrication is being
done in accordance with the specifications. Also para 8.8 of IS 803 shall be applicable.
2.6 Materials that are ready for the inspection shall be given in writing two weeks in prior.
3.1 Fabricator shall submit Mill Test Certificates for materials in their scope and supply.
3.2 The fabricator shall also submit Test Certificates of materials for both physical and
chemical properties, tested by a reputed Laboratory approved by Lloyds or Bureau
Veritas.
3.3 All plate edges shall be inspected for any cracks and laminations.
3.5 Materials shall be marked to identify the same with the Test Certificates and to facilitate
erection.
4.0 Fabrication
4.0 The fabrication shall be done according to the standard and in accordance with the
specifications and drawings.
4.1 For the requirements of fabrication, the Fabricator shall refer to Section 8 of IS 803 and
Section 4 of API 650.
4.2 Fabrication shall only be done according to the fabrication drawings prepared by the
Fabricator and approved by Purchaser.
5.0 Erection
5.1 All the Welding Procedures and Welders or welding operators shall be qualified as per
Section 7 of API 650 and ASME Section IX Boiler and Pressure Vessel Code.
5.2 All welds shall be done in accordance with approved Welding Procedures (WPS) only.
5.3 Welding rods shall be of reputed brands of D&H, ADVANI, THYSEEN, and KOBE & ESAB etc
only. Fabricator shall get the same approved before commencement of any production
welding. Welding machines shall be either rectifier type or generators.
5.4 Before starting with the erection, the Fabricator shall obtain the consent of the concerned
authority regarding the foundation.
5.5 The erection in all respect shall comply with Section 5 of API 650 or Section 9 & 10 of IS
803, whichever applicable.
5.6 Painting and stenciling shall be done according to the specification and drawings. Dry Film
Thickness check shall be done.
6.1 Inspection of welds shall be done with reference to clause 5.3.2 and section 6 of
API 650. Also, all T joints shall be radiographed 100% and 10% of other weld joints
shall be radiographed.
6.2 Bottom testing shall be done either conforming to clause 12.1 of IS 803 or Clause
5.3.4 of API 650.
6.3 Vacuum Testing as described in clause 5.3.3 of API 650 shall be employed. Refer clause
12.1.3 of IS 803 also.
6.4 Bottom plate to shell fillet joints shall be checked using NDT (PT / MT).
6.5 Reinforcement plate welds shall be inspected as per clause 5.3.5 of API 650.
6.6 Testing of shell and roof shall be done according to clause 5.3.6 & 5.3.7 of API 650
respectively or clause 12.2 & 12.3 of IS 803 respectively. Accurately calibrated pressure
gauge shall be used and the calibration certificate of the gauge shall be produced
whenever the Purchasers Inspector demands.
6.7 For dimensional tolerances refer to clauses 9.3.5, 9.3.6 and 9.4 of IS 803 or clause
5.5 of API 650.
7.1 Repair of the leaks shall be done with the concurrence of the Inspector only.
7.3 The repair of leaks shall be carried out as per clause 5.4 and clause 6.1.7 of API 650 only.
INSPECTION PROGRAMME
ANNEXURE-3
Following Inspection programme provides step by step instructions for general inspection procedure
4.0 Marking, cutting and welding of nozzle opening and man way, checking.
7.0 Inspection of bottom fillet weld. Liquid Penetrant Test / Vacuum box test etc.
8.0 Welding of circumferential and vertical joints. Dimensional check and RT as per specification.
9.0 Fit-up, welding and inspection of Curb angle. Magnetic Particle Test of the weldment.
11.0 Final dimensional and internal check prior to fit up of top roof.
17.0 For inspection & test chart for storage tanks refer Annexure -3A
PROJECT:
PHYSICAL PROPERTIES TEST
RADIOGRAPHIC TEST
CHEMICAL ANALYSIS
VISUAL INSPECTION
HYDROSTATIC TEST
ULTRASONIC TEST
DESCRIPTION:
PNEUMATIC TEST
HARDNESS TEST
FERRITE TEST
IMPACT TEST
MICRO TEST
* IGC TEST
LEAK TEST
REMARKS
ENQ. NO:
PART /
MATERIAL /
STAGE
SHELL &
BOTTOM
MATERIAL
ROOF
MATERIAL
CURB ANGLE
MATERIAL
GIRDER
MATERIAL
R.F PLATE +
PAD PLATE
MATL.
NOZZLE
PIPE+FLANGE
MATL.
INTERNALS.
LUGS, CLEATS,
LIFTING
HOOKS
STIFFNERS &
NAME PLATE
ETC.
PROFILE AND
SET UP
WELDING
FASTENERS
GASKETS
HEAT
TREATMENT AS PER STANDARD CODE
FINAL
INSPECTION
Over 12 to 45 19
Over 45 to 75 25
Over 75 32
2.0 The maximum out-of-plumpness of the top of shell relative to the bottom of shell shall not exceed
1/200 of the total tank height. It applies to fixed roof columns also.
3.0 The out-of-plumpness in one shell course shall not exceed the permissible variations for flatness
and waviness as specified in ASTM A 6M/A 6, ASTM A 20M/A 20 or ASTM A 480M/A 48, whichever
is applicable.
4.0 Deviations (peaking) at vertical weld joint shall not exceed 13mm.
5.0 Deviations (banding) at horizontal weld joint shall not exceed 13mm.
Spots measured in the vertical plane shall not exceed the appropriate plate flatness and waviness
requirements (refer Flat Sr.No.3.0)
6.0 For concrete ring wall foundation under the shell, the top of the ring wall shall be level within
3mm (1/8 in.) in any 9m of the circumference and within 6 mm ( in.) in the total circumference
measured from average elevation.
7.0 For foundation other than concrete ring, the foundation under the shell shall be level within
3mm (1/8 in.) in any 3m of the circumference and within 13mm (1/2 in.) in the total
circumference measured from average elevation.
8.0 When a concrete slab foundation is provided, the first 0.3m of the foundation, measured from the
outside of the tank radially towards the center, shall comply with the concrete ring wall
requirement. The remainder of the foundation shall be within 13mm (1/2 in.) of the design
shape.
1.0 Scope
To provide guidelines towards achieving better quality in fabrication of Vessels, Heat Exchangers
or Storage tanks.
2.0 General
2.1 The fabricator should make sure that they have understood the design and requirements
properly and if there is any doubt, the same shall be cleared beforehand. Equipment data
sheet shall be referred along with this QA plan.
2.2 No deviation from drawings / standards shall be permitted without written approval by
the Purchaser.
2.3 Fabricator can in general refer to ASME Sec. VIII Div.1, ASME Sec V, ASME Sec II, ASME Sec
IX, TEMA, IS 803 and API 650 as applicable for the fabrication, inspection and testing.
3.0 Material
3.1 All the materials of construction should be strictly in accordance with the
purchasers drawings and specifications. Alternative materials shall be used only
on written approval by the IBIC/Purchaser.
3.2 The Fabricator should provide proper evidence to prove that the materials used in
fabrication are according to approved drawings and specifications and are
acceptable.
3.2.1 Fabricator should submit Mill test certificate for the materials in their scope and
supply for both physical and chemical properties and also get the materials tested
for the same by a reputed laboratory approved by IBIC and submit the certificate
for the Purchasers approval.
3.2.2 All the materials if specified should be inspected and certified by a qualified
inspector using non- destructive testing methods as per ASME Sec.V and
Sec. II.
General Ref: UW-26 to UW-42, UG-75 to UG-85, UG-90 to UG-103 and UW-11, UW-46 to UW-53.
4.1 The Fabricator shall furnish fabrication procedure / fabrication drawings for Purchaser's
approval.
4.2 All weld joints circumferential and longitudinal shall be marked on drawing. All
longitudinal joints shall be marked on orientation.
4.3 For fabrication tolerance, Fabricator can refer to TEMA F1, F2 & F3 for heat
exchangers; for vessels, fabricator can refer to the tolerance specification sheets
File Location: Page 26
General Engineering Documentation
IBIC-400-SS-0004
Standard Specification
400 Static equipment Engineering Rev. R0
Standard Specification for Storage tanks Date of Rev. 02/03/2017
attached to data sheets and API 650 or IS 803 for storage tanks.
4.4 Fabricator shall use electrodes of reputed brand names only and get the same approved
from IBIC/ Purchaser before beginning with any production welding.
4.8.1 In two pieces, with welding seam included in the middle third and
preferably on the central line.
4.8.2 In petal construction, with meridianal seams and central cap of diameter
not larger than 0.75 times the vessels OD.
4.9 As far as practicable, the shell sections shall be made out of a single plate with one
longitudinal weld seam only. The longitudinal seams of adjacent courses shall be
staggered and, as far as possible, seams shall be positioned clear of supports /
nozzles, so as to be readily accessible for examination. Ref. UG-79.
4.10 Nozzles shall be located, as far as possible, clear of longitudinal weld joints. Where this
4.11 All longitudinal and circumferential shell joints shall be full penetration double- welded
butt joints. The reverse side shall be welded after chipping, grinding or gouging out the
rest of first side to sound metal. Where sound back welding is not feasible, single welded
joints with backing strips or rings shall be used. Alternatively, root run shall be done with
TIG or MIG welding process to ensure proper penetration.
5.2 Formats for inspection reports should be same as that provided by the Purchaser or the
Fabricator should get their own alternative format approved from the purchaser.
1.0 General
1.1 This specification covers requirements for cleaning, pickling and passivating all stainless
steel process equipment constructed of alloys containing more than 12% Cr.
1.2 In case of equipment / piping assemblies subjected to post weld heat treatment the whole
surface shall be given the pickling treatment. Otherwise, only the weld joints and
sealed surfaces are to be pickled. Passivation shall be the last operation before
equipment / piping is put into service after testing.
1.3 The pickling and passivating solutions shall not be allowed to contact ferrous surfaces
containing less than 12% Cr. or any non-ferrous surfaces.
2.0 Procedures
2.1 Cleaning
2.1.1 All welding flux and weld spatter shall be removed by grinding or buffing.
2.1.2 All dirt, cinders, fly-ash or other extraneous matter shall be removed by brushing
with a hard fiber brush or stainless steel wire brush. Carbon steel wire brush
shall not be used to clean SS welding.
2.1.3 All organic materials, paint, crayon marks, soaps, oils or grease shall be removed
by washing with any commercial paint remover (those containing HCl or H2SO4
are not permitted) light solvent naphtha, di-chlorcethane or benzene. Soap
solutions or similar detergents may also be used. Motor Petrol shall not be
used.
2.2 Pickling
2.2.2 The material shall be exposed to the pickling solution only to an extent just
necessary and sufficient to remove residual scale. The maximum period for which
the pickling solution shall be allowed to remain on the surface is 30 minutes.
During pickling, the removal of the oxides may be hastened by brushing with a
hard fiber or S.S. wire brush together with clean sand. The pickling agent shall
finally be washed off with plenty of water so as to leave no trace behind.
2.3 Passivating
2.3.2 Tanks, pipelines and other equipments shall be filled with the solution.
Small parts shall be immersed in a tank containing this solution. The
solution shall be held in the equipment for:
a) At least 24 hours at 25 C
Temperature Duration
35 C 15 hours
50 C 8 hours
65 C 4 hours
80 C 2 hours
2.4 Rinsing
Finally the surface shall be thoroughly washed with a jet of water. Rubbing and
brushing are prohibited during and after passivating. Water used for rinsing shall
contain not more than 1-ppm chloride.
3.0 Inspection
3.1 After treatment, the equipment shall be free of waterbreak (see note *) as observed
during the rinsing operation.
3.2.1 The passivating solution used in clad or lined equipment shall be tested for
iron at the midpoint of the treatment and the liquor shall show no
increased rate of iron pick-up during the second half of the operation. An
increasing rate indicates either a break in the cladding or an unusual iron
contamination calling for repairs or replacement.
File Location: Page 33
General Engineering Documentation
IBIC-400-SS-0004
Standard Specification
400 Static equipment Engineering Rev. R0
Standard Specification for Storage tanks Date of Rev. 02/03/2017
3.2.2 The free iron test shall be used on accessible parts of the equipment to avoid further
contamination, unless the inspector has reasons to believe failure has occurred on some
inaccessible surfaces.
The solution shall be mixed within 24 hours on use and shall be applied by brush or spray
on test area. Blood red color indicates presence of free iron and equipment must be
rejected. Light pink color is acceptable.
WELDING NECK
When O. D is 24" or Less 1/16"*
Outside diameter
When O. D. is above 24" 1/8"*
10" and Smaller 1/32"
Inside Diameter 12" thru 18" 1/16"
20" and above + 1/8", -1/16"
1/16" Raised face 1/32"
Diameter of contact Face " Raised face Tongue & Groove
1/64"
Male, Female
When "X" is 24" or Smaller 1/16" *
Diameter of Hub at base (X)
When "X" is 24" & above 1/8 *
5" and Smaller + 3/32", -1/32"
Diameter Hub at point of Welding
6" & Larger + 5/32", - 1/32"
Bolt Circle diameter
1/16"
(1/2"- 24")
Bolt hole spacing 1/32"
Drilling
Eccentricity of bolt circle with respect to facing
2 and smaller 1/32" Max.
3 and larger 1/16" Max.
Eccentricity of bolt circle with
1/32 Max. *
respect to bore
Eccentricity of facing with respect
1/32 Max. *
to bore
18" and Smaller + 1/8", -0"
Flange Thickness
Over 18" + 3/16", -0"
10" and Smaller 1/16"
Overall length Through Hub
12" and above 1/8"
Class 150 (LG type) Class 150 Class 300 (LG type) Class 300
(WNRF type) (WNRF type)
Sr. Nozzle W/O Blind With Blind W/O With W/O Blind With Blind W/O With
No. Size Flange Flange Blind Blind Flange Flange Blind Blind
Flange Flange Flange Flange
(LT type) (LT type)
1 Up to 1"
2 1 1/2"
3 2"
4 3"
5 4
6 6
7 8" NOT NOT NOT NOT
8 10" APPLICABLE APPLICABLE APPLICABLE APPLICABLE
9 12"
10 14"
11 16"
12 18"
13 20"
14 24"
15 24
Manhole
as per
API 650
NOTE
1. The Schedule of rates includes supply of nozzle neck, flanges, studs/bolts, nuts & gaskets.
Class 150 (LG type) Class 150 Class 300 (LG type) Class 300
(WNRF type) (WNRF type)
Sr. Nozzle W/O Blind With Blind W/O With W/O Blind With Blind W/O With
No. Size Flange Flange Blind Blind Flange Flange Blind Blind
Flange Flange Flange Flange
(LT type) (LT type)
1 Up to 1"
2 1 1/2"
3 2"
4 3"
5 4
6 6
7 8" NOT NOT NOT NOT
8 10" APPLICABLE APPLICABLE APPLICABLE APPLICABLE
9 12"
10 14"
11 16"
12 18"
13 20"
14 24"
15 24
Manhole
as per
API 650
NOTE
1. The Schedule of rates includes supply of nozzle neck, flanges, studs/bolts, nuts & gaskets.
Class 150 (LG type) Class 150 Class 300 (LG type) Class 300
(WNRF type) (WNRF type)
Sr. Nozzle W/O Blind With Blind W/O With W/O Blind With Blind W/O With
No. Size Flange Flange Blind Blind Flange Flange Blind Blind
Flange Flange Flange Flange
(LT type) (LT type)
1 Up to 1"
2 1 1/2"
3 2"
4 3"
5 4
6 6
7 8" NOT NOT NOT NOT
8 10" APPLICABLE APPLICABLE APPLICABLE APPLICABLE
9 12"
10 14"
11 16"
12 18"
13 20"
14 24"
15 24
Manhole
as per
API 650
NOTE
1. The Schedule of rates includes supply of nozzle neck, flanges, studs/bolts, nuts & gaskets.
Class 150 (LG type) Class 150 Class 300 (LG type) Class 300
(WNRF type) (WNRF type)
Sr. Nozzle W/O Blind With Blind W/O With W/O Blind With Blind W/O With
No. Size Flange Flange Blind Blind Flange Flange Blind Blind
Flange Flange Flange Flange
(LT type) (LT type)
1 Up to 1"
2 1 1/2"
3 2"
4 3"
5 4
6 6
7 8" NOT NOT NOT NOT
8 10" APPLICABLE APPLICABLE APPLICABLE APPLICABLE
9 12"
10 14"
11 16"
12 18"
13 20"
14 24"
15 24
Manhole
as per
API 650
NOTE
1. The Schedule of rates includes supply of nozzle neck, flanges, studs/bolts, nuts & gaskets.
1)
2)
3)
4)
For Exotic along with
grade
1)
2)
3)
4)
Note: - This cost includes all the requirements. (i.e.-material, labor, fabrication, testing, inspection, painting etc.)
DEVIATION FORM
ANNEXURE-10
DEVIATION FORM
ANNEXURE - 10
Sr. No. Clause no. Deviation
Declaration by Bidder:
We have read the Enquiry document with related engineering requirements and specifications. We
agree to fulfill the requirements indicated therein.
Deviations taken by bidder are indicated clause wise for each document in separate bunch of sheets titled
as DEVIATION ON POINTS FOR..SYSTEM/EQUIPMENT. Other than the deviations indicated there,
all other requirements are acceptable unconditionally.
1.0 Scope
This specification describes the various aspects of painting of pressure vessels and related
structure. This specification also covers and defines the material specification, surface
preparation, application of paints, inspection and test.
Note: Stainless Steel and other alloys, Plastic and Aluminum should not be painted.
Finish paint type: Rich Silicone Finish - thickness (dry) min 3 mils
If the client is required the specific paint requirement then contractor should follow the same.
3.1 Dressing
A careful dressing shall be carried out to eliminate all foreign materials, particularly
glyceroids, hydrocarbon such as grease, oil naphtha and similar substances from the surface
required to be painted.
Dressing shall be carried out as follows:
Dry sand blasting shall be carried out by skilled personnel, approved by the
Engineer-in- charge, on external plate surface unless otherwise specified.
Before sand blasting all greasy substances shall be removed by means of adequate
washing. The portion that appears to be still greasy after the sand blasting shall be
cleaned with solvents and re-blasted. The sand blasting operation shall obtain
surface of uniform grayish-white color. Sand blasted surface shall be rough
enough to obtain the best condition for applying primer.
File Location: Page 47
General Engineering Documentation
IBIC-400-SS-0004
Standard Specification
400 Static equipment Engineering Rev. R0
Standard Specification for Storage tanks Date of Rev. 02/03/2017
The surface examined under naked eye, should be free from corrosions, scales,
oxide, paints, oil and other undesirable foreign matters. The compressed air used
shall be free from moisture, oil and liquid vapours. Sand blasting shall be
restricted to daytime only, however, night sand blasting may be permitted with
the approval of the Engineer-in-charge.
The sand blasting operation shall be suspended whenever the treated surface
appears to be humid or the relative humidity of the environment exceeds 80%.
The primer must be supplied on the sand blasted surface on the same day before
sunset and in any case before any oxidation occurs. Any surface where primer has
not been applied after sand blasting and consequently appears to the humid or
oxidized will be blasted again.
Mechanical cleaning shall be carried out on external structure and all internal
surfaces by means of equipment approved by the Engineer-in-charge. This
operation shall be restricted to daytime only unless approved by the Engineer-in-
charge. Painting shall be carried out on the same day the cleaning operation takes
place. The surface not promptly painted will have to be brushed again if they
appear to be humid or rusty. Greasy substances will have to be removed by
solvent before the mechanical cleaning starts. Engineer-in-charge resolves the
right to modify any procedures.
5.1. All consumables products such as paints, solvents, thinners etc. can be brought inside
the work site only when they are supplied in sealed containers, as dispatched from the
manufacturer. Specimen of such product shall be handed over to the Engineer-in- charge
and will be kept separately to carry out a comparison if so desired by the Engineer-in-
charge.
5.2. If, in the opinion of the Engineer-in-charge any tests are to be conducted for the paints,
the Contractor at his own cost will carry out the tests.
File Location: Page 48
General Engineering Documentation
IBIC-400-SS-0004
Standard Specification
400 Static equipment Engineering Rev. R0
Standard Specification for Storage tanks Date of Rev. 02/03/2017
Item to be
Final color Munsel No RAL No
painted
Bare surfaces
Medium
Frame works 7.5G7/2 6021
STRUCTURAL STEEL
green
Medium
Platforms, stairs, floor plate, support 7.5G7/2 6021
green
CLASSIFICATION:
Q - WITH BID.
P - PDF (IBIC+CLIENT)
QUANTITY REQUIRED
Q C F
Serial
Drawing / Data /Documents By By
No.
P H P H Weeks R H Weeks
1 Bar Chart (M.S. Project Form) 1+1 3+4 1+1 2+2 2 1+2 1+4 2
2 QAP (Inspection & Testing Plan) 1+1 3+4 1+1 2+2 2 1+2 1+4 2
NDT Procedure (LPT, MPT, UT, RT, - - 1+1 2+2 2 1+2 1+4 2
8
LT)
11 SubOrder Copies & Sub Vendor List 1+1 3+4 1+1 2+2 2 1+2 1+4 2
Page 1
Project Documentation
IBIC-210-400-DSS-0001
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R0
Document schedule for Shop fabricated Tanks Date of Rev 19/05/2017
23 Packing list - - - - - - - -
Page 2
IBIC-210-400-ENQ-0058
Project Documentation
NITRIC ACID COMPLEX-DAHEJ
PJ-210, DFPCL 0 19-05-17 Issue for Enquiry SAS ANS UAD
Rev. Date Description Prpd by Bhkd by Apprd by
N.A
Total Amount
INR
Excise Duty
CST/VAT
Transportation From Vendors Works upto DFPCL-Dahej site
Grand Total with all taxes/duties
Note:
Project Documentation
IBIC-210-400-ENQ-0058
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R0
Deviation Form for Shop Fabricated Tanks Date of Rev 19/05/2017
DEVIATION FORM
Declaration by Bidder:
We have read the Enquiry document with related engineering requirements and specifications.
We agree to fulfill the requirements indicated therein.
Deviations taken by bidder are indicated clause wise for each document in separate bunch of
sheets titled as DEVIATION ON POINTS FOR..SYSTEM/EQUIPMENT. Other than the
deviations indicated there, all other requirements are acceptable unconditionally.
Page 1
Project Documentation
IBIC-210-400-ADN-0002
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R0
Addition/Deletion Of Nozzles/ Fabrication Works Date of Rev 19/05/2017
Class 150 (LG type) Class 150 Class 300 (LG type) Class 300
(WNRF type) (WNRF type)
Sr. Nozzle W/O Blind With Blind W/O With W/O Blind With Blind W/O With
No. Size Flange Flange Blind Blind Flange Flange Blind Blind
Flange Flange Flange Flange
(LT type) (LT type)
1 Up to 1"
2 1 1/2"
3 2"
4 3"
5 4
6 6
7 8" NOT NOT NOT NOT
8 10" APPLICABLE APPLICABLE APPLICABLE APPLICABLE
9 12"
10 14"
11 16"
12 18"
13 20"
14 24"
15 24
Manhole
as per
API 650
NOTE
1. The Schedule of rates includes supply of nozzle neck, flanges, studs/bolts, nuts & gaskets.
Page 1
Project Documentation
IBIC-210-400-ADN-0002
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R0
Addition/Deletion Of Nozzles/ Fabrication Works Date of Rev 19/05/2017
Class 150 (LG type) Class 150 Class 300 (LG type) Class 300
(WNRF type) (WNRF type)
Sr. Nozzle W/O Blind With Blind W/O With W/O Blind With Blind W/O With
No. Size Flange Flange Blind Blind Flange Flange Blind Blind
Flange Flange Flange Flange
(LT type) (LT type)
1 Up to 1"
2 1 1/2"
3 2"
4 3"
5 4
6 6
7 8" NOT NOT NOT NOT
8 10" APPLICABLE APPLICABLE APPLICABLE APPLICABLE
9 12"
10 14"
11 16"
12 18"
13 20"
14 24"
15 24
Manhole
as per
API 650
NOTE
1. The Schedule of rates includes supply of nozzle neck, flanges, studs/bolts, nuts & gaskets.
Page 2
Project Documentation
IBIC-210-400-ADN-0002
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R0
Addition/Deletion Of Nozzles/ Fabrication Works Date of Rev 19/05/2017
Class 150 (LG type) Class 150 Class 300 (LG type) Class 300
(WNRF type) (WNRF type)
Sr. Nozzle W/O Blind With Blind W/O With W/O Blind With Blind W/O With
No. Size Flange Flange Blind Blind Flange Flange Blind Blind
Flange Flange Flange Flange
(LT type) (LT type)
1 Up to 1"
2 1 1/2"
3 2"
4 3"
5 4
6 6
7 8" NOT NOT NOT NOT
8 10" APPLICABLE APPLICABLE APPLICABLE APPLICABLE
9 12"
10 14"
11 16"
12 18"
13 20"
14 24"
15 24
Manhole
as per
API 650
NOTE
1. The Schedule of rates includes supply of nozzle neck, flanges, studs/bolts, nuts & gaskets.
Page 3
Project Documentation
IBIC-210-400-ADN-0002
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R0
Addition/Deletion Of Nozzles/ Fabrication Works Date of Rev 19/05/2017
Class 150 (LG type) Class 150 Class 300 (LG type) Class 300
(WNRF type) (WNRF type)
Sr. Nozzle W/O Blind With Blind W/O With W/O Blind With Blind W/O With
No. Size Flange Flange Blind Blind Flange Flange Blind Blind
Flange Flange Flange Flange
(LT type) (LT type)
1 Up to 1"
2 1 1/2"
3 2"
4 3"
5 4
6 6
7 8" NOT NOT NOT NOT
8 10" APPLICABLE APPLICABLE APPLICABLE APPLICABLE
9 12"
10 14"
11 16"
12 18"
13 20"
14 24"
15 24
Manhole
as per
API 650
NOTE
1. The Schedule of rates includes supply of nozzle neck, flanges, studs/bolts, nuts & gaskets.
Page 4
Project Documentation
IBIC-210-400-ADN-0002
NITRIC ACID COMPLEX -DAHEJ
PJ-210, DFPCL Rev R0
Addition/Deletion Of Nozzles/ Fabrication Works Date of Rev 19/05/2017
1)
2)
3)
4)
For Exotic along with
grade
1)
2)
3)
4)
Note: - This cost includes all the requirements. (I.e.-material, labor, fabrication, testing, inspection, painting etc.)
Page 5