01 OBRAS PRELIMINARES 10,428 .73


01 .01 CAMPAMENTO DE OBRA m2 40 .00 96 .32 3,852 .80
01 .02 CARTEL DE IDENTIFICACION DE LA OBRA DE 3 .60 X 2 .40 m u 1 .00 975 .93 975 .93
01 .03 MOVILIZACIN Y DESMOVILIZACIN DE EQUIPOS Y HERRAMIENTAS glb 1 .00 5,000 .00 5,000 .00
01 .04 SS .HH . PROVISIONAL PARA OBRA glb 1 .00 600 .00 600 .00
02 CERCO PERIMETRICO 411,718.75
02 .01 TRABAJOS PRELIMINARES 3,888.36
02 .01 .01 LIMPIEZA DE TERRENO MANUAL m2 268 .80 2 .21 594 .05
02 .01 .02 TRAZO, NIVELES Y REPLANTEO m2 201 .60 2 .16 435 .46
02 .01 .03 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m2 201 .60 1 .78 358 .85
02 .01 .04 CERCO PROVISIONAL DE SEGURIDAD DE OBRA glb 1 .00 2,500 .00 2,500 .00
02 .02 DEMOLICIONES 12,656 .17
02 .02 .01 DEMOLICIN DE MURO DE ADOBE Y TAPIAL m3 420 .00 6 .18 2,595 .60
02 .02 .02 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 15 km m3 775 .68 12 .97 10,060 .57
02 .03 MOVIMIENTO DE TIERRAS 14,018 .68
02 .03 .01 EXCAVACIN MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 266 .82 35 .28 9,413 .41
02 .03 .02 RELLENO COMPACTADO CON MATERIAL PROPIO, MANUAL m3 49 .48 12 .36 611 .57
02 .03 .03 ACARREO DE MATERIAL EXCEDENTE HASTA D PROM .=30 M . m3 271 .68 14 .70 3,993 .70
02 .04 OBRAS DE CONCRETO SIMPLE 64,810 .76
02 .04 .01 CIMIENTOS CORRIDOS MEZCLA 1:10 C-H + 30% PIEDRA m3 169 .80 195 .79 33,245 .14
02 .04 .02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 282 .73 43 .38 12,264 .83
02 .04 .03 CONCRETO 1:8+25% P .M . PARA SOBRECIMIENTOS m3 84 .82 227 .55 19,300 .79
02 .05 OBRAS DE CONCRETO ARMADO 266,738.10
02 .05 .01 CIMIENTOS Y SOBRECIMIENTOS 2,473.88
02 .05 .01 .01 ACERO DE REFUERZO FY=4200 KG/CM2 EN CIMIENTO CORRIDO Y kg 543 .71 4 .55 2,473 .88
SOBRECIMIENTO
02 .05 .02 COLUMNAS 172,763.74
02 .05 .02 .01 CONCRETO EN COLUMNAS F'C=175 KG/CM2 m3 405 .90 365 .04 148,169 .74
02 .05 .02 .02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 178 .35 53 .01 9,454 .33
02 .05 .02 .03 ACERO DE REFUERZO FY=4200 KG/CM2 EN COLUMNAS kg 3,327 .40 4 .55 15,139 .67
02 .05 .03 VIGAS 84,954 .14
02 .05 .03 .01 CONCRETO EN VIGAS F'C=175 KG/CM2 m3 202 .94 358 .15 72,682 .96
02 .05 .03 .02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 121 .28 62 .91 7,629 .72
02 .05 .03 .03 ACERO DE REFUERZO FY=4200 KG/CM2 EN VIGAS kg 1,020 .10 4 .55 4,641 .46
02 .05 .04 JUNTAS DE DILATACION 6,546.34
02 .05 .04 .01 JUNTAS DE DILATACION EN COLUMNAS m 162 .40 40 .31 6,546 .34
02 .06 ALBAILERIA 29,580 .43
02 .06 .01 MURO DE LADRILLO KK . DE ARCILLA CARAVISTA DE SOGA m2 514 .89 57 .45 29,580 .43
02 .07 REVOQUES ENLUCIDOS Y MOLDURAS 10,063 .13
02 .07 .01 TARRAJEO EN COLUMNAS EN EXTERIORES m2 305 .04 21 .56 6,576 .66
02 .07 .02 TARRAJEO EN VIGAS EN EXTERIORES m2 161 .71 21 .56 3,486 .47
02 .08 CONTRAZOCALOS 4,483.47
02 .08 .01 CONTRAZOCALO CEMENTO S/COLOREAR H=50 CM . m 404 .28 11 .09 4,483 .47
02 .09 PINTURA 5,479.65
02 .09 .01 PINTURA VINILICA 2 MANOS EN COLUMNAS EN EXTERIORES m2 305 .04 11 .74 3,581 .17
02 .09 .02 PINTURA VINILICA 2 MANOS EN VIGAS EN EXTERIORES m2 161 .71 11 .74 1,898 .48
03 SEPULCRO Y TRATAMIENTO PAISAJISTICO 193,995.46
03 .01 TRABAJOS PRELIMINARES 158.87
03 .01 .01 TRAZO, NIVELES Y REPLANTEO m2 73 .55 2 .16 158 .87
03 .02 MOVIMIENTO DE TIERRAS 5,502.13
03 .02 .01 EXCAVACION DE PLATAFORMA Y NIVELACION EN TIERRA m3 88 .25 34 .61 3,054 .33
03 .02 .02 EXCAVACION DE ZANJAS PARA ZAPATAS HASTA 1 .70M m3 23 .97 24 .72 592 .54
03 .02 .03 RELLENO Y COMPACTADO E=4", CON MATERIAL DE PRESTAMO m3 7 .60 14 .60 110 .96
03 .02 .04 ACARREO DE MATERIAL EXCEDENTE D(PROM)=30M m3 118 .66 14 .70 1,744 .30
S10 Pgina 2

Presupuesto
Presupuesto 0301019 MEJORAMIENTO DEL CEMENTERIO MUNICIPAL DE LA CIUDAD DE SAN MARCOS, DISTRITO DE SAN MARCOS - HUARI
- ANCASH
Cliente MUNICIPALIDAD DISTRITAL DE SAN MARCOS Costo al 0110612009
Lugar ANCASH - HUARI - SAN MARCOS

Item Descripcin Und. Metrado Precio SI.Parcial S/

03 .03 CONCRETO SIMPLE 181 .62


03 .03 .01 SOLADOS PARA ZAPATAS DE 3", MEZCLA 1:12 (C:H) m2 1 .41 20 .21 28 .50
03 .03 .02 BASE PARA PLATAFORMA DE CONCRETO F'C = 175 KG/CM2 m3 0 .44 348 .01 153 .12
03 .04 CONCRETO ARMADO 92,863 .06
03 .04 .01 ZAPATAS Y VIGAS DE CONEXCION 7,554.03
03 .04 .01 .01 ACERO fy=4200 kg/cm2 GRADO 60 P/ZAPATAS kg 218 .18 4 .55 992 .72
03 .04 .01 .02 CONCRETO f'c=210 kg/cm2 P/ZAPATAS m3 7 .05 352 .46 2,484 .84
03 .04 .01 .03 ACERO fy=4200 kg/cm2 GRADO 60 P/VIGAS DE CIMENTACION kg 361 .69 4 .55 1,645 .69
03 .04 .01 .04 ENCOFRADO Y DESENCOFRADO P/ VIGAS DE CIMENTACION m2 17 .73 62 .93 1,115 .75
03 .04 .01 .05 CONCRETO f'c=210 kg/cm2 P/ VIGAS DE CIMENTACION m3 3 .55 370 .43 1,315 .03
03 .04 .02 COLUMNAS 15,679 .35
03 .04 .02 .01 ACERO fy=4200 kg/cm2 GRADO 60 P/ COLUMNAS kg 662 .29 4 .55 3,013 .42
03 .04 .02 .02 ENCOFRADO Y DESENCOFRADO P/ COLUMNAS m2 73 .80 58 .56 4,321 .73
03 .04 .02 .03 CONCRETO f'c=210 kg/cm2 P/ COLUMNAS m3 18 .45 452 .26 8,344 .20
03 .04 .03 VIGAS 21,393 .61
03 .04 .03 .01 ACERO fy=4200 kg/cm2 GRADO 60 P/VIGAS kg 1,808 .46 4 .75 8,590 .19
03 .04 .03 .02 ENCOFRADO Y DESENCOFRADO P/ VIGAS m2 88 .65 48 .79 4,325 .23
03 .04 .03 .03 CONCRETO f'c=210 kg/cm2 P/ VIGAS m3 22 .16 382 .59 8,478 .19
03 .04 .04 LOSAS ALIGERADAS 48,236 .07
03 .04 .04 .01 ACERO fy=4200 kg/cm2 GRADO 60 P/ LOSAS ALIGERADAS kg 2,579 .37 4 .75 12,252 .01
03 .04 .04 .02 ENCOFRADO Y DESENCOFRADO P/ LOSAS ALIGERADAS m2 47 .60 57 .15 2,720 .34
03 .04 .04 .03 CONCRETO f'c=210 kg/cm2 P/ LOSAS ALIGERDAS m3 73 .55 452 .26 33,263 .72
03 .05 ALBAILERIA 57,538 .80
03 .05 .01 MURO DE LADRILLO KIN KONG DE CABEZA m2 495 .00 116 .24 57,538 .80
03 .06 REVOQUES Y ENLUCIDOS 6,343.35
03 .06 .01 TARRAJEO EN INTERIORES m2 190 .00 14 .40 2,736 .00
03 .06 .02 TARRAJEO EN EXTERIORES m2 119 .33 30 .23 3,607 .35
03 .07 PISOS Y PAVIMENTOS 10,960 .33
03 .07 .01 ENCOFRADO Y DESENCOFRADO P/ VEREDAS m2 13 .84 45 .20 625 .57
03 .07 .02 CONCRETO f'c=175 kg/cm2 P/ VEREDAS m3 29 .04 355 .88 10,334 .76
03 .08 COBERTURA 18,094 .30
03 .08 .01 VIGA CUMBRERA DE MADERA 4"X6" m 17 .12 56 .35 964 .71
03 .08 .02 VIGA DE MADERA 4"X4" m 145 .00 37 .21 5,395 .45
03 .08 .03 CORREA DE MADERA 2 1/2"X3" m 121 .80 20 .81 2,534 .66
03 .08 .04 COBERTURA DE TEJA ANDINA m2 106 .61 64 .84 6,912 .59
03 .08 .05 CUMBRERA DE TEJA ANDINA m 17 .12 133 .58 2,286 .89
03 .09 PINTURA 1,379.45
03 .09 .01 PINTURA VINILICA EN MUROS EXTERIORES 2 MANOS m2 119 .33 11 .56 1,379 .45
03 .10 INSTALACIONES ELECTRICAS 973.55
03 .10 .01 SALIDA PARA FAROLA EXTERIOR pto 5 .00 131 .05 655 .25
03 .10 .02 FAROLA DE ILUMINACION EXTERIOR DE 125W INC. EQUIPO u 5 .00 63 .66 318 .30
04 CAPILLA DE REZO 181,419.35
04 .01 TRABAJOS PRELIMINARES 146.25
04 .01 .01 TRAZO, NIVELES Y REPLANTEO m2 67 .71 2 .16 146 .25
04 .02 MOVIMIENTO DE TIERRAS 1,206.16
04 .02 .01 EXCAVACION DE ZANJAS PARA CIMIENTOS CORRIDOS HASTA 1 .15 M m3 23 .75 25 .20 598 .50
04 .02 .02 EXCAVACION DE ZANJAS PARA ZAPATAS HASTA 1 .15 M m3 13 .25 25 .20 333 .90
04 .02 .03 RELLENO Y COMPACTADO E=4", CON MATERIAL DE PRESTAMO m3 6 .85 14 .60 100 .01
04 .02 .04 ELIMINACION DE MATERIAL EXCEDENTE D(PROM)=30M m3 39 .40 4 .41 173 .75
04 .03 CONCRETO SIMPLE 5,375.09
04 .03 .01 SOLADOS PARA ZAPATAS DE 3", MEZCLA 1:12 (C:H) m2 1 .15 20 .21 23 .24
04 .03 .02 CIMIENTOS CORRIDOS 1:10 + 30% PG m3 14 .46 221 .67 3,205 .35
04 .03 .03 SOBRECIMIENTOS E=0 .25, 1:8 + 25% PM m3 4 .13 231 .35 955 .48
S10 Pgina 3

Presupuesto
Presupuesto 0301019 MEJORAMIENTO DEL CEMENTERIO MUNICIPAL DE LA CIUDAD DE SAN MARCOS, DISTRITO DE SAN MARCOS - HUARI
- ANCASH
Cliente MUNICIPALIDAD DISTRITAL DE SAN MARCOS Costo al 0110612009
Lugar ANCASH - HUARI - SAN MARCOS

Item Descripcin Und. Metrado Precio SI.Parcial SI

04 .03 .04 FALSO PISO DE 4" DE CONCRETO 1:10 (C:H) m2 67 .71 17 .59 1,191 .02
04 .04 CONCRETO ARMADO 46,268 .60
04 .04 .01 ZAPATAS 5,327.65
04 .04 .01 .01 ACERO fy=4200 kg/cm2 GRADO 60 P/ZAPATAS kg 724 .72 4 .55 3,297 .48
04 .04 .01 .02 CONCRETO f?c=210 kg/cm2 P/ZAPATAS m3 5 .76 352 .46 2,030 .17
04 .04 .02 COLUMNAS 28,955 .35
04 .04 .02 .01 ACERO fy=4200 kg/cm2 GRADO 60 P/ COLUMNAS kg 724 .72 4 .55 3,297 .48
04 .04 .02 .02 ENCOFRADO Y DESENCOFRADO P/ COLUMNAS m2 346 .32 58 .56 20,280 .50
04 .04 .02 .03 CONCRETO f?c=210 kg/cm2 P/ COLUMNAS m3 11 .89 452 .26 5,377 .37
04 .04 .03 VIGAS 11,985 .60
04 .04 .03 .01 ACERO fy=4200 kg/cm2 GRADO 60 P/VIGAS kg 713 .51 4 .75 3,389 .17
04 .04 .03 .02 ENCOFRADO Y DESENCOFRADO P/ VIGAS m2 118 .40 48 .79 5,776 .74
04 .04 .03 .03 CONCRETO f?c=210 kg/cm2 P/ VIGAS m3 7 .37 382 .59 2,819 .69
04 .05 ALBAILERIA 19,090 .73
04 .05 .01 MURO DE LADRILLO KIN KONG DE CABEZA m2 141 .15 116 .24 16,407 .28
04 .05 .02 MURO DE LADRILLO KIN KONG DE SOGA m2 30 .58 57 .40 1,755 .29
04 .05 .03 MURO DE LADRILLO KIN KONG DE SOGA PARA TIMPANO m2 16 .17 57 .40 928 .16
04 .06 REVOQUES Y ENLUCIDOS 7,990.84
04 .06 .01 TARRAJEO EN INTERIORES + ARISTAS Y DERRAMES EN VIGAS Y COLUMNAS m2 165 .01 23 .73 3,915 .69
04 .06 .02 TARRAJEO EN EXTERIORES + ARISTAS Y DERRAMES EN VIGAS Y COLUMNAS m2 171 .73 23 .73 4,075 .15
04 .07 PISOS Y PAVIMENTOS 18,606 .93
04 .07 .01 ENCOFRADO Y DESENCOFRADO P/ VEREDAS m2 23 .80 45 .20 1,075 .76
04 .07 .02 CONCRETO f?c=175 kg/cm2 P/ VEREDAS m3 11 .90 355 .88 4,234 .97
04 .07 .03 PISO DE CONCRETO E=2" SIN COLOREAR m2 48 .75 108 .64 5,296 .20
04 .07 .04 BANCAS DE CONCRETO ARMADO CON TARRAJEO glb 1 .00 8,000 .00 8,000 .00
04 .08 ZOCALOS Y CONTRAZOCALOS 1,413.19
04 .08 .01 CONTRAZOCALO DE CEMENTO DE E=2 cm H=30 cm SIN COLOREAR m 91 .00 10 .40 946 .40
04 .08 .02 ZOCALO DE MAYOLICA BLANCA DE 15 X 15 cm DE 1RA . m2 6 .90 67 .65 466 .79
04 .09 CIELORRASOS 1,871 .40
04 .09 .01 VIGUETA DE MADERA TORNILLO 2"X4" m 24 .40 41 .54 1,013 .58
04 .09 .02 LISTON DE MADERA TORNILLO 2"X3" m 17 .30 26 .67 461 .39
04 .09 .03 CIELO RASO CON TRIPLAY m2 6 .20 63 .94 396 .43
04 .10 COBERTURA 38,024 .85
04 .10 .01 VIGA CUMBRERA DE MADERA 4"X6" m 9 .10 56 .35 512 .79
04 .10 .02 VIGA CUMBRERA DE MADERA 4"X8" m 8 .50 86 .18 732 .53
04 .10 .03 VIGA DE MADERA 3"X4" m 121 .80 55 .57 6,768 .43
04 .10 .04 VIGA DE MADERA 3"X8" m 103 .00 90 .60 9,331 .80
04 .10 .05 CORREA DE MADERA 2 1/2"X3" m 31 .50 20 .81 655 .52
04 .10 .06 COBERTURA DE TEJA ANDINA m2 122 .25 64 .84 7,926 .69
04 .10 .07 CUMBRERA DE TEJA ANDINA m 15 .50 133 .58 2,070 .49
04 .10 .08 MACHIEMBRADO DE MADERA TORNILLO EN COBERTURA m2 102 .00 98 .30 10,026 .60
04 .11 CARPINTERIA DE MADERA 4,420.00
04 .11 .01 PUERTA DE MADERA APANELADA CEDRO B=2 .00 u 2 .00 1,860 .00 3,720 .00
04 .11 .02 PUERTA DE MADERA CONTRAPLACADA CEDRO B=0 .70 u 2 .00 350 .00 700 .00
04 .12 VENTANA METALICA 3,080.33
04 .12 .01 VENTANA DE FIERRO CON PERFIL DE 1" X 1/8" + HOJA BASTIDOR "L" 3/4" . u 11 .00 280 .03 3,080 .33
04 .13 PINTURA 5,681 .42
04 .13 .01 PINTURA VINILICA EN MUROS INTERIORES 2 MANOS m2 165 .01 22 .40 3,696 .22
04 .13 .02 PINTURA VINILICA EN MUROS EXTERIORES 2 MANOS m2 171 .73 11 .56 1,985 .20
04 .14 VIDRIOS, CRISTALES Y SIMILARES 226.21
04 .14 .01 VIDRIO SEMIDOBLE PROVISION Y COLOCACION EN VENTANAS FIERRO p2 2 .16 22 .28 48 .12
04 .14 .02 VIDRIO CATEDRAL PROVISION Y COLOCACION EN VENTANAS FIERRO p2 9 .85 18 .08 178 .09
04 .15 INSTALACIONES ELECTRICAS 1,131 .10
S10 Pgina 4

Presupuesto
Presupuesto 0301019 MEJORAMIENTO DEL CEMENTERIO MUNICIPAL DE LA CIUDAD DE SAN MARCOS, DISTRITO DE SAN MARCOS - HUARI
- ANCASH
Cliente MUNICIPALIDAD DISTRITAL DE SAN MARCOS Costo al 0110612009
Lugar ANCASH - HUARI - SAN MARCOS

Item Descripcin Und. Metrado Precio SI.Parcial SI

04 .15 .01 SALIDA PARA CENTROS DE LUZ CON INTERRUPTOR SIMPLE pto 4 .00 18 .59 74 .36
04 .15 .02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CON PVC . pto 3 .00 29 .70 89 .10
04 .15 .03 ACCESORIOS PARA SISTEMA ELECTRICO glb 1 .00 345 .00 345 .00
04 .15 .04 POZO CONEXIN A TIERRA glb 1 .00 622 .64 622 .64
04 .16 INSTALACIONES SANITARIA 26,886 .25
04 .16 .01 SISTEMA DE AGUA FRIA 1,036.77
04 .16 .01 .01 COLOCACION DE ACCESORIOS SANITARIOS pza 2 .00 31 .41 62 .82
04 .16 .01 .02 TUBERIA PVC SAP C-10 AGUA POTABLE DE 1/2" m 67 .60 7 .52 508 .35
04 .16 .01 .03 TUBERIA PVC SAP C-10 AGUA POTABLE DE 3/4" m 20 .00 20 .48 409 .60
04 .16 .01 .04 ACCESORIOS PARA AGUA POTABLE glb 1 .00 56 .00 56 .00
04 .16 .02 SISTEMA DE DESAGUE 8,361 .53
04 .16 .02 .01 APARATOS SANITARIOS glb 1 .00 508 .00 508 .00
04 .16 .02 .02 TUBERIA DE PVC SAL 2" m 4 .00 213 .04 852 .16
04 .16 .02 .03 TUBERIA DE PVC SAL 4" m 15 .00 40 .17 602 .55
04 .16 .02 .04 COLOCACION DE ACCESORIOS SANITARIOS pza 4 .00 31 .41 125 .64
04 .16 .02 .05 COLOCACION DE APARATOS SANITARIOS pza 4 .00 31 .41 125 .64
04 .16 .02 .06 SALIDA DE DESAGUE EN PVC . pto 12 .00 6 .28 75 .36
04 .16 .02 .07 SUMIDERO DE BRONCE 2" PROVISION Y COLOCACION . u 2 .00 50 .71 101 .42
04 .16 .02 .08 REGISTRO DE BRONCE 2" PROVISION Y COLOCACION . u 2 .00 39 .58 79 .16
04 .16 .02 .09 CANAL SEMICIRCULAR PLANCHA GALVANIZADA m 51 .50 114 .40 5,891 .60
04 .16 .03 POZO PERCOLADOR 17,487 .95
04 .16 .03 .01 TRAZO Y REPLANTEO m2 9 .62 2 .35 22 .61
04 .16 .03 .02 EXCAVACION DE ZANJA MANUAL EN POZO PERCOLADOR m3 26 .46 25 .20 666 .79
04 .16 .03 .03 ELIMINACION DE MATERIAL EXCEDENTE m3 33 .07 14 .70 486 .13
04 .16 .03 .04 ANILLO DE CONCRETO SIMPLE EN BASE m3 3 .85 262 .20 1,009 .47
04 .16 .03 .05 ACERO fy=4200 kg/cm2 GRADO 60 P/ LOSA DE TECHO kg 22 .72 3 .91 88 .84
04 .16 .03 .06 ENCOFRADO Y DESENCOFRADO EN POZO PERCOLADOR m2 28 .59 42 .46 1,213 .93
04 .16 .03 .07 CONCRETO Fc= 175 KG/cm2 EN LOSA PARED Y LOSA m3 4 .54 388 .50 1,763 .79
04 .16 .03 .08 MURO DE CABEZA LADRILLO KINKONG C/A 1/4 m2 96 .72 91 .35 8,835 .37
04 .16 .03 .09 ACERO fy=4200 kg/cm2 GRADO 60 P/ ANILLO DE REFUERZO kg 108 .08 4 .02 434 .48
04 .16 .03 .10 ENCOFRADO Y DESENCOFRADO EN ANILLO DE REFUERZO m2 26 .39 37 .50 989 .63
04 .16 .03 .11 CONCRETO Fc= 175 KG/cm2 EN ANILLO DE REFUERZO m3 0 .99 388 .50 384 .62
04 .16 .03 .12 FILTRO DE GRAVA O CASCAJO m3 14 .84 45 .13 669 .73
04 .16 .03 .13 RED DE DERIVACION PVC SAL PARA DESAGUE DE4" m 8 .00 27 .82 222 .56
04 .16 .03 .14 ACCESORIOS PARA POZOS PERCOLADORES glb 1 .00 500 .00 500 .00
04 .16 .03 .15 TAPA PREFABRICADA DE 0 .60 DE DIAMETRO glb 1 .00 200 .00 200 .00
05 MURO DE CONTENCION 215,160.13
05 .01 TRABAJOS PRELIMINARES 479.84
05 .01 .01 TRAZO, NIVELES Y REPLANTEO m2 222 .15 2 .16 479 .84
05 .02 MOVIMIENTO DE TIERRAS 11,934 .97
05 .02 .01 EXCAVACION DE ZANJAS PARA ZAPATAS HASTA 1 .4 M m3 137 .13 25 .20 3,455 .68
05 .02 .02 EXCAVACION DE ZANJAS PARA ZAPATAS HASTA 1 .5 M m3 186 .30 25 .20 4,694 .76
05 .02 .03 RELLENO Y COMPACTADO E=4", CON MATERIAL PROPIO m3 506 .40 5 .88 2,977 .63
05 .02 .04 ELIMINACION DE MATERIAL EXCEDENTE D(PROM)=30M m3 182 .97 4 .41 806 .90
05 .03 CONCRETO SIMPLE 4,489.65
05 .03 .01 SOLADOS PARA ZAPATAS DE 3", MEZCLA 1:12 (C:H) m2 222 .15 20 .21 4,489 .65
05 .04 CONCRETO ARMADO 165,880.66
05 .04 .01 ZAPATA EN MURO DE CONTENCION 63,958 .60
05 .04 .01 .01 ACERO fy=4200 kg/cm2 GRADO 60 P/ZAPATAS DE MURO DE CONTENCION kg 4,518 .00 4 .75 21,460 .50
05 .04 .01 .02 CONCRETO f?c=210 kg/cm2 P/ZAPATAS DE MURO DE CONTENCION m3 111 .08 382 .59 42,498 .10
05 .04 .02 PANTALLA EN MURO DE CONTENCION 75,080 .27
05 .04 .02 .01 ACERO fy=4200 kg/cm2 GRADO 60 P/ PANTALLA EN MURO kg 4,009 .08 4 .55 18,241 .31
05 .04 .02 .02 ENCOFRADO Y DESENCOFRADO P/ PANTALLAS EN MURO m2 609 .35 34 .56 21,059 .14
S10 Pgina 5

Presupuesto
Presupuesto 0301019 MEJORAMIENTO DEL CEMENTERIO MUNICIPAL DE LA CIUDAD DE SAN MARCOS, DISTRITO DE SAN MARCOS - HUARI
- ANCASH
Cliente MUNICIPALIDAD DISTRITAL DE SAN MARCOS Costo al 0110612009
Lugar ANCASH - HUARI - SAN MARCOS

Item Descripcin Und. Metrado Precio SI.Parcial SI

05 .04 .02 .03 CONCRETO f?c=210 kglcm2 PI PANTALLA EN MURO DE CONTENCION m3 93 .52 382 .59 35,779 .82
05 .04 .03 VIGAS 11,172 .99
05 .04 .03 .01 ACERO fy=4200 kglcm2 GRADO 60 PNIGAS kg 1,004 .71 4 .75 4,772 .37
05 .04 .03 .02 ENCOFRADO Y DESENCOFRADO P/ VIGAS m2 80 .57 48 .79 3,931 .01
05 .04 .03 .03 CONCRETO f?c=175 kglcm2 PI VIGAS m3 5 .37 459 .89 2,469 .61
05 .04 .04 COLUMNAS 15,668 .80
05 .04 .04 .01 ACERO fy=4200 kglcm2 GRADO 60 PI COLUMNAS kg 1,474 .55 4 .55 6,709 .20
05 .04 .04 .02 ENCOFRADO Y DESENCOFRADO PI COLUMNAS m2 104 .40 58 .56 6,113 .66
05 .04 .04 .03 CONCRETO f?c=175 kglcm2 PARA COLUMNAS m3 6 .96 408 .90 2,845 .94
05 .05 ALBAILERIA 28,292 .19
05 .05 .01 MURO DE LADRILLO KK . DE ARCILLA CARAVISTA DE SOGA m2 355 .83 55 .91 19,894 .46
05 .05 .02 TARRAJEO EN CARA EXTERIOR , EN PANTALLA DE CONTENCION m2 391 .32 21 .46 8,397 .73
05 .06 REVOQUES ENLUCIDOS Y MOLDURAS 4,082.82
05 .06 .01 JUNTAS DE DILATACION EN MUROS m 44 .77 1 .85 82 .82
05 .06 .02 PUERTA PRINCIPAL DE REJAS glb 1 .00 4,000 .00 4,000 .00
06 CONSTRUCCION DE GRADERIAS 34,509 .78
06 .01 TRABAJOS PRELIMINARES 844.56
06 .01 .01 TRAZO, NIVELES Y REPLANTEO m2 391 .00 2 .16 844 .56
06 .02 MOVIMIENTO DE TIERRAS 4,992.64
06 .02 .01 EXCAVACION DE ZANJAS PARA GRADERIAS 0 .1 M m3 25 .00 50 .40 1,260 .00
06 .02 .02 EXCAVACION DE ZANJAS PARA CORREDORES 0 .5 M m3 47 .00 50 .40 2,368 .80
06 .02 .03 ELIMINACION DE MATERIAL EXCEDENTE D(PROM)=30M m3 154 .63 8 .82 1,363 .84
06 .03 CONCRETO SIMPLE 28,672 .58
06 .03 .01 MAMPOSTERIA DE PIEDRA m3 75 .00 145 .01 10,875 .75
06 .03 .02 CONCRETO 1:10 +30% P .G . PARA CORREDORES m3 75 .20 236 .66 17,796 .83
07 FLETE DE MATERIALES Y OTROS 125,000.00
07 .01 FLETE TERRESTRE glb 1 .00 30,000 .00 30,000 .00
07 .02 FLETE RURAL glb 1 .00 95,000 .00 95,000 .00
COSTO DIRECTO 1,172,232.20
GASTOS GENERALES 117,223.22
UTILIDAD 10% 117,223.22
SUB TOTAL 1,406,678.64
IGV (19%) 267,268.94
TOTAL DE INVERSION POR EJECUCION DE OBRA 1,673,947.58