You are on page 1of 8

MIGHTY IRON

CONSTRUCTION MACHINES AT WORK www.mightyiron.com

Big Challenge,
Deep Tunnel

CONVENTION CENTER RUNOFF PUTS ENGINEERS TO THE TEST


Chicago Digs
DEEP-TUNNEL SYSTEM TO SIPHON STORM RUNOFF
FROM CONVENTION CENTER TO LAKE MICHIGAN

Deep

By JOE HANNEMAN / Photos by CHRIS DUZYNSKI

C
HICAGO — One of the to nearby Lake Michigan instead.
world’s largest convention Reliable Contracting & Equipment
centers is undergoing an $850 Co. of Chicago was already well
million expansion, but one of the along in installing sewers, water, site
most impressive things about the drainage and telecommunications
McCormick Place West project is the when the decision was made to empty
massive underground system being the site drainage into a deep tunnel.
built to handle storm water runoff Even as Reliable and its Volvo
from the 27-acre site. EC460B excavator dug and installed
Construction had already started piping on the site, engineers were busy
on the McCormick Place expansion designing a 12.5-foot-diameter deep
in 2004 when the city of Chicago tunnel to direct millions of gallons of
decided it no longer wanted a system clean storm water from the site out to
that would direct all the clean storm Lake Michigan.
runoff to water treatment plants, but (continues)

2 3
Chicago Digs
DEEP-TUNNEL SYSTEM TO SIPHON STORM RUNOFF
FROM CONVENTION CENTER TO LAKE MICHIGAN

Deep

By JOE HANNEMAN / Photos by CHRIS DUZYNSKI

C
HICAGO — One of the to nearby Lake Michigan instead.
world’s largest convention Reliable Contracting & Equipment
centers is undergoing an $850 Co. of Chicago was already well
million expansion, but one of the along in installing sewers, water, site
most impressive things about the drainage and telecommunications
McCormick Place West project is the when the decision was made to empty
massive underground system being the site drainage into a deep tunnel.
built to handle storm water runoff Even as Reliable and its Volvo
from the 27-acre site. EC460B excavator dug and installed
Construction had already started piping on the site, engineers were busy
on the McCormick Place expansion designing a 12.5-foot-diameter deep
in 2004 when the city of Chicago tunnel to direct millions of gallons of
decided it no longer wanted a system clean storm water from the site out to
that would direct all the clean storm Lake Michigan.
runoff to water treatment plants, but (continues)

2 3
Tunnel to run through bedrock siphon to force storm-water from
Open excavation or even a shallow the convention center to the lake at a
tunnel would run into old urban fill, maximum flow rate of 500 cubic feet per
building pilings, old terra cotta piping second.
and more. “It’s permanently full of water at the
“Obviously if you’re going to dig a elevation of the lake,” Klodzen said.
tunnel, you want the shortest route “The head difference between our water
possible,” Klodzen said. “Well, to go coming in and the lake level forces it
under buildings, the most logical thing through to the lake.”
then was to go down into the rock. That Designers had to ensure the outfall
way we did not have to worry about any at Northerly Island would not cause
interference with the foundations for significant lake currents that could
existing buildings.” disrupt boat traffic at the narrow opening
The tunnel will run 3,385 feet from of Burnham Harbor, Klodzen said.
the outfall at McCormick Place West
to Northerly Island (site of Chicago’s
Tunnel required utilities changes
Engineers decided to add three new
former Meigs Field airport). It will run
pump stations after the tunnel concept
about 150 feet below ground level. STS
was approved. With the first-flush
Consultants of Chicago designed the
contaminated runoff going to the sewer
tunnel for Mc4 West Constructors and
for treatment, positive pressure was
will build it utilizing a 12 foot 6 inch
needed to keep the sewers from backing
Robbins M81218-304 tunnel-boring
up.
machine.
Bob Borello, utilities superin-tendent
“The boring machine makes a huge
for Mc4West Constructors, said the
difference in the capacity of the tunnel,
Utilities excavation kept things moving. tunnel did not require a redesign of
because it creates a much smoother
the new sewer system being built
surface,” Klodzen said. the city is transforming from its former along Prairie Avenue, the major utility
To build the deep tunnel, a 22-foot- use as a single-strip airport for private corridor in the area. But some elements
diameter shaft will be dug on the east aircraft into a 75-acre park. that connect into it, such as bottom-
end of the tunnel route. Digging will The tunnel pipe itself will be unlined. elevation inverts, had to be changed.
proceed west to another shaft on the The inlet shaft will be lined with Borello credits the subcontractor,
McCormick Place West site. The rock reinforced concrete, while the outlet Reliable Contracting, with keeping
and earthen spoil will be used for shaft will be lined with cast-in-place
landscaping on Northerly Island, which concrete. It will work as an inverted (continues)

Reliable Contracting & Equipment Co. installed site utilities, including storm drainage running to the deep tunnel.

6 7
Tunnel to run through bedrock siphon to force storm-water from
Open excavation or even a shallow the convention center to the lake at a
tunnel would run into old urban fill, maximum flow rate of 500 cubic feet per
building pilings, old terra cotta piping second.
and more. “It’s permanently full of water at the
“Obviously if you’re going to dig a elevation of the lake,” Klodzen said.
tunnel, you want the shortest route “The head difference between our water
possible,” Klodzen said. “Well, to go coming in and the lake level forces it
under buildings, the most logical thing through to the lake.”
then was to go down into the rock. That Designers had to ensure the outfall
way we did not have to worry about any at Northerly Island would not cause
interference with the foundations for significant lake currents that could
existing buildings.” disrupt boat traffic at the narrow opening
The tunnel will run 3,385 feet from of Burnham Harbor, Klodzen said.
the outfall at McCormick Place West
to Northerly Island (site of Chicago’s
Tunnel required utilities changes
Engineers decided to add three new
former Meigs Field airport). It will run
pump stations after the tunnel concept
about 150 feet below ground level. STS
was approved. With the first-flush
Consultants of Chicago designed the
contaminated runoff going to the sewer
tunnel for Mc4 West Constructors and
for treatment, positive pressure was
will build it utilizing a 12 foot 6 inch
needed to keep the sewers from backing
Robbins M81218-304 tunnel-boring
up.
machine.
Bob Borello, utilities superin-tendent
“The boring machine makes a huge
for Mc4West Constructors, said the
difference in the capacity of the tunnel,
Utilities excavation kept things moving. tunnel did not require a redesign of
because it creates a much smoother
the new sewer system being built
surface,” Klodzen said. the city is transforming from its former along Prairie Avenue, the major utility
To build the deep tunnel, a 22-foot- use as a single-strip airport for private corridor in the area. But some elements
diameter shaft will be dug on the east aircraft into a 75-acre park. that connect into it, such as bottom-
end of the tunnel route. Digging will The tunnel pipe itself will be unlined. elevation inverts, had to be changed.
proceed west to another shaft on the The inlet shaft will be lined with Borello credits the subcontractor,
McCormick Place West site. The rock reinforced concrete, while the outlet Reliable Contracting, with keeping
and earthen spoil will be used for shaft will be lined with cast-in-place
landscaping on Northerly Island, which concrete. It will work as an inverted (continues)

Reliable Contracting & Equipment Co. installed site utilities, including storm drainage running to the deep tunnel.

6 7
“We really needed to have a decision have on the city each year.
early on,” said Gary Schalmo, president “The convention and tourism industry
of Mc4 West Constructors LLC, the contributes more than $8 billion a year
design-build group for McCormick to the local economy and generates
Place West. “It was either tunnel or more than 128,000 jobs throughout
storm detention. Once the decision was the metropolitan area,” Daley said. “If it
made to make the tunnel we needed to doesn’t remain strong, the economy of
make sure we stuck with it. Once the the Chicago area and the entire state of
decision was made there was no turning Illinois will suffer. We will lose jobs. And
back.” we will lose revenue. We can’t afford to
A big design change like this could lose either.”
have the potential to cause long delays or McCormick Place West will add
budget overruns, but neither happened 470,000 square feet of exhibition space,
in this case. Chicago Mayor Richard M. 250,000 square feet of meeting space,
Daley lent strong support, part of his with 60 meeting rooms and an impressive
water agenda to reduce pressure on city 100,000-square-foot ballroom.
treatment plants by keeping clean water
Storm runoff presents challenges
out of the sewer system.
The expansive roof and the truck
“It was a huge political accom-
docks will collect millions of gallons
plishment to get through the Illinois
of runoff during heavy storms. This
EPA, the Illinois Department of
posed a big design challenge for facility
Natural Resources, the (Army) Corps
planners. When the original RFP
of Engineers, the Greater Chicago
was published, the plan was for an
Metropolitan Water Reclamation
underground detention system to hold
District and the Lake Michigan
runoff until it could be released into the
Federation all to agree to allow this
sanitary sewers.
tunnel,” said Keith Klodzen, an engineer
Utilities construction on the
with Mc4 West LLC. “So that happened
McCormick site was already underway
remarkably fast.”
in 2004 when the mayor’s administration
Chicago’s history of flood woes said it wanted the storm system to empty
The kind of big thinking that inspired into Lake Michigan instead of going to
the deep-tunnel system for McCormick sewer treatment plants.
Place West has plenty of precedent in “Being in relatively close proximity
Chicago. Built on essentially swampland to Lake Michigan, there was strong
and now developed with buildings, parks incentive on their part to try and get all
and parking lots, Chicago has often had of the runoff from this 26-acre roof to
troubles with flooding. In 1997, heavy Lake Michigan, because that roof has
rains backed up the combined sewers, essentially clean runoff,” Klodzen said.
flooding thousands of basements and “That’s where the storm-water tunnel
causing more than $30 million in came in.”
damage. The massive 27-acre expansion of McCormick Place posed significant challenges on how to control storm runoff and keep it from the overburdened sewer system. The water-diversion system for the
This is the city that reversed the flow facility is designed to handle runoff from
of the Chicago River in 1900 from east
sanitary/storm sewer systems. In to spend more than $50 million a year infrastructure, Chicago can demonstrate Keeping Chicago competitive a 100-year flood. But it’s not as simple
Cook County, Ill., alone, there are 51 upgrading and cleaning the 4,400 miles the common-sense approach of man- McCormick Place West is badly as piping rainwater into Lake Michigan.
to west. That project was designed to
communities with combined sewers. of city sewer lines. The second is the aging storm water before it reaches the needed for Chicago to stay competitive Runoff from the 3.5-acre truck delivery
keep effluent out of Lake Michigan and
When heavy rainfall occurs, storm water Deep Tunnel, began in the 1970s to carve sewer system,” Daley said when unveiling with Las Vegas, Orlando and other cities dock and parking areas must be diverted
prevent a repeat of the poisoning of
can flood the system, causing overflows 109 miles of underground storage to his water agenda. in attracting and keeping major trade to the sanitary sewer.
the city’s water intake — which caused
into the city’s canal system or even into capture billions of gallons of combined The plan is to have McCormick Place shows. The city has set goals to not only The city’s plan called for a tunnel
waves of cholera and typhoid deaths in
Lake Michigan. This type of overflow— sewer overflow during heavy rains. That West achieve LEED® certification from expand its convention space, but also to for the clean roof runoff, but the water
the 1880s and 1890s. It was the first river
which spills into U.S. waterways at an system will be complete by 2017. the U.S. Green Building Council. The control costs and combat a reputation from the truck docks and parking areas
to flow away from its mouth.
estimated volume of 850 billion gallons Recently, residents have been Leadership in Energy & Environmental as a high-cost venue. must be subject to a “ first flush” where
Chicago is also in the midst of the 40-
a year — can contain a wide range of encouraged to disconnect downspouts Design (LEED) rating system recognizes McCormick Place’s main exhibit the initial run-off is sent to a water
year Tunnel and Reservoir Plan (“Deep
pathogens and threaten the health of from the sewer system, and more than sustainable site planning, safeguarding halls consistently run above practical treatment plant.
Tunnel”) to store billions of gallons of
those who use the waterways. 200,000 restrictor valves were installed water, water efficiency, energy efficiency maximum capacity. The expansion will “After that first flush, all the
storm runoff and prevent flooding and
Unveiled in 2003, the city of Chicago’s in street catch basins to control storm and renewable energy, conservation of make more convention dates available, contaminants have theoretically been
sewer overflow into Lake Michigan and
water agenda has taken a multi-prong flow into the system. The city is also materials and indoor environmental create a balance of meeting and exhibit washed away and the overflow is then
area rivers.
approach to preventing overflow from encouraging construction of rooftop quality. In 2004, Mayor Daley announced space, attract smaller meetings when the clean and can go to the lake,” Klodzen
Chicago is one of 750 communities
reaching area waterways like the long- gardens to capture rain runoff. all new public buildings in Chicago main facilities are booked, and add to the said.
in the United States with combined
polluted Chicago River. One strategy is “By expanding our use of green would be LEED certified. multi-billion-dollar impact conventions (continues)

4 5
“We really needed to have a decision have on the city each year.
early on,” said Gary Schalmo, president “The convention and tourism industry
of Mc4 West Constructors LLC, the contributes more than $8 billion a year
design-build group for McCormick to the local economy and generates
Place West. “It was either tunnel or more than 128,000 jobs throughout
storm detention. Once the decision was the metropolitan area,” Daley said. “If it
made to make the tunnel we needed to doesn’t remain strong, the economy of
make sure we stuck with it. Once the the Chicago area and the entire state of
decision was made there was no turning Illinois will suffer. We will lose jobs. And
back.” we will lose revenue. We can’t afford to
A big design change like this could lose either.”
have the potential to cause long delays or McCormick Place West will add
budget overruns, but neither happened 470,000 square feet of exhibition space,
in this case. Chicago Mayor Richard M. 250,000 square feet of meeting space,
Daley lent strong support, part of his with 60 meeting rooms and an impressive
water agenda to reduce pressure on city 100,000-square-foot ballroom.
treatment plants by keeping clean water
Storm runoff presents challenges
out of the sewer system.
The expansive roof and the truck
“It was a huge political accom-
docks will collect millions of gallons
plishment to get through the Illinois
of runoff during heavy storms. This
EPA, the Illinois Department of
posed a big design challenge for facility
Natural Resources, the (Army) Corps
planners. When the original RFP
of Engineers, the Greater Chicago
was published, the plan was for an
Metropolitan Water Reclamation
underground detention system to hold
District and the Lake Michigan
runoff until it could be released into the
Federation all to agree to allow this
sanitary sewers.
tunnel,” said Keith Klodzen, an engineer
Utilities construction on the
with Mc4 West LLC. “So that happened
McCormick site was already underway
remarkably fast.”
in 2004 when the mayor’s administration
Chicago’s history of flood woes said it wanted the storm system to empty
The kind of big thinking that inspired into Lake Michigan instead of going to
the deep-tunnel system for McCormick sewer treatment plants.
Place West has plenty of precedent in “Being in relatively close proximity
Chicago. Built on essentially swampland to Lake Michigan, there was strong
and now developed with buildings, parks incentive on their part to try and get all
and parking lots, Chicago has often had of the runoff from this 26-acre roof to
troubles with flooding. In 1997, heavy Lake Michigan, because that roof has
rains backed up the combined sewers, essentially clean runoff,” Klodzen said.
flooding thousands of basements and “That’s where the storm-water tunnel
causing more than $30 million in came in.”
damage. The massive 27-acre expansion of McCormick Place posed significant challenges on how to control storm runoff and keep it from the overburdened sewer system. The water-diversion system for the
This is the city that reversed the flow facility is designed to handle runoff from
of the Chicago River in 1900 from east
sanitary/storm sewer systems. In to spend more than $50 million a year infrastructure, Chicago can demonstrate Keeping Chicago competitive a 100-year flood. But it’s not as simple
Cook County, Ill., alone, there are 51 upgrading and cleaning the 4,400 miles the common-sense approach of man- McCormick Place West is badly as piping rainwater into Lake Michigan.
to west. That project was designed to
communities with combined sewers. of city sewer lines. The second is the aging storm water before it reaches the needed for Chicago to stay competitive Runoff from the 3.5-acre truck delivery
keep effluent out of Lake Michigan and
When heavy rainfall occurs, storm water Deep Tunnel, began in the 1970s to carve sewer system,” Daley said when unveiling with Las Vegas, Orlando and other cities dock and parking areas must be diverted
prevent a repeat of the poisoning of
can flood the system, causing overflows 109 miles of underground storage to his water agenda. in attracting and keeping major trade to the sanitary sewer.
the city’s water intake — which caused
into the city’s canal system or even into capture billions of gallons of combined The plan is to have McCormick Place shows. The city has set goals to not only The city’s plan called for a tunnel
waves of cholera and typhoid deaths in
Lake Michigan. This type of overflow— sewer overflow during heavy rains. That West achieve LEED® certification from expand its convention space, but also to for the clean roof runoff, but the water
the 1880s and 1890s. It was the first river
which spills into U.S. waterways at an system will be complete by 2017. the U.S. Green Building Council. The control costs and combat a reputation from the truck docks and parking areas
to flow away from its mouth.
estimated volume of 850 billion gallons Recently, residents have been Leadership in Energy & Environmental as a high-cost venue. must be subject to a “ first flush” where
Chicago is also in the midst of the 40-
a year — can contain a wide range of encouraged to disconnect downspouts Design (LEED) rating system recognizes McCormick Place’s main exhibit the initial run-off is sent to a water
year Tunnel and Reservoir Plan (“Deep
pathogens and threaten the health of from the sewer system, and more than sustainable site planning, safeguarding halls consistently run above practical treatment plant.
Tunnel”) to store billions of gallons of
those who use the waterways. 200,000 restrictor valves were installed water, water efficiency, energy efficiency maximum capacity. The expansion will “After that first flush, all the
storm runoff and prevent flooding and
Unveiled in 2003, the city of Chicago’s in street catch basins to control storm and renewable energy, conservation of make more convention dates available, contaminants have theoretically been
sewer overflow into Lake Michigan and
water agenda has taken a multi-prong flow into the system. The city is also materials and indoor environmental create a balance of meeting and exhibit washed away and the overflow is then
area rivers.
approach to preventing overflow from encouraging construction of rooftop quality. In 2004, Mayor Daley announced space, attract smaller meetings when the clean and can go to the lake,” Klodzen
Chicago is one of 750 communities
reaching area waterways like the long- gardens to capture rain runoff. all new public buildings in Chicago main facilities are booked, and add to the said.
in the United States with combined
polluted Chicago River. One strategy is “By expanding our use of green would be LEED certified. multi-billion-dollar impact conventions (continues)

4 5
The storm drainage system that will link to the deep tunnel includes pump stations that will prevent backflow problems.

construction moving smoothly despite as brick sewers, railroad ties and more.
“It was a major the design changes. Reliable kept ahead
of the foundation contractor while
“On Cottage Grove, remnants of an
old trolley line were still down there,”
accomplishment. It’s relocating existing utilities, building a
new utility corridor along Prairie Avenue
Borello said. “The tracks, the ties,
the whole thing. Electric cabling —
a very positive thing, and installing new piping for sanitary,
water and drainage.
everything was still in there.”
Klodzen said a parking garage
because it takes a huge Reliable also had to dig carefully adjacent to McCormick Place West also
had to be tied into the storm-runoff
around existing telecom lines, some
load off the existing of which were housed in fragile, old system. Designers had to replace the
terra cotta conduit. Excavators also planned rooftop detention system in the
sewer system.” encountered some old urban debris such parking garage and direct flow of runoff
into the site’s drainage system.
“If we would have allowed all this
water that could have overflowed from
the garage into our sanitary sewer, the
sanitary sewer capacity would have
been eaten up by the rainfall,” Klodzen
said. “We had to make sure we collected
it all.”
The tunnel has capacity to hold a 100-
year-storm runoff from up to 61 acres,
Klodzen said. That means it could hold
runoff from more of the McCormick
Place site, although no decision on that
has been made.
“It’s a big deal. It was a major
accomplishment. It’s a very positive
thing, because it takes a huge load off the
existing sewer system,” Klodzen said. l
McCormick Place West’s massive roof will generate a big supply of storm runoff.

You might also like