no Description UOM Amount Remarks


1 Earth work M3 56,294.62
2 PCC M3 39,530.70
3 Shuttering M2 66,914.50
4 Reinforcement MT 599,400.00
5 RCC M3 742,068.88

1,504,208.70
7200 203.966
Sl.no Description UOM QTY Rate Amount

General Excavation for footings,


trenches in Soil/Disintegrated rock
by Mechanical Means .
Scope includes Dressing/ Trimming
the edge etc.Stacking the Excavated
earth at a distance of 1 m From the
excavated Trench . All measurement
1 Shall be as per IS 1200 M3 203.97 180.00 36,713.88

Backfilling the Foundation area /


Trenches with the Excavated earth
in laryers not exceeding 150 mm
and the Same Should be
Compacted with OMC to achive
Desired Compaction using Hand
2 Rollers M3 163.17 120 19580.7365439
3
56,294.62
Remarks

Upto 6 feet
depth 7200 203.966
Sl.no Description UOM QTY Rate

Providing and Laying PCC of 1:4: 8 150 mm


thick for foundation/columns etc complete
using river sand and 20 mm down size
aggegate.
Cost includes spreading/levelling etc
1 complete at all levels M3 15.81 2500.00
Amount Remarks

39,530.70 12 columns 12
column size
0.5 0.3
Colum are 0.15 m2
footing siz 1.44
Depth 0.9
Sl.no Description UOM QTY Rate

Providing and Fixing Shuttering board to all


the structural elements at all leads and lift.
Cost includes board making , designing proper
supporting systems , oil, nailng, providiing tie
1 rods etc complete M2 89.22 750.00
Amount Remarks

66,914.50 1200 111.5242


16.72862
Sl.no Description UOM QTY Rate

Providing and Laying Reinforecment of Fe-500


for all structral elements including, Cutting,
Bending, Placing and tieing the rods with
Bending Wire with approirate knots at all level
1.
a Footing MT 2.16
a Slabs MT 7.2
c Colums MT 2.88
d Stair Case MT 1.08

13.32 45000
Amount Remarks

1200 3600
- 3.6
-
-
-

599,400.00
Sl.no Description UOM QTY Rate

Providing and Laying RMC for


foundation/columns /Beams /Slabs etc
complete with 53 grade Cement as per the
Specification of Manufacturer at all levels
including lead lift etc complete
Cost to include pumping, Laying, Vibration,
Compacting and curing the concerete as per
1 the instruction of EIC
a For Columns and Footings-M40 M3 26.892 5200
b For Slabs -M25 M3 33.46 4500
c For Beams-M25 M3 10.04 45000
Amount Remarks

1200 111.5242
139,838.40 16.72862
150,557.62 33.45725
451,672.86

742,068.88