RESUMEN PRESUPUESTO ANALTICO - COSTO DIRECTO

FTE.FTO : TESORO PUBLICO


UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE TURPO
CONSTRUCCIN DE PISTAS Y VEREDAS DEL CENTRO
PROYECTO POBLADO DE SOCOSPATA DEL DISTRITO DE TURPO
ANDAHUAYLLAS APURIMAC.

CDIGO ESPECIFICA DE GASTOS C.DIRECTO


2.6.2.3.4.3 PERSONAL 842,791.91 ###
2.6.2.3.4.4 MATERIALES 784,616.57
2.6.2.3.4.5 EQUIPOS Y HERRAMIENTAS 210,166.01
2.6.2.3.4.6 SUB CONTRATOS 87,000.00
TOTAL COSTO DIRECTO 1,924,574.49

DESAGREGADO DEL PRESUPUESTO ANALTICO

COSTO DIRECTO
2.6.2.3.4.3 PERSONAL S/. 842,791.91

CARGO UNIDAD CANTIDAD P.U TOTAL


OPERADOR DE EQUIPO LIVIANO hh 1,987.4000 15.00 29,811.000
TOPOGRAFO hh 241.9180 15.00 3,628.770
OFICIAL hh 4,751.9826 12.61 59,922.501
OPERARIO hh 6,214.5818 14.37 89,303.540 ###
CONTROLADOR DE EQUIPO PESADO hh 399.0152 15.00 5,985.228
PEON hh 18,469.5365 11.41 210,737.411 ###
PEON hh 38,860.9518 11.41 443,403.460 ###
TOTAL 842,791.91

2.6.2.3.4.4 MATERIALES DE CONSTRUCCION S/. 784,616.57

DESCRIPCION UNIDAD CANTIDAD P.U TOTAL


ALAMBRE NEGRO N 08 kg 243.9560 5.00 1,219.78
ALAMBRE NEGRO # 16 kg 10.0000 5.00 50.00
CLAVOS PARA MADERA CON CABEZA DE 3" kg 233.2361 5.00 1,166.18
ACERO LISO DE 1/2" m 0.3600 4.50 1.62
FIERRO FY = 4200 KG/CM2. kg 6,123.6000 9.50 58,174.20
ARENA FINA m3 9.3974 140.00 1,315.64
PIEDRA CHANCADA DE 1/2" m3 20.8926 120.00 2,507.11
PIEDRA MEDIANA m3 1.2701 95.00 120.66
HORMIGN m3 235.6720 130.00 30,637.36
ARENA GRUESA CLASIFICADA m3 34.7575 115.00 3,997.11
GRAVA PARA FILTRO m3 265.3700 120.00 31,844.40
LADRILLO CALCAREO DE SOGA u 1,277.5000 0.80 1,022.00
CEMENTO PORTLAND TIPO I (42.5 kg) bls 3,145.4632 31.00 97,509.36
CAJA CONCRETO SIMPLE DESAGUE 0.3 X 0.6 m INCLUYE FLETE u 309.0000 7.50 2,317.50
TAPA DE CONCRETO ARMADO PARA BUZON u 3.0000 138.00 414.00
CANDADO u 4.0000 60.00 240.00
YESO DE 28 Kg bls 93.6700 12.00 1,124.04
SOLDADURA SUPERCITO PUNTO AZUL 1/8" kg 0.3600 54.00 19.44
ADITIVO IMPERMEABILIZANTE gal 154.2815 35.00 5,399.85
PEGAMENTO PARA PVC gal 129.2764 105.00 13,574.02
CINTA TEFLON pza 12.0000 3.00 36.00
LIJA u 57.3828 3.00 172.15
GASOLINA 84 OCTANOS gal 0.3024 11.60 3.51
HORMIGON (PUESTO EN OBRA) m3 5.2874 130.00 687.36
AGUA m3 12,165.8261 1.84 22,385.12
CARTEL DE OBRA INCLUIDO INSTALACION Y TRANSPORTE glb 1.0000 1,500.00 1,500.00
TRANSPORTE DE MATERIAL POR KILOGRAMO ALMACEN - OBRA kg 1.0000 15,000.00 15,000.00 hh
TRANSPORTE DE MATERIAL DE LA ZONA A OBRA glb 2.0000 10,000.00 20,000.00 hh
TAPA METALICA DE METAL DE 0.80X0.80 INCLUYE MARCO u 6.0000 160.00 960.00 hh
ESTACA DE MADERA p2 114.6650 2.00 229.33 hh
MADERA TORNILLO INCLUYE CORTE PARA ENCOFRADO p2 7,314.0384 3.50 25,599.13
TAPA CON MARCO FIERRO FUNDIDO DE DESAGUE 12" X 24" pza 309.0000 45.00 13,905.00
PETROLEO DIESSEL # 2 gal 74.8120 13.80 1,032.41
PINTURA ESMALTE gal 0.7643 39.00 29.81
UNION UNIVERSAL DE FIERRO GALVANIZADO 6" pza 8.0000 15.00 120.00
NIPLE DE FIERRO GALVANIZADO DE 6" X 9" u 4.0000 10.00 40.00
NIPLE DE FIERRO GALVANIZADO DE 6" X 10" u 4.0000 10.00 40.00
TUBERIA PVC SAL 6" X 5M m 1,585.7365 32.90 52,170.73
RESUMEN PRESUPUESTO ANALTICO - COSTO DIRECTO
FTE.FTO : TESORO PUBLICO
UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE TURPO
CONSTRUCCIN DE PISTAS Y VEREDAS DEL CENTRO
PROYECTO POBLADO DE SOCOSPATA DEL DISTRITO DE TURPO
ANDAHUAYLLAS APURIMAC.

TUBERIA PVC SAL PARA DESAGUE DE 6" X 5 m m 9,429.6500 33.80 318,722.17


TUBERIA PVC SAL PARA DESAGUE DE 8" X 5 m m 805.4600 43.50 35,037.51
TUBERIA PVC SAL PARA DESAGUE DE 4" m 1.0000 13.00 13.00
TUBERIA PVC SAL PARA DESAGUE DE 6" m 11.5000 112.00 1,288.00
TUBERIA PVC SAL PARA DESAGUE DE 8" m 10.7120 177.00 1,896.02
TUBERIA PVC SAL 4" m 556.2000 22.60 12,570.12
VALVULA COMPUERTA DE BRONCE DE 6" u 4.0000 1,368.00 5,472.00
CALAMINA pl 80.0000 25.00 2,000.00
PLACA RECORDATORIO ACRILICA INCLUYE INSTALACION Y glb 1.0000 800.00 800.00
TRANSPORTE
REGLA DE MADERA p2 8.5033 9.00 76.53
IMPERMEABILIZANTE SIKA-1 kg 3.9200 45.00 176.40
TOTAL 784,616.57

2.6.2.3.4.5 EQUIPOS Y HERRAMIENTAS S/. 210,166.01

DESCRIPCION UNIDAD CANTIDAD P.U TOTAL


HERRAMIENTAS glb 1.0000 27,294.2800 27,294.28
HOJAS DE SIERRA u 0.3600 2.40 0.86
HOJAS DE SIERRA DE 24 DIENTES u 21.0130 4.20 88.25
BOMBA PARA PRUEBAS HIDRAULICAS hm 79.6592 5.00 398.30
COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP hm 1,987.4000 15.00 29,811.00
RETROEXCAVADOR SOBRE ORUGA 115-165 HP 0.75-1.4 Y hm 399.0152 280.00 111,724.26
VIBRADOR DE CONCRETO 4 HP 2.40" d 2.5806 15.00 38.71
MOTOSOLDADORA DE 250 A hm 0.1200 15.00 1.80
MEZCLADORA DE CONCRETO TROMPO 8 HP 9 p3 hm 179.0827 15.00 2,686.24
PLANCHA COMPACTADORA DE 8 HP hm 2,302.2860 15.00 34,534.29
EQUIPO TOPOGRFICO glb 239.2013 15.00 3,588.02
TOTAL 210,166.01

2.6.2.3.4.6 SUB CONTRATOS S/. 87,000.00


DESCRIPCION UNIDAD CANTIDAD P.U TOTAL
CAPACITACIN DESPUES DE LA EJECUCIN DE LA OBRA glb 3.0000 3,000.00 9,000.00
CAPACITACIN ANTES DE LA EJECUCIN DE LA OBRA glb 3.0000 3,000.00 9,000.00
CAPACITACIN DURANTE LA EJECUCIN DE LA OBRA glb 3.0000 3,000.00 9,000.00
CONSERVACION DEL MEDIO AMBIENTE glb 2.0000 30,000.00 60,000.00
TOTAL 87,000.00

S/. 1,924,574.49
RESUMEN PRESUPUESTO ANALTICO - GASTOS GENERALES
FTE.FTO : TESORO PUBLICO
UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE TURPO
PROYECTO CONSTRUCCIN DE PISTAS Y VEREDAS DEL CENTRO
POBLADO DE SOCOSPATA DEL DISTRITO DE TURPO
ANDAHUAYLLAS APURIMAC.

CDIGO ESPECIFICA DE GASTOS G. GRALES


2.6.2.2.2.3 PERSONAL 309,654.80
2.6.2.2.2.4 BIENES 15,302.45
2.6.2.2.2.5 SERVICIOS 6,840.00
2.6.2.2.2.6 OTROS 13,482.59
TOTAL GASTOS GENERALES 345,279.85 345,279.85

DESAGREGADO DEL PRESUPUESTO ANALTICO

GASTOS GENERALES

2.6.2.2.2.3 PERSONAL 309,654.80

RETRIBUCIONES COMPLEMENTARIAS-CONTRATOS A PLAZO FIJO 280,344.00

1 JORNAL
DEL EMPLEADO EVENTUAL

N DE
CARGO MESES COSTO SUB TOTAL
PERSONAS
RESIDENTE DE OBRA 1.00 12.00 5,000.00 60,000.00
ASISTENTE TECNICO 2.00 12.00 2,600.00 62,400.00
ASISTENTE ADNINISTRATIVO 1.00 12.00 2,600.00 31,200.00
MAESTRO DE OBRA 2.00 12.00 1,800.00 43,200.00
ALMACENERO 1.00 12.00 1,100.00 13,200.00
GUARDIAN 2.00 12.00 1,200.00 28,800.00
SECRETARIA 1.00 12.00 1,100.00 13,200.00
TOTAL 252,000.00

2 REFRIGERIO Y MOVILIDAD
DEL EMPLEADO EVENTUAL

N DE
CARGO MESES COSTO SUB TOTAL
PERSONAS
RESIDENTE DE OBRA 1.00 12.00 300.00 3,600.00
ASISTENTE TECNICO 2.00 12.00 280.00 6,720.00
ASISTENTE ADNINISTRATIVO 1.00 12.00 280.00 3,360.00
MAESTRO DE OBRA 2.00 12.00 250.00 6,000.00
ALMACENERO 1.00 12.00 180.00 2,160.00
GUARDIAN 2.00 12.00 181.00 4,344.00
SECRETARIA 1.00 12.00 180.00 2,160.00
TOTAL 28,344.00

OBLIGACIONES DEL EMPLEADOR S/. 25,300.80


1 ESSALUD (9%)
DEL EMPLEADO EVENTUAL

N DE
CARGO MESES COSTO SUB TOTAL
PERSONAS
RESIDENTE DE OBRA 1.00 12.00 450.00 5,400.00
ASISTENTE TECNICO 2.00 12.00 234.00 5,616.00
ASISTENTE ADNINISTRATIVO 1.00 12.00 234.00 2,808.00
MAESTRO DE OBRA 2.00 12.00 162.00 3,888.00
ALMACENERO 1.00 12.00 99.00 1,188.00
GUARDIAN 2.00 12.00 108.00 2,592.00
SECRETARIA 1.00 12.00 99.00 1,188.00
TOTAL 22,680.00
3 SEGURO COMPLEMENTARIO DE TRABAJO DE RIESGO (1.04%)
DEL EMPLEADO EVENTUAL

N DE
CARGO MESES COSTO SUB TOTAL
PERSONAS
RESIDENTE DE OBRA 1.00 12.00 52.00 624.00
ASISTENTE TECNICO 2.00 12.00 27.04 648.96
ASISTENTE ADNINISTRATIVO 1.00 12.00 27.04 324.48
MAESTRO DE OBRA 2.00 12.00 18.72 449.28
ALMACENERO 1.00 12.00 11.44 137.28
GUARDIAN 2.00 12.00 12.48 299.52
SECRETARIA 1.00 12.00 11.44 137.28
TOTAL 2,620.80

GASTOS VARIABLES Y OCASIONALES 4,010.00

2 AGUINALDOS POR ESCOLARIDAD


DEL EMPLEADO EVENTUAL

N DE
CARGO MESES COSTO SUB TOTAL
PERSONAS
RESIDENTE DE OBRA 1.00 1.00 138.89 138.89
ASISTENTE TECNICO 2.00 1.00 95.00 190.00
ASISTENTE ADNINISTRATIVO 1.00 1.00 95.00 95.00
MAESTRO DE OBRA 2.00 1.00 72.22 144.44
ALMACENERO 1.00 1.00 50.00 50.00
GUARDIAN 2.00 1.00 30.56 61.11
SECRETARIA 1.00 1.00 30.56 30.56
TOTAL 710.00

4 AGUINALDOS NAVIDAD
DEL EMPLEADO EVENTUAL

N DE
CARGO MESES COSTO SUB TOTAL
PERSONAS
RESIDENTE DE OBRA 1.00 1.00 5,000.00 300.00
ASISTENTE TECNICO 2.00 1.00 2,600.00 1,200.00
ASISTENTE ADNINISTRATIVO 1.00 1.00 2,600.00 600.00
MAESTRO DE OBRA 2.00 1.00 1,800.00 300.00
ALMACENERO 1.00 1.00 1,100.00 300.00
GUARDIAN 2.00 1.00 1,200.00 300.00
SECRETARIA 1.00 1.00 1,100.00 300.00
TOTAL 3,300.00

2.6.2.2.2.4 BIENES S/. 15,302.45

1 MATERIALES MEDICOS Y MEDICINAS

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


AGUA OXIGENADA FRASCO 6.00 10.00 60.00
ALCOHOL LTS 12.00 15.00 180.00
ALGODN X 25 GR PQTE 12.00 10.00 120.00
YODO LTS 6.00 15.00 90.00
IBUPROFENO DE 800 UND 12.00 15.00 180.00
AMOXICILINA DE 500 UND 12.00 15.00 180.00
BUSCAPINA UND 12.00 15.00 180.00
TOTAL 990.00

2 MATERIALES DE LIMPIEZA

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


ESCOBA DOAFLORINDA UND 2.00 50.00 100.00
RECOGEDOR DE PLASTICO UND 2.00 50.00 100.00
TOTAL 200.00
3 IMPLEMENTOS DE SEGURIDAD

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


CASCO TIPO JOKEY COLOR BLANCO UND 4.00 35.00 140.00
CASCO TIPO JOKEY DE COLOR UND 50.00 25.00 1,250.00
BOTAS DE JEBE UND 50.00 30.00 1,500.00
BOTAS DE CUERO UND 4.00 70.00 280.00
WANTES DE JEBE UND 50.00 5.00 250.00
WANTES DE CUERO UND 50.00 7.00 350.00
OTROS UND 49.44 9.00 444.95
TOTAL 4,214.95

4 MATERIALES DE ESCRITORIO

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


ARCHIVADOR DE LOMO ANCHO PARA FORMATO A-4 UND 10.00 9.00 90.00
ANILLOS DE 5/8" UND 100.00 5.00 500.00
CD RW REGRABABLES UND 10.00 2.50 25.00
CLIP WINGO PEQUEO X 100 UNID CJA 11.00 5.00 55.00
CINTA MASKING X 1" UND 13.00 6.00 78.00
CORRECTOR UND 8.00 8.00 64.00
LIBRETA TOPOGRFICA FIELD BOOK UND 10.00 8.00 80.00
LIBRETA TOPOGRFICA LEVEL BOOK UND 10.00 8.00 80.00
CUADERNO 50 HOJAS UND 12.00 2.00 24.00
CUADERNO DE OBRA 1X3COPIAS X 50 HOJAS UND 4.00 28.00 112.00
CUADERNO ESPIRALADO 200 HJAS UND 10.00 8.00 80.00
CUADERNO ESPIRALADO 200 HJAS UND 1.00 30.00 30.00
CUTER GRANDE UND 2.00 5.50 11.00
ENGRAMPADOR UND 2.00 35.00 70.00
ESPIRALES DE 7 MM UND 16.00 0.50 8.00
FASTENERX50 UND CJA 10.00 15.00 150.00
FILES UND 16.00 2.00 32.00
LAPICERO AZUL/NEGRO 033 FABER CASTELL UND 16.00 8.00 128.00
LIBRETA DE CAMPO UND 10.00 10.00 100.00
PAPEL CARBON X100 HJAS CJA 1.00 19.50 19.50
PAPEL FOTOCOPIA 80 GR A-4 MLL 10.00 32.00 320.00
PARTES DIARIOS 1X3 COPIAS BLOCK 15.00 15.00 225.00
PEGAMENTO EN BARRA UND 16.00 8.00 128.00
PERFORADOR S/C UND 5.00 20.00 100.00
PLUMONES DELGADOS FC 45 UND 9.00 1.00 9.00
PLUMONES GRUESOS PARA PAEL FC UND 10.00 5.00 50.00
PLUMON INDELEBLE DELGADO DIFER. COLORES UND 10.00 8.00 80.00
PLUMON INDELEBLE GRUESO DIFER. COLORES UND 11.00 8.00 88.00
POST IT CUADRADO COLORES PZA 10.00 8.00 80.00
PORTAMINAS UND 13.00 8.50 110.50
REPUESTOS PARA PORTAMINAS UND 15.00 8.00 120.00
RESALTADOR UND 10.00 8.00 80.00
SELLO DE OBRA UND 6.00 25.00 150.00
THONER HP LASERJET 1015 UND 12.00 350.00 4,200.00
OTROS GLB 12.00 200.00 2,400.00
TOTAL 9,897.50

2.6.2.2.2.5 SERVICIOS S/. 6,840.00

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


LEGALIZACION DE CUADERNO DE OBRAS UND 1.00 40.00 40.00
PRUEBA DE LABORATORIO( ROTURA DE BRIQUETAS) UND 8.00 100.00 800.00
TRANSPORTE GLB 12.00 500.00 6,000.00
TOTAL 6,840.00

2.6.2.2.2.6 OTROS S/. 13,482.59

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


GASOLINA GL 484.97 14.00 6,789.59
PETROLEO GL 485.00 13.80 6,693.00
TOTAL 13,482.59

TOTAL GASTOS GENERALES S/. 345,279.85


RESUMEN PRESUPUESTO ANALTICO - SUPERVISION
FTE.FTO : TESORO PUBLICO
UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE TURPO

CONSTRUCCIN DE PISTAS Y VEREDAS DEL CENTRO POBLADO DE


PROYECTO
SOCOSPATA DEL DISTRITO DE TURPO ANDAHUAYLLAS APURIMAC.

CDIGO ESPECIFICA DE GASTOS G. GRALES


2.6.2.2.2.3 PERSONAL 94,920.00
2.6.2.2.2.4 BIENES 1,609.11
2.6.2.2.2.5 SERVICIOS 2,000.00
2.6.2.2.2.6 OTROS 11,518.12

TOTAL GASTOS SUPERVISION 110,047.23

DESAGREGADO DEL PRESUPUESTO ANALTICO

GASTOS DE SUPERVISION

2.6.2.2.2.3 PERSONAL 94,920.00

RETRIBUCIONES COMPLEMENTARIAS-CONTRATOS A PLAZO FIJO 87,600.00

1 JORNAL
DEL EMPLEADO EVENTUAL

CARGO N DE PERSONAS MESES COSTO SUB TOTAL


SUPERVISOR DE OBRA 1.00 12.00 6,500.00 78,000.00
TOTAL 78,000.00

2 REFRIGERIO Y MOVILIDAD
DEL EMPLEADO EVENTUAL

CARGO N DE PERSONAS MESES COSTO SUB TOTAL


SUPERVISOR DE OBRA 1.00 12.00 800.00 9,600.00
TOTAL 9,600.00

OBLIGACIONES DEL EMPLEADOR S/. 7,020.00

1 ESSALUD (9%)
DEL EMPLEADO EVENTUAL

CARGO N DE PERSONAS MESES COSTO SUB TOTAL


SUPERVISOR DE OBRA 1.00 12.00 585.00 7,020.00
TOTAL 7,020.00

GASTOS VARIABLES Y OCASIONALES 300.00

4 AGUINALDOS NAVIDAD
DEL EMPLEADO EVENTUAL

CARGO N DE PERSONAS MESES COSTO SUB TOTAL


SUPERVISOR DE OBRA 1.00 1.00 300.00 300.00
TOTAL 300.00

2.6.2.2.2.4 BIENES S/. 1,609.11


3 IMPLEMENTOS DE SEGURIDAD

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


CASCO TIPO JOKEY COLOR BLANCO UND 4.00 25.00 100.00
CASCO TIPO JOKEY DE COLOR UND 4.00 20.00 80.00
BOTAS DE CUERO UND 4.00 90.00 360.00
OTROS UND 4.00 100.00 400.00
TOTAL 940.00

4 MATERIALES DE ESCRITORIO

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


PAPEL BOND 80 GR A-4 MLL 4.00 23.50 94.00
ARCHIVADOR DE LOMO ANCHO PARA FORMATO A-4 UND 10.00 8.00 80.00
BORRADOR DE LPIZ FABER CASTELL UND 10.00 0.30 3.00
CD EN BLANCO UND 20.00 1.00 20.00
CORRECTOR UND 10.00 1.50 15.00
CUADERNO 100 HOJAS UND 10.00 4.00 40.00
USB UND 2.00 52.31 104.61
LAPICERO PUNTA FINA PILOT COLOR ROJO UND 20.00 2.50 50.00
LAPICERO PUNTA FINA PILOT COLOR AZUL UND 20.00 2.50 50.00
LAPICERO PUNTA FINA PILOT COLOR NEGRO UND 5.00 2.50 12.50
PORTAMINAS ROTRING UND 5.00 6.00 30.00
SELLO TRODAC UND 5.00 15.00 75.00
PAPEL BOND A3 MLL 1.00 40.00 40.00
FOLDER MANILA UND 10.00 0.50 5.00
RESALTADOR UND 10.00 5.00 50.00
TOTAL 669.11
2.6.2.2.2.5 SERVICIOS S/. 2,000.00

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


TRANSPORTE GLB 1.00 2,000.00 2,000.00
TOTAL 2,000.00

2.6.2.2.2.6 OTROS S/. 11,518.12

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


GASOLINA UNID 250.01 13.20 3,300.10
PETROLEO UNID 233.19 13.80 3,218.02
VARIOS GLB 1.00 5,000.00 5,000.00
TOTAL 11,518.12

TOTAL GASTOS SUPERVISION S/. 110,047.23


RESUMEN PRESUPUESTO ANALTICO - EXPEDIENTE TECNICO
FTE.FTO : TESORO PUBLICO
UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE TURPO

CONSTRUCCIN DE PISTAS Y VEREDAS DEL CENTRO POBLADO DE


PROYECTO
SOCOSPATA DEL DISTRITO DE TURPO ANDAHUAYLLAS APURIMAC.

CDIGO ESPECIFICA DE GASTOS G. GRALES


2.6.2.2.2.3 PERSONAL 30,850.00
2.6.2.2.2.4 BIENES 3,243.79
2.6.2.2.2.5 SERVICIOS 3,500.00
2.6.2.2.2.6 OTROS 1,293.44
TOTAL GASTOS EN LA ELABORACION DE EXPEDIENTES TECNICOS 38,887.23

DESAGREGADO DEL PRESUPUESTO ANALTICO

GASTOS EN LA ELABORACION DE EXPEDIENTES TECNICOS

2.6.2.2.2.3 PERSONAL 30,850.00

RETRIBUCIONES COMPLEMENTARIAS-CONTRATOS A PLAZO FIJO 30,850.00

1 JORNAL
DEL EMPLEADO EVENTUAL

CARGO N DE PERSONAS CANTIDAD COSTO SUB TOTAL


INGENIERO CIVIL 1.00 2.00 4,500.00 9,000.00
INGENIERO GEOLOGO (GEOTECNISTA) 1.00 1.50 3,500.00 5,250.00
ASISTENTE TECNICO 1.00 2.00 3,000.00 6,000.00
TOPOGRAFO 1.00 2.00 2,000.00 4,000.00
DIBUJANTE DE CAD 1.00 1.00 1,800.00 1,800.00
TOTAL 26,050.00

2 REFRIGERIO
DEL EMPLEADO EVENTUAL

CARGO N DE PERSONAS CANTIDAD COSTO SUB TOTAL


INGENIERO CIVIL 1.00 10.00 100.00 1,000.00
INGENIERO GEOLOGO (GEOTECNISTA) 1.00 10.00 100.00 1,000.00
ASISTENTE TECNICO 1.00 10.00 100.00 1,000.00
TOPOGRAFO 1.00 10.00 100.00 1,000.00
DIBUJANTE DE CAD 1.00 10.00 80.00 800.00
TOTAL 4,800.00

2.6.2.2.2.4 BIENES S/. 3,243.79

3 IMPLEMENTOS DE SEGURIDAD

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


CASCO TIPO JOKEY COLOR BLANCO UND 6.00 80.00 480.00
CASCO TIPO JOKEY DE COLOR UND 6.00 42.00 252.00
BOTAS DE CUERO UND 5.00 110.00 550.00
OTROS UND 6.00 150.00 900.00
TOTAL 2,182.00

4 MATERIALES DE ESCRITORIO

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


PAPEL BOND 80 GR A-4 MLL 6.00 45.00 270.00
ARCHIVADOR DE LOMO ANCHO PARA FORMATO A-4 UND 1.00 8.00 8.00
BORRADOR DE LPIZ FABER CASTELL UND 3.00 0.30 0.90
CD EN BLANCO UND 4.00 2.00 8.00
CORRECTOR UND 4.00 2.00 8.00
CUADERNO 100 HOJAS UND 2.00 10.00 20.00
USB UND 1.00 55.00 55.00
LAPICERO PUNTA FINA PILOT COLOR ROJO UND 2.00 3.00 6.00
LAPICERO PUNTA FINA PILOT COLOR AZUL UND 2.00 3.00 6.00
LAPICERO PUNTA FINA PILOT COLOR NEGRO UND 2.00 2.70 5.39
PORTAMINAS ROTRING UND 2.00 6.00 12.00
SELLO TRODAC UND 1.00 15.00 15.00
PAPEL BOND A3 MLL 0.25 160.00 40.00
TONER PARA IMPRESORA UND 1.00 600.00 600.00
FOLDER MANILA UND 5.00 0.50 2.50
RESALTADOR UND 1.00 5.00 5.00
TOTAL 1,061.79
RESUMEN PRESUPUESTO ANALTICO - EXPEDIENTE TECNICO
FTE.FTO : TESORO PUBLICO
UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE TURPO

CONSTRUCCIN DE PISTAS Y VEREDAS DEL CENTRO POBLADO DE


PROYECTO
SOCOSPATA DEL DISTRITO DE TURPO ANDAHUAYLLAS APURIMAC.

2.6.2.2.2.5 SERVICIOS S/. 3,500.00

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


TRANSPORTE GLB 1.00 1,000.00 1,000.00
LEVANTAMIENTO TOPOGRAFICO GLB 1.00 1,000.00 1,000.00
ESTUDIO DE SUELOS GLB 1.00 1,000.00 1,000.00
IMPRESIN PLANOS GLB 1.00 500.00 500.00
TOTAL 3,500.00

2.6.2.2.2.6 OTROS S/. 1,293.44

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


GASOLINA GALONES 50.00 13.20 660.00
PETROLEO GALONES 45.90 13.80 633.44
TOTAL 1,293.44

TOTAL GASTOS GENERALES S/. 38,887.23


RESUMEN PRESUPUESTO ANALTICO - LIQUIDACION.
FTE.FTO : TESORO PUBLICO
UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE TURPO
CONSTRUCCIN DE PISTAS Y VEREDAS DEL CENTRO POBLADO DE
PROYECTO SOCOSPATA DEL DISTRITO DE TURPO ANDAHUAYLLAS
APURIMAC.

CDIGO ESPECIFICA DE GASTOS G. GRALES


2.6.2.2.2.3 PERSONAL 12,067.39
2.6.2.2.2.4 BIENES 618.90
2.6.2.2.2.5 SERVICIOS 1,000.00
2.6.2.2.2.6 OTROS 3,305.20
TOTAL GASTOS DE LIQUIDACION 16,991.49

DESAGREGADO DEL PRESUPUESTO ANALTICO

GASTOS DE LIQUIDACION

2.6.2.2.2.3 PERSONAL

RETRIBUCIONES COMPLEMENTARIAS-CONTRATOS A PLAZO FIJO

1 JORNAL
DEL EMPLEADO EVENTUAL

CARGO N DE PERSONAS CANTIDAD COSTO SUB TOTAL


INGENIERO CIVIL 1.00 1.00 5,000.00 5,000.00
CONTADOR PUBLICO COLEGIADO 1.00 1.00 4,000.00 4,000.00
ASISTENTE ADMINISTRATIVO 1.00 1.00 2,500.00 2,500.00
TOTAL 11,500.00

2 REFRIGERIO
DEL EMPLEADO EVENTUAL

CARGO N DE PERSONAS CANTIDAD COSTO SUB TOTAL


INGENIERO CIVIL 1.00 1.00 200.00 200.00
CONTADOR PUBLICO COLEGIADO 1.00 1.00 200.00 200.00
ASISTENTE ADMINISTRATIVO 1.00 1.00 167.39 167.39
TOTAL 567.39

2.6.2.2.2.4 BIENES S/.

1 MATERIALES DE ESCRITORIO

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


PAPEL BOND 80 GR A-4 MLL 4.00 45.00 180.00
ARCHIVADOR DE LOMO ANCHO PARA FORMATO A-4 UND 1.00 8.00 8.00
BORRADOR DE LPIZ FABER CASTELL UND 3.00 0.30 0.90
CD EN BLANCO UND 4.00 1.50 6.00
CORRECTOR UND 4.00 1.50 6.00
CUADERNO 100 HOJAS UND 2.00 4.00 8.00
USB UND 1.00 50.00 50.00
LAPICERO PUNTA FINA PILOT COLOR ROJO UND 2.00 2.50 5.00
LAPICERO PUNTA FINA PILOT COLOR AZUL UND 2.00 2.50 5.00
LAPICERO PUNTA FINA PILOT COLOR NEGRO UND 2.00 2.50 5.00
PORTAMINAS ROTRING UND 2.00 6.00 12.00
SELLO TRODAC UND 1.00 15.00 15.00
PAPEL BOND A3 MLL 0.25 250.00 62.50
TONER PARA IMPRESORA UND 1.00 250.00 250.00
FOLDER MANILA UND 5.00 0.50 2.50
RESALTADOR UND 1.00 3.00 3.00
TOTAL 618.90

2.6.2.2.2.4 SERVICIOS S/.

DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL


TRANSPORTE GLB 1.00 500.00 500.00
IMPRESIN PLANOS GLB 1.00 500.00 500.00
TOTAL 1,000.00

2.6.2.2.2.5 OTROS S/.


DESCRIPCIN UND. CANTIDAD P.U. SUB TOTAL
GASOLINA UNID 120.76 13.20 1,594.00
PETROLEO UNID 124.00 13.80 1,711.20
TOTAL 3,305.20
TOTAL GASTOS GENERALES S/.
ON.

DEL CENTRO POBLADO DE


ANDAHUAYLLAS

12,067.39

12,067.39

618.90

1,000.00

3,305.20
16,991.49
RESUMEN DE PRESUPUESTO TOTAL
FTE.FTO : TESORO PUBLICO
UNIDAD GEST. : MUNICIPALIDAD DISTRITAL DE TURPO

CONSTRUCCIN DE PISTAS Y VEREDAS DEL


CENTRO POBLADO DE SOCOSPATA DEL DISTRITO
PROYECTO DE TURPO ANDAHUAYLLAS APURIMAC.

RESUMEN DE PRESUPUESTO TOTAL

DESCRIPCION TOTAL S/.


COSTO DIRECTO 3,948,974.60
GASTOS GENERALES 10% 345,279.85
UTILIDAD 10% 315,917.97
SUB PRESUPUESTO 4,610,172.41
IMPUESTO GENERAL A LAS VENTAS 18% 829,831.03
COSTO TOTAL DE OBRA 5,440,003.45
SUPERVISION 3% 110,047.23
EXPEDIENTE TECNICO 3% 38,887.23
ESTUDIO DE LIQUIDACION 2% 16,991.49
TOTAL PRESUPUESTO 5,605,929.39