You are on page 1of 76

Chartered Institution of Civil Engineering Surveyors

CONSTRUCTION LAW REVIEW 20th Anniversary Issue

2016
Diales
uncompromised expertise

OUR TECHNICAL TEAM


DIALES TECHNICAL EXPERTS:
Q P
 rovide soundly reasoned Q W
 ork globally
and evidenced advice on Q R
 esolve difculties before
engineering and construction completion
disputes, often characterised by Q A
 ssist in resolving problems
a complex mix of interrelated after completion
design, construction and Q P
 rovide technical evidence in
engineering activities dispute resolution fora

Winners of the AI Magazine 2016 Dispute Resolution Awards for


Best for Engineering & Construction Expert Witness Services
For more information about our experts and services visit www.diales.com
or email info@diales.com. The DIALES App is also available to download from

BMW Goodwood Festival of Speed


Sculpture Centrepiece 2016
Sculptor: Gerry Judah
Structural Engineers:
DIALES Technical
2016
Contents
Features
04. Forewords 44. Performance bond calls
David Loosemore, Chartered Institution Stephanie Barwise QC and Omar Eljadi,
of Civil Engineering Surveyors, and Atkin Chambers
Julian Bailey, Society of Construction Law
47. FIDIC Red Book, sub-clause 2.4
07. Civil litigation: 20 years on Simon F Fegen, Leach Consultancy
Alexander Nissen QC, Keating Chambers
50. Could the payment provisions of the
11. Articial intelligence and law construction act displace capped payment
Simon Tolson, Fenwick Elliott LLP sums set out in letters of intent?
Edwina Acland, Sharpe Pritchard
16. Expert errors
John Mullen, Diales 52. An (e)stopped clock is right twice a
day: Is your engineers conduct a ticking
18. Foreseeing the unforeseeable
time bomb?
David Carrick, Hill International
Sarah McCann, Hardwicke
25. Employers claims under FIDIC
55. Harding v Paice: Rhyming slang for
Jonathan Hosie, Mayer Brown International
hard cases do not make good law?
28. Adverse weather David Sears QC, Crown Ofce Chambers
Emily Monastiriotis, Susanne Hose and
58. The making of IChemEs new
Simos Schizas, Bond Dickinson
professional services agreement
30. Payment provisions under LDEDCA 2009 John Challenger,
Peter Barnes, Blue Sky ADR Institution of Chemical Engineers

33. Proving extension of time claims 63. Concurrent delay: Time does not
Cover: Goja1 Manoj Bahl, FTI Consulting always equal money
Andrew Bayne, Centra Consult
36. Fixed payment schedules:
Grove v Balfour Beatty 66. With great risk comes...?
Chartered Institution of Civil Engineering Surveyors Alan Williamson, Schoeld Lothian Gordon Lees, JGL Consulting
Dominion House, Sibson Road, Sale,
Cheshire M33 7PP, United Kingdom
39. Knocked out on penalties 69. Contract administration for claims and
+44 (0)161 972 3100 www.cices.org
President: David Loosemore FCInstCES Kate Corby and William Jones, claims avoidance
Honorary Secretary: AH Palmer MBE FCInstCES
Chief Executive Ofcer: Bill Pryke HonFCInstCES Baker & McKenzie Andy Hewitt, Institute of Construction
Claims Practitioners
ICES Publishing
Edited, designed and produced by ICES Publishing.
42. Collateral warranties
ICES Publishing is operated by SURCO Limited, a subsidiary of Fenella Mason, Burness Paull 71. Index of Construction Law
the Chartered Institution of Civil Engineering Surveyors
Operations Director and Editor in Chief: Darrell Smart BEng
Professionals
dsmart@cices.org @darrellsmart
Managing Editor: Abigail M Tomkins BA(Hons)
atomkins@cices.org @amtomkins
Media Sales Manager: Alan Lees
alees@cices.org @alan_lees
Administrator and Subscriptions Manager: Joanne Gray
jgray@cices.org

Construction Law Review 2017 copy date: 31 May 2017.

Chartered ICES CharteredICES CInstCES CharteredICES


Published by the Chartered Institution of Civil Engineering Surveyors. Statements made and opinions expressed in this publication do not necessarily reect the views of the institution, its Council of
Management or other committees. No material may be reproduced in whole or in part without the written permission of the publisher. All rights reserved. Printed using PEFC-certied paper as part
of the institutions commitment to promote sustainable forest management. Printed by Buxton Press Limited, Palace Road, Buxton, Derbyshire SK17 6AE.
2016 Chartered Institution of Civil Engineering Surveyors. ISSN 0266-139X
4 Foreword Construction Law Review

A celebratory issue
20 years of the Construction Law Review

David Loosemore, President, Chartered Institution of Civil Engineering Surveyors

I TS been 20 years since the Chartered


Institution of Civil Engineering
Surveyors rst published the
Construction Law Review. That was in 1996
a year forever associated with another
construction law development, the Housing
Grants, Construction and Regeneration Act.
And what an act it was, one that continues
to create debate amongst the brightest legal
and construction professional minds.
20 years on, I am delighted to see three
of those minds still writing for us. David
Carrick, Alexander Nissen and Jonathan
Hosie wrote for us back in the very rst
Construction Law Review and join us again
here today. They, and all the authors
who have written for us over the last two
decades, understand the need to bring
legal developments to the attention of
commercial managers, quantity surveyors,
cost consultants, estimators, project
managers the people on the ground that
these very cases affect.
I am also pleased to see our colleagues
at the Society of Construction Law once
again opening this publication. We learn
much operating in our own specialist
elds, but it is so important to look up and
share that knowledge, and friendship, with
Then and now... The articles of David Carrick, Jonathan Hosie and Alexander Nissen.
those around us.
For those of us involved in civils
projects, 20 years is not such a long time.
You only have to look at the newly opened
Gotthard Base Tunnel to see what takes
20 years to create. Yet throughout these
major projects the HS2s, the Crossrails,
the Millau Viaducts, the Hong Kong
ZhuhaiMacau Bridges are professionals
enthused and impassioned by how they are
crafted and intrigued by the mechanisms of
interaction that go on between the myriad
bodies that are involved.
Construction, and the law that governs
it, is a marvellous arena to work in. Heres
to the next 20...

David Loosemore FCInstCES


President, Chartered Institution of Civil
Engineering Surveyors
President@cices.org
www.cices.org
@CharteredICES
2016 Foreword 5

Does construction law matter?


Julian Bailey, Partner, White & Case, and Chair, Society of Construction Law

There are two matters at the core of


SCLs activities. First, SCL holds lectures
around the UK (and even abroad) on
current construction law issues. Since its
foundation, SCL has provided a continuous
programme of seminars and conferences
where leaders in the eld lecture on and
debate the latest issues.
Secondly, to complement these lectures
and conferences SCL publishes papers
that are distributed to all members. The
societys papers offer the latest thinking on
the most important construction law issues
of the day. Additionally, SCLs website
provides a vast repository of published

D
papers that can be accessed and searched
OES construction law matter? by the societys members.
Anyone who reads the articles Perhaps the unique and most
in this Construction Law important feature of SCL is that it is open
Review would unhesitatingly answer yes. to all comers who have an interest in
Construction and engineering projects, construction law. So, our members are
whether they be small or large in scale, not just lawyers, but include architects,
are important enterprises in all countries. engineers, surveyors, property developers,
They are important because they are claims consultants, adjudicators, expert
fundamental to a countrys needs and witnesses and many others. The
ultimately to its prosperity. environment of SCL is therefore an
Concomitantly, the law provides an interdisciplinary one.
essential framework for the delivery of Happily, the environment of SCL is also
projects. Construction and engineering a very sociable one, and the society holds a
contracts dene what work is to be done, great number of regular and ad hoc events
how much is to be paid for it, and what is which allow our members to network
to happen if the project does not proceed and to meet up with friends and contacts.
according to plan. Completing the picture SCL has much to offer and, if you are not
is a vast body of statute and case law already a member, I warmly encourage you
which determines, in varying degrees of to join the society.
detail, the rights and obligations of parties
to construction and engineering contracts. Our world
Construction law is therefore important. Construction law matters, and if you are
It is also vast and highly nuanced. There is interested in construction law then the
much to learn about it, and therefore much Society of Construction Law is for you.
to discuss. With that introduction, may I encourage
you to start turning the pages of this
SCL Construction Law Review, and to explore
The Society of Construction Law was the richness of issues that exist in our
founded in 1983 in the kitchen of John construction law world.
Tackaberry QC. The germ of Johns idea, to
create a forum for promoting the education Julian Bailey, Partner, White & Case, and
and discussion of construction law issues, Chair, Society of Construction Law (UK)
quickly took hold. More than three decades julian.bailey@whitecase.com
later the UK SCL now has more than 2,500 www.whitecase.com
members, and worldwide there are SCLs on www.scl.org.uk
every continent. @SCL_UK
Specialist Advocates
to the Industry

Commercial Dispute Resolution | Construction & Engineering


Energy & Natural Resources | Infrastructure & Utilities
International Arbitration | IT & Technology
Offshore Construction & Marine Engineering
PFI/PPP | Professional Negligence | Property | Public Procurement

www.keatingchambers.com | +44 (0)20 7544 2600 | clerks@keatingchambers.com


Keating Chambers, 15 Essex Street, London, WC2R 3AA, United Kingdom
Follow us: @keatingchambers
2016 20 Years 7

Civil litigation: 20 years on


Alexander Nissen QC, Barrister, Keating Chambers

W RITING in the very rst volume of this journal,


published in autumn 1996, I addressed the nal
report on the civil justice system produced by Lord
Woolf and its likely impact on litigation generally and ofcial
referees business specically. The intervening 20 years have seen
signicant changes to the landscape of construction litigation,
much of which related to the introduction of the Civil Procedure
Rules 1998 as a result of Lord Woolfs report.
Delivering a paper to the Society of Construction Law in March
2007, Mr Justice Jackson (now Lord Justice Jackson) commented
on the impact of the 1998 Woolf reforms:

Although it is fashionable to carp about detailed glitches


and infelicities in the Civil Procedure Rules 1998, it is worth
pausing for a moment to note the huge benets which they have
brought to court users. The scandal of civil litigation dragging
on inefciently for many years and then being struck out for
want of prosecution has come to an end. An increasing number
of disputes are now resolved without any formal legal process
at all. Pre-action protocols (one of Lord Woolfs innovations)
lead to many cases settling before they start. Mediation is now
encouraged by the courts and often leads to earlier settlements. 1

While the impact of the reforms was undeniably dramatic, whether


they have all beneted the process of litigation is a matter of
perennial debate amongst practitioners and court users. This article
will review some of the key changes to construction litigation that
have occurred in the last 20 years and looks to its future prospects.

TCC guide and pre-action protocol


Since the introduction of the Civil Procedure Rules in 1998,
litigation in England and Wales has been radically transformed.
While many of the measures implemented by the CPR had been

A look at two decades pioneered in the Technology and Construction Court, construction
litigation has not been immune to change. The court now has a
of construction law much greater role in the management of litigation, with the aim of
enabling the court to deal with cases justly and at proportionate
cost. 2 The CPR is supplemented by the TCC guide, which is
currently in its second edition with a new edition expected shortly.
One of the most signicant new measures introduced by
the Woolf Reforms was the use of pre-action protocols. These
require the parties to a dispute to engage in reasonably extensive
correspondence, setting out the basis for the claim and the
rejection of it, before they are allowed to issue court proceedings.
The aim of this has been to crystallise the matters in dispute at
the earliest stage, so that parties can attempt to settle, or at least
understand, the case which they have to meet.
A unique feature of the TCC pre-action protocol was the
provision for at least one pre-action meeting between the parties.
1
Mr Justice Jackson, The Tower of Babel: What Happens when a Building Contract
Goes Wrong SCL Paper 136, March 2007
2
CPR, r1.1(1)
8 20 Years Construction Law Review

One consequence of the protocol has been the front-loading of


costs. This has been particularly acute in construction litigation,
where a great deal of time and costs can be spent in attempting
to set out the nature of the dispute. Parties have often got bogged
down in protocol requirements and it has sometimes felt as
though the process wastes time and cost rather than saves it. As a
result, the two organisations which represent construction lawyers
Technology and Construction Bar Association (TECBAR) and
Technology and Construction Solicitors Association (TeCSA) are Failure to le a costs budget on time results in
working with the TCC to develop a new, streamlined and more the rather draconian position whereby the party is
cost effective version. This is likely to be published before the end
of the year. Whilst it is expected to retain the meeting, the process deemed to have led a budget which claims court
will be shorter and more focused. Parties will be able to opt out of
it by agreement.
fees only.
The effect of the pre-action protocol can be seen in the number
of claims issued in the TCC. In 1996, 1,778 writs were issued.3 In
of costs budgets and, when assessing costs at the conclusion of
2014-2015 there were a total of 948 claim forms issued in London
the litigation, it will not depart from the budgeted gures unless
and the various regional TCCs.4 In all likelihood, a substantial
there is good reason to do so. Failure to le a costs budget on
proportion of the claims issued back in 1996 would have never
time results in the rather draconian position whereby the party is
made it to trial, and it may be that the same amount of cases are
deemed to have led a budget which claims court fees only.6
making it to trial now. The difference could be accounted for by
This regime does not automatically apply to claims which are
the fact that, prior to the requirements of the pre-action protocol,
valued at more than 10m. However, the court has the power to
parties would often issue a writ simply as part of the negotiation
make costs management orders which can require the ling and
process. Now, because of the increased costs which must be
exchange of costs budgets. In at least one recent decision, the
incurred before issue, parties are incentivised to negotiate before
TCC has emphasised that the courts power to make such orders
resorting to issuing proceedings.
is unfettered, that there is no presumption that costs management
will not be ordered and that it should be considered in all cases.7
Expert evidence
The obligation to prepare accurate costs budgets has
Another area where substantial change has been felt is the use of
undoubtedly added to the administrative burden of litigation and
expert evidence; a regular feature of construction litigation. Both
has received a mixed response from the legal professions. Lord
the CPR and the TCC guide give the court far more control over
Justice Jacksons conclusion at the time of the introduction of
the use and presentation of expert evidence. For instance, the
his reforms was that there was little appetite amongst lawyers
court has the power to order the instruction of a single joint
for engaging with costs in a detailed way; many regarding such
expert on any given issue. Where there are separate experts, the
matters as the exclusive preserve of specialist costs lawyers and
court will usually require them to meet prior to the trial to discuss
accountants. That said, the pilot schemes for costs management
their respective evidence and produce a joint statement setting
which were run in the Birmingham and London TCCs, were
out the areas in which they agree, the issues upon which they
considered a success. Despite initial scepticism about the value
disagree and the reasons for this disagreement. This is intended to
of budgets and the provision of unrealistic estimates, many
clarify the matters actually in dispute and narrow the issues before
solicitors acknowledged that budgets made them focus on the
the court.
future conduct of the litigation, the tactics which they adopted and
The court also has control over the manner in which expert
whether settlement should be considered.8
evidence is presented. It is possible for experts to give concurrent
The next development in this area may be xed recoverable
evidence (colloquially known as hot-tubbing) so that in disputes
costs. In a recent speech dramatically entitled Fixed costs the
involving multiple technical issues, the court can more easily
time has come,9 Lord Justice Jackson called for the introduction of
identify what the opposing expert evidence is on a given issue.
a xed costs regime which would apply to all civil claims worth
The use of hot-tubbing varies widely across the various TCC
less than 250,000. Prescribed total fees rather than hourly rates
courts, with some judges expressing enthusiasm,5 and others rarely
would be set for each stage of litigation, increasing in a series of
using it. The judiciary is now undertaking an enquiry into the
bands linked to the value of the case.
varied uptake of hot-tubbing to see if it could be more frequently
The supposed benet of this approach, apart from aiming
used to further the efcient conduct of litigation.
to ensure that only costs proportionate to the sums at stake are
incurred, is that it will alleviate the burden of costs management
Costs management
for lower value claims. This recognises that for cases worth less
The other signicant procedural reform which has been
than 250,000, attempting to control costs by means of costs
introduced since 1998 is costs management. After completing
management orders and costs budgets can be counterproductive.
a review of costs in civil litigation in 2013, Lord Justice Jackson
Under the xed costs regime there would be no need to engage in
introduced reforms to the manner in which costs are dealt with
budgeting, as a relatively simple assessment could be conducted
in civil litigation. There has been a complete change in emphasis,
at the conclusion of the litigation. It seems that the principle of
away from retrospective review of costs, towards prospective
xed recoverable costs for low value claims has the backing of
costs budgeting.
the senior judiciary.10 On the other hand, given the welter of
The mainstay of these reforms is the obligation to le costs
objections from the legal profession, it remains to be seen whether
budgets in almost all cases which are worth less than 10m. The
its time has truly come.
parties are bound to attempt to agree their budgets between
6
themselves and if this is not possible the court will approve the CPR PD 3E
7
budgets. The court is given a hands-on role in the management CIP Properties (AIPT) Ltd v Galliford Try Infrastructure Ltd (2014) EWHC 2546 (TCC)
8
F Sinclair QC et al, The Pioneering TCC: Pushing the Boundaries on Litigation Costs
3
Dr R Gaitskell QC, Trends in Construction Dispute Resolution, SCL Paper 129, SCL Paper D185, December 2015
9
December 2005, p3 Jackson LJ, Fixed Costs The Time Has Come IPA Annual Lecture, 26th January
4
TCC Annual Report 2014-2015, p8 2016
5 10
Her Honour Judge Frances Kirkham CBE, Reections on Life as A Judge of the Senior judges oppose singling out clinical negligence for xed costs as consultation
Technology and Construction Court, SCL Paper D134, April 2012 nears, Litigation Futures, 23rd May 2016
2016 20 Years 9

for the users of the Rolls Building (which


the TCC shares with the Commercial Court
and Chancery Division) so as to create a
new Business Court with ticketed judges
for particular types of case.

Adjudication
The eld of construction litigation has
Despite the passage of time, the TCC seems to be also been affected by the creation of the
in no immediate danger of losing its reputation adjudication regime recommended by Sir
Michael Lathams report Constructing the
as a pre-eminent venue for the resolution of Team. The resulting adjudication system
implemented by the Housing Grants,
construction disputes. Construction and Regeneration Act 1996
(as amended by the Local Democracy,
Economic Development and Construction
:OVY[LYHUKL_PISL[YPHSZZJhemes Act 2009) gives parties to a construction
The TCC, along with other courts in the Rolls Building, is piloting contract the option of referring disputes
two new schemes; the shorter trials scheme and the exible to adjudication, rather than waiting for
trials scheme. arbitration or litigation. This is a speedy
process, where the adjudicator is usually
Shorter trials scheme required to deliver a decision within 28
The shorter trials scheme is intended to allow speedy resolution days of being appointed. In most cases the
of cases that do not involve allegations of fraud or dishonesty,
dispute is resolved entirely on the papers,
multiple issues or parties, intellectual property claims or public
without any oral hearings.
procurement claims. Its goal is to have the trial within eight
The scheme has been an enormous
months of the case management conference.
success. While it has generated a eld of
The trial itself is restricted to four days, all applications are
litigation all of its own, it has reduced the
dealt with on the papers and the pre-action protocol does not
number of construction claims led in the
apply (though parties do have to send the equivalent of a letter of
TCC. Domestic construction arbitrations
claim). All of this is overseen by a docketed judge who is assigned
are virtually extinct. While the decision
at the case management conference and remains with the case
of an adjudicator is only temporarily
throughout the process. There are shortened timescales for the
binding with parties retaining the option
service of pleadings (which can be no longer than 20 pages).
of re-ghting the dispute in arbitration or
Parties only have to disclose documents upon which they are
litigation anecdotal evidence suggests
relying and/or those ordered after a request for specic disclosure.
that in 80% of adjudications, the parties
Evidence is by witness statements which can be no longer than
content themselves with the decision of
25 pages and expert evidence is by written report. After trial the
the adjudicator.11
judge will endeavour to give judgment within six weeks.
The other signicant feature, apart from the lack of a pre-action
protocol, is that the costs management provisions of the CPR do
Conclusion
A great deal has changed in the world of
not apply. Costs will usually be summarily assessed on the basis of
exchanged costs schedules. construction litigation since 1996. Many
It is too early to determine how this scheme will function, but of the reforms which have been applied
it has the potential to provide great reductions in both costs and to civil litigation generally have been
time for those with straightforward cases. pioneered in the TCC. This is part of a long
tradition of construction litigation being at
Flexible trials scheme the forefront of procedural reform.
The exible trials scheme is more focused on the manner in which It was in the old Ofcial Referees
evidence is gathered and presented. The scheme itself is largely Courts that the use of written witness
facilitative; it prescribes few rules, but allows parties to agree on a statements as evidence, the early exchange
variety of issues relating to the evidence. of expert reports, and the use of Scott
Parties must disclose evidence upon which they rely and which schedules were pioneered all of which
they know to meet the normal disclosure test; though there is no still form key parts of construction litigation
obligation to conduct searches for evidence which may meet the today. Despite the passage of time, the
test. Witness and expert evidence is given in written form and oral TCC seems to be in no immediate danger
evidence is limited to issues identied at the case management of losing its reputation as a pre-eminent
conference. Oral submissions and cross-examination are subject venue for the resolution of construction
to time limits, which are either agreed or directed. Where oral disputes. I look forward to writing about
evidence is necessary, it is limited to the principal parts of a developments in 2036!
partys case.
Alexander Nissen QC, Barrister,
The Briggs Review Keating Chambers
At the present time there is an additional review of the civil anissen@keatingchambers.com
courts structure being undertaken by Lord Justice Briggs. Matters www.keatingchambers.com
within his review include the creation of an online court, which @keatingchambers
is unlikely to affect users of the TCC; a possible weakening of the
division lines between the Queens Bench and Chancery Division; 11
Dr R Gaitskell QC, Trends in Construction Dispute
and the question of whether there ought to be a unied structure Resolution, SCL Paper 129, December 2005
Accelerated Membership for
RICS Fellows and Members

Belong here

Is the focus of your work in the civil engineering or geospatial industries?


Join the chartered professional body that specialises in these sectors
and only these sectors
Industry respect and recognition, specialised CPD events and networking
Members and fellows of the Royal Institution of Chartered Surveyors who can demonstrate significant
experience in the civil engineering and geospatial sectors may apply directly to ICES on the basis of a
straightforward desk assessment.

Contact: Membership Coordinator


Chartered Institution of Civil Engineering Surveyors
+44 (0)161 972 3100
membership@cices.org
www.cices.org

The Chartered Institution of Civil Engineering Surveyors is a registered educational charity.


2016 AI 11

(Y[PJPHSPU[LSSPNLUJLHUKSH^
Simon Tolson, Senior Partner, Fenwick Elliott LLP

C OMPUTER use and digital databases of any real practical


use started in the legal profession coincidentally from
about the time when I was an undergraduate law student
in 1979. Back in those days one had an operator and paid line
time by the minute. It was hit and miss even in a university
faculty. It was slow progress. It was all code input-based and one
marvelled if anything useful came out, more often it didnt.
I recall that Lexis started providing its services to the Law
Society and university libraries in about 1983. Then Windows
3.1 came on the scene in about 1993. Windows 95 arrived on
the world stage the year before its name suggests. By 1995,
some lawyers like me became mobile with their legal data. I
was using a Psion Organiser with a QWERTY keyboard, with
a comprehensive self-typed construction law database; no cut
and paste then! Corporate systems started to become available
in the late 1990s as the World Wide Web developed and steadily
accelerated exponentially over the past 18 years or so.
I would say that in or about 1996 (the year I sent my rst
email), Fenwick Elliott was one of the rst law rms to use it in
London and boy was it slow (no fast broadband then). But we
had the big bang when the legal profession, and how it accessed
material, began to change forever. It changed law in a way
nothing else had for c.300 years.
Simple memory typewriters were with us in 1983 and word
processors in 1990, but processing power, the commercial
emergence of email and personal computers and the internet have
been the facilitators for what we see today. Everything is digital
and many of us work virtually paperless. Our desk is a dynamic
creature that moves up and down, our ultra-at twin screens and
tablets are where we scribe our real craft or to some sophistry!

AI today
Believe it or not law rms are really investing in articial

Finding the legal intelligence (AI); the capability of a machine(s) to imitate


intelligent human behaviour. There has even been speculation
profession of this that law is ripe for uberisation,1 becoming the next target of
technological transformation. The millennials generation is
millennium pushing the changes hardest and law rms are making a dash
to harness the power of cognitive computing and the natural
language processing capabilities of computers; investing heavily
in AI to automate the mundane tasks that are part and parcel of
the law and legal services. Professional services generally rely on
a lot of data and information, and a relatively small amount of
judgment, which means tasks can be speeded up considerably.
However, robots are unlikely to replace lawyers in court, but they
can prepare papers for hearings and do other clever things with
massive data.
The recent media fever about AI has been inevitable. This
vision has conceivably come a step closer with the arrival of IBM
1
A recent study by Jomati, Civilisation 2030: The Near Future for Law Firms, points
out that after long incubation and experimentation, technology can suddenly race
ahead at astonishing speed.
12 AI Construction Law Review

We had the big bang when the legal profession, and how it accessed
material, began to change forever. It changed law in a way nothing
else had for c.300 years.

Watson2 and Richard and Daniel Susskinds latest book, The Future of the Professions,
which predict an internet society with greater virtual interaction with professional services
such as doctors, teachers, accountants, architects and lawyers.
Linklaters and Pinsent Masons are the latest law rms to announce publicly their
investment in AI, as the legal profession tries to automate the most mundane tasks
that traditionally have been the preserve of more junior lawyers. Pinsent Masons has
developed a program that reads and analyses clauses in loan agreements. Its TermFrame
system also helps guide lawyers through transactions and point them towards the correct
precedents at each stage of a process.
Another law rm, Dentons, has set up NextLaw Labs,3 a virtual company which looks
at the application of technology within the law. It has invested in ROSS,4 an IBM Watson
powered legal adviser app, that streamlines legal research, saving lawyers time and
clients money. BLP and Linklaters have signed on with developer RAVN5 and developed
a computer program to sift through various UK and European regulatory registers to
check client names for banks. In transactional work, LONald can, for example, send
an enquiry to Companies House to check if the address in a document matches the
company number. If the address is out of date, the computer will ag it for review. The
team will then consider all agged documents in one go at the review stage. It thus
converts unstructured data (for example, contracts) into structured output (for example, a
spreadsheet) in a fraction of the time (a few seconds) it takes a human and with a higher
degree of accuracy! The lawyers then do the higher-level strategic review to make sure
nothing is missed.
Professor Richard Susskind, who is also IT adviser to the Lord Chief Justice, has
predicted radical change in the legal sector, pointing out that intelligent search systems
could now outperform junior lawyers and paralegals in reviewing large sets of documents
and selecting the most relevant. Prof Susskind said at a conference recently6 that he
believes the legal profession had ve years to reinvent itself from being legal advisers to
legal technologists and criticised law schools for churning out 20th-century lawyers.
Prof Susskind stated that over the course of the next decade, AI would move forward
so quickly that systems themselves would be able to assess, diagnose and respond to
the legal problems posed by clients. But instead of suggesting that this was a threat to
the profession, he instead claimed that it was an opportunity to become engineers of
knowledge, and to shape the future of the profession in a positive way. He stated:

For the next ve years, the legal profession will work on using better human-resource
models, delegate to paralegals, move to better locations and give lawyers far better
systems... It is not that there are no jobs in the future, but the 2020s will be a decade
of redeployment not unemployment. It is not an emergency but over the next ve years
we have to prepare. More and more legal services will be enabled by the support of new
technology. You can say that is for the technology industry to sort out, or you can be
part of the technology industry.

Where next?
So where is all this headed? Well, for sure, away from where we are now. Much the same
applies with how building information modelling can expedite design improvement and
2
It is amazing that Watson analyses unstructured data, understands complex questions, and presents answers and
solutions. www.ibm.com/smarterplanet/us/en/ibmwatson/
3
A global collaborative innovation platform set up in May 2015 focused on developing, deploying and investing in
new technologies and processes to transform the practice of law around the world. www.nextlawlabs.com/
4
ROSS is an articially intelligent attorney to help power through legal research. www.rossintelligence.com/lawyers/
5
RAVN helps you make sense of the explosion of big data in your organisation through state-of-the-art software
solutions. www.ravn.co.uk/
6
Law Societys Law Management Annual Conference: http://communities.lawsociety.org.uk/law-management/events/
law-management-section-events/law-management-section-annual-conference-27-april-2016-london/5052637.fullarticle
2016 AI 13

Robots are unlikely to replace lawyers in court, but they can prepare
papers for hearings and do other clever things with massive data.

aid the best selection of materials and/or provide the opportunity of testing and assessing
different design alternatives that may impact say on the energy performance of buildings.
I know for a fact computer modelling techniques and stochastic analysis7 in hydrogeology
are now helping developers address run-off and drainage issues in the UK8 and provide
real-time ood forecasting from catchment to national scales. In the law, text analytics and
machine learning can be incredibly helpful in enabling the data to tell its story, and what
we are nding is that computers are learning in large data cases they can be better
than human lawyers, particularly tired human lawyers.
Predictive coding enables users to sample data such as on a large project and identify
what is relevant. Through sampling, the program is able to learn which documents are
relevant. This process greatly reduces the time needed for e-discovery and document
review because the program is searching for concepts as opposed to simple keywords.
Indeed our own Law Society president, Jonathan Smithers, is bang on the money on
this issue. He acknowledges we live in complicated times. Complicated times require
the knowledge and advice of the global legal community, practical experts who can
develop long-lasting solutions to help us mitigate the crisis micro-economically, macro-
economically and geopolitically. The legal community, however, is often called too late.
We are involved when our clients have reached crisis. We are called to re ght, we are
the A&E department. At this point, the role of the legal professional may be rather limited.
Bright lawyers and astute law rms need to ask themselves, what are the common
developing legal issues coming over the skyline? The impact of technology on the law
is one such issue. We live in a globalised world. The exponential growth of technology
has created a new world order. It affects how we talk, how we learn, how we trade. The
world is, quite simply, more interconnected than ever and using big data is key.
The future is not desolate. The globalised world has also brought hope and
opportunity. Technology has already restructured the way we do business and
signicantly impacted the practice of law. We are already using technology to
communicate with our clients more quickly, to manage their data and to make our
businesses more efcient. Skype, instant messaging, WebEx online meetings and email are
part of our everyday working lives.
AI will become more embedded in our lives. In many ways, it is already part of the
way we interact with each other and with the world. When ebay suggests products you
may like, that is AI. Siri on your iPhone, thats also AI. Anti-lock braking systems on cars
and systems that wake you up as you nod off; AI. It is already everywhere. But, what
does this mean for lawyers?
Many of our business clients Google their legal problems before they come to see us.
Pro bono portals are available, helping people to access legal advice early. Of course,
self-diagnosis can never be a replacement for legal professionals any more than it can for
physicians. The functions we carry out as lawyers extend far beyond dispensing black-
letter legal advice. Lawyers will, however, need to consider the ethical and legal dilemmas
brought by AI in much the same way that architects and engineers are doing with
building information modelling and intellectual property.

Ethical duties
Lord Neuberger, president of the Supreme Court, only last week called for a debate on
the ethical implications of AI and for greater prominence for ethics in legal training.9
Law schools will therefore need to pull up a sock or two. Lord Neuberger made his plea
for greater prominence for ethics training both on university law courses and professional
legal training courses.
7
Having a random probability distribution or pattern that may be analysed statistically but may not be predicted
precisely
8
The Groundwater Foundation, a non-prot organisation that educates people and inspires action to ensure
sustainable, clean groundwater for future generations
9
Lord Slynn memorial lecture, 15 June 2016: www.supremecourt.uk/docs/speech-160615.pdf
14 AI Construction Law Review

Lord Neuberger said that the earlier and more effectively potential professional lawyers
and advocates could be trained to appreciate and understand the importance and nature
of their ethical duties, the stronger a legal profession we will have, and the stronger the rule
of law will be.
Back in 2013, the judge urged the legal profession not to lose sight of its fundamental
principles in the rush for modernisation, warning about the risks of pressure from
hard-nosed businessmen who may invest in law rms. The legal profession should be
preparing for the problems and opportunities that may arise from such an enormous
potential area of development, and one of the most difcult challenges will be to consider
the potential ethical implications and challenges.
Whilst Lord Neuberger does not fully embrace the Susskind view of future legal life, he
does say that the Susskinds point out that this potential development has ethical, as well
as employment, implications and they rightly call for a public debate on the issue. Lord
Neuberger likewise warned of increased potential for ethical conicts where alternative
business structures (ABS) were owned by non-lawyer investors who are ultimately
only concerned with the bottom line. The investors will often have no experience of, or
interest in, the lawyers ethical duties.

When it goes wrong


As computers take on more and more responsibility, one also has to ask the question of
where the liability lies when things go wrong. Volkswagen expects the rst self-driving
cars on the market by 2019.10 These self-driving systems may need to make split-second
decisions that raise real legal questions. Driverless vehicles can legally be tested on public
roads in the UK today. The UK is uniquely positioned to become a premium global
location for the development of these technologies.11
10
In April 2016 six convoys of semi-automated smart trucks arrived in Rotterdams harbour after an experiment its
organisers (DAF, Daimler, Iveco, MAN, Scania and Volvo) say will revolutionise future road transport on Europes
busy highways. Watch out for truck platooning
11
The Department for Transport review of existing legislation found that our legal and regulatory framework is
not a barrier to the testing of automated vehicles on public roads. Real-world testing of automated technologies is
possible in the UK provided a test driver is present and takes responsibility for the safe operation of the vehicle; and
that the vehicle can be used compatibly with road trafc law. North America has been the rst country to introduce
legislation to permit testing of automated vehicles, but only four states have done this. 15 states have rejected bills
related to automated driving. In Europe, only Germany and Sweden are known to have completed a review of their
legislation in this area

Pace. Agility. Focus.


Our specialist construction and energy lawyers
have the experience and insight to act quickly,
think creatively and advise commercially,
whatever the scope of your project, both in the
UK and overseas.

Acute legal analysis with


practical commercial advice
www.fenwickelliott.com
2016 AI 15

Responding to the technological realities of the 21st century is an imperative. A child


suddenly runs into the road and the car has to choose; hit the child or swerve into an
oncoming truck. How does the vehicle decide? Who decides what the car decides? Ditto
the JCB on a construction site; does it avoid the trench with a man in it or does it strike
the building if it cannot avoid both? And who is liable if it chooses the wrong one, the
plant owner or the programmer? These are questions for lawyers. It is for us, the legal
experts, to answer these questions now. Lawyers should not be re-ghting.

What about now?


We must identify and solve the legal issues of tomorrow, now. And if we want to achieve
this we must be:

Explorers, not mere voyagers.


Architects, not plain builders.
On the front line, not in the pursers ofce.

We live in exciting times. The legal community must clinch this:

We dont have to repeat the past.


We dont have to relive the present.
We can shape the future.
If we dont others will.
Shepherd or sheep, its your choice.

The world will always be complicated. But if lawyers take the time to put their
minds together, to learn from one another, they can x pervasive problems like new
technological solutions. If we are successful, we will make the legal profession worthy of
this millennium, all the more so with regard to the construction industry.

Simon Tolson, Senior Partner, Fenwick Elliott


stolson@fenwickelliott.com
www.fenwickelliott.com
@fenwickelliott

The Journal of the Chartered Institution of Civil Engineering Surveyors

CIVIL ENGINEERING SURVEYOR

Subscribe Today
Includes the annual supplements
CONSTRUCTION LAW REVIEW
GEOSPATIAL ENGINEERING

Call +44 (0)161 972 3110 45.60 (UK)


ces@cices.org 50.75 (Europe)
or subscribe online at www.cices.org/journalsubs 55.85 (Rest of the World)
16 Expert Witness Construction Law Review

Expert errors
John Mullen FRICS FCInstCES FCIArb, Quantum Expert and Principal, Diales

I T can be of some frustration, to those of us whose main


market is international arbitration, that arbitral awards are
private and that some experts do not receive the censure
that they deserve. It appears that, in any event, many international
arbitrators are reluctant to comment on the expert evidence
provided to them, with awards just focusing on which evidence
they prefer and adopt. Perhaps it is considered that, in the privacy
of an arbitration, there is no wider purpose to recording such
criticisms. Alternatively, perhaps the tribunals are concerned
that criticisms of a partys expert may be construed, in some
jurisdictions, as evidencing bias against that party.
The frustration this causes is exacerbated by the poor quality and
hired gun nature of much of the expert evidence presented in
international arbitrations. Contrary to the impression one might
gain from reading certain Technology and Construction Court
judgments, the UK can be proud of the quality of much of the
expert evidence that its practitioners provide around the world.
When reading some of the TCC judges more damning comments
on the experts appearing before them, it is often tempting to
recall examples of similar, or worse, testimony in international
arbitrations that passed without published critical comment.
Under English law, the role and duties of experts were set
out 20 years ago by Justice Cresswell in the Court of Appeal in
National Justice Compania Naviera SA v Prudential Assurance
Company [Ikarian Reefer] (1995) 1 Lloyds Rep.455. In the courts of
England and Wales, and in Scotland, their Civil Procedure Rules
(CPR) set out the procedural requirements of expert evidence.
Those CPRs followed Lord Woolfs reports of the mid-1990s,1
which criticised the unnecessary costs and lack of neutrality
of much expert evidence. Thus, in the domestic markets the
requirements of experts are well developed and the courts
criticisms are made against that background.
Internationally, few jurisdictions have developed, through

Pitfalls in picking the their legislature or precedents, such a detailed framework for
experts to work in. However, this is not to say that experts will
wrong expert witness not be suitably chastised where appropriate. As with the England
and Wales judgments, some overseas judgments can be similarly
informative as to the potential pitfalls for experts and those
instructing them. They also might offer some light relief for those
suffering published criticism in the UK, or frustrated at the lack of
it in international arbitration.
The world took an understandable interest in last years South
African proceedings in the Oscar Pistorius trial. Whilst there is
disappointment in some quarters at his sentence, he appears to
have achieved that outcome notwithstanding the quality of the
expert evidence adduced by his team.
Oscar Pistorius chief witness was a former police ofcer, Roger
Dixon,2 who gave expert evidence on ballistics, gunshot wounds,
pathology and blood splatter. He was also involved in both audio
and visual tests. However, he admitted to not being an expert in
1
Access to Justice, Interim Report, June 1995; Access to Justice, Final Report, July 1996
2
Who unfortunately did not gain his early training in Londons Dock Green area
2016 Expert Witness 17

any of these elds, but was actually a


forensic geologist. On the detail of his
investigations, he admitted to the
following failings: adhered to international standards that they extradited Shrien
Dewani to South Africa for trial. The Oscar Pistorius judge
He had not done his testing with any described Miss Vergeers evidence as: Slapdash, disappointing
light meters or equipment other than and had a negative effect on her credibility as a witness.
his own vision. Whilst the high prole nature of the Oscar Pistorius case drew
He testied on a recording of gun international media attention to the poor nature of some of its
shots and a cricket bat striking a door, expert testimony, a judgment of rather more signicance locally
although he was not there when is that of the Supreme Court of Appeal of South Africa in the
the tests were conducted and knew recent case PriceWaterhouseCoopers Inc & others v National Potato
nothing about the sound equipment Co-operative Ltd & another (451/12) (2015) ZASCA 2 (4 March 2015).
used. This involved a claim against PriceWaterhouseCoopers (PwC) for
He overlooked and omitted Oscar alleged negligent audit services, in which the rst respondent
Pistorius height when conducting the relied for its entire case on the expert testimony of David Collett.
test, which meant that his assistant, Before assessing the experts evidence, the court set out the
while kneeling, was a good 20cm standards to be expected of expert testimony. The judge started
shorter than Pistorius on his stumps. by quoting from Justice Cresswell in the Ikarian Reefer case and
Regarding bres he claimed to have noting how the principles therein echoed those set out in a South
found in a door that matched Pistorius African case Stock v Stock (1981) (3) SA 1280 (A). The Canadian
socks, he admitted that he had only judgment of Justice Marie St-Pierre in Wightman v Widdrington
seen photographs of the socks but had (Succession de) (2013) QCCA 1187 (CanLII), was then quoted from as
never examined them or looked at the being helpful to the judge. The South African court found that
bres concerned under a microscope. Mr Colletts evidence did not measure up to those standards.
Mr Colletts only practical audit experience was when he was
Furthermore, he never drafted a formal training, 22 years earlier. The detailed criticisms of his performance
report on his evidence, but made notes are lengthy, but include describing some of his opinions as
on his computer, which he had given to risible and his approach as pedantic, rigid and dogmatic. The
the defence. criticisms cover most of the potential errors that an expert witness
A second expert relied upon by Oscar might make, but included:
Pistorius, Tom Wolmarans, gave evidence
on the noises made by gunshots and Contradicting himself.
cricket bats, but admitted that: Seeking to avoid answering hypothetical questions.
Only reluctantly making concessions.
He was not an expert in any of Mostly basing opinions on hearsay evidence.
these elds. Acting as an advocate advancing his clients case.
In particular, he was not a sound Not giving evidence objectively, but to justify the conclusions
expert. he had formed.
He had a hearing defect. Disregarding or discounting facts inconsistent with his own
His gun jammed on rst test. theories or conclusions.
He was unable to record rapid Lacking independence from his client in that he:
gun re. -Undertook the original investigation leading to the claim.
The quality of his recordings was -Was involved in the gathering of evidence and pleaded
affected by frog sounds in the formulation of the claim.
background. -Giving evidence in areas where he lacked expertise.
He could not repeat the recordings,
as the door he had used had been The judge concluded that, when tested against the standards
broken. enunciated by Justice Cresswell and Justice St-Pierre, Mr Colletts
evidence did not satisfy the tests for admissibility as expert
A third expert appeared for Oscar Pistorius evidence and was of little or no value in this case.
in relation to sentencing. Miss Annette In conclusion, while experts practising in the UK courts may
Vergeer was a social worker and registered feel aggrieved at their vulnerability to public reproach for their
probation ofcer at the Department of efforts, particularly where they also observe what happens in other
Correctional Services. She gave testimony jurisdictions, they might take some comfort from those criticisms
on the suitability of South African jails, that are published in other jurisdictions. Those judgments provide
warning that Pistorius would be at risk a useful resource for those acting as experts to understand the
from slippery oors; toilets and showers pitfalls of the role.
with no hand rails; and having his Similarly, those instructing experts might consider how it came
prosthetic leg taken away. However, she to be that Messrs Dixon and Collett were instructed in the rst
admitted that her evidence was based on place to roles for which they were wholly unsuited. In the end,
statistics published nine years previously. the real victim of expert evidence that is held to be of little or no
Her evidence was contrasted with value is the party whose case suffers as a result.
the evidence provided in the Shrien
Dewani case.3 There the UK courts were John Mullen FRICS FCInstCES FCIArb, Quantum Expert and Principal,
so convinced that South African prisons Diales
3
The British businessman acquitted last year of john.mullen@diales.com
murdering his wife on their honeymoon in South Africa www.diales.com
18 Ground Conditions Construction Law Review

Foreseeing the unforeseeable


David Carrick FCInstCES FICE FCIArb MRICS MCIPS MBAE, Senior Vice President, Hill International

T HERE I was, sitting in my ofce, trying to get my head around a particularly difcult point in an
adjudication when Alan Lees from the Chartered Institution of Civil Engineering Surveyors phoned me. I
was grateful for the call, not only because it is always good to talk to Alan, but also it meant a break from
the mind warping adjudication. Alan reminded me that the rst publication of the Construction Law Review was
20 years ago and that I had featured in it. Kindly, if somewhat embarrassingly, Alan sent me a copy of the article.
It included a photograph. I have searched the attic in vain but sadly the original appears to have been lost.
On the topic of photographs, one of my colleagues mentioned the photograph I had shown her of my
endeavours to do some setting out at the beginning of my career and that in turn led to a discussion about my
rst overseas trip and a war story. It seems that as ones career matures, so war stories become more or less
mandatory. However, this one is relevant to the subject matter of this article so please bear with me.

Some personal history


The case of Obrascon I was involved in a project that involved
additional runway lighting and drainage on
After a few minutes we were on the radio
to ATC to tell them that gunre was still
Huarte Lain SA v Gibraltar an existing runway, and also the removal continuing. They said they would send
of some particularly leaky disused fuel and the RAF out to tell them to stop. We
de-icing uid tanks that had once been cleared off to the dispersal area somewhat
used by the RAF. These were on the south concerned at the ongoing sound of gunre.
side of the runway at the eastern end and We saw the landing lights of the plane in
had been leaking for years. the distance as the RAF Land Rover went
One day when I was on site we belting down the road on the other side
attended the usual morning brieng of the runway. As the aircraft got closer
with the RAF air trafc control. On that eventually the gunre stopped. However,
particular morning we were joined by a then the fun began. The range ofcer
small band of army reservists. They would clutching a large red ag ran into the
be making use of a rie range quite close middle of the runway and started waving
to the runway. My foreman was well it at the aircraft. The very unhappy pilot
versed in the protocol for clearing the had to spool up his engines and abort the
runway for incoming aircraft and was in landing much to the angst of the crew and
constant radio contact with the control passengers alike.
tower. However, the tower envisaged The next morning we were summoned
some problems with the rie practice. The to see a very senior RAF ofcer. He
arrangement was that when aircraft were thanked us for our collaboration and for
coming into land we would get the usual our safety record but said the time had
warning by radio from the tower and clear come when the rie range really had to
out of the way of the approaching aircraft. be disposed of. This was at the north
The army reservists were unlikely to hear side of the runway at the eastern end. He
the radio on account of their gunre, so would organise a variation order for us
accordingly the arrangement was that the to atten the rie range with a dozer. We
tower would re a are over the rie range duly did and were somewhat surprised at
and the ring would cease. The range the amount of lead and copper that this
ofcer was handed a large red ag. He produced (but the range had been in use
looked bemused. The rather harassed ATC for many years). End of war story.
ofcer explained to him: Plane comes in.
I re red are over your position. You wave FIDIC
red ag. Everyone stops shooting. Ok? A lot of my work nowadays is international
Off we went and on schedule the work and I nd myself quite often
lunchtime aircraft arrived from London. As working with the International Federation
ever the ATC told us when it was about of Consulting Engineers (FIDIC) forms
20 minutes away and we started clearing of contract. For those of you of a similar
up. The red are duly went up over the vintage to myself who have not used
rie range but nothing else happened. the FIDIC form, you would immediately
,/>>E,>WzKhDE'd,,/',Z/^<^K&KE^dZhd/KE

t 6            
,/
t               
     t        

t
,
K
^ WD^

td WD
 WD
>^ D
 WDK
 dWd
D ^
 D
> W
ZD 
^/,d 

&&

Z d,
,/h<> ,/h<>
Z^,^ W^
d >sZE
 d

WD
,/h<>
<
^W
W
tz
d


Kh<
20 Ground Conditions Construction Law Review

Gibraltar contended the conditions were entirely


foreseeable, OHL had brought a lot of the
difculties on its own head by the way it dealt with
the ground conditions.
Figure 1: Gibraltar International Airport taken from the Rock of Gibraltar, looking north with the east
end of the runway on the right.

recognise it as having some very close resemblance to the old The main areas of dispute
Institution of Civil Engineers (ICE) or the current Infrastructure Gibraltar entered into contract with Obrascon Huarte Lain SA
Conditions of Contract (ICC) forms. (OHL) under a FIDIC Yellow Book design and construct contract.
Most of the FIDIC forms have got provisions for unforeseeable It all went horribly wrong. Eventually Gibraltar terminated the
physical conditions, just like the old ICE clause 12. They also contract on the basis of poor progress, amongst other things.
have fairly draconian notice provisions where failure to comply OHL contended that progress had been impeded by unforeseen
with these provisions seems to result in a loss of entitlement. physical conditions (contaminated ground) and the termination
Because the standard dispute resolution procedure is the dispute was wrongful. Conversely Gibraltar contended the conditions were
adjudication board followed by arbitration, the FIDIC forms are entirely foreseeable, OHL had brought a lot of the difculties on
rarely considered by courts. Suddenly one appeared and it covers its own head by the way it dealt with the ground conditions, and
these rather difcult issues and also the matter of termination. in any event had not given notice in accordance with the contract
and so had forfeited its rights to make a claim. The contention that
Obrascon Huarte Lain SA v HM Attorney General for Gibraltar OHL had to redesign the tunnel because of the contamination and
I was particularly interested in the unforeseen physical conditions that the engineer had issued what OHL contended were variations
aspect of Obrascon Huarte Lain SA v HM Attorney General for were also contested by Gibraltar.
Gibraltar. It is a frequent problem in other civil engineering forms The dispute came before Mr Justice Akenhead in the
of contract, where there is relief available to the contractor should Technology and Construction Court in the rst instance1 and then
such circumstances arise. Obviously the facts and circumstances went on to the Court of Appeal.2 The main issue was termination
and the particular wording of the contract have paramount but that is not the issue that I address in this article but rather the
importance when considering if a particular judgment is relevant
underlying matters. The ground condition issue was subject to
to another dispute. We will get back to the matter of applicability
appeal and it is convenient to consider that matter before looking
of this judgment in a more general sense later. However, some
at the issue of notice.
background to the dispute is pretty important to understand what
happened not only in the rst instance case but also in the
Unforeseen adverse physical conditions
appeal court case.
The OHL proposition was that the amount of contaminated
The defendant party was the government of Gibraltar
matter excavated exceeded the quantity that could have been
represented by Her Majestys Attorney General for Gibraltar. The
expected. That meant not only greater expense but redesign and
works giving rise to the dispute unsurprisingly took place in
lengthy delays that explained the poor progress and made the
Gibraltar. The appeal case succinctly sets out some background.
termination unlawful.
Spain ceded Gibraltar to the United Kingdom by the Treaty of
The means of construction was to construct the walls of the
Utrecht in 1713 and the local population has occupied Gibraltar
under UK rule since that date. The territory has played an tunnel as diaphragm walls below original ground level using
important role in many wars, with the last of these being the rst bentonite, then cast the roof slab. The ground under the slab
and second world wars. The long military history of the territory would be excavated once the roof was strong enough to support
has an impact on the issues in dispute. itself and restrain the outer diaphragm walls. OHL considered
Gibraltar is connected to the south of Spain by a relatively that the amount of contaminated ground meant it was unsafe to
narrow isthmus that runs north/south. The airport is located on excavate in the conned space, work had to be suspended and
the isthmus close to the border with Spain and its runway crosses the works redesigned. The contract had the following provisions:
the isthmus running east/west and protruding into the sea. That
means that all the vehicle trafc going to and from Spain has to 1.1.6.8 Unforeseeable means not reasonably foreseeable by an
cross the runway. experienced contractor by the date for submission of the tender...
Figure 1 is taken from the Rock of Gibraltar and is looking
north with the east end of the runway on the right. The road has 4.10 Site data: The employer shall have made available to
to be closed when the runway is in use by aircraft (always a good the contractor for his information, prior to the base date, all
idea) so the government of Gibraltar decided to build a tunnel relevant data in the employers possession on sub-surface and
under the runway. To avoid prolonged closure of the runway hydrological conditions at the site, including environmental
this was to be built at the eastern end of the runway. Doubtless aspects. The employer shall similarly make available to the
a certain amount of ducking was anticipated by the labour force 1
(2014) EWHC 1028 (TCC)
when aircraft were landing. 2
(2015) EWCA Civ 712
2016 Ground Conditions 21

This notice shall describe the physical conditions, so that they


can be inspected by the engineer, and shall set out the reasons
why the contractor considers them to be unforeseeable. The
contractor shall continue executing the works, using such proper
and reasonable measures as are appropriate for the physical
conditions, and shall comply with any instructions which the
engineer may give. If an instruction constitutes a variation,
clause 13 (variations and adjustment) shall apply.

If any to the extent that the contractor encounters physical


There was a recognition that there was conditions which are unforeseeable, gives such a notice, and
contaminated land, including elevated copper suffers delay and/or incurs cost due to these conditions,
the contractor shall be entitled subject to sub-clause 20.1
levels, fuel contamination and potentially (contractors claims) to:
unexploded ordnance. (a) an extension of the time for such delay, if completion is
or will be delayed, under sub-clause 8.4 (extension of time for
completion), and
(b) payment of any such cost, which shall be included in the
contract price.
contractor all such data which come into the employers After receiving such notice and inspecting and/or investigating
possession after the base date. The contractor shall be these physical conditions, the engineer shall proceed in
responsible for interpreting all such data. accordance with sub-clause 3.5 (determinations) to agree or
determine (i) whether and (if so) to what extent these physical
To the extent which was practicable (taking account conditions were unforeseeable, and (ii) the matters described in
of cost and time), the contractor shall be deemed to sub-paragraphs (a) and (b) above related to this extent.
have obtained all necessary information as to risks,
contingencies and other circumstances which may However, before additional cost is nally agreed or determined
inuence or affect the tender or works. To the same extent, under sub-paragraph (ii), the engineer may also review whether
the contractor shall be deemed to have inspected and examined other physical conditions in similar parts of the works (if any)
the site, its surroundings, the above data and other available were more favourable than could reasonably have been foreseen
information, and to have been satised before submitting the when the contractor submitted the tender. If and to the extent
tender as to all relevant matters, including (without limitation): that these more favourable conditions were encountered, the
(a) the form and nature of the site, including sub-surface engineer may proceed in accordance with sub-clause 3.5
conditions, (determinations) to agree or determine the reductions in cost
(b) the hydrological and climatic conditions, which were due to these conditions, which may be included
(c) the extent and nature of the work and goods necessary for (as deductions) in the contract price and payment certicates.
the execution and completion of the works and the remedying of However, the net effect of all adjustments under sub-paragraph
any defects, (b) and all these reductions, for all the physical conditions
(d) the laws, procedures and labour practices of the country, encountered in similar parts of the works, shall not result in a
and net reduction in the contract price.
(e) the contractors requirements for access, accommodation,
facilities, personnel, power, transport, water and other services. The engineer may take account of any evidence of the physical
conditions foreseen by the contractor when submitting the
4.11 Sufciency of the accepted contract amount: The contractor tender, which may be made available by the contractor, but
shall be deemed to: shall not be bound by any such evidence.
(a) have satised himself as to the correctness and sufciency of
the accepted contract amount, and My emphasis added.
(b) have based the accepted contract amount on the
data, interpretations, necessary information, inspections, The facts
examinations and satisfaction as to all relevant matters referred The initial pre-contract consideration required a desktop study
to in sub-clause 4.10 (site data) and any further data and that led to an environmental statement being produced and
relevant to the contractors design. subsequently included in the contract. That statement suggested
that approximately 200,000m3 of excavation would be required,
Unless otherwise stated in the contract, the accepted contract of which 10,000m3 would be contaminated. There was a site
amount covers all the contractors obligations under the contract investigation that was also incorporated into the contract. There
(including those under provisional sums, if any) and all things were extensive references to past military use including a rie
necessary for the proper design, execution and completion of the range and aircraft fuel leakage. The contract contained an
works and the remedying of any defects. obligation to conduct post contract site investigation to determine
the actual ground conditions and to ensure that the waste
4.12 Unforeseeable physical conditions: In this sub-clause, materials were disposed of in an appropriate manner. There was a
physical conditions means natural physical conditions recognition that there was contaminated land, including elevated
and manmade other physical obstructions and pollutants, copper levels, fuel contamination and potentially unexploded
which the contractor encounters at the site when executing the ordnance. A pre-tender bulletin informed tenderers that no on-site
works, including sub-surface and hydrological conditions but storage for excavated material was available and that consequently
excluding climatic conditions. all or most excavated material would have to go into landll sites
If the contractor encounters adverse physical conditions which in Spain.
he considers to have been unforeseeable, the contractor shall The contract was entered into with a commencement date of
give notice to the engineer as soon as practicable. 1 December 2008 and completion two years later. In November
22 Ground Conditions Construction Law Review

2009 OHL drilled further boreholes and


these showed elevated lead levels. The
initial design was not approved until
21 December 2009.
When excavation started in the
tunnel area, similar elevated lead levels
were found together with other nasty
contaminates. By May 2010, as well as
the main excavations for the diaphragm
walls, the oversite strip of about 2m
depth had been carried out but OHL had
Much discussion and little construction work took
not segregated contaminated and non- place and, on 28 July 2011, Gibraltar terminated
contaminated soil. By autumn 2010 the
levels of contamination were becoming a the contract.
real concern and OHL nally served notice
under clause 4.12 of a claim for extension
of time and for extra payment in respect of And the relevant part of the rst instance judgment:4
unforeseeable physical conditions
Much discussion and little construction The problem here for tendering contractors is and was the
work took place and, on 28 July 2011, foreseeable uncertainty of precisely what and where (and at
Gibraltar terminated the contract. what depths within the made ground) in terms of quantity and
location the contaminated soil would be. That there was a
The appeal court decision very real prospect of encountering contaminated material
In the context of unforeseen physical in substantial quantities anywhere within the made
conditions the rst instance decision was ground was eminently foreseeable by an experienced
upheld in that the amount of contamination contractor at tender stage. How (may it be asked)
was foreseeable. Why? could an experienced contractor in OHLs position have
The initial consideration was that the addressed this foreseeable risk? There is no help within the
history of the site was clearly set out in evidence as to how OHL did address it pre-contract, if it did at
the desktop study. The previous presence all. However, what on the evidence could reasonably have been
of a rie range that had been in use since done is all or some of the following: (a) Make a substantial
the 19th century and aviation fuel storage nancial allowance within the tendered price for actually
tanks was shown. There was evidence encountering and dealing with a large quantity of such
of contamination from lead waste from material...
bullets, aviation fuel and de-icing uids.
OHL had not segregated the My emphasis added.
contaminated materials, so the entire
excavation had to be disposed of in The impact of Gibraltar on Yellow Book contracts
suitable landll sites in Spain. As an aside Making nancial provision for the worst possible scenario in a
it also meant that it was impossible to competitive tendering situation is not an easy call. Does that mean
quantify the actual amount of contaminated that OHL should have allowed for the entire excavation being
soil that had been excavated. contaminated? I dont think that is what was meant at all.
The key nding was that the tendering What was meant was that if there was any doubt about
contractor cannot rely on someone elses contamination the tenderer had to err on the pessimistic side.
interpretation of the data (in this case a Nevertheless a high threshold for foreseeability has been set by
gure of 10,000m3 of contaminated ground this judgment.
was shown in the tender enquiry) but the
contractor must make its own appraisal of The impact on other contracts
the quantity using all the available data. It If ever a judgment had to be considered against its facts this is
is ne to take the given data into account it. To apply the ratio of this case disregarding the facts is in my
but that is insufcient and the tendering opinion asking for trouble.
contractor must consider the data in its However, assuming that the same facts pertained in the other
entirety and use its own investigation commonly used FIDIC forms (Red and Silver) would the outcome
and experience to determine what is have been the same?
foreseeable. However the Court of Appeal
judgment went even further:3 Red Book
The Red Book uses a bill of quantities but no method of
Furthermore the historical material measurement is specied; the choice is down to the drafter of
provided to the contractor made it clear the contract. Most methods would require contaminated material
that very extensive contamination was to be measured separately so the direct cost would be covered
foreseeable across the site. The contractor in re-measurement. With this form of contract the employer is
needed to make provision for a possible responsible for design so the hotly disputed redesign issue in this
worst case scenario; the contractor case would not arise.
should have made allowance for a
proper investigation and removal of all Silver Book
contaminated material: see paragraph This FIDIC form has no relief for adverse conditions, so the issue
223 of the judgment. doesnt arise.
3 4
Paragraph 94 Paragraph 223
2016 Ground Conditions 23

time for completion and/or any additional payment under


any clause of these conditions or otherwise in connection with
the contract, the contractor shall give notice to the engineer,
describing the event or circumstance giving rise to the claim. The
notice shall be given as soon as practicable, and not later than
28 days after the contractor became aware, or should
have become aware, of the event or circumstance.

If the contractor fails to give notice of a claim within such period


of 28 days, the time for completion shall not be extended, the
What emerges from the case is a contractor shall not be entitled to additional payment, and the
need for the tendering contractor employer shall be discharged from all liability in connection
with the claim. Otherwise, the following provisions of this sub-
to make its own investigations. clause shall apply...

Clause 8.4 deals with extensions of time in FIDIC contracts and the
NEC relevant part is the following terms:
The application of this case to NEC is, in
my humble opinion, difcult. The recovery The contractor shall be entitled subject to sub-clause 20.1...
of direct cost via a re-measured bill of to an extension of the time for completion if and to the extent
quantities depends on the main option that the completion for the purposes of sub-clause 10.1... is or
choice within the contract. will be delayed by any of the following causes...
In terms of relief from adverse physical
conditions the main option choice is My emphasis added.
irrelevant; the same procedure applies
to all options. What emerges from the In the rst instance judgment6 deals with the matter of notices.
Gibraltar case is a need for the tendering Two issues emerged; the form of the notice and its timing. In
contractor to make its own investigations as general terms, the judge took a fairly pragmatic view of these
well as taking into account the information provisions saying that they should be construed reasonably
supplied with the tender. broadly given the serious effect that they would have if strictly
In the NEC contracts there is relief for construed. There is no need for the notice to be any particular
unforeseen physical conditions and there form, but it must be identiable as notifying a claim and given
is also a need for the employer to provide in writing.
known information in the site information. The timing of notices was also dealt with on a non-prescriptive
However the compensation event for the basis. The provisions of clause 8.4 are said to allow two dates that
adverse physical conditions relief5 has to affect the notice. These are when completion (i) is being delayed
be read with the provisions of clauses or (ii) will be delayed. The rst is termed a retrospective delay
60.2 and 60.3. In particular clause 60.3 in because the delay has started, and the second a prospective future
the following terms seemingly causes a delay. Either date can trigger the claim and apparently can be the
problem to applying the Gibraltar case: start of the 28-day period within which the notice must be issued
as required by clause 20.1.
If there is an ambiguity or inconsistency I am reluctant to comment too much on this issue but I will say
within the site information (including that it is not an approach that I have seen in practice. Stretched
the information referred to in it), the to its limit, could it mean that a whole raft of extension of time
contractor is assumed to have taken into claims could be notied on the scheduled completion date, i.e.
account the physical conditions more when completion is absolutely known to be delayed?
favourable to doing the work. Does the same ethos apply to any additional payment because
clause 20.1 deals with both? This may not be so clean cut because
Had the Gibraltar case contract included clause 8.4 only refers to extensions of time and not additional
the desktop study concluding that payment. OHL was only awarded a one day extension on account
10,000m3 of excavation was likely to of encountering rock the extension of time claim for weather
be contaminated, and the wealth of delays was rejected for lack of notice.
information indicating a greater quantity, Would I advise a contractor not to notify the very instant
could OHL have relied on the more it became aware of a potential delay? The answer to that is a
optimistic 10,000m3? It certainly seems to resounding no! Would I advise a contractor that had not notied
be a reasonable potential argument. until it became aware of an actual delay to completion to use this
case? Yes.
Notices for extensions of time under FIDIC
Having possibly depressed contractors, an Just to close... Yes, the runway I recollected in my personal history
aspect of the rst instance judgment that was Gibraltar. But you probably guessed that anyway.
was not appealed showed a bit of leniency.
Clause 20.1 is a standard feature of FIDIC David Carrick FCInstCES FICE FCIArb MRICS MCIPS MBAE,
contracts and the relevant part is the Senior Vice President, Hill International
following terms: davidcarrick@hillintl.com
www.hillintl.com
20.1 If the contractor considers himself @hillintl
to be entitled to any extension of the
5 6
Clause 60.1 (12) Paragraphs 312 and 313 in particular
Managing with the MMHW
An examination of the use of the Method of Measurement for Highway Works

Hamish Mitchell FCInstCES

A book that is long overdue.


It is well researched and
written by one of the most
experienced highway
quantity surveyors in the
UK, Hamish Mitchell. This
book will help practitioners
and students alike understand highway
measurement in a much more structured
way than was previously possible.
 
  
 
 
 

Highway measurement is not just measurement


A book from ICES covering the background, development and usage of the MMHW.
Author Hamish Mitchell presents case studies and examples to help readers understand the
practicalities of highway measurement.

19.95* Available now

Contact: ICES Publishing


Chartered Institution of Civil Engineering Surveyors
+44 (0)161 972 3110
mmhw@cices.org
www.cices.org/mmhw
(*Free postage UK, 6.95 overseas)

The Chartered Institution of Civil Engineering Surveyors is a registered educational charity.


2016 FIDIC 25

Employers claims under FIDIC


Jonathan Hosie, Partner, Construction & Engineering Group, Mayer Brown International

T HE International Federation of Consulting Engineers


(FIDIC) forms of construction contract are amongst the
most widely used internationally.1 FIDIC contracts started
out life with a focus on the European market, initially with a
focus on civil engineering projects. Nowadays, they are promoted
globally and encountered in many jurisdictions beyond Europe,
including South America, China, the Far East and Africa, and in
sectors from civil engineering infrastructure to process engineering
and power generation.
Much has been written about claims made by contractors
under the FIDIC forms, but until recently, not much attention has
been focused on the administration of employers claims. This
brief article seeks to redress that balance and to do so in light of
two recent and important court decisions. The rst is a decision
of the judicial committee of the Privy Council, NI International
(Caribbean) Limited v National Insurance Property Development
Company Limited (No. 2) (2015) UK PC 37. The second is a decision
of Mrs Justice Carr in the Technology and Construction Court,
J Murphy & Sons Ltd v Beckton Energy Ltd (2016) EWHC 607 (TCC).

:PNUPJHUJLVM[OL507+,*KLJPZPVU
The judicial committee of the Privy Council originated as the
highest court of appeal for the British Empire. It now fulls the
same purpose for many current and former Commonwealth
countries. It is binding in the jurisdiction to which it relates and
has persuasive authority in all other common law jurisdictions,
including England, Wales and Northern Ireland.
The contract in NIPDEC was based upon the FIDIC general
conditions of contract for construction, rst edition 1999,
also known as the Red Book. The terms of the Red Book, as
considered by the court in the NIPDEC case, are identical to
those found in the FIDIC Yellow and Silver Books.2 This decision
is therefore of widespread application for international projects
which use FIDIC Red, Yellow or Silver Book terms as the basis of
Two recent decisions the construction contract and which are subject to common law.

on the administration of Furthermore, given that one third of the worlds population live
in jurisdictions subject to common law and the geographically
employers claims widespread use of FIDIC forms, the NIPDEC decision has a
potentially far reaching signicance for projects globally.

The NIPDEC case


The NIPDEC decision is a judgment of the Privy Council, on
appeal from a decision of the Court of Appeal of the Republic of
Trinidad and Tobago. The case concerns disputes between the
employer (NIPDEC) and the contractor (NHIC) arising out of a
contract for the construction of the new Scarborough Hospital
in Tobago. Following disagreements between the parties, NHIC
1
There are other standard form contracts used internationally including those prepared
by the Engineering Advancement Association of Japan (ENNA); the Institution
of Chemical Engineers (IChemE); the Institutions of Mechanical Engineers and
Engineering & Technology (IMechE); and the New Engineering Contract (NEC)
2
Yellow Book, Conditions of Contract for Plant and Design-Build and Silver Book,
Conditions of Contract for EPC/Turnkey Projects, both rst editions, 1999
26 FIDIC Construction Law Review

The interesting point to note here is the contrast with the


requirements for the giving of notice required from the contractor
when giving notice of its claims against the employer, under sub-
clause 20.1. In the case of the contractor:

...notice shall be given as soon as practicable, and not later


than 28 days after the contractor became aware, or should have
There is no long-stop date for notication of become aware, of the event or circumstance.

employers claims. This might appear to suggest a In contrast, there is no long-stop date for notication of employers
less strict regime for the employer, but there is a claims. This might appear to suggest a less strict regime for the
employer in the provision of such notices, but there is a sting in
sting in the tail of sub-clause 2.5. the tail of sub-clause 2.5, as we shall see below. As to details of
the claim to be given, sub-clause 2.5 provides:

suspended works and purported to The particulars shall specify the clause or other basis of the
exercise its right to determine the contract. claim, and shall include substantiation of the amount and/or
The parties then referred a number of extension to which the employer considers himself to be entitled
differences to arbitration under the terms in connection with the contract.
of the contract. The arbitrator issued a
number of awards, two of which were Clearly, the intention here is that the contractor is given sufcient
then challenged. These two issues were details to be able to assess and respond to the employers claim.
connected. The rst was the arbitrators Immediately after the provision of such particulars, the linkage
decision that the contractor, NHIC, was with the determination process is found:
entitled to terminate the contract. This
arose from a question as to whether The engineer shall then proceed in accordance with sub-clause
the employer, NIPDEC, had met the 3.5 (determinations) to agree or determine (i) the amount (if
threshold for giving nancial security for any) which the employer is entitled to be paid...
performance of its payment obligations
under the contract (issue no. 1). The The determination machinery is a unique feature of the FIDIC
second aspect related to certain nancial forms. This involves the engineer (under the Red and Yellow
claims. This concerned the requirements Books) making a determination of whether and if so how much is
for NIPDEC to commence and maintain its due to the employer.3 It is necessary for the employer to provide
claims against the contractor (issue no. 2). details of its claims, not just to the contractor but also to the
This article considers issue no. 2 only. engineer, so that the engineer can perform the function required
of it under sub-clause 3.5.
Employers claims under FIDIC The Privy Council looked at the purpose of the provision and
In particular, issue no.2 concerns sub- identied that under FIDIC, the claims machinery applicable to
clause 2.5 of the FIDIC form and notices employers claims leads directly into the determination process
of claim by the employer. In common with under sub-clause 3.5. Thus, in NIPDEC, the court observed:
the drafting style of FIDIC, a number of
separate points are located within a single If an employers claim is allowed to be made late, there would
sub-clause. It may be helpful to break the not appear to be any method by which it could be determined
clause down into its constituent parts. Sub- as the engineers function is linked to the particulars, which in
clause 2.5 commences with the following: turn has to be served as soon as practicable. 4

If the employer considers himself to NIPDEC is therefore persuasive authority in common law
be entitled to any payment under any jurisdictions for the proposition that if there is no valid employers
clause of these conditions or otherwise claim under sub-clause 2.5, there can be no determination under
in connection with the contract... he sub-clause 3.5.
shall give notice and particulars to the
contractor. Notice requirements for employers claims as a condition
precedent to entitlement
This opening provision requires the The sting in the tail of sub-clause 2.5, as identied by the Privy
employer to take the initiative and give a Council in NIPDEC, states:
notice to the contractor. It is a mandatory
requirement, and if the employer fails to The employer shall only be entitled to set off against or
give notice, it will be in breach of contract. make any deduction from an amount certied in a payment
However, any such breach has other certicate, or to otherwise claim against the contractor, in
serious consequences, as we shall see. accordance with this sub-clause.
Another important provision within sub-
clause 2.5 deals with the time for giving This also provides a point of contrast with the regime for
notice, and provides: contractors claims under sub-clause 20.1, which includes express
3
The notice shall be given as soon as Under the Silver Book, where there is no independent engineer engaged to
administer the contract, the employer determines the validity and quantum of its own
practicable after the employer became claims, albeit the contractor may give notice of dissatisfaction within 14 days and
aware of the event or circumstances thereby avoid having to give effect to the determination
giving rise to the claim. 4
Paragraph 38 of Privy Council judgment
2016 FIDIC 27

language which spells out the consequences of non-compliance


with the notice provisions:

If the contractor fails to give notice of a claim within such


period of 28 days, the time for completion shall not be extended,
the contractor shall not be entitled to additional payment, and
the employer shall be discharged from all liability in connection
with the claim. The decision in Beckton Energy illustrates the
In common law jurisdictions, most commentators would regard importance of bespoke amendments to the FIDIC
the drafting of sub-clause 20.1 of the FIDIC form as making due
notice from the contractor a condition precedent to its entitlement
forms of contract. The court commented that the
to pursue recovery of its claims. amendments had not been fully thought through.
The ingredients for an effective condition precedent are
often said to be that a precise period of time is stated within
which notice must be given and the consequences of any non- that it does not justify any payment or is
compliance with that time period are spelled out expressly. The worth materially less than the unit rate or
language of sub-clause 20.1 satises these requirements, with lump sum price in the contract.
the effect that if the contractor fails to give notice within the The case was remitted to the arbitrator
prescribed period, it forfeits its claim. to disallow sums which (i) were not
This gives rise to the question as to whether the requirements
subject of notication in accordance
of sub-clause 2.5 for employers claims contain the necessary
with sub-clause 2.5 and (ii) could not be
ingredients for an effective condition precedent, even though
characterised as abatement claims. Not
the notice provision lacks the precision in terms of its permitted
good news for the employer.
timing. Thanks to the Privy Council in NIPDEC, we now have an
answer and it is not good news for employers. Lord Neuberger of
The Beckton Energy case
the Privy Council said this of sub-clause 2.5:
The decision in the Beckton Energy
case is also important here. The contract
Its purpose is to ensure that claims which an employer wishes
which gave rise to the dispute in that
to raise, whether or not they are intended to be relied on as
case was based on the FIDIC Yellow
set-offs or cross-claims, should not be allowed unless they have
Book. Murphy was seeking a declaration
been subject of a notice, which must have been given as soon as
that the employer rst had to obtain a
practicable. 5
determination of the engineer in its favour
under sub-clause 3.5 before it could
...the natural effect of the closing part of clause 2.5 is that in
lawfully deduct liquidated damages for
order to be valid, any claim by an employer must comply with
delay. The liquidated damages claim of the
the rst two parts of the clause, and that this extends to, but,
in the light of the word otherwise is not limited to, set-offs and employer was substantial, amounting to
cross claims. 6 8.274m.
Sub-clauses 2.5 and 3.5 of the contract
This leads to the surprising conclusion that the absence of a in the Beckton Energy case were
28-day longstop (and any other) in sub-clause 2.4, means that unamended from the FIDIC standard form.
the requirement for an employers claim notice has the potential Following NIPDEC, one might therefore
to be more demanding than that for a contractors; as soon have expected the declaration to be
as practicable may well expire sooner than 28 days after the granted in favour of Murphy. However,
employer considers itself to be entitled to any payment. the court found that the obligation to pay
So, even with what may otherwise be a valid claim by an liquidated damages under sub-clause 8.7
employer, if it is notied later than as soon as practicable, it arose independently of sub-clauses 2.5
cannot proceed under sub-clause 2.5. This could affect employers and 3.5, and was not contingent upon
claims to deduct liquidated damages or to recover costs incurred an engineers determination. Importantly,
itself in rectifying defective works. the contract in Beckton Energy had been
amended. In sub-clause 8.7, the words
Not all employer claims and complaints are time barred subject to sub-clause 2.5 qualifying
The decision in NIPDEC is also persuasive authority in common Murphys obligation to pay liquidated
law jurisdictions for the proposition that where the employer fails damages had been deleted. Rather, the
to notify a claim in accordance with sub-clause 2.5: bespoke drafting of sub-clause 8.7 meant
that the obligation to pay liquidated
...the back door of set off or cross- claims is as rmly shut to it damages for delay was contingent only
as the front door of an originating claim. 7 in the contractor failing to achieve the
required milestone date for completion.
However and importantly, it will be noted that sub-clause 2.5 is Similarly, in the Beckton Energy case
concerned with entitlement to payment and the giving of notices the standard form of FIDIC bond wording
to this effect. Sub-clause 2.5 does not preclude the employer from had been rejected. That FIDIC wording
raising an abatement argument, namely that the work for which expressly limited the employers right to
the contractor is seeking payment was poorly carried out, such calling the bond only when the engineer
5
Paragraph 38 of Privy Council judgment
had made a determination.
6
Paragraph 39 of Privy Council judgment Interestingly, the court found that
7
Paragraph 40 of Privy Council judgment the deletion of words from a standard
28 FIDIC/Adverse Weather Construction Law Review

form was only context and by no means


determinative but it was nevertheless
relevant background which the court was Where the governing law of the FIDIC contract is
entitled to take into account in determining
the objective intention of the parties based on other legal systems, such as civil law or
and interpreting the true meaning of the
particular provisions in issue. Sharia law, the same result may not prevail.
Concluding remarks
One nal comment. The Privy Council decision in NIPDEC
The decision in Beckton Energy illustrates
applies common law principles to two important provisions found
the importance of bespoke amendments
in some of the main forms of FIDIC contract used on projects
to the FIDIC forms of contract. The court
commented that the amendments had not internationally. Where the governing law of the FIDIC contract is
been fully thought through (noting the based on other legal systems, such as civil law or Sharia law, the
NIPDEC decision and the tension between same result may not prevail.
sub-clause 2.5 and the liquidated damages With the worlds population in 2016 approaching 7.5 billion,
deduction provision in sub-clause 8.7, common law still applies to about 2.5 billion people. Not all of
even with the deleted words). However them will be involved in the construction sector, but many will be
and on balance, the court in Beckton affected by assets built under FIDIC forms.
Energy found that the right to deduct
damages in sub-clause 8.7 (as amended) Jonathan Hosie, Partner,
created a self-contained and separate Construction and Engineering Group, Mayer Brown International
right of the employer to make deductions jhosie@mayerbrown.com
against, or require payment from, the www.mayerbrown.com
contractor, independent of the employers @Mayer_Brown_UK
claim machinery in sub-clause 2.5 or the
determination machinery in sub-clause 3.5. Jonathan Hosie is the ICES advisory solicitor.

Adverse weather
What are the differences?
Emily Monastiriotis, Partner, with Susanne Hose, Solicitor, and Simos Schizas, Paralegal, Bond Dickinson

G IVEN that often in the UK we


dont quite know whether to
carry umbrellas, snow boots
or sunglasses (or indeed all three), its
adverse weather, rather than
exceptional. Alternatively, a more
detailed guide is incorporated into
the agreement so as to achieve the
worthwhile to set out how standard form objectivity of NEC3 contracts.
building contracts deal with adverse If the contract form is either JCT,
weather. The table across shows the key ICE or FIDIC, then records of
clauses to consider in relation to claims weather changes must be regularly
relating to adverse weather under forms of kept (if possible on a daily basis).
contract from the Joint Contracts Tribunal Parties bringing a claim under
(JCT), Institution of Civil Engineers (ICE), JCT, ICE or FIDIC contracts should
New Engineering Contract (NEC3) and prove not only that the weather
the International Federation of Consulting was exceptionally adverse, but also
Engineers (FIDIC). that the delay caused was of an
Checking the provisions of the contract adverse nature.
should be the number one priority all
parties to the contract should be aware Emily Monastiriotis, Partner, Susanne Hose,
of how the risks are apportioned before Solicitor, and Simos Schizas, Paralegal,
signing it. Some key tips to remember: Bond Dickinson
emily.monastiriotis@bonddickinson.com
If the contract is JCT, ICE or FIDIC, www.bonddickinson.com
then amendments are often made to @Bond_Dickinson
the agreement to refer to normal @EMonastiriotis
2016 Adverse Weather 29

Contract Extension of Time Clause Wording / Denition Notice Comments

JCT Yes (relevant event) Exceptionally adverse weather 1. The contractor has to notify the This is quite a broad (vague) denition.
Standard: 2.29.9 conditions. contract manager as soon as it realises Exceptionally adverse conditions are
Design & Build: 2.26.8 that completion will be delayed the considered to be greater than usual
Intermediate: 2.20.8 notice should incorporate all material adverse conditions. Exceptional means
Major Project Construction: N/A events (clause 2.27.1). having much more than average...
2. The contractor has to notify the (Collins English Dictionary, 1999).
contract manager of the result of the There is no accepted prescriptive
delay (clause 2.27.2). denition for adverse weather
3. The contractor should continue to give conditions.
notices with updates as matters progress JCT also contains a force majeure
(clause 2.27.3). clause but given the existence of a clause
regarding weather conditions, the force
majeure clause is unlikely to apply.
Whether or not the weather is as
adverse as it needs to be will be up to the
contract administrator to decide.

NEC3 Yes (compensation event) A weather measurement is recorded: 1. Notice must be given to the project The contract data includes very clear
60.1 (13) Within a calendar month manager within eight weeks of the and objective measurement details,
Before the completion date for the contractor becoming aware of the event which are often negotiated between the
whole of the works and (clause 61.3). parties to the contract. It provides a more
At the place stated in the contract data. 2. If notice is not given, the contractor prescriptive denition, one that parties
The value of which, by comparison with loses its right to any additional money often rely on for its clarity.
the weather data, is shown to occur on or time. Only deals with cold, snow, and rain
average less frequently than once in nothing relating to extreme heat, wind
ten years. Only the difference between (think of cranes) or worse.
the physical conditions encountered If the weather in question occurs less
and those for which it would have been frequently than once in ten years then it
reasonable to have allowed is taken into can qualify as a compensation event.
account in assessing a compensation There are four ways of measuring the
event. weather cumulative rainfall (mm);
number of days with rainfall more than
5mm; number of days with minimum air
temperature less than 0C (32F); number
of days with snow lying at a stated time
GMT.
The intention of weather measurements
is to report the weather over one month
not hourly/daily.
Weather measurements and data
should be taken on site or as close as
possible to the site in question.

ICE Yes (relevant event) Exceptionally adverse weather. 1. Notice must be given by the contractor A similar explanation to that of JCT
44 (1) to the engineer within 28 days after the very broad and vague. The engineer will
cause of the delay. usually assess whether the weather is
2. The engineer must then make sufciently adverse.
an assessment upon receipt of the Having historical records would be
particulars of the delay and notify the very helpful in determining whether the
contractor (clause 44 (2)). weather conditions were exceptionally
3. The engineer must then make an adverse not clear how far back these
interim extension of time award if found records should go (some say 10 years,
that the contractor needs more time others more).
towards completion (clause 44 (3)).
4. The engineer must, within 14 days of
the completion date decide whether an
extension of time is appropriate or not
(clause 44 (4)).
5. The engineer must review and make
a nal determination as to the extension
of time within 28 days of the issue of
the certicate of substantial completion
(clause 44 (5)).

Yes (relevant event) Exceptionally adverse climatic 1. Notice must be given to the contract Again, similar wording to that of JCT
FIDIC Red Book: 8.4 (c) conditions. administrator with a full description of and ICE vague and no guidance and
Silver Book: N/A the events as soon as practicable, and more subjective than NEC3.
not later than 28 days after the contractor Claimants must not confuse
became aware or should have been exceptional with unforeseeable
aware of the delay (clause 20.1). (employers risks clause 17.3/17.4).
2. Provide all particulars of the claim
within 42 days of becoming aware of
the claim or within 42 days of when the
contractor should have become aware, of
the event or circumstance.
3. On receipt of the notice, the
administrator must respond within 42
days of receipt of the claim approving or
disapproving the claim.
30 Payment Construction Law Review

*SVZPUN[OLVVKNH[LZ
The effect of the payment provisions under LDEDCA 2009

Peter Barnes FCIArb FCIOB MCInstCES MICE MRICS, Director, Blue Sky ADR

F OR the 2015 Construction Law Review, I wrote an article


entitled Be careful what you wish for lest it becomes
true. It focused on the ISG Construction Ltd v Seevic College
(2014) EWHC 4007 (TCC) and Galliford Try Building Ltd v Estura Ltd
(2015) EWHC 412 (TCC) cases, and how the judicial interpretation
of the payment provisions of the Local Democracy, Economic
Development and Construction Act (2009) from those cases, in
effect, opened the oodgates for default payment notice claims.
My feeling at that time was that when the courts realised just how
wide the oodgates had been opened, they may try to close the
oodgates somewhat; and this is something that they have clearly
been trying to do doing over the past year.
First, it seems clear to me that the courts did not intend for
the oodgates to be opened quite so wide in the rst place. This
became apparent from the comments of Mr Justice Edwards-Stuart
in the Galliford Try case. He emphasised again the binding effect
of a notied sum in respect of a default payment notice that
had not been challenged by a valid pay less notice. He made it
clear that the amount due arising from a default payment notice
only related to that particular interim payment cycle, and there
was nothing to stop a party from rectifying the position (if it was
indeed incorrect) in a subsequent interim payment cycle.
However, both the ISG and Galliford Try cases were decided
upon Joint Contracts Tribunal (JCT) contracts. Unless amended,
JCT contracts do not allow for negative valuations and do not
allow for payments being repaid by a contractor on an interim
valuation basis. The only reconciliation of this kind is carried out
at the nal certicate stage. Therefore, even though a contractor
could have a revaluation of the works conrmed at a later
valuation date under a JCT contract, in practice this would have
no contractual effect as, rstly, the initial adjudicators decision
would still be enforced and, secondly, there is not an option for a
negative valuation in respect of interim valuations.

12 months on, another In reality the above factors (amongst several other exceptional
circumstances particular to the case) were part of the reason
look at default payment why Mr Justice Edwards-Stuart came to the judgment he did
in the Galliford Try case to defer part of the enforcement of
notice claims the adjudicators decision. (Although it must be noted that the
principles owing from the ISG case were still followed.)

Matthew Harding v Paice and Springhall


About this same time, another signicant case was going through
the courts (eventually being heard by the Court of Appeal in
November 2015). Matthew Harding v Paice and Springhall (2015)
EWCA Civ 1231 related specically to a termination account. In
that case, the Court of Appeal reached the conclusion that nal
account type applications (which they considered a termination
account to be) are bound by different rules from interim payment
account type applications. Therefore, this case had no impact in
respect of interim payments under unamended JCT contracts.
The general perception after the ISG and Galliford Try cases
was that all you needed to do was put a document in at about the
2016 Payment 31

right time, with an amount due being shown (without being overly concerned with its
content), and one that could be construed as being a default payment notice. If no pay
less notice was issued, the amount requested in the default payment notice would be the
amount that would need to be paid. However, the courts had other ideas.

Leeds v Waco
The rst matter that the courts dealt with was in the Leeds City Council v Waco UK Ltd
(2015) EWHC 1400 (TCC) case. It was in respect of what default payment notices needed to
be submitted at the right time to be valid.
After practical completion, Waco submitted its September 2014 payment application six
days before the contractual date specied. The employers agent refused to recognise the
payment application as it had been served prematurely. The contractor referred the matter
to adjudication and obtained a decision in its favour.
However, in subsequent part 8 proceedings, the court found that the contractors
September 2014 post-practical completion payment application was not valid. It had been
served too early, even though a previous post-practical completion payment application
was issued early and was accepted by the employers agent. Therefore, the contractor
could not rely on the September 2014 payment application as being a default payment
notice as it had not been served at the correct time.

Caledonian v Mar City


Soon after this, another case, Caledonian Modular Ltd v Mar City Developments Ltd (2015)
EWHC 1855 (TCC), considered a further related matter. Caledonian sought payment in respect
of a payment application that it said had been made on 13 February 2015.
Mar City said the claim for payment had not been made until 19 March 2015, and that
Mar City had issued a pay less notice to nullify any effect that the payment application
may have had. Caledonian sent an email on 13 February 2015 (with attachments) and this
was sent to Mar by registered post and was received by Mar on 16 February 2015. On
19 March 2015, Caledonian submitted its invoice, and attached the breakdown attached
to the email dated 13 February 2015. Upon receipt of that invoice, Mar issued a pay less
notice which nullied the effect of the invoice.
However, Caledonian said that its invoice was a default payment notice, and its original
payment claim had been by way of the email dated 13 February 2015, which had not
been countered by a pay less notice from Mar. The adjudicator agreed with Caledonian,
but in the ensuing enforcement proceedings, the court did not agree.
The court had no hesitation in concluding that the documents sent by email on
13 February 2015 did not constitute an application for payment or a default payment
notice, because none of the documents said that they were a new application for interim
payment, and the invoice dated 19 March 2015 did not say it was a default payment
notice. Therefore, there had been a lack of transparency in respect of the purpose of
Caledonians email dated 13 February 2015, and the court did not accept that it could be
accepted as being a payment application or a default payment notice.

Henia v Beck
Following on from this, the case of Henia Investments Inc v Beck Interiors Ltd (2015) EWHC
2433 (TCC)came along. In this case, Beck submitted an application for payment on 28 April
2015, six days later than it should have been submitted.
The contract administrator issued its own payment certicate in respect of the April
2015 valuation period, on 6 May 2015, but the payment certicate was one day late. Beck
did not submit a payment application for the end of May 2015 valuation period, but the
contract administrator issued a payment certicate in any event, although that certicate
was again issued one day late. The employer issued a pay less notice against this latter
payment certicate, reducing the amount due to the contractor to nil.
At this point, Beck said that if its application for payment dated 28 April 2015 had been
served too late for the end of the April 2015 valuation date, it should be carried over as
the payment application for the end of May 2015 valuation. Also because the contract
administrators payment certicate at the beginning of June 2015 had been issued one
day late and was therefore in-valid (and as the pay less notice related to that said in-valid
payment certicate was also by default in-valid), Becks application for payment dated
28 April 2015 became the default payment notice which set out the notied sum that
needed to be paid. The adjudicator agreed with this position, but the court did not.
The court found that there was nothing in the 28 April 2015 payment application that
indicated that it was a payment application for 29 May 2015 (in fact the document said
that the works had been valued up to 30 April 2015). Also, the said document was not
in the substance or form of all previous payment applications. Therefore, Becks
payment application dated 28 April 2015 could not be relied upon as being a default
payment notice.
32 Payment Construction Law Review

And others...
Following on from the above, the Severeld (UK) Ltd v Duro Felguera UK Ltd (2015)
EWHC 3352 (TCC) case made it clear that a default payment notice needed to clearly set
out the basis on which the sum claimed had been calculated. The Grove Developments
Ltd v Balfour Beatty Regional Construction Ltd (2016) EWHC 168 (TCC) case found that
the payment provisions of the scheme were not imported to provide for further interim
payments after the last date on an agreed schedule of dates had expired.
Other similar cases followed in respect of the need to comply precisely with the
required timing of applications and/or the need for there to be complete transparency
of submissions. These include Manor Asset Ltd v Demolition Services Ltd (2016) EWHC
222 (TCC); RMC Building & Civil Engineering Ltd v UK Construction Ltd (2016) EWHC 241
(TCC); and Jawaby Property Investment Limited v The Interiors Group Limited (2016) EWHC
557(TCC).

Whats the position?


In summary of the above, the courts position is that there is little scope for latitude. If a
contractor wishes to have the benet of the interim payment regime pursuant to LDEDCA
2009, then its application for interim payment must be submitted at the right time, it must
be in substance, form and intent an interim application/default payment notice stating
the sum considered by the contractor as due at the relevant due date, and it must be
transparent and free from ambiguity.
Despite all of the above, one aspect that the courts have not yet decided upon is
in respect of the substance of a default payment notice. It is therefore not clear what
the courts will say about a default payment notice that does not comply with the
requirements of the contract in terms of its content, but this may be something that is
claried through judicial guidance during the coming year.
Therefore, at the moment the oodgates referred to at the beginning of this article have
been drawn much closer together than they were a year ago. It is possible that they will
be drawn together even closer during the course of the coming year, thereby reducing the
full ow of default payment notice claims to a mere trickle.

Peter Barnes FCIArb FCIOB MCInstCES MICE MRICS, Director, Blue Sky ADR
www.blueskyadr.com pbarnes@blueskyadr.com
2016 Extensions of Time 33

Proving extension of time claims


Manoj Bahl CEng MICE, Senior Director, FTI Consulting

E XTENSIONS of time are again hitting the headlines following the recent
Technology and Construction Court decision in Carillion Construction Ltd v Woods
Bagot Europe Ltd and others (2016) EWHC 905 (TCC). It was a dispute in relation
to the proper interpretation of a standard form of construction subcontract provision.
Carillion contended that the nature of the particular subcontract clause warranted a
departure from the method by which extensions of time are usually applied. However,
the court rejected this argument, and found in Emcors favour that an extension of time
was to be treated in the usual manner. With this in mind, what are the key parameters for
determining extensions of time and what is the level of proof required?

Background
Uncertainty is endemic within the construction industry and, through a combination of
many factors, construction projects do not proceed as planned with the risk that the
contractual completion date will not be met. For contractors, this results in a delay to the
completion of the works, with a corresponding liability to the employer for liquidated
damages and the potential of cost overruns due to the increased costs of performance
arising from prolongation. For employers, delays result in a loss of prot, loss of revenue
and potential liability to the design team and other members of the professional team.
The construction team at FTI Consulting is regularly engaged

What are the key


to provide expert delay services in relation to formal dispute
procedures but also, as a precursor, to prepare or rebut extension
parameters for of time claims. In these instances a contractor will seek assistance
in identifying and setting out its entitlement to an extension of
determining extensions of time or an employer may seek assistance in assessing the
criticality of alleged delays and the appropriate award of an
time and what is the level extension of time. In doing so, the key principles relating to

of proof required?
the preparation and award of extensions of time are often
misinterpreted or over simplied.

The need for extension of time provisions


The prevention principle is derived from Holme v Guppy (1838)
150 ER1195 where an employer withheld payment following delay,
even though it had failed to give possession of the site for four
weeks following the execution of the contract. It states that
where a contractor is prevented by the act of the employer, it is
not in default.
This position was conrmed in Peak Construction (Liverpool)
v McKinney Foundations (1971) 1 BLR 111 CA where it was added
that if, for reasons within the employers control, the contractor is
prevented from completing the works by the completion date, and
there is no mechanism to extend time for performance (or it has
not been properly extended), the employer can no longer hold the
contractor to the original completion date. Instead there is no rm
date from which liquidated damages may be calculated from and,
as a result, time is then said to be at large.1 In such instances the
contractor is granted a reasonable time to complete the works.
Therefore the provision to award an extension of time acts
as a mechanism to extend the contract completion date, thus
preventing the contract period becoming at large and relieving the
1
Per Wells v Army & Navy Cooperative Society (1902) 86 LT 764 where it was held that
if time has become at large because of some act or default of the employer, there
will be no date from which the liquidated damages can run and therefore the right to
claim them will have gone
34 Extensions of Time Construction Law Review

Addressing the issue of


likely to cause, or indeed has caused, a delay to progress of the
concurrent delay is one of works, and consequently has impacted upon the completion date.
The burden of proof in relation to demonstrating the effect of
the most important factors to delay requires consideration of two key principles:
consider when demonstrating an
Critical delay-differentiating between a delay to progress and
extension of time claim. a delay to completion
For an entitlement to an extension of time to arise a delay
must be critical to completion. One accepted and approved
contractor from a liability to pay liquidated denition2 as to what constitutes the critical path is that it is
damages up to the extended contract the longest logic-linked path through a programme to the
completion date. completion date. Accordingly, a delay to any of the activities
on the critical path would lead to a delay to the completion
What needs to be proved? date. Where (total) oat3 exists within the overall programme
In order to determine whether an against the completion date this would need to be eliminated
entitlement to an extension of time exists, before any critical delay is experienced. Further, where an
it is necessary to establish that: (i) the excusable event affects non-critical activities the delay will
cause of the delay was excusable, under have to be sufcient to eliminate all oat before a critical
the terms of the contract; and also (ii) as a delay is experienced.
consequence, there was a delay to the date Concurrent delay-often claimed, seldom properly identied
for completion. Addressing the issue of concurrent delay is one of the
most important factors to consider when demonstrating an
Identifying an excusable event extension of time claim. As a result of this it is becoming
In light of the judicial decision in Peak increasingly common for concurrent delay clauses to be
Construction v McKinney Foundations, included within construction contracts. The absence of such
express provision is now included within provision frequently gives rise to disputes.
standard forms of construction contracts to
grant time relief for delays caused by the The commonly accepted and approved denition4 of concurrent
employer (or its representatives). Moreover, delay is when there are two or more delay events occurring at
todays standard forms go further and allow the same time which are approximately equal in terms of causing
for the granting of an extension of time for delay to the completion date. This narrow denition results in
a range of specied events. the occurrence of true concurrency being rare. Frequently, this
Each standard form of construction principle is falsely alleged in instances where one of the events
contract deals with this risk allocation/ can properly be said to be only a minor cause of the delay, and
sharing differently, but these excusable so can be disregarded altogether resulting in there being no
events (referred to as relevant events concurrency.
under the Joint Contracts Tribunal (JCT) There are broadly three different situations in which concurrent
and compensation events under the New delay could occur. Firstly, and most simply, when both an
Engineering Contract (NEC)) provide the employer and a contractor delay each simultaneously affect an
contractor with an entitlement to extension activity on the critical path and thus delay the overall project.
of time to complete its works. A list of The second is where there is an employer and contractor delay
excusable events is set out at clause 2.29 of each affecting different critical paths of activities within the
the JCT standard building contract; clause programme at the same time, but where the delays to each of
60 of NEC3; clause 8.4 of the International these paths equally affect the overall completion of the project.
Federation of Consulting Engineers (FIDIC) The third scenario is where during a period of either (contractor
or employer) delay there is a further delay attributable to the other
Red Book; and clause 18.3 of the Project
party which equally causes a delay to the completion date during
Partnering Contracts (PPC2000).
the period of time over which it occurs.
Following the decision in Walter Lilly & Company Ltd v Mackay
Demonstrating a delay to the date for completion
and another (2012) EWHC 1773 (TCC), the preferred position5 states
In the absence of express terms to the
that in each of these scenarios, where a contractors delay runs
contrary, the occurrence of an excusable
truly concurrent with an employers delay, the contractors delay
event alone is insufcient to give rise
should not reduce any extension of time due.
to an entitlement to an extension of
2
time. Instead, in order to successfully Burr A. (2016), Delay and Disruption in Construction Contracts, Fifth Edition:
London, Sweet & Maxwell at 1-029
demonstrate such entitlement, the standard 3
Float, with regards to critical path analysis, is a term used to dene the period of time
forms of construction contract (for example in which no dened work is shown to take place. Furthermore total oat is used to
clause 2.28.2 of the JCT standard form describe the maximum amount of time an activity within a programme can be delayed
2011 edition; 63.3 of NEC3; clause 8.4 of before the date for completion is impacted by virtue of the logic links present
4
John Marrin QC, Concurrent Delay, SCL paper 100 (February 2002) - as approved in
FIDIC Red Book 1999 edition; and clause Adyard Abu Dhabi v SD Marine Services (2011) EWHC 848
18.3 of PPC2000) require the contractor to 5
Which follows the principles set out within Henry Boot Construction (UK) Limited v
demonstrate that the excusable event is Malmaison Hotel (Manhattan) Limited (1999) All ER 118
2016 Extensions of Time 35

Critical path analysis


Whilst case law suggests that there is no requirement for an It is becoming increasingly
extension of time application to contain a critical path analysis6, common for concurrent delay
and that instead it is possible to leave it to the employer to form
an opinion as to the effect of an alleged delay with or without clauses to be included within
employing its own analysis, it would naturally be preferable
for the contractor to demonstrate its claim for delay. Often
construction contracts.
a contractors allegation that an excusable event delayed the
completion date is unfounded and upon the implementation of a subjectivity of this process and set out
proper critical path delay analysis, it becomes apparent that the the following criteria to be adopted in
critical progress of the works remained unaffected by the event calculating a fair and reasonable award:
being claimed by the contractor.
There are various methods of critical path analysis which Application of the rules of the contract.
exist for analysing and demonstrating the effects of delay events. Recognition of the effects of change.
The methodology selected to objectively illustrate cause and A logical analysis, in a methodical
effect within an extension of time claim is normally dictated
way, of the effect of relevant events on
by the timing of the analysis together with the availability of
the contractors programme.
contemporaneous records and time/resource. The timing is of
An objective calculation, rather than an
relevance as the use of a prospective analysis (based upon the
impressionist assessment, of the delay
likely effects of a delay) or a retrospective analysis (based upon
caused by the excusable event(s).
actual fact) will provide different results.
The Society of Construction Laws Delay and Disruption
Therefore, it would follow that any
Protocol provides guidance as to appropriate methods of delay
extension of time application prepared
analysis. In doing so it is noted that different methods of critical
by a contractor should assist the employer
path analysis have the ability to produce very different results. The
in carrying out the above steps. In doing
selection of a suitable technique requires careful consideration
so the importance of a proper critical
with regards to achieving the goal of demonstrating and illustrating
path analysis, to illustrate the delay to
the critical effects of the delay events complained about.
the completion date experienced, cannot
be overlooked.
A further obstacle
As a precursor to being granted relief for an excusable delay, most
Conclusion
standard forms of construction contracts require the contractor to
The majority of standard forms of
provide notication when the progress of the works is affected by
construction contract enable the contract
a delay, excusable or otherwise, as close as possible to when the
administrator to grant an extension of time
delay arises. For example, clause 2.27 of the JCT standard form,
where a delay occurs due to its own act
61.3 of NEC3, clause 20.1 of FIDIC Red Book and clause 18.4 of
of prevention or for certain other specied
PPC2000 all expressly state a requirement for such notice.
causes. However, before the employer can
The common law position raises doubts as to whether a
grant an extension of time, it needs to be
condition precedent, as set out within the JCT suite, is effective
satised that not only has an excusable
in dismissing the prevention principle in relation to an excusable
event, as dened under the contract,
critical delay,7 although the NEC3 and FIDIC forms expressly
occurred, but also that it is likely to cause,
state that a failure to provide a timely notication dismisses any
or has caused, the completion of the works
subsequent claim for an extension of time.8
to be delayed.
Herein lies the opportunity for the
The basis for an award
contractor to assist in this evaluation
If a contractor demonstrates that an excusable delay event was
process by way of including a robust
critical, then there is an obligation upon the employer (or its
delay analysis demonstrating the causative
representatives) to make a fair and reasonable assessment of
effect of the excusable delay. The proper
what the excusable delay to the completion date is/was and the
application of a critical path analysis,
entitlement to an extension of time which is due.
although not compulsory, can accordingly
The judgment in John Barker Construction Limited v London
be used to effectively demonstrate the
Portman Hotel Limited (1996) 83 BLR 31 sought to clarify the
criticality of delays, either as a driving
6
John Barker Construction Limited v London Portman Hotel Limited (1996) 83 BLR 31 delay or concurrent delay, and the
7
In line with the Scottish case of City Inn Ltd v Shepherd Construction Ltd (2007) Scot
CSOH 190 and Multiplex Construction (UK) Ltd v Honeywell Control Systems Ltd (2007)
entitlement to an extension of time which
EWHC 236 (TCC) which have cast doubts on whether Gaymark Investments Pty Ltd v is due as a result.
Walter Construction Group (1999), which stated that failure by a contractor to comply
with a condition precedent notifying the employer of a delay rendered the extension Manoj Bahl CEng MICE, Senior Director
of time provision ineffective and set time at large, is the position in English law
8
These clauses are drafted in line with Bremer Handelsgesellschaft MBH v Vanden
FTI Consulting
Avenne Izegem (1978) 2 Lloyds Rep. 109 which stated that precise/clear timetables www.fticonsulting.com
must be identiable and the result of missing this timetable must be clearly spelt out @FTIConsulting
36 Payment Construction Law Review

Fixed payment schedules:


Grove v Balfour Beatty
Alan Williamson FCInstCES, Principal Consultant, Schoeld Lothian

A T rst blush, the judgment in


this case seems somewhat odd.
It appears to y in the face of
the contractors statutory right to receive
when any pay less notice should be served
prior to this.
Balfour Beatty served a notice of
adjudication on 19 November, followed by
regular interim payments during the course its referral notice on 26 November 2015,
of a construction contract of over 45 days seeking an award of circa 23.20m, as
duration. However, when the courts applied for in its application number 24 of
judgment is considered in full, it can be 21 August 2015. The adjudicator awarded
understood how the contract specic facts Balfour Beatty an amount of circa 2m, but
led to this conclusion. Grove paid no further monies and during
the adjudication proceedings issued part
The dispute 8 proceedings seeking clarication of its
The brief details of this dispute leading rights under the contract.
up to the decision in the Technology and
Construction Court earlier this year can be The TCC decision
summarised as such. Grove Developments In court, Balfour Beatty raised two
Limited and Balfour Beatty Construction principal arguments in its defence,
Limited entered into a Joint Contracts both relying upon certain aspects of
Tribunal (JCT) design and build contract, the statutory payment mechanism of
with a contract sum of 121,059,632, the Housing Grants, Construction and
a commencement date of July 2013 Regeneration Act (1996), as enacted by
and a completion date of 22 July 2015. the Scheme for Construction Contracts
Subsequently, the parties agreed to a (England and Wales) Regulations of 1998,
payment schedule running from September as amended by the Local Democracy,
2013 to July 2015, consisting of 23 interim Economic Development and Construction
applications. Act (2009):
The works were not completed on
time and Balfour Beatty issued application Balfour Beattys right to instalment
number 24 on 21 August 2015 for 23.17m. payments under a construction
In response to this, Groves agent issued contract exceeding 45 days duration,
a payment certicate on 28 August 2015 which it contended that commercial
in the sum of 2,349,504, with the caveat common sense dictated should be
that the employer may withhold or deduct made in relation to all work carried
liquidated damages. Grove did indeed out under the said contract.
(SVVRH[JVU[YHJ[ZWLJPJ subsequently issue a pay less notice on As the parties had been unable to
payment mechanisms 15 September 2015, showing a much lesser
sum to now be paid to Balfour Beatty of
agree a payment mechanism for
further payments after application 23,
439,503. the entire payment mechanism of the
Probably in the realisation that scheme should be imported instead.
the project was not now going to be This would have the result of Groves
completed on time, the parties engaged in pay less notice served in relation to
considerable correspondence between May application 24 being late, with the
and September 2015 endeavouring to agree consequence that the full amount
further valuation dates after application 23. claimed should be paid to Balfour
However, no agreement was concluded Beatty.
due to disagreement as to whether the due
date should be considered as the date of It is worth briey summarising here what
Balfour Beattys application or the date of precise statutory payment mechanisms
Groves payment certicate. Clearly, this the legislation requires to be incorporated
would impact upon what the nal date for into all construction contracts. The act
payment should be, which fell to be 28 and scheme give the entitlement to stage
days after the due date and, consequently, payments if the contract is longer than 45
Contract Services
Schofield Lothian is a professional services
consultancy delivering added value with a
collaborative approach on construction and
infrastructure projects. Established in 1979,
we have delivered legal and contract services
on many large infrastructure programmes and
property projects throughout the UK with major
contractors, public organisations and property
companies. We provide the following contract
services:

Claims Avoidance Contract Drafting


Contract Review & Advice Dispute Resolution
Expert Witness Legal Commercial Advice
Litigation Support Risk Management

For information on Contract Services,


contact Alan Williamson,
alanwilliamson@schofieldlothian.com
For other services, contact Mike Upton,
07810 850030, mikeupton@schofieldlothian.com

Consents & Engagement | Environment & Sustainability | Estimating | Project Management | Quantity Surveying | Contract Services
Schofield Lothian Limited, 3-7 Temple Avenue, London EC4Y 0DT 020 7842 0920 www.schofieldlothian.com

CONSTRUCTION & INFRASTRUCTURE CONSULTANTS


38 Payment Construction Law Review

Probably in the realisation that the project was not


now going to be completed on time, the parties
engaged in considerable correspondence.

days duration, but the parties are free to agree the amounts and 15 September 2015 was on time. Thus
intervals of the said stage payments. If no such provisions are the payment mechanism of the scheme
included, then those of the scheme are to apply. Furthermore, did not need to be imported, as the
the contract should provide an adequate mechanism to determine contract already had compliant payment
when payments become due and a nal date for payment provisions. Furthermore, the contractor
again, the parties are free to agree the period between the due was estopped from changing its argument
date and the nal date for payment, with the provisions of the to the schemes payment mechanism in
scheme to apply if no such provisions are included within the any event, due to earlier representations
construction contract. made in correspondence as to its view
However, Mr Justice Edwards-Stuart was not swayed by either upon the applicable nal dates for payment
of these propositions, stating that the court should not strain based upon the original contract payment
to nd ambiguity where none exists. He considered that the schedule.
requirements of the act and scheme had been met and that it was
not automatic for instalment payments to continue to be made for Summing up
all work under a construction contract. As already commented in the introduction,
Indeed, he went so far as to say that the employers ability to the ndings in this case initially appear
refuse further interim payments could be used to exert commercial to be somewhat surprising. It is a very
pressure upon the contractor to complete on time. If further common occurrence for projects to overrun
periodic payments owed, in addition to those already agreed, and the employer to continue to make
this would restrict the parties commercial freedom to agree to any interim payments to the contractor, even if
amounts being paid at any intervals, for example the front loading the dates upon an incorporated payment
or end loading of payments. schedule have in fact expired. Although
The court further recorded that just because interim payments the ndings here will not be of general
did not cover all of the works duration, this did not mean that the application, due to certain case specic
whole of the schemes payment mechanism should be imported circumstances, contractors will nonetheless
into the contract. The contract already provided due dates and need to be wary when xed payment
nal dates for payment which, when read together with the schedules are incorporated into their
applications schedule, demonstrated that the parties had agreed conditions of contract.
the intervals and circumstances in which payments became due. Whilst most conditions provide for a
The parties had entered into an agreement for stage payments for further nal account payment at the end
23 interim payments upon the agreed dates within the schedule of the project, this could be many months
and no more. away in the event of signicant programme
Mr Justice Edwards-Stuart went on to assert that it was not overruns often at the end of the defects
possible to construe implied terms into the contract in such correction period that would be of at least
circumstances, as the contractor would have been aware of the 12 months duration, with consequential
consequences of not nishing on time and running out of interim adverse effects upon the contractors
payments. It had the opportunity to negotiate protective measures cashow with subcontractors, suppliers
at the outset but did not, so terms could not be implied due to and the like still requiring payment in
commercial common sense. this period of overrun. Contractors would
Although it was admitted that further interim payments after therefore be well advised, if in doubt,
application 23 were discussed between the parties, the terms to seek the incorporation of an express
under which they were to be made were not agreed. This would provision, at the contract negotiation stage,
be a pre-condition to a legally binding agreement. setting out what would happen should
Drawing all of these threads together, clearly the courts the applications provided for within any
decision was that Balfour Beatty was not entitled to any further incorporated payment schedule expire
interim payments after application 23. prior to the works being complete.
Although it was not necessary for the judge to decide upon
the issue of whether Grove had served a valid pay less notice Alan Williamson FCInstCES,
in respect of application 24, due to the above conclusions, Mr Principal Consultant,
Justice Edwards-Stuart did pass comment upon this second Schoeld Lothian
point. He concluded that whatever way the contract payment alanwilliamson@schoeldlothian.com
mechanism was looked at, Groves pay less notice given on www.schoeldlothian.com
2016 Penalties 39

Knocked out on penalties


Kate Corby, Partner, and William Jones, Associate, Baker & McKenzie

W ITH Euro 2016 in full swing


at the time of writing, the rule
against penalties may sound
like a dream come true for any die hard
Some commentators had
England fan. Indeed, the Supreme Courts
handing down of its decision in the case speculated that the Supreme
of Cavendish Square Holding BV v Talal
El Makdessi (2015) UKSC 67 on 4 November Court might use the opportunity
2015 was awaited with almost as much to abolish this principle.
anticipation as this years main event in the
footballing calendar.
El Makdessi was the rst time in a whether a clause should be classed as an
century that the UKs most senior court unenforceable penalty. In this article, we
had considered the rule against penalties, examine how El Makdessi has re-shaped
and some commentators had speculated the penalty rule in the context of liquidated
that the Supreme Court might use the damages clauses, and look forward to what
opportunity to abolish this principle. The impact this may have on businesses in the
rule against penalties operates to prevent construction industry in the future.
enforcement of a contractual clause that
imposes a penalty on a party who has Previous law
breached the contract. The logic is that a Prior to the judgment in El Makdessi, the
party should be free to breach a contract, leading case was Dunlop Pneumatic Tyre
provided it pays damages to its contractual Co Ltd v New Garage and Motor Co Ltd
counterparty, which should compensate (1915) AC 79. The speech of Lord Dunedin
the innocent party for the loss it suffers in this case contains the guidance that was
arising from the breach, rather than act so most commonly referred to by practitioners
as to punish the defaulting party. on the distinction between a penalty and
The penalty rule most commonly comes a liquidated damages clause. This can be
into play in construction contracts in summarised as follows:
relation to the enforceability of liquidated
damages provisions. Liquidated damages 1. Although the words the parties use
to describe a particular provision are
provisions are used to agree in advance
not irrelevant, the court must decide
the level of damages one party will pay
in substance whether a provision is a
Liquidated damages to the other if it breaches the contract.
Such clauses are attractive as they provide
penalty or a liquidated damages clause.
2. The essence of a penalty is that it
clauses and the rule a contractor with certainty about the
maximum liability it could face in relation
seeks to deter a party from committing a

against penalties to the relevant breaches, thereby offering


breach by requiring them to pay money
on occurrence of that breach. The
a means of controlling the level of risk essence of a liquidated damages clause
taken on in relation to a particular contract. is that it is a genuine pre-estimate of
In addition they, in theory at least, allow loss agreed by the parties.
for disputes to be resolved quickly and 3. Whether a provision is a penalty or
without recourse to the courts (or an liquidated damages clause depends on
arbitral tribunal). In practice, however, the the terms and circumstances of each
question of whether liquidated damages particular contract, assessed from the
are unenforceable due to the penalty rule perspective of when the contract was
may itself lead to a time-consuming and created, rather than when the breach
bitterly contested satellite dispute. occurred.
Ultimately, the Supreme Court did 4. A number of tests may be used,
not use El Makdessi to kick the penalty which if applicable to a particular case,
rule out of English contract law. It did, may assist with assessing the nature of a
however, reformulate the legal test as to particular provision:
40 Penalties Construction Law Review

The El Makdessi decision


The decision in El Makdessi has
reformulated the law against penalties,
and arguably allows more exibility for
Indeed, the risk of being liable to pay damages contracting parties when it comes to
devising liquidated damages, or similar,
itself functions as a deterrent against breach. clauses. In the leading joint judgment,
Lords Neuberger and Sumption explained
as follows:
a. A provision will be a penalty if the sum payable is
The true test is whether the impugned
extravagant and unconscionable when compared with
provision is a secondary obligation
the greatest loss that conceivably could have followed which imposes a detriment on the
from a breach. contract-breaker out of all proportion to
b. A provision will be a penalty if the breach in question is any legitimate interest of the innocent
a party failing to pay a sum of money, and the sum payable party in the enforcement of the primary
is larger than the amount that ought to have been paid in obligation. 1
the rst place.
c. There is a presumption that a clause will be a penalty if It is also useful to look at the language
the same amount is required to be paid when one, or more, used to set out the legal test in the
of several different breaches occur, and some of these judgments of the other lords. Lord Mance
events cause serious, and others insignicant, loss to the explained the test as follows:
innocent party.
d. Nevertheless, a provision should not be prevented from What is necessary in each case is to
being enforced simply because the consequences of the consider, rst, whether any (and if
breach were almost impossible to predict when the contract so what) legitimate business interest
was entered into. is served and protected by the clause,
and, second, whether assuming such
Looking at this guidance more closely, points 1 and 3 can be an interest to exist, the provision made
said to be restatements of general principles of contractual for the interest is nevertheless in the
interpretation. As such, point 2, taken in light of the four tests circumstances, extravagant, exorbitant
set out in point 4 (as applicable), was previously taken to be or unconscionable.
the classic test of whether a liquidated damages clause was
enforceable or not. Simply put, under the old law, a liquidated Lord Hodges formulation was:
damages clause would be enforceable if the amount to be paid
on a particular breach of a contract represented a genuine attempt the correct test for a penalty is
by the parties to estimate what the likely loss owing from whether the sum or remedy stipulated
that breach would be. On the contrary, a clause would be an as a consequence of a breach of
unenforceable penalty where its core intention was to deter the contract is exorbitant or unconscionable
potential payer of damages from breaching the contract, or where when regard is had to the innocent
the amount of damages to be paid was clearly disproportionate partys interest in the performance of
the contract.
compared to the amount of loss that could have been envisaged to
ow from the breach.
On rst reading, one may be forgiven for
Prior to the decision in El Makdessi, commentators and
thinking that their Lordships language does
practitioners had expressed widespread frustration with this
more to cloud rather than clarify matters.
formulation of the law for numerous reasons. For example, the
Nonetheless, our view is that the El
rule against penalties seemed to represent a agrant contradiction
Makdessi judgment can be unpacked into a
of the principle that contracting parties should have the freedom three-step test, as follows:
to decide between themselves the terms of agreements that bind
them, which is at the heart of English contract law. Further, there Step 1: Does the clause in question
did not appear to be any good reason why including a term in a only come into play once a breach has
contract designed to deter one party from breaching the contract occurred (i.e. is it a secondary, rather
should be unenforceable. Indeed, the risk of being liable to pay than a primary, obligation)?
damages itself functions as a deterrent against breach. Step 2: Does the innocent party have
Another frustration lay in the fact that the task of attempting to a legitimate business interest that the
estimate in advance the likely loss owing from a breach felt very clause serves to protect?
much like arbitrary crystal-ball gazing. Finally, this formulation Step 3: Are the consequences of the
of the law prevented a number of contractual mechanisms put in clause for the party in breach out of all
place for sensible and practical commercial reasons. One example proportion to the legitimate business
would be a consideration clause that offered bonus payments interest of the innocent party?
where a party delivered a project early by a set time period,
tied with a clause that reduced the level of consideration by an Aside from the re-formulation of the legal
equivalent amount if a project were delayed by that same amount test for the penalty rule itself, El Makdessi
of time. This carrot and stick approach to encourage a contracting
1
party to complete work on time makes good commercial sense. The distinction between primary and secondary
obligations is that the former is a contractual obligation
Nonetheless, under the old law against penalties, unless the clause to be performed in the normal course of the contract,
reducing the consideration could be said to represent a genuine and the latter is one that only comes into play if the
pre-estimate of loss, it could fall to be unenforceable. contract is breached
2016 Penalties 41

contains some other guidance as to how the rule against penalties


operates and when it will come into play. Specically, the court
made clear that in a commercial context, the principle of freedom
of contract should be upheld as far as possible:

In a negotiated contract between properly advised parties


of comparable bargaining power, the strong initial presumption
must be that the parties themselves are the best judges of what
is legitimate in a provision dealing with the consequences Does the clause in question only come into
of breach. play once a breach has occurred?

Their Lordships also appeared to remove (or at least lessen)


consideration of the concepts of genuine pre-estimate of loss and N
whether a clause acts as a deterrent to breach, from the legal test.
Distancing their analysis from that of Lord Dunedin in Dunlop, Not a penalty Y
Lords Neuberger and Sumption explained:

The real question when a contractual provision is challenged


as a penalty is whether it is penal, not whether it is a pre-
estimate of loss The fact that the clause is not a pre-estimate Does the innocent party have a
of loss does not therefore, at any rate without more, mean that legitimate business interest that the
it is penal. To describe it as a deterrent does not add anything. clause serves to protect?
A deterrent provision in a contract is simply one species of
provision designed to inuence the conduct of the party
N
potentially affected.

Nonetheless, the court refrained from abandoning the concept of Penalty Y


genuine pre-estimate of loss altogether, and seemed to suggest
that this test may still have some use in the liquidated damages
context. Lords Neuberger and Sumption said that:
Are the consequences of the clause for
In the case of a straightforward damages clause, [the innocent the party in breach out of all proportion
partys] interest will rarely extend beyond compensation for the to the legitimate business interest of
breach, and we therefore expect that Lord Dunedins four tests the innocent party?
would usually be perfectly adequate to determine its validity.
N Y
Lord Hodge echoed this and went further still, stating that:
Not a penalty Penalty
The focus on the disproportion between the specied sum and
damage capable of pre-estimation makes sense in the context of The penalty owchart.
a damages clause

He continued:
provision dealing with the consequences
Where the test [for a penalty] is to be applied to a clause xing of breach are honoured by the lower
the level of damages to be paid on breach, an extravagant courts. For those in the process of drafting,
disproportion between the stipulated sum and the highest level or analysing the enforceability of, a
of damages that could possibly arise from the breach would liquidated damages clause, our guidance
amount to a penalty and thus be unenforceable. would be to refer rst to the three-stage
test set out above.
This element of the Supreme Court judgment seems somewhat If the clause can also be shown to pass
self-contradictory, and may ultimately lead to some confusion the genuine pre-estimate of loss test,
when considering the enforceability of a liquidated damages this should provide additional comfort
clause. Nonetheless, our view is that their Lordships were that it will be enforceable. This approach
unequivocal that the genuine legal test for assessing whether a should allow players to enforce liquidated
clause is penal is the three-step test we set out earlier. damages clauses in the course of a project,
without wasting extra time debating
Comment whether or not something falls foul of the
At the time of writing, there have not yet been any reported penalty rule.
cases that apply the El Makdessi decision to a liquidated damages
scenario. As such, it remains to be seen how the courts will Kate Corby, Partner, and William Jones,
interpret the Supreme Courts reframing of the penalty rule, and Associate, Baker & McKenzie
whether they will allow contracting parties more leeway to agree Kate.Corby@bakermckenzie.com
in advance the amounts of damages to be paid on breach. William.Jones@bakermckenzie.com
Since liquidated damages provisions are a useful and practical www.bakermckenzie.com
tool for parties to avoid disputes arising from construction @bakermckenzie
projects, it is hoped that the Supreme Courts comments about
parties being themselves the best judges of what is legitimate in a Kate Corby is the ICES advisory solicitor.
42 Collateral Warranties Construction Law Review

Collateral warranties:
I know I said I would give you them, but...
Fenella Mason, Head of Construction and Projects, Burness Paull

C OLLATERAL warranties are a fact of life in construction


projects. Whether you view them as a necessary evil or an
essential protection depends on which side of the fence
you sit on. Each side would probably agree that giving/chasing
collateral warranties, particularly on a big project, can be difcult
and costly from an administrative point of view. However, a recent
decision of the Scottish courts has curtailed the scope to resist
production of a warranty once a commitment to produce the
warranty has been given.

The story begins


The story starts 10 years ago in 2006 when a council appointed
a contractor to build a swimming pool and leisure complex. The
contractor undertook to produce a collateral warranty in favour of
the council from all the design consultants and subcontractors it
employed on the project.
The contractor appointed a consultant to provide the services
of architect, civil engineer and structural engineer. In that
appointment, the consultant undertook to provide a signed
collateral warranty in favour of the council within 14 days of a
formal request from the contractor. A style warranty was annexed
to the appointment. It mirrored the style in the main contract. It
contained a net contribution clause which apportioned liability
among the relevant parties in the event of a claim by the council.
No names were listed in the style warranty. Instead a footnote 10
said insert full designation of consultants/building contractor who
are sharing in the net contribution clause.
The leisure centre was duly built. Some years later, court
proceedings were started by the council against the contractor in
respect of alleged defects in the centre. The contractor formally
joined the consultant to the action as a third party. In order
to widen the scope of its argument against the consultant, the
contractor sought to rely on the collateral warranty that the

The Scottish courts sink consultant had undertaken, but failed, to produce.

a consultants armada 2015: The contractor asks for the collateral warranty
In 2015 the contractor sent a collateral warranty to the consultant
of arguments about and asked them to sign and return it. The style warrantys blank

why it should not deliver


spaces in the net contribution clause and in the professional
insurance clause had been lled in.
outstanding collateral 2015: The consultant agrees, but then changes tack and refuses
warranties The consultant was initially reluctant to sign the collateral warranty
but its solicitor eventually agreed to deliver it on payment of
certain outstanding fees (known as the 2015 bargain). The
contractors solicitors sent a cheque in payment of the fees and
asked for delivery of the collateral warranty. The consultant then
changed tack, presumably appreciating that signing the collateral
warranty would create a contractual link which would increase
its exposure in respect of the alleged defects claim raised by
the council. The consultant refused to deliver it. The contractor
asked the court to grant an order for what is known in Scotland
2016 Collateral Warranties 43

The terms of the collateral warranty to be signed must


be clear.
There are subtle differences between the law of specic
implement in Scotland and the law of specic performance
in England.
There are restrictions on the granting of such court orders.
A consultant will not be ordered to produce the collateral
warranty if it cannot actually do so. The simple, if somewhat
dramatic, reason for this is that in Scotland the remedy for
The simple, if somewhat dramatic, reason is that failure to comply with an order for specic implement is
in Scotland the remedy for failure to comply with imprisonment.
Most disputes tend to turn on their own facts. In this case
an order for specic implement is imprisonment. the judge was of the view that the obligation to provide the
warranty was a standalone requirement. This may not
always be the situation. Obligations to pay fees may be
as specic implement, ie. an order compelling a party to do a regarded as counterpart obligations whereas obligations
specic act. in relation to physical performance, for example timely
instructions, may not.
An armada of arguments is launched... and sunk
The consultant defended the court proceedings with what the To conclude, while resorting to court proceedings to get an
judge described as an armada of arguments including: outstanding collateral warranty might seem like a using sledge
hammer to crack a nut, it could be a useful option. However,
The parties had not actually concluded a separate 2015 perhaps the true value of this court judgment lies in reminding
bargain to deliver the collateral warranty on payment of their us of the enduring, and potentially very serious, consequences
outstanding fees. for a consultant in agreeing to produce collateral warranties in the
>Judge: No. The exchange of emails between the parties rst place.
solicitors had created a separate binding agreement. It was
technically therefore unnecessary for the judge to address the Fenella Mason, Head of Construction and Projects, Burness Paull
remaining arguments (fortunately for the readers, he did...) Fenella.Mason@burnesspaull.com
www.burnesspaull.com
The consultant had no obligation to sign until the blank terms
in the style warranty had been agreed further negotiations Judgment: Kier Construction Ltd v WM Saunders Partnership LLP (2016) CSOH 17
would have been required.
>Judge: No. The appointment set out a simple procedure
for completion of the style collateral warranty. The net
contribution clause and insurance blanks could be completed
by the contractors solicitors. The judge said: The parties
had to complete the blank in the NCC to reect the roster
of consultants and subcontractors that [the contractor]
assembled. Necessarily that could only be done after the date
of the appointment. The blank in the insurance clause was to
be completed by inserting the gure agreed by the parties in
respect of the professional indemnity cover to be maintained
by the consultant. The use of the word shall in the
appointment had made it clear that the consultant was under
an obligation to provide the collateral warranty.

The contractor was allegedly in breach of the appointment


itself (by failing, for example, to provide reasonable
instructions) and therefore the consultant did not need to
perform its side of the bargain.
>Judge: No. The obligation to provide a warranty is a stand
alone requirement.

2016: Result, signed collateral warranty produced by consultant


Various options may be available in the event of a failure to
produce a collateral warranty. The appointment may specically
address the consequences of any such failure by imposing
nancial sanctions. Another option might be to claim damages for
breach of contract. However, sometimes what is required is the
actual document itself. This judgment reminds us that there may
be a third option; asking the court to ordain/order a consultant
to produce the collateral warranty. Although it should be
remembered that this may not be as easy as it sounds:

There has to be a very clear undertaking in the appointment


(or by virtue of a subsequent document or agreement) to
produce a collateral warranty.
44 Bonds Construction Law Review

Being demanding
Recent cases on performance bond calls

Stephanie Barwise QC and Omar Eljadi, Barrister, Atkin Chambers

P ERFORMANCE bonds occupy a vital role in modern


infrastructure projects. They are a form of indemnity
protecting employers and contractors against the
potentially serious nancial consequences of a counter-partys
breach of contract (or other event) by providing a quickly
realisable monetary security from a solvent third party, usually
a bank or other reputable nancial institution (the issuer). The
conditions that must be satised in order to effect a valid claim
under a performance bond (termed a call or demand) can vary
substantially, but are rarely more closely construed than in the
most stringent variety of performance bond, namely the on-
demand bond.
Under the terms of an on-demand bond, the issuers obligation
to pay is triggered solely by the presentation of a written demand
which complies with the agreed requirements of substance and
form. In determining whether to pay, the issuers sole concern is
whether the demand conforms, on its face, to those requirements.
If a conforming demand is made, then, save in the case of
established or obvious fraud, immediate payment is required; no
investigation into the veracity of what is stated in the documents,
or underlying the state of affairs between the contracting parties, is
necessary or justied.

Demand requirements: Some background


The relative ease with which an issuers obligation to pay
substantial sums can be triggered, coupled with the dependence
the issuer places upon statements in documents rather than any
proof of facts, is sometimes said to justify the application by
analogy of the doctrine of strict compliance; a principle developed
in the context of letters of credit, under which documents
presented as part of a call are required to conform very strictly to
the agreed requirements if the issuers obligation is to be triggered.
Under that doctrine, there is no room for documents which are

Where are we now when it almost the same, or will do just as well.
In IE Contractors v Lloyds Bank (1990) 2 Lloyds Rep 496, the
comes to making demands Court of Appeal expressed the view that there was less need
for that doctrine in the case of performance bonds because they
on bonds? were used less frequently, and attracted attention at a higher
level in banks, than letters of credit (which formed part of the
ordinary day-to-day mechanism of trade). That distinction
between letters of credit and performance bonds has not met
with universal approval.1 Indeed, 26 years on, it may not have
quite the same force.
Nevertheless, the position2 is that: The degree of compliance
required by a performance bond may be strict, or not so strict. It
is a question of construction of the bond. 3 This ostensibly more
exible stance should not give too much comfort to beneciaries.
Any cursory examination of the decisions on this subject reveals
the need to ensure that the terms of the bond governing notice
1
Sea-Cargo Skips v State Bank of India (2013) EWHC 177 (Comm) at [27]
2
Established in IE Contractors at p.501
3
See also Sea-Cargo Skips at [29] - [30]
2016 Bonds 45

are scrutinised extremely carefully, and to determine whether the delay alleged Although nothing new, the prospect of
that demands are drafted with the utmost was of the type referred to in article IV1(E), invoking requirements not explicitly stated
caution. The slightest non-conformity may and therefore whether its obligation to pay in the bond, coupled with the apparently
justify a refusal to pay. was triggered. fairly strict approach to requiring
In Frans Maas v Habib Bank (2001) Determining the stipulations which compliance, seems recently to have proven
Lloyds Rep. Bank. 14, the bond required the must be included in a demand is a matter grist to the mill of issuers. Two instances of
party making a claim thereunder to state of interpretation. The requirements are rejected calls have been reported already
that its counter-party in the underlying often stated clearly and expressly, causing this year. The decisions illustrate well the
contract had failed to pay you under little difculty for the prudent beneciary. courts present approach to interpretation
their contractual obligation. The demand Occasionally, however, the precise in this context, and explore the limits of
stated we claim the sum of 500,000, statements to be contained in a demand issuers ability to rely on alleged non-
[the other party] having failed to meet their are less obvious. On its true construction conformities within the demand in an effort
contractual obligation to us. The bank a bond may require a particular statement to resist payment.
or assertion to be made in a demand, even
refused to pay and the court held that its
though that requirement is not expressly
refusal was justied. The key statement Lukoil v Barclays Bank
stipulated, on the basis that the statement
was a failure to pay. A failure to meet Often a failed call will be no grave matter.
was necessary to enable the bank to
obligations did not necessarily equate to The beneciary will usually be able to
determine on the face of the document
a failure to pay. It was ambiguous and the make a revised demand that complies with
whether its obligation is engaged.
bank was not obliged to accept it. the bonds requirements. That was not so
In Esal (Commodities) Ltd v Oriental
In Sea-Cargo Skips, a bond procured in Credit (1985) 2 Lloyds Rep. 546, for example, in Lukoil Mid-East Ltd v Barclays Bank plc
relation to a shipbuilding contract required the Court of Appeal decided that an (2016) EWHC 166 (TCC), (2016) BLR 162, where,
a demand thereunder to state: undertaking to pay on your written by the time Lukoil received Barclays +
demand in the event that the supplier letter rejecting its US$7m demand, the
That the vessel or the construction fails to execute the contract in perfect bond had expired, preventing a further call.
thereof is delayed with more than 270 performance required the demand to state Whether Barclays was right to reject the
days as set out in the contract article that it was made because the supplier had call therefore bore enormous importance.
IV1(E) which entitles the buyer to cancel failed to execute the contract. Similarly, The bond served as security for
the contract and to receive repayment of in IE Contractors, an undertaking to pay the contractors performance of oil
the advance payments. you the said amount on demand, being drilling works that Lukoil had engaged
your claim in damages brought about by it to execute in southeast Iraq. Barclays
The buyers demand under the bond the above named principal required the contended that Lukoils demand was
failed to refer to the relevant article of the demand to state that it was a claim for defective because it failed to state that
contract, such that the bank was not able damages brought about by the principal. no amendment had been made to the

An impressive array
of silks and juniors
Legal 500

Construction, Engineering and Infrastructure


Energy, Natural Resources and Utilities
Information Technology and Telecommunications
Professional Negligence
Shipbuilding, Repair and Conversion

t: +44 (0)20 7404 0102


www.atkinchambers.com
46 Bonds Construction Law Review

underlying drilling contract which impacted specic sum because once Coface knew
upon the timely performance of those the councils costs, the sum to be paid was
works. It relied on the following words determined by a relatively straightforward
from the fourth paragraph of the bond: process of calculation, applying the
schedule and index linking provisions in
[Barclays] shall be responsible for the the bond. Coface was able to carry this out
payment of the total above mentioned just as easily as the council.
amount in full at [Lukoils] rst written Cofaces second argument fared no
request submitted to [Barclays] before better. The bond required notice in
the expiry date if [Barclayss client] fails following cessation of mining at an writing of any breach. The councils
to full the contract provisions, on the opencast coal mine near Douglas. The demand had stated that the contractor was
condition that no amendment has been amount recoverable from Coface varied in breach of its obligation to carry out
made to the contract concluded between over time in accordance with a schedule to the restoration works. Coface argued that
[Lukoil] and [Barclayss client] impacting the bond and certain indexing provisions, greater specication of the precise breach
the timely performance of the works but was subject to a maximum liability of that had occurred was required. However,
under the contract. 4,499,411. in circumstances where the contractor had
Before completing the restoration entered insolvency and could not carry
Stuart-Smith J held that the demand was works, the contractor became insolvent. out the works, the court noted that it was
valid. He acknowledged that, in light It ceased work and was wound up. The impossible to specify the breach beyond
of IE Contractors and Esal, stipulations council made a call on the bond by a stating that the restoration works would not
as to the required content of a demand single notice, which stated both that the be carried out.
might, on a proper interpretation of the contractor was insolvent and in breach of
bond, be implied rather than express, its requirement to carry out the restoration Where are we now?
but held that the principal justication works, and that the cost of completing Although requirements as to the content or
underpinning the interpretation of the the restoration works was some 9m. Not form of a demand may be expressly
bonds in those cases was that the bank long after the councils call, the amount framed as such, further requirements may
needed to know, based on the contents of recoverable under the bond decreased not be explicit, and only apparent from a
the demand alone, whether its obligation substantially. Accordingly, as in Lukoil, the careful interpretation of the words of the
to pay was triggered.4 That justication did validity or otherwise of the councils call bond. This is most frequently so where a
not avail Barclays. The statement alleged was important. certain fact (usually a breach by the issuers
to be necessary could have no bearing Coface rejected the councils call, client) is framed as a prerequisite to the
on the obligation to pay because the arguing that the bond required a two- issuers obligation to pay.9 It also occurs
fth paragraph of the bond very clearly stage notice procedure to be followed; where the nature of the sums to which
acknowledged that no amendments or a written notice of breach and the cost the beneciary of the bond is entitled is
addenda to the underlying contract would of the restoration works, followed by a described in the bond.10
relieve Barclays of its obligations and that separate demand for payment of a specic Parties making calls under bonds which
Barclays waived the right to be notied sum. It also contended, as a secondary describe or condition the issuers liability
of the same. Although that provision ground, that the council had failed to state to pay, should be astute to make clear
conicted with the closing words of the the contractors breach with adequate in their demand that those conditions
fourth paragraph, Barclays accepted specicity. Neither ground for rejection or descriptions are met. Moreover, it is
(correctly, the judge said) that the bond found favour at rst instance, or on appeal a counsel of prudence that the demand
was not invalidated by amendment.5 to the Court of Session, which held that should provide a reasonable level of
This acceptance effectively brought only one notice was required and that detail on those matters such that there
an end to the matter. Barclays was the breach was sufciently stated. The can be no challenge to the demand on
unable to point to any justication for councils demand was valid; Coface was this front either. The objective is always to
the statement which satised the judge. obliged to pay. The existence of a two make it clear to the issuer on the face of
Barclays suggestion that it had an interest stage procedure was not expressly stated the demand that its obligation to pay has
in knowing of any amendment, because it in the bond. Cofaces contention was been triggered.
increased the risk of a call, was dismissed instead based on a detailed and, it must These recent cases make clear, however,
be said, fairly strained interpretation of that there is a limit to the scope for
as ignoring contractual realities.6 The judge
the language used in the bond, predicated interpreting the bond as imposing demand
also found that it was commercially absurd
upon minor differences in expression. requirements that are not expressly stated.
to expect Lukoil to be able to make the
The court disagreed with this approach. Where the content of the statements
required statement. Given the size of the
It stated that the provisions of the bond allegedly required can have no bearing on
project, extensive changes were inevitable.7
had to be construed in a practical manner, the issuers obligation to pay, and serve
in accordance with commercial common no real commercial purpose (other than
South Lanarkshire Council v Coface
sense and having regard to the essential posing a further technical hurdle to the
A similarly purposive approach to
purpose of a performance bond. An unduly issuers liability), issuers are likely to face
interpretation was applied by the Scottish
technical construction was to be avoided.8 an uphill struggle in persuading the courts
Court of Session (Inner House) in South
Paramount in the courts reasoning of the merits of that interpretation.
Lanarkshire Council v Coface SA (2016)
was that the second notice in the alleged
CSIH 15, [2016] BLR 237, where the council
two-stage notice procedure (one making Stephanie Barwise QC and
was the beneciary of a bond issued
a demand for a specic sum) served no Omar Eljadi, Barrister, Atkin Chambers
by Coface to secure the contractors
commercial purpose. That the council was sbarwise@atkinchambers.com
completion of certain restoration works
demanding payment would be clear from oeljadi@atkinchambers.com
4
See [19] the rst notice they served. There was no http://www.atkinchambers.com
5
See [26] need for a second notice demanding a
6 9
See [28] See Esal
7 8 10
See [30] See [22] See IE Contractors
2016 FIDIC 47

FIDIC Red Book, sub-clause 2.4 revisited


Simon F Fegen MRICS FAArb, Director, Leach Consultancy

S HORTLY after the publication of the article FIDIC Red


Book sub-clause 2.4: A useful tool or a paper sword?
in the 2015 Construction Law Review, the Privy Council
gave judgment on a matter in respect of a dispute that involved
a contractors request under sub-clause 2.4 (employers nancial
arrangements). The judgment may throw some light on questions
raised in that article.
The matter before the Privy Council was NH International
(Caribbean) Limited v National Insurance Property Development
Company Limited (Trinidad & Tobago), and NH International
(Caribbean) Limited v National Insurance Property Development
Company Limited (no. 2) (Trinidad & Tobago) (2015) UKPC 37. NH
International (NHIC), the contractor, entered into a contract to
construct the new Scarborough Hospital in Tobago for the Ministry
of Health, on behalf of National Insurance Property Development
Company (NIPDEC), the employer. The contract was the
International Federation of Consulting Engineers (FIDIC) general
conditions of contract, rst edition 1999 (Red Book).
During the course of the works, various disputes arose between
the parties which were referred to arbitration. Challenges arose
thereafter to some of the arbitrators decisions in the award, and
these issues eventually found their way to the Court of Appeal,
and ultimately to the Privy Council.
The 2015 article explored as to what might be considered
reasonable evidence as provided for under sub-clause 2.4, and
whether or not sufcient clarity could be made of such a term
so that a contractor might have condence when exercising its
entitlement under the contract.
It is not so much what the Privy Council judgment directs,
but the record therein of the arbitrators award that is of interest.
Rarely does a dispute arising under a FIDIC contract reach the
light of day the majority are satisfactorily resolved by dispute
boards. Alternatively, for those that do seep through to arbitration,
the details are protected by condentiality.
Has another year brought The Privy Council sought not amend those aspects of the
arbitrators award that were deemed to be conclusions of fact
any more clarity on rather than of law, asserting that the parties had chosen their

sub-clause 2.4?
arbitrator and it was not open to the courts to interfere.
So, although the devil is as always in the detail, the arbitrators
award might offer a clearer view of what may be acceptable as
reasonable evidence under sub-clause 2.4.

The facts
Chronologically, the brief facts of the case are:

On 3 September 2004, NHIC issued a request to NIPDEC


under sub-clause 2.4 for reasonable evidence of the
employers nancial arrangements.
On 29 December 2004, NIPDEC responded, enclosing a letter
from the Ministry of Health which advised that (government)
cabinet had approved additional funding for the project.
On 28 April 2005, NHIC made another request under sub-
clause 2.4.
48 FIDIC Construction Law Review

On 23 June 2005, NHIC gave notice to reduce the rate of work.


On 5 July 2005, the Ministry of Health wrote to NHIC stating without prejudice that
funds were available.
On 8 July 2005, NHIC wrote express concern at the use of the phrase without
prejudice in the ministrys letter and sought conrmation from NIPDEC that cabinet
had approved the sums due under the contract. NHIC did not receive a response
from NIPDEC to this last request.
On 23 September 2005, NHIC gave notice to suspend work.
On 19 October 2006 (a year later), NHIC received a letter from the Ministry of Health,
dated 6 October 2006, conrming that funds were available for the project.
On 27 October 2006, NHIC requested from NIPDEC conrmation that the funding
had cabinet approval. No response was received from NIPDEC.
On 3 November 2006, NHIC gave notice to terminate the contract.

Sub-clause 2.4 provides:

The employer shall submit, within 28 days after receiving any request from the
contractor, reasonable evidence that nancial arrangements have been made and
are being maintained which will enable the employer to pay the contract price (as
estimated at that time) in accordance with clause 14 (contract price and payment). If
the employer intends to make any material change to his nancial arrangements, the
employer shall give notice to the contractor with detailed particulars.

The contract does not dene reasonable evidence. The arbitrator considered that the
letters sent on behalf of NIPDEC, in reply to NHICs requests for reasonable evidence,
were insufcient to satisfy the requirements of sub-clause 2.4; this was founded on there
being no evidence of cabinet approval for the funding.
On 3 September 2004, NHIC issued a request for reasonable evidence of the
employers nancial arrangements under sub-clause 2.4. NIPDECs response, on
29 December 2004, referred to there being cabinet approval for the additional funding.
On 28 April 2005, NHIC made its second request for reasonable evidence of the
employers nancial arrangements. On 23 June 2005, having not received a response,
NHIC gave notice under sub-clause 16.1 to reduce the rate of work.

QUANTITY SURVEYORS SERVING CONSTRUCTION


IN THE UK AND WORLDWIDE

Services include Quanty Surveying, Esmaons, Commercial Management, PFI/PPP, Dispute


Avoidance and Dispute Management and Resoluon, Adjudicaon and Arbitraon, Planning and
Programming, Expert Witness and Mediaon

Head oce: Unit 10, Forest Gate, Pewsham,


Chippenham, Wiltshire SN15 3RS UK
Also at: London, Birmingham and York

Tel: +44 (0)1249 443118 Email: info@leachgroup.com Website: www.leachgroup.com


2016 FIDIC 49

The permanent secretary at the Ministry of Health wrote on


5 July 2005 that the ministry advise without prejudice that
funds are available in [this] sum to meet the estimated nal cost
to completion. Three days later, NHIC requested from NIPDEC
conrmation that cabinet approval had been given for the funding.
On 23 September 2005, having not received a response, NHIC
gave notice under sub-clause 16.1 to suspend work. Rarely does a dispute arising under a FIDIC
On 19 October 2006, NHIC received a letter from the contract reach the light of day the majority
permanent secretary at the Ministry of Heath, dated 6 October
2006, conrming that the government considered that the are satisfactorily resolved by dispute boards...
completion of the hospital project was of the highest priority and
that moneys certied or found due to NHIC... will be paid by the
for those that do seep through to arbitration, the
government, and further the government stands fully behind the details are protected by condentiality.
project... and will meet the contractual nancial requirements for
completion of the project.
On 27 October 2006, NHIC responded to NIPDEC seeking together with NIPDECs failure to respond
conrmation that the cabinet had approved the funding. There to NHICs letter of 8 July 2005 in which it
was no response and on 3 November 2006 NHIC gave notice of expressed concern at the use of the words
termination under sub-clause 16.2. Sub-clause 16.2 (termination by without prejudice.
contractor) provides, inter alia:
Further, the arbitrators award supported
NHICs entitlement to terminate the
The contractor shall be entitled to terminate the contract if: (a)
contract, under sub-clause 16.2, on
the contractor does not receive the reasonable evidence within
3 November 2006, for similar reasons to
42 days after giving notice under sub-clause 16.1 (contractors
the above. Notwithstanding that, evidence
entitlement to suspend work) in respect of a failure to comply
in arbitration showed that as at 3 October
sub-clause 2.4 (employers nancial arrangement).
2006 the cabinet gave its approval for the
required funding; however, this information
The validity of the termination was the subject of dispute between
had not been transmitted to NHIC.
the parties and was referred, as required under the contract, to
Although the ministry had expressed,
arbitration. The parties accepted that this matter in arbitration
in the letter dated 6 October 2006, its
turned on whether or not NIPDEC had responded to NHICs
conrmation that the project was of the
request with reasonable evidence, as obliged under sub-clause 2.4.
highest priority, that the government
stands fully behind the project and that
The decisions
the government will meet the contractual
The arbitrator gave two reasons in support of his decision to
uphold the contractors entitlement to terminate the contract nancial requirements for completion of
on 3 November 2006. The arbitrators primary reason was that the project, the letter failed to mention
reasonable evidence was not given by NIPDEC. The other reason anything regarding whether cabinet
relates to whether the sums referred to in the responses were approval was being sought or had been
adequate under sub-clause 2.4; this aspect is not dealt with here sanctioned.
merely due to shortage of editorial space another time perhaps? This may give some assistance as to
The Privy Council judgment does not make any mention of the what response should satisfy a contractors
fact that on two occasions the Ministry of Health responded to request under sub-clause 2.4, bearing
NHIC, instead of NIPDEC as required under the contract. in mind that what one arbitrator may
The arbitrator decided that NIPDECs letter of 29 December consider is reasonable evidence, another
2004, and the Ministry of Healths of 5 July 2005 and 6 October may not. Perhaps it may also give a clearer
2006, did not amount to such reasonable evidence that nancial idea of what might not be considered as
arrangements have been made and are being maintained which reasonable evidence.
will enable the employer to pay the contract price as required The difculty will always remain to
under sub-clause 2.4. evaluate reasonable evidence, and to
The arbitrator referred to evidence given by the permanent consider whether or not it is sufcient to
secretary, who explained that she had sought cabinet approval uphold the requirements of sub-clause 2.4,
on receipt of NHICs letter of 27 October 2006, as demonstrating or if it will give the contractual grounds
that cabinet approval was necessary for the payment of funds. to proceed under sub-clause 16.1 to
Further evidence was that the need for cabinet approval prior to reduce the rate of work and/or to suspend
expenditure on construction contracts was rarely, if ever, work, or under sub-clause 16.2 to terminate
departed from. the work.
Referring to sub-clause 2.4, the arbitrator concluded that As always, each case will have to be
providing reasonable evidence that nancial arrangements have judged on its own merits, but hopefully
been made by the employer requires more than just showing what is reasonable evidence is a little
that the employer was able to pay, and that more positive steps clearer. One thing that is clear is that
were required; i.e. NIPDEC had to produce evidence that professional advice should be sought
cabinet approval for payment of sums due under the contract had before acting under clause 16.
been obtained.
The arbitrators award supported NHICs entitlement to suspend Simon F Fegen MRICS FAArb, Director,
the work under sub-clause 16.1 on 23 September 2005 on the Leach Consultancy
basis of the words without prejudice and the absence of any s.fegen@leachgroup.com
conrmation of cabinet approval in the letter of 5 July 2005, www.leachgroup.com
50 Letters of Intent Construction Law Review

Could the payment provisions of the


construction act displace capped payment
sums set out in letters of intent?
Edwina Acland, Solicitor, Sharpe Pritchard

T HERE has been much written about (and cautioned against) the use of letters
of intent over the years. It is perhaps a testament to the attention letters of intent
have been given that the courts have seen very few cases recently where the
parties are governed, or said to be governed, by them.
It is not my intention to repeat what are perhaps now trite warnings over the use of
letters of intent in place of entering into formal contractual arrangements although,
there is no harm in repeating it, if just once. There is, however, one aspect in respect of
them which has had less practitioner attention than perhaps it ought; the impact of the
payment provisions of the amended construction act on the payment arrangements under
letters of intent.

Edwina Acland on an
Given the recent prolicacy of payment-
related construction cases reaching the
aspect of letters of intent courts, it may be only a matter of time
before the applicability or otherwise of the
that isnt widely debated payment provisions of the act, intertwined
with the complications of letters of intent,
comes before the courts.1 It is not my intention to repeat
It is not uncommon for letters of intent
to include a cap on the amount payable what are perhaps now trite
to the contractor for the duration of time
the letter is intended to cover. This should warnings over the use of letters
be relatively straightforward, particularly of intent in place of entering into
where there is an agreed schedule of
rates or priced activities list, along with a formal contractual arrangements
clear scope of works and programme for
the contractor to adhere to. In an ideal
although, there is no harm in
world (where the use of letters of intent repeating it, if just once.
is unavoidable), the scope of works, time
period and cap are reasonably well aligned
and the fully executed contract is entered into before either party
has the opportunity to start raising concerns.
However, as is too often the case, the parties do not agree on
the terms of the nal contract and letters of intent continue to be
issued and re-issued, or worse elapse, leaving a void as to how
the relationship is governed. As time goes on, the likelihood of
disagreements increases. And the chances are they will relate in
some way or form to payment.
Assuming that the work authorised under a binding letter of
intent is for a period of at least 45 days, it seems to me that the
letter of intent could be construed as a construction contract for the
purpose of the act, entitling the contractor to periodic payments.
The implications of this could be quite signicant for both
parties. If and to the extent the payment terms of the letters of
intent do not comply with the amended act, then the relevant
provisions of the act (and scheme) would apply. As such, a
contractor under a lump sum/capped letter of intent could be
1
In Allen Wilson Shoptters v Mr Anthony Buckingham (2005) EWHC 1165, HHJ
Peter Coulson QC (as he was then) commented upon this issue, but this was before
the amendments made to the 1996 act by part 8 of the Local Democracy, Economic
Development and Construction Act 2009 and was an adjudication enforcement case
and so the judge declined to review the correctness or otherwise of the adjudicators
decision on the matter
2016 Letters of Intent 51

If the employer has not been administering the applications as


closely as the act requires, then the sum total of the periodic notied
sums may exceed the cap in the letters of intent.

entitled to periodic payments for the work undue comfort from any capped gure
done, even if the letter of intent did not in the letter and be alert to any interim/
anticipate this and the total payable periodic payment applications made by the
in respect of such payments would not contractor. Failure to respond timely and
necessarily equate to the cap. comprehensively with payment and/or pay
This not only places an administrative less notices runs the risk of the letters of
burden on the parties by needing to intent cap being dislodged by the sum total
be alert to the importance of preparing of the notied sums.
compliant and timely payment (and pay
less) notices at regular intervals, but it also Edwina Acland, Solicitor,
opens up the question as to how much the Sharpe Pritchard
contractor is entitled to. As it is unlikely the eacland@sharpepritchard.co.uk
parties would have agreed the amounts of www.sharpepritchard.co.uk
the periodic payments (as these were not @SharpePritchard
anticipated), such amounts are implied by
the provisions of the act and scheme. The
key phrase in the scheme in analysing this
is the contract price, as it is this which sets
the upper limit of the amount payable. It is
dened as:
KE^dZhd/KE/^Whd
The entire sum payable under the
construction contract in respect of
the work.

An employer may argue that this means the


agreed capped gure set out in the letter
of intent a position which, arguably, ,/E' Z/sE
accords with common sense. However, as &KZ :h/d/KE
the construction contract is subject to all of :h/d/KE EKd/
the payment provisions of the act (to the
extent that the letters of intent payment zKhE >>KhZZW/
terms are non-compliant), section 111(1) ^dZd'z Z^WKE^^Zs/
cannot be overlooked. This requires the
employer to pay the notied sum. In the $GMXGLFDWLRQ$GYLFHLVDVSHFLDOLVWVHUYLFHRIIHUHGE\6KDUSH3ULWFKDUGV
absence of any valid payment or pay less FRQVWUXFWLRQODZDQGGLVSXWHUHVROXWLRQWHDPV
notice from the employer, such sum is :KDWHYHU\RXUSRVLWLRQZHZLOOVXSSRUW\RXZLWK
the amount notied by the contractor (by
 GLVSXWHUHVROXWLRQVWUDWHJ\  SUHSDUDWLRQIRUDGMXGLFDWLRQ
means, usually, of payment applications).  OLDLVRQZLWKH[SHUWV  SUHSDUDWLRQRIUHVSRQVHV
If the employer has not been administering  DGYLFHRQSURFHGXUH  DSSHDOLQJDGHFLVLRQ
the applications as closely as the act  UDSLGUHVSRQVH  HQIRUFHPHQW
ADJUDIC
ATION
requires, then the sum total of the periodic
notied sums may exceed the cap in the
ZYh^dzKhZ&Z'h/
letters of intent. The contractor may have THE PRO
CESS
dKd,:h/d/KEWZK^^ A handy guide

some force in arguing that these become process for: to understanding the
referring a
responding
dispute to
to an adjud
adjudicatio
n
adjudicatio
n

ication notice

the entire sum payable by the employer. .

7RGLVFXVVKRZ6KDUSH3ULWFKDUG
The obvious way to avoid this risk is to FDQKHOSFRQWDFW
 


  



ensure that, if a letter of intent is absolutely -XVWLQ0HQGHOOH


necessary, its payment terms are compliant 7
(MPHQGHOOH#VKDUSHSULWFKDUGFRXN
with the amended act, and administered
ZZZDGMXGLFDWLRQDGYLFHFRXN
as such. Failing that, the employer (or
its contract administrator) must not take
52 Estoppel Construction Law Review

An (e)stopped clock is right twice a day


Is your engineers conduct a ticking time bomb?

Sarah McCann, Barrister, Hardwicke

A S the deluge of smash and


grab adjudications continues to
percolate through the construction
industry, shrewd contractors are advancing
argument was raised in front of Edwards-
Stuart J, and Waco relied on Jacobs failure
to insist upon the contractual valuation
date as a course of conduct that had led
more and more creative legal submissions it to believe that an application would be
as a way of reviving interim payment accepted, even if it had not been made
applications that have somewhere on the precise contractual valuation date,
gone awry. Twice in the past year, the from which it would be unconscionable to
Technology and Construction Court has permit LCC to resile.
been addressed on the issue of whether Edwards-Stuart J was persuaded that
a contractor can rely on an estoppel to there was sufcient evidence of a course
resuscitate an interim application; and of conduct that gave rise to an estoppel.
in one of those cases, that estoppel was However, the estoppel would only apply
created solely out of the actions of the to interim applications made after the
contract administrator. Although the TCC specied contractual valuation date, and
has yet to fully articulate all of those not before:
situations in which the actions of the
engineer or contract administrator are I nd that there was a course of
capable of giving rise to an estoppel, conduct by which Jacobs, on behalf
construction professionals would be wise of LCC, agreed to accept monthly
to exercise a degree of caution and be applications that were made up to
wary of inadvertently bestowing such rights three to four business days after the
upon the contractor, much to the detriment contractual valuation date. Jacobs was
of the employer. the agent authorised to administer the
contract and in my view LCC would
Leeds v Waco UK not have been permitted to reject, in,
In Leeds City Council v Waco UK Ltd (2015) say, January 2013, had it been minded
EWHC 1400 (TCC), Edwards-Stuart J had to to do so, an application made three to
determine whether a common failure to four business days after the contractual
adhere to the payment timetable outlined valuation date. That would be
in the contract was capable of giving rise inconsistent with the course of conduct
to an estoppel. Leeds City Council (LCC) that was by then established. [43]
had engaged Waco UK to assemble and

The estoppel argument furnish a number of modular classroom


buildings at a primary school, and the
Jacobs conduct had created an estoppel
that, on different facts, would have entitled
in smash and grab contract specied the 26th of each month
as the required date for Waco to issue
Waco to payment. The point may be
crucial in other cases, but it is equally
adjudications interim applications. Over the course of the important to note the limits that Edwards-
project, the contract administrator (Jacobs) Stuart J identied in relation to Jacobs
had routinely certied amounts from authority to bind LCC to the estoppel. The
interim applications that were made three court had to look to the authority conferred
to four days after the contractual valuation upon Jacobs and determine whether it was
date; it was this conduct that Waco later acting within the ambit of that authority
alleged formed the basis of the estoppel. or whether it was exercising more broad
The critical payment application was powers and purporting to vary the terms of
issued by Waco on 22 September 2014. the contract. In the latter case, LCC would
Jacobs did not certify payment because the not be bound by the estoppel. However,
application had been made too early. Waco because the contract had specied that
referred the dispute to adjudication and the valuation dates would stand unless
quickly secured a smash and grab victory, otherwise agreed, in this case Jacobs was
which LCC thereafter sought to challenge merely exercising the contractual power
by way of part 8 proceedings. The estoppel vested in LCC as its agent.
2016 Estoppel 53

Grove v Balfour Beatty


The estoppel argument was ventilated more recently in Grove
Developments v Balfour Beatty Regional Construction Ltd (2016)
EWHC 168 (TCC), again by a contractor in relation to a successful
smash and grab adjudication that was challenged by way of
part 8 proceedings. Balfour Beatty (BB) had been engaged to
build a hotel and serviced apartments adjoining the O2 complex in
Greenwich and the contract had included an agreed schedule of
23 valuation and payment dates, but did not identify any valuation
dates thereafter. The project was delayed and ran past the nal
One might question why it would bar Balfour
date identied in the schedule. BB issued an interim application Beattys claim when the point was apparently
seeking further interim payment. The issue was whether BB had
any contractual right to further interim payments, either on the never raised in Leeds.
correct construction of the contract or by estoppel.
Stuart-Smith J ultimately found that there was no right for
BB to make further interim applications. The interesting point Where are we now?
to note about the decision is the basis on which Stuart-Smith J Although the estoppel argument continues to be aired in smash
rejected BBs estoppel argument. BB submitted that the parties and grab adjudications and payment disputes, the TCC has yet to
were operating on the mistaken assumption that BB was entitled fully tease out the limits of the doctrine as it will apply to building
to receive further interim payments, with GDLs issuing of contracts and, indeed, the authority of the engineer or contract
payment certicates operating as communications of that mistaken administrator to bind an employer to the estoppel. The authorities
assumption. That argument failed, in part, because: convey a number of salient points that bear remembering, and
will provide useful guidance to construction professionals until
It is a classic example of an attempt to set up an estoppel that is more substantive authorities emerge which identify the limits to
to be used as a sword rather than a shield. [40] the doctrine:

This is an important limit placed on any estoppel, but one There will be no estoppel without a sufcient number of
might question why it would bar BBs claim when the point occurrences to form a course of conduct.
was apparently never raised in Leeds. In both cases, hadnt the The engineer or contract administrator must have the
contractor sought to rely on the estoppel as the basis for its claim authority to alter the contractual valuation dates, or else the
for interim payment? However, although the estoppel might have estoppel will fail.
appeared to act as a sword in Leeds, the difference was that in The estoppel cannot be used to create any new rights beyond
Grove, BB was attempting to use the estoppel to create a right those conferred under the contract.
to obtain further interim payments, rather than just varying the
route through which an already existing contractual right could Sarah McCann, Barrister, Hardwicke
be exercised. Waco was therefore able to rely on the estoppel and sarah.mccann@hardwicke.co.uk
there was no question of it being used as a sword. www.hardwicke.co.uk @hardwickelaw

Excellent and very personable counsel


(Chambers UK)

Hardwicke is a leading barristers chambers for domestic and


international adjudication, arbitration and litigation claims in:
Construction and Engineering
Insurance
Professional Negligence
Property Damage
Hardwicke Building, New Square, Lincolns Inn, London WC2A 3SB
www.hardwicke.co.uk | +44 (0)20 7242 2523 | @HardwickeConstr
Competencies

Commercial management and


geospatial competencies
The ICES competencies are essential for membership and help demonstrate
you are a qualified civil engineering surveyor. See how you compare and
begin your pathway to professional membership.

TRAINING MENTORING COMPETENCIES APPRAISAL FEEDBACK

Contact: Education, Professional Development and Membership Department


Chartered Institution of Civil Engineering Surveyors
+44 (0)161 972 3100
applications@cices.org
www.cices.org/competencies
2016 Payment 55

Harding v Paice
Rhyming slang for hard cases do not make good law?

David Sears QC, Crown Ofce Chambers

T HERE has been a number of cases


recently concerning what have
become known, perhaps unfairly,
as smash and grab adjudications. So called
sum stated in the account. However, the
employers did not accept that any sum
was due to the contractor and therefore
determined not to pay. Instead, they
because the bad guy (otherwise known as commenced a fourth adjudication in which
the contractor) throws a brick (otherwise they sought a decision that the value of the
known as a payment application) through contract works was 340,032.60 or such
the window to see if the good guy other sum as the adjudicator may decide.
(otherwise known as the employer) will A decision in their favour would result in a
do anything about it (i.e. serve a pay less net payment to them from the contractor.
notice). The employer does nothing and The contractor sought an injunction
the contractor immediately sets off to its restraining the fourth adjudication on
fence (also known as the adjudicator) to the basis that the third adjudicator had
obtain a decision requiring the employer already determined the amount properly
to pay the full amount claimed solely due in respect of the account and that it
on the basis of the employers failure to was therefore not open to the employers
serve a pay less notice and without any to reopen the issue in fresh adjudication
assessment of the amount which might proceedings.
actually be due. Edwards-Stuart J refused to grant an
Harding v Paice (2014) EWHC 3824; 157 injunction. He said that what was due
ConLR 98 was one of three cases in which under clause 8.12.5 of the Joint Contracts
the question arose what (if anything) an Tribunal (JCT) contract was the amount
employer can do in such circumstances properly due in respect of the termination
to prevent a contractor from obtaining account and that the adjudicator had not
payment of the full amount claimed or, decided what was properly due. All the
perhaps more accurately, to obtain a adjudicator had decided was that, in the
decision as to the true amount payable. All absence of a valid pay less notice, the
three cases were decided at rst instance employer had to pay the amount stated in
by Mr Justice Edwards-Stuart between the account. Although the employers had
December 2014 and February 2015. to pay the amount awarded, there was no
reason why they could not commence a
([YZ[PUZ[HUJL fresh adjudication to determine the amount
Harding v Paice was the rst of the properly due.

Who decided what, three cases. The contractor, Mr Harding,


served a termination account following
The decision in that case is to be
compared and contrasted with the
when and what are the termination of his contract with the
employers, Mr Paice and Ms Springall.
decisions by the same judge in ISG v
Seevic (2015) BLR 233 and Galliford Try v
the implications? The account showed that the value of Estura (2015) BLR 321. The ISG case was
the works was 797,859 and that, after decided only days after Harding and the
taking into account previous payments, the Galliford Try case was decided only a
amount due and payable was 397,912. few weeks later. Both were cases where
The employers failed to serve a pay less the employer failed to serve a pay less
notice in time and the contractor started an notice in respect of an interim payment
adjudication (the third between the parties) application. Both were cases where the
seeking a declaration that the amount employer nevertheless disputed the amount
properly due was 397,912 (or such other claimed by the contractor and, to that end,
sum as the adjudicator might decide). either started or attempted to commence a
The adjudicator decided that if the second adjudication to determine the true
employers wished to pay less than the sum value of the works as at the date of the
stated in the termination account, they had relevant payment application.
to issue a pay less notice and, because In both cases, Edwards-Stuart J decided
they had not done so, they had to pay the that it was not open to the employer to
56 Payment Construction Law Review

The failure to serve a pay less notice should either have a deeming
effect in relation to all payment applications or in relation to none.

dispute the decision of the adjudicator in a subsequent adjudication because, or so he


held, by failing to serve a valid pay less notice, the employer was to be taken to be
agreeing the value stated in the application and, moreover, the adjudicator must be
taken to have decided the question of the value of the work carried out by the contractor for
the purposes of the interim application in question.
However, the judge stressed that the deemed agreement could not constitute any
agreement as to the value of the work at some later date. There was nothing to prevent
the employer challenging the value of the work on the next application, even if it
was contending for a sum which was lower than the amount stated in the previous
application. Of course, that may be all very well if the contract between the parties allows
for negative valuations but it offers little comfort to an employer whose contract does not.

The appeal
Both the contractor in Harding and the employer in ISG launched appeals, but the ISG
appeal settled before it was due to be heard. However, amongst the points raised by the
contractor in the Harding appeal1 was an argument that the fourth adjudicator did not
have jurisdiction to decide the dispute as to the proper value of the termination account
because the third adjudicator had already decided the amount properly due in respect of
the account. In making that argument, the contractor relied upon the decision in ISG,
contending that, by failing to serve a pay less notice, the employer must be deemed to
have agreed the value of the account and the adjudicator had to be taken to have decided
the value of the work carried out.
The contractor also argued in the alternative that, even if the third adjudicator had not
decided the amount properly due (i.e. because it had decided the dispute only on the
basis of the lack of a pay less notice), it had nevertheless been asked to decide that issue
and had made a decision in that adjudication, thereby engaging paragraph 9(2) of the
scheme which provides that:

An adjudicator must resign when the dispute is the same or substantially the same as
one which has previously been referred to adjudication, and a decision has been taken
in that adjudication.

In giving the leading judgment, Jackson LJ took the latter point rst. He held that the
word decision in paragraph 9(2) means decision in relation to that dispute and that
ultimately it is what the rst adjudicator actually decided which determines how much
or how little remains available for the second adjudicator. He said that Parliament could
not have intended that if a claimant refers 20 disputes to adjudication but the adjudicator
decided only one, future adjudications about the other 19 were to be prohibited. In the
present case, the third adjudicator had made no decision in relation to the value of the
account and the judge was therefore correct to interpret paragraph 9(2) in the way he did.
So far as the other ground of appeal was concerned, Jackson LJ disagreed with the
contractor that the fourth adjudicator did not have jurisdiction to decide the dispute
because it was the same, or substantially the same, as the dispute already decided by
the third adjudicator, namely the amount properly due in respect of the account. He said
that, on a proper analysis, the contractor had referred a dispute involving two alternative
issues to the third adjudicator, one relating to the failure to serve the pay less notice
(the contractual issue) and one relating to the amount properly due on the account (the
valuation issue). It was clear that the third adjudicator had only dealt with the former.
Jackson LJ said it was unnecessary to embark on an analysis of ISG. He therefore did
not think it necessary to consider what the judge had said about deemed agreement was
correct. The important point so far as he was concerned was that the passage in the ISG
1
(2015) EWCA Civ 1231; (2016) BLR 85; 163 ConLR 299
2016 Payment 57

judgment upon which the contractor relied not there is an opportunity for subsequent adjustment should
did not apply to nal accounts. make no difference. The failure to serve a pay less notice should
Jackson LJ therefore held that although either have a deeming effect in relation to all payment applications
the employers failure to serve a pay or in relation to none.
less notice meant that the employer had The Court of Appeal could (and probably should) have said
to pay the full amount shown on the that, whilst the judge was right to decide that, as a matter of
contractors account, it did not mean that contract, interim applications had to be paid in full in the absence
the employer was precluded from starting a of a pay less notice, he was wrong to say that an employer was
new adjudication in order to determine the to be deemed to have agreed the value of the interim valuation
correct value of the contractors account. put forward by the contractor. There was no need for any deemed
agreement, still less for the adjudicator to have been deemed to
Comment have decided the question of the proper value of the account.
It is regrettable that the Court of Appeal did However, as things stand, there must remain some uncertainty as
not take the opportunity to decide whether to whether what the judge said about that was right.
the judge was right in both ISG and Another aspect of the decision which may give rise to more
Galliford Try to say that an employer, by questions than it answers is the nding that this was one dispute
failing to serve a pay less notice, was to be with two alternative issues, only one of which was decided by the
deemed to have agreed the amount stated third adjudicator. Not only was that true of the dispute in Harding
by the contractor to be due. Instead, the but it was also true of the disputes in ISG and Galliford Try. Were
Court of Appeal seems to have accepted it not for their deemed agreement, the employers in both those
as the judge himself had tried to explain other cases would have wished to argue the same, namely that
in Galliford Try that a different regime the adjudicator had only decided the contractual issue and not the
should apply in relation to nal accounts. valuation issue.
In contrast with interim payments where an More generally, it seems likely that the decision will spawn any
adjustment for overpayment could always number of cases where the scope of a dispute and its constituent
be made on the next interim valuation, an issues will give rise to argument as to what has already been
employer would otherwise have no means decided and what therefore remains for subsequent adjudication.
of challenging and adjusting the amount Harding v Paice was a hard case. The result was almost certainly
subsequently. right but, for all the above reasons, it is doubtful whether it makes
There is no logical basis for the good law.
distinction. There is no reason why any
deeming effect should depend upon the David Sears QC, Crown Ofce Chambers
type of payment application. Whether or www.crownofcechambers.com sears@crownofcechambers.com

*VUZ[Y\J[PVU
,_WLY[PZL,
*VTTLYJPHS
=HS\LZ
Adjudication
Arbitration
Construction
Energy
Engineering
Infrastructure
Insurance
Professional Negligence
SPECIALIST BARRISTERS Property Damage

Contact: +44 (0)20 7797 8100


^^^JYV^UVMJLJOHTILYZJVT
58 Contracts Construction Law Review

The making of IChemEs new professional


services agreement
John Challenger CEng FIChemE FIMechE, Chair, Contracts Committee, Institution of Chemical Engineers

T HE Contracts Committee of the Institution of Chemical


Engineers (IChemE) has recognised that there are a
number of missing elements in its well-established suite
of contracts. In particular, there has been a longstanding need for
a professional services contract that can be used for consultancy,
design and certain types of management services.
The scope of professional services required by the process and
related industries can vary from relatively small and uncomplicated
activities to large-scale and complex projects. In order to cover this
range, we have decided to create two forms of contract; the rst to
be published is the short form of professional services agreement.
This will be followed by a full or long form of agreement for
larger scale professional services.
The need for a short form of contract was recognised many
years ago and up to 2004, IChemE included a consultancy
agreement in a short publication entitled Consultancy An
Engineers Guide to Getting Started by Henry Rowson and David
Wright. The form of contract included within the publication is no
longer capable of meeting the full range of applications currently
required, so we completely redrafted the short form of contract
within the IChemE suite.

Whats new?
Previous users of IChemE contracts will nd many aspects of this
new short form familiar. However, it varies from previous contracts
in that it is for the provision of services only and does not include
John Challenger on the within its scope the procurement of materials or the installation
or construction of plant. The obligations and liabilities of the
latest form from IChemE parties are thus quite different. Nevertheless, the general sequence
of clauses and schedules and their titles follow the previously
published forms of contract.
This short form is suitable for pure consultancy services, such
as feasibility and concept studies, the development of business
cases or research and development activities, which are likely to
have a relatively low contract price and are generally of a short
duration. It is equally suitable for other industries and types of
work unconnected with the process sector, where professional
services for concept/feasibility studies, business or product
development, or cost estimating and management are required.
This short form has not been developed to act as an
employment contract for agency staff, secondments or sole traders
working essentially as employees of the purchasing company. It
contains a typical form of agreement, a set of general conditions of
contract and recommended schedules.
Guidance is provided on how to compile the agreement
and the schedules to which reference is made in the general
conditions. The guide notes have been included that will aid
interpretation of some of the general conditions and to explain the
need for certain special conditions. As with all previous IChemE
published forms, users are strongly encouraged to read the
relevant guide notes before completing the agreement, preparing
any special conditions (if required) and completing the schedules
IChemE Forms of Contract
For over 45 years IChemE have partnered with experienced
industry professionals to publish their acclaimed UK and
international Forms of Contract.

The Red Book Lump Sum Contract


The Green Book Reimbursable Contract
The Burgundy Book Target Cost Contract
The Yellow Book Subcontract
The Brown Book Subcontract for Civil Engineering Works
The Orange Book Minor Works
The Silver Book Professional Services Agreement

The contracts are available to purchase in hard copy, printable PDF,


view only PDF and editable word document formats.
For more information or to make a purchase please contact our sales team on:
+44 (0)1788 534470 or sales@icheme.org
www.icheme.org/foc
60 Contracts Construction Law Review

We took the view that disputes are likely to be a rare occurrence


under the short form. As a result, the approach to dispute resolution
has been deliberately simplied.

(some of which are optional), all of which to refer the dispute to the relevant court.
will have to be written individually. Clearly in some locations this may not be
a cost effective approach and therefore the
Location parties are encouraged to include a special
Since 2007, IChemE has published contracts condition that will dene the preferred
specically for use either in the UK or method of dispute resolution.
for international application; however,
this short form is structured so that it General conditions
may be used in any location. As with the The general conditions in particular have
previously published international forms been formulated to reect best practice
of contract, the short form will require the and relationships within the process plant
general conditions to be supplemented by sector, which is generally recognised as
the drafting of special conditions to deal being far less adversarial than other parts
with those matters arising out of specic of the construction industry. IChemE has
governing law/jurisdiction and/or location always adopted the basic philosophy that
of any intended project. the parties should co-operate to achieve
The general conditions have been the mutual objective of a successful project.
drafted on the basis that the contract is It is in the best interests of the parties to
in compliance with the laws of England. deal fairly with each other and with their
In view of the wide variations in law sub-consultants, specialists and advisors
and practices in different countries, in an atmosphere of co-operation in order
advice should always be sought as to the to achieve successful solutions to the
appropriateness of any terms, or the need problems that will inevitably arise during
for additional matters, having regard to the course of any project.
the law of the contract and the law of the Given the relatively low cost and limited
country where the services are performed liabilities associated with the application
or the project is situated. of the short form, it is anticipated that the
contract can be used without change to the
Dispute resolution general conditions. As with all contracts
We took the view that disputes are likely published by IChemE, the institution
to be a rare occurrence under the short advises against modications to the general
form. As a result, the approach to dispute conditions in order to avoid introducing
resolution has been deliberately simplied provisions that may conict with these
and does not include clauses in the general well-established practices and relationships.
conditions for arbitration, adjudication or Users should particularly be aware of the
expert determination. risk of introducing inconsistencies within
The primary approach to resolving the contract conditions, or provisions that
disputes is to escalate the matter to more may be unenforceable. The consultants
senior management of the contracted liabilities are also considerably different to
parties rather than to an external body. those of a contractor and the short form
If this fails then the default approach is reects this by deliberately limiting the

The process plant sector is generally recognised as being far less


adversarial than other parts of the construction industry.
2016 Contracts 61

containing the purchasers information and requirements. The


better the denition in the tender invitation, the shorter will be the
time needed for clarication and evaluation of the tenders.

Agreement
It is strongly recommended that the agreement be used in the
form provided. The agreement denes those documents which
comprise the contract. This will include incorporating into the
special conditions or the schedules all those documents in the
The consultants liabilities are considerably consultants tender which have been agreed by the parties to form
part of the contract.
different to those of a contractor and the short When there have been changes in concept during pre-contract
form reects this. negotiations, any relevant special conditions or schedules should
be amended before the agreement is signed. The contract can be
modied by agreement between the parties at any time after it
nancial obligations of the consultant in has been signed, but it is important that any modication should
the event that it fails to satisfactorily carry be expressed in unambiguous terms in a document signed by
out the services. both parties.
The short form is available in digital format, which is
Pricing and payment consistent with forms of consultancy contract available from other
As the range and variety of professional institutions. A printed version will be made available as part of the
or consultancy services covered by this long form of professional services contract when it is published in
contract could differ widely, then the the near future.
payment mechanisms to be applied may
be equally wide. If, for example, the John Challenger CEng FIChemE FIMechE, Chair, Contracts Committee,
services are for a dened project with a Institution of Chemical Engineers
predetermined timescale, the contract price john.challenger@wh-partnership.com
is likely to be based on a xed lump sum. www.icheme.org/foc @icheme
Conversely, pure consultancy services, for
which the outcome is unknown and the
terms of reference and timescales are not
capable of being fully dened, are likely
to be undertaken on a reimbursable rates
basis. The parties must carefully select and
agree the pricing mechanisms adopted if
disputes are to be avoided.
No purchaser will wish to commit
to an unlimited expenditure so it is
imperative, even where it is not possible Claims Advice
to fully dene the scope of work initially, Dispute Resolution Consultancy Services
that some means of nancial and/or
time control should be applied to avoid Adeooersacomprehensive,independent
misunderstandings emerging in the latter contractual and commercial service designed
toguideclientsthroughthecomplexitiesof
stages of the services. Based on this
construction and engineering projects
approach to pricing and payment, the from inception to completion.
contract price is not to be stated in the
agreement at the time of making the
contract, but rather is dened as the total
amount payable to the consultant.

Competence
As with all other IChemE forms of contract,
it is emphasised that the purchaser should
satisfy itself of the qualication and
competence of any potential consultants
or other service providers under
consideration. In this regard it is also wise
to seek references from clients for which Commercial and Contractual Negotiation Claims Appraisal,
the consultant has undertaken relevant Preparation and Defence ADR Contract Advice and Problem
services in the recent past. Solving Delay and Disruption Analysis Claims Negotiation and
Settlement Preparation of Documentation for Adjudication,
The purchaser should also devote
Mediation and Arbitration Negotiation and Settlement of Final
sufcient time to compiling information Accounts Expert Determination Claims Avoidance
that will help to minimise variations in
the consultants tenders. In this regard,
the tender invitation should incorporate ContactHeadOceon01403821770
a draft contract document including, enquiries@adeo.uk.com www.adeo.uk.com
as a minimum, drafts of the schedules
Accredited Courses

Accreditation of degrees and diplomas by ICES is a mark of assurance that


the programmes meet the standards set by industry; producing graduates with
enough knowledge and background to become professional surveyors
TRAINING MENTORING COMPETENCIES APPRAISAL FEEDBACK

Contact: Professional Development and Membership Coordinator


Chartered Institution of Civil Engineering Surveyors
+44 (0)161 972 3100
development@cices.org
www.cices.org/courses.html
2016 Delay 63

Concurrent delay:
Time does not always equal money
Andrew Bayne, Partner, Centra Consult

P RIOR to City Inn v Shepherd (2010) CSIH 68, it had been a


fairly well established legal position that where an event
gives rise to an extension of time, the contractor is entitled
to it even if there is concurrent contractor delay. It is worth noting
that the fundamental purpose of the extension of time mechanism
in a contract is to protect the employers right to deduct liquidated
and ascertained damages in the event of the works being
completed late. If the employer has prevented the contractor from
completing its works by the completion date, it would appear
to be iniquitous for liquidated and ascertained damages to be
deducted from the contractor.
City Inn involved a traditional Joint Contracts Tribunal (JCT)
building contract. At paragraph 42 of the decision, Lord Osborne
states that:

In such a situation, which could be described as one of


concurrent causes it will be open to the decision-maker,
whether the architect, or other tribunal, approaching the issue in
a fair and reasonable way, to apportion delay in the completion
of the works occasioned thereby as between the relevant event
and the other event.

In contrast to City Inn, Walter Lilly & Co Ltd v Mackay (2012) EWHC
1773 (TCC) reafrmed what had been the established position. At
paragraph 370 of the judgment, Mr Justice Akenhead states:

In any event, I am clearly of the view that, where there is an


extension of time clause such as that agreed upon in this case
and where delay is caused by two or more effective causes, one
of which entitles the contractor to an extension of time as being
a relevant event, the contractor is entitled to a full extension
of time.

It is noted that the judge made reference to an article by John


Extensions of time, LADs Marrin QC1 and what he described as a useful working denition
and concurrent delay of concurrent delay as:

where are we up to? A period of project overrun which is caused by two or more
effective causes of delay which are of approximately equal
causative potency.

For an event to give rise to an extension of time, it is established


ground that it would need to affect the works critical path an
effective cause of delay. However, with many extension of time
matters being the subject of retrospective analysis, it is possible
that a number of matters may have caused, or had the potential
to cause, critical path delay. It could be viewed that the matter
of equal causative potency introduces a level of subjective
assessment.
A relevant event (to use the JCT term) may appear on the face
of it to be de minimis in nature perhaps to undertake some
1
(2002) 18 Const LJ No.6 436
64 Delay Construction Law Review

additional works but it may still result concurrent delay was operative and where
in critical path delay. The contractor may costs were being incurred pursuant to the
be experiencing delay which is its own failings of the contractor. However, where
responsibility (shortage of labour is an two concurrent issues exist, it should be
example used in the above judgments) but possible for the chain of causation to be
where does this result with regards to an established whereby costs arising from the
extension of time being due? Perhaps to effect of relevant events can be recovered
an employer or contract administrator, the by the contractor. An example would be
shortage of labour may be the effective where the relevant event has prolonged
cause of critical delay. However, if the the period that a tower crane was needed
impact of the relevant event results in on site. Site staff costs are perhaps less
a chain of causation upon the critical easily disentangled for the purpose of
path which delays completion, then a attributing to a relevant event so a
contractor would feel somewhat aggrieved degree of apportionment would perhaps
if the employer is still entitled to deduct be understandable. If an extension of time
liquidated and ascertained damages. is granted, it does not necessarily result
in a situation whereby the contractor can
Time v money recover all of its time-related costs. But
It is important to emphasise the distinction in relation to time, if a chain of causation
between time and money. It is entirely can be established where a relevant event
possible that an extension of time may has delayed completion, albeit during a
be due, but that no loss and expense period of concurrent delay, should the
is payable and vice-versa. The chain employer be entitled to deduct damages
of causation should apply to loss and for contractor delay during this period?
expense as well. However, perhaps the Under a traditional standard form
apportionment approach described in the contract, where assessment of extension of
City Inn case is more appropriate with time is undertaken retrospectively, the full
regards to loss and expense? effect of a relevant event may already be
In general, time related costs such as known at the point in time an extension
preliminaries would not be payable to the of time is granted. It may be that, in
contractor during a period of concurrent retrospect, the contract administrator takes
delay. The contractor would still need the view that the effective cause of critical
to be on site for the period where its delay during the period the relevant event
2016 Delay 65

construction project. Under the JCT and


the old Institution of Civil Engineers (ICE)
forms of contract there was no obligation
upon the contract administrator or
engineer to undertake any specic form
of delay analysis.
In City Inn, Lord Drummond Young
concluded that a complex retrospective
Whilst the traditional forms of contract apply critical path delay analysis, in this case
an ostensibly retrospective approach, the NEC where an electronic baseline programme
was unavailable, is not essential for a
contracts envisage a prospective means of partys extension of time claim to succeed.
An approach which applies the principles
calculating critical delay. of experience and common sense is to be
preferred over one that relies on a more
was ongoing is the lack of progress on the part of the contractor. theoretical critical path approach. In City
But this is a subjective assessment and, if the above chain of Inn the parties had agreed an as-built
causation can be established arising from the relevant event, the programme, so there was a factual basis
English position reafrmed in Walter Lilly would suggest that the available for undertaking an assessment of
contractor should be granted an extension of time. the effect of relevant events and contractor
progress delays. It is noted that the City
NEC mechanism Inn judgment does not reject complex
Obviously, parties are at liberty to agree to contractual provisions electronic delay analysis, but it has to be
as they wish. However, it is perhaps worthwhile to reect on the reliable with logic links being correct.
mechanism in the New Engineering Contract (NEC) with regards
to extension of time. Whilst the traditional forms of contract apply
:VTLUHSX\LZ[PVUZ
It is understandable that in a situation
an ostensibly retrospective approach, the NEC contracts envisage a
where concurrent delay exists that one
prospective means of calculating critical delay.
cause of delay may prima facie appear
NEC envisages that the contractor will submit an electronic
to be more signicant than another.
programme to the project manager for acceptance and that,
However, if a concurrent employer liability
pursuant to this process, the parties have an agreed baseline
event has caused critical delay, an effective
programme for measuring progress and the effect that any
cause of critical delay, then should the
compensation event may have upon the planned programme. Key
principle that the employer has prevented
to this mechanism operating correctly is that the programme is
the contractor from completing its works in
regularly updated with progress and rescheduled to ascertain the
the period of concurrent delay apply?
projected completion date as the works progress.
City Inn considers the JCT terminology
in relation to the architect undertaking a
An example
fair and reasonable assessment. Perhaps
For example, after week six of the works, the progress reschedule
such an approach may have some merit in
indicates that the completion date has slipped by one week
resolving quantum where concurrent delay
due to lack of contractor progress say in relation to drainage
exists, but should the employer retain the
installation. On week seven, a compensation event arises. The
right to deduct liquidated and ascertained
contractor undertakes an assessment of the compensation event
damages in a period it has caused critical,
and submits a quotation describing the time and cost implications.
albeit concurrent, delay to the works? In
The assessed effect of the delay is inserted into the programme, such circumstances is the employer not
which has been rescheduled up to and including week six. This in fact beneting from its own failing in
involves the creation of new activity bar(s) within the programme being able to deduct damages and delay
and logically linking the new bar(s) to the existing activities the works?
as appropriate and then rescheduling the programme. If the
critical path is affected, and the completion date is delayed, NEC Andrew Bayne, Partner, Centra Consult
envisages that an extension of time should be granted. However, andrewbayne@centra-consult.com
when progress is rescheduled at the end of week ten, the drainage www.centra-consult.com
emerges once again as a critical driving activity. Throughout the
period of the compensation event, the drainage delay has been
ongoing and was an effective cause of concurrent critical delay.
Here, a situation exists where there is concurrent delay but the
contract provides that an extension of time should be granted Should the employer retain the right to deduct
with costs.
LADs in a period it has caused critical, albeit
Measuring time concurrent, delay to the works?
Clearly one of the key objectives of delay analysis is to identify
criticality and concurrency of delay events. The process envisaged
by NEC is ostensibly a time impact analysis approach as the works
proceed. This was also the methodology that was recommended
in the rst publication of the Society of Construction Laws Delay
and Disruption Protocol. One signicant drawback of this is that
it can be a very expensive way of managing time and delay on a
66 Risk Construction Law Review

With great risk comes...?


Gordon Lees FCInstCES, JGL Consulting

Risk comes from not knowing


what we are doing.
Warren Edward Buffett

T HE construction industry is inherently a high risk industry.


The nature of the operations undertaken and the varying
physical and nancial conditions under which each project
is carried out expose each party to a construction contract to risk
for various and differing reasons. While these risks are inherent in
the construction process it is only the severity and occurrence of
those risks that can have an impact on a construction project with
varying degrees of consequence. The construction client is at risk
from the well-known triumvirate of cost, time and quality, and it
is for the client to balance these three in the procurement stage of
the project.
Initially, the construction client must assess the feasibility of
the overall project in current market conditions and whether the
funding requirements can be met, the design responsibility that
could impact on quality depending on the route chosen and the
potential impact on revenue if the project is not delivered on time.
It could be considered tempting for the client to pass all of this
risk onto the contractor via a PFI model or design and build form
of contract, or even by way of drafting mitigation measures into
amendments to the form of contract used for the project.
However, is the relinquishing of any control of the risk good
business practice?
Passing more risk on to the contractor only results in a
higher cost. The uncertainty of the risk will likely be mitigated
by contingencies in the tenders received, as the contractors
commitment to providing cost and time certainty in the tender will
be governed to some extent by the perceived risk in the project
and the contractors share of that risk. The risk to the contractor
is inherent in the execution of the project if the assumptions it
has made in respect of construction methods and materials are
The management of risk in incorrect, and its supply chain does not perform or provide a
suitable standard of workmanship.
construction projects Further, the project itself is subject to risks of which unforeseen
conditions, changes in legislation, lack of resources, changes in
commodity prices, currency uctuations and health and safety can
detrimentally affect the time and cost of the works. These risks are
required to be mitigated in order to deliver the project.
The management of risk should therefore be, if not at the
forefront of endeavours, at least on the radar. The identication
and minimisation of risk will reduce or eliminate those adverse
consequences and give a better guarantee of potential outcome.
While the management of risk and uncertainty in a construction
project can be dealt with by an arbitrary contingency sum in the
tender for construction works, is it an effective method for any of
the parties to the project?

Risk management systems


The implementation of an effective risk management system
should therefore be considered in the assessment of a
2016 Risk 67

is important to not only concentrate on the


known risks, i.e. those that regularly occur
on the type of project under consideration
and can be identied from historic
knowledge or information available in the
public domain, but also the unknown
risks that could impact the objectives no
The construction client is at risk from the well- matter how remote and are likely to be
specic to the project. These unknown
known triumvirate of cost, time and quality, and risks can be identied through workshops,
brainstorming or more formal forums
it is for the client to balance these three in the such as hazard identication (HAZID) and
procurement stage of the project. hazard and operability studies (HAZOP).
Once risks are identied, the next stage
in their management is the assessment of
the potential severity of impact and the
construction project to reduce, if not
probability of them occurring during the
eliminate, the requirement for an course of the project. This risk assessment
arbitrary risk contingency. To assist with can be difcult where unknown risks
the implementation of an effective risk are identied and limited information is
management system, the International available on the potential occurrence, in
Organisation for Standardisation which case the management must make
has published ISO 31000:2009 (risk a judgment on the probability and impact
management principles and guidelines) any such risk may have.
to provide both guidance on the purpose This stage includes qualitative risk
and implementation of a risk management assessment. The impact of the risk on the
system and an international standard for project is assessed on the basis of physical
risk management. This document provides impact and quantitative assessment,
a basis for the implementation of effective whereby the risk is allocated a numerical
project risk management by allowing the value against which impact is measured.
parties to the project to identify where Both methods of assessment investigate
any risk is best allocated between them; effect and probability in assessing the risk,
identifying risk between the parties for and are to a great extent intertwined. The
mitigation during the course of the project; assessment of the risk can be identied for
the framework in which risk can be management purposes by way of a risk
identied, analysed and evaluated; and formula to provide a comparable method
proposals for mitigation to be considered of risk evaluation.
for implementation as necessary. Qualitative risk assessment is generally
An important aspect of risk management described as subjective and as such is
is the concept that the risk is borne by applicable to matters such as health and
the project and the allocation of that risk safety, where the outcome of risk analysis
is best distributed between the parties is to reduce the potential health and safety
on the basis of who is best placed to risk to as low as reasonably practicable
carry that risk, i.e. who has the resources (ALARP), without the encumbrance of
consideration of economic aspects.
and expertise to best mitigate that risk to
On completion of the assessment of
the project.
the effect and probability of a risk, there is
The accompanying guide to the
then the process of assessing the mitigation
ISO denes risk as being the effect of
measures that could be implemented to
uncertainty on objectives 1 rather than the
minimise or eliminate that risk from the
traditional denition a possibility of harm project. These mitigation measures will
or damage/nancial loss.2 This different be determined by the probability of the
denition introduces the concept that risk risk having an impact on the time, quality
can be perceived as having a positive effect or cost of the project. These mitigation
as well as a negative effect. To that end, measures can include consideration
risk should be considered between the of insurance against the risk; revised
parties as a risk to the project, as this is construction methods to avoid the risk;
the common objective of the parties, rather or the implementation of procedures and
than being passed between the parties processes to reduce the risk.
without consideration of who is best Once the assessment is completed and
placed to accept that risk and mitigate it for the risk is quantied, the risk contingency
the benet of the project. for any risks accepted as being inherent in
the project can be included in the tender
Identify, assess, manage on the basis that the risk contingency is
The process of risk management begins now an empirical determination of the
with the identication of the risk where it potential nancial and programme impact
1
ISO/IEC CD2 Guide 73, Risk Management
of the identied risks. The cost and time
Vocabulary, 1 April 2008 associated with these risks can be included
2
Abstract taken from Oxford English Dictionary in the tender as appropriate.
68 Risk Construction Law Review

This different denition introduces the concept that risk can be perceived as having a
positive effect as well as a negative effect.

The management of risk during the course Knowing what we are doing
of the project is an iterative process The implementation of an effective risk management system for
to monitor the identied risks and the both tendering and project execution, whether in accordance with
implementation of the mitigation measures ISO:31000 or not, will allow a party to a construction project to
and identify, assess and evaluate any better understand the potential problems that are likely to arise
new risks that may arise and were not and how best to mitigate or eliminate them.
considered in the tender process. The The management and mitigation of risk is therefore an
introduction of the early warning system important aspect of the construction process for any size of
into contracts, most notably in the New project. An effective risk management system will reduce the risk
Engineering Contract (NEC) suite, has that comes from not knowing what we are doing and provide
pointed out the requirement for a project greater certainty to the parties to the project.
to identify and deal with risks that could
impact the time, quality and cost of a Gordon Lees FCInstCES
project in a collaborative manner, and JGL Consulting
to allocate risks to the party best able to gordon@jglconsulting.co.uk
mitigate them for the good of the project. www.jglconsulting.co.uk
2016 Contract Administration 69

Contract administration for claims and


claims avoidance
Andy Hewitt FCInstCES FICCP FCIOB FQSi ACIArb, Executive Ofcer, Institute of Construction Claims Practitioners

What really matters in


Disputes often arise through the interpretation of the contract and
it is true to say that if the contract documents are poorly drafted
contract administration and compiled, the potential for disputes increases tremendously.
For these reasons it is innitely preferable to keep the other
documents section as small as possible and to amend the tender

C
documents to take into account any changes that have been
ONTRACT administration is a far- negotiated and agreed between the parties within the appropriate
reaching topic and much of it falls section of the contract. This also applies to tender queries and
outside the purpose of this article, their responses, which will arise in the rst instance from lack of
but there are many ways in which good clarity, ambiguity or conict within the documents. Rather than
contract administration will help when a just including the tender queries and responses as an addendum to
claim situation occurs. Additionally, many the contract as is often the practice, the relevant documents should
claims arise from conicts or ambiguities in be amended to reect the instructions given in the responses to
contract documents or the failure of one of such queries.
the parties to comply with its obligations The best time to complete and sign the contract is as soon as
under the contract. Good contract possible after the agreement has been made. If this is not done,
administration can also therefore play an personnel responsible for the construction and administration of
important part in avoiding claims. the project will often replace the people involved in the tender
and subsequent negotiations or memories will grow dim. Whilst
The contract documents there should be pressure to produce the contract documents for
The contract documents will usually completion and signature as soon as possible, it should always be
form the basis of any claim. If something remembered that rushing this very important task and producing a
has changed, the extent of the change poor set of contract documents could have serious consequences
may only be measured and evaluated by later on.
reference to the drawings and specication
upon which the contract is based. The Programmes and planning
claimants entitlement to make a claim will Most forms of contract require the contractor to submit a
usually be spelled out in the conditions programme of the works to the engineer for acceptance or
of contract, as will the procedure to be approval. This usually has to be done within a specied time
followed in the case of a claim. If there frame. The contractor should do its utmost to produce the most
is a disagreement between the parties as detailed and accurate programme possible within the time
to design, quality, responsibility, scope of stipulated. As a minimum, the programme should include:
works or procedures, the contract is the
place to look for guidance and resolution. A clear intention of the time and sequence of how the work is
There is a great temptation for those intended to progress.
whose job it is to prepare and compile the A clear critical path to completion.
contract, to dump all sorts of documents Dates when the employers input is required, with links to the
into it. Typically these may consist of critical path.
correspondence between the parties
between the time of tender and the If delays occur and the contractor wishes to pursue an extension
letter of acceptance, tender queries and of time claim, then the programme will be the yardstick against
clarications, tender bulletins, minutes of which to measure the effect of delays, so it is essential to have this
meetings during the negotiation process in place as soon as possible. It is usual for contracts to allow for
and the like. The potential for conict revised programmes to be prepared should the previous version
between such documents and other no longer reect the intended sequencing of the project, current
contract documents becomes high in such progress or extensions of time awards. A revised programme is
a situation and may, according to the the one in which to make amendments and not in the original
order of precedence stated in the contract, baseline programme.
not reect pre-contract negotiations and Contract administration procedures should allow for an updated
subsequent agreements between the programme to be maintained, recorded, submitted, agreed and
parties. The possibility for error is also kept as a record on a regular basis. The updates should include
increased if important points are hidden for changes such as additional work, omitted work and extensions
away in the main contract documents. of time awards. If logic errors have been discovered within the
70 Contract Administration Construction Law Review

baseline programme, then these should be discussed with the


engineer and corrected accordingly. Should it be necessary in a
claim situation to demonstrate whether or not the project was
proceeding as planned or that there were no concurrent delays at
any time, such a record will become an essential tool in doing so.
Many extension of time claims ounder on the method of delay
analysis used to demonstrate the effect of delays. The contractor The contractor often wishes to perform one
often wishes to perform one method of delay analysis and the method of delay analysis and the engineer
engineer considers that another method is more appropriate. Such
disagreements will only serve to prolong the resolution of a claim considers that another method is more
and involve the parties in additional expense. It is suggested that
if the employer or engineer prefers a specic method of delay
appropriate. Such disagreements will only
analysis to be utilised, then this requirement is included within serve to prolong the resolution of a claim.
the contract. This will ensure that the contractor maintains all the
necessary records and produces programmes that will allow an
analysis to be performed in the required manner. measures may be undertaken, the prudent employer will include
Contract administration systems should establish procedures for provisions for the forthcoming claim in its budget.
the early identication of potential claims, rstly because notices The contract will sometimes state the requirements for a notice;
or early warning of such will usually have to be submitted in
will often prescribe time frames within which notices must be
order to protect entitlement and, secondly, so that the contract
submitted; and will usually provide details of how notices should
administration system can kick in and appropriate actions be
be sent or delivered. Some contracts provide that the submission
taken. One of the early things that should be done from a claim
of notices is condition precedent to entitlement, which means that
point of view is to consult with the planners to ascertain whether
if the contractor does not comply with the requirements of the
an event will have any effect on the programme and, if so,
contract in this respect, it will lose the rights for compensation.
what the likely effect will be. At this stage you are attempting
It is fairly obvious that the contractors contract administration
to discover whether a delay to the completion date is likely and
systems should place particular importance on the subject of
consequently whether an early warning or notice of an extension
submitting notices. Remember that good contract administration
of time should be submitted. An in-depth analysis is not necessary
will help in both the avoidance and resolution of claims.
at this stage, but the planners should at least provide a best
opinion on which to base the decision as to whether to send a
notice or ag the event as a potential claim. It is always better to Andy Hewitt FCInstCES FICCP FCIOB FQSi ACIArb, Executive Ofcer,
send a notice and later advise that having investigated the matter Institute of Construction Claims Practitioners
further no claim will be pursued, than not to send a notice. Andy.hewitt@hewittconsultancy.com
http://instituteccp.com @ICCPMembership
Records, records, records
Many knowledgeable people have said it previously, but the three
most important aspects to a successful claim are good records,
good records and good records. I have found absolutely no reason
to disagree with this statement and have also come across several
situations where a potentially good case has been spoiled for the
Get recognised for your
absence of adequate records.
The burden of the claimant is to prove its case on the balance
skills, qualications and
of probabilities. In order to do so, it must substantiate that the expertise as a
events have actually occurred, possibly substantiate the timing of
the events and substantiate that the provisions of the contract have construction claims
been complied with in terms of notices and submissions. The only
way this may be done is by reference to the project records and professional
if the claimant does not have such records, it will be very difcult
to prove the claim. It is therefore extremely important that, rstly,
a robust contract administration system is created and secondly,
that systems and procedures are put in place to adequately record
the events and the effects on a contemporaneous basis. Good
records will establish events, dates and times, which, particularly
in the case of an extension of time claim, will prove to be of
great benet. Computerised document management systems are
common on construction projects and may be used to great effect
in claim situations.

Notices
Many forms of contract include requirements for the contractor Available on an international basis to
individuals and companies that possess
to provide notices or early warning of events or circumstances
skills, qualications and expertise in the
that it considers may provide entitlement to additional time or specialist eld of construction claims.
payment within a specied time frame of the event occurring.
The reasoning behind such requirements is that the employer and Become a member. Get the recognition
that you deserve. Apply today at
its agents need to be made aware of the circumstances as soon
www.instituteccp.com
as possible, in order that they may consider corrective action or
mitigation measures which may be implemented to minimise
the effects of the circumstances. Additionally, if no mitigation
CONSTRUCTION LAW PROFESSIONALS
Affiliate

Image Terry Higginson MCInstCES

Do you support the vital work of civil engineering surveyors?


Are you ready to start the path to professional recognition?
Do you know someone who would benefit from joining ICES as an Affiliate?
ICESAffiliates gain access tospecialist publications, including the monthly journal Civil Engineering
Surveyor,regional events, discounted conferences andseminars. If you are thinking of membership but
arent sure where to begin or if you know someone who should be affiliated to ICES, get in touch. Help
ICES continue to be the leading professional body for civil engineering surveyors.

Contact: Membership Department


Chartered Institution of Civil Engineering Surveyors
+44 (0)161 972 3100
development@cices.org
www.cices.org

The Chartered Institution of Civil Engineering Surveyors is a registered educational charity.


2016 Construction Law Professionals 73

Blue Sky ADR of time submissions for construction Practitioners. The institute offers associate,
30-32 Howard Business Park disputes. He has over 10 years experience member and fellow membership to
Howard Close working for contractors involved in professionals working in the specialist
Waltham Abbey building and civil engineering works eld of construction claims based on
Essex and has produced expert reports for qualications, expertise and experience.
EN9 1XE the purposes of court action. Andrew Corporate membership is also available
UK Bayne also has a masters degree in to companies providing services within
+44 (0)845 371 2575 construction law. this eld. The ICCP is an international
admin@blueskyadr.com Alexander Dickson BSc MBA LLB MCIOB FCIArb organisation and is accessible to claims
www.blueskyadr.com sandydickson@centra-consult.com practitioners on a worldwide basis.
Peter Barnes MSc FCIArb FCIOB MRICS MICE MCInstCES Chairman. Sandy Dickson is a quantity
Arbitrator, adjudicator, mediator and surveyor with chartered status within the
expert witness in respect of both liability construction industry. He is experienced in John Papworth Limited
and quantum issues. Represents parties in commercial management; the preparation White Shutters, 47 High Lane
arbitration, adjudication and mediation. and defence of claims; and preparation and Shapwick
Provides seminars and training and author/ adoption of commercial control systems Bridgwater
co-author of several books including Delay for commercial organisations. He has Somerset
and Disruption Claims in Construction. prepared expert witness reports and also TA7 9NB
Matthew Davies BSc(Hons) LLB(Hons) LPC MRICS has extensive experience in representing UK
Specialises in providing legal, commercial parties within adjudication and more +44 (0)7747 778 517
and contractual management, construction recently in mediation. www.johnpapworth.com
claims and dispute resolution services Peter McKernan HNC Building MCIOB ACIArb John Papworth
to the construction industry. Drafts and petermckernan@centra-consult.com johnrobertpapworth@gmail.com
reviews contracts, subcontracts and Partner. Peter McKernan is a highly
Consultant in international dispute
collateral warranties and advises on a experienced project manager and planner
resolution engineering and construction.
variety of contentious and non-contentious who has worked in both the contracting
Chartered arbitrator; FIDIC listed dispute
construction matters. Matthew Davies and consulting sides of the industry. His
board member; adjudicator, mediator,
is on the Royal Institution of Chartered experience spans more than 30 years and
conciliator, expert determiner. 46 years
Surveyors panel of adjudicators. he is experienced in the preparation of
experience in different continents and
delay analysis and production of reports
jurisdictions on oil and gas, power
for adjudication, litigation and mediation
generation and transmission, building, civil,
Centra Consult submissions.
process, electrical, mechanical and nuclear
17a Spylaw Street
engineering projects. Gives training and
Edinburgh
Corbett & Co International Construction talks to rms and professional groups.
EH13 0JS
UK Lawyers
+44 (0)131 441 0800 George House
www.centra-consult.com 2 Claremont Road Keating Chambers
Teddington London
Ana Almeida MCE Civil Engineering PMP
anaalmeida@centra-consult.com TW11 8DG WC2R 3AA
Consultant. Ana Almeida is a chartered UK UK
engineer with experience in project +44 (0)20 8614 6200 +44 (0)20 7544 2600
management in the UK and overseas. Prior info@corbett.co.uk clerks@keatingchambers.com
to joining Centra Consult, her experience www.corbett.co.uk Alexander Nissen QC
was gained working for contractors on Edward Corbett anissen@keatingchambers.com
multimillion pound construction projects. Recognised as a principal construction Alexander Nissen QC is a highly acclaimed
Ana Almeida is currently completing her law practice dealing with international silk who acts for and against major
studies to achieve an MBA. arbitration, litigation and the FIDIC forms players across the construction industry
Chris Atkinson BSc(Hons) LLM(Construction Law) of contract. The company works both in a range of domestic and international
MCInstCES MCIArb internationally and in the UK advising claims (via litigation, arbitration,
chrisatkinson@centra-consult.com on procurement, drafting and negotiating adjudication and mediation). Alexander
Partner. Chris Atkinson is a quantity contracts, dispute avoidance and dispute is a member of leading commercial set
surveyor with over 20 years experience resolution. Edward Corbett heads the Keating Chambers, which has unparalleled
within the construction industry and a company which has one of the most expertise and experience in construction
masters degree in construction law. He is experienced construction law teams in law. Its outstanding silks and juniors
experienced in commercial management; the UK. are specialist advocates, committed
the preparation and defence of claims; to providing the best legal advice, in
the preparation and adoption of conjunction with a practical strategic
commercial control systems for contracting Institute of Construction Claims understanding of the commercial pressures
organisations; and a variety of dispute Practitioners specic to the construction industry.
resolution processes, notably adjudication. Kissack Court, 29 Parliament Street
Chris Atkinson is on the Chartered Institute Ramsey
of Building and Construction Industry IM8 1AT
Council lists of adjudicators. Isle of Man
Andrew Bayne BSc MSc LLM(Construction Law) MCIOB hello@instituteccp.com
MCIArb ARICS http://instituteccp.com
andrewbayne@centra-consult.com Andy Hewitt FCInstCES FICCP FCIOB FQSi ACIArb
Partner. Andrew Bayne is a delay analyst Andy Hewitt is executive ofcer of
specialising in the preparation of extension the Institute of Construction Claims
74 Construction Law Professionals Construction Law Review

Leach Group in arbitration and DAB proceedings. He Schoeld Lothian


Unit 10 has worked extensively in Europe, the 3-7 Temple Avenue
Forest Gate Caribbean, Latin America, USA and the London
Pewsham Middle East. EC4Y 0DT
Chippenham UK
SN15 3RS www.schoeldlothian.com
UK QUALSURV International Dr Glyn Jones BSc MBA FRICS FCInstCES FCIArb
+44 (0)1249 443 118 8 Charles Court +44 (0)20 7842 0920
www.leachgroup.com Budbrooke Road glynjones@schoeldlothian.com
Simon F Fegen MRICS FAArb(Southern Africa) MCIArb Warwick Principal consultant experienced in all
CEDR Accredited Mediator CV34 5LZ aspects of commercial management and in
s.fegen@leachgroup.com UK principal forms of construction contracts,
Simon Fegen specialises in the preparation +44 (0)1926 499750 nationally and internationally. Sector
and negotiation of contractual claims info@qualsurv.co.uk experience in construction, transport,
on major building and civil engineering www.qualsurv.co.uk infrastructure and energy. Specialisms
projects. He prepares submissions, David Fishwick FCInstCES ACIArb MAPM include contract preparation, procurement,
represents clients in DAB and arbitration, david.shwick@qualsurv.co.uk risk and contract management, for
and conducts training programmes Director QUALSURV group of companies, employers and contractors. Also
on dispute avoidance and contract providing specialist contract commercial experienced in carrying out dispute
administration. He is a CEDR accredited management/dispute resolution services avoidance and management, involving
mediator. He was based in Africa and the both in the UK and internationally. Broad preparation and negotiation of claims.
Middle East for 30 years and works in experience in diverse sectors, particularly Alan Williamson FCInstCES MRICS MBIDP
Africa, Asia, the Middle East and Europe. civil engineering; energy; and commercial +44 (0)20 7842 0926
Melvyn D Smith FCInstCES FFB building. Recent repeat commissions +44 (0)7703 207598
m.smith@leachgroup.com include procurement/contract alanwilliamson@schoeldlothian.com
Leach Group managing director. He has management of off-shore wind farms Principal consultant experienced
extensive building, civil engineering and renewable energy plants; claims in preparation and negotiation of
and M&E experience in the preparation preparation; expert reports for claims under most principal forms of
and negotiation of contractual claims. international arbitration proceedings. construction contracts, both nationally
Melvyn Smith, an experienced quantum and internationally. Specialises in dispute
expert, provides advice on dispute resolution through adjudication, arbitration,
avoidance and contract administration, mediation and litigation, representing
prepares submissions, represents clients contractors, subcontractors and employers
in adjudication, and assists legal teams as either claimant or respondent. Regular
contributor of construction law articles to
a number of publications. Alan Williamson
also provides bespoke training courses,
particularly upon New Engineering
Contract based contracts. Member of the
Society of Construction Law.
Construction
Solutions
Drawing on decades of experience working on some
of the worlds most complex, high prole construction
projects, FTI Consulting has a proven track record
in providing solutions that help our clients prevent,
manage and resolve construction issues.

We help resolve disputes by establishing a


clear, commercially driven strategy, promoting
early resolution. Our team has in-depth experience
of preparing and evaluating claims, analysing
PREVENT delays and costs, and giving evidence in court and
arbitral panels on contractual, delay and
quantum matters.

For further information on our service offerings,


or if you are interested in joining our growing team,
MANAGE please contact:
Tim Haynes
Senior Managing Director
Head of Construction Solutions, EMEA
+44 (0) 20 3727 1237
tim.haynes@fticonsulting.com

RESOLVE

Follow us on LinkedIn:
FTI Consulting Construction Solutions

www.fticonsulting.co.uk

CRITICAL THINKING AT THE CRITICAL TIME


2016 FTI Consulting, Inc. All rights reserved.

You might also like