Canal linings shall be constructed where shown on the drawings. The lining will be unreinforced concrete containing polypropylene fibers, placed over a geomembrane liner, except that where placed at canal structures or shown on the drawings, the concrete lining will be reinforced. A. The Contractor shall provide evidence of previous construction experience on similar type pneumatically applied mortar projects if so requested by the Engineer. B. Unit price bid per square meter in the Bid Schedule, and shall include all work and materials required in preparing the earth foundation, placing, and curing the concrete lining, placing cut-off walls at the ends of the lined section, polypropylene fibers, furnishing and placing reinforcing steel and escape ladders, panel repair, and shall be in addition to the unit price bid in the Bid Schedule for canal excavation and compacting embankments. Excavation for the concrete footings at the transitions from the canal lining to the concrete structures below the canal prism shall be as shown in the Drawings and all payment therefor will be included in the unit price bid in the Bid Schedule for reinforced canal lining. PART 2: MATERIALS: 2.1 Concrete: A. Cement: All cement shall be Portland cement, Type II, low alkali, and shall conform to ASTM Designation C-150. The cement shall be free of lumps and properly aged. B. Aggregates: Fine and coarse aggregates shall conform to the requirements of ASTM C-33. The maximum nominal size of coarse aggregate shall be inch for concrete lining. Aggregate for air blown mortar may consist of not more than 30% pea gravel with a maximum nominal size less than 3/8 inches. C. Water: Water shall be clean and free from oils, acids, salts, or other injurious substances. D. Admixtures: The Contractor may use an air entraining agent conforming to the requirements of ASTM Designation C-260 in all concrete. The amount of air entraining agent, if used, shall be such as will affect the entrainment of four to six percent (4%-6%) of air, by volume of the concrete at the time of discharge from the mixer. The Contractor may use a pozzolan conforming to the requirements of ASTM Designation C-618 or a liquid admixture with pozzolan characteristics in accordance with ASTM Designation C-494. E. Fiber Reinforcement: Polypropylene fiber filaments shall conform to ASTM C-1116. The fiber length shall be three-quarters inch (). Fibers shall be added to the concrete mix at the time of batching at the rate of 2 pounds per cubic yard of concrete. 2.2 Reinforcement: A. Reinforcement in reinforced concrete canal lining shall be #4 reinforcing bars. B. Polypropylene fiber filaments shall conform to ASTM C-1116. The fiber length shall be three-quarters inch (). Fibers shall be added to the concrete mix at the time of batching at the rate of 1 pounds per cubic yard of concrete. 2.3 Pneumatically Applied Mortar Lining: A. Pneumatically applied mortar shall consist of a mixture of Portland cement, sand, and water placed under pneumatic pressure. One part, by weight, of cement will be used with 4.5 parts, by weight, of surface dry sand. B. The Contractor shall provide such means and equipment as are required to control accurately the relative amounts of cement, sand, and water entering the mortar. The equipment and its operation shall be subject to the approval of the Engineer. C. The mortar shall be proportioned on the basis of integral sacks of cement, and the amount of sand shall be determined by direct weighing. The amount of water used shall be that required to produce mortar of suitable consistency, quality, and uniformity with the minimum rebound. D. Fine aggregates shall conform to the requirements of ASTM C-33. Aggregate for air blown mortar may consist of not more than 30% pea gravel with a maximum nominal size less than 3/8 inches. 2.4 Geomembrane: A. Material shall be surfaced coextruded textured high density polyethylene geomembrane, indicated in tender technical specifications, or approved equal and will have a minimum warranty of 5 years. B. Minimum Values 1. Thickness (minimum average) (ASTM D 5994): 38 mil (0.96 mm) 2. Density (ASTM D 1505): 0.94 g/cm3 3. Tensile Properties, each direction (ASTM D 6693, Type IV): a. Strength at Break: 60 lb/in-width (11 N/mm) b. Strength at Yield: 84 lb/in-width (15 N/mm) c. Elongation at Break: 100% d. Elongation at Yield: 12% 4. Tear Resistance: 28 lb (125 N) 5. Puncture Resistance: 60 lb (267 N) 2.5 Joint Sealant: A. The adhesive sealant will be a single component high performance low modulus elastomeric sealant acceptable for a water immersion application, Sika/Sikaflex-1a or approved equal. The color of the sealant will be white or as approved by the Engineer. B. The joint sealant primer will be non-toxic and non-staining, Sika/Sikaflex Primer 429/202, or as recommended by the joint sealants manufacturer. C. The sealant backer rod will be compressible polyethylene foam rod or other flexible, permanent, durable non-absorptive material recommended by the joint sealant manufacturer and compatible with the joint sealant. 2.6 Escape Ladders: A. Ladders shall be fabricated per the Standard Details, and shall be galvanized before installation in or onto the concrete lining. PART 3: EXECUTION: 3.1 Excavation And Preparing Earth Foundation For Canal Lining: A. Excavation for canal lining shall be as provided for in the applicable portions of Tender Technical Specifications Earthwork. B. Where the natural ground surface is below the elevation of the top of the canal lining shown on the drawings, the foundation for the concrete lining shall be compacted as provided for in Tender Technical Specifications - Earthwork. The Contractor shall trim and finish the earth surfaces to provide a firm foundation for the concrete lining. If, at any point, the natural foundation material is disturbed or loosened during the excavation process or otherwise, it shall be consolidated in a manner satisfactory to the Engineer. If, at any point, material is excavated beyond the neat lines required to receive the concrete, the excess excavation shall be filled with selected material, moistened, if required, and compacted in a manner satisfactory to the Engineer. C. Immediately prior to placing concrete, the foundation shall be thoroughly moistened. 3.2 Geomembrane Lining: A. Deployment: The geomembrane panels shall be set out in accordance with the manufacturers recommendations and shall comply with the following guidelines: i. Sandbags or approved equal shall be used for ballast and to prevent wind uplift. ii. Personnel walking on the geomembrane shall not engage in activities or wear shoes that could damage the geomembrane. Smoking will not be permitted on the geomembrane. iii. Heavy vehicular or equipment will not be permitted to travel directly on the geomembrane unless protective measures are followed as required by the geomembrane manufacturer. iv. Sufficient material (slack) shall be provided to allow for thermal expansion and contraction of the geomembrane during installation. B. Field Seaming: a. To the maximum extent possible, the seams shall be perpendicular to the canal unless otherwise approved by the Engineer. b. Slope panels shall extend a minimum of five (5) feet beyond the grade break into the flat area. c. Alignment of the seam overlaps shall be consistent with the requirements of the welding equipment being used. A minimum of six (6) inches of overlap is required. d. Welding equipment and accessories shall meet the manufacturers recommendations and requirements. e. Trial welds shall be performed on geomembrane samples to verify the welding equipment is operating properly. f. No welding equipment or welder shall be allowed to perform production welds until the equipment and welders have successfully completed acceptable trial welds. g. Seaming shall not proceed when ambient air temperature or adverse weather conditions jeopardize the integrity of the liner installation. C. Repair: a. Damaged geomembrane shall be removed and replaced with acceptable geomembrane material if damage cannot be satisfactorily repaired as directed by the Engineer. b. All patches or caps shall extend a minimum of six (6) inches for extrusion welds and four (4) inches for wedge welds beyond the edge of the defect and around all edges of the patch material. c. Damaged geomembrane shall be repaired using one of the following repair methods as agreed upon by the Contractor and the Engineer: i. Abrading and Re-welding used to repair a short section of seam. ii. Spot Welding used to repair pinholes or other minor, localized flaws or where the geomembrane thickness has been reduced. iii. Capping used to repair long lengths of failed seams. iv. Flap Welding used to extrusion weld the flap (excess outer portion) of a fusion weld in lieu of a full cap. v. Remove the unacceptable seam and replace with new material. 3.3 Placing Reinforcement: A. Reinforcement for canal linings shall be placed at 12 inches on center each way within the lining slab. B. Reinforcement placement shall conform to tender technical specifications . 3.4 Concrete Handling And Placing: A. In preparation for the placing of concrete, all water, construction debris and extraneous matter shall be removed from the canal section. The concrete shall be placed as nearly as possible to its final position by means that avoid segregation of the materials and displacement of the reinforcement. B. Precautions and provisions shall be made to avoid plastic shrinkage cracking. When site and/or environmental conditions exist that have a high possibility for plastic shrinkage cracking, the Contractor shall follow these additional requirements: 1. Concrete shall not be placed in conditions where wind speed is or is anticipated to exceed 15 mph or if the combination of environmental and site conditions promote plastic shrinkage cracking. 2. A written proposal shall be submitted to the Engineer for approval. The proposal will include the method of concrete placement, alternative mix designs, list of materials, additional finishers and laborers and equipment necessary to minimize the cracking. 3. curing compound shall be applied to the surface immediately following the finishing operation and the entire surface covered with polyethylene sheeting. 3.5 Placing Slip-Formed Canal Lining: A. The lining shall be placed against undisturbed earth or compacted embankment. Type of construction will be provided that neat, accurate, and durable concrete lining, as provided for in these methodology, is the finished product. 3.6 Placing Pneumatically-Applied Mortar Lining: A. All canal gates, pumps and appurtenances shall be properly covered and protected with viscuine prior to the placement of the concrete lining. B. All absorptive surfaces against which pneumatically applied mortar is to be placed shall be moistened thoroughly. Free water will not be permitted on the surface during the application. Ground wires shall be installed in the canal prism to outline the finished surface of the lining as shown on the plans or as directed by the Engineer. C. The mortar shall be applied from a nozzle held approximately four feet (4') from the surface, and in a stream as nearly perpendicular to the surface being covered as practicable. D. The pressure in the placing machine shall be maintained at not less than forty-five pounds per square inch (45 psi) for hose lengths up to one hundred feet (100') and shall be increased five pounds per square inch (5 psi) for each additional fifty feet (50') of hose. Water pressure shall be maintained at least fifteen pounds per square inch (15 psi) greater than the pressure in the placing machine. E. Sand pockets shall be removed and replaced with pneumatically applied mortar as herein specified. Rebound shall not be incorporated in the work in any manner. D. Construction joints shall be sloped to a thin edge and the edge shall be thoroughly cleaned and wetted before the adjacent section of mortar is placed. 3.7 Finishing Canal Lining: A. The finished surface of canal lining shall be equivalent in evenness, smoothness, and freedom from rock pockets and surface voids to that obtainable by the effective use of a long-handled steel trowel. Shallow surface pitting and trowel marks are not objectionable. B. Deviations from true line and grade shall not exceed one-tenth foot (0.1'). There shall be no abrupt changes in section, line or grade. C. Transverse grooves, three-quarter inch (3/4") deep and approximate one-half inch (") wide, shall be made in the concrete lining. The first groove shall be made ten feet (10') from the end of the lined section and at ten-foot intervals throughout the full length of the lined section. 3.8 Curing Canal Lining: A. Concrete lining shall be cured by a white pigmented membrane curing compound. Membrane curing shall be by application of a sealing compound conforming to ASTM C -309. Sealing compound shall be applied to the concrete surfaces by spraying in one coat to provide a continuous, uniform membrane over all areas. B. The maximum temperature of concrete as placed shall be less than 90F. When the temperature of concrete as placed may be 90F or higher, as may be reasonably predicted from current temperatures of materials and the likelihood of rises in weather temperatures, the Contractor shall employ effective means, such as precooling aggregates and mixing water, use of ice as part of the mixing water, shading aggregates, or placing at night, as necessary, to maintain the temperature of concrete, as placed, below 90F. 3.9 Concrete Panel Inspection And Repair: A. After three days of curing, the concrete panels will be inspected. All visible cracks will be marked with a water-based spray paint and be given a rating of 0, 1, 2 or 3 based on its severity. a. Rating 0 (0 to less than 1/8 in width): Crack will be monitored for thirty (30) days after the placement of the concrete. Crack will not be repaired unless it expands to a rating of 1. b. Rating 1 (1/8 to less than 5/16 in width): Crack will be primed and sealed with an adhesive joint sealant. Crack will be properly prepared and primed for water immersion as directed by the joint sealants manufacturer. c. Rating 2 (5/16 to less than 1/2 in width): Crack will be repaired with properly sized and installed sealant backer rod, primer and adhesive joint sealant. Crack will be properly prepared and primed for water immersion as directed by the joint sealants manufacturer. d. Rating 3 (1/2 and greater in width): Concrete panel will be removed and replaced or repaired as directed by the Engineer. B. The crack shall be clean, dry and free of oil and grease. Curing compound residue and other foreign matter must be thoroughly removed prior to the application of the joint sealant primer. C. The air temperature at the time of application will be between 40 and 100F or as recommended by the sealant and primer manufacturer. D. All cracks shall be repaired and allowed to cure for one week prior to total water immersion. 3.10 Escape Ladders: A. Ladders shall be installed in all lined canals and reservoirs at the locations and spacings shown in the Drawings. Ladders shall be embedded in the freshly placed lining before it sets.