Professional Documents
Culture Documents
MBA
(Annual Pattern)
First Year
Page No.
UNIT I
Lesson 1 Introduction to Operation Management 7
Lesson 2 Types of Production Systems 35
UNIT II
Lesson 3 Product and Product Design 45
Lesson 4 Operations Technology and Facility Location 72
Lesson 5 Plant Layout 107
UNIT III
Lesson 6 Production Planning and Control 143
Lesson 7 ERP and MRP-II Overview 173
UNIT IV
Lesson 8 Introduction to Materials Management 189
Lesson 9 Inventory Control 210
UNIT V
Lesson 10 Total Quality Management 257
Lesson 11 ISO Quality Certification Concepts 282
OPERATIONS MANAGEMENT
SYLLABUS
UNIT I
Operations Management Meaning Importance Historical contributions System
view of OM Operations strategy and competitiveness Functions of OM Types of
production systems
UNIT II
Production design and process selection Evaluation and selection of appropriate
Production and Operations Technology Product design and process selection.
Types of layout Analysis and selection of layout Product and/or Process layout
Cellular Lean and Agile manufacturing systems Computer Integrated Manufacturing
Systems Assembly line balancing.
UNIT III
Production planning and control Meaning Functions Aggregate Planning Master
Production Schedule (MPS) Material Requirement Planning (MRP) BOM Capacity
Requirement Planning (CRP) An Introduction to MRP II and ERP Business Process
Re-engineering Total Productive Maintenance (TPM)
UNIT IV
Materials Management Functions Material Planning and Budgeting Value
Analysis Purchase functions and Procedure Inventory Control Types of
Inventory Safety stock Order Point Service level Inventory Control Systems
Perpetual Periodic JIT KANBAN
UNIT V
Total Quality Management Concept Statistical Quality Control for acceptance sampling
and process control Concepts of OC Curve Use of the OC curve Concept of
Type I and Type II error Quality Movement Quality Circles ISO Quality Certifications
and Type Quality Assurance Six sigma concept
5
Introduction to
Operation Management
UNIT I
6
Operations Management
7
LESSON Introduction to
Operation Management
1
INTRODUCTION TO OPERATION MANAGEMENT
CONTENTS
1.0 Aims and Objectives
1.1 Introduction
1.2 Meaning of Operation Management
1.3 Importance of OM
1.4 Historical Contributions
1.4.1 Scientific Management Time and Motion Studies
1.4.2 World War II to the 1960s Operations Research
1.4.3 The 1970s and 1980s Japanese Challenge
1.4.4 The 1990s and After
1.5 Systems View of Operations Management
1.5.1 Transformation Approach
1.5.2 Value Driven Approach
1.5.3 Operations Management Basics
1.6 Operation Strategy and Competitiveness
1.7 Functions of Operations Manager
1.7.1 Interface with other Functions
1.7.2 Operations Managements Future Challenges
1.8 Efficiency and Effectiveness
1.9 Let us Sum up
1.10 Lesson End Activities
1.11 Keywords
1.12 Questions for Discussion
1.13 Suggested Readings
8 Discuss the roles of operations and operations managers within the firm and the
Operations Management
interactions with engineering, marketing, finance, accounting, and human resource
management
Analyse the concept of value and the value equation, including definitions of
performance and costs
Learn about future challenges that operations managers are likely to face.
1.1 INTRODUCTION
A number of forces are impacting most businesses today. These are the forces of
change. They are impacting businesses through international trade, transactional
finance, and global production; challenging traditional beliefs and practices
challenging the way businesses compete with each other.
This is good news and bad. The bad news is that never before in the history of
mankind has the rate of change, the challenges, and the cost of failure, been so high.
And the good news is, never before has humankind had so much knowledge to meet
the challenges.
The winds of change have brought in new industries, new products and services into
the marketplace with increased competition from national and multinational
corporations. The winds of change are impacting all industries, while some seemingly
change gradually, and others change so rapidly that some businesses can not respond
quickly enough to these changes. This makes managing change complex and difficult.
No management system works well for firms competing at the different extremes of
this pace spectrum.
People and processes produce the organizations products, be it a service (e.g. booking
an airline ticket) or a product (e.g. a bar of soap). All these products have one thing
that is common a conversion process. As a discipline that manages the conversion
processes, Operations Management is expected to provide solutions to many of these
challenges.
The first step, to meet these challenges, is to find some means to classify firms and
industries on the basis of their requirement to change. Charles Fine of MIT tackled
this problem. He coined the term clock-speed to describe the pace of change
existing within an industry and by the rate at which customers demand or are able to
get new goods or services.
While it is difficult to define one attribute to measure a firms clock-speed, Fine cites
a list of industries to illustrate the concept.
Table 1.1: Industry Classification by Clock-speed
Fast Clock-speed Moderate Clock-speed Slow Clock-speed
Personal computers Bicycles Commercial aircraft
Software Automobiles Tobacco
Toys and games Computer operating systems Steel
Athletic footwear Agriculture Military aircraft
Semiconductors Fast food Shipbuilding
Clock-speed also indicates how fast a firm or parts of a firm must respond to
competitive threats, and to other organizational challenges. It provides a framework
for organizations to decide whether they should act reactively, actively or proactively.
Slow and steady improvement is appropriate in some situations, while in others,
attempts at dramatic breakthroughs are appropriate. Different improvement strategies
require different resources, management styles, and support structures. They not only 9
Introduction to
require different organizational capabilities but also require creating new ones. Operation Management
In fast-paced organizations most competitive advantages are quite temporary. The
challenge for such organizations is to be able to anticipate and adapt to change fast
enough to avoid decline and possibly extinction.
In slow clock-speed industries, change comes, but at a more gradual pace. These
changes are often predictable because they have their roots in the driving forces and
you have the time to prepare for them.
Competitive advantage flows from the ability to make the conversion process more
efficient, eliminate wastes, lower costs, increase the outputs from limited resources
and provide more value to the consumer. All organizations whether manufacturing a
product or offering a service, whether fast clock-speed or slow clock-speed, must
manage processes and people effectively to achieve this state.
1.3 IMPORTANCE OF OM
The importance of Operations Management can be measured by its ability in creating
world class companies. For example, in moderate clock-speed industries, Bajaj Auto
has focused on Operations Management to emerge as lowest cost manufacturer of
two-wheelers in the world. Reliance Industries leads worldwide in project
management. In slow clock-speed industries, Tata Steel is the lowest cost steel
producer, internationally. Infosys, Tata Consultancy Services and Wipro have
established their superiority over their international rivals in fast clock-speed products
like software. These and many such Indian stories and case studies will be elaborated
in the rest of the book.
10 The concepts associated with Operations Management, perhaps, have their roots
Operations Management
embedded in the development of early organizations. The class of problems
represented by Operations Management came into high relief in the era after the
Industrial Revolution. This was a period of radical changes. People got replaced by
machines, and water and mule power replaced human muscular effort. These
developments changed the nature of production. As production moved from the
cottage to the factory, the seeds of operations management spouted on fertile ground.
The combination of computer and communication advances affected the way business
was conducted and it particularly impacted many service industries. The development
of the better and faster microprocessors, communication technology, miniaturization,
and digitization created a new lease of life and added vigour to the development of
new techniques in Operations Management.
14
Operations Management
15
1.5 SYSTEMS VIEW OF OPERATIONS MANAGEMENT Introduction to
Operation Management
Productive systems are those that convert or transform resource inputs into useful
goods and services as outputs. Such productive systems are generally referred to as
Operations systems. Operations Management, often described as Production and
Operations Management (POM), relates to the management of such systems. Of the
many developments taking place in the discipline in the recent past, the most radical is
perhaps the concept of what the discipline represents. Up to the 1970s, Operations
Management was considered as a centre system with its basic focus on cost
reduction. Since the 1990s, it has been increasingly recognized as a basis for value
creation within the organization.
Both these views on Operations Management co-exist today. In smaller organizations
where the competition is price sensitive, markets are small and the customer needs are
well defined, the focus is on the cost reduction aspect of Operations Management.
However, as organizations grow, the parameters of competition increase, market
logistics become more complex and customers become more demanding, the focus of
Operations Management as a value creation function, provides greater rewards.
There are, therefore, two ways traditional and modern in which Operations
Management is viewed:
1. The traditional view perceives Operations Management as a system that is
involved with the manufacture and production of goods and services.
2. The more modern view perceives Operations Management as a system designed
to deliver value.
Let us discuss these two perspectives in greater detail.
Performance
Measurement
The four core business processes in this model are described below:
1. Determine Customer Needs: It is critical for the organization to know the
customers needs in order to support the firm's demand, its forecasting needs and
its product design and development activities. In order to do this it is necessary to
monitor the competitive environment. The supporting business processes are
involved in marketing products and providing after-sales service. There has to be
a measure of customer satisfaction. There is also a requirement to understand the
specific needs of different market segments and the nature of the competitive
environment. For fast-pace firms, Customer Relations Management (CRM) has
become important. Many software firms in India are developing applications that
are designed to keep them in a position to understand what their customers want
and in some cases, how it can enhance the marketing capabilities of its sales force.
2. Develop Product Strategy: This involves marketing, operations, and engineering
activities in order to create products that customers desire. This requires an ability
to evaluate product concepts so that there is support to design new products or
introduce product improvements. The slower the pace, the more is the focus on
delighting customers by finding better ways to incrementally improve products
that already exist. But as the pace of business increases, the greater is the need to
be aware of the competitive challenges that new technologies and competitors
introduce into the marketplace.
The organization has to develop the ability to understand the potential customer
and the pleasing/displeasing consequences associated with changes. An aggressive
competitive market exploits the limitations of an organization; as such, it has to
possess the ability to design, build and test prototypes, and develop new products
or product improvements before the competition. The risk is that if the firm does
not replace, upgrade its existing products in time, some other firm will.
3. Secure Processes and Materials to Satisfy Demand: Management activities
involve selection of raw materials from vendors and the ultimate delivering and
servicing of the product for the customer. These activities include operations
planning and control processes and managing the product transformation
processes. In addition, the business logistics and the supply chain process play a
critical part and have to be managed effectively. In today's world, supply chain
18 players are widely distributed and will seldom lie within the firm's boundaries,
Operations Management
hence making the need to manage the flow of materials effectively more
challenging.
4. Manage Strategic Planning Processes: Support business processes are essential
to all organizations. The strategic planning process defines the firm's as well as its
own Operations Management function. It also specifies what it must do to achieve
its corporate goals. The human resource management function creates an
organization design that is suited to the competitive environment and provides
and/or enhances the human capital needed by other functions to effectively carry
out their tasks. The Management Information Systems groups provide timely
information that is needed to assess the competitive environment and the
performance of its business functions. The accounting and finance groups monitor
the use of financial assets and take steps to ensure that the financial base of the
organization is both adequate and efficiently utilized. There has to be an adequate
interface between all these functions.
Operations Management activities are mostly involved in the second and third core
processes. Operations Management, as a value creating activity, contributes to the
customer satisfaction process by assisting to design and develop products that possess
the capability to satisfy the customers functional need with the desired level of
design, quality and cost. Operations Management is defined as the following:
Operations Management constitutes all of the activities that an organization conducts
in order to deliver value to its customers. It is the set of processes that transforms
either materials or information into a product or service.
The operations function contributes to the value delivery to customers by significant
improvements in the cost, quality, timeliness, and availability of products and
services. Organizations can use effective Operations Management either to show
improvements in performance and quality, coupled with lower prices in real value, or
to help raise their bottom-line.
Consider the Consumer Durable Sector in India: During the last twelve months, the
market leaders have given a lead by lowering prices by 25-40 per cent on almost their
entire product range. The decline in prices is attributed to substantial value
engineering and technology improvement. This in turn has resulted in a 16-18 per cent
increase in consumer demand for the industry. Such dramatic changes are also seen in
other technology products.
On the other hand, during the same period in the FMCG segment, most leading
companies have reported appreciable growth in profits despite the reductions in sale
and sagging top-lines. They have managed to effectively protect prices by squeezing
costs through better sourcing, better supply chain and by reducing overhead costs. The
average profit growth has been in the region of 10 per cent while average sales have
reduced by 5 per cent.
These two functions have to work together, for innovation and systematization go 19
Introduction to
hand in hand. It is only possible with tight integration between these two functions Operation Management
that more new products can be launched faster. Shrinking product lifecycles makes
this an important requirement, especially for fast clock-speed industries. Initiatives
such as simultaneous engineering and early supplier involvement in the product design
process elevate the role of operations in the product and service concept design
process.
Operations Management designs and manages the value chain for manufacturing
goods and delivering services, i.e., the process and supply chain needed to create,
deliver, and service the products sold. It is in addition, involved in designing and
managing processes that support the value chainsuch as purchasing and materials
management, storage and transportation, customer support, and work systems.
Its performance metrics in delivering value in controlling and improving the value
chain and support processes to achieve and sustain high levels of business and
organizational performance can be judged on its capability to:
Deliver a product that measures up to design specifications
Be flexible enough to offer products to customers depending on how, when, and
where they want it.
Do the above at an acceptable cost.
Operations Management is no longer merely something that has to "get done" in order
to proceed with business as usual. It successfully helps organizations to squeeze out
the waste, and to focus on how to differentiate from competitors in meaningful ways.
Where Operations Management was once viewed primarily as a manufacturing
function, service firms are now recognizing its tremendous competitive potential.
Instead of a focus on cost, the focus now encompasses reliability as well as delivery
times. Operations Management is now a major contributor to the design and
management of the supply chain needed to create, deliver, and service the products
sold.
20 For example, a consumer product company like Hindustan Lever must pay attention to
Operations Management
consumers needs for product quality and performance, as well as to external
customers (an independent retail outlet like Morning Stores in Delhi) needs to supply
the right products at the right time.
Timeliness is the ability of a firm to get the right product to targeted customers at the 21
Introduction to
most desirable time. Operation Management
Flexibility is the input to the value equation relating to the ability of the Operations
Management system to give the customer the desired product.
Operations managers evaluate cost, measured in money terms, for its contributions in
two important roles:
1. Enhancing value, and
2. Serving as a performance metric for evaluating business processes.
The element in the value equation that is of primary importance is often called the
order winner. Order winners are attributes that reflect a customer's preference and
dominate the other elements of value. Excellent food offered by a restaurant may be
an order winner. Over time, order winners often evolve into order qualifiers, as the
value provided by competition improves.
For example, Sonys Trinitron picture tube that was an order winner became an order
qualifier as the quality of competition improved. Having a high-quality picture tube
was no longer enough for Sony to win the customer.
Sometimes, a value equation component has a trait that can make the consumer decide
in not purchasing the product. Such traits are called order losers. Human rights
activists dissuade people from buying products made through child labour. In this
case, products identified as being produced by children become order losers.
Figure 1.4: Relationship between the Business Strategy and the Functional Strategies
22 Remember that the operations function is responsible for managing the resources
Operations Management
needed to produce the companys goods and services. Operations strategy is the plan
that specifies the design and use of resources to support the business strategy. This
includes the location, size, and type of facilities available; worker skills and talents
required; use of technology, special processes needed, special equipment; and quality
control methods. The operations strategy must be aligned with the companys business
strategy and enable the company to achieve its long-term plan. For example, the
business strategy of FedEx, the worlds largest provider of expedited delivery
services, is to compete on time and dependability of deliveries. The operations
strategy of FedEx developed a plan for resources to support its business strategy. To
provide speed of delivery, FedEx acquired its own fleet of airplanes. To provide
dependability of deliveries, FedEx invested in a sophisticated bar code technology to
track all packages.
23
Feedback Introduction to
Operation Management
INPUTS:
Materials Processes OUTPUTS:
Capital Goods
Suppliers Equipment (Tangible) Customers
People Services
Information (Intangible)
Energy
Operations
Management
The departmental mission will to a large extent depend on the nature of the product
whether the organization is dealing with goods, services or contracts. Whatever the
product, the departments mission is judged on three major components:
1. Cost minimization,
2. Delivery reliability, and
3. Product quality
Equally if not more important, is the ability to manage humans in a way that is
mutually satisfying to the subordinates, peers, and superiors and this involves getting
the necessary things done. Effective operations managers must show commitment
both to their employees and to the organization's objectives.
Workers expect good managers to be fair and impartial. In an era of downsizing and 25
Introduction to
disintermediation, workers would like to feel that their manager is an effective Operation Management
advocate when it comes to advancing or protecting their jobs.
Box 1.3: New United Motor Manufacturing (NUMMI)
Established in 1984 as a joint venture between General Motors Corp. and Toyota, New United Motor
Manufacturing (NUMMI) took over the former General Motors plant. The plant, on 211 acres east of
Interstate 880 and south of Fremont Boulevard, occupies about 5.3 million square feet. This was a
50-50 joint venture that produced Toyota Corollas and Chevrolet Novas.
Toyota's secrets aren't secret. Its production system, which stresses eliminating all wasted material
and labour, has been written about in excruciating detail. NUMMI is proof of this. The plant, which
had operated from 1963 to 1981, had been closed down as it was plagued by labour disputes. Toyota
turned the plant around extra quick. They hired the best of the former workers and created teams of
multi-skilled workers. Absenteeism dropped to less than 2 per cent compared to 20 per cent under the
old management. Productivity at the plant rose to twice the average level at other GM plants. The
Toyota managers achieved this improvement by focusing on five areas:
1. New products were designed for easy assembly and easy modification.
2. Production layout was organized by product needs.
3. Production flow was managed with little or no inventory.
4. Workers shared responsibility for quality.
5. Employees were encouraged to participate in nearly all decisions.
The system improvements did not come from technology investment; it was transformed by how the
managers were able to integrate the different elements into a coherent operations strategy. Even
without much automation, each worker was producing 63 cars a year by 1989, more than any other
US plant and 40 per cent above the average at that time.
Twenty years later in 2004, the company sells 2.1 million vehicles in North America. Today,
NUMMI continues to flourish as a company of 5,000 team members. With Toyota's engineering
content, Toyotas managers transformed an antiquated NUMMI assembly plant into GMs most
efficient factory using what is described as the Toyota Way a corporate philosophy that
empowers employees.
This advocacy role is often in conflict with another real corporate need the need to
have team players that understand and are committed to the corporate mission.
Resolving this conflict to everyones satisfaction is often an art. Operations
Management is also the art of getting work done through people. Box 1.3 is a case
where dramatic changes were obtained by the effective use of software of
operations.
The operations manager is also the supply chain manager/coordinator. In a
manufacturing organization, for example, the manager must view the entire flow of
goods and information within the supply chain, whether this falls within the
corporation's legal boundaries or within that of suppliers and customers outside the
organization.
The operations manager also has duties that involve cross-functional participation
with the business processes in the other three core processes. The most important
non-supply chain business process is the product innovation process. But activities
involving human resource management, accounting, marketing, and R&D processes
also are critical contributors to the operations managers effectiveness.
In fast paced business settings, since operations managers are amongst those closest to
the customer, they can provide quick feedback to the strategic planning process
regarding the changes in the market. Good operations managers are expected to
manage existing business processes while helping get the firm ready for the future.
products faster requires tight integration between the design and Operations 27
Introduction to
Management functions. Initiatives such as simultaneous engineering and early Operation Management
supplier involvement in the product design process not only add to the role of
operations but also improve the perception of value provided in the product and
service concept design process.
In addition, process development and engineering is responsible for production
methods necessary to make the products. This function has a great impact on
operations. Therefore, co-operation between these three functions, i.e., process
engineering, design and operations, leads to improved organizational
performance.
Operations Management Human Resource Interface: No plant manager
anywhere would ignore the role of good people management in running an
efficient operation. The human resource function includes operation's approaches
such as continuous improvement and total quality that rely mainly on human
inputs. Decisions about people and the organization of the operations function
interact significantly with both structural and infrastructural decisions. Such issues
are not unique to the operations function, however; they impact other functions
and are dealt with more effectively through the human resource management
function.
In services, the human resource focus is vital, as customer's perceptions of an
organization are generally formed by their interaction with customer contact
personnel, such as customer service representatives. As organizations increasingly
opt for 'flextime', the operations function has to develop unique process
configurations to accommodate employees with minimum disruption in the flow
of work. Operations Management and Human Resource departments have to
co-operate for recruiting and training employees, enhancing employee well-being
and development, and fostering motivation that are vital to the success of
management policies in practice.
Operations Management Information Systems: Information systems provide,
analyze, and co-ordinate the information needs of operations. The distributed
processing environment and the growth and evolution of Enterprise Resource
Planning (ERP) systems for the organization have a direct impact on operations.
It allows organizations to generate relevant information and make appropriate
information available when needed. The operational plans become the driver of all
business planning including recruiting, cash flows, and marketing promotions.
With Computer Integrated Manufacturing (CIM) systems IT plays a very
important role.
In many organizations, similar activities are performed at different locations or at the
same location by different people. Examples would be a manufacturer with plants
spread out all over the world. However, knowledge is rarely, if ever, shared among
employees performing similar jobs. Information technology provides an option for
managing and sharing knowledge. It dramatically improves the task of managing
knowledge. Advances in process automation allow firms to redefine their core
processes and design better systems to accommodate the needs of product and service
variety. E-commerce creates new demands for managing processes while also
providing new opportunities for reconfiguring them. Much progress in information
technologies is wasted if the operations function does not respond to the challenges
created by the increased availability of information and knowledge.
This approach emphasizes cross-functional thinking and relates it to the context of
overall activities of the organization. Operations Management measures the
effectiveness of people, processes, and technology so that an enterprise can perform
28 better, faster, and with greater productivity. It provides customers with products and
Operations Management
services; and supports corporate strategies by working with marketing, finance and
human resource areas.
Marketplace Challenges
1. Market Fragmentation: Competitive advantage was historically based on
mass-marketing and mass-manufacturing processes. However, this is now
changing. Domestic customers increasingly want their goods and services their
way. The challenge is even greater in marketing goods and services on a global
scale. Organizations will need an increased ability to customize product for local
markets.
2. Vocal Customers: Some customers become increasingly vocal-especially those
with single-issue agendas. Environmental concerns will be voiced loudly.
Recently a single memo from Greenpeace to Gerbers Swiss parent led this
baby-food firm to switch to organic inputs for its product. Similarly, new issues
are cropping up like endangered rain forests, child labour, non-biodegradable
polymers, etc. Privacy concerns will become commonplace as society more fully
understands the extent to which they know all about you.
3. Customer-Supplier Relationship: The customer is increasingly becoming a
partner-often unwillingly. This trend is particularly visible in the service industry.
For example, restaurants will give you a beeper to tell you when you should come
up to serve yourself. This is extending to manufacturing too. This trend is driven
by competition; with new low-cost technologies enabling organizations to provide
added value, and customers demanding value.
4. Disruptive Technologies: Customers, employees, and supply chain players will
become increasingly wired-often via wireless technology. There are numerous
possibilities; global positioning technology will spread quickly, which in turn will
create some interesting employee control/privacy issues; three dimensional bar
coding will greatly enhance the amount of information that can be stored on a
product or workstation; digital image technology will create new norms of
supervision and control; and wireless access to databases will become common.
These are just a few of the possibilities.
between operations and organizations, new process designs will emerge merging 29
Introduction to
the physical flow system, social system, and information system into a Operation Management
self-consistent whole.
2. Employee Diversity: The job of managing an increasingly diverse workforce will
become an even greater challenge. The Operations Management function will
have to figure how to manage an increasingly diverse workforce.
3. Human Resource Scarcity: Businesses will find it increasingly difficult to hire
and keep quality workers. While the number of skilled workers tends to increase,
in an expanding economy, the increase will be insufficient. A shortage of hirable
unskilled workers will continue to plague the service industry. The time has come
to begin viewing employees as a renewable resource, and to keep them as long as
one can.
4. Global Workforce: The location of work and workers will be dramatically
impacted by communication technologies. The output of many service activities
can be done by competent persons residing in lower cost areas of the world.
General Electric moved many of its back office jobs to India, while Boeing is
hiring Russian engineers to design products at its Moscow Engineering Centre.
The Chairman of Hyundai Motors has gone on record that the Korean major in
seriously working towards developing India as a global hub for their auto
components.
5. Declining Raw Material Prices: In the late 1990s, the prices of certain electronic
parts were declining at a rate of 1.5% a month. If this trend continues, deflation
may be a real possibility. It will be a buyer's market that could drastically impact
some supply chain management concepts.
Technological Challenges
1. Technological Change: The challenge of investing in and mastering the right
technologies is a major one. No firm has either the financial or the managerial
resources to engage every new technology. Short product/process life spans mean
that investing firms must recover investments even faster.
2. Bio-genetic: Synthetic and/or animal substitutes will become commonplace in the
form of replacement body parts, foodstuffs, and drugs. On the plus side, advances
in medical health may alleviate some of the more troublesome behavioural
problems in the workplace.
3. Miniaturization: The size of products and processes will continue to become
smaller. Nano-technology is creating a revolution; self-healing garments,
tiny mechanical roto-rooters clean out our bodies, etc. More functions and
remote-control capabilities will be added to the gadgets at home and office.
Societal Challenges
1. Environment: Technologies, to make products more earth friendly, will be
developed. It is already being done to some degree in the product packaging area.
Firms need to realize that there is no way that most businesses will ever satisfy
certain sectors of the environmental movement. Nor do most of their customers
want to forego the conveniences of the products they require. The challenge to
deal effectively with environmental enthusiasts will have to be tackled.
2. Intellectual Property: Protection will lie more with the delivery process rather
than the product. Firms will rely more on industry alliances than governments to
protect intellectual property.
30 3. Financial Reporting: There will be fuller disclosure rules. This will require that a
Operations Management
firm's financial control system should have better and more timely inputs from
operations possibly to stabilize short-term earnings. If that is not possible,
operations managers will need to be able to alert top management whenever there
are significant deviations from the announced financial projections.
Geopolitical Challenges
1. China: Ever since Marco Polo, Western entrepreneurs have dreamt of selling
millions of products to the worlds most populous nation. With a few minor
exceptions, these dreams have remained unfulfilled. Initial sales often are quickly
replaced with Chinese goods since the Chinese have proved themselves to be
particularly adept in adopting new technologies. China's rising industrial base will
result in major economic changes as it will not be willing to remain solely as the
source of low-cost, labour-intensive products.
2. Japan: Even though Japan's economic problems seem intractable, it remains a
formidable manufacturing threat. Toyota continues to extend its manufacturing
advantage as it hones its ability to make vehicles desired by Americansat the
expense of Detroits Big Twos market share. This will extend into other areas of
business too.
3. India: With a GDP growth approximating 7 per cent, India is emerging as a
potential economic power. The growth today is based on the availability of skilled
labour. The country is progressing into higher value added products in areas such
as software development, biotechnology and pharmaceuticals. However, in the
long run, as a source of semi-skilled and unskilled labour, India will provide a
competitive advantage in the global marketplace.
New research by the McKinsey Global Institute indicates that the introduction of
foreign competition in IT, business-process outsourcing, and the automotive industry
has forced Indian companies to revamp their operations and boost productivity, and
some have become formidable global competitors. Thousands of new jobs have been
created in these industries. Consumers benefit from lower prices, better quality, and
from availability of a wider selection of products and services.
India has demonstrated to the world that the country is a credible off-shoring
destination. There are legions of trained local workers, and the skills of Indian
companies are established. Indian outsourcing firms now control over half of the
intensely competitive global IT and back-office outsourcing market.
Now that China has been admitted to the WTO, India is losing low-cost jobs.
However, with its bio-diversity, the country will be one of best sources of biological
materials. Unfortunately, the country has not advanced sufficiently in its economic
infrastructure which is the new area of focus of the Government. India can take full
advantage of its competitive advantage, by greatly expanding its investment in human
resources. If it continues to integrate itself into the global economy, India should
provide intense competition in many areas to world class companies from the
developed economies.
33
1.10 LESSON END ACTIVITIES Introduction to
Operation Management
1. Students should select at least two organizations they are familiar with. One of
these organizations should be involved in providing a tangible product and the
other an intangible product. They should draw out the transformation process to
the inputs and show what the outputs are, and what is involved in the
transformation process. How is value added?
2. Explain the important issues with transformation. Take a hospital, say Apollo
Hospital, and explain the conversions taking place. What are the hospitals overall
objectives of the operations systems and how does the hospital achieve it?
1.11 KEYWORDS
Clock-speed: It is an important attribute for it defines how fast a firm, or parts of a
firm, must respond to change, to competitive threats, and other organizational
challenges.
Scientific Management: It was a set of principles postulated by Frederick Winslow
Taylor. The principles of scientific management were: scientific laws govern work, so
scientific methods can be used to analyze work; workers are different, so match
workers to their job and then train them thoroughly; use employee self-interest to
motivate and separate the responsibilities of workers and managers.
Time and Motion Study: It is an analysis of the operations required to produce a
manufactured article in a factory, with the aim of increasing efficiency. Each
operation is studied minutely and analyzed in order to eliminate unnecessary motions
and thus reduce production time and raise output, which increases productivity.
Operations Research (OR): Operations research is the application of scientific
methods to improve the effectiveness of operations, decisions and management, by
means, such as analyzing data, creating mathematical models and proposing
innovative approaches.
Operations Management constitutes all activities that an organization conducts in
order to deliver value to its customers. Its the set of processes that transforms either
materials or information into a product or service.
Goods: These are tangible items that are usually produced in one location and
purchased in another. They can be transferred from one place to another and stored for
purchase by a consumer at a later time.
Services: Services are intangible products that are consumed as they are created.
Direct customer contact is a key characteristic of services.
CYP 1
1. False
2. False
3. True
4. False
5. False
CYP 2
1. True
2. True
3. False
4. True
35
LESSON Types of Production Systems
2
TYPES OF PRODUCTION SYSTEMS
CONTENTS
2.0 Aims and Objectives
2.1 Introduction
2.2 Production Systems
2.3 Types of Production Systems
2.3.1 Project
2.3.2 Job Shop
2.3.3 Batch Production (Disconnected Line)
2.3.4 Assembly Line
2.3.5 Continuous Flow
2.3.6 Cell Manufacturing (Group Technology)
2.3.7 Flexible Manufacturing Systems (FMS)
2.4 Production System and its Environment
2.5 Let us Sum up
2.6 Lesson End Activity
2.7 Keywords
2.8 Questions for Discussion
2.9 Suggested Readings
2.1 INTRODUCTION
The study here suggests a set of potential profiles for different types of production
systems and manufacturing strategies and deals with the contingency framework that
links production systems to manufacturing strategies. Specifically, an explicit
conceptual link is drawn between generic manufacturing strategy that uses two
dimensions of strategy (cost efficiency and differentiation) and the complementary
production system typology in manufacturing that uses technical complexity and
technical flexibility. Proposed production systems are intermittent production
37
2.3 TYPES OF PRODUCTION SYSTEMS Types of Production Systems
2.3.1 Project
These are generally one-off projects. It is based on extensive customisation that is
suited to the customer's need. Many construction projects, project management
contracts, shipbuilding and civil engineering projects fall in this category.
For example, Larson and Toubros main business is executing projects. Much of the
work is carried out at site rather than in a factory. All equipment, tools, materials,
labour, etc., are placed at the site itself. Infosys sends its teams to the customer's
facilities to install, test, and customize its software.
2.7 KEYWORDS
Flexible Manufacturing System: It is a manufacturing system that consists of a
number of CNC machine tools and a materials handling system that is controlled by
one or more dedicated computers.
Manufacturing Flexibility: It is the ability of a manufacturing system to respond, at a
reasonable cost and at an appropriate speed, to planned and unanticipated changes in
external and internal environments.
Mix Flexibility: The ability of a system to present a wide range of products or variants
with fast set ups.
Changeover Flexibility: The ability of an OM system to introduce a large variety of
major design change quickly within existing facilities.
Modification Flexibility: The ability of the transformation process to implement
minor product design changes, quite possibly after the product has been delivered.
Volume Flexibility: The ability of the transformation process to profitably
accommodate variations in production quantities. Systems with high fixed costs beget
inflexibility since the firm will always be striving to maintain high utilization rates.
CYP 2
1. True
2. True
3. False
4. False
5. True
43
Product and Product Design
UNIT II
44
Operations Management
45
LESSON Product and Product Design
3
PRODUCT AND PRODUCT DESIGN
CONTENTS
3.0 Aims and Objectives
3.1 Introduction
3.2 Typology of Products
3.3 Product Development Process
3.3.1 Clarification of the Task
3.3.2 Concept Generation
3.3.3 Embodiment Design
3.3.4 Detailed Engineering Design
3.3.5 Physical Evaluation
3.3.6 Speed of Product Development
3.4 Product Design and Architecture
3.4.1 Product Architecture
3.4.2 Engineering Economy
3.4.3 Measuring Costs and Identifying Waste
3.4.4 Design for Manufacturability (DFM)
3.4.5 DFX Design for X
3.4.6 End Product and Parts Standardization
3.4.7 Modular Designs
3.5 Product Development in Services
3.6 Product Development Strategies
3.6.1 Internal Development
3.6.2 Reverse Engineering
3.6.3 Collaborative Development and Contracted Out R&D
3.6.4 Joint Ventures
3.6.5 Producer-customer
3.6.6 Manufacturing Sub-contracting
3.7 Types of Production System
3.7.1 Job Shop Production
3.7.2 Batch Production
Contd
3.1 INTRODUCTION
Product decisions often make or break companies. Studies indicate that nearly two out
of three new products fail after launch. In addition, companies in many sectors are
under continual pressure to speed up the pace of product development even to adapt
products that are still in the pipeline to the demands of a constantly changing
marketplace. This lesson will discuss product design and process selection, which are
crucial areas in operations management.
hotels, hospitals, law offices, educational institutions, and public utilities. They 47
Product and Product Design
provide such services as a restful and satisfying vacation, responsive healthcare, legal
defense, knowledge enrichment, and safe drinking water.
Services also include back-office support for internal customers of an organization,
such as IT support, training, and legal services. Services take place in direct contact
between a customer and representatives of the service function.
Customer contact is a key characteristic of services. A high quality of customer
contact is characteristic of a good service organization. This is vital to retain current
customers as well as for attracting new ones. Most service organizations though they
seldom carry finished inventory do have supporting inventory. Hospitals keep drugs,
surgical supplies, emergency supplies and equipment spares; Banks have forms,
cheque books, and other supplies.
Contracts are business exchanges in which neither services nor goods are transferred;
instead, there is an implicit understanding between the customer and the provider that
goods and services will be provided on an as needed basis. With a contract, the
customer pays a fee and then is entitled to a manufactured goods or services. Many
goods and services are now evolving into contracts.
Historically, manufacturing organizations have operated tertiary and often secondary
activities on contracts. Today, increasingly, many businesses are moving to contract
based transactions. For example, Internet and Applications Service Providers (ASPs);
security organizations; maintenance, healthcare and many other businesses design
their operations based on contracts.
Service and contracts require more attention and better planning than manufacturing.
A manufacturing defect can always be reworked before dispatch. Service, however,
occurs in the presence of the service provider, making it difficult to manage capacity
and control quality since inventory cannot be stored and inspected prior to the service
encounter. Contractual transactions can be even more complicated. The complication
arises because it is difficult to enhance capacity overnight and all customers may
choose to exercise their options at the same time.
Many recent thinkers have suggested that most manufacturing firms are better off
thinking of their output in terms of the service bundle they provide to the customer.
For example, Mercedes has announced that it is developing a system that will connect
the cars software via the Internet to a customer assistance center. This system will be
able to detect, diagnose and repair the problem.
Another example is Xerox. It has redefined its product as facilitating
communications rather than just selling copy machines. In its strategy to be the
Document Company, Xerox now offers products that can copy handwritten
documents, convert them to electronic form, and e-mail them. Such products have
allowed Xerox to increase the services related to document management in its output
bundle. This type of transition creates significant challenges for Operations
Management.
Today, increasingly organizations are trying to grow their presence in the market and
earn a competitive edge over competition by mixing goods, services and contracts.
This brings in a number of permutations and combination, significantly changing the
landscape of operations.
Inventory Products can be stored Services are consumed Many operations can be
for later consumption. as they are created. conducted off-line, or
not in the presence of the
customer.
Table 3.1 summarizes some key differences and operational consequences among
goods, services, and contracts across several factors that shape operational decisions in
organizations.
49
3.3 PRODUCT DEVELOPMENT PROCESS Product and Product Design
50 Based on this exercise the general specifications of the product or service are
Operations Management
drawn up.
The product idea must demonstrate that it fulfills some consumer need, and that
existing products do not already fulfill.
52 and the response to different stress patterns seen visually on the computer screen,
Operations Management
without building a physical prototype.
53
3.4 PRODUCT DESIGN AND ARCHITECTURE Product and Product Design
The first step in developing a new product strategy is that the organizations should
decide their target customers, what they value, and the likely size of the market of
their interest. These are key inputs to make product architecture decisions.
Raw Materials
Labor
Manufacturing System Finished Goods
Purchased
Components
As a rule of thumb, 70 percent of the cost of the product or service is firmed up by the 55
Product and Product Design
time the conceptual design has been completed. By the time the system definition is
completed 80 percent of the cost is finalized and 90 percent of the cost is firmed up
before production. For example, the geometrical shape of a part or assembly
determines the subsequent manufacturing processes by which it may be manufactured.
This, in turn, limits the materials to just those few that are suitable for those processes.
Source: M Lilienthal, Defence Modelling and Simulation Office, Observations on the use of Modelling and
Simulation, 2003.
flexibility and quality will not enhance a firms competitiveness in the long run. For 57
Product and Product Design
example, a firm that uses cheaper material that reduces quality to lower cost may save
money in the short term. However, over the long haul they reduce the ability of the
firm to deliver a product consumers value. They may buy the product once, but not
thereafter.
Design-to-cost: Factor costs, scale effects, and productivity differentials should not be
the only criteria for design decisions. Perhaps the greatest of all scope for
improvement lies in design-to-cost. This means cost is taken as a basis for the final
design decision.
This technique requires the organization to have experience in systems optimization
and good knowledge of the manufacturing processes involved. Often the supplier has
this knowledge. For example, the amount of costly platinum needed for an automotive
catalytic converter used by BMW was considerably reduced when a suppliers
experience in flow optimization was applied at an early stage of development.
Exchanges of experience between manufacturer and supplier often bring to light
unexpected opportunities for making improvements. One German manufacturer sent a
standard part to Japan for redesign and a comparative quotation, and initially had its
expectations confirmed: the Japanese supplier could deliver around 30 percent
cheaper.
The German manufacturer was surprised at the second attempt, when it sent a much
more complex part for development. The Japanese supplier was some 18 percent more
expensive than the company itself, despite the redesign. A closer look at the Japanese
suppliers redesign explained the results. On its own, the complex part offered hardly
any optimization opportunities, being interconnected with too many other
components.
By optimizing the total system redesign and fresh development of all the
components, the Japanese supplier revealed the full potential for cost reduction. Once
the costs of the optimization had been properly allocated to the total system, the
Japanese alternative proved to be more cost-effective in the long term than in-house
development had been.
Proposed Design
Estimate the
Manufacturing Costs
Recompute the
Manufacturing Costs
N Good
enough?
Acceptable Design
cross-functional experts. The performance measures are established and items are 59
Product and Product Design
identified that will simplify the process and at the same time provide value to the
customer.
An example is of Escorts Ltd., a company that was making heating elements for
electrical kettles. The holder that screwed on the element to the kettle was made as a
casting. The casting had to be pre-machined, sized, cut and turned before it was ready
for threading.
The technical requirements were not critical, as the function of the part was to protect
the consumer from contact with the electrical contacts and guide the external socket to
the corresponding part of the heating element. Standard tubes were found that met the
dimensional requirements for the component. This greatly simplified the process,
avoided a number of operations, reduced the number of parts, and also reduced costs.
Equipment Indirect
Standard Custom Labor Support
and Tooling Allocation
The key to successful product development is to know what features or parts of the 61
Product and Product Design
end product need to be customized to meet the expectations of the target customers.
Check Your Progress 2
State whether the following statements are true or false:
1. Engineering economy is the discipline concerned with the economic
aspects of engineering.
2. Economies of scale occur when product design costs are spread over a
large volume.
The risk in such ventures is low. It has other advantages of licensing agreement. The
disadvantage of technology absorption is largely removed. Due to the ongoing
relationship between the companies, the opportunity to learn on both sides exists.
However, the disadvantage is that neither partner can make decisions on their own.
Joint ventures have been a major source of technology acquisition in developing
countries. For example, Escorts Limited had a joint venture with JCB of the UK to
manufacture small excavators. Escorts again, entered into a joint venture with Hughes
Communications of USA for manufacture of communication equipment.
3.6.5 Producer-customer
This is normally done in the form of buying a piece of production machinery with
embedded technology. This is perhaps the quickest form of technology transfer
because the technology is already packaged and ready to use. It is low risk because the
equipment has been proven to work technically and evidence can be acquired from
other users to back-up the producers claims. In addition, the producer normally would
be glad to provide implementation support in the form of setting up the machine and
in the training of personnel.
66
Operations Management 3.7 TYPES OF PRODUCTION SYSTEM
Production systems can be classified as Job Shop, Batch, Mass and Continuous
Production systems.
Characteristics
The Job-shop production system is followed when there is:
1. High variety of products and low volume.
2. Use of general purpose machines and facilities.
3. Highly skilled operators who can take up each job as a challenge because of
uniqueness.
4. Large inventory of materials, tools, parts.
5. Detailed planning is essential for sequencing the requirements of each product,
capacities for each work centre and order priorities.
Characteristics
Batch production system is used under the following circumstances:
1. When there is shorter production runs.
2. When plant and machinery are flexible.
3. When plant and machinery set up is used for the production of item in a batch and
change of set up is required for processing the next batch.
4. When manufacturing lead time and cost are lower as compared to job order
production.
Characteristics 67
Product and Product Design
Mass production is used under the following circumstances:
1. Standardization of product and process sequence.
2. Dedicated special purpose machines having higher production capacities and
output rates.
3. Large volume of products.
4. Shorter cycle time of production.
5. Lower in process inventory.
6. Perfectly balanced production lines.
7. Flow of materials, components and parts is continuous and without any back
tracking.
8. Production planning and control is easy.
9. Material handling can be completely automatic.
Check Your Progress 3
Fill in the blanks:
1. is a form of contractual arrangement.
2. Consulting Engineering Firms are often a source of ..
3. .. have been a major source of technology acquisition in
developing countries.
Characteristics
Continuous production is used under the following circumstances:
1. Dedicated plant and equipment with zero flexibility.
2. Material handling is fully automated.
3. Process follows a predetermined sequence of operations.
4. Component materials cannot be readily identified with final product.
5. Planning and scheduling is a routine action.
68 Product design provides the operations team the basis for preparing plans for:
Operations Management
(a) Materials acquisitions, and (b) Production.
Once the product is introduced, the organization needs to monitor customer
satisfaction and detect product weaknesses so as provide feedback to the design team.
Concurrent engineering approach is to speed up the product development process.
With an integration team ensuring the exchange of information between the teams
working on different aspects, it is possible to considerably reduce development times
and create high quality product designs that meet customer expectations.
As a rule of thumb, 70 percent of the cost of the product or service is firmed up by the
time the conceptual design has been completed. By the time the system definition is
completed 80 percent of the cost is finalized and 90 percent of the cost is firmed up
before production.
Product architecture, therefore, is extremely important as it establishes the functional
capabilities of the product, its features, and post-sale servicing needs, the capabilities
of the product delivery system and post-sale support that the customer expects and
determine the ability of the organization to provide for these, and the roles and risks
each player within the supply chain will assume.
Some concepts related to good product design and architecture are Design-to-cost,
Design for Manufacturability, Design for X, End Product and Parts Standardization,
and Modular Designs.
Services, with a low degree of customer contact, involve the same stages as the design
of manufactured products. However, services with a high degree of customer contact,
normally require a much higher levels of capacity relative to demand and also require
greater flexibility.
Different strategies are employed in product development. These are Internal
Development, Collaborative or R&D with Networking, R&D Contract/Consulting
Engineers, Licensing, Joint Venture, Manufacturing Sub-contract/Producer-customer,
Acquisition of a Company with Technology and Reverse Engineering.
3.10 KEYWORDS
Products are artifacts that provide value to the customer. They can be tangible or
intangible.
Goods are tangible items that are usually produced in one location and purchased in
another.
Services are intangible products that are consumed as they are created.
Contracts are business exchanges in which neither services nor goods are transferred;
instead, there is an implicit understanding between the customer and the provider that
goods and services will be provided on an as needed basis.
The Product Lifecycle model is a simplistic representation of the cumulative impact
of changes in the business environment on the life of a manufactured product.
Technological Life Cycle is a representation of the cumulative impact of changes in
market growth and technology.
70 4. What are the steps and stages of product development? Is it possible to reduce the
Operations Management
time and the number of stages and come out with a new product and service? Give
details of procedures and techniques.
5. Differentiate between fixed costs and variable costs and explain how they help in
determining the breakeven point.
6. Explain the following in relation to new product development:
(a) Standardization
(b) Simplification
(c) Speed to Market
(d) Activity based Costing
(e) Value Engineering
(f) Modular Design
7. How does Design for Manufacturability (DFM) work? How are DFM and Value
Engineering different? Explain with examples.
8. Work out the design of any simple object of your choice using the Principles of
DFM?
9. How do product development strategies relate to the other organizational
strategies (i.e. competitive and functional)? What is the difference between single
and multi-business organizations? Provide examples.
CYP 2
1. True
2. True
CYP 3
1. Licensing
2. technology
3. Joint ventures
72
Operations Management
LESSON
4
OPERATIONS TECHNOLOGY AND
FACILITY LOCATION
CONTENTS
4.0 Aims and Objectives
4.1 Introduction
4.2 Growing Importance of Evaluation and Selection of P&O Technology
4.3 Selection of Technology
4.3.1 Technology Compatibility
4.3.2 System Impact of Technologies
4.3.3 Technology Readiness
4.3.4 Technology Development and Uncertainty
4.3.5 Technology Forecasting
4.3.6 Bounding Technological Uncertainty
4.3.7 Uncertainty in Forecasting a Technology
4.3.8 Technology Evaluation
4.3.9 Deterministic Evaluation
4.3.10 Technology Sensitivities
4.3.11 Probabilistic Evaluation
4.3.12 Technology Frontiers
4.3.13 How will the Technology Frontier Change for Different Levels of
Confidence?
4.3.14 Resource Allocation
4.4 Technology Identification, Evaluation and Selection Method
4.5 Need for a Facility Location Planning
4.6 Nature of Location Decisions
4.7 Factors affecting Location Decisions
4.7.1 Factors affecting Manufactured Products
4.7.2 Factors affecting Service Products
4.8 Selection of Site for the Plant
4.8.1 Country
4.8.2 State/District
4.8.3 Plant Location
Contd...
4.1 INTRODUCTION
The management is often faced with the problem of selecting a new site for locating a
new production facility or a new warehouse. Very often the cost of transportation of
inputs and outputs to the processing units or the marketplace are critical parameters.
In such cases, the transportation method can be used in finding out the lowest cost
location insofar as the location factors can be quantified.
Every industry has become dynamic, growth-oriented, and a major contributor to the
strength of the economy in the evolving global competitive environment.
Characterized by firms of various sizes working in a competitive and quickly
changing environment, each particular industry offers fertile ground for investigating
changes that are currently taking place in small business management. One important
domain of management is the selection and evaluation of suppliers. This lesson
explores the techniques currently used to select and evaluate production and operation
technology in a sample of small and large firms in any industry.
74 have become even more critical (Abegglen and Stalk, Jr. 1985). The increasing
Operations Management
adoption of just-in-time (JIT) manufacturing practices has placed a new emphasis on
supply base reduction, making the processes of the selection and evaluation of
suppliers increasingly critical. Even many firms without a formal implementation of
JIT manufacturing are in the process of supply base reduction (Emshwiller 1991).
Supply base reduction involves a longer time commitment to suppliers on the part of
buyers. This commitment usually brings greater interaction between the buyer and
supplier which may lead to a sharing of resources. Resource sharing may involve
training and development in an effort to improve quality, reduce costs, and emphasize
continuous improvement in all areas of interaction (Watts and Hahn 1993). The
strategy of involving suppliers early in the product design, has become more important
in the era of global competition.
78 application (i.e., TRL=9). As more information and data becomes available, the
Operations Management
forecast should be updated and re-evaluated.
Based on this rationale, the uncertainty, or confidence limits, may be bound based on a
logical reasoning and with the method of analogy to what should happen as a
technology program progresses without any unforeseen problems. For example, one
may assume that a successful technology program develops along a linear trend. Point
A represents a technology in the infancy stage of development, TRL=2. The desired
capability of the performance improvement is Point D and is assumed to be the
expert defined impact when a TRL of 9 is reached.
80 technology impacts on the system are probabilistic. Thus, information regarding the
Operations Management
different metric CDFs may be lost in the down select process and include the
variability that is associated with a given mix of technologies. As a simplified solution
the limitations, one could select the top alternatives for different confidence levels and
weighting scenarios. Once the top alternatives are determined, the results may be
compared to conclude if any combinations consistently rank in the top ten or so,
regardless of confidence level. Although this is a simple approach, visualizing the
impact of uncertainty of the top alternatives is not necessarily intuitive. One should
note that the results of the top alternatives for different confidence levels might not be
identical due to the fact that the distribution variance for each technology alternative
changes. The variance is driven by the uncertainty associated with an immature
technology (low TRL) and increases when more technologies are added. Finally, the
numerical values obtained from the ranking of alternatives are not intuitive to the
decision-maker, especially for visual representations. Thus, additional selection
techniques are suggested to aid in the decision-making process.
4.3.13 How will the Technology Frontier Change for Different Levels of
Confidence?
Technology Evaluation, assessing a technology combination without uncertainty
yields the theoretical limit of the technology impact. Similarly, different frontiers may
be established for different confidence levels.
To identify the technology alternatives that may satisfy the customer requirements, or
criteria, effectiveness thresholds should be established. An effectiveness threshold
defines how much improvement is needed from each criterion to create a feasible
space.
The technology alternatives that fall within this region are easily identified and may be
investigated in further detail. If no alternatives fall within this region, then no
technology combinations can meet the imposed customer requirements. Yet, the 81
Operations Technology and
combinations that come closest to the feasible region may be readily identified. The Facility Location
decision maker may re-evaluate the development schedule of the three technologies to
determine if costs savings can be achieved. The technology frontiers provide a rapid
and visual means of selecting a family of feasible alternatives while including
technological uncertainty via multiple frontiers.
82 The potential applications of the TIES method are numerous. The steps required for
Operations Management
implementation are generic such that any complex system could be analyzed.
However, the basic requirements for application of TIES include the ability to identify
a set of customer requirements for which the system may be judged as successful or
not. Further, a Modeling and Simulation (M&S) environment in some capacity must
exist whereby the customer requirements can be quantitatively assessed. Finally, the
technologies to be infused to the system must be quantifiable in the M&S
environment. The remaining steps are not specific to any class of systems or vehicles
and the TIES method could be applied to a wide-range of complex systems including
missiles, torpedoes, ships, power generators, automobiles, telecommunication
systems, and the list could go on indefinitely although a few procedures described
may have to be modified for the problem of interest.
One final comment should be made regarding a validation of the TIES method. The
likelihood of entire method being validated is minute. To validate the entire method,
one would have to obtain the data and information regarding the decisions,
configurations, and technology options throughout an existing system. Unfortunately,
most companies do not retain the detailed information regarding previous designs and
how the development process evolved from concept formulation to product launch.
Types of Facilities
The various types of facilities are briefly described below:
Heavy Manufacturing
Heavy manufacturing facilities are primarily plants that are relatively large and require
a lot of space and as a result, are expensive to construct.
Example: Automobile plants, steel mills and oil refineries.
Important factors in the location decision for plants include construction costs, modes
of transportation for shipping heavy manufactured items and receiving bulk shipments
of raw materials, proximity to raw materials, utilities, means of waste disposal and
labour availability. Sites for manufacturing plants are normally selected where
construction and land costs can be kept at a minimum and raw material sources are
nearby in order to reduce transportation costs. Access to rail-roads is frequently a
major factor in locating a plant. Environmental issues have increasingly become a
major factor in plant location decisions. Plants can create various forms of pool
pollution and traffic pollution. These plants must be located where the harm to the
environment is minimised. Although proximity to customers is an important factor for
some facility types, it is less so for manufacturing plants.
Light Industry
Light industry facilities are typically perceived as smaller, cleaner plants that produce
electronic equipment and components, parts used in assemblies, or assembled
products.
Example: Making stereos, TVs, or computers, tool and die shop, breweries, or
pharmaceutical firms.
84 Several factors are important for light industry. Land and construction costs are not
Operations Management
generally as crucial, because the plants tend to be smaller and require less engineering.
It is not as important to be near raw materials, since they are not received in large bulk
quantities, nor is storage capacity required to as great a degree. As a result,
transportation costs are somewhat less important. Many parts and material suppliers
fall into this category and as such, proximity to customers can be an important factor.
Alternatively, many light industries ship directly to regional warehouses or
distributors, making it less important to be near customers. Environmental issues are
less important in light industry, since burning raw materials is not normally part of
their production processes, not are there large quantities of waste. Important factors
include the labour pool, especially the availability of skilled workers, the community
environment, access to commercial air travel, government regulation and land use
requirements.
Ideally, the design progresses from global to sub-micro in distinct, sequential phases. 85
Operations Technology and
At the end of each phase, the design is 'frozen' by consensus. Moving in a sequential Facility Location
manner helps management in the following manner:
Settling the more global issues first.
It allows smooth progress without continually revisiting unresolved issues.
It prevents detail from overwhelming the project.
Based on strategic importance, the macro layout is accepted to be the most critical and
strategically important aspect of facility planning. However, all the stages have their
own importance and significance.
Table 4.1: Facility Planning Matrix
Level Activity Space Planning Unit Environment
Global Site Location & Sites World or Country
Selection
Macro Site Planning Site Features, and Site and Building Concept
Layout Departments
Micro Layout Facility, Building Buildings, Workstations Plant or Departments
and Factory Layout Features
Sub Micro Workstation & Cell Tool & Fixture Locations Workstation & Cells
Layout Design
Many countries, like China and India, are turning out to be attractive locations for 87
Operations Technology and
industries that require large contingents of unskilled labour. Facility Location
Though, this is often very appealing, you need to bear in mind that conditions can
change in time. For example, while labour costs may be low in a certain
geographic location now, this will change if the demand for labour grows
significantly.
In considering the labour supply, the following points should be considered:
Skills available size of the labour force productivity levels.
Unionization prevailing labour management attitudes.
History of local labour relations turnover rates absenteeism, etc.
Some organizations have relocated from a high skill/high cost area to a low
skill/low cost area without any decrease in productivity. Sometimes it has been
due to skill availability and labour-management relations but often it has been the
result of higher investment in mechanization.
Location of other Plants and Warehouses: Organizations need to look at their
plant locations for the complete system point of view:
Distribution and supply requirements require the support of sister-plants and
warehouses that complement the system.
The system should be designed to minimize total system costs.
The locations of competitor's plant and warehouses must also be considered
(what do they know, that you don't) the object being to obtain an advantage in
both freight costs and the level of customer service.
Climate: The recent typhoons in the Gulf of Mexico have indicated the need to
look at climatic conditions as a parameter for making location decisions.
Example: Petrochemical plants near Houston were seriously threatened by
Hurricane Katrina.
Japan has seismic regions that could be extremely risky for large fixed
investments in products that are hazardous or dangerous or uses raw materials or
produces by products that may have similar impacts.
Governmental Controls and Regulations: Table 4.2 shows the composite ranking
of the business environment in 20 countries, based upon factors including
government controls, regulations and incentives and labour conditions. Labour
conditions include skills, availability, unionization and history of labour relations.
Table 4.2: Ranking of the Business Environment in 20 Countries, 1997 -2001
1 Netherlands 11 Finland
2 Britain 12 Belgium
3 Canada 13 New Zealand
4 Singapore 14 Hong Kong
5 U.S. 15 Austria
6 Denmark 16 Australia
7 Germany 17 Norway
8 France 18 Ireland
9 Switzerland 19 Italy
10 Sweden 20 Chile
88 In another ranking, this time by the World Bank in their 'Doing Business in 2006'
Operations Management
ratings, India was ranked 116 out of the 155 countries in the listing. New Zealand was
number one, closely followed by Singapore. According to this report, starting a
business in India requires 11 procedures and around 72 days, the highest in the Asian
region. Business in India requires 20 procedures. In 'rigidity of employment' that
relates to hiring and firing people, India ranks 62 on an index of 100. Around
40 procedures and 425 days are required for a contract. Also, taxes must be paid 59
times during the year.
Tax regulations, environmental regulations or various other kinds of government
policies and regulations can be important factors in the location decision. There may
be a more favourable investment climate in a particular geographical or political
region that may attract industry to invest in that region.
89
4.8 SELECTION OF SITE FOR THE PLANT Operations Technology and
Facility Location
When we see on the television news or read in the newspaper that a company has
selected a site for a new plant, the decision can appear to be almost trivial. Usually, it
is reported that a particular site was selected from among two or three alternatives and
a few reasons are provided such as good community or available land. However, such
media reports conceal the long, detailed process for selecting a site for a major
manufacturing facility.
Example: When General Motors selected Spring Hill, Tennessee, as the location for
their new Saturn Plant in 1985, it culminated a selection process that required several
years and the evaluation of hundreds of potential sites.
When the site selection process is initiated, the pool of potential locations for a
manufacturing facility is, literally, global. Since proximity to customers is not
normally an important location factor for a manufacturing plant, countries around the
world become potential sites. As such, the site selection process is one of gradually
and methodically narrowing down the pool of alternatives until the final location is
determined. In the following discussion we identify some of the more important
factors that companies consider when determining the district, region, state and site at
which to locate a facility.
4.8.1 Country
Until recent years companies almost exclusively tended to locate within their national
borders. This has changed somewhat in recent years as US companies began to locate
outside the continental United States to take advantage of lower labour costs. This was
largely an initial reaction to the competitive edge gained by overseas firms, especially
Far Eastern countries, in the 1970 and 1980. US companies too quickly perceived that
foreign competitors were gaining a competitive edge primarily because of lower
labour costs. They failed to recognise that the real reason was often a new managerial
philosophy based on quality and the reduction of all production related costs. High
transportation costs for overseas shipping, the lack of skilled labour, unfavourable
foreign exchange rates and changes in an unstable government have often combined to
negate any potential savings in labour costs gained by locating overseas. Ironically,
some German companies, such as Mercedes-Benz, are now locating plants in the
United States because of lower labour costs. An overseas location is also attractive to
some companies who need to be closer to their customers, especially many suppliers.
The next stage in the site selection process is to determine the part of the country or
the state in which to locate the facility.
In India the Western and Central regions are generally most preferable and the Eastern
region is least preferable for manufacturing facilities. This reflects a general migration
of industry from the Eastern to the Western and Central regions during the last two
decades primarily due to labour relations. The factors that influence in what part of the
country to locate are more focused and area-specific than the general location factors
for determining a country.
4.8.2 State/District
The site selection process further narrows the pool of potential locations for the
facility down to several communities or localities. Many of the same location factors
that are considered in selecting the country or region in which to locate are also
considered at this level of the process.
91
4.9 PROCEDURES FOR LOCATION DECISIONS Operations Technology and
Facility Location
At macro level, the plans of the site are developed. These plans should include
number, size and location of buildings. It should also include infrastructure such as
roads, rail, water and energy. Planning of this stage has the greatest strategic impact
on the facility planning decision. This is the time to look ahead and consider the
different impacts and site and plant expansions leading to the eventual site saturation.
Planning at the macro level stage should include the following:
Development of a facility master plan to guide facility investments over a
multi-year period
Impact planning
Evaluation
Facility layout, space allocation and capacity
Development of space standards.
92 The master planning team's work is broadly divided into two phases: Phase I deals
Operations Management
with information gathering and analysis. Phase II addresses the synthesis of gathered
information into the development of a master plan.
In addition, the topography, soil mixture and drainage must be suited to the type of 93
Operations Technology and
building required. The soil must be capable of providing it with a proper foundation. Facility Location
It should not be a low-lying area. Ingress of excess water during monsoons should not
disturb operations. Land improvements or piling and concrete rafting to provide
protection and the required strength to the foundations always prove expensive. Even
when the price of land is low, it may not prove to be economical to build on such sites.
In India we have laws to protect the air, water, and ground. Both air and water are
impacted by the wastes that are produced and the manner in which wastes are
disposed of. Will the plant be situated in a smoke-free zone? Can water and oil be
discharged directly or must it be transported from the plant? What local agencies are
available to provide solutions?
Recently there were news reports that oil seepage from an oil storage depot of Indian
Oil Corporation in Bihar, had found its way into the water table. Water supply in the
area has become unfit for human consumption. This raises questions of various threats
to the environment from factory operations.
The legal requirements of the Government of India and the types of impacts that need
to be controlled to meet environmental and local laws include the following:
Air pollution
Water pollution
Waste treatment
Solid waste disposal
Hazardous chemicals
Disposal of sludge
Noise
Dust
Radiation
Toxic chemicals
Industrial accidents
Chemical or fuel spills
Box 4.1: Infrastructure for Environmental Requirements
Questionnaire
This identifies a number of services and features that may be linked to infrastructural requirements of
the unit. Who provides or is responsible for the following services, tools or actions?
1. Industrial Estate Authority
2. Operational Units
3. Government Authority
4. Private Sector
5. Others
1 2 3 4 5
Energy
Centralized energy supply o o o o o
Individual energy supply o o o o o
Supply and recovery of waste heat (cogeneration) o o o o o
Contd
96 network serving the local community. The plant should also be easily accessible
Operations Management
by car and public transport.
Intangible factors to consider include the reliability and network of the available
carriers, the frequency of service, and freight and terminal facilities, and distance
from the nearest airport. These can reflect on the cost and time required to
transport the finished product to market and raw materials to the plant. They may
also impact on the time required to contact or service a customer. These are
important issues that must also be considered.
4. Land Costs: These are non-recurring costs and of little importance in the
determination of the facility location. In general, the plant site will be one of the
following locations: city location; industrial areas or estates; or interior areas.
Locating an establishment can be in a (a) city, (b) industrial estate or industrial
area, or (c) at a greenfield location. Each option has advantages and
disadvantages. The criteria for choosing each of these locations are given above:
City Location:
Availability of high proportion of highly skilled employees.
Fast transportation or quick contact with customers and suppliers.
Size of plant often a limitation, small plant sites or multi-floor operations.
Transportation of large variety of materials and supplies possible, but
usually in relatively small quantities.
Urban facilities and utilities available at reasonable rates.
Possible to start production with a minimum investment in land,
buildings, etc., as these can usually be rented.
Industrial Estates/Industrial Areas:
Limitations in locating close to employee's homes.
Often provided exemptions from high taxes.
Freedom from strict city building and zoning restrictions.
Infrastructure often not a major concern.
Environmental concerns can be met at minimum cost outlay.
The site should be close to transportation and population.
Interior Greenfield Location:
Large land requirement.
Suitable to production processes/product which are dangerous or
objectionable.
Requirement for large volumes of relatively pure water.
Often provided exemptions from high taxes.
Limited availability of highly skilled employees.
Need to invest in infrastructure and housing.
Plant location analysis is a periodic task. Management should recognize that
successful businesses are dynamic. A location may not remain optimal forever.
Check Your Progress 3 97
Operations Technology and
1. List some plant specific factors. Facility Location
.
.
2. Facility master planning strategy involves:
.
.
Jammu gets very high scores in government regulations, ability to expand, and impact
analysis. Government offers incentives relating to exemption of sales tax and lower
income taxes in Jammu. As the promoters are based in Jammu, their ability to acquire
assets to expand is going to be easier in Jammu. As the level of industrialization in
Jammu is low, the level of the investment in clean technologies is expected to be low
as the base levels of pollution are low.
Chandigarh gets very high scores both on ability to expand and availability of required
land. This is because the company already owns sufficient land at Chandigarh.
98 Gurgaon gets very high scores at ease of funding, because Maruti has a policy of
Operations Management
investing in its ancillaries around Gurgaon as a joint venture partner. This would not
only ease the fund requirements of the owners, but would also make availability of
additional funds easier. It would be located adjacent to its market, Maruti Udyog Ltd.,
and most of the suppliers of inputs would be relatively close.
Table 4.4: Composite Location Scores
We can now convert the factor rating and location score into a composite score. This
is done easily by multiplying the factor rating with the location scores. The product is
the composite score for the location. The totals of all the factors are added and
compared. The location with the highest composite location score is the preferred
location. This has been worked out in Table 4.4.
Based on the Factor Rating Analysis, Gurgaon is the best site for locating the new
plant. It is a significantly better location than Chandigarh or Jammu based on the
factors that were identified and the salience that was given to these factors.
There is an implicit assumption in this model that either the cost differences between
the locations are not significant or that the benefits also reflect the cost advantages of
the location decision. This assumption may or may not be true. In the example we
have discussed above, the cost of land in Gurgaon could be extremely high, while the
historical cost of the Chandigarh land may be insignificant. The cost of pollution
control devices required at Gurgaon may be significantly higher than that required in
Jammu.
It is often better to use this model along with a quantitative model and compare the
results before taking a facility location decision. A number of other models are
available and commonly used that quantify both the benefits and costs of a specific
location compared to others.
Agra Jaipur
50, 200 350, 210
South
Kms.
Delhi
200, 50
Kms.
West
100 Using the rectilinear model, which is more popular, we are framing below a general
Operations Management
procedure for such problems. Assume the coordinate location of each existing facility
is (xi, yi).
Since all loads must be on rectangular paths, distance between each existing facility
and the new plant will be measured by the difference in the x-coordinates and the
difference in the y-coordinates.
If we let (xo, yo) be the co-ordinates of a proposed new plant, then
Di = |(xo xi)| + |(yo xi)|
Our goal is to find an optimal solution for xo and yo (new plant) that results in
minimum transportation costs. We follow three steps:
1. Identify the median value of the loads L i moved.
2. Find the x and y-coordinates to the existing facility that sends (or receives) the
median load.
3. Find the y-coordinate value of the existing facility that sends (or receives) the
median load.
The x and y-coordinates found in steps 2 and 3 define the new plant's best location.
Table 4.5: Location of Manufacturing Facility
Location- Loads Distance Unit Load-Distance
Median
new travel
Euclidean Rectilinear Loads Euclidean Rectilinear
Facility between
Delhi 212 300 100 21200 30000
Agra (A)
Jaipur 300 310 60 18000 29200 18600 38600
Delhi 220 310 100 22000 31000
Jaipur (B)
Agra 300 310 60 18000 30000 18600 39600
Agra 212 300 60 12720 18000
Delhi (C)
Jaipur 220 310 60 13200 25920 18600 36600
Table 4.5 shows the number of loads to be shipped monthly between the different
locations. It also shows the Euclidean and rectilinear distances between the locations,
and calculates the load-distance factor for the different location options. In this case,
as the total transit cost depends on distance only and the transported units are similar,
the total transportation cost is a constant and does not affect the final results.
If the cost to move one unit of load Ci and the number of loads are Li, the general
formula for transportation costs is:
n
Total Transportation Cost = Ci L i D i
i 1
The model does not consider road availability, physical terrain, or many other
important location considerations. This provides a rule of thumb method to determine
location. More rigorous quantitative models are often used. Two such quantitative
models are Linear Programming (LP) and Transportation models.
According to this method, a site is chosen for industrial development where total costs 101
Operations Technology and
are theoretically at their lowest, as opposed to location at the point of maximum Facility Location
revenue.
A model of industrial location proposed by A. Weber, assumes that industrialists
choose a least-cost location for the development of new industry. The theory is based
on a number of assumptions, among them that markets are fixed at certain specific
points, that transport costs are proportional to the weight of the goods and the distance
covered by a raw material or a finished product, that perfect competition exists, and
that decisions are made by economic man.
Weber argued that raw materials and markets would exert a 'pull' on the location of an
industry through transport costs. Industries with a high material index would be pulled
towards the raw material. Industries with a low material index would be pulled
towards the market.
Once a least-cost location has been established, Weber goes on to consider the
deflecting effect of labour costs.
START
Make another
Allocation
102 This process is shown in Figure 4.2. In handling such problems, as many
Operations Management
transportation tables are set up as there are location choices, treating them as separate
transportation problems. When the final solution of the problems is arrived at, the one
with the least cost points to the optimum location.
However, location problems are handled slightly differently than simple transportation
problems. Transportation tables are set up for each of the location options. Each
choice is treated as a separate transportation problem. The final solution of each of the
problems is compared and the problem that provides the least cost solution is the
optimum location.
We will explain the method using an example. Musgrave Inc. has three factories in
Boston, Detroit and Los Angeles. It is a manufacturer of washing machines, and its
current production is 200 units per day at Boston, 250 units at Detroit and 400 units at
Los Angeles. It is planning to increase its production capacity to 400 units at Detroit,
600 units at Los Angeles, and 300 units at Boston.
The company has, at present, two warehouses. The warehouse in Chicago has a
demand of 500 machines, and the one in Birmingham takes 350 machines. With the
expansion program for production, the company is planning to set up a new
warehouse. The choice is between Dallas and Pittsburgh. The costs per unit are given
in Table 4.6.
Table 4.6: Transportation Costs
($ per unit)
Chicago Birmingham Dallas Pittsburg
Boston 10 8 11 9
Detroit 8 9 11 8
Los Angeles 9 8 10 11
Assuming that the demand is estimated at 450 units at Dallas as well as Pittsburgh,
and that the transportation costs is the only factor in decision-making, where should
the company locate the new warehouse?
Make the Initial Allocation for the first option, i.e. setting up the warehouse at Dallas.
In making the initial allocation we follow the north-west Corner Rule. Start with the
top left-hand (north-west) corner cell. In our illustration it is cell AD. We make
maximum allocation to AD such that either the total supply in the opposite extreme
right-hand side of the cell is completely exhausted, or the demand for that warehouse,
shown in the bottom extreme left-hand side cell, is completely filled.
Table 4.7: Transportation Table with Warehouse at Dallas
Chicago Birmingham Dallas Supply
(D) (E) (F)
Boston (A) AD 10 AE 8 AF 11
300 0 0 300
Detroit (B) BD 8 BE 9 BF 11
200 200 0 400
Los Angeles (C) CD 9 CE 8 CF 10
0 150 450 600
Demand 500 350 450 1300
We then move to the top cell in the first row and the second column (AE). If any
supply is left unallocated, exhaust it, until either the supply is finished or the demand
is completely filled in. If any supply is still left, allocate it to the last cell in the first
row and third column. Following the procedure, we construct the transportation table 103
Operations Technology and
shown as Table 4.7. Facility Location
We check this table for degeneracy. It is easily seen that there is no degeneracy.
Therefore, we check the table for optimization.
Table 4.8: Net Effect on Cost Pattern by Moving Units for Musgrave Inc .
Empty cell Cells to which an additional Effect on cost Net effect
name unit is given/taken from
AE + AE, AD, BE , + BD + 8 10 + 8 9 3
AF + AF, AD, CF, + BD 11 10 10 + 8 1
BF + BF, BE, + CE, CF 11 9 + 8 10 0
CD + CD, CE, + BE, BD 98+98 2
We now select the empty cell with the largest negative figure which has the greatest
cost saving potential i.e. cell AE, and move 200 units from cell AD. We then balance
the table so that all total of all rows and columns remain unchanged. The new
transportation table is shown as Table 4.9.
Table 4.9: Transportation Table with Warehouse at Dallas, 2nd Allocation
Chicago Birmingham Dallas Supply
(D) (E) (F)
Boston (A) AD 10 AE 8 AF 11
100 200 0 300
Detroit (B) BD 8 BE 9 BF 11
400 0 0 400
Los Angeles (C) CD 9 CE 8 CF 10
0 150 450 600
Demand 500 350 450 1300
This is the optimal solution i.e. if the new warehouse is located in Dallas, the optimum
allocation and the combined cost of transportation will be:
Cost of Transportation = 10(100) + 8(200) + 8(400) + 8(150) + 10(450) = $11,500
We now take the second option of locating the warehouse at Pittsburgh, and draw up
its transportation table. This table is shown as Table 4.10.
Table 4.10: Transportation Table with Warehouse at Pittsburgh
Chicago Birmingham Dallas Supply
(D) (E) (F)
Boston (A) AD 10 AE 8 AF 9
300 0 0 300
Detroit (B) BD 8 BE 9 BF 8
200 200 0 400
Los Angeles (C) CD 9 CE 8 CF 11
0 150 450 600
Demand 500 350 450 1300
On the second allocation, we obtain the optimal configuration for this option. This is
shown as Table 4.11.
104 Table 4.11: Transportation Table with Warehouse at Pittsburgh, 2nd Allocation
Operations Management
Chicago Birmingham Dallas Supply
(D) (E) (F)
Boston (A) AD 10 AE 8 AF 11
0 0 300 300
Detroit (B) BD 8 BE 9 BF 11
250 0 150 400
Los Angeles (C) CD 9 CE 8 CF 10
250 350 0 600
Demand 500 350 450 1300
If the new warehouse is located in Pittsburgh, the combined cost of transportation will
be:
Cost of Transportation = 9 (300) + 8 (250) + 8 (150) + 9 (250) + 8 (350) = $ 10,950
By comparing the answers of the two problems that we set up, we come to the
conclusion that the optimum allocation with the new warehouse in Pittsburgh is more
economical than the one at Dallas. The new warehouse should, therefore, be located in
Pittsburgh.
These types of questions can also be solved using Vogels Approximation Method.
The solved example below has used VAM to arrive at the solution.
4.14 KEYWORDS
Capacity: Capacity is defined as the maximum load that can be handled by a facility
during a given period. The load can be expressed in terms of the inputs or outputs.
Layout: Layout of a facility is the physical location of various departments/units of
the facility in the premises of the facility.
Effective Capacity: Effective capacity is the maximum rate of output that can be
practically achieved under the constraints of time consumed it set-ups, oiling and
cleaning, defective items, etc.
Cycle Time: Cycle time is a time period after which completed units come off the
assembly line.
CYP 2
1. Facilities location may be defined as selection of suitable location.
2. Some heavy manufacturing units are: Automobile plants, steel mills and
oil refineries.
CYP 3
1. Some plant specific factors are:
(a) Customer base
(b) Construction/Leasing cost
(c) Land cost
(d) Site size
(e) Transportation
(f) Utilities
Contd
107
LESSON Plant Layout
5
PLANT LAYOUT
CONTENTS
5.0 Aims and Objectives
5.1 Introduction
5.2 Facility Layout
5.3 Types of Layout
5.4 Process Layout
5.4.1 Process Layout and Material Handling Costs
5.4.2 Process Layout in Nokia
5.4.3 Advantages and Disadvantages of Process Layout
5.5 Product or Line Layout
5.5.1 Assembly Line
5.5.2 Defining the Layout Problem
5.5.3 Assembly Line Balancing
5.5.4 Graphic and Schematic Analysis
5.5.5 Limitations of Product Layout
5.6 Fixed Layout
5.7 Cellular or Group Layout
5.7.1 The U-shaped Assembly Line
5.7.2 Advantages and Disadvantages of Cellular Layouts
5.7.3 Comparison of Layouts
5.8 New Approaches to Layout Design
5.8.1 Flexibility
5.8.2 Mixed Model Line
5.9 Lean Manufacturing System
5.10 Agile Manufacturing System
5.11 Computer-integrated Manufacturing System
5.12 Assembly Line Balancing
5.13 Let us Sum up
5.14 Lesson End Activity
5.15 Keywords
5.16 Questions for Discussion
5.17 Suggested Readings
108
Operations Management 5.0 AIMS AND OBJECTIVES
After studying this lesson, you will be able to:
Describe the basic layout types of fixed position layout, process layout, cell layout
and product layout
Know the effect of volume and variety on layout type
Use some of the more common techniques, which can be used in layout decisions
Know about the new approaches to layout design.
5.1 INTRODUCTION
A typical manufacturing plant has a number of diverse activities interacting with each
other. Raw materials arrive at a shipping dock, they are unpacked and checked in a
quality control area, they may then be processed through several processing areas, and
finally the finished product again passes through the shipping dock. In addition to
areas specifically related to production, there must be dressing rooms, lunch rooms,
and restrooms for employees; offices for supervision, design, and production control;
and space for inventory and aisles. In fact, a plant may be viewed as a number of finite
geometric areas arranged on the floor space of the building. The problem of arranging
these areas in an effective manner is the facility layout problem.
Clearly, the layout problem has relevance in many areas of facility and equipment
design. This lesson tries to disseminate knowledge on the design and planning of
service and production facilities. It discusses the different types of layouts, blending
organizational expectations with effective use of space to create a work environment
that is efficient.
The goal of functional layout is to allow workers and equipment to operate as 109
Plant Layout
effectively as possible. In order to do so, the following questions need to be addressed:
What should the layout include for each economic activity center? The
economic activity center should reflect decisions that maximize productivity. For
example, a central tool room is often efficient for most processes, but keeping
tools at individual workstations makes more sense for other processes.
How much space and capacity does each economic activity center need? Space
is a cost but inadequate space can reduce productivity and even create safety and
health hazards.
How should each economic activity centers space be configured? The space, its
shape, and the elements need to be interrelated. For example, in a store the
placement of the show windows, spaces planned so that products are visible and
providing a pleasing atmosphere are necessary parts of the layout configuration
decisions.
The location of an economic activity center has two dimensions that affect a centers
performance.
Relative location, or the placement of a center relative to other centers, and
Absolute location or the particular space that the center occupies within the
facility.
Where should each economic activity center be located? Location can significantly
affect productivity. Employees who must frequently interact with one another should
be placed close together so that interaction becomes easier; sections or departments
should be planned to reduce time lost in moving material or traveling of personnel
back and forth.
Building Design
INPUTS OUTPUTS
Materials
Forecasts Handling Capacity
Drawings Workplace Internal
Specifications Design External
Operation sheets Layout
Route sheets Support Process
Job descriptions Services Product
Plant location Fixed-position
Cellular
Equipment
Type
Quantity
Location
110 sales may dominate; whereas in an office, communication effectiveness and team
Operations Management
building may be crucial.
Operations Departments point of view is perhaps the most important level of 111
Plant Layout
planning.
Stores
Inspection Stock
Shaping-B Drilling-C Milling-D
114 High product variety can be easily handled, therefore, different product designs
Operations Management
and varying production volumes can be easily adopted.
The overhead cost is low.
Breakdown of one machine does not result in total stoppage of production.
Maintenance of machines is relatively easy as it can be scheduled without greatly
impacting production.
Easy, effective and specialized supervision of each function area is easy to
achieve. With different departments for different processes, better teamwork can
be achieved.
There is low setup and maintenance cost compared to other layouts.
Though the advantages outweigh the disadvantages in job shops and batch production,
there are some disadvantages of process layout:
There is high degree of material handling. Parts may have to backtrack in the
same department.
Large work in-process inventory is common. This may lead to more storage area.
Workers are more skilled. This is because of variety in products and difference in
design, therefore, labor cost is higher.
Total cycle time is high. This is due to waiting in different departments and longer
material flow.
Inspection is more frequent which result in higher supervision cost.
It is difficult to fix responsibility for a defect or quality problem. The work moves
in different departments in which the machine preference is not fixed. Therefore,
which machine or which operator was faulty during a quality lapse may be
difficult to trace in some cases.
The production planning and control is relatively difficult.
1 2 3 Product
One or group of
operations
to store as inventory i.e. they are available off the shelf. The layout of continuous flow 115
Plant Layout
is shown in Figure 5.5.
116 How this is achieved can be best understood with an example. ABC Electricals is a
Operations Management
medium sized firm in Delhi. It has an established design of a contact breaker
assembly, used industry-wide to protect all electrical circuits. The company has
established an assembly line to manufacture the product.
The operator starts the assembly process with a molding half. Into this molding he
puts the contacts, springs, plastic levers, etc. The assembly is closed off with a similar
molding half. The final assembly, comprised up to four of these units, is secured with
four rivets passing through the sandwich. The assembly is then tested. Testing is a
critical operation, as the contact breaker assembly carries up to 415 volts. If the unit is
found acceptable, it is labeled and packed for dispatch.
The method of assembly was on a series of benches with the sub-assemblies being
placed to boxes for transfer to the riveting press. The rivet operation involved the
manual placing of four long tubular rivets, placing to a 5 tonne press and secured. The
product was again boxed for transfer to testing.
The demand for this was 3000 units per month. However, due to the high rate of
rejection and the highly labor intensive process, they were unable to meet the demand.
Table 5.1 gives the assembly line details for the product.
Table 5.1: Assembly Line for Contact Breaker
Work Preceding Task Assigned Predecessor Task Operators
Station Work Task Time/ per station
Station Unit
(Hours)
1 - A: Contact Breaker None 0.010 1
Assembly; Take Molding
Half and clean burrs etc.
2 1 B: Install contacts A 0.020 2
C: Install Springs B 0.020
D: Install plastic levers A,C 0.040
etc. on Molding Half.
3 1 E: Install contacts A 0.020 2
F: Install Springs B 0.020
G: Install plastic levers A,C 0.040
etc. on Molding Half.
4 2,3 H: Close with other G 0.050 2
Molding Half
Is capacity adequate? The number of units this layout permits the company to
produce each day depends on the station whose tasks take the longest time to perform.
From Table 5.1 we know that:
The task assigned to station 1 require 0.010 hours,
Station 2 and station 3 are parallel paths and the tasks assigned take 0.080 hours, 117
Plant Layout
Station 4 requires 0.50 hours,
The longest time is needed at station 6 that is 0.098 hours, and so on.
Since every unit passes through all stations, station 3 is the bottleneck operation. This
station restricts the rate of flow of the line. With this layout, a finished contact breaker
will flow of the end of the line every 0.098 hours. This time is called the cycle time of
the line.
The cycle time is, in fact, also the time after which the conveyor moves in a moving
assembly line. Cycle time is defined as the time period after which completed units
come off the assembly line. Completed units are available after each movement of the
conveyor, as the basic structure worked upon at the last workstation will become a
completed unit in that time.
With a cycle time of 0.098 hours, how many contact breakers are produced daily?
If the operation runs for on 8-hour shift each day, the available productive time each
day is 8 hours. Therefore, maximum daily output can be as follows:
Maximum daily output = Available time/(Cycle time/unit)
= 8.0/0.098 = 81.63 units
Since this assembly line can generate 81 units daily, and the requirement is 3000 units
per month, capacity is inadequate.
An alternative method for determining whether capacity is adequate is to calculate the
maximum allowable cycle time give a desired capacity 3000 units/month.
Maximum allowable cycle time = Time Available/Desired number of units
= (8 24)/3000 = 0.064 hours/unit
This calculation shows that a layout whose cycle time is 0.064 hours or less will yield
the desired capacity.
Is the sequence of tasks feasible? For now, we will assume that the proposed
sequence of tasks is feasible. By examining the product, we can see the sequence
restrictions that must be observed in its assembly. For example, the moldings have to
be assembled prior to subsequent assembly steps to ensure that the four moldings can
be connected together. Finally, the contact breaker cannot be assembled until the
moldings have been riveted together.
This sequence must be observed because the contact breaker cannot be assembled
correctly in any other way. One the other hand, it makes no difference whether the
contacts are placed before the plastic lever or after the springs are assembled in the
molding. Similarly, the order of the riveting is irrelevant.
In general, the assembly tasks, listed in the table, are broken down into the smallest
whole activity. For each task, we note in column 4 of Table 5.1, the task or tasks that
must immediately precede it. However, job simplification is possible even within the
requirement of precedence.
Is the line efficient? The revised layout had six stations manned by 14 operators. All
workers are paid for 8 hours daily. How much of their time was spent productively?
This assignment was given to Technology & Management Systems (TAMS).
ABC Electricals, due to the traditional approach, believed that the assembly was very
labor intensive. Even with parallel processing they were utilizing up to fourteen
operators as is shown in column 6 of Table 5.1. TAMS decided to balance the
assembly line.
For larger problems with thousands of tasks and hundreds of stations, we often use 119
Plant Layout
heuristics. We will apply a Longest Operation Time (LOT) heuristic to find a balance
for the 0.098 hours/unit cycle time. The LOT steps are:
Heuristic Step 1: Longest operation time gives the top priority of assignment to the
task requiring the longest operation time. Assign first the task that takes the most time
to the first station. However, the precedence requirements have to be maintained.
In our example, task K requires the longest operation time of 5 minutes (the
bottleneck operation); therefore, this task has the highest priority of assignment at the
first workstation. Table 5.1 shows that task K has precedence requirement of other
tasks, i.e., there is a need for other tasks to be competed for the execution of task K.
Therefore, task K cannot be assigned to the first workstation. We have to assign task
A as the first task.
Heuristic Step 2: In the first rule, task A is the eligible task for the first workstation
and is assigned to it. As the task time of A is 0.010 hours, and the bottleneck task is
0.098 hours, additional tasks can be assigned to the station. Therefore, tasks B, C,
and D which require a total time of 0.080 hours can also be assigned to this station.
The time available on station 1 after completing these tasks is 0.008 hours. As there is
no other task that has this timing, no more tasks can be assigned to this station.
Heuristic Step 3: For workstation 3, we see that task H requires the longest task time
of 0.050 hours. From Table 5.1, notice that tasks I and J require 0.008 and 0.040
hours respectively. In keeping with the precedence requirement, tasks H, I and J can
be assigned to workstation 3 as the total of the time required to complete these tasks is
0.098 hours.
Heuristic Step 4: Workstation 4 is the bottleneck station. The task K cannot be split
into parts, this task has to be assigned to a workstation and the cycle time cannot be
less than the duration of this task. No other task can be accommodated at this
workstation.
Heuristic Steps 5-7: Repeat the above-explained process to get Table 5.2. Note that
we have used five workstations for the assignment of all the tasks. It could have
been more; for example if task I required more time, we would have ended up with
6 workstations. This explains why this is called the theoretical minimum workstations.
This entire process, carried to completion, is summarized in Table 5.2, showing a
five-station assembly line comprising 10 tasks.
Table 5.2: Line Balancing Problem
Work Preceding Task Assigned Predecessor Task Operators
Station Work Task Time per station
Station /Unit
(Hours)
1 - A: Contact Breaker None
Assembly; Take A 0.010 1
Molding Half and clean
burrs etc.
B: Install contacts B 0.020
C: Install Springs A,C 0.020
D: Install plastic A 0.040
levers etc. on Molding
Half.
Contd
Many other heuristics may be used instead of the Longest-Operation Time (LOT)
approach. Several computerized heuristics are available, and since different heuristics
can lead to different layouts, it may be worthwhile to want to try more than one
approach. Mathematical and computer-based Heuristic models can identify and
evaluate alternative layouts far more rapidly than manual or intuitive methods.
Though these models use observation and experimentation as they do theory, they
have their limitations.
R
E
S Final Product
O (SHIP)
U
R
C
E Ship building yard
Space requirements for storage of material and equipment are generally large. 123
Plant Layout
Products essentially require high class planning and focused attention on critical
activities to maximize margins.
124 their manufacturing process. This is a time-consuming and tedious task, which can be
Operations Management
accomplished by the following methods:
Visual inspection method (for grouping items according to design similarities),
which is very simple in application but not very accurate.
Examination of design and production data (for grouping items according to
design similarities), which is more complex to implement than visual inspection
but much more accurate.
Analysis of the production flow of items (for grouping items according to
manufacturing process similarities).
This identification and coding is the chart of group technology. The equipment to
make these is grouped together and designated for these parts. To some extent, a
process layout, characteristic of job shops, is changed to a small well-defined product
layout. This group of equipment is called a cell, and the arrangement of cells is called
a cellular layout.
Figure 5.8 illustrates the difference between the two alternative layouts. Two parts
require different tooling;
One part could be made in a job shop moving from machine A to C to D to E.
The second part can be made moving from machine A to C to D to B.
In the Process Layout, the machines are grouped together and the product moves to
the machines. In the Cellular Layout, the machines are grouped in a line flow.
A A C C
A B D D
A B D E
Process Layout
A A
Cellular Layout C C
D D
E B
In order for a cell to be economical and practical in the long term, the machines must 125
Plant Layout
be closely grouped, and the cell must be flexible in its mix of capacity and must be big
enough so any on absent employee does not shut it down, yet small enough for
employees to identify with the cell and understand the products and equipment.
Cell manufacturing is also the building block of Flexible Manufacturing Systems
(FMS). It is, in essence, FMS with some manual operations. The Cellular Layout
principles are adopted in FMS because the concepts make it easier to process large
volume of information because of the decomposed manufacturing system; it is easier
to manage the operational facilities compared to functional manufacturing due to
limitation on cell size, and the technological compulsions often require grouping some
operations like forging machines and heat treatment unit.
Although cellular layout is catchy new term, the phenomenon is not new. For decades,
large job shops have grouped equipment for high-volume parts or special customers.
Similarly, assembly lines may group machines by type to make or modify a variety of
parts that feed into the main assembly line.
For example, Telco, Jamshedpur, has different machine shops and die shops whose
output is finally fed into the assembly line. When considering a new technique such
as cellular layout, managers need to thoroughly look at past practices as a guide to
changing the manufacturing environment.
126 as well, though that might take other interventions beyond the layout change. Other
Operations Management
advantages are given below:
Lower work-in-process inventories,
A reduction in materials handling costs,
Shorter flow times in production,
Simplified scheduling of materials and labor,
Quicker set-ups and fewer tooling changes, and
Improved functional and visual control.
Disadvantages include the following:
Reduced manufacturing flexibility.
Unless the forecasting system in place is extremely accurate, it also has the
potential to increase machine downtime (since machines are dedicated to cells and
may not be used all the time).
There is also the risk that the cells that may become out-of-date as products and
processes change, and the disruption and cost of changing to cells can be
significant.
There is increased operator responsibility, and therefore behavioral aspects of
management become crucial.
Arrangement of Facilities move Placed along the Grouped by Similar parts are 127
facilities where the fixed line of product specialty and by grouped in part- Plant Layout
product/ project flow in a function family one
is being specialized machines cells is
implemented sequence of tasks formed which
for each unit contains all
facilities needed by
corresponding part-
family
Cost of layout General purpose Large investment General purpose Moderate to low
equipment. in specialized equipment and
Moderate to low equipment and processes.
processes. Moderate to
high
Inventory Variable High turnover of Low turnover of High turnover of
inventories and raw material and raw material raw material and
frequent tie-ups work in process and work in lower work in
because process, High process
production cycle raw material
is generally long. inventory
Material Flow variable, Predictable, flow Flow variable, Flow variable, can
handling often low. May systemized and handling often be reasonably high
require heavy often automated duplicated
duty handling
equipment
Material travel Variable path Fixed path Often high Fixed path
Utilization of Moderate Very high General purpose High
facilities
Operating General purpose Special purpose Skilled Special purpose
facilities
Employee skill Unskilled/skilled Unskilled Skilled Multi-skilled as one
operator may
handle more than
one operation
Quality/Product Normally 1, as Large (Q/P) Moderate (Q/P) Small (Q/P)
Variety Ratio single product
production
Product Cost Relatively low Relatively high Relatively low Reasonable level of
fixed costs; high fixed costs; low fixed costs; high fixed costs;
unit labor and unit costs for unit costs for relatively low unit
material costs direct labor and labor, material costs for direct
materials handling and labor and materials
material
128 Japan has been in the forefront in bringing to the industrial world a rethink on work
Operations Management
simplification and continuous improvement. In Japanese management practice, the
team concept is mainly associated with kaizen or continuous improvement, the
constant drive to remove waste from the production process. Central to this are
suggestion schemes which capture the creative thinking or inventive ideas, from
workers, either as individuals or through the team-based activities of quality circles.
The Japanese have developed it to a fine art. Process layout is one application where
the Japanese change both the physical layout and the managerial system. A Japanese
innovation is the U-shaped assembly line, which is used to encourage employee
involvement.
5.8.1 Flexibility
Flexibility has become a very important requirement in todays marketplace. It is
expected that with increasing competition, the importance of flexibility will go up
rather than down.
Advantages of a flexible layout are:
A flexible layout allows a firm to adapt quickly to changing customer needs and
preferences and is best for many situations.
Layout flexibility means either that the facility remains desirable after significant
changes occur or that it can be easily and inexpensively adapted in response to
changes.
This is a way to minimize the cost of layout changes.
These changes are taking place around us all the time. We see these in the mix of
customers served by a store, goods made a plant, space management in a warehouse,
or organizational structure in an office. For example, many offices now use modular
furniture and partitions, rather then permanent load-bearing walls. This is one way to
minimize the cost of office layout changes.
Manufacturers are adopting wide bays, heavy-duly floors, and extra electrical
connections in a plant. In the center aisle of the Sahara Mall, retailers use kiosks that
display a variety of novelties and specialty items. The ever-changing array of
merchandise transforms once-utilitarian passageways into retailing hot spots. They are
right where the customers have to walk and create a stream of impulses purchase.
models so as not to overload some stations for too long. Despite these difficulties, the 129
Plant Layout
mixed-model line may be the only reasonable choice when product plants call for
many customers options, as volumes may not be high enough to justify a separate line
for each model.
Check Your Progress 2
State whether the following statements are true or false.
1. Group layout is suitable when a large variety of products are needed in
small volumes.
2. Cell layouts cant be in several configurations.
3. Cell manufacturing is also the building block of Flexible Manufacturing
Systems (FMS).
130 has been more productive than its competitors. In 2001, Toyota continued to maintain
Operations Management
industry leadership. Consumer Reports rated Toyota models first in four of ten product
categories. This is true even today. Toyota has consistently outperformed competitors.
Two engineers, Taiichi Ohno and Shigeo Shingo devised the basis of what we call
Lean Manufacturing philosophy. They called it the Toyota Production System (TPS).
TPS uses waste elimination to increase profitability, quality and productivity. Waste is
considered to be any part of the process that takes time and resources but adds little or
no value to the product. Ohno identified the following seven types of waste as the
most prominent ones:
Waste from overproduction
Waste of waiting time
Transportation waste
Processing waste
Inventory waste
Waste of motion
Waste from product defect
The essential elements of Lean Manufacturing do not substantially differ from the
techniques developed by Ohno. Lean Manufacturing is aimed at the elimination of
waste in every area of production including customer relations, product design,
supplier networks and factory management. Its goal is to incorporate less human
effort, less inventory, less time to develop products, and less space to become highly
responsive to customer demand while producing top quality products in the most
efficient and economical manner possible.
The philosophy is reflected in the business model or strategy, the organizational
structure as well as the operational capability of the organization. Conventional mass
production models are relatively inflexible bodies that focus on exploiting economies
of scale, and pushing products into the market. They have rigid organizational
hierarchies: a relatively untrained workforce follows orders strictly and are expected
to do the same tasks, hour after hour, day-in and day-out. Tools to improve
productivity assume an extreme division of labor.
A lean manufacturing enterprise has a flat, team-based structure, with a high degree of
work autonomy that encourages initiative and innovation. It breaks down
organizational barriers and develops highly-trained, motivated employees who
investigate problems and find solutions as part of their job.
A lean manufacturing enterprise does this by encouraging problem identification,
hypothesis generation, and experimentation at all levels in the organization. It also
integrates its suppliers, and thinks more about its customers than it does about running
big machines fast to absorb labor costs and overhead.
Unlike conventional mass production principles, lean manufacturing systems involve
a relentless pursuit of process improvement which results in reduction in production
lot sizes. Reduction in product lot sizes triggers a chain of events involving improved
motivation, improved quality control, and a reduction in wastes. The ultimate
objective is to eliminate wastes. The comparison of the two systems is shown in
Table 5.5.
Table 5.5: Differences between Lean Manufacturing and Mass Manufacturing 131
Plant Layout
Areas Affected Mass Production Lean Enterprise
Business strategy Product-out strategy focused on Customer focused strategy
exploiting economies of scale of stable focused on identifying and
product designs and non-unique exploiting shifting competitive
technologies. advantage
Organizational Hierarchical structures that encourage Flat structures that encourage
structure following orders and discourage the initiative and encourage the flow
flow of vital information that highlights of vital information that highlights
defects, operator errors, equipment defects, operator errors,
abnormalities, and organizational equipment abnormalities, and
deficiencies. organizational deficiencies.
Operational Dumb tools that assume an extreme Smart tools that assume
capability division of labor, the following of standardized work, strength in
orders, and no problem solving skills. problem identification, hypothesis
generation, and experimentation.
132 We should ask ourselves what we are going to do to restore our competitiveness.
Operations Management
Should we adopt lean manufacturing in our own enterprises? Should we mimic the
Japanese? Or should we do something different and something better?
Without doubt there are now a significant number of people who believe that we have
to adopt lean manufacturing. But in adopting this approach we run the risk of forever
chasing after a moving target, for the Japanese are not going to standstill and wait to
be outperformed by US and European enterprises. The Japanese will keep innovating
and perfecting their methods. Thus, adopting lean manufacturing can only be a short
term measure aimed doing something to close the competitive gap. In the longer term,
if we want to catch up with and overtake the Japanese, lean manufacturing is not the
answer. What we need to do, is something which the Japanese cannot do.
Enter Agile Manufacturing. This is not another program of the month. Nor is it
another term for computer integrated manufacturing (CIM), or any number of other
fashionable buzzwords. Agile Manufacturing is primarily a business concept. Its aim
is quite simple - to put our enterprises way out in front of our primary competitors. In
Agile Manufacturing, our aim is to combine our organisation, people and technology
into an integrated and coordinated whole. We will then use the agility that arises from
this integrated and coordinated whole for competitive advantage, by being able to
rapidly respond to changes occurring in the market environment and through our
ability to use and exploit a fundamental resource - knowledge.
Fundamental to the exploitation of this resource is the idea of using technologies to
lever the skills and knowledge of our people. Our people must also be brought
together, in dynamic teams formed around clearly identified market opportunities, so
that it becomes possible to lever one another's knowledge. Through these processes we
seek to achieve the transformation of knowledge and ideas into new products and
services, as well as improvements to our existing products and services.
The concept of Agile Manufacturing is built around the synthesis of a number of
enterprises that each have some core skills or competencies which they bring to a joint
venturing operation, which is based on using each partners facilities and resources.
For this reason, these joint venture enterprises are called virtual corporations, because
they do not own significant capital resources of their own. This helps to make them
Agile, as they can be formed and changed very rapidly.
Central to the ability to form these joint ventures is the deployment of advanced
information technologies and the development of highly nimble organisational
structures to support highly skilled, knowledgeable and empowered people. Agile
Manufacturing builds on what is good in lean manufacturing and uses what can be
adapted to western cultures, but it also adds the power of the individual and the
opportunities afforded by new technologies.
Agile Manufacturing enterprises will be capable of rapidly responding to changes in
customer demand. They will be able to take advantage of the windows of
opportunities that, from time to time, appear in the market place. With Agile
Manufacturing we will be able to develop new ways of interacting with our customers
and suppliers. Our customers will not only be able to gain access to our products and
services, but will also be able to easily assess and exploit our competencies, so
enabling them to use these competencies to achieve the things that they are seeking.
The key to agility however, lies in several places. An agile enterprise needs highly
skilled and knowledgeable people who are flexible, motivated and responsive to
change. An agile enterprise also needs new forms of organisational structures which
engender non-hierarchical management styles and which stimulate and support
individuals as well as cooperation and team working. Agile manufacturing enterprises
also need advanced computer based technologies.
To achieve Agile Manufacturing, enterprises will have to bring together a wide range 133
Plant Layout
of knowledge in the design of a manufacturing system that encompass suppliers and
customers, and which addresses all dimensions of the system, including organisation,
people, technology, management accounting practices, etc. Most importantly, the
inter-related nature of all these areas needs to be recognised, and an interdisciplinary
manufacturing systems design method adopted as standard practice. This means going
beyond the multidisciplinary approaches that are currently being adopted, and looking
at areas between professions.
There is however, a fundamental problem, a barrier which hinders progress in this area
of interdisciplinary design. For the past two hundred years or more, the industrialised
world has organised knowledge into well defined boxes which have been represented
by professional groups often working in separate departments. Anything that did not
fit into these well defined areas of knowledge has been ignored or allowed to fall
through the cracks that we have created between professions. This has resulted in such
countermeasures as design for manufacture, where we are attempting to overcome the
problems that arise from our fundamental operating philosophies.
In manufacturing we have tended to treat organisation, people and technology issues
independently, and for the most part this division of knowledge has worked well in the
past. However, this approach does not work very well today, because over the last ten
years or so the world has changed enormously and has become a much more complex
place. Technologies have become more sophisticated, markets have become more
global and dynamic, and people have started to become more demanding, both as
customers and as employees. The traditional paradigms which fostered the growth of
manufacturing industry have started to shown signs of breaking down. We are now
entering upon a new era, and as manufacturing begins to move from the old industrial
era to the new knowledge intensive age, new paradigms are being forged. Agile
Manufacturing is a new paradigm. It is highly likely that it will form the basis of
21st century manufacturing strategy.
Interdisciplinary design will form the basis of designing Agile Manufacturing systems
in the new knowledge intensive era. Interdisciplinary design however, means more
than just applying knowledge from other domains, such as psychology and
organisational science, to the design of Agile Manufacturing systems. It also implies
looking into the unexplored areas between these disciplines and the areas where they
overlap, to find new insights, new knowledge and new and original solutions. This is
one of the most important challenges that managers and system designers and
integrators will face in the years ahead, for interdisciplinary design leads us to new
approaches and new ways of working and of thinking. However, to successfully adopt
an interdisciplinary design method, we also need to:
Challenge our accepted design strategies and develop new and better approaches;
Question our established and cherished beliefs and theories, and develop new ones
to replace those that no longer have any validity;
Consider how we address organisation, people and technology, and other issues in
the design of manufacturing systems, so that we can achieve systems that are
better for performance, for the environment and for the people who form a part of
these systems;
Go beyond the automation paradigm of the industrial era, to use technology in a way
that makes human skill, knowledge, and intelligence more effective and productive,
and that allows us to tap into the creativity and talent of all our people.
The challenges that we face with respect to all these issues are enormous. If we look at
the world of manufacturing we will see that it is very complex. There are a massive
Explore and understand the nature of the mass production paradigm and the nature 135
Plant Layout
of the cultural and methodological difficulties involved in the transition to Agile
Manufacturing.
Define a methodology for designing a 21st century manufacturing enterprise.
136 Personnel
Operations Management
Instructions and specifications
Production facilities.
MES includes:
Shop floor scheduling and control systems
Machine control systems
Robotics control systems
Process control systems
Some of the benefits of CIM are:
Increased efficiency through:
Work simplification and automation,
Better production schedule planning
Better balancing of production workloads in production capacity
Improved utilization of facilities, higher productivity, better quality control
through:
Continuous monitoring
Feedback and control of factory operations, equipment and robots.
Reduced investments in production inventories and facilities
Work simplification
Just-in-time inventory policies
Better planning and control of production
Better planning and control of finished goods requirements
Improved customer service
Reducing out-of-stock situations
Producing high-quality products that better meet customer requirements.
Check Your Progress 3
Fill in the blanks:
1. .. refers to a collection of tools used to promote
long-term profitability, and growth, by doing more with less.
2. .. Manufacturing enterprises will be capable of rapidly
responding to changes in customer demand.
3. . is about organisation, people, technology,
management accounting, business strategy, etc.
works to workstation alongside an Assembly Line and that operation will be optima in 137
Plant Layout
sense. Henry Ford who introduced the Assembly Line Balancing and in early times it
was simple Line Balancing (LB) which has optimized the industrial importance, the
effective difference between the optimal and sub-optimal operation can afford savings
which will be million dollars every year.
LB: It is a Classical Operation Research (OR) which optimizes the problem, and it has
been handled by OR for many decades. Most of the algorithms have been proposed to
this problem and it contempt the usual importance of the issue and the OR use to
handle this. Its commercial software which is available to optimize the industry and
their lines.
Assembly Line Balancing is dependent on 3 models and it is described that these 3
kinds of models is related to Assembly Line Balancing and they are Single-Model
Assembly lines, mixed models, and multi-model Assembly lines.
Singe-model Assembly Line: In early times assembly lines were used in high level
production of a single product. But now the products will attract customers without
any difference and allows the profitable utilization of Assembly Lines. An advanced
technology of production which enables the automated setup of operations and it is
negotiated time and money. Once the product is assembled in the same line and it
wont variant the setup or significant setup and its time that is used, this assembly
system is called as Single Model Line.
Mixed Model Assembly Line: In this model the setup time between the models would
be decreased sufficiently and enough to be ignored. So this internal mixed model
determines the assembled on the same line. And the type of assembly line in which
workers work in different models of a product in the same assembly line is called
Mixed Assembly Line.
Multi-model Assembly Line: In this model the uniformity of the assembled products
and the production system is not that much sufficient to accept the enabling of the
product and the production levels. To reduce the time and money this assembly is
arranged in batches, and this allows the short term lot-sizing issues which made in
groups of the models to batches and the result will be on the assembly levels.
138
Operations Management 5.15 KEYWORDS
Fixed Position Layout: Material remains fixed and tools, machinery and men are
brought to the location of the material.
Flexible Manufacturing: Ability of a manufacturing system to respond at a
reasonable cost and at an appropriate speed.
Group Layout: Combination of both process and product layout and incorporates the
strong points of both of these.
Mixed Layout: Produces several items belonging to the same family.
Process Layout: Similar machines or similar operations are located at one place as per
the functions
Product Layout: Facilities are located based on the sequence of operation on parts.
CYP 2
1. True
2. False
3. True
CYP 3
1. Lean Concept
2. Agile
3. Manufacturing
139
5.17 SUGGESTED READINGS Plant Layout
Adam & Ebert, Production and Operations Management Concepts, Models and
Behavior, Prentice Hall of India, 1992
Bradley Gale, Managing Customer Value: Creating Quality and Service that
Customers can see, Free Press, NY, 1994
Buffa and Sarin, Modern Production/Operations Management, John Wiley & Sons,
1994
Clayton Christensen, The Innovators Dilemma: When New Technologies Cause
Great Firms to Fail, HBS Press, 1997
Chase, Jacobs, Aquilano, Operations Management for Competitive Advantage,
Tata McGraw Hill, Delhi, 2004
Krajewski and Ritzman, Operations Management, Strategy and Analysis, Pearson
Education, 2002
Melnyk, S. and D. Denzler, Operations Management: A Value Driven Approach,
McGraw Hill, 1996
Vonderembse, Mark, White, Gregory, Operations Management, Concepts, Methods
and Strategies, John Wiley & Sons, 2004
30
Micro-Finance:
Perspectives and Operations
141
Production Planning and Control
UNIT III
142
Operations Management
143
LESSON Production Planning and Control
6
PRODUCTION PLANNING AND CONTROL
CONTENTS
6.0 Aims and Objectives
6.1 Introduction
6.2 Meaning of Production Planning
6.3 Functions of Production Planning and Control
6.4 Aggregate Planning
6.4.1 Various Steps involved in the Aggregate Planning
6.4.2 Objectives of Aggregate Planning
6.4.3 Various Strategies involved in Aggregate Planning
6.4.4 Varying Workforce Level to Meet Demand
6.5 Master Production Schedule
6.6 Material Requirement Planning (MRP)
6.6.1 Assumptions and Pre-requisites
6.6.2 Material Planning
6.6.3 MRP Process
6.6.4 MRP System
6.6.5 Benefits of MRP System
6.6.6 Outputs The Materials Requirement Plan
6.6.7 Priority Planning
6.7 Bill of Materials (BOM)
6.7.1 Costing Bill of Materials
6.7.2 Planning or Modular Bill of Materials
6.7.3 Phantom Bill of Materials
6.7.4 Engineering Bill of Materials
6.7.5 Pseudo Bill of Materials
6.7.6 Features of Bill of Materials
6.8 Capacity Requirement Planning
6.9 Techniques of CRP
6.10 Problems in MRP and CRP
6.10.1 Material Requirements Planning (MRP) Problems
6.10.2 CRP Problems
Contd
6.1 INTRODUCTION
The conversion of a customers order to a finished product needs generally the
organization and planning of the manufacturing process. The overall objective of any
organization is to improve its profitability through productivity i.e. by employing
various inputs (Men, Machines, Materials, Money & Management) effectively so as to
bring about the desired manufacturing results in terms of quality, time and place.
145
6.3 FUNCTIONS OF PRODUCTION PLANNING AND Production Planning and Control
CONTROL
Following are the main functions performed by a PPC department:
Order Preparation
Once an order, through the sales department, is received for execution, activities like
preparation of the work-order, converting the same into shop-order and then releasing
the same to various departments for planning action at their end for their concerned
activities get started.
Materials Planning
Material Requirement Planning (MRP) is based on the orders on hand, the inventory
position of the finished goods & raw materials; the expected demand from
marketing/sales department, the capacity of various production shops and bills of
materials, the lead time and constantly following up of the status with purchase and
stores departments against specific shop orders is done.
Scheduling
Scheduling of manufacturing order takes care of the following:
Preparation of machine loads.
Fixation of calendar dates of various operations/sequence of operations to be
performed on the jobs & follow-up the same.
Coordination with sales to confirm delivery dates of new items and keeping them
informed about the periodical dispatch schedules.
Dispatching
Dispatching concerns preparation and distribution of show orders and manufacturing
instructions to the concerned departments. The instruments and show orders received
by various departments is an authority for them to perform the work according to that
schedule.
Progressing
Progressing means control, i.e., collection of data from various manufacturing shops,
recording the progress of work and comparing progress against the plan.
Expediting
Expediting means chasing intensively the bottle neck areas causing delays/
interruptions in carrying out smooth production and taking appropriate actions from
time to time and keeping the concerned authorities well informed about the progress
of planned targets. Also to communicate the sales department promptly about the
failure in delivering commitments, if any.
Master Schedule
Month Rating Apr. May Jun. Jul. Aug. Sept.
6A 2000 2000 3000 3000 4000 2000
16A 1200 500 1000 1000 1000 -
20A - 200 - 500 - -
25A - - 500 - 500 500
32A 500 - 500 200 200 200
40A 200 - 500 100 100 100
63A 100 - 500 100 100 100
4000 2700 5500 5000 6000 3000
Sub-contracting
Sub-contracting means meeting demand through acquiring part of goods from other
manufacturers/producers rather than making in-house. House benefits must be
weighed against cost and quantity.
Capacity Utilisation
Capacity utilisation is very common to service industries, organisations or companies
which cannot store products or services. They must arrange to meet peak load through
sharing capacity utilizations. Example: Telephone Companies, Electric Power
Companies & Computer Time Sharing Companies.
Show the daily requirement and cumulative demand graphically and determine the 149
Production Planning and Control
production rate to meet the average demand.
Solution: The production requirements are tabulated hereunder:
Month Forecasted No. of Production Demand Cumulative Cumulative
Demand Days Available per day Production Demand
(2/3) Days (units)
1 2 3 4 5 6
April 200 20 10 20 200
May 81 27 3 47 281
June 210 27 10 74 551
July 560 28 20 102 1111
August 805 23 35 125 1916
Sept 100 25 4 150 2016
Oct 260 20 13 170 2276
Nov 176 22 8 192 2452
Dec 84 28 3 220 2536
Jan 108 27 4 247 2644
Feb 190 19 10 266 2834
March 450 25 18 291 3224
3224 291
Solution:
MONTH April May June July Aug Sept.
= 20 = 45 = 18 = 31 = 32 = 42
4. LAY-OFF 21000
(`) REQD =2000
1. MEN REQD 30 30 30 30 30 30
153
6.6 MATERIAL REQUIREMENT PLANNING (MRP) Production Planning and Control
154 In the process of planning, MRP system allocates existing inventories on hand to the
Operations Management
items to be manufactured. And based on the gross requirements, it reevaluates the
validity of the timing of any outstanding orders. The system establishes a schedule of
planned orders for each item, including orders, if any, to be released immediately plus
orders scheduled for release at specific future dates. Planned order quantities are
computed using any of several lot sizing rules.
Assumptions
The MRP system makes certain assumptions regarding inventories. The models
assume that:
Lead times for all inventory items are known and can be supplied to the system, at
least as estimates.
Every inventory item under item control goes into and out of stock, i.e., there will
be reportable receipts, following which the item will be in an 'on-hand' state and
will eventually be disbursed to support an order for an item into which it is
merged.
All components of an assembly must be available at the time an order for that
assembly is to be released to the factory.
Components and materials are discretely disbursed and used. In the case of
materials that come in continuous form (e.g., rolls of sheet metal), the standard
planning procedures are modified and the system adapted to handle such
inventory items properly.
The process is independent, i.e., a manufacturing order for any given inventory
item can be started and completed on its own and not be contingent on the
existence or progress of some other order for completing the process. Thus,
mating part relationships and set up dependencies do not fit the scheme of MRP.
Prerequisites
In order to develop a MRP model there are some prerequisites. The principle
prerequisites for a standard MRP system are as follows.
A Master Production Schedule exists and can be stated in bill of materials form;
All inventory items are uniquely identified;
A bill of material exists at the time of planning;
Inventory records contain data on the status of every item; and
There is integrity of file data.
In addition, other prerequisites in building MRP models are:
Individual item lead times are known;
Every inventory item goes into and out of stock;
All of the components of an assembly are needed at the time of release of
assembly orders;
158 The system is also capable of providing to provide a number of secondary outputs.
Operations Management
Apart from the primary outputs an MRP System can be used for:
Inventory order action,
Re-planning order quantities,
Safeguarding priority integrity,
Performance control, and
Reporting errors, incongruities and out-of-bounds situations in the system.
Some of the secondary outputs that can be provided by the MRP system are:
Exception notices reporting errors, incongruities, and out-of-bound situations.
Inventory level projections.
Purchase commitment reports.
Tracing demand sources.
Performance reports.
An MRP system that is properly designed, implemented and used will also contain
valid and timely information that can assist in the functioning of the organization on
three separate levels:
Planning and control of inventories.
Planning of open order priorities.
Inputs to the capacity requirements planning system.
Dynamic updating of operation priority is based on the critical ratio and not due dates 159
Production Planning and Control
and established relative priorities. The dependent priority procedure computes the
value of the critical ratio for the next operation to be performed on every open shop
order, as follows:
Ratio A = Quantity On-hand/Order Point
Ratio B = Lead time for Balance Work/Total Lead time
Critical Ratio = A/ B
Ratio A is a measure of need and represents the degree of stock depletion. Ratio B
is a measure of the response and reflects the degree of work completion. A critical
ratio of 1 signifies that work on the order has kept pace with the rate of stock
depletionthe order is on Schedule. A value, lower than 1, indicates an order
ahead of schedule. The priority of the job becomes higher as the value of critical
ratio falls or becomes lower.
In the case of assembly products, horizontal dependence exists. In such a situation, the
MRP system must re-plan requirements and dates of need for the component orders in
question, in case of change or rescheduling in parent product requirements. However,
in independent demand situations, ratio A is meaningless.
Table 6.1 shows a typical engineering bill of materials. Each engineering bill of
materials has a parent. The parent is the item (product, assembly, subassembly,
intermediate, etc), which is to be made. All the controls on the bill of materials relate
to the parent. In other words, it has context and instruction that allows manufacturing
engineers to derive the manufacturing bill of materials.
The product structure must be defined in terms of levels of manufacture.
Subassemblies, which never see a stock room because they are immediately consumed
in the assembly of their parents, called transient subassemblies, should also be
accounted for. A technique called phantom bill can be used to handle these.
You will also come across certain apparent discrepancies; let us take a hypothetical
case where part no. 18701-19302 appears twice in the bill of materials. The parent part
requires 4 units of enclosures, the first 3 enclosures are used for the sub-assemblies
and the fourth is used at the final-assembly stage. In a situation like this, to avoid the
possibility of placing separate orders for the same part, the part is always assigned the
lowest level (highest level number) at which it appears. Thus, the enclosures should
always appear as a level 3 item. This is called low-level coding. Such coding also
facilitates computer processing.
Column 4 provides information on the quantity required for each parent item.
Column 5 provides information on the unit of measurement. The metrics adopted are
very important and should be consistent. Column 6 gives the description of the
inventory item. This may or may not be unique. The last column provides information
on the sourcing of the inventory item.
162 Next level end level where-used: An item, all the parents in which it is a direct
Operations Management
component, and the top-level parents (products) of which they form part.
Summarized bill: A list of all components (at all levels) in a parent with total
quantities, but not displaying any structure information.
The bill of material structure is the arrangement of inventory item data within the bill
of materials file. Information in the bill of materials includes:
Item identities: Assignment of item identity eliminates ambiguity and identifies
levels of manufacture. It cross-references the item master data. An item may be
able to be listed as a component more than once in a bill.
Sequence Number: Can be used to present the bill in a particular way, grouping
all component items of a given type together, or presenting a picking sequence.
Also known as a find number or balloon number.
Component Quantity: The amount of the component item to be used in
manufacturing the parent, normally stated as quantity per unit of the parent but
expressed per batch in some formula-based systems. Also known as quantity
per.
Unit of Measure: May be provided automatically by an MRP II or ERP or other
system or specified by the user if unit conversions are available.
Relationship: Indicates whether the component is used in the quantity stated per
unit or batch of the parent or in some other way, such as per order or as required.
Type of Component: shows whether the item is a normal component or a special
type. Types of component in addition to standard include phantoms, sometimes
called pseudo, options, reference items and others.
The bill of material should reflect, through its level structure, the way material flows
in and out of stock. Thus it is expected to specify not only the composition of a
product but also the process stages in the products manufacture. The product structure
must be defined in terms of levels of manufacture. Sub-assemblies which never see a
stock room because they are immediately consumed in the assembly of their parents
are called transient subassemblies.
163
6.8 CAPACITY REQUIREMENT PLANNING Production Planning and Control
164 The master schedule is exploded through the MRP using bills-of-material, producing a
Operations Management
set of recommended planned orders, for in-house production, as well as orders to
suppliers for any bought-out material items, and indicate, based on the master
schedule and the associated material buy plan, which items should be replenished first
and the due dates. It can also include rescheduling of the open orders.
In a job shop situation, using the saved routings of the various items, these planned-
orders are converted to requirements (for example, in machine and labor hours) at the
various work centers. In this way the required capacity for each work center in each
time period is determined. As MRP assumes infinite capacity, and in the general
approach of infinite loading, capacity constraints are ignored in developing the
capacity profile. In finite loading, the master schedule is developed within the capacity
constraints at all work centers.
The other major drawback of MRP is that takes no account of capacity in its 165
Production Planning and Control
calculations. This means it will give results that are impossible to implement due to
manpower or machine or supplier capacity constraints. However this is largely dealt
with by MRP II.
<<supply>> <<supply>>
<<goal>>
<<Process>>
Event Output
Business Process
A business process:
1. Has a Goal;
2. Has specific input;
3. Has specific output;
4. Uses resources;
5. Has a number of activities that are performed
in some order;
6. May affect more than one organizational unit.
Horizontal organizational impact;
7. Creates value of some kind for the customer.
The customer may be internal or external
Process Models
Business Process
A business process is a collection of activities designed to produce a specific output
for a particular customer or market. It implies a strong emphasis on how the work is
done within and organization, in contrast to a products focus on what. A process is
168 thus a specific ordering of work activities across time and place, with a beginning, an
Operations Management
end, and clearly defined inputs and outputs: a structure for action.
Connections
Supply link from object Information. A supply link indicates that the information or
object linked to the process is not used up in the processing phase. For example, order
templates may be used over and over to provide new orders of a certain style - the
templates are not altered or exhausted as part of this activity.
Supply link from object Resource. An input link indicates that the attached object or
resource is consumed in the processing procedure. As an example, as customer orders
are processed they are completed and signed off, and typically are used only once per
unique resource (order).
Goal link to object goal indicates the attached object to the business process describes
the goal of the process. A goal is the business justification for performing the activity.
Object
Object
Goal
A business process has some well defined goal. This is the reason the organization
does this work, and should be defined in terms of the benefits this process has for the
organization as a whole and in satisfying the business needs.
Goal link from activity Business Process indicates the attached object to the business
process describes the goal of the process. A goal is the business justification for
performing the activity.
Information
Business processes use information to tailor or complete their activities. Information,
unlike resources, is not consumed in the process - rather it is used as part of the
transformation process. In formation may come from external sources, from
customers, from internal organizational units and may even be the product of other
processes.
Supply link to activity Business Process indicates that the information or object linked
to the process is not used up in the processing phase. For example, order templates
may be used over and over to provide new orders of a certain style - the templates are
not altered or exhausted as part of this activity.
Output 169
Production Planning and Control
A business process will typically produce one or more outputs of value to the
business, either for internal use of to satisfy external requirements. An output may be
a physical object (such as a report or invoice), a transformation of raw resources into a
new arrangement (a daily schedule or roster) or an overall business result such as
completing a customer order.
An output of one business process may feed into another process, either as a requested
item or a trigger to initiate new activities.
Resource
A resource is an input to a business process, and, unlike information, is typically
consumed during the processing. For example, as each daily train service is run and
actual recorded, the service resource is used up as far as the process of recording
actual train times is concerned.
Supply link to activity Business Process. An input link indicates that the attached
object or resource is consumed in the processing procedure. As an example, as
customer orders are processed they are completed and signed off, and typically are
used only once per unique resource (order).
170 TPM is a Japanese idea that can be traced back to 1951 when preventive maintenance
Operations Management
was introduced into Japan from the USA. Nippondenso, part of Toyota, was the first
company in Japan to introduce plant wide preventive maintenance in 1960. In
preventive maintenance operators produced goods using machines and the
maintenance group was dedicated to the work of maintaining those machines.
However with the high level of automation of Nippondenso maintenance became a
problem as so many more maintenance personnel were now required. So the
management decided that the routine maintenance of equipment would now be carried
out by the operators themselves (This is Autonomous maintenance, one of the features
of TPM). The maintenance group then focused only on 'maintenance' works for
upgrades.
The maintenance group performed equipment modification that would improve its
reliability. These modifications were then made or incorporated into new equipment.
The work of the maintenance group is then to make changes that lead to maintenance
prevention. Thus preventive maintenance along with Maintenance prevention and
Maintainability Improvement were grouped as Productive maintenance. The aim of
productive maintenance was to maximize plant and equipment effectiveness to
achieve the optimum life cycle cost of production equipment.
Nippondenso already had quality circles which involved the employees in changes.
Therefore, now, all employees took part in implementing Productive maintenance.
Based on these developments Nippondenso was awarded the distinguished plant prize
for developing and implementing TPM, by the Japanese Institute of Plant Engineers
(JIPE). This Nippondenso of the Toyota group became the first company to obtain the
TPM certifications.
Implementation
TPM has five goals:
1. Maximize equipment effectiveness.
2. Develop a system of productive maintenance for the life of the equipment.
3. Involve all departments that plan, design, use, or maintain equipment in
implementing TPM.
4. Actively involve all employees.
5. Promote TPM through motivational management.
TPM identifies the 16 types of waste (Muda) and then works systematically to
eliminate them by making improvements (Kaizen). TPM has 8 pillars of activity, each
being set to achieve a zero target. These pillars are:
1. Focused improvement (Kobetsu-Kaizen): for eliminating waste.
2. Autonomous maintenance (Jishu-Hozen): in autonomous maintenance, the
operator is the key player. It involves daily maintenance activities carried out by
the operators themselves that prevent the deterioration of the equipment.
3. Planned maintenance: for achieving zero breakdowns.
4. Education and training: for increasing productivity.
5. Early equipment/product management: to reduce waste occurring during the
implementation of a new machine or the production of a new product.
6. Quality maintenance (Hinshitsu-Hozen): This is actually maintenance for
quality. It includes the most effective quality tool of TPM: poka-yoke, which
aims to achieve zero loss by taking necessary measures to prevent loss.
7. Safety, hygiene, and environment: for achieving zero work-related accidents and 171
Production Planning and Control
for protecting the environment.
8. Office TPM: for involvement of all parties to TPM since office processes can be
improved in a similar manner as well.
9. TPM Success Measurement: A set of performance metrics, which is considered
to fit well in a Lean/TPM environment, is Overall Equipment Effectiveness, or
OEE.
Check Your Progress 3
State whether the following statements are true or false:
1. Process planning begins during the engineering design of the product.
2. Contracting out maintenance jobs is a fairly common practice in India.
3. The MRP process is initiated once the customer orders for the finished
goods from the supplier.
6.16 KEYWORDS
Material Requirement Planning: MRP is a system for planning the future
requirements of dependent demand items.
Master Production Schedule: MPS is an extension of the aggregate production plan.
It tells us the number of units of different models of a product to be manufactured on a
weekly or monthly basis.
Process Planning: Process Planning means fixing the process of manufacturing/
sequence of operations.
Dispatching: Dispatching concerns preparation and distribution of show orders and
manufacturing instructions to the concerned departments.
CYP 2
1. Production Planning and Control is to set the realisation targets in terms
of Standard Output, measure the actual production performance against
the target set in advance and take remedial action as and when necessary.
2. Expediting means chasing intensively the bottle neck areas causing
delays/interruptions in carrying out smooth production and taking
appropriate actions from time to time and keeping the concerned
authorities well informed about the progress of planned targets.
CYP 3
1. True
2. False
3. True
173
LESSON ERP and MRP-II Overview
7
ERP AND MRP-II OVERVIEW
CONTENTS
7.0 Aims and Objectives
7.1 Introduction
7.2 Introduction to ERP
7.3 Overview of ERP
7.4 What is ERP?
7.4.1 The Ideal ERP System
7.4.2 Implementation of an ERP System
7.5 Evolution of ERP
7.6 Reasons for Growth of ERP
7.7 Benefits of ERP
7.8 Failure of ERP Implementation
7.9 Integrated Data Model
7.10 Manufacturing Resource Planning (MRP II)
7.11 Let us Sum up
7.12 Lesson End Activity
7.13 Keywords
7.14 Questions for Discussion
7.15 Suggested Readings
7.1 INTRODUCTION
ERP systems are now ubiquitous in large businesses and the current move by vendors
is to repackage them for Small to Medium Enterprises (SMEs). This migration has
many consequences that have to be addressed through understanding the history and
evolution of ERP systems and their current architectures. The advantages and
disadvantages of the ERP systems will impact their penetration in this new market.
174 The market position and general strategy of the major systems providers in
Operations Management
preparation for this push are described. The lesson concludes that the growth and
success of ERP adoption and development in the new millennium will depend on the
legacy ERP systems capability of extending to Customer Relationship Management
(CRM), Supply Chain Management (SCM) and other extended modules, and
integration with the Internet-enabled applications.
175
7.3 OVERVIEW OF ERP ERP and MRP-II Overview
ERP is much more than just a computer software. An ERP System includes ERP
Software, Business Processes, Users and Hardware that run the ERP software.
An ERP system is more than the sum of its parts or components. Those components
interact together to achieve a common goal - streamline and improve organizations
business processes. Most important factor for ERP system is the users. Successful
implementation of any ERP System depends more on intelligent users who are going
to use them, because any standard ERP Software would consist hundreds of input
information for any particular business activity. Thus good knowledge of each entity
of system by the users is the most important factor in ERP Software.
176
Operations Management
177
ERP and MRP-II Overview
178 the fact that consultants are usually more cost effective and are specifically trained in
Operations Management
implementing these types of systems.
One of the most important traits that an organization should have when implementing
an ERP system is ownership of the project. Because so many changes take place and
its broad effect on almost every individual in the organization, it is important to make
sure that everyone is on board and will help make the project and using the new ERP
system a success.
Usually organizations use ERP vendors or consulting companies to implement their
customized ERP system. There are three types of professional services that are
provided when implementing an ERP system, they are Consulting, Customization and
Support.
Consulting Services: Usually consulting services are responsible for the initial stages
of ERP implementation, they help an organization go live with their new system, with
product training, workflow, improve ERP's use in the specific organization, etc.
Customization Services: Customization services work by extending the use of the new
ERP system or changing its use by creating customized interfaces and/or underlying
application code. While ERP systems are made for many core routines, there are still
some needs that need to be built or customized for an organization.
Support Services: Support services include both support and maintenance of ERP
systems. For instance, trouble shooting and assistance with ERP issues.
Check Your Progress 1
Fill in the blanks:
1. MRP-I stands for ..
2. ERP stands for ..
3. MRP-II stands for ..
Advanced Planning and Scheduling (APS), e-business solutions such as customer 179
ERP and MRP-II Overview
relationship management (CRM) and supply chain management (SCM). Figure 7.6
summarizes the historical events related with ERP.
180
Operations Management 7.7 BENEFITS OF ERP
The ERP packages promise the seamless integration of all information flowing
through an organization; they are becoming the fastest growing softwares in the world.
The ERP vendors like SAP, Oracle, Baan, QAD, J.D. Edwards, Peoplesoft are in
demand for their packages. The main task of the ERP system is to deliver products to
the companies to manage their internal and external functions efficiently. There are
several other advantages of adopting the ERP system, few of them are as follows:
1. Improved Efficiency: This is achieved by reduction of cycle time, inventory
reduction, order fulfillment, improving support to supply chain, management, etc.
2. Business Integration: ERP packages are integrated. i.e. Exchange of data among
related business components is possible. In the large companies timing of system
constructions, directive differs for each product and department function.
3. Better Decision-making: The decision making procedure become easier because
of highly structured programmed process. These processes governs days to day
operations and produces reports in structured form, which are further used by top
management of organization to meet with its basic goals and objectives and to
monitor the whole organization.
4. Quick Response Time to Customers: The system is easy to operate so, that not
much computer skills are required to handle the operations. Because of its
comprehensive nature the system avoids unnecessary duplication and redundancy
in data gathering and storage. Thus the response time to customer is reduced.
5. Business Integration: ERP creates the common database across the organization
which is used by various departments within the organization. The ERP supports
the flow of information within department automatically. This business integration
capabilities makes it easy to group business details in real time and carry out
various types of management decision in time. The support systems like DSS can
use this common database. Thus information and the data are on the fingertip of
top level management.
6. Analysis and Planning Capabilities: Though different types of decisions support
systems and simulation function, ERP makes the analysis of data easier. The DSS
also supports the middle and top management for tactical and strategic planning.
7. Technology Support: Utilization of latest development in Information technology
is quickly adapted by the ERP packages. Distributed system, open system, client
server technology, internet, intranet, E-commerce, CALS (Computer aided
Acquisition and Logistic Support) are some examples of flexible environment
adopted by ERP. The ERP packages itself design in a way that they can
incorporate with latest technology even during the customization, maintenance
and expansion phases.
very expensive and very risky. Since the files, activities, and corporate reports are 181
ERP and MRP-II Overview
centralized, there is a high possibility that some important and confidential files could
be lost.
While advantages usually outweigh disadvantages for most organizations
implementing an ERP system, here are some of the most common obstacles
experienced:
Usually many obstacles can be prevented if adequate investment is made and adequate
training is involved, however, success does depend on skills and the experience of the
workforce to quickly adapt to the new system.
Customization in many situations is limited
The need to reengineer business processes
ERP systems can be cost prohibitive to install and run
Technical support can be shoddy
ERP's may be too rigid for specific organizations that are either new or want to
move in a new direction in the near future.
182 Access Control: User privilege as per authority levels for process execution.
Operations Management
Customization: To meet the extension, addition, change in process flow.
To implement ERP systems, companies often seek the help of an ERP vendor or of
third-party consulting companies. These firms typically provide three areas of
professional services: consulting, customization and support. The client organisation
may also employ independent program management, business analysis, change
management and UAT specialists to ensure their business requirements remain a
priority during implementation.
Data migration is one of the most important activities in determining the success of an
ERP implementation. Since many decisions must be made before migration, a
significant amount of planning must occur. Unfortunately, data migration is the last
activity before the production phase of an ERP implementation, and therefore receives
minimal attention due to time constraints. The following are the steps of a data
migration strategy that can help with the success of an ERP implementation:
Identifying the data to be migrated
Determining the timing of data migration
Generating the data templates
Freezing the tools for data migration
Deciding on migration related setups
Deciding on data archiving
Global ERP
Multinationals seeking to centralise financial reporting and close their monthly or
quarterly financials faster.
Companies looking to minimise the variety of financial controls in place to
simplify regulatory compliance activities.
Corporations that stand to gain operational efficiencies by centralising
management and control of operational procedures, such as order management,
materials handling and inventory control.
Organisations seeking to maintain common business processes across various
divisions and geographies.
Corporations that are highly distributed or operate as collections of regional
businesses.
Companies that need customised systems to meet unique business requirements in
particular markets.
Multinationals subject to various local rules and regulations that require reporting
of financials or operational data in formats different from those used by the rest of
the company.
Far-flung companies whose regional units may be subject to infrastructure
instability, making it difficult to maintain consistent high-speed connections to a
host system located across the world.
183
ERP and MRP-II Overview
184 Almost every MRP II system is modular in construction. Characteristic basic modules
Operations Management
in an MRP II system are:
Master Production Schedule (MPS)
Item Master Data (Technical Data)
Bill of materials (BOM) (Technical Data)
Production Resources Data (Manufacturing Technical Data)
Inventories and Orders (Inventory Control)
Purchasing Management
Material Requirements Planning (MRP)
Shop Floor Control (SFC)
Capacity planning or Capacity Requirements Planning (CRP)
Standard Costing (Cost Control)
Cost Reporting/Management (Cost Control)
Benefits of MRP II
MRP II systems can provide:
Better control of inventories
Improved scheduling
Productive relationships with suppliers
For Design/Engineering:
Improved design control
Better quality and quality control
For Financial and Costing:
Reduced working capital for inventory
Improved cash flow through quicker deliveries
Accurate inventory records
Timely and valid cost and profitability information.
MRP II systems have been implemented in most manufacturing industries. Some
industries need specialised functions e.g. lot traceability in regulated manufacturing
such as pharmaceuticals or food. Other industries can afford to disregard facilities
required by others e.g. the tableware industry has few starting materials mainly
clay and does not need complex materials planning. Capacity planning is the key to
success in this as in many industries, and it is in those that MRP II is less appropriate.
Check Your Progress 2
Fill in the blanks:
1. creates the common database across the organization
which is used by various departments within the organization.
2. Data migration is one of the most important activities in determining the
success of an .
185
7.11 LET US SUM UP ERP and MRP-II Overview
ERP is the abbreviation of Enterprise Resource Planning and means, the techniques
and concepts for integrated management of businesses as a whole from the viewpoint
of the effective use of management resources to improve the efficiency of enterprise
management. ERP provides the backbone for an enterprise-wide information system.
At the core of this enterprise software is a central database which draws data from and
feeds data into modular applications that operate on a common computing platform,
thus standardizing business processes and data definitions into a unified environment.
With an ERP system, data needs to be entered only once. The system provides
consistency and visibility or transparency across the entire enterprise. A primary
benefit of ERP is easier access to reliable, integrated information. A related benefit is
the elimination of redundant data and the rationalization of processes, which result in
substantial cost savings.
7.13 KEYWORDS
Enterprise Resource Planning: Enterprise applications used to manage information
about organizational resources such as raw materials, products, staff and customers as
part of delivery of a product or service.
Customer Relationship Management (CRM): An approach to building and sustaining
long-term business with customers.
Information System: A collection of hardware, software, data, and people designed to
collect, process, and distribute data throughout an organization.
CYP 1
1. Material Requirement Planning
2. Enterprise Resource Planning
3. Manufacturing Resource Planning
CYP 2
1. ERP
2. ERP implementation
187
Introduction to
Materials Management
UNIT IV
188
Operations Management
189
LESSON Introduction to
Materials Management
8
INTRODUCTION TO MATERIALS MANAGEMENT
CONTENTS
8.0 Aims and Objectives
8.1 Introduction
8.2 Materials Management
8.3 Role of Materials Management in a Business
8.4 Objectives of Materials Management
8.5 Functions of Materials Management
8.5.1 Material Requirement Planning
8.5.2 Buying or Purchasing
8.5.3 Logistics Transportation and Warehousing
8.6 Evolution of Materials Management
8.7 Importance of Materials Management
8.7.1 Expenditure on Materials Management
8.7.2 Profit Impact of Materials Management
8.8 Integrated Materials Management
8.9 Material Planning
8.9.1 Factors affecting Material Planning
8.9.2 Material Planning Process
8.10 Budgeting
8.10.1 Strategy, Planning and Budgeting
8.10.2 The Budget Period
8.10.3 Programme Budget and Responsibility Budget
8.10.4 Organization for Budgeting
8.10.5 The Budget Base
8.10.6 Production Budget
8.10.7 Materials and Purchases Budgets
8.11 Introduction to Value Analysis
8.11.1 The Value Analysis Method
8.11.2 Value Analysis Process
8.12 Purchase Functions and Procedures
8.13 Let us Sum up
8.14 Lesson End Activity
Contd
8.1 INTRODUCTION
Materials management is an essential business function. It is concerned with planning,
acquisition and flow of materials within the supply chain. Material is one of the four
basic resources (labour, material, equipment and capital) of any industrial or business
activity. For a long time, it was regarded as a routine function with less importance.
But over the years, with accelerating economic, technological, societal and
environmental changes, this function has become more important, more complex, and
more professional.
Materials management creates a competitive edge by delivering quality product(s) or
service on time and offering lower cost by cutting its own cost as well as cutting
purchased item costs, which account for over fifty per cent of the sales revenue, thus
imparting superior value.
However, it is complex as it confronts various issues including outsourcing, global
sourcing, size of supply base, shorter Lead time, smaller lot size, price determination,
mode/carrier selection, maintaining long-term relationship with suppliers, choosing
the right type of information technology, legal issues, etc.
It has evolved out of common sense or rule of thumb approach. It has organized
principles and a wealth of knowledge in the form of tools, techniques, models,
heuristics, systems and procedures, methodology and a huge database and is being
studied and the undergraduate, postgraduate and doctoral level in colleges/universities
and is practiced extensively in industry. Today, it finds an important place in an
organizations hierarchy and is manned by highly qualified professionals.
For our purposes, the materials function is an integrated approach to planning, 191
Introduction to
acquisition, conversion, flow, and distribution of materials. The paramount objective, Materials Management
of this function, is to reduce materials costs - more precisely, to reduce the total costs
associated with the acquisition and management of materials.
The materials function is a functional area composed of a number of sub-functions.
The sub-functions associated with it include:
Procurement: Total cost of ownership, the right time, in the right place;
Make or Buy: What to buy from who;
Material Planning: Product Line Specific Planning, Facility Location, Network
Design;
Inventory Management: How much to stock where, Trigger points,
Replenishment;
Stores and Warehousing: Storage layout, Order Processing, Receiving, Break
bulk, Pick Pack and Ship, What to stock and where; and
Materials Handling: How to move product, Packaging, Containerization.
192 these costs were not accounted separately and were generally included in
Operations Management
overheads. As such, their impact was not felt. But now their combined
contribution is measured, which is quite significant and provides good scope for
cutting cost.
In case of purchase by tenders, tenders or bids are invited from prospective suppliers. 193
Introduction to
Bids are opened and analyzed and the lowest or otherwise best bid is selected and Materials Management
purchase order is placed. In some cases, buyers go for Negotiation with short-listed
suppliers.
Purchasing process has several phases including:
Purchase requisition
Selection of suppliers
Ordering: pricing, terms and conditions and placement of purchase order
Follow-up
Receipt and inspection
Maintain records
Supplier Management supplier relations, evaluation and development
194 involving carefully chosen suppliers at an early stage in design and development, and
Operations Management
increasing integration of information system.
All of the above actions allowed purchasing to fulfill its role as an expense controller
for the organization and helped to increase regard for the purchasing department as a
contributor to Profit.
Towards the end of the twentieth century firms believed in purchasing fewer items.
Generally, they were purchasing raw materials and converting these into end products.
Even functions like education, hospitals, and townships were managed in-house. Then
the concept of core competency and a number of competent suppliers emerged.
Consequently, the concept of outsourcing emerged and firms tried to outsource items
which did not fall under their core competency.
Responsibility of outsourcing fell on the purchasing manager. This responsibility is on
the rise, making materials managers role a very important one. Table 8.1 presents the
evolution of materials management in brief.
Table 8.1: Evolution of Materials Management
Figure 8.1: Percentage distribution of the sales dollar for the average
US manufacturing concern in 1991
Over half of the income received from sales of manufactured products is spent on
the purchase of materials, services and equipment needed to produce these goods.
Figure 8.1, which shows the percentage distribution of sales revenue for the average
US manufacturing firms, supports this. This fact also highlights that materials
management function is a key area for cost reduction and innovation resulting in
increased Profit.
196
Operations Management 8.8 INTEGRATED MATERIALS MANAGEMENT
For running any industry or business, we need a number of resources. These resources
are popularly known as 5 M's of any Industrial activity i.e.
Men
Machines
Materials
Money
Management.
All these resources which are basic inputs, are important but their relative importance
depends upon the particular type of industry and also other environmental factors.
Earlier, when many modern machines were not even known, whole activity was
around men.
But now the importance has shifted from men to machines and in the present
environment materials are the life blood of any industry or business and for their
proper running, materials should be available at proper time in proper quantity at
proper place.
Traditionally, various activities related to managing materials were looked after by
various departments. While purchases were generally arranged by top management
with the assistance of a Purchase Agent or Purchase Officer, store keeping and stock
control was the responsibility of the production head with the assistance of a store
keeper or Stores Officer. Apart from these two main activities, distribution of
materials (mostly finished goods) was the responsibility of marketing.
After realizing the profitability potential of Materials Management function, when
attempts were made to exploit this potential, it was realized that there were many
problems in achieving the objectives due to inherent conflicts amongst various
departmental objectives. When a purchasing personnel wants to purchase in bulk to
get price discounts, inventory of the stores personnel becomes high. Similarly desire
of marketing personnel to have adequate stocks of finished goods in order not to loose
any opportunity of sale resorts in high inventory.
In the traditional set up one person could not be held responsible for all the functions
of materials management to achieve overall economy. Therefore necessity of placing
all the functions related to materials management e.g. purchasing, stocking, inventory
control and distribution under one department headed by an executive of status at par
with other departmental heads, was felt.
Thus evolved the concept of integrated materials management which can be defined as
the function which is responsible for the coordination of planning, selecting sources,
purchasing, moving, storing and controlling materials in an optimum manner so as to
provide a pre-decided service to the customer at a minimum cost.
198
Operations Management
Let us look at how, traditionally, material planning has been carried out. Materials 199
Introduction to
department (Inventory) and Purchase department are the two functions which had the Materials Management
onus on controlling cost. Material department maintains the inventory, receipts, issues
and plans for any new requirement based on "Re-Order Point", "Min-Max" and
various other methods.
In most of these methods, the experience of the individual is given a higher
importance. The quantity was decided by "average consumption" during a given
period. So the key requirement of this department is to keep as much as possible "low
stock/inventory". The Purchase department on the other hand has to procure the
material at the lowest price to reduce the material cost. Unit cost is low when volumes
increase. The tendency is to order for higher volumes to reduce cost. If we observe
carefully, this objective contradicts the Materials department objective. In the process,
there is no real gain in the material cost reduction program. Generally this tendency
leads to excess unwanted material and shortage of the most needed material.
8.10 BUDGETING
A budget is a quantitative expression of plans. It is commonly used by business firms,
governmental agencies, non-profit institutions, and even households. While there is
considerable variation in the scope, degree of formality, and level of sophistication
applied to budgeting, most of the well-managed business firms use a budget which is a
comprehensive and coordinated plan for the operations and resources of the firm. Such
a budget is developed by a formal and intricate process.
How are budgets useful? Budgets provide several benefits in that they:
induce managements to think systematically about the future
serve as a device for coordinating the complex operations of the business
provide a medium for communicating the plans of the firm
motivate managers at all levels to perform well
serve as a standard against which the actual performance may be judged
instructions on how the budgets have to be prepared, provides past data useful for 201
Introduction to
estimation purposes, offers aid in computing various budget figures, persuades people Materials Management
to submit their budgets on time, and assembles the budgets prepared by the line
organization. It should be emphasised that the budget director is responsible mainly
for the mechanics of budget preparation, not the substance of budgets themselves. The
line organization provides, by its decisions and judgements, this content. Commenting
on this, Robert Anthony says: "The budget organization is like a telephone company,
operating an important communication system; it is responsible for the speed,
accuracy, and clarity with which messages flow through the system, but not the
content of the messages themselves".
202 with this approach, a compromise solution may be worked out. The zero-base review
Operations Management
can be done once every four (or five) years and the incremental approach applied in
the intervening years.
Materials Budget
Materials used in a manufacturing unit are traditionally classified as direct and
indirect. Direct materials are materials which are directly identified with the product
and are visibly incorporated in it. Indirect materials cannot be traced directly to the
product. The materials budget generally is concerned only with direct materials.
Indirect materials and supplies are covered by the manufacturing overhead budget.
The materials budget shows the quantities, and often the prices, of materials planned
to be purchased.
Purchase Budget
This budget shows: (i) the quantities of each type of raw material to be purchased,
(ii) the schedule of purchases, and (iii) the estimated cost of purchases.
In developing the purchase budget, one has to take into account the following:
(i) the quantities specified in the materials budget,
(ii) the planned changes in material inventories,
(iii) re-order levels of various inventory items, and
(iv) economic order quantities of various inventory items.
203
8.11 INTRODUCTION TO VALUE ANALYSIS Introduction to
Materials Management
Lawrence Miles conceived of Value Analysis (VA) in the 1945 based on the
application of function analysis to the component parts of a product. Component cost
reduction was an effective and popular way to improve "value" when direct labor and
material cost determined the success of a product. The value analysis technique
supported cost reduction activities by relating the cost of components to their function
contributions.
Value analysis defines a "basic function" as anything that makes the product work or
sell. A function that is defined as "basic" cannot change. Secondary functions, also
called "supporting functions", described the manner in which the basic function were
implemented. Secondary functions could be modified or eliminated to reduce product
cost.
As VA progressed to larger and more complex products and systems, emphasis shifted
to "upstream" product development activities where VA can be more effectively
applied to a product before it reaches the production phase. However, as products have
become more complex and sophisticated, the technique needed to be adapted to the
"systems" approach that is involved in many products today.
The first VALUE ANALYSIS (VA) program was established in the General Electric,
USA by about 1947, since then the programme has received considerable attention
and many successful applications have been reported. Though the technique started
with analysis of purchased items it has been extended to manufactured items as well.
The idea behind Value Analysis is not new. The approach to the problem essentially
differs from that of the other Cost Reduction techniques. A customer when buying a
product weighs its functional and other features (appearance, attractiveness, get up)
against its price and judges the VALUE of the product. Manufacturer in turn, in order
to enhance the VALUE of his products must ensure that he offers all the necessary
functional features at the lowest possible price. This functional approach is the basic
criteria of VALUE ANALYSIS. It tries to obtain a FUNCTION and NOT the
PART, at a lesser COST.
This has the fundamental base, as the USER is not at all interested as to how the part
looks like, or what it is made of, as long as the DESIRED FUNCTION is performed to
HIS satisfaction along with the required level of Quality & Reliability.
204 solution and not how it is to be accomplished. How the function is identified
Operations Management
determines the scope, or range of solutions that can be considered.
That functions designated as "basic" represent the operative function of the item or
product and must be maintained and protected. Determining the basic function of
single components can be relatively simple. By definition then, functions designated
as "basic" will not change, but the way those functions are implemented is open to
innovative speculation.
As important as the basic function is to the success of any product, the cost to perform
that function is inversely proportional to its importance. This is not an absolute rule,
but rather an observation of the consumer products market. Few people purchase
consumer products based on performance or the lowest cost of basic functions alone.
When purchasing a product it is assumed that the basic function is operative. The
customer's attention is then directed to those visible secondary support functions, or
product features, which determine the worth of the product. From a product design
point of view, products that are perceived to have high value first address the basic
function's performance and stress the achievement of all of the performance attributes.
Once the basic functions are satisfied, the designer's then address the secondary
functions necessary to attract customers. Secondary functions are incorporated in the
product as features to support and enhance the basic function and help sell the product.
The elimination of secondary functions that are not very important to the customer
will reduce product cost and increase value without detracting from the worth of the
product.
The cost contribution of the basic function does not, by itself, establish the value of
the product. Few products are sold on the basis of their basic function alone. If this
were so, the market for "no name" brands would be more popular than it is today.
Although the cost contribution of the basic function is relatively small, its loss will
cause the loss of the market value of the product.
One objective of value analysis or function analysis, to improve value by reducing the
cost-function relationship of a product, is achieved by eliminating or combining as
many secondary functions as possible.
A variation of the Function-Cost Matrix is the Value Analysis Matrix. This matrix was 205
Introduction to
derived from the Quality Function Deployment (QFD) methodology. It is more Materials Management
powerful in two ways. First, it associates functions back to customer needs or
requirements. In doing this, it carries forward an importance rating to associate with
these functions based on the original customer needs or requirements. Functions are
then related to mechanisms, the same as with the Function-Cost Matrix. Mechanisms
are related to functions as either strongly, moderately or weakly supporting the given
function. This relationship is noted with the standard QFD relationship symbols. The
associated weighting factor is multiplied by customer or function importance and each
columns value is added.
These totals are normalized to calculate each mechanism's relative weight in satisfying
the designated functions. This is where the second difference with the Function-Cost
Matrix arises. This mechanism weight can then be used as the basis to allocate the
overall item or product cost. The mechanism target costs can be compared with the
actual or estimated costs to see where costs are out of line with the value of that
mechanism as derived from customer requirements and function analysis.
206 A demand should not be split into small quantities for the sole purpose of avoiding
Operations Management
the necessity of taking approval of the higher authority required for sanctioning
the purchase of the original demand.
prices to be paid for such goods shall not exceed those stipulated in the rate contract 207
Introduction to
and the other salient terms and conditions of the purchase should be in line with those Materials Management
specified in the rate contract. The Ministry/Department shall make its own
arrangement for inspection and testing of such goods where required.
E-Procurement
Purchase of goods through electronic mode of interface with tenderers and IT enabled
management of the entire procurement process (notice inviting tenders, supply of
tender documents, receipt of bids, evaluation of bids, award of contract, and execution
of contract through systematic enforcement of its various clauses and tracking of
claims, counter-claims and payments) is gradually gaining popularity. In order to cut
down transaction costs and improve efficiency and transparency, the Government
aims to make it mandatory for all the Ministries/Departments including the Central
Public Sector Undertakings under their administrative control to conduct all
their procurements electronically beyond 31st December, 2006. The Ministries/
Departments have been advised to fix appropriate cut-off points in terms of the size of
procurement to switch over to e-procurement. The Director General (Supplies &
Disposal) has made significant progress in this direction and the National Informatics
Centre is engaged in pilot projects to design a secure IT solution addressing concerns
like encryption/decryption of bids, digital signatures, secure payment gateways,
date/time stamp for activities, access control, etc. The Ministries/Departments have
already been directed to publicize all their tenders on their websites as the first step
towards full-fledged e-procurement. The Ministries/Departments are advised to
proactively engage themselves in articulating user needs in the development of IT
systems for e-procurement. The system should be secure, capable of maintaining
complete confidentiality at appropriate stages of the bidding process, so that the
tenderers feel confidence in electronically transmitting their queries and bids.
However, as all the tendering firms may not have the facility of transmitting their
quotations through e-mail, the Ministry/Departments should allow the receipt of
quotations through hard copies as well as by e-mail. The closing date & time for
receipt of tenders should be identical for both types of tenders.
Check Your Progress 2
Fill in the blanks:
1. Production manager is answerable for parts
2. Logistics is concerned with the management of warehousing (receiving,
storing and issue of materials) and ..
208
Operations Management 8.14 LESSON END ACTIVITY
Do you think today materials budgets are relevant in an ever changing business
scenario? Give reasons in support of your answer.
8.15 KEYWORDS
Materials Management: It is concerned with planning, acquisition and flow of
material in the supply chain.
Material Productivity: The output achieved from an activity divided by the material
inputs.
Materials: The physical items that are necessary to produce the goods and services we
consume.
CYP 2
1. produced in-house
2. flow of materials
Prahlad, CK, Core Competency Revisited, Enterprise, October 1993, p.20. Also quoted 209
Introduction to
in Dobler, DW, and Burt DN, Production and Supply Chain Management Materials Management
(6th Edition), Tata McGraw-Hill, p.23. 1996.
Syson, Russell, Improving Purchase Performance, Pitman Publishing, 1992.
Prime source of this section is the book, Purchasing, Principle and Application
(8th Edition) by Farrel, Paul K, Giunipero, Larry C and Kolchin, Michael G,
Published by Prentice Hall, 1991.
Dobler, DW and Burt, DN, Production and Supply Chain Management (6th Edition),
Tata McGraw-Hill, Figure 2-3, Page 28, 1996.
210
Operations Management
LESSON
9
INVENTORY CONTROL
CONTENTS
9.0 Aims and Objectives
9.1 Introduction
9.2 Inventory Management
9.3 Types of Inventory
9.3.1 Manufacturing Inventory
9.3.2 Types of Inventory by Function
9.4 Safety Stock
9.5 Importance of Inventory
9.5.1 Manufacturing of Inventory
9.5.2 Functions of Inventory
9.6 Inventory Costs
9.6.1 Holding (or Carrying) Costs
9.6.2 Cost of Ordering
9.6.3 Setup (or Production Change) Costs
9.6.4 Shortage or Stock-out Costs
9.7 Inventory Classification
9.7.1 ABC Classification
9.7.2 Other Models
9.8 Fundamental Approaches to Manage Inventory
9.9 Fixed-order Quantity Approach
9.9.1 Fixed-order Quantity Modeling
9.9.2 Inventory Model with Uncertainty
9.9.3 Fixed-order Interval Approach
9.10 Inventory Control
9.10.1 Reasons for Maintaining Inventory
9.10.2 The Eyeball System
9.10.3 Reserve Stock (or Brown Bag) System
9.10.4 Perpetual Inventory Systems
9.10.5 Stock Control
9.10.6 Inventory Control Records
Contd...
9.1 INTRODUCTION
The term inventory means any stock of direct or indirect material (raw materials or
finished items or both) stocked in order to meet the expected and unexpected demand
in the future. A basic purpose of inventory management is to control inventory by
managing the flows of materials. It sets policies and controls to monitor levels of
inventory and determine what levels should be maintained, when stock should be
replenished, and how large orders should be.
212 entire production operation can be halted. This would mean a heavy loss to the firm.
Operations Management
To avoid starting a production run and then discovering the shortage of a vital raw
material or other component, firms maintain inventories.
The goal of effective inventory management is to minimize the total costs - direct and
indirect - that are associated with holding these assets. However, the importance of
inventory management to the company depends upon the extent of investment in
inventory. As the value of the inventory goes up, the criticality of the function in
Inventory Management enables an organization to meet or exceed customers'
expectations of product availability while maximizing net profits or minimizing costs.
What is Inventory?
The term inventory means any stock of direct or indirect material (raw materials or
finished items or both) stocked in order to meet the expected and unexpected demand
in the future. A basic purpose of inventory management is to control inventory by
managing the flows of materials. It sets policies and controls to monitor levels of
inventory and determine what levels should be maintained, when stock should be
replenished, and how large orders should be.
3. Finished goods: When the leather items are completely ready to sell at craft 213
Inventory Control
shows or other venues, they are finished goods. The finished goods inventory also
consists of the cost of raw materials, labor and manufacturing overhead, now for
the entire product.
214 Here, we shall present the calculation of safety stock of P and Q systems using
Operations Management
approximate method and considering the criteria as given below:
Specified probability of no stock out
Specified Fraction of demand fulfillment.
Wholesale: The wholesaler purchases large quantities from manufacturers and sells 215
Inventory Control
small quantities to retailers. He provides the capability to provide retail customers
with assorted merchandise from different manufacturers in smaller quantities.
Expansion of product lines has increased the width and inventory risk. Where products
are seasonal, the wholesaler has to take an inventory position far in advance of selling.
Retail: For a retailer, inventory management is fundamentally a matter buying and
selling. The retailer purchases a wide variety of products and markets them. The prime
emphasis in retailing is on inventory turnover and direct product profitability.
Turnover measures inventory velocity and is calculated as the ratio of annual sales
divided by average inventory.
Not all types of inventories are held by all businesses. Table 9.1 summarizes the
inventory types held by different kinds of business organizations. Retail service
organizations hold only supplies. Retail sales organizations, wholesalers and
distributors hold both supplies and finished products. Projects and intermittent
processes in manufacturing hold supplies, raw materials and in-process inventory.
However, most continuous manufacturing organizations hold all the different types of
inventory.
Table 9.1: Organizational Inventories
Type of Inventory
Type of Organization Raw In-Process Finished
Supplies
Materials Inventory Goods
A. Retail systems
1. Sale of services *
2. Sale of goods * *
B. Wholesale/Distribution * *
C. Manufacturing systems
1. Projects * * *
2. Intermittent process * * *
3. Continuous process * * * *
216 Anticipation Stock: Stock kept at hand to meet seasonal fluctuations in demand or
Operations Management
to meet the shortfall caused by erratic production. Also called build stock or
seasonal stock.
Pipeline Stock: This is stock that is on the books of the firm but is not physically
available, e.g., stock in transit.
Decoupling Stock: A buffer stock used between productions processes to make
one process independent of the other.
Psychic Stock: Used in retail, it is retail display inventory used for stimulating
demand.
Production If I can produce larger lot sizes, I can reduce per unit cost and function
efficiency.
Purchasing I can reduce the per unit cost if I buy large quantities in bulk.
Warehousing I am out of space. I can't fit anything else in the building.
Finance Where am I going to get the funds to pay for the inventory? The levels
should be lower.
These comments in Table 9.2 place the focus on the functional significance of
inventory for different departments in the organization.
Marketing would like to have a large inventory so that customer service can be
improved and sales can increase.
Production would like to minimize set-up costs and increase worker productivity by
having large production runs adding on to the in-process inventory (work-in-progress
and finished goods).
Purchasing can bring down prices by buying in bulk and obtaining quantity discounts.
Stores or warehousing has storage constraints in storing and moving large quantities
of stock.
But the bottom line is equally important. All these requirements can be met at a cost.
Larger inventories mean more capital investment, lower cash flows, idle inventory,
and lower profitability. This is reflected in the comments made by Finance.
All this is clearly seen below in Table 9.3 the whole picture of inventory becomes
clear when seen in the context of the different functional objectives of departments
within the organization.
Table 9.3: Functional Significance of Inventory
Functional Functional Inventory
Inventory Goal
Area Responsibility Inclination
Maximize customer
Marketing Sell the Product High
service
Production Make the Product Efficient lot sizes High
Purchasing Buy required materials Low cost per unit High
Finance Provide working capital Efficient use of capital Low
Engineering Design the product Avoid obsolescence Low
As will be apparent from Table 9.3, some functional areas find inventory desirable,
while others do not. What is important to note is that both the inclination to hold
inventory and the inventory goals of the different functions are significantly different.
For example, inventory can be used to promote sales by reducing customers waiting
time, improve work performance by reducing the number of setups, or protect
218 employment levels by minimizing the cost of changing the rate of production.
Operations Management
Therefore, it is desirable to maintain inventories in order to enhance stability of
production and employment levels.
The functionality of inventory becomes clear only when it is considered in light of all
quality, customer service and economic factors - from the viewpoints of purchasing,
manufacturing, sales and finance. Inventory build-up is important as it is meant to
permit them to meet their functional objectives.
The major issue in inventory decisions is how to reconcile the differences between the
different functional requirements of the different parts of the organization and the
goals of the organization as a whole. No matter what the viewpoint of each department
is or what each function desires, in the ultimate analysis; effective inventory
management has to provide an economic advantage that is essential to organizational
competitiveness.
A significant percentage of assets of many firms are tied up in inventories. This could
range from fifteen per cent to nearly fifty percent of the capital utilized in a typical
firm. Holding of inventory, therefore, reflects a type of risk to the firm, these are risks
related to the capital investment and the potential for obsolescence of the inventory.
For the manufacturer, inventory risk has a long-term dimension. Although retailers or
wholesalers have a wider product line than the manufacturer, the manufacturer's
inventory commitment is relatively deep and of long duration. Wholesaler risk
exposure is narrower but deeper and of longer duration than that of retailers. Although
retailers assume a position of risk on a variety of products, the position on anyone
product is not deep. This does not mean that their risk is lesser; due to the variety of
merchandise the risk is wider. For example, a typical supermarket carries more than
10,000 SKUs. This variety of merchandise reflects the risk of the retailer. If an
individual enterprise plans to operate at more than one level of the distribution
channel, it must be prepared to assume additional inventory risk.
Only when considered in light of all quality, customer service and economic factors
from the viewpoints of purchasing, manufacturing, sales and financedoes the whole
picture of inventory functionality become clear. No matter the viewpoint, effective
inventory management is essential to organizational competitiveness as excessive
inventory is a drain to the profitability of the organization. This is discussed in the
next section.
Check Your Progress 1
Broadly speaking, some other functions of inventories are:
1. To protect against unpredictable variations in demand and supply
2. To take the advantage of price discounts by bulk purchases
3. To take the advantage of batches and longer production run
4. To provide slack to allow changes in marketing plans, etc; and
5. To facilitate intermittent production.
Which of these statements are true?
219
9.6 INVENTORY COSTS Inventory Control
The heart of inventory decisions lies in the identification of inventory costs and
optimizing the costs relative to the operations of the organization. Therefore, an
analysis of inventory is useful to determine the level of stocks. The resultant stock
keeping decision specifies:
1. When items should be ordered,
2. How large the order should be?
3. When and how many to deliver?
It must be remembered that inventory is costly and large amounts are generally
undesirable. Inventory can have a significant impact on both a companys productivity
and its delivery time. Large holdings of inventory also cause long cycle times which
may not be desirable as well. What are the costs identified with inventory?
The costs generally associated with inventories are shown in Figure 9.2. The different
components of cost are discussed below:
One major component of cost associated with inventory is the cost of replenishing it.
If a part or raw material is ordered form outside suppliers, and places orders for a
given part with its supplier three times per year instead of six times per year, the costs
to the organization that would change are the variable costs, and which would
probably not are the fixed costs.
There are costs incurred in maintaining and updating the information system,
developing vendors, evaluating capabilities of vendors. Ordering costs also include all
the details, such as counting items and calculating order quantities. The costs
associated with maintaining the system needed to track orders are also included in
ordering costs. This includes phone calls, typing, postage, and so on.
Though Vendor development is an ongoing process, it is also a very expensive
process. With a good vendor base, it is possible to enter into longer-term relationships
to supply needs for perhaps the entire year. This changes the when to how many to
order and brings about a reduction both in the complexity and costs of ordering.
different product. If there were no costs or loss of time associated in changing form 221
Inventory Control
one product to another, many small lots would be produced, permitting reduction in
inventory levels and the resultant savings in costs.
according to their importance and increased attention is paid to the items that are more 223
Inventory Control
important. For instance, high-value, high-usage items must be tracked carefully and
continuously but certain parts with a relatively low value or infrequent use can be
monitored loosely.
The ABC Analysis is also a guide to physical count of items of inventory. Counts are
conducted depending on the importance of inventory items. A items are counted
frequently, B items less frequently and C items are counted the least frequently.
Accuracy of the count also depends on the classification. APICS recommends 0.2
percent for A items, 1 percent for B items and 5 percent for C items.
However, ABC analysis should be used prudently. It cannot always be applied across
the board. Some categories of items where the application of ABC analysis is fraught
with high risk are identified below:
Difficult Procurement Items
Short Shelf Life
Large Storage Space Requirements
Items Operational Criticality
Likelihood of Theft
Difficult Forecast Items
Other similar types of classifications are the XYZ Classification, VED Classification,
and the HML classification of inventory. The basic difference between the ABC
Classification and the XYZ Classification is that it is based on the inventory in stock
rather than usage.
The VED Classification is based on the criticality of the inventory item. In normal
practice, items in the V category are often monitored manually; in addition to the
computer monitoring that may be in place. The HML reflects a classification based on
the unit price of the item. Obviously, the H category items require additional
attention, especially if the lead times are long, as it may often be in imported
components. The time triggered reorder system has some advantages in production
cycling, in such high value items.
All these techniques are used to focus management attention in deciding on the degree
of control necessary for different items in the inventory. However, it should be kept in
mind that changes in the business environment, e.g. customer demand patterns or
material costs, can cause material item classifications to change. This in turn can
affect key planning & scheduling decisions.
Inventory decisions are made on issues relating to cost and to customer service 225
Inventory Control
requirements. Increasing investments in inventory generally result in higher levels of
customer service, but can options be identified that will result in higher levels of
customer service along with reduced investments in inventories. That is the challenge.
However, several factors make this an achievable objective:
1. More responsive order-processing and order-management systems;
2. Enhanced ability to strategically manage logistics information;
3. More capable and reliable transportation resources; and
4. Improvements in the ability to position inventories so that they will be available
when and where they are needed.
226 Continuing with the Edsel example, Suppose, Ford decided to manufacture 15,000
Operations Management
units of the automobile for the first year based on a forecast of the independent
demand. Based on this, Ford knew exactly how many steering wheels are needed and
when. This is because the demand for these items is dependent on the production
schedule of 15,000 automobiles for the year. The steering wheels are dependent
demand items because:
1. The firm controls their demand through the production schedule, and
2. Their demand is tied to the production of automobiles.
Dependent demand, in a manufacturing unit, is based on the sub-assemblies or
components or raw materials that are part of the BOM for the end items. The demand
for these items is indirect or comes from the finished products demand when we
explode the BOM (Bill of Material).
Material Planning: Materials Planning has been automated, to a large extent, in many
organizations through the use of MRP I and MRP II. MRP I, is also called
Materials Requirement Planning, and MRP II is called Manufacturing Resource
Planning. These are software solutions that integrate many areas of the manufacturing
enterprise into a single entity for planning and control purposes in order to minimize
inventory when the demand is dependent. It uses the basic principal that external
demand is generally independent and internal demand is generally dependent. This
genre of planning starts with aggregate planning and includes MRP I and MRP II.
The push/pull relationship is that between a product or piece of information and who 227
Inventory Control
is moving it. Customers "pull" things towards themselves, while a producer "pushes"
things toward customers.
Another way of looking at the transformation operations of any product is whether
they are executed in response to a customer order or in anticipation of customer
orders. Pull processes are initiated by a customer order whereas push process are
initiated and performed in anticipation of customer orders. Engineered-to-Order
(ETO) and Made-to-Order (MTO) are based on pull processes, whereas Made-to-
Stock (MTS) is based on a push process. Assembled-to-Order (ATO) is a combination
of pull and push processes.
For example, Tata Steel collects orders that are similar enough to enable it to
consolidate demand and produce specific products in large quantities. In this case, the
manufacturing cycle is reacting to customer demand (referred to as a pull process).
The other example is Hindustan Lever Ltd, a consumer products firm, which must
produce in anticipation of demand. In this case the manufacturing cycle is anticipating
customer demand (referred to as a push process).
A push/pull view of the transformation processes is very useful when considering
strategic decisions relating to planning for material requirements. This view forces a
more global consideration of operations as they relate to fulfilling the customers
order.
Push is a planning based approach and is more appropriate for dependent demand,
scale economies, supply uncertainties, source capacity limitations, or seasonal build-
ups. In general, push systems are more prevalent in organizations having greater
logistics sophistication.
Customer
Order PULL
Cycle PROCESS Customer Order Cycle Customer
Retailer
Customer Replenishment and
Order Manufacturing Cycle
Arrives
Manufacturer
Procurement PUSH
Procurement Cycle
Manufacturing, PROCESS Supplier
Replenishment Cycle
228 A process or market orientation that has more pull processes has a significant impact
Operations Management
on reducing the requirement of inventory in the system. Just like in the case of
collaborative forecasting, more pull processes can help eliminate excess inventory as
it minimizes the inventory carried to cover uncertainty due to independent demand.
Just-in-Time (JIT) is, in a sense, a pull system. The firm places an order for an item
only when the amount on hand reaches a certain level, thus pulling inventory through
the system as needed. There is a time phased approach to inventory scheduling and
inventory receipt. The Economic Order Quantity (EOQ) approach, which we will
study in this lesson, on the other hand is generally pull based, but is quite often a
hybrid system.
These differences and the nature of operations tend to influence the choice of the 229
Inventory Control
inventory system that is more appropriate.
No Is position
< Recorder point?
Yes
230 4. Lead time is zero or constant and it is independent of both demand as well as the
Operations Management
quantity ordered.
5. The entire quantity is delivered as a single package (or produced in a single run).
The objective of the model is to minimize the average annual variable costs. And it
provides a solution to the problem of determining when an order should be placed and
how much should be ordered. The schematic representation of the EOQ Model is
given in Figure 9.7. It shows the inventory level vs. time relationship.
Inventory Level Q
Time T T
1. EOQ Model with Lead Time: In the above discussion we considered that lead 231
Inventory Control
time is zero. However, if lead time is constant the above results can be used
without any modification.
Inventory Level
Reorder Level, R0
L L L
Time
T T T
T1 T1 T1 Time
T2 T2 T2
T T T
Using these concepts, we can tackle problems with constant lead time and variable 235
Inventory Control
demand. Data has been provided in Table 9.7 to illustrate such a problem. In the
problem, it is assumed that the weekly demand is variable and the lead time is
constant at 2 weeks.
Table 9.7: Calculation of Lead Time Demand
Demand Probability Demand Probability Lead time Probability
first week p(D) second week p(D) demand (col. 2)(col. 4)
(D) (D) (col. 1)(col. p(M)
3) (M)
1. 0.60 1 0.60 2 0.36
3 0.30 4 0.18
4 0.10 5 0.06
2. 0.30 1 0.60 4 0.18
3 0.30 6 0.09
4 0.10 7 0.03
3. 0.10 1 0.60 5 0.06
3 0.30 7 0.03
4 0.10 8 0.01
The basic data in Table 9.7, in columns 1 to 3 are used to calculate the lead time
demand and the probability of lead time demand, which are given in columns 5 and 6.
The lead time demand obtained and the probability of lead time demand obtained in
Table 9.7 have been rearranged in Table 9.8 to obtain the distribution.
Table 9.8: Lead Time Demand and Probability
Lead time demand (M) Probability P(M)
0 0
1 0
2 0.36
3 0
4 0.36
5 0.12
6 0.09
7 0.06
8 0.01
Total 1.00
We have worked out the example of constant lead time and variable demand above.
A reasonable approximation method for determining model parameters is to use the
EOQ model to solve for the order size. The time between orders is then simply the
order quantity divided by annual demand. The standard deviation of demand during
the order interval is found by determining the daily standard deviation of demand and
multiplying by the square root of the length of the order interval. Different
relationships emerge when there is:
1. Variable demand and constant lead time,
2. Constant demand with variable lead time, and
3. Variable demand with variable lead time.
236 Each of these relationships is shown below. The notations that are used are as follows:
Operations Management
B= Reorder point in units.
M = Lead time demand in units (a random variable).
f (M) = Probability density function of lead time demand.
p (M)= Probability of a lead time demand of M units.
L = Expected lead time
Lm = Maximum lead time
= Standard deviation of lead time demand
Q = Lot size
S = Set-up cost or Ordering Cost ( /year)
SS = Safety Stock
D = Annual Demand
P = Unit Price ( /unit)
H = Holding or Carrying cost per Unit ( /Unit)
F = Inventory Carrying Charges Factor
Q* = Economic Order Quantity (to be determined)
Figure 9.12: Inventory Risk: Variable Demand and Constant Lead Time
The relationships that emerge when Demand is variable and Lead Time is constant are
shown in Figure 9.12. The figure shows the relationships that are given below:
B SS = Expected lead time demand
B - J = Minimum lead time demand
B + W = Maximum lead time demand
p(M>B) = Probability of a stock out
Figure 9.13: Inventory Risk: Variable Demand and Variable Lead Time
The relationships when there is constant demand with variable lead time are shown in 237
Inventory Control
Figure 9.13. The relationships that emerge from this configuration are given below:
p (M > B) = Probability of a stock out
B S = Expected lead time demand
B + W = Maximum lead time demand
The lot order size is given by the expression:
Q* = 2DS / H (1)
And the reorder point is given by:
B = M + SS (2)
When both demand and lead times are probabilistic, the basic procedure for finding
operating doctrines is a convergence procedure. This is a directed trial an error
method. For the quantity/reorder point model, the order quantity is computed
assuming constant demand. Then the reorder point is calculated using the computed
order quantity. This value is then used to recalculate the order quantity and recalculate
the reorder point. Eventually, the order quantity the reorder point coverage to their
optimal values. The example of ABC Ltd. illustrates the method.
ABC Ltd. for one of its class A items, has an ordering cost is 5,400.00, the
inventory holding cost is 40 percent, and the cost per unit is 40.00.
D = Annual demand = 8 150 = 1200 units
P = Unit purchase cost = 40.00
S = Ordering Cost = 5400.00
F = Holding Cost = 40%
The lead time to deliver the item is 10 days. The Lead time demand is given in the
table below.
Lead time demand Probability P(M) Lead time demand Probability P(M)
(M) (M)
0 0 1 0
2 0.36 3 0
4 0.36 5 0.12
6 0.09 7 0.06
8 0.01 Total 1.00
What is the lowest cost reorder point if the stock out cost is 5 per unit?
Using the Economic Order Equation:
Q* = (2DS/H) = (2DS/FP) = EOQ
= (2 5400 1200)/(0.40 40) = 900 units.
Reorder Level: (RB) = L D = (10/365) 1200 33 units
= (34 33) 0.36 + (34 33) 0.00 + (34 33) 0.36 + (34 33) 0.12 +
(34 33) 0.09 + (34 33) 0.06 + (34 33) 0.01
= 1 unit
TCS = Holding Cost + Stock out Cost
= (B M) H + SCS E (M>B)/ Q
TCS = (34 - 33) 1 + 5400 2 1/ 900
= 1 + 12 = 13.00
8
B = 35 E (M > B) = ( M 33) p ( M )
2 1
= (36 33) 0.12 + (36 33) 0.09 + (36 33) 0.06 + (36 33) 0.01
= 1.12 units
TCS = (36 33) 1 + 5400 2 1.12/ 900
= 4 + 13.44 = 17.44
8
B = 37 E (M > B) = ( M 33) p ( M )
5 1
The models that emanate from fixed-order system are for perpetual systems that
require continual monitoring of inventory. Every time a withdrawal from inventory or
an addition to inventory is made, records must be updated.
In comparison with the basic EOQ approach: the fixed interval model does not require
close surveillance of inventory levels; thus, monitoring is less expensive. The fixed-
time models are similar to batch processing systems, counting takes place only at the
review period. The firm can order low-valued items infrequently and in large
240 quantities, checking only infrequently to determine exactly how much is on hand at
Operations Management
any particular time.
In many retail merchandising systems, a fixed-time period system is used. Sales
people make routine visits to customers and take orders for their complete line of
products. Inventory, therefore, is counted only at particular times, such as every week
or every month or when the suppliers visit is due. Sometimes, this is also resorted to
in order to combine orders to save transportation costs.
Inventory control involves the procurement, care and disposition of materials. There 241
Inventory Control
are three kinds of inventory that are of concern to managers:
1. Raw materials,
2. In-process or semi-finished goods, and
3. Finished goods.
If a manager effectively controls these three types of inventory, capital can be released
that may be tied up in unnecessary inventory, production control can be improved and
can protect against obsolescence, deterioration and/or theft.
242 open stock. At this time, a reorder is immediately placed. If the reserve stock quantity
Operations Management
has been calculated properly, the new shipment should arrive just as the last of the
reserve stock is being used.
In order to calculate the proper reserve stock quantity, it is necessary to know the rate
of product usage and the order cycle delivery time. Thus, if the rate of product units
sold is 100 units per week and the order cycle delivery time is two weeks, the
appropriate reserve stock would consist of 200 units (100u x 2w). This is fine as long
as the two-week cycle holds. If the order cycle is extended, the reserve stock
quantities must be increased. When the new order arrives, the reserve stock amount is
packaged again and placed at the rear of the storage area.
This is a very simple system to operate and one that is highly effective for virtually
any type of organization. The variations on the reserve stock system merely involve
the management of the reserve stock itself. Larger items may remain in inventory but
be cordoned off in some way to indicate that it is the reserve stock and should trigger a
reorder.
that provides the level of information required to make knowledgeable decisions about 243
Inventory Control
effective inventory management.
Most smaller operations today, except for the very smallest, are using some form of a
perpetual online system to record the movement of inventories into and out of their
facilities. In a retail operation, the clerk at the register merely scans the ticket with a
reader, and the system shows the current price and removes the item from the
inventory control system. A similar process occurs in a manufacturing operation,
except that the "sale" is actually a transfer of the inventory from control to production.
This is a particularly critical system in a large operation such as a grocery store where
they regularly maintain 12,000 plus items. Often a vendor will provide on-site or
computerized assistance needed to help their smaller customers maintain a good
understanding of their own inventory levels and so keep them in balance.
244 serve to document ordering habits and procedures and so may be used to help reveal
Operations Management
and/or resolve future potential problems.
Returned goods files provide a continuous record of merchandise that has been
returned to suppliers. They should indicate amounts, dates and reasons for the returns.
This information is useful in controlling debits, credits and quality Issues.
Price books, maintained in alphabetical order according to supplier, provide a record
of purchase prices, selling prices, markdowns, and markups. It is important to keep
this record completely up to date in order to be able to access the latest price and profit
information on materials purchased for resale.
On the other hand, because suppliers have problems with inventory control, just as 245
Inventory Control
sellers do, they may be interested in making deals to induce customers to purchase
inventories off-season, usually at substantial savings. They want to shift the carrying
costs of purchase and storage from the seller to the buyer. Thus, there are seasonal
implications to inventory control as well, both positive and negative. The point is that
these seasonable implications must be built into the planning process in order to
support an effective inventory management system.
246 Stock turnover is really the way businesses make money. It is not so much the profit
Operations Management
per unit of sale that makes money for the business, but sales on a regular basis over
time that eventually results in profitability. The stock turnover rate is the rate at which
the average inventory is replaced or turned over, throughout a pre-defined standard
operating period, typically one year. It is generally seen as the multiple that sales
represent of the average inventory for a given period of time.
Turnover averages are available for virtually any industry or business maintaining
inventories and having sales. These figures act as an efficient and effective benchmark
with which to compare the business in question, in order to determine its effectiveness
relative to its capital investment. Too frequent inventory turns can be as great a
potential problem as too few. Too frequent inventory turns may indicate the business
is trying to overwork a limited capital base, and may carry with it the attendant costs
of stock-outs and unhappy and lost customers.
Stock turns or turnover, is the number of times the "average" inventory of a given
product is sold annually. It is an important concept because it helps to determine what
the inventory level should be to achieve or support the sales levels predicted or
desired. Inventory turnover is computed by dividing the volume of goods sold by the
average inventory. Stock turns or inventory turnover can be calculated by the
following equations:
Cost of Goods Sold
Stock Turn =
Average Inventory at Cost
Or
Sales
=
Average Inventory at Sales Value
If the inventory is recorded at cost, stock turn equals cost of goods sold divided by the
average inventory. If the inventory is recorded at sales value, stock turn is equal to
sales divided by average inventory. Stock turns four times a year on the average for
many businesses. Jewelry stores are slow, with two turns a year, and grocery stores
may go up to 45 turns a year.
If the dollar value of a particular inventory compares favorably with the industry
average, but the turnover of the inventory is less than the industry average, a further
analysis of that inventory is needed. Is it too heavy in some areas? Are there reasons
that suggest more inventories are needed in certain categories? Are there conditions
peculiar to that particular firm? The point is that all markets are not uniform and
circumstances may be found that will justify a variation from average figures.
In the accumulation of comparative data for any particular type of firm, a wide
variation will be found for most significant statistical comparisons. Averages are just
that, and often most firms in the group are somewhat different from that result.
Nevertheless, they serve as very useful guides for the adequacy of industry turnover,
and for other ratios as well. The important thing for each firm is to know how the firm
compares with the averages and to determine whether deviations from the averages
are to its benefit or disadvantage.
9.12 JUST-IN-TIME
Just-in-Time (JIT) is a term that has often been used interchangeably with Lean
Manufacturing. Some say it is a predecessor to Lean Manufacturing, but in any case, it
is an essential part of lean manufacturing.
JIT is a management philosophy that strives to eliminate sources of manufacturing
waste by producing the right part in the right place at the right time. Waste results
from any activity that adds cost without adding value such as moving and storage. JIT
improves profits and return on investment by reducing inventory levels, reducing
variability, improving product quality and reducing production and delivery lead
times. In a JIT system, underutilized (excess) capacity is used instead of buffer
inventories to hedge against problems that may arise.
Just-in-time is a movement and idea that has gained wide acceptance over the past
decade. As companies became more and more competitive and the pressures from
Japan's continuous improvement culture mounted, other firms were forced to find
innovative ways to cut costs and compete. The notion of pushing materials in large
quantities no longer made sense. Both the financial costs and the required resources of
doing so are counter productive in the long run. It is wiser to deliver materials only
just before they are needed and only in the quantity required.
A firm cannot implement a JIT system by itself; it must have the complete cooperation
of its entire Supply Chain. A large amount of information is needed for a JIT system
to operate well. It demands partnerships to be formed and nurtured, almost to the point
at which an entire supply chain operates as one firm. Examples of these kinds of
partnerships are everywhere in todays business world.
9.13 KANBAN
Kanban is a Japanese word meaning flag or signal and is a visual aid to convey the
message that action is required. The Kanban inventory control system was an integral
part of TPS and some aspects of the Kanban have been discussed in the 'pull concept'.
JIT uses a Kanban system. It works on the basis that each process on a production line
pulls just the number and type of components the process requires, at just the right
time. Kanban is usually a physical card but other devices can be used. A Kanban is a
card that is attached to a storage and transport container. It identifies the part number
248 and container capacity along with other information. There are two common types of
Operations Management
Kanban systems used; the one-card system and the two-card system.
Lean Manufacturing strives to maximize long-term profitability and growth. Kanbans 249
Inventory Control
help simplify planning and to fine-tune production to meet changing customer demand
of up to 10%. The system requires planned monthly and weekly production
schedules. Kanbans simplify day-to-day flexibility, hence changes to the production
schedule only need to be given to the final assembly process and then automatically
work their way back up the line.
Kanban systems can be tightened by removing cards or by reducing the number of
parts on a pallet. The effect will be to speed the flow through the process and hence
reduce lead times. However, it also makes the system more vulnerable to breakdowns
and other causes of dislocation. By identifying the areas within the line that are
causing disruption, efforts can be made to improve them. Thus, the overall efficiency
of the line is raised by tackling the key points.
A Kanban system is a pull system, in which the Kanban is used to pull parts to the
next production stage when they are needed; an MRP system (or any schedule based
system) is a push system, in which a detailed production schedule for each part is used
to push parts to the next production stage when scheduled. The weakness of a push
system (MRP) is that customer demand must be forecast and production lead times
must be estimated accurately. The weakness of a pull system (Kanban) is that
following the Lean Manufacturing philosophy is essential, especially concerning the
elements of short setup times and small lot sizes.
Single Card Kanban Systems: In a single-card Kanban system, parts are produced and
bought according to a daily schedule and deliveries to the user are controlled by a
C-Kanban. In effect, the single-card system is a push system for production coupled
with a pull system for delivery to the point of use.
Single-card Kanban controls deliveries very tightly so that the using work center never
has more than a container or two of parts and the stock points serving the work center
are eliminated. Single-card systems work well in companies in which it is relatively
easy to associate the required quantity and timing of component parts with the
schedule of end products. These are usually companies with a relatively small range of
end products or products which are not subject to rapid, unexpected changes in
demand levels.
250
Operations Management
Table 9.10. One can see the increases in productivity and simultaneous reductions in 251
Inventory Control
lead-time and inventory.
Table 9.10: Aisin Mattress Production: Historical Mix, Volume and Inventory
252 be ordered, how large the order should be, and when and how many to deliver.
Operations Management
The following costs are generally associated with inventories: Holding (or carrying)
costs, Cost of ordering, Setup (or production change) costs, and Shortage or Stock-out
Costs.
Many selective inventory management techniques are used. The most common is the
ABC Classification. The ABC classification is based on focusing efforts where the
payoff is highest; i.e. high-value, high-usage items are tracked carefully and
continuously, while the level of control for other items tapers off. Other similar types
of classifications are the XYZ Classification, VED Classification, and the HML
classification of inventory. All these techniques are used to focus management
attention in deciding on the degree of control necessary for different items in the
inventory.
9.16 KEYWORDS
ABC Classification, or the alphabetical approach, is based on the annual consumption
value based on the 80:20 principle, efforts are focused where the payoff is highest.
Anticipation Stock: Stock kept at hand to meet seasonal fluctuations in demand or to
meet the shortfall caused by erratic production. Also called build stock or seasonal
stock.
Cost of Ordering: The cost to replenish inventory.
Decoupling Stock: A buffer stock used between productions processes to make one
process independent of the other.
Economic Order Quantity (EOQ): Models determine order size by minimizing the
cost of ordering and the cost of holding inventory.
Fixed-order Quantity Models: At an identified level of the stock the fixed-order
quantity model initiates an order; they are event triggered.
Fixed-time Period Models are time triggered i.e. the model initiates an order after a
fixed-time.
Holding (or Carrying) Costs: The cost to hold inventory. This category includes the
costs for storage facilities, handling, insurance, pilferage, breakage, obsolescence,
depreciation, taxes, and the opportunity cost of capital.
CYP 2
1. True
2. True
3. True
4. True
CYP 3
1. False
2. False
255
Total Quality Management
UNIT V
256
Operations Management
257
LESSON Total Quality Management
10
TOTAL QUALITY MANAGEMENT
CONTENTS
10.0 Aims and Objectives
10.1 Introduction
10.2 Definition
10.3 Why Quality Management?
10.4 Statistical Process Control (SPC)
10.5 Statistical Quality Control (SQC)
10.6 Company Wide Quality Control (CWQC)
10.7 Acceptance Sampling
10.8 Acceptance Sampling Plan
10.8.1 Sampling Plans
10.8.2 Characteristics of a Good Sampling Plan
10.8.3 Points to remember while using Acceptance Sampling
10.9 OC Curve
10.9.1 The Shape of the OC Curve
10.9.2 Some Specific Points on the OC Curve
10.9.3 A Stream of Lots and the Binomial Distribution
10.9.4 The Isolated Lot and the Hypergeometric Distribution
10.9.5 Single and Double Sample Plans
10.10 Use of OC Curve
10.11 Concept of Type I and Type II Error
10.11.1 Type I Error
10.11.2 Type II Error
10.11.3 Type I and Type II Errors and their Applications
10.12 Quality Movement
10.13 Quality Circles
10.14 Let us Sum up
10.15 Lesson End Activity
10.16 Keywords
10.17 Questions for Discussion
10.18 Suggested Readings
258
Operations Management 10.0 AIMS AND OBJECTIVES
After studying this lesson, you will be able to:
Describe TQM concept
Attempt an analysis of the improvement process
Understand the principles of the total quality management
Know about the implementation and measurement of TQM
10.1 INTRODUCTION
Total Quality Management (TQM), a buzzword phrase of the 1980's, has been killed
and resurrected on a number of occasions. The concept and principles, though simple
seem to be creeping back into existence by "bits and pieces" through the evolution of
the ISO 9001 Management Quality System standard.
"Total Quality Control" was the key concept of Armand Feigenbaum's 1951 book,
Quality Control: Principles, Practice, and Administration, in a chapter titled "Total
Quality Control" Feigenbaum grabs on to an idea that sparked many scholars interest
in the following decades, that would later be catapulted from Total Quality Control to
Total Quality Management. W. Edwards Deming, Joseph Juran, Philip B. Crosby, and
Kaoru Ishikawa, known as the big four, also contributed to the body of knowledge
now known as Total Quality Management.
The American Society for Quality says that the term Total Quality Management was
used by the U.S. Naval Air Systems Command "to describe its Japanese-style
management approach to quality improvement." This is consistent with the story that
the United States Navy Personnel Research and Development Center began
researching the use of Statistical Process Control (SPC); the work of Juran, Crosby,
and Ishikawa; and the philosophy of W. Edwards Deming to make performance
improvements in 1984. This approach was first tested at the North Island Naval
Aviation Depot.
Companies who have implemented TQM include Ford Motor Company, Phillips
Semiconductor, SGL Carbon, Motorola and Toyota Motor Company.
The latest changes coming up for the ISO 9001:2000 standards "Process Model"
seem to complete the embodiment. TQM is the concept that quality can be managed
and that it is a process.
Total Quality Management (TQM) is a management strategy aimed at embedding
awareness of quality in all organizational processes. TQM has been widely used in
manufacturing, education, government, and service industries, as well as NASA space
and science programs.
259
10.2 DEFINITION Total Quality Management
A Comprehensive Definition
TQM Total Quality Management is the organization wide management of quality. We
know that management consists of planning, organizing, directing, control, and
assurance. Then, one has to define "total quality". Total quality is called total because
it consists of 3 qualities: Quality of return to satisfy the needs of the shareholders.
260 Crosby, Ishikawa and many others. We will learn more about the work of these
Operations Management
quality Gurus in the next unit as we go along. The quality movement has thus
progressed until the present day when quality has taken a central place in determining
the organisational objectives and competitive positives.
It seems that, besides the Japanese, the rest of the world has suddenly woken up from
a long sleep with eagerness and a sense of urgency to be updated on all the potential
benefits of quality which is being adopted as a way of conducting business. Let us
now look briefly at some of the important factors, which caused this realization. They
are:
Question of survival in an intense competitive environment: The industrial
development in any society/country takes place in phase. In the initial phase,
subsequent to identifying a need, one or few suppliers emerge to provide the
product/service to satisfy the need of customers. This near-monopoly situation
dominated by the supplier creates a seller's market enabling the suppliers to
provide a product/service of the quality they are capable of providing without
bothering whether their products satisfy the need or not. However, soon in the
later phase, more and more suppliers looking for business opportunities emerge on
the scene creating a buyer's market enabling the customers to choose a supplier.
As you must have observed, over the last 10 years or so, phenomenal changes
have taken place in the economic scenario all over the world. By now, we are
sure, you are familiar with the terms "globalisation and "liberalisation".
Economic barriers, which existed in many world economies, have broken down
and the whole world, economy-wise, has shrunk as one big market allowing
almost free exchange of goods and services. Suppliers now not only face
competition from domestic suppliers but also from the international ones. All the
suppliers try their best to retain and possibly increase their market share. We are
in the era of intense competition, and for suppliers all over the world it has
become a question of survival. Just conforming to specifications and satisfying the
needs of the customer is no more enough. The emphasis now is on delighting and
winning over customers. The earlier concepts of quality management have been
found inadequate to meet this objective, giving rise to the present concept of total
quality management.
Increasing Customer Consciousness: Customers all over the world are becoming
increasingly conscious about getting more than just value for the money paid for
products and services they buy. Backed by government laws and regulations, a
number of agencies (governmental and non-governmental) have emerged which
are working for protection of consumer's interests. The needs of the customers
also keep on changing fast. Unless the suppliers are fast enough and are capable of
satisfying the changed needs, they just lose the customers, ultimately resulting in a
reduction in their market share.
Need for earning profit instead of making profit: All business organisations have
to be profit-oriented as profits are essential for the very survival of the
organisation-and are also needed for its growth. In the earlier economic situation
of seller's market, organisations used to make profit through the age-old equation
of cost price (CP) + Profit (P) = Sales price (SP). The selling price used to be
fixed in such a way that it automatically ensured making of as much profit as
desired by the supplier organisation. In the present prevailing competitive buyer-
dominated situation, this equation is no more valid as the market forces now
determine the selling price. Therefore, if the supplier organisation has to achieve
the profit objective, it has now to earn profit by controlling the cost price. As you
are aware, some of the major components which make up cost price are costs of
material, energy and human resources. You are also aware how all the three costs
keep on rising and the supplier organisation has no control on the cost of these 261
Total Quality Management
inputs. So, for controlling the cost price, the only major way in the hands of the
supplier is to reduce what is known as 'quality cost' i.e. cost incurred by an
organisation for making non-conforming products. The cost of repair,
reprocessing, regarding and/or scrapping non-conforming products form a big
chunk of the total sales turnover - as much as 20 to 30% as revealed by way of
case studies. You will learn more about quality cost as you go along. To reduce
the Quality Cost, the objective of the supplier should, therefore, be to make things
right first time and every time a TQM approach.
Organisational issues pointing to the need to focus on TQM:
That Leadership plays a very crucial le in the total business performance of
the organisation has now been realized. The quality of ah organisation is
largely influenced by the quality of its leader. And, therefore, it has to be a
major ingredient of quality management.
Human resource management is one issue that is receiving increasing
attention in organisations all, over the world. In fact, it has been a major factor
for many Japanese organisations to become world leaders. Though not
considered important enough earlier, it now forms another major component
of quality management.
The advent of revolution in information technology.
It intensifies the need for everyone in the organisation to be computer literate.
The distribution of power relating to technical, problems solving, and
decision-making abilities in the organisation through computer networks.
The speed, directness and immediacy of information exchange, both within
the organisation at all levels and between organizations and key external
stakeholders (suppliers and customers), is redefining business relationship and
responsibilities.
If you appreciate the factors listed above, you will realize the inadequacy of the earlier
static approach to quality management and the need for some dynamic approach. This
is provided by what has come to be known as Total Quality Management approach
(TQM). As per definition provided by the International Organisation for
Standardisation (ISO), TQM is a "management approach of an organisation, centered
on quality, based on the participation of all its members and aiming at long-term
success through customer satisfaction, and benefits to all members of the organisation
and to society".
262 SPC is used to monitor the consistency of processes used to manufacture a product as
Operations Management
designed. It aims to get and keep processes under control. No matter how good or bad
the design, SPC can ensure that the product is being manufactured as designed and
intended. Thus, SPC will not improve a poorly designed product's reliability, but can
be used to maintain the consistency of how the product is made and, therefore, of the
manufactured product itself and its as-designed reliability.
A primary tool used for SPC is the control chart, a graphical representation of certain
descriptive statistics for specific quantitative measurements of the manufacturing
process. These descriptive statistics are displayed in the control chart in comparison to
their "in-control" sampling distributions. The comparison detects any unusual
variation in the manufacturing process, which could indicate a problem with the
process. Several different descriptive statistics can be used in control charts and there
are several different types of control charts that can test for different causes, such as
how quickly major vs. minor shifts in process means are detected. Control charts are
also used with product measurements to analyze process capability and for continuous
process improvement efforts.
Benefits
Provides surveillance and feedback for keeping processes in control
Signals when a problem with the process has occurred
Detects assignable causes of variation
Accomplishes process characterization
Reduces need for inspection
Monitors process quality
Provides mechanism to make process changes and track effects of those changes
Once a process is stable (assignable causes of variation have been eliminated),
provides process capability analysis with comparison to the product tolerance.
The application of statistical techniques to control quality. Often used interchangeably 263
Total Quality Management
with the term statistical process control, although statistical quality control includes
acceptance sampling, which statistical process control does not. It provides the
methods and tools for the manufacturing manager to improve quality, increase
productivity, and enhance the competitive position of the manufacturing line.
Proposes potentially controversial methods of performance appraisals, operation
certification, line qualification, vendor certification, and just-in-time manufacturing.
Statistical quality control provides the statistical techniques necessary to assure and
improve the quality of products. Most of the statistical quality techniques used now
have been developed during the last century. Basic steps in statistical quality control
methodology are represented in Figure 10.2, which also lists the output of each step.
Acceptance sampling plans are commonly used in manufacturing to decide whether to 265
Total Quality Management
accept or to reject lots of product. However, they can also be used during validation to
accept or to reject the process.
Acceptance sampling will require the selection of a sampling plan. Sampling plans are
used to make product disposition decisions. A sampling plan will determine the size of
a sample and the number of defectives permitted in the sample top determine the
acceptance or rejection of the population.
The two parameters of sampling plans are:
N = Sample size (number of units in the sample)
C = Acceptance number (maximum number of defective units allowed in a sample to
decide the acceptance or rejection of the population)
Types of acceptance sampling plans: This categorization depends on when the
inspection takes place. Outgoing inspection happens when the batches are inspected
before the product is shipped to the consumer. If the inspection is done by the
consumer, after they were received from the supplier, it is called incoming inspection.
Rectifying vs. outgoing inspections: This determines what is done with non-
conforming items that were found during the inspection. The cost of replacing faulty
items with new ones, or reworking them is accounted for, the sampling plan is
rectifying.
Sampling by attributes vs. sampling by variables: Sampling by attributes occurs when
the inspection of an item is done for an attribute and leads to binary result or the
numbers of non-conformities in an item are counted. When inspection is done to a
continuous measurement, then we are sampling by variables.
Single, double, and multiple plans: The sampling procedure may consist of drawing a
single sample, or it may be done in two or more steps. A double sampling procedure
means that if the sample taken from the batch is not informative enough, another
sample is taken. In multiple sampling, additional samples can be drawn after the
second sample.
Following the acceptance by a sampling plan, one can make confidence statement
such as: With 95% confidence, the defect rate is below 1% defective. A point to
remember is that the main purpose of acceptance sampling is to decide whether or not
the lot is likely to be acceptable, not to estimate the quality of the lot.
For selecting statistically valid sampling plans, one must clearly define the objective
of the inspection and one must demonstrate that the sampling plan allows this
objective to be met.
The selection of a sampling plan must be guided by:
Cost of the inspection that will be incurred
Protection provided to the producer and customer by the high efficiency of the
sampling.
Ideally, a sampling plan should reject all bad lots while accepting all good lots.
However, because the sampling plan bases it decisions on a sample of the lot and not
the entire lot, these is always a chance of making an incorrect decision.
10.9 OC CURVE
The Operating Characteristic (OC) curve describes the probability of accepting a lot as
a function of the lots quality. Figure 10.3 shows a typical OC Curve.
268
Operations Management
The only way to realize the ideal OC curve is 100% inspection. With sampling, we 269
Total Quality Management
can come close. In general, as the sample size increases, keeping the acceptance
number proportional, the OC curve approaches the ideal, as shown in Figure 10.5.
Figure 10.6: As c Increases, for Fixed n, the OC Curve Approaches the Ideal
270
Operations Management
In a single sample plan we accept the lot if the number of non-conforming items is c
or less. This means we are interesting in the probability of 0, 1, , c items. We write
this as
271
Total Quality Management
The probability of accepting the lot is the probability that there are c or fewer non-
conforming items in the sample. This is the equation above, and is what we plot as the
OC curve.
Here, N is the lot size, n is the sample size, and d is the number of non-conforming
items in the lot.
If we are interested in determining the probability of c or fewer non-conforming items
in the sample then we write:
We can use this equation to draw the OC curve for the isolated lot.
Often, the risk is applied to each lot, instead of the stream of lots. In these cases, the
quality level corresponding to a probability of acceptance equal to is called the Lot
Tolerance Percent Defective (LTPD).
272 ci is the maximum number of non-conforming items allowed for acceptance on the ith
Operations Management
sample, and
ri is the minimum number of non-conforming items allowed for rejection on the ith
sample.
For example, a single sample plan may be:
n = 20, c = 2, r = 3.
A double sample plan may be:
n1 = 20, c1 = 1, r1 = 4
n2 = 20, c2 = 4, r2 = 5
In this example, if we had 2 non-conforming items on the first sample, we would draw
the second sample. In total, we would have sampled 40 items.
We can calculate the probability of acceptance, the information we need to define the
OC curve, by the following equation.
The probabilities are, as described above, calculated using either the binomial or
hypergeometric distributions.
Notice how quickly the c=0 plan drops off. The figure also has dashed horizontal lines 273
Total Quality Management
at 5% and 95% probability of acceptance. The AQL and RQL for these plans are listed
below.
C=0 C=2
AQL 0.26% 4.21%
RQL 13.9% 28.3%
It is easy to see that c=0 plan will accept many fewer lots than the corresponding c=2
plan. If your process cannot tolerate even a few non-conforming units, c=0 plans may
be a good approach. However, recognize that lot rejection incurs a transaction cost,
that may be high. The selection is a c=0 plan is certainly an economic decision.
With this ideal (no risks) curve, all batches with 1% defective incoming quality level
would have a probability of acceptance (Pa) of 1.0. And, all lots with > 1% defective
would have a Pa of 0. The Pa is the probability that the sampling plan will accept the
lot. It is the long-run % of submitted lots that would be accepted when many lots of a
stated quality level are submitted for inspection. It is the probability of accepting lots
from a steady stream of product having a fraction defective P.
274 Example: If the cholesterol level of healthy men is normally distributed with a mean
Operations Management
of 180 and a standard deviation of 20, and men with cholesterol levels over 225 are
diagnosed as not healthy, what is the probability of a type one error?
z = (225-180)/20=2.25; the corresponding tail area is .0122, which is the probability of
a type I error.
If the cholesterol level of healthy men is normally distributed with a mean of 180 and
a standard deviation of 20, at what level (in excess of 180) should men be diagnosed
as not healthy if you want the probability of a type one error to be 2%?
2% in the tail corresponds to a z-score of 2.05; 2.05 20 = 41; 180 + 41 = 221.
Type I and Type II errors can be defined in terms of hypothesis testing. 275
Total Quality Management
A Type I error ( ) is the probability of rejecting a true null hypothesis.
A Type II error ( ) is the probability of failing to reject a false null hypothesis.
Check Your Progress 3
State whether the following statements are true of false:
1. TQM helps to improve product quality using a long-term approach at
improving production and customer satisfaction while decreasing wastes.
2. Variety of organizational mechanisms have not been used to promote
continuous improvement, such as work teams, quality circles, and
suggestion systems.
276 equipment operations, and accurate process feedback. Juran's seminar also became a
Operations Management
part of JUSE's educational programs. Juran provided the move from SQC to TQC
(total quality control) in Japan. This included company-wide activities and education
in quality control (QC), QC circles and audits, and promotion of quality management
principles. By 1968, Kaoru Ishikawa, one of the fathers of TQC in Japan, had outlined
the elements of TQC management:
Quality comes first, not short-term profits
The customer comes first, not the producer
Customers are the next process with no organizational barriers
Decisions are based on facts and data
Management is participatory and respectful of all employees
Management is driven by cross-functional committees covering product planning,
product design, production planning, purchasing, manufacturing, sales, and
distribution (Ishikawa 1985).
By 1991, JUSE had registered over 331,000 quality circles with over 2.5 million
participants in its activities. Today, JUSE continues to provide over 200 courses per
year, including five executive management courses, ten management courses, and a
full range of technical training programs.
One of the innovative TQC methodologies developed in Japan is referred to as the
"Ishikawa" or "cause-and-effect" diagram. After collecting statistical data, Ishikawa
found that dispersion came from four common causes, as shown in Figure 10.9.
Materials Processes
Quality
Equipment Measurement
CAUSES EFFECT
use of such charts, and companies that had received ISO 9000 certification also posted 277
Total Quality Management
the process information required for each machine. However, the panel was surprised
at the relatively limited use of SPC charts within the factories visited. The Japanese
believe that the greatest benefit occurs when defect detection is implemented within
the manufacturing sequence, thus minimizing the time required for detection,
maximizing return on investment, and indirectly improving product reliability.
278 Quality Circle has a progressive and systematic approach towards soling a problem
Operations Management
based on Identify, Select, Analyze and Solve using the following techniques.
Brain storming
Data collection
Pareto analysis
Cause and effect or Ishikawa Diagram.
280
Operations Management 10.16 KEYWORDS
Total Quality Management (TQM) is a management approach aimed at satisfying all
customer requirements, needs and expectations using a Continuous Improvement
approach.
Metrics translate the customer needs into technical characteristics of the desired
information solution.
Quality: Defined as that aspect of things under which they are considered in thinking
or speaking of their nature, condition, or properties.
Statistical Process Control (SPC): A process to control the variability of output using
control charts.
Statistical Quality Control (SQC): Use of statistical methods to improve or enhance
quality for customer satisfaction. It involves monitoring a process to identify the
unique causes of variation for signaling appropriate corrective actions.
CYP 2
1. Quality circle
2. January 1981
Drucker, P.E., The Information Executives Truly Need, Harvard Business Review. 281
Total Quality Management
Fox, C., Levitin, A. and Redman, T., The Notion of Data and its Quality
Dimensions, Information Processing & Management.
Greene, R.T., Global Quality A Synthesis of the World Best Management Methods,
1993, New York, ASQC Quality Press.
Hari, A. (editor), The Quality Terms Lexicon, 1995, Israel, Quality and Excellence
Center, Prime Minister Office (Hebrew Text).
Rolph, P. and Bartram, P., The Information Agenda: Harnessing Relevant
Information in a Changing Business Environment, 1994, London, Management
Books.
282
Operations Management
LESSON
11
ISO QUALITY CERTIFICATION CONCEPTS
CONTENTS
11.0 Aims and Objectives
11.1 Introduction
11.2 Essence of International Standards
11.3 Overview of ISO Standards
11.4 ISO 9000 Quality Standard
11.5 ISO 9000 Quality System Certification
11.6 ISO 9000 Family
11.7 ISO 14000
11.8 QS 9000
11.9 Documentation of Quality System
11.9.1 Quality Manual
11.9.2 Quality Procedures
11.9.3 Quality Records
11.9.4 Controlled Documents
11.10 Implementing ISO 9001: 2000
11.11 Quality Assurance
11.12 Quality Assurance Review
11.13 Objectives of Quality Assurance Review
11.13.1 Business Review
11.13.2 Technical Review
11.13.3 Management Review
11.13.4 Roles and Responsibilities
11.14 Six Sigma Concepts
11.15 Six Sigma Roles and Responsibilities
11.16 Six Sigma Methodology
11.16.1 The Differences of DMAIC and DMADV
11.16.2 When to use DMAIC
11.16.3 When to use DMADV
11.17 Let us Sum up
11.18 Lesson End Activity
Contd
11.1 INTRODUCTION
Introduction to ISO 9000 is a family of standards for quality management systems.
ISO 9000 is maintained by ISO, the International Organization for Standardization
and is administered by accreditation and certification bodies. Some of the
requirements in ISO 9001 (which is one of the standards in the ISO 9000 family)
include:
a set of procedures that cover all key processes in the business;
monitoring processes to ensure they are effective;
keeping adequate records;
checking output for defects, with appropriate and corrective action where
necessary;
regularly reviewing individual processes and the quality system itself for
effectiveness; and
facilitating continual improvement.
A company or organization that has been independently audited and certified to be in
conformance with ISO 9001 may publicly state that it is "ISO 9001 certified" or "ISO
9001 registered." Certification to an ISO 9000 standard does not guarantee the
compliance (and therefore the quality) of end products and services; rather, it certifies
that consistent business processes are being applied.
Although the standards originated in manufacturing, they are now employed across a
wide range of other types of organizations. A "product", in ISO vocabulary, can mean
a physical object, or services, or software. In fact, according to ISO in 2004, "service
sectors now account by far for the highest number of ISO 9001:2000 certificates -
about 31% of the total."
ISO 9001 certification does not guarantee that the company delivers products of
superior (or even decent) quality. It just certifies that the company engages internally
in paperwork prescribed by the standard. Indeed, some companies enter the ISO 9001
certification as a marketing tool.
Standards are documented agreements containing technical specifications or other
precise criteria to be used consistently as rules, guidelines, or definitions of
characteristics, to ensure that materials, products, processes and services are fit for
their purpose.
For example, the format of the credit cards, phone cards, and smart cards that have
become commonplace is derived from an ISO International Standard. Adhering to the
284 standard, which defines such features as an optimal thickness (0.76 mm), means that
Operations Management
the cards can be used worldwide.
International Standards thus contribute to making life simpler, and to increasing the
reliability and effectiveness of the goods and services we use.
Similarity, there are several existing international standards for software development
organization and more are added from time to time depending on the requirement.
Interpenetration of Sectors
No industry in todays world can truly claim to be completely independent of
components, products, rules of application, etc., that have been developed in other
sectors.
Bolts are used in aviation and for agricultural machinery, welding plays a role in
mechanical and nuclear engineering, and electronic data processing has penetrated
all industries.
Environmentally friendly products and processes, and recyclable or biodegradable
packaging are pervasive concerns.
Here, the need for standardization is in defining terminology and accumulating 285
ISO Quality Certification Concepts
databases of quantitative information.
Developing Countries
Development agencies are increasingly recognizing that a standardization
infrastructure is a basic condition for the success of economic policies aimed at
achieving sustainable development.
Creating such an infrastructure in developing countries is essential for improving
productivity, market competitiveness, and export capability.
Industry wide standardization is a condition existing within a particular industrial
sector when the large majority of products or services confirm to the same standards.
It results from consensus agreements reached between all economic players in that
industrial sector suppliers, users, and often governments. They agree on specifications
and criteria to be applied consistently in the choice and classification of materials, the
manufacture of products, and the provision of services.
The aim is to facilitate trade, exchange and technology transfer through:
Enhanced product quality and reliability at a reasonable price.
Improved health, safety and environmental protection, and reduction of waste.
Greater compatibility and interoperability of goods and services.
Simplification for improved usability.
Reduction in the number of models, and thus reduction in costs.
Increased distribution efficiency, and ease of maintenance.
Users have more confidence in products and services that confirm to International
Standards. Assurance of conformity can be provided by manufacturers declaration or
by audits carried out by independent bodies.
286 Satisfied customers may buy again. Poor quality offerings cause companies to waste
Operations Management
time, money and materials. The result may be the loss of customers, or worse yet, the
risk of going out of business.
Quality should be a key business strategy. That is why companies are learning the
language of quality as spoken by the ISO 9000 international standard.
ISO Standards
ISO standards are written specification and guidance documents that establish
internationally harmonized conventions for the operation, design, performance, or
management of products (technical standards) and processes (management standards).
ISO standards are developed within ISO Technical Committees, commonly referred to
as TSc. TCs are made up of individual experts from industry, government, public
interest groups and academia from any member countries that wish to participate. TCs
prepare draft versions of the standards which are sent for formal support and
comments to each of the participating ISO member countries. Through iterations,
using a consensus building process, feedback is incorporated with the goal of realizing
an agreed upon international standard. ISO standards are adopted as final when
approved by at least 75% of the member bodies casting a vote. This process usually
takes 7 to 8 years. Most ISO standards are technical standards. The ISO 9000 Series
and the ISO 14000 Series are management standards.
ISO 9004: Generic Guidelines for Quality Management and Systems. 287
ISO Quality Certification Concepts
ISO 9004-2: Guidelines for Services
ISO 14001: Environmental Management System Guidelines for Principles, Systems,
and Supporting Techniques.
Some other System Standards include:
QS 9000: Encompasses ISO 9000 and the Big Three Auto Makers specific
requirements.
TS 9000: Based on ISO 9001 establishes quality systems requirements for the
worldwide telecommunications network.
FDA-CGMP: Medical Device, Current Good Manufacturing Practices (includes all of
ISO 9001).
Check Your Progress 1
Fill in the blanks:
1. The International Organization for Standardization based in
..
2. ISO consists of .. member countries each represented by
a national organization.
3. .. is a series of standards dealing with quality
management systems.
see ("List of ISO 9000 standards" from ISO), many of them not even carrying "ISO 289
ISO Quality Certification Concepts
900x" numbers. For example, some standards in the 10,000 range are considered part
of the 9000 family: ISO 10007:1995 discusses Configuration management, which for
most organizations is just one element of a complete management system. ISO notes:
"The emphasis on certification tends to overshadow the fact that there is an entire
family of ISO 9000 standards ... Organizations stand to obtain the greatest value when
the standards in the new core series are used in an integrated manner, both with each
other and with the other standards making up the ISO 9000 family as a whole".
Note that the previous members of the ISO 9000 family, 9001, 9002 and 9003, have
all been integrated into 9001. In most cases, an organization claiming to be "ISO 9000
registered" is referring to ISO 9001.
Standards
The material included in this family of specifications is very broad. The major parts of
ISO 14000 are:
ISO 14001 is the standard against which organizations are assessed. ISO 14001 is
generic and flexible enough to apply to any organization producing and/or
manufacturing any product, or even providing a service anywhere in the world.
ISO 14004 is a guidance document that explains the 14001 requirements in more
detail. These present a structured approach to setting environmental objectives and
targets and to establishing and monitoring operational controls.
These are further expanded upon by the following:
ISO 14020 series (14020 to 14025), Environmental Labeling, covers labels and
declarations.
ISO 14030 discusses post-production environmental assessment.
ISO 14031 Evaluation of Environmental Performance.
290 ISO 14040 series (14040 to 14044), Life Cycle Assessment, LCA, discusses
Operations Management
pre-production planning and environment goal setting.
ISO 14050 terms and definitions.
ISO 14062 discusses making improvements to environmental impact goals.
ISO 14063 is an addendum to 14020, discussing further communications on
environmental impact.
ISO 14064-1:2006 is Greenhouse gases Part 1: Specification with guidance at
the organization level for the description, quantification and reporting of
greenhouse gas emissions and removals.
ISO 14064-2:2006 is Greenhouse gases Part 2: Specification with guidance at
the project level for the description, quantification, monitoring and reporting of
greenhouse gas emission reductions and removal enhancements.
ISO 14064-3:2006 is Greenhouse gases Part 3: Specification with guidance for
the validation and verification of greenhouse gas assertion.
ISO 19011 which specifies one audit protocol for both 14000 and 9000 series
standards together. This replaces ISO 14011 meta-evaluationhow to tell if your
intended regulatory tools worked. 19011 is now the only recommended way to
determine this.
11.8 QS 9000
QS 9000 is the name given to the Quality System Requirements of the automotive
industry which were developed by Chrysler, Ford, General Motors and major truck
manufacturers and issued in late 1994. QS-9000 replaces such quality system
requirements as Ford Q-101, Chrysler's Supplier Quality Assurance Manual, GM's
NAO Targets for Excellence and the Truck Manufacturer's quality system manuals.
The influence of QS-9000 is being seen throughout the automotive industry as it has
virtually eliminated varying demands and waste associated with redundant systems.
Proof of conformance to QS-9000 is certification/registration by an accredited third
party such as Underwriter's Laboratories (UL) or the American Bureau of Shipping
(ABS). Companies that become registered under QS-9000 will be considered to have
higher standards and better quality products.
QS-9000 will help companies to stay ahead of their competition. It will do this by
filling gaps in the business and quality systems that can cause problems. QS-9000
eliminates redundant and unnecessary work practices. QS-9000 tells current and
potential customers that the product has consistent quality and is manufactured under
controlled conditions. This system is globally accepted as proof of quality in the
automotive industry and is also a major customer requirement.
Once the quality system plan of the company has been completed, the quality system 291
ISO Quality Certification Concepts
must undergo full documentation that comprehends:
The complexity of the production process.
The manpower skills required for production, and
The training requirements to achieve these manpower skills.
Some of the main objectives of an organizations documentation are:
As a tool for information transmission and communication
Evidence of conformity to confirm what was planned, has actually been done
Knowledge sharing by disseminating and preserving the organizations
experiences.
Documentation requirements documents may be in any form or type of medium like:
Paper
Magnetic
Electronic or optical Computer Disc
Photograph
Master Sample, etc.
The extent of the QMS documentation may differ from one organization to another
due to:
The size of organization and type of activities;
The complexity of processes and their interactions, and
The competence of personnel.
At the minimum, quality system documentation should include the companys quality
manual and specifications showing the company processes, work instructions in
support of these processes, and production/quality records required by these work
instructions.
Processes exist within the organization and the initial approach should be limited to
identifying and managing them in the most appropriate way. In determining which
processes should be documented the organization may wish to consider factors such
as:
Effect of quality
Risk of customer dissatisfaction
Statutory and/or regulatory requirements
Economic risk
Effectiveness and efficiency
Competence of personnel
Complexity of processes
Where it is found necessary to document processes, a number of different methods can
be used, such as graphical representations, written instructions, checklists, flow charts,
visual media, or electronic methods.
294 Theyre complex. Documents can be structured on a logical basis, a temporal axis
Operations Management
or almost any configuration.
They may contain other documents. They can include vital and volatile source
information from CAD, spreadsheets or MRP that needs to be updated regularly.
They may contain technical drawing and images.
They can be developed using pencil and paper, a CAD system, a spreadsheet or a
word processor.
They are the circulatory system of an organization. And they must be managed to
be effective.
These are the vital elements of any ISO 9000 project. Because these documents are 295
ISO Quality Certification Concepts
dynamic, the document control is critical to ensure that the right version of these
documents are used and maintained.
Software Testing
Appropriate strategies for software testing should be applied. Note that testing cannot
uncover all errors.
Enforcement of Standards
There are several quality standards such as ISO 9000, SEI CMMs, etc. meant for
ensuring software quality. If these standards are used, can be applied by developers as
part of a formal review. These can be independently verified by SQA group
conducting an audit.
Control of Change
Changes can introduce errors. Change control includes:
Formalized requests for change
Evaluates the nature of the change
Controls the impact of the change
Measurement
Software metrics are needed to track quality and assess impact of methodological and
procedural changes.
Facilitator
The facilitator is the individual who thoroughly understand the subject matter under
review and can present the background information and assign roles to other members.
The facilitator also encourages participation for all the attendees and ensures all
problems are adequately reviewed. The facilitator understands the issues and keeps the
meeting focused and moving. In addition, he or she makes a general agreement on
problem and makes sure that everyone has a chance to express view or receive
clarification on any misunderstanding. The facilitator is required to perform the duties
of a reviewer and records issues if the recorder is not present.
Author (Producer)
The author ensures that the subject material is ready for the review and distributes it.
During the meeting, the author paraphrases the document a section at a time. The
author is responsible for scheduling the review; selecting the review participants,
determining if entry criteria for the review are met; providing information about the
product during all stages; clarifying any unclear issues and correcting any problems 303
ISO Quality Certification Concepts
identified and providing dates for reworks and resolution.
Recorder
The recorder collects and records each defect uncovered during the review meeting.
Then, the recorder develops and issues list and identifies whose responsibility it is to
resolve each issue. In addition, he or she records meeting decisions on the issues,
prepares the minutes, and publishes the minutes.
Reviewer
Each member of the review team spends time prior to the meeting reviewing the
information, makes notes of defects and becomes familiar with the product to be
reviewed and identifies strengths of the product.
Observer
The observer is a new member to the project team who learns the product and
observes the review techniques.
Where,
x is the value of the attribute
x is the mean value, and
n is the number of readings
The philosophy underlying Six Sigma is to reduce process output variation. The
performance of a process in terms of its variability is compared with different
processes using a common metric. This metric is defects per million opportunities
(DPMO). This calculation requires three pieces of data:
Unit. The item produced or being serviced.
Defect. Any item or event that does not meet the customers requirements.
Opportunity. A chance for a defect to occur.
Process Owner (PO) Process owners are responsible for specific processes. For instance, in the
marketing department there is usually one person in charge of marketingthe chief of marketing is
the process owner for marketing. Depending on the size of the business and core activities, there may
be process owners at lower levels of the organizational structure. For example, in the marketing
department there may be a head of marketing services: that's the process owner.
Black Belt (BB) Black Belts are at the heart of the Six Sigma quality initiative. Their main purpose
is to lead quality projects and work full time until they are complete. Black Belts can typically
complete four to six projects per year. They also coach Green Belts on their projects.
Green Belt (GB) Green Belts are employees trained in Six Sigma who spend a portion of their time
completing projects, but maintain their regular work role and responsibilities.
306 Six sigma needs leaders and champions, truly committed to it, to promote it
Operations Management
throughout the organization. Corporate wide training in Six Sigma concepts and tools
is essential. Professionals in the organization need to be qualified in Six Sigma
techniques. MBBs receive in-depth training on statistical tools and process
improvement techniques. They must identify appropriate metrics early in the project.
They must make certain that the improvement effort focuses on business results that
are to be improved. They are the trainers of trainers.
should be used when a product or process is in existence at your company but is not 307
ISO Quality Certification Concepts
meeting customer specification or is not performing adequately. The objective here is
to modify the process to stay within acceptable range. Determine the control
parameters and how to maintain the improvements. Put tools in place to ensure that
the key variables remain within the maximum acceptance ranges under the modified
process.
308
Operations Management 11.19 KEYWORDS
ISO 9000: It is a family of standards for quality management systems.
ISO 14000: The environmental management standards exist to help organizations
minimize how their operations negatively affect the environment (cause adverse
changes to air, water, or land), comply with applicable laws and regulations).
Standard: A practice or procedure that is imposed and enforced throughout the
organization.
Vendor: A person or organization that sells part or all of a product, usually for
inclusion in a large product being developed by a producer.
CYP 2
1. ISO 9000
2. Environmental management standards
CYP 3
1. ISO 14000
2. Competition
3. defect
Greene, R.T., Global Quality A Synthesis of the World Best Management Methods, 309
ISO Quality Certification Concepts
1993, New York, ASQC Quality Press.
Hari, A. (editor), The Quality Terms Lexicon, 1995, Israel, Quality and Excellence
Center, Prime minister Office (Hebrew text).
Rolph, P. and Bartram, P., The Information Agenda: Harnessing Relevant
Information in a Changing Business Environment, 1994, London, Management
Books.
30
Micro-Finance:
Perspectives and Operations
Model Question Paper
309
30
Micro-Finance:
Perspectives and Operations