You are on page 1of 12

A White Paper from the Experts

in Business-Critical ContinuityTM

The Four Trends Driving the Future of Data Center


Infrastructure Design and Management
Introduction technologies, along with more advanced
monitoring and management systems, to
Throughout the first decade of the 21st address the reliability issues facing high-
century, countless new technologies, density data centers.
unprecedented business demands, and
expanding IT budgets created the modern But the pace of change and inability
data center. On the cusp of this century’s to forecast future demand remained a
second decade, the data center finds itself challenge. This challenge was increasingly
balancing efficiency and availability while being met by new infrastructure solutions
computing demand and energy costs are that could more efficiently adapt to short-
increasing and IT budgets are contracting. and long-term change.
Looking ahead to the next 10 years, the
companies emerging as leaders will be the At the same time, a new issue was emerging:
ones that are able to maintain or improve energy consumption. According to a 2008
availability while implementing technologies Digital Realty Trust survey of senior data
and services that reduce costs by improving center decision-makers, power usage of data
design, management and operating centers (average kW use per rack) jumped
efficiency. This paper reviews four trends that 12 percent from 2007 to 2008. Looking back
will drive these changes. further, the Uptime Institute reports data
center energy use doubled between 2000
The data center as we know it today started and 2006 and predicts it will double again by
to take shape as the dot-com bubble 2012. With this in mind, the industry started
expanded in the late 1990s. Growth slowed to turn its attention to reducing data center
when the bubble burst, but by 2003 the energy consumption.
pace of change was accelerating again.
Server shipments in the fourth quarter of Those efforts ramped up in the second
2003 were 25 percent higher than the fourth half of 2008 as the U.S. economy entered
quarter of 2002 and continued to grow at a deep recession and companies were
a double-digit rate the next two years as forced to find ways to reduce spending. IT
IT organizations scrambled to meet the organizations began to look seriously at
nearly insatiable demand for computing energy efficiency in terms of cost savings as
and expectations for 24x7 availability. well as environmental responsibility. This
In the absence of management tools to is reflected in survey data compiled by the
help predict future capacity, data centers Data Center Users’ Group (DCUG). DCUG
routinely were built to handle capacities two members surveyed in 2005 did not include
to three times the initial requirements. energy efficiency in their top five data center
It wasn’t only the number of servers that concerns. In spring of 2008, efficiency made
was growing but the density and power the list at No. 5. In spring of 2009, efficiency
consumption of those servers. Server had moved to the second position (Figure 1).
density rose rapidly between 2000 and
2005, allowing more computing power The challenge for data center managers
to be packaged in smaller enclosures. now is to maintain or improve availability in
Racks that once had held 8 or 12 servers increasingly dense computing environments
were being packed with as many as 48 while reducing costs and increasing
servers. The industry responded with next- efficiency. A rash of well-publicized data
generation UPS and density-specific cooling center outages in 2008 and 2009 led to

1
Top Five Data Center Concerns
Fall 2005 Spring 2008 Spring 2009 Fall 2009
Heat Density Heat Density Heat Density Availability
Infrastructure
Power Density Power Density Efficiency
Management
Availability Availability Adequate Monitoring Heat Density
Fuzzy growth plans Adequate Monitoring Availability Efficiency
Technology Changes Efficiency Power Density Power Density
Adequate Monitoring

Figure 1. Summary results from Data Center Users Group surveys. Source: DCUG

speculation that cost-cutting was resulting accomplished by establishing data center


in increased downtime. In the wake of infrastructures that leverage four distinct
those outages, respondents to the fall 2009 opportunities to enhance efficiency without
DCUG survey showed a renewed respect for compromising availability. These are the
availability. It jumped from the fourth most opportunities that will drive data center
important concern just six months earlier to infrastructure design and management in
the number one concern (Figure 2). the coming years.
Fall 2008 Fall 2009
0% 10% 20% 30% 40% 50% 0% 10% 20% 30% 40% 50%

1% 1%
1 – Reducing energy usage 1 – Reducing energy usage
is our main priority is our main priority

2% 2%
2 2

7% 6%
3 3

21% 17%
4 4

23% 15%
5 5

6 23% 6 25%

23% 31%
7 – Maintaining high availability 7 – Maintaining high availability
is our main priority is our main priority

The likely reason again is economic: one Defining Efficiency


significant outage can be so costly that it
wipes out years of savings achieved through
Efficiency is the ability to produce an output
incremental efficiency improvements (Figure 3).
with a minimum of effort, expense or waste.
To meet the sometimes conflicting In the data center, efficiency traditionally has
objectives of reducing costs and increasing been used to refer to energy. But in reality,
availability, data center management must energy is just one of the resources consumed
enter a new stage of maturity. That can be by a data center. And energy efficiency, while

2
7 without increasing operating or
6 management costs has been just as
successful at improving efficiency as
5 one that cuts costs by half.
4 Taking advantage of the
opportunities outlined in this paper
3
enables IT organizations to more
2 efficiently deploy and use all of their
1 resources throughout the life of the
data center—including physical space,
0
capital equipment dollars, design and
Banking Energy Telecom Manufacturing Retail Healthcare
management time, service costs and,
Downtime Cost yes, energy.
($M/Hour)
1. Density Creates Efficiency
Data centers already are moving
toward high-density computing
environments as newer, more
important, is just one chapter in the larger
dense servers are deployed. In the fall 2009
data center lifecycle story. For example,
DCUG survey, respondents indicated they
is a system that offers excellent operating
expect average rack densities to be 11 kW
efficiency but can’t accommodate growth
in two years and 17 kW within 10 years—
or change really that efficient? How about
significantly higher than the 7.4 kW average
a system that offers small energy efficiency
when the survey was taken (Figure 5). The
gains but exposes critical IT systems to
reasons cited for moving to higher densities
greater risk?
include saving facility space and reducing
energy costs. This indicates there is growing
That’s why a data center efficiency equation
understanding of the savings that can be
should involve Design, Management and
achieved through efficiency; however,
Operation (Figure 4). Of course, data center
the magnitude of the savings available
output is the other side of this formula. A
through increasing density continues to be
data center that can double its capacity
underestimated.

Design & For example, industry estimates put the cost


Deployment of building a data center (the building shell
■ Shorten Time and raised floor) at $200-$400 per square
■ Minimize Space
foot. By building a data center with 2,500
square feet of raised floor space operating
at 20kW per rack versus a data center with
Management 10,000 square feet of raised floor space at
Operation
& Planning 5 kW per rack, the capital savings could
■ Improve Performance ■ Increase Availability reach $1 - $3 million. Operational savings
■ Increased Control ■ Reduce Energy
also are impressive – about 35 percent of the
cost of cooling the data center is eliminated
by the high-density cooling infrastructure.
Figure 4. Energy is just one of the factors that
contribute to data center lifecycle costs.

3
The days when data centers opened with 18
huge areas of unused floor space set aside 16
for a decade’s worth of growth are coming 14
to an end. Instead of building out, like a city 12
with a growing population supported by 10
sprawling suburbs, data center designers and 8
managers are beginning to understand it is 6
more efficient to build “up” and replace the
4
sprawl with higher density racks. Sixty-three
2
percent of the respondents to the fall 2009
-
DCUG survey indicated they plan to make
2006 2007 2008 2009 In 2 years In 10 years
their next data center new build or expansion
a high-density (>10kW/rack) facility.
This does require a different approach to
infrastructure design, including:
movement—containment. Aisle containment
prevents the mixing of hot and cold air
High-density cooling: High-density cooling
to improve cooling efficiency. While hot-
brings cooling closer to the source of heat
aisle and cold-aisle containment systems
through high-efficiency cooling units
are available, cold aisle containment
located near the rack to complement the
presents some clear advantages. Cold aisle
base room air conditioning. These systems
containment can be used with or without
can reduce cooling power consumption
conventional raised-floor cooling, can be
by as much as 32 percent compared to
retrofitted easily into existing raised-floor
traditional room-only designs. Pumped
data centers and works in tandem with the
refrigerant solutions remove heat from the
raised floor as well as with high-density
data center more efficiently than air-cooled
cooling systems to produce highly efficient
systems and provide incremental energy
cooling. By integrating the cold aisle
savings of between 25 and 48 percent
containment with the cooling system and
based on kW of cooling capacity per kW of
leveraging intelligent controls to closely
heat load. Originally designed to address
monitor the contained environment,
hot spots or zones within the data center,
systems can automatically adjust the
high-density cooling systems have become
temperature and airflow to match server
a basic building block of the data center of
requirements. This results in optimal
the future, delivering the ability to meet the
performance and energy efficiency.
needs of today’s 10, 20 and 30 kW racks
while offering the ability to support densities
High-density power distribution: Power
of 60 kW or higher in the future. Also, these
distribution has evolved from single-stage to
cooling systems can use high-efficiency
two-stage designs to enable increased density,
pumped R134a refrigerant that turns into
reduced cabling and more effective use of
a gas if it ever touches the air. This prevents
data center space. Single-stage distribution
an unlikely leak from ever damaging IT
often is unable to support the number of
equipment and triggering an outage.
devices in today’s data center as breaker space
is expended long before system capacity is
Intelligent aisle containment: The
reached. Two-stage distribution eliminates
efficient and well established practice of
this limitation by separating deliverable
hot/cold aisle alignments sets up another
capacity and physical distribution capability

4
into subsystems. The first stage receives unavailable for about an hour and suffered
high-voltage power from the UPS and can be further interruptions over an additional 3.5
configured with a mix of circuit and branch- hours. Pingdom, a company specializing in
level distribution breakers. The second uptime monitoring, estimated the cost of the
stage or load-level units can be tailored to outage to the firm at between $7 million and
the requirements of specific racks or rows. $32 million.
Growing density can be supported by adding
breakers to the primary distribution unit and Renewed concern over the possibility of
adding additional load-level distribution units. outages was reflected in the latest DCUG
Additionally, higher amperage in-rack power survey. Availability vaulted back to the top
distribution units (PDUs), like the Liebert of the key issues list – now a concern for 56
MPX, can be deployed to manage higher percent of respondents versus just 41 percent
electrical requirements within the rack. These six months earlier (Figure 1).
systems can provide 60amp capacity per strip,
compared with 15 amp for traditional rack A large percentage of outages are triggered
power strips, and also feature a modular design either by electrical or thermal issues that can
that makes it easy to add additional receptacles be minimized or eliminated with adequate
or support high-density equipment. power and cooling solutions. The challenge
is optimizing the efficiency gains available
Together, these new advances in power and in power and cooling approaches with IT
cooling technology are enabling high-density criticality and the need for availability. Some
environments to achieve the same levels of the choices to be made and the potential
of availability and scalability as low density trade-offs between efficiency and availability
environments while offering significant savings include:
in design and operating costs.
Uninterruptible Power Supply: Data
2. Availability Makes a Comeback center managers should consider the power
topology and the availability requirements
The second area of opportunity in the coming when selecting a UPS. In terms of topology,
decade involves optimizing IT performance online double conversion systems provide
while achieving high levels of availability. In the better protection than other types of UPS
race to achieve improved energy efficiency— because they completely isolate sensitive
and, ultimately, cut costs—some businesses electronics from the incoming power source,
lost sight of that balance and paid the price remove a wider range of disturbances and
with costly outages. The Uptime Institute provide a seamless transition to backup
issues Flash Reports to its members when it power sources. Online double conversion
sees a data center experiencing failures that systems are the preferred choice for the
could occur at other sites with the same kind data center, and are displacing standby or
of infrastructure equipment. According to line-interactive UPS systems in network
an August 2009 article in Computerworld, it access rooms as overall network availability
sent out six Flash Reports in all of 2008 — and requirements rise. UPS design also should
17 in just the first eight months of 2009. In be considered. There is growing interest,
addition, many of these outages were reported based on efficiency and other factors such
in the media, including a popular online as floor space, in utilizing transformerless
financial transaction provider, which suffered UPS modules in high-power, three-phase
an outage in August of 2009. The service was applications. However, for large enterprise

5
data centers and other applications the cooling system, can be an effective
where availability is critical, a traditional approach to lowering energy consumption
transformer-based UPS still provides the if they are properly applied. Two base
highest reliability. Transformers within the methods exist, air side and water side.
UPS provide fault and galvanic isolation, Water-side economizers provide the benefit
which prevents fault currents from entering of bypassing the compressor, using fluid from
critical systems and causing outages. the cooling tower or drycooler system to
Technology developments and configuration reject heat directly when conditions permit.
options allow the latest generation of The components in expensive IT systems
transformer-based designs to operate at are sensitive and can be damaged by
higher efficiencies compared to previous gaseous contamination and particulates
designs, making them more comparable presented in air side economizers if not
to the transformerless models in the properly filtered. Corrosion is another
marketplace. In fact, a transformerless issue to be considered. Filters, automated
UPS only achieves better efficiency than dampers, bypass circuits, air-quality
a traditional transformer-based UPS at monitoring, humidity management and
loaded capacities greater than 40 percent, control systems can help, but all add
with real cost savings coming at capacities significant construction costs along with
greater than 60 percent. Most dual bus UPS operation and maintenance expense.
configurations operate under 50 percent
load for 99.99 percent of the time and so Water-side economization allows
would produce no efficiency savings with a organizations to achieve the benefits
transformerless UPS. of economization without the risks of
contaminants presented by air-side
Advancements also have been made in approaches. All approaches have pros and
how UPS systems are employed to reduce cons. Data center professionals should
power losses. Energy conversion or “eco” discuss the appropriate applications with
modes allow these systems to achieve local experts.
efficiencies comparable to less robust
technologies, but not without affecting Service: A proactive view of service
availability. In eco mode the UPS switches and preventive maintenance in the data
to static bypass during normal operation. center can deliver additional efficiencies.
When power problems are detected, the Making business decisions with the goal
UPS automatically switches back to double of minimizing service-related issues may
conversion mode. This allows double- result in additional expense up front, but
conversion UPS systems to achieve 97 it can increase life cycle costs. Meanwhile,
percent full load operating efficiency, but establishing and following a comprehensive
could allow certain faults and conditions service and preventive maintenance program
to be exposed to the load. Some systems can extend the life cycle of IT equipment
claim 99 percent efficiency in eco mode, but and delay major capital investments. An
that comes with a further compromise to Emerson Network Power study of the impact
availability. Proper application of eco mode of preventive maintenance on UPS reliability
technology should be enforced. revealed that the Mean Time Between
Failures (MTBF) for units that received two
Economization: Economizers, which use preventive maintenance service visits a
outside air to reduce work required by year is 23 times better than a UPS with no

6
preventive maintenance visits. According Newer data center cooling technologies can
to the study, reliability continued to adapt to change and deliver high-efficiency
steadily increase with additional visits when at reduced loads. Specifically, digital scroll
conducted by highly trained engineers. compressors allow the capacity of room air
conditioners to be dynamically matched to
The move to introduce more efficient power room conditions, minimizing compressor
and cooling technologies into the data cycling, which reduces wear and creates
center will continue for the foreseeable energy savings of up to 30 percent over
future, but when these technologies traditional technologies. Variable speed
introduce greater risk than the technologies drive fans allow fan speed and power draw
they displace, the economics of downtime to be increased or reduced to match the load
will drive organizations to rethink their resulting in fan energy savings of 50 percent
priorities of optimizing efficiency and or more.
availability.
New designs in power systems allow
3. Change Remains a Constant improved component performance at
40-60 percent load compared to full load.
Flexibility is critical in today’s data center Power curves that once showed efficiency
environment and will be imperative for increasing with load now have been
businesses in the years ahead. IT demand effectively flattened as peak efficiencies can
fluctuates depending on the time of be achieved at important 40-50 percent load
day (peaking during business hours, for thresholds.
example), the day of the week (banks may
see significant increases in demand on Friday In the distribution system, new transformers
paydays), or certain business cycles (such are more efficient at half load than they
as holiday shopping season for retailers). are at full load. Modular in-rack PDUs allow
The data center also has to adjust to more rack power distribution systems to adapt to
long-term variations such as organizational changing technology requirements through
growth and the addition of new applications the addition of snap-in modules. They also
requiring IT support. Simply put, the data provide monitoring at the receptacle level to
center is a dynamic environment and give data center and IT managers the ability
optimizing performance in that environment to proactively manage changes.
requires a flexible infrastructure.
Adding digital control capabilities to the
Previous generations of infrastructure power and cooling systems is another way
systems were unable to adjust to variations in to better match performance to demand
load. Cooling systems had to operate at full and increase efficiency. As an example, the
capacity all the time, regardless of actual load Liebert iCOM control system coordinates
demands. UPS systems, meanwhile, operated operation among multiple precision cooling
most efficiently at full load, but full load units, allowing them to function as a single
operation is the exception rather than norm. coordinated team while also providing
The lack of flexibility in the power and cooling advanced diagnostics for the entire
systems led to inherent energy inefficiency. operation, leading to improved efficiency
and availability.
This creates an especially large opportunity
for cooling systems as cooling can account On the power side, scalable UPS solutions
for 35 percent of data center energy costs. allow data center managers to add capacity

7
when needed. SoftscaleTM technology, for benefits is a comprehensive infrastructure
example, enables businesses to purchase management solution.
the UPS capacity they need today while
providing the flexibility to ensure additional Infrastructure management typically
capacity in the future through a software progresses through phases. The first phase
modification. Thanks to the flattened UPS should involve a data center assessment
efficiency curve mentioned previously, to provide insight into current conditions
Softscale systems deliver the same high in the data center and opportunities for
efficiency at 50 percent utilization as at improvement. After establishing that
100 percent. This development has had baseline, a sensor network is strategically
the added benefit of allowing smaller data deployed to collect power, temperature
centers to take advantage of the higher and equipment status for critical devices
reliability and lower cost per kilowatt of in the rack, row and room. Data from the
a centralized UPS compared to operating sensor network is continuously collected
several smaller UPS systems. by centralized monitoring systems—such as
Liebert SiteScan or Liebert Nform—to not
Where previous generation data centers only provide a window into equipment and
were unable to achieve optimum efficiency facility performance, but point out trends
at anything less than full load, today’s and prevent problems wherever they may
facilities can take full advantage of these be located. For example, if an unmonitored
innovative technologies to match the data branch power circuit operating at 80 percent
center’s power and cooling needs more or more of full capacity has a load blindly
precisely, regardless of the load demands applied, it could cause the distribution
and operating conditions. breaker to trip, powering down that entire
distribution leg. Or take the addition of blade
4. Visibility and Control servers to an unmonitored rack. Users could
Enables Optimization be at the thermal threshold of heat creep,
unknowingly subjecting systems to serious
Today’s data center supports more critical, problems.
interdependent devices and IT systems
in higher density environments than Another example involves batteries,
ever before. This fact has increased the often described as the weakest link in the
complexity of data center operations – and power chain. The best way to determine a
created the need for more sophisticated and battery’s health without discharging it is
automated approaches to IT infrastructure to use a monitoring system that measures
management. the internal resistance of all of the cells in
the battery, utilizing an integrated battery
Gaining control of the infrastructure monitoring service that combines state-
environment leads to an optimized data of-the-art technology with proactive
center that improves availability and maintenance and service response.
energy efficiency, extends equipment life,
proactively manages the inventory and Centralized or remote infrastructure
capacity of the IT operation, increases monitoring provides this real-time control,
the effectiveness of staff and decreases historical performance trending, alarm
the consumption of resources. The key to notifications and event escalations to
achieving these performance optimization minimize or eliminate downtime. In addition,

8
Data Center Issues
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Experienced hot spots 55%

Run out of power 28%

Experienced a “Water Event” (leak or water incursion) 28%

Experienced an outage 27%

NA – Have not had any issues 23%

Run out of cooling 20%

Run out of floor space 16%

Other 6%

Figure 6. Making strides in the infrastructure management area of opportunity will help reduce
the number of issues faced by data center managers during the course of a year.

users can manage energy consumption the three cycles: design and deployment,
through thermal and power metering. operations, and management and planning.

The final phase is optimization. A Data centers moving to a higher density IT


comprehensive infrastructure management space can improve efficiency as a result. Yet,
system can help data center managers data center, IT and facilities managers must
improve equipment utilization, reduce server take steps to avoid compromising availability
deployment times and more accurately as the higher density puts additional stress
forecast future equipment requirements, on the power and cooling infrastructure.
resulting in operating and capital expense To more efficiently support the more
reductions. Managers not only improve complex IT environment, the data center
inventory and capacity management, infrastructure must be able to continually
but also process management—ensuring adjust to changes in capacity and demand.
all assets are performing at optimum The best way to make those adjustments
levels. Effective optimization can provide and truly optimize performance is through
a common window into the data center, advanced visibility and control that
improving forecasts, managing supply and comes with comprehensive infrastructure
demand, improving levels of efficiency and management.
availability. For example, a large retailer
used Aperture infrastructure management It all starts at the design and deployment
software to reduce server deployment time stage, when companies can leverage pre-
by 30 percent while slashing the error rate engineered solutions and high-density
from 25 percent to 0, using proven process architectures to reduce the time, space
management functionality. and capital required for construction
of the building. During operation, data
Conclusion center managers can reduce costs by using
efficient technologies and strategies while
During the data center’s next decade, simultaneously decreasing downtime
opportunities to improve efficiency and costs by employing high-availability
optimize performance will exist throughout configurations. And additional savings

9
are available by using infrastructure
management controls to streamline
operations and facilitate a comprehensive
maintenance program.

The key is to look beyond energy when


considering efficiency and to take every
opportunity throughout the lifecycle of the
data center to achieve efficiencies—without
compromising performance.

10
Emerson Network Power
1050 Dearborn Drive
P.O. Box 29186
Columbus, Ohio 43229
800.877.9222 (U.S. & Canada Only)
614.888.0246 (Outside U.S.)
Fax: 614.841.6022

EmersonNetworkPower.com
Liebert.com

While every precaution has been taken to ensure


accuracy and completeness in this literature, Liebert
Corporation assumes no responsibility, and disclaims all
liability for damages resulting from use of this information
or for any errors or omissions. Specifications subject to
change without notice. ©2009 Liebert Corporation. All
rights reserved throughout the world. Trademarks or
registered trademarks are property of their respective
owners. ®Liebert and the Liebert logo are registered
trademarks of the Liebert Corporation. Business-Critical
Continuity, Emerson Network Power and the Emerson
Network Power logo are trademarks and service marks
of Emerson Electric Co. ©2009 Emerson Electric Co.

WP167-39
SL-24637

Emerson Network Power.


The global leader in enabling Business-Critical Continuity™. EmersonNetworkPower.com
AC Power Embedded Computing Outside Plant Racks & Integrated Cabinets
Connectivity Embedded Power Power Switching & Controls Services
DC Power Monitoring Precision Cooling Surge Protection

You might also like