Method Statement
LDIP-P4-MS-BW-M-0 6
GUIDANCE NOTES
1. Where this page is over-stamped with the words Controlled Copy this means:
a) Distribution is centralized - in this case from the Quality Manager.
b) Each copy is issued to a particular person or organization. If no longer required it should be
returned.
c) It is not to be photocopied either in whole or in part. Additional copies are available on request.
d) Copy holders will be automatically issued with any amendments. Responsibility for
incorporating such amendments rests with the copy holder.
Table of Contents
1. General...............................................................................................3
1.1 Purpose.........................................................................................3
1.2 Specification and BOQ.................................................................3
1.3 Referred construction drawings....................................................3
2. Scope of Works ..................................................................................
............................................................................................................
............................................................................................................
............................................................................................................
............................................................................................................3
3. Construction procedure and method statement.................................3
3.1 Scope of the manual....................................................................3
3.2 Execution of work........................................................................4
3.2.1 Flow chart.............................................................................4
3.2.2 Execution.............................................................................5
3.3 List of instrument & Material.........................................................12
4. Construction schedule........................................................................12
5. Organization.......................................................................................13
6. Inspection and test procedure............................................................14
7. Safety control......................................................................................15
8. Environmental control.........................................................................15
9. Risk assessment.................................................................................15
Attachments........................................................................................16
CONTENT:
1 General:
1.1 Purpose:
The purpose of this method of statement is to guide and implement the standard
installation procedure of sanitary fixture for IP Office
1.2 Specification and BOQ:
2 Scope of works:
The sanitary fixtures included all toilet area fixtures and pantry sink.
Submission of Method
statement; get approval
Preparation work
Not
Rectification Inspection with
of Work NKC-THIKECO/ approved
NCC
Approved
JAC/KOTM/REE/
Cleaning
SEC & Touch up
Representative
3.2.2. Execution
i. Preparation.
- Checks all shop drawings and confirm latest drawings are used.
- Confirm all material procured against material approval list.
- Ensure that fabrication details and methods are fully comprehended by the
workers.
- Prepare and check sanitary fixtures and necessary accessories including anchor
bolts for fixtures supports.
- Prepare tools and equipment such as, electric drilling machine, bar bubble level.
- Prepare safety signs and secure barricade working area.
- Workers with personal safety equipment.
Urinal installation
ELEVATION OF URINAL
- Open Isolation valve and check all angle valve connection of fixtures for leak. If
leak repair connection immediately and proceed to testing.
- Test flush tank operation and adjust ball float valve for volume requirement.
- Check tank connection for leak.
- Repeat 3 times flushing for visual inspection.
- Open Isolation valve and check all angle valve connection of fixtures for leak. If
leak repair connection immediately and proceed to testing.
- Plug drain of wash basin and fill up water up to overflow rim
- Unplug drain and check p trap connection for leak.
- Repeat 3 times for visual inspection.
- Regulate faucet water supply pressure through angle valve, minimized volume
water not to splash to wash basin when you open faucet.
- Open Flush valve and check all flush valve connection of fixtures for leak. If leak
repair connection immediately and proceed to testing.
- Test flush valve operation and adjust for volume requirement.
- Check drain connection for leak.
- Repeat 3 times flushing for visual inspection.
5 Marker 01 Set
4. Construction schedule:
Installation of sanitary fixture will be closely coordinated with building work with
following approved construction schedule of building work
5. Organization
MAIN CONTACTOR
NCC Project Manager
Building Manager
SUBCONTACTOR
SANYO E&C
M&E Manager
Site Manager
M&E Piping
Team
6.2 Procedure
The Site Engineer shall ensure that permit to work is issued from the construction
drawing and working drawing prior to commencing for each stage and also prior
permission to placement of each layer of material is issued by the Engineer if any.
6.4 Documentation
7. Safety control:
As per the contractors safety obligations and policy, we will follow our
Occupational, Health, Safety and Rehabilitation plan and our Project Safety
Plan.
Take care when workers working over-head (installation of high level conduit).
Take care when workers doing on scaffolding.
Take care when workers doing with electrical equipment and welding machine.
Take care of building work surrounding.
8. Environmental control
All works will be carried out in accordance with the requirements of the approved
Environmental Management Plan.
9. Risk assessment
ATTACHMENTS
1. Risk assessment
Risk assessment- Conduit Works: RA-LDIP-P4-MS-BW-M-06
2. Inspection and test procedure
a. Material-Equipment request for approval: RFA-LDIP-P4-MS-
BW-M-06
b. Inspection and Testing Plan: ITP-LDIP-P4-MS-BW-M-06
c. Internal Inspection checklist: IIC-LDIP-P4-MS-BW-M-06
d. Request For Inspection: RFI-LDIP-P4-MS-BW-M-06
e. Photo Report
3. Attached Drawings.
4. Attached Master Schedule.