Professional Documents
Culture Documents
Prepared For:
2013
Depreciation Report
Depreciation Report
BCS 2429 The Point
610 Victoria Street, New Westminster, BC, V3M 0A5
Pursuant to your request for a Depreciation Report (Reserve Fund Study) for the within described
condominium project, we have prepared, and submit to you, this report.
The Introduction and Executive Summary describe the reserve fund concepts and major reserve fund
items, and outline the key conclusions of the report. This document provides current and future
replacement reserve estimates, and recommends reserve fund actions. The Depreciation Report is a
complex document and should be reviewed in detail and within the context of this report.
We recommend that a reserve fund plan and strategy be adopted and implemented, and that reserve
fund contributions of $60,000 in 2013 be increased to $ 68,100 per annum in 2014, and further
increased as per the cash flow table each subsequent year. As outlined in this report, the current
reserve fund and proposed contributions/special assessments will ensure reserve funds are adequate
to cover potential expenditures required to repair or replace common elements and assets of the
corporation when needed.
Maintenance Operations Program would be pleased to provide you with a three year update,
including site review, as per legislated requirements. We appreciate the opportunity to perform this
Depreciation Report for you. If you have any questions, please do not hesitate to contact the
undersigned.
Respectfully submitted,
2013 2
Depreciation Report
Table of Contents
Table of Contents _______________________________________________________________________ 3
Table of Figures_________________________________________________________________________ 5
Introduction ___________________________________________________________________________ 6
Certification ____________________________________________________________________________________8
This Report Is Subject to the Following Limiting Conditions_______________________________________________9
Executive Summary _____________________________________________________________________________11
Cash Flow Table _______________________________________________________________________ 13
Report Overview________________________________________________________________________________14
Reserve Expenditures & Forecasting ________________________________________________________________15
Purpose of Depreciation Report __________________________________________________________ 17
Strata Property Act _____________________________________________________________________ 18
In This Manual ________________________________________________________________________ 21
Legislated Requirements: _________________________________________________________________________21
Additional Information ___________________________________________________________________________21
Methodology _________________________________________________________________________ 22
Depreciation Report _____________________________________________________________________________22
Certified Reserve Fund Planning Standards __________________________________________________________22
General Conditions and Assumptions _______________________________________________________________23
Depreciation Report Projection Factors _____________________________________________________________23
Means Historical Cost Index _______________________________________________________________________24
Property Information ____________________________________________________________________________27
Building Plans __________________________________________________________________________________27
Site Plan ______________________________________________________________________________________28
Basic Construction Components ___________________________________________________________________29
Reserve Component Analysis and Estimated Costs ___________________________________________ 31
Current Cost Estimates ___________________________________________________________________________32
Reserve Component Descriptions and Analyses _______________________________________________________35
Reserve Components ___________________________________________________________________ 36
Building - Structural and Architectural ______________________________________________________________36
Building Finishes and Decoration _________________________________________________________________66
Building Mechanical Systems ____________________________________________________________________81
Building - Electrical Systems ______________________________________________________________________95
Site Improvements ____________________________________________________________________________ 101
Reserve Fund Component Estimates ______________________________________________________ 108
REIC Benchmark Analysis _______________________________________________________________________ 108
Schedule A Benchmark Analysis ________________________________________________________________ 108
Schedule A - Benchmark Analysis ________________________________________________________ 109
2013 3
Depreciation Report
Summary of Reserve Fund Estimates _____________________________________________________________ 110
Analysis of Reserve Fund Operations _____________________________________________________________ 111
Corporations Financial Statements _______________________________________________________________ 111
Exceptions ___________________________________________________________________________________ 111
Schedule B - Statement of Historical Reserve Fund Operations _________________________________ 112
Benchmark Deficiency Analysis __________________________________________________________ 113
Adequacy of Depreciation Report ________________________________________________________________ 114
Reserve Fund Management 30 Year Projections ___________________________________________ 115
Schedule C 30 Year Projected Cash Flow and Deficiency Analysis _____________________________________ 115
Schedule C - 30 Year Reserve Fund Cash Flow Projection and Deficiency Analysis __________________ 116
Future Reserve Fund Management _______________________________________________________ 117
Maintenance Guidelines and Forms ______________________________________________________ 119
Your Stratas Maintenance Plan__________________________________________________________________ 120
Maintenance Inspection Sheet __________________________________________________________________ 122
Individual Owner Maintenance Review Guidelines __________________________________________________ 123
Owner Survey ________________________________________________________________________________ 124
How to Use Your Maintenance Schedule __________________________________________________________ 125
Maintenance Schedule _________________________________________________________________________ 126
Addenda Section _____________________________________________________________________________ 130
2013 4
Depreciation Report
Table of Figures
Cash Flow Table _____________________________________________________________________________________13
Depreciation Report Overview Table _____________________________________________________________________14
Underground Parkade with Cold-Applied Elastomeric Surface Membrane _______________________________________37
Overhead Door Hoist at The Point _______________________________________________________________________40
Aluminum Framed Window-Wall System _________________________________________________________________42
Brick Masonry at The Point ____________________________________________________________________________44
Aluminum Framed Storefront Wall and Door System ________________________________________________________46
Penthouse Eyebrow Protected by a Cold-Applied Elastomeric Waterproofing Membrane ___________________________48
Face-Mounted Aluminum Railing with Tempered Glass Inserts ________________________________________________50
Metal Awning with Glazed Canopy ______________________________________________________________________52
Double-Glazed Aluminum Framed Casement Style Windows _________________________________________________54
Aluminum Framed Sliding Glass Doors at Juliet Balconies ____________________________________________________56
Steel Security Door with Wired Glass Vision Lite ____________________________________________________________58
Polyurethane Caulking at Awning to Masonry Transition ____________________________________________________60
Painted (Elastomeric) Concrete Wall at The Point __________________________________________________________63
2-Ply SBS Roofing System with River Rock Ballast ___________________________________________________________65
Common Area Hallway Finishes, Baseboards, and Carpeting _________________________________________________67
Tower Entryway Tile Flooring at The Point ________________________________________________________________69
Suite Entryway Door at The Point _______________________________________________________________________71
Tower Lobby at The Point _____________________________________________________________________________73
Exercise Room at The Point ____________________________________________________________________________76
Media/Games Room Flooring, Pool Table, and Furniture ____________________________________________________78
Pool Area at The Point ________________________________________________________________________________80
Traction Elevator Hoist at The Point _____________________________________________________________________82
Primary Air Handling Unit at The Point ___________________________________________________________________86
Emergency Generator ________________________________________________________________________________88
Common Area Commercial Grade Hot Water Heater ________________________________________________________90
Working Sump Pit at The Point _________________________________________________________________________92
Sprinkler System Mechanicals at The Point ________________________________________________________________94
Access Control System Interface with Security Camera ______________________________________________________97
Common Area Baseboard Heater at The Point ___________________________________________________________ 100
Concrete Walkway and Seating at The Point ____________________________________________________________ 102
Exterior Light Post and Wall-Mounted Fixtures __________________________________________________________ 106
Schedule A Benchmark Analysis _____________________________________________________________________ 109
Schedule C - 30 Year Reserve Fund Cash Flow Projection and Deficiency Analysis _______________________________ 116
2013 5
Depreciation Report
Introduction
The common area components of every multi-unit building will require replacement and
repair over time, and the easiest way to approach these major tasks is with a progressive
strategy. A Depreciation Report creates that strategy by comprehensively studying the
common area components of a building, pricing their replacement, and establishing a
plan to obtain the funds necessary. A good plan will be tailored to the needs of each
strata, and may include special assessments, fee increases over time, or loans, depending
on what the Strata Council feels is the best approach for their owners.
Reserve Fund Study: Although Depreciation Report is the term used in B.C.s
legislation, it is interchangeable with the term Reserve Fund Study.
Adequacy: In Depreciation Reports, the term adequate refers to a report that provides
for all major replacements and repairs, never has a negative starting or ending balance,
and does not include any unplanned special assessments. There is no legislated
requirement for adequacy in B.C., but many Provinces, including Ontario, require
Depreciation Reports to be adequate.
2013 6
Depreciation Report
Current Reserve Fund Requirements: A ratio of how much funding should
already be in place, in order to reach full funding at the annual reserve fund
assessment level listed.
Future Reserve Fund Requirements: Are the Future Replacement Costs minus
the Future Reserve Fund Accumulation.
By following the recommendations in this report, the Strata Corporation will be able to
effectively manage their expenditures on major replacements and repairs, utilizing a
funding model most suited to their goals.
Remember, major maintenance, repair items, and operating costs consume the bulk of
expenditures over a buildings life span, so be sure to make adequate Depreciation Report
funding a priority.
***Homeowner Protection Office Steering Committee. "Maintenance Matters." Homeowner Protection Office.
BC Housing, 2009. Web. December, 2009. <http://www.hpo.bc.ca/files/download/MMR/MM7.pdf>.
2013 7
Depreciation Report
Certification
We hereby certify that we are prescribed persons empowered to conduct Depreciation
Reports, as stipulated in B.C. Regulation 43/2000 under the British Columbia Strata
Property Amendment Act, 2009, and that Markus Rissiek, BA, CRP, has personally
inspected the within described property, and that he personally examined the building
plans and/or documents as identified herein. To the best of our knowledge and belief, the
information and data used herein are true and correct.
This Depreciation Report was prepared in conformity with the Depreciation Report
Standards published by the Real Estate Institute of Canada, and it complies with the
British Columbia Strata Property Amendment Act, 2009, and Regulation 43-2000.
Maintenance Operations Program presently holds Errors and Omissions Insurance in the
amount of $2,000,000.00 from Trisura Guarantee Insurance Company. Markus Rissiek,
this reports preparer, is a Certified Reserves Planner, and has 6 years of experience as a
technical writer working on multi-family housing in B.C.
________________________________________
Markus Rissiek
2013 8
Depreciation Report
Sketches, drawings, diagrams, and photographs presented in this report, if any, are included
for the sole purpose of illustration. No legal survey, soil tests, engineering investigations,
detailed quantity survey compilations, nor exhaustive physical examinations have been made.
Accordingly, no responsibility is assumed concerning these matters, or other technical and
engineering techniques which would be required to discover any inherent or hidden condition
of the property. In addition, Maintenance Operations Program is not responsible for work
performed, or conclusions reached, that are based upon information or services provided by
the Client, or any third party not operating under the direct supervision of Maintenance
Operations Program.
In order to arrive at supportable replacement cost estimates, it was found necessary to utilize
both documented data, and information derived from industry experience and consultation. A
concerted effort has been put forth to verify the accuracy of the information contained herein.
Accordingly, the information is believed to be reliable and correct, and it has been gathered to
standard professional procedures, but no guarantee as to the accuracy of the data is implied.
The distribution of cost and other estimates in this report apply only under the programme of
utilization as identified in this report. The estimates herein must not be used in conjunction
with any other appraisal or Depreciation Report, and may be invalid if so used. The client to
whom this report is addressed may use it in deliberations affecting the subject property only,
and in so doing, the report must not be abstracted; it must be used in its entirety.
Possession of this report or any copy thereof does not carry with it the right of publication, nor
may it be used for any purpose by anyone but the applicant without the written consent of the
author, and in any event, only with the proper qualifications.
The agreed compensation for services rendered in preparing this report does not include fees
for consultations and/or arbitrations, if any. Should personal appearances be required in
connection with this report, additional fees will be negotiated.
The total amount of claims the Client may have against Maintenance Operations Program,
and its employees, under this engagement, including but not limited to claims for negligence,
negligent misrepresentation, and breach of Contract, shall be strictly limited to the amount of
any professional liability insurance available at the time such claims are made. No claims may
be brought more than 2 years after the services are rendered.
The Client expressly agrees that Maintenance Operations Programs employees, principals,
and partners shall have no personal liability to the Client in respect of a claim, whether in
contract, tort, and/or any other cause of action in law. Accordingly, the client expressly
agrees that it will bring no proceedings and take no action in any court of law against any of
the consultants employees, principals, or partners in their personal capacity.
2013 9
Depreciation Report
All rights reserved. No part of this report shall be reproduced or used in any form by any
means, graphic, electronic, or mechanical, including photocopying, recording, typing or
information storage and retrieval, without the written permission of the author.
Notwithstanding the foregoing, the applicant herein has permission to reproduce the
report in whole or in part for the legitimate purposes of providing information to the
board of directors, unit owners, and others who have an interest in the project.
Specifically, the applicant has permission to provide insurance appraisal and Depreciation
Report information in disclosure documents, such as a Form B.
2013 10
Depreciation Report
Executive Summary
This executive summary has been prepared as a quick reference of pertinent facts and
estimates of this Depreciation Report, and is provided for convenience only. Readers are
advised to refer to the full text of this Depreciation Report for detailed information.
2013 11
Depreciation Report
*****
Current Replacement Cost: Is the price to replace or repair a major component right now.
Future Replacement Cost: Is the price to replace or repair a component when it will need
to be replaced, including inflation over the number of remaining years in the components
life span.
Current Reserve Fund Requirements: A ratio of how much funding should already be in
place, in order to reach full funding at the annual reserve fund assessment level listed.
Future Reserve Fund Accumulation: Is the Current Reserve Fund Requirements plus
compounded interest over the remaining life span of the component.
Future Reserve Fund Requirements: Are the Future Replacement Costs minus the Future
Reserve Fund Accumulation.
Annual Reserve Fund Assessment: Is the amount of money required annually to conduct
the needed replacements, assuming a fully funded model, and based upon a reverse
calculation from the previous figures.
Reserve Fund Asset Allocation: Defines the component costs as a percentage of the total.
2013 12
Depreciation Report
2013 13
Depreciation Report
Report Overview
The green bars represent the recommended annual contributions for the strata corporation as a whole. These will be divided between the owners based on unit entitlement, and broken down monthly.
The gradual rise in fees will allow the strata corporation to stay ahead of expenditures, and ideally avoid most special assessments.
Though included here as a graph item, The Points selected funding model does not include any special assessments.
The blue line represents the expenditures that are expected over the 30 year span of the Depreciation Report.
2013
14
Depreciation Report
The above chart represents annual expenditures toward reserve items in the coming 10
years. Since the complex is relatively new, the only significant upcoming expenditures are
for Exterior Finishes and Caulking in 2018. The first year of substantial expenditures is 2027,
where replacements are expected for the Balcony Waterproofing, Balcony Doors, and Security
Doors.
2013 15
Depreciation Report
Recommendations
Based on present financial conditions and the buildings age, the contingency reserve
fund for BCS 2429 The Point, is moderately deficient against the benchmark analysis.
Any deficiencies should be eliminated over time in order to meet adequacy, and ensure
proper funds are in place for major repairs and replacements.
Maintenance Operations Program recommendations, set out below and detailed in this
report, will assist the corporation in achieving and maintaining an adequate reserve fund.
In our opinion, if adhered to, the current reserve fund balance, recommended annual
contributions, and earned investment income will adequately fund immediate and future
reserve fund expenditures.
2. Major repairs and replacements should continue to be recorded in, and funded
from, a contingency reserve fund account.
3. The contingency reserve fund contribution of $ 60,000 per annum in 2013 should
be increased to $ 68,100 per annum in 2014 and thereafter by the amounts
detailed in the cash flow table, each subsequent year.
6. The reserve fund should be reviewed by the strata council every year to ensure
that the underlying assumptions are still valid and that the estimates remain
current. Changes should be catalogued and provided to the Depreciation Report
Planner prior to the legislated 3-year update.
7. The corporation should update the Depreciation Report every three (3) years in
accordance with the provisions of Section 94 of the British Columbia Strata
Property Act, amended 2009, Regulation 43/2000.
2013 16
Depreciation Report
May 17th/2013
2013 17
Depreciation Report
Depreciation report
6.2 (1) For the purposes of section 94 of the Act, a depreciation report must include all of
the following:
(d) the name of the person from whom the depreciation report was obtained
and a description of
(ii) the error and omission insurance, if any, carried by that person, and
(iii) the relationship between that person and the strata corporation;
(f) any other information or analysis that the strata corporation or the person
providing the depreciation report considers appropriate.
(2) For the purposes of subsection (1) (a) and (b) of this section, the physical component
inventory and evaluation must
(a) be based on an on-site visual inspection of the site and, where practicable, of
the items listed in paragraph (b) conducted by the person preparing the
depreciation report,
(b) include a description and estimated service life over 30 years of those items
that comprise the common property, the common assets and those parts of a
strata lot or limited common property, or both, that the strata corporation is
responsible to maintain or repair under the Act, the strata corporations bylaws
or an agreement with an owner, including, but not limited to, the following
items:
(ii) the building's exterior, including roofs, roof decks, doors, windows
and skylights;
2013 18
Depreciation Report
(iv) common amenities and facilities;
(c) identify common property and limited common property that the strata lot
owner, and not the strata corporation, is responsible to maintain and repair.
(3) For the purposes of subsection (1) (c), the financial forecasting section must include
(a) the anticipated maintenance, repair and replacement costs for common
expenses that usually occur less often than once a year or that do not usually
occur, projected over 30 years, beginning with the current or previous fiscal
year of the strata corporation, of the items listed in subsection (2) (b),
(b) a description of the factors and assumptions, including interest rates and
rates of inflation, used to calculate the costs referred to in paragraph (a),
(c) a description of how the contingency reserve fund is currently being funded,
(d) the current balance of the contingency reserve fund minus any expenditures
that have been approved but not yet taken from the fund, and
(e) at least 3 cash-flow funding models for the contingency reserve fund
relating to the maintenance, repair and replacement over 30 years, beginning
with the current or previous fiscal year of the strata corporation, of the items
listed in subsection (2) (b).
(4) For the purposes of subsection (3) (e), the cash-flow funding models may include any
one or more of the following:
(a) balances of, contributions to and withdrawals from the contingency reserve
fund;
(c) borrowings.
(6) For the purposes of section 94 (1) of the Act, "qualified person" means any person
who has the knowledge and expertise to understand the individual components, scope
and complexity of the strata corporations common property, common assets and those
2013 19
Depreciation Report
parts of a strata lot or limited common property, or both, that the strata corporation is
responsible to maintain or repair under the Act, the strata corporation's bylaws or an
agreement with an owner and to prepare a depreciation report that complies with
subsections (1) to (4).
(a) for the purposes of section 94 (2) (b) of the Act, 3 years;
(b) for the purposes of section 94 (2) (c) of the Act, 18 months;
(c) for the purposes of section 94 (3) (a) of the Act, the one year period
immediately preceding the date on or before which the depreciation report is
required to be obtained.
(8) A strata corporation is prescribed for the purposes of section 94 (3) (b) of the Act if
and for so long as there are fewer than 5 strata lots in the strata plan.
2013 20
Depreciation Report
In This Manual
Maintenance Operations Program is committed to meeting and surpassing the B.C.
Governments requirements for Depreciation Reports. To follow is a quick guide to
finding each of the legislated requirements of a Depreciation Report within this
document.
Legislated Requirements:
Strata Property Act B.C. Reg. 43/2000
6.2(1)(c) & 6.2(3)(a,c,d): Schedule C 30 Year Reserve Fund Cash Flow Projection and
Deficiency Analysis section, page 116
Additional Information
Executive Summary: This section provides a quick and simple overview of the findings of
the Depreciation Report, including the Cash Flow Table, which summarizes the financial
conclusions of the report. Charts and graphs further illuminate the data, illustrating the
major components, yearly expenditures, and the forecast for the next 10 years.
Methodology: The methodology section explains the contents of the report, and includes a
detailed analysis of how the figures for inflation and interest are obtained.
Benchmark Analysis: The benchmark analysis is a tool which assesses the ideal funding
level for your complex, and measures your funding levels against the ideal figure (fully-
funded). A fully-funded strata will never require special assessments or loans, and pays
equal amounts each year, preventing owners from paying for mistakes made by owners
before them. This section includes historical data, where available, to create the most
complete picture of the stratas financial needs.
Maintenance Guidelines and Forms: This section includes review guidelines and
reporting forms, suggestions on maintenance practices, and a Maintenance Schedule for
tasks that occur annually or more frequently. This schedule fills in the gaps in
expenditures, as the Depreciation Report only covers repair and maintenance tasks that
take place less often than annually.
2013 21
Depreciation Report
Methodology
Depreciation Report
A Depreciation Report is a financial document, which provides the basis for funding
major repairs and replacements of the common elements and assets of the corporation.
1. it identifies the reserve components and assesses their quality, normal life span,
and present condition;
2. it estimates the remaining serviceable years for each of the reserve components,
and proposes a time schedule for repairs and/or replacements;
5. it projects the future value of current reserve funds compounded at a long term
interest rate;
The Depreciation Report is a practical guide to assist the Strata Council in planning
budgets and maintenance programs.
REIC has established Reserve Fund Planning Standards that exceed the regulatory
requirements, and are now recognized and emulated across Canada. These standards,
presented throughout this report, consist of investigations, analyses, and calculations that
provide realistic and supportable reserve fund estimates.
2013 22
Depreciation Report
The anticipated maintenance, repair, and replacement costs for common expenses
that usually occur less often than once a year or that do not usually occur,
projected over 30 years, beginning with the current or previous fiscal year of the
strata corporation, of the items listed in subsection (2)(b)
A description of the factors and assumptions, including interest rates and rates of
inflation, used to calculate the costs referred to in paragraph (a).
This report provides an objective basis for any estimates of inflation factors and interest
rates. Inflation factors and interest rates must be derived from an economic analysis of the
marketplace.
The estimated inflation factor and the selected interest rate are powerful factors in
projecting reserve fund contributions and requirements. They can vary dramatically over
time, and must be periodically reviewed to ensure their relevance and accuracy.
The reserve fund projection factors must be periodically reviewed and adjusted in
accordance with changing economic conditions as part of the reserve fund updating
process, as mandated by the regulations.
Inflation Factors
Inflation measurement in reserve fund projections must be based on construction indices,
rather than the widely quoted Consumer Price Index (CPI), which measures the cost of a
basket of consumer goods, not construction costs.
The most widely recognized construction cost services providing periodic cost indices are
R.S. Means and Marshall & Swift / Boeckh.
2013 23
Depreciation Report
These numbers indicate that the trend of construction inflation rates over the past 20 years
has been fluid, but the year over year inflation rate seems to have peaked between 2004
and 2008, and levelled off since. The most recent Means Historical Cost Index data
indicates a 1.54% inflation increase between 2012 and initial data for 2013.
Each building has its own unique combination of basic costs. MSB uses 83 basic types of
costs necessary to build workable weighted schedules, comprising 19 building trades and
64 material types. The following are the percentage changes for MSBs Building Cost
Indexes relevant to BC (Western) for the previous 5 years, for both typical B.C. wood-
frame construction (D), and highrise construction (B):
2013 24
Depreciation Report
Judging by recent construction cost trends, it may be difficult to forecast inflation rates in
the coming years. A rate of 2-2.5% annually is probably fairly accurate given Marshall &
Swift/Boecks historical rates, and the slightly higher inflation value for highrise
construction.
We have adopted the RS Means / Marshall & Swift median rate of 2.50% for annual
inflation in calculating the future replacement costs hereinafter, to allow for potential
volatility. This figure should be updated regularly.
Interest Rates
Investment income can be a significant and increasing source of revenue for contingency
reserve funds, therefore, it is imperative that contingency reserve funds are continuously
and prudently invested. Prudent investment also includes a careful reading of the Strata
Property Act (B.C. Reg. 43/2000, amended March 2012, entitled Permitted investments for
investment of money from contingency reserve fund), which is included in the Addenda
section at the end of this document for reference. This document outlines what
investments are permitted for a strata corporations contingency reserve fund.
Reserve fund investments must be directly or indirectly guaranteed by governments.
Bank deposits and various investment instruments are insured by the Canada Deposit
Insurance Corporation up to a maximum of $100,000, covering principal and interest.
The ability of condominium corporations to earn the highest rate of interest available in
the marketplace, given the restricted conditions of investments, depends on the expertise
of financial management and the amount of available funds for investment. The balance
of the reserve fund, primarily, will dictate investment options and their corresponding
interest rates. Investment opportunities are widely advertised, ranging from bank
deposits, term deposits, and guaranteed investment certificates (GICs), to money market
instruments and government bonds.
The following are some basic investment returns achievable for corporations, given
present market conditions (May 17th/2013), low-risk, and local institutions.
TD Canada Trust:
3 Year Premium Rate Cashable GIC 1.70%
High-Interest Savings Account 1.10%
Royal Bank:
RBC High Interest eSavings Account 1.20%
Five Year Redeemable GIC 1.825%
*** The investment returns listed above should be verified by the institution prior to budgeting, as rates can change rapidly and
without notice. The listings above should not be considered an endorsement by Maintenance Operations Program.
Prudent reserve fund investment requires that investments are reasonably matched with
anticipated reserve fund expenditures, ensuring reserve fund liquidity. Therefore, funds
should be invested in a laddered portfolio, which ensures that reserve funds are available
when needed.
2013 25
Depreciation Report
Some management firms use their purchasing power by directing business to a
particular financial institution to negotiate favourable interest rates for all their clients.
This approach may benefit the smaller corporations and is an important consideration
when selecting an appropriate interest rate.
The benchmark calculations and the reserve fund projections are based on the assumption
that reserve fund contributions are constantly and continuously invested.
For the purposes of this Depreciation Report, a 1.25% interest rate will be used, based
upon the corporations present interest rate.
* The above outline is for reference only. Strata investment decisions should be based upon a
thorough examination of the Strata Property Act, as well as consultation with a recognized
professional in the field.
2013 26
Depreciation Report
Property Information
Property Description:
BCS 2429 The Point
610 Victoria Street
New Westminster, BC, V3M 0A5
Baywest Management Corp. manages the property. The firm has a great deal of
experience in managing properties in the lower mainland, and the firms representative,
Robert Douglas, has been managing residential properties for many years.
Building Plans
The following plans were examined in the performance of the Depreciation Report:
2013 27
Depreciation Report
Site Plan
2013 28
Depreciation Report
Exterior Walls
The exterior walls consist of painted (elastomeric) concrete, aluminum framed double-
glazed window wall systems, brick masonry, and aluminum framed and glazed
storefront systems.
Interior Construction
Drywall ceilings and walls, painted, with wood baseboards. Stairwells are painted
concrete. Flooring is predominantly carpet in corridors, with some ceramic tile at the
entryways.
Mechanical
Dry sprinkler system (fire) covering the underground Parkade; central HVAC system;
sanitary exhaust fans, and common area electric baseboard heating. Parkade is
mechanically vented (automatic), with blower units for storage and mechanical spaces.
Hot water is produced by hot water heaters located in each suite.
Conveying Systems
Two traction elevators service the complexs vertical conveying needs, alongside several
concrete stairwells.
2013 29
Depreciation Report
Electrical
Incoming metered service with main disconnects and distribution panel for each floor;
wiring and fixtures for light and power; telephone/cable wiring; house panels. Incoming
utilities are underground.
Amenities
Heated pool, hot tub, and sauna, including washrooms/change rooms. Exercise room and
media/games room. Landscaped central courtyard area.
2013 30
Depreciation Report
Property Inspection
The property was inspected for the purposes of preparing this report on July 17th, 2012, by
Markus Rissiek.
Depreciation Reports
No previous depreciation reports were available for review.
Component Classification
Reserve Fund Components are conveniently classified in terms of component types,
common element facilities, and site improvements. The component inventory consists of
the reserve components, described and analyzed hereinafter, and shown in Schedules
A, B, and C.
Type of Component
Utilization
Material
Workmanship
Quality
Functional Obsolescence
Environmental Factors
Regular Maintenance
Preventive Maintenance
Observed Condition
2013 31
Depreciation Report
The critical aspect in a Life Span Analysis is the observed condition of each reserve
component, which is based on:
The Life Span Analysis culminates in component life span estimates, as follows:
A life span analysis is a subjective, or empirical, assessment of the life cycle status of a
reserve component, and as such, it is only as good as the considered opinion of the
reserve fund planner. Furthermore, the life span of a reserve component is subject to
change due to numerous factors.
2013 32
Depreciation Report
Cost data have been calculated using construction cost services, including Marshall &
Swift/Boeckh Commercial Building Valuation System, the Means Repair & Remodelling
Cost Data, and the Hanscomb's Yardstick for Costing, modified as to time, location and
quality of construction. We also verified some estimates by seeking quotations from
contractors, fabricators, and suppliers. Moreover, we have used our own computer
programs and extensive cost compilations and databases.
All costs are strictly estimates, and are subject to confirmation at the time competitive bids
are obtained from contractors specializing in the repair or replacement work required.
The following factors have been considered in calculating the Repair and Replacement
Cost Estimates:
Quality of construction
Replacement cost estimates are based on the assumption of using quality materials, as
specified or built, or in the case of older developments, as required under current building
code regulations, at contractors' prices, using union labour and current construction
techniques, and including contractors' overhead and profit.
The costs of repairs and/or replacements of many reserve components are invariably
higher than original building costs when contractors have considerable latitude in
planning their work and can utilize economies of scale to keep costs within construction
budgets. In contrast, repair work must frequently be performed in an expedient manner
with proper safety precautions and within certain constraints.
Cost estimates take into account such additional costs as special construction, safety
installations, limited access, noise abatements, and the convenience of the occupants.
Contingency Reserves
It is frequently impossible to forecast the incidence of repairs or replacements of various
reserve components, particularly, major components such as: road pavement, sewer, and
2013 33
Depreciation Report
water systems. Therefore, reserve estimates are of a contingency nature, and as such, they
are subject to changing conditions and repair experience over time.
2013 34
Depreciation Report
Description
Potential Deterioration
Unit Quantities
Deficiency Analysis
2013 35
Depreciation Report
Reserve Components
Building - Structural and Architectural
Substructure & Parkade
Physical Description: This component is an allowance designed to cover the ongoing
upkeep of the four level parking structure and foundation. This includes: crack repair for
the floors, walls, and ceilings, epoxy injections for minor leaks, columns, expansion joints,
and repair items for the electrical, garbage, generator, and storage rooms. The mechanical
systems themselves, however, are included later in this report, under Building
Mechanical Systems. The replacement of the suspended slab waterproofing is not included
here, but should be considered of critical importance should persistent parkade leakage or
membrane damage become apparent. An allowance for spot repairs to this membrane is
included here, but consider a full replacement if any significant issues are noted with the
suspended slab membrane, or at the direction of a professional in the field.
Financial Analysis: No major expenditures were reported with regard to the parkade
area. This component should be considered an allowance for potential issues, and not a
replacement value.
Current Repair/
Replacement Cost Estimate: $419,189
2013 36
Depreciation Report
Deficiency Analysis: The condition of the parkade structure is generally very good, but
several active and inactive leaks have been noted (Apex Building Sciences, June 2012).
Monitor for signs of further deterioration and repair as needed.
2013 37
Depreciation Report
Superstructure
Physical Description: This component is an allowance designed to cover the ongoing
upkeep of the complexs superstructure, consisting of the reinforced concrete walls and
floors, as well as the cantilevered concrete balconies. This includes minor crack repair and
patching, as well as reapplication of relevant waterproofing to repaired areas. Structural
issues should be directed by a professional in the field, and are not included here.
Current Repair/
Replacement Cost Estimate: $61,274
Deficiency Analysis: Numerous issues have been noted with regard to the
Superstructure, including hairline cracking in multiple locations, and voids in the
concrete, which in some cases are interrupting the function of associated waterproofing
membranes (Apex Building Sciences, June 2012). Monitor for signs of further deterioration
and repair as needed.
2013 38
Depreciation Report
Garage Doors
Physical Description: This component includes the horizontally operable underground
Parkade gate, motor, and hoist systems.
Financial Analysis: No major replacements or repairs were noted for the overhead garage
doors. This component includes a full replacement of each door, including its hoist and
motor.
Condition Analysis: The garage door and hoist systems appear to be in good condition
overall, with no significant defects or issues. Maintenance is believed to be performed by
Ideal Door.
Current Repair/
Replacement Cost Estimate: $74,576
2013 39
Depreciation Report
2013 40
Depreciation Report
Financial Analysis: No major expenditures have been reported for the window wall
system. This component is designed to prepare the strata corporation for the replacement
of the window wall system. Though the typical life span of this system (40 years) puts its
replacement outside of the scope of this study, the substantial nature of the expenditure
makes preparing for it vital. Though no replacement is expected within 30 years, this
component includes the majority of a total replacement cost, to make transitioning to a
replacement value (for coming legislated updates) easier. There is also some industry
debate regarding the expected life span of a window wall system, making preparedness
essential.
Condition Analysis: The window wall cladding system appears to be in good overall
condition, though some issues have been noted with hardware operability and
weatherstripping.
Unit Quantity and Cost Estimates: Unit Quantity: 31,113 sq. ft.
Current Repair/
Replacement Cost Estimate: $1,451,764
Deficiency Analysis: Some minor issues have been noted with regard to operability of
windows and air infiltration (Apex Building Sciences, June 2012).
2013 41
Depreciation Report
Aluminum
Framed
Window-Wall
System
2013 42
Depreciation Report
Financial Analysis: No major expenditures have been noted with regard to the brick
masonry. This component includes re-pointing and repair of the masonry only, and is not
a replacement item.
Condition Analysis: The masonry appears to be in good overall condition, though some
staining and efflorescence has been noted.
Current Repair/
Replacement Cost Estimate: $51,695
Deficiency Analysis: Some efflorescence and staining of the masonry has been noted
(Apex Building Sciences, June 2012), though condition overall appears to be very good.
2013 43
Depreciation Report
Brick
Masonry at
The Point
2013 44
Depreciation Report
Financial Analysis: No major expenditures were noted for the storefront cladding system.
This component includes a full replacement of the storefront system, including glazing,
framing, and doors. This component is priced in the same way as the Window Wall
system, to allow for the allotment of funds beyond the 30 year scope of the study (See
Exterior Walls: Window Wall earlier in this report).
Unit Quantity and Cost Estimates: Unit Quantity: 6,458 sq. ft.
Current Repair/
Replacement Cost Estimate: $548,423
2013 45
Depreciation Report
2013 46
Depreciation Report
Financial Analysis: No major expenditures have been reported for the balcony and
eyebrow waterproofing. This component includes a full replacement of these
waterproofing systems.
Condition Analysis: The condition of the balconies appears to be very good, with only
minor deficiencies noted.
Current Repair/
Replacement Cost Estimate: $281,381
Deficiency Analysis: Some sloping issues have been noted, and the waterproofing may
be compromised in some areas where voids in the concrete prevented proper application
of the membrane (Apex Building Sciences, June 2012). Assuming these deficiencies are
repaired, the balcony and eyebrow waterproofing appears to be in very good condition.
2013 47
Depreciation Report
2013 48
Depreciation Report
Balcony Railings
Physical Description: This component includes the powder-coated aluminum railings
throughout the complex, including both picket style railings and railings with tempered
glass inserts.
Financial Analysis: No significant expenditures have been reported for the exterior
railings. This component includes a full replacement for all exterior railings, as well as an
incidental allowance for failed fasteners, damage, and premature failures.
Condition Analysis: The railings appear to be in very good overall condition, with no
major issues noted.
Current Repair/
Replacement Cost Estimate: $650,948
2013 49
Depreciation Report
2013 50
Depreciation Report
Exterior Awnings
Physical Description: This component includes the metal awnings sheltering the
sidewalks around The Point, including the canopy glazing.
Financial Analysis: No major expenditures were reported for the exterior awnings. The
awning system is expected to outlast the scope of this report, therefore no full
replacement is included here. This component includes periodic high-pressure washing
(roughly once every 10 years), and an allowance for incidental glass failure. Refinishing of
the metal framework is also included in this report, under the Exterior Finishes component.
The awnings should also be periodically assessed for structural integrity by a professional
in the field.
Condition Analysis: The awnings appear to be in good overall condition, with no major
issues noted.
Unit Quantity and Cost Estimates: Unit Quantity: 2,562 sq. ft.
Current Repair/
Replacement Cost Estimate: $36,824
2013 51
Depreciation Report
2013 52
Depreciation Report
Windows
Physical Description: This component includes all exterior double-glazed aluminum
framed windows throughout the building envelope, excluding the window wall and
storefront systems.
Financial Analysis: No major expenditures have been reported for the exterior windows.
This component includes a full replacement of all exterior windows, including frames,
glazing, and accessories.
Condition Analysis: The windows appear to be in good overall condition, with some
minor issues relating to operability and drafts.
Current Repair/
Replacement Cost Estimate: $310,989
Deficiency Analysis: Some issues were reported with regard to operability and drafts
(Apex Building Sciences, June 2012). There are also extensive weatherstripping issues,
potentially contributing to or causing drafts, which will be addressed separately in the
Weatherstripping component later in this report.
2013 53
Depreciation Report
2013 54
Depreciation Report
Financial Analysis: No major expenditures were reported for the Balcony Doors. This
component includes a full replacement for all swing and sliding style balcony doors,
including glazing and accessories.
Condition Analysis: The doors appear to be in very good overall condition, with no
significant issues to note.
Current Repair/
Replacement Cost Estimate: $376,573
2013 55
Depreciation Report
2013 56
Depreciation Report
Security Doors
Physical Description: This component includes the exterior metal security doors, some of
which include wired glass vision lites.
Financial Analysis: No major expenditures have been recorded for the security doors.
The value included here is for the full replacement of the exterior security doors and
associated hardware.
Condition Analysis: The security doors appear to be in good condition overall, with no
major deficiencies reported.
Current Repair/
Replacement Cost Estimate: $115,890
2013 57
Depreciation Report
2013 58
Depreciation Report
Caulking
Physical Description: This component includes the polyurethane joint sealant (caulking)
throughout the building envelope.
Financial Analysis: No major expenditures have been noted for the caulking. This
component includes both replacements and ongoing spot repairs for the caulking
throughout the building envelope.
Condition Analysis: The condition of the caulking is generally good, with a few issues
noted.
Current Repair/
Replacement Cost Estimate: $114,290
Deficiency Analysis: Some debonding has been noted, and some locations requiring
caulking have not had it applied (Apex Building Sciences, June 2012). Deficiencies should
be remedied as soon as possible, and caulking repairs should be made on an ongoing
basis, as necessary.
2013 59
Depreciation Report
2013 60
Depreciation Report
Weatherstripping
Physical Description: This component includes all weatherstripping throughout the
building envelope.
Financial Analysis: No major expenditures have been noted for the weatherstripping at
The Point. This component provides for a full replacement of all weatherstripping
throughout the building envelope.
Current Repair/
Replacement Cost Estimate: $78,247
Deficiency Analysis: Widespread issues have been noted with the weatherstripping at
The Point (Apex Building Sciences, June 2012). Weatherstripping is noted to be loose,
missing, or falling off in a significant portion of applied locations. Replacement is
recommended immediately.
2013 61
Depreciation Report
Exterior Finishes
Physical Description: This component includes exterior finishing tasks for the exterior
metal surfaces (security doors, awnings, light posts, etc.), exposed concrete including
balcony undersides (elastomeric paint), and all exterior wood products (benches, etc.).
Financial Analysis: No major expenditures have been recorded for the exterior finishes at
The Point. Though these finishing tasks are listed as a single expenditure, which may help
the strata save money in set-up costs, they can just as easily be separated for a
replacement date more in line with each individual components failure rate, though
moderate adjustments will be required for additional setup costs. The strata council
should make an informed decision on refinishing tasks as they become necessary,
whether aesthetic or for protective purposes. This component also includes touch-ups to
areas of damage or premature failure.
Condition Analysis: The exterior finishes are generally in fairly good condition, with
some issues noted.
Unit Quantity and Cost Estimates: Unit Quantity: 69,789 sq. ft.
Current Repair/
Replacement Cost Estimate: $201,146
Deficiency Analysis: Some incidences of chipping and staining were noted, and extensive
peeling has been noted as well, particularly to areas exposed to persistent moisture (Apex
Building Sciences, June 2012). Touch-up damaged finishes as required.
2013 62
Depreciation Report
2013 63
Depreciation Report
Financial Analysis: No major expenditures have been reported for the roofing system at
The Point. This component includes a full replacement of all flat roofing systems,
including filter fabric, insulation, cap flashing, and associated accessories.
Condition Analysis: The roofing membrane condition, where visible, appears to be good,
though some vegetation growth, nesting birds, and drain blockages have been noted.
Unit Quantity and Cost Estimates: Unit Quantity: 16,360 sq. ft.
Current Repair/
Replacement Cost Estimate: $221,024
Deficiency Analysis: Bi-level drain blockages have been reported (Apex Building
Sciences, June 2012), and there appear to be nests and vegetation growth amongst the
river rock ballast in some areas.
2013 64
Depreciation Report
2013 65
Depreciation Report
Financial Analysis: No major expenditures have been reported for the interior decorating
and painting. This component includes prep work and repainting for the interior walls
and stairwells, as well as painting of the door frames, baseboards, and trim. The
refinishings and replacements included in this expenditure are grouped together to take
advantage of economy of scale. Each component, however, can be individually
remediated as necessary using these funds, at such a time as deemed necessary by the
strata council, with minor adjustments for additional setup costs.
Unit Quantity and Cost Estimates: Unit Quantity: 59,872 sq. ft.
Current Repair/
Replacement Cost Estimate: $91,766
Deficiency Analysis: Some minor water damage and staining was noted (Apex Building
Sciences, June 2012).
2013 66
Depreciation Report
2013 67
Depreciation Report
Financial Analysis: No major expenditures have been reported for the common area
flooring. The removal and replacement of the carpeting and tile systems has been
included here, as well as commercial grade sponge rubber carpet padding for the
common area hallways.
Condition Analysis: The interior common area carpeting, as well as tile, appears to be
well maintained and performing well.
Unit Quantity and Cost Estimates: Unit Quantity: 14,016 sq. ft.
Current Repair/
Replacement Cost Estimate: $187,380
2013 68
Depreciation Report
2013 69
Depreciation Report
Financial Analysis: No major repairs or replacements have been reported for the suite
doors and interior fire doors. This component does not include a full replacement. The
allowance listed here is for general touch-up and repair, as well as proportional
replacements of locksets and hardware which are damaged or prematurely break down,
based on a conservative failure rate estimate. Changing fire codes may require updates to
egress doors, which should be considered independently of the expenditure listed here.
Repair and refinishing is meant to take place as needed, and the 30 year remaining life
span estimate is designed simply to stretch the expenditure over the duration of the
report, not restrict the strata councils decisions on repair.
Condition Analysis: The interior suite doors and fire doors appear to be in good overall
condition, with no major issues noted.
Current Repair/
Replacement Cost Estimate: $25,650
2013 70
Depreciation Report
2013 71
Depreciation Report
Lobby Renovation
Physical Description: This component covers the lobby elements not covered elsewhere
in this Depreciation Report, specifically the furniture, decorative plants, and
miscellaneous expenditures.
Financial Analysis: No major replacements or repairs have been noted for the common
area lobby. This component includes a furniture and decoration allowance, as well as a
general contingency value. Interior painting, flooring, baseboards, fire equipment, and
doors are all included in other entries in this Depreciation Report.
Condition Analysis: The lobby appears to be well maintained, and in good condition.
Current Repair/
Replacement Cost Estimate: $4,704
2013 72
Depreciation Report
2013 73
Depreciation Report
Financial Analysis: No major expenditures have been noted for the elevator cabs at The
Point. This component includes ceiling and flooring replacement, as well as an allowance
for incidental costs such as minor physical damage and graffiti removal.
Condition Analysis: The elevator cabs appear to be in good condition, with no major
issues observed.
Current Repair/
Replacement Cost Estimate: $15,870
2013 74
Depreciation Report
Exercise Room
Physical Description: This component covers the exercise room, including mirrors,
equipment provision, and upkeep.
Financial Analysis: No major expenditures have been reported for the exercise room.
This component covers basic maintenance items, repair, and upkeep. A full equipment
replacement is not included here, and upgrades or modernizations should be priced for
separately.
Condition Analysis: The condition of the exercise room appears to be very good. No
major issues have been reported.
Current Repair/
Replacement Cost Estimate: $3,920
2013 75
Depreciation Report
2013 76
Depreciation Report
Media/Games Room
Physical Description: This component covers the media/games room at The Point,
including pool table, furniture, decoration, fixtures, and washroom.
Financial Analysis: No major expenditures have been reported for the media/games
room. This component includes minor repairs and replacement items for the pool table,
furniture, and decorations. The remaining fixtures (fridge, sink, washroom fixtures) are
included for basic maintenance purposes only.
Condition Analysis: The condition of the media/games room appears to be very good,
and no major issues have been reported.
Current Repair/
Replacement Cost Estimate: $4,144
2013 77
Depreciation Report
2013 78
Depreciation Report
Financial Analysis: A recent expenditure was noted for the upkeep of the pool area
equipment. This component includes the full replacement of the sauna equipment, as well
as a repair allowance for the pool/hot-tub equipment, plumbing fixtures, furniture, and
sauna woodwork. No replacement value is allotted for the tile work, though a
proportional value is included for isolated damage or premature breakdown.
Condition Analysis: The pool area appears to be well maintained and in good overall
condition.
Current Repair/
Replacement Cost Estimate: $44,800
2013 79
Depreciation Report
2013 80
Depreciation Report
Financial Analysis: No major replacements or overhauls have been reported for to the
elevating systems. This component includes a full modernization, but no allotment for
structural components.
Potential Deterioration: Potential deterioration for the elevator system comes primarily
from mechanical and electrical failures as the unit ages. A solid professional maintenance
regimen, however, will not only prolong the service life of the elevator system, but
prevent inconvenient breakdowns.
Condition Analysis: The elevating devices at The Point appear to be in good condition,
with a solid professional maintenance regime undertaken. The maintenance contractor is
ThyssenKrupp Elevator.
Current Repair/
Replacement Cost Estimate: $414,400
2013 81
Depreciation Report
2013 82
Depreciation Report
Plumbing System
Physical Description: Included here is an allowance for the ongoing upkeep of the
plumbing system at The Point. This component is concerned primarily with the upkeep of
the piping itself, including risers, branch piping, and circulation pumps.
Financial Analysis: The funds allotted here are designated for ongoing repairs to the
system, as pinhole leaks and minor failures occur over time. This includes repairs to
drywall, as well as finishes damaged as a result of failures. This option was chosen based
upon a business as usual policy generally undertaken by most strata corporations.
Other options include a full replacement of the piping system, which typically takes the
form of a PEX (flexible plastic) or rigid plastic (PVC, CPVC, or ABS) piping system, but
may also consist of a replacement in kind. A water treatment system may also be effective
in the management of pinhole leaks, and an epoxy coating for the inside of the piping can
prolong the life of the system. Should the strata council choose a different strategy on
plumbing upkeep, an adjustment should be made to this report to reflect the change in
course. Though the expenditure is included at year 20 of this report, this component is an
allowance designed to cover costs over time. The selection of a near term date is simply
designed to amass the needed funds sooner, rather than later, in preparation for
unanticipated failures.
Current Repair/
Replacement Cost Estimate: $409,248
2013 83
Depreciation Report
HVAC Systems
Physical Description: This component covers the primary air handling unit and
supporting fan system, heat pumps servicing the commercial units**, as well as the
parkade exhaust systems, including blowers, CO2 sensors, and ventilation fans for the
service and storage rooms. Necessary accessories are included for all systems.
Condition Analysis: No major issues have been reported. The HVAC systems are
professionally maintained by Gordon Latham Ltd. (Lathams).
Current Repair/
Replacement Cost Estimate: $54,461
**Commercial heat pumps are included here, and are one of the only components at The
Point exclusive to the commercial units. Strata sections were not represented in this report
due to the small scale of exclusive use components. Additionally, no differentiation was
requested. Should the corporation require a separation of these components, it can be
accommodated, but will influence the final data negligibly.
2013 84
Depreciation Report
2013 85
Depreciation Report
2013 86
Depreciation Report
Emergency Generator
Physical Description: This component covers the Emergency Generator, including
batteries, fuel storage, ventilation, and associated accessories.
Financial Analysis: No major expenditures have been noted for the emergency generator.
A full replacement of the major systems is included here, excluding structural elements.
Condition Analysis: No significant emergency generator issues have been reported, and
ongoing maintenance is being undertaken by Simson-Maxwell. Replacement or repair
should be undertaken at the direction of the mechanical professional responsible for this
system.
Current Repair/
Replacement Cost Estimate: $30,413
2013 87
Depreciation Report
Emergency Generator
2013 88
Depreciation Report
Financial Analysis: No major expenditures were reported for the common area domestic
hot water system. This item is included as an allowance for the ongoing repair and
replacement of the mechanical components of the common area domestic hot water
system. Repairs and replacements should be undertaken as needed, with consultation
from a professional mechanical firm in the field.
Condition Analysis: The common area domestic hot water system appears to be in fair
condition.
Current Repair/
Replacement Cost Estimate: $6,850
2013 89
Depreciation Report
2013 90
Depreciation Report
Financial Analysis: No major expenditures or repairs were noted for the sump pump
system. This component includes the full replacement of the sump system.
Condition Analysis: The sump pump systems were submerged during on-site review,
but appeared to be functioning as intended.
Current Repair/
Replacement Cost Estimate: $3,229
2013 91
Depreciation Report
2013 92
Depreciation Report
Sprinkler System
Physical Description: This component is a maintenance and repair allowance for the
sprinkler systems, and does not include a full replacement cost. The sprinkler systems at
The Point protect the four levels of underground parkade, as well as associated service
and storage rooms.
Financial Analysis: No major expenditures have been reported for the sprinkler systems.
The expenditure listed here is an allowance for periodic replacements of deficient
components. The expenditure listed in 2031 does not indicate repairs or replacements, but
is designed to ensure needed funds are ready when necessary. Major repairs and
replacements should be made with the professional input of a qualified fire system
professional.
Condition Analysis: The sprinkler system appears to be well maintained, and is currently
monitored by Mircom Engineered Systems. This system should continue to be regularly
monitored by a qualified fire systems professional.
Current Repair/
Replacement Cost Estimate: $54,898
2013 93
Depreciation Report
2013 94
Depreciation Report
Electrical Distribution
Physical Description: This component is included as an ongoing maintenance and repair
allowance for the electrical system, and does not include a full replacement.
Financial Analysis: No major expenditures have been reported for the electrical system.
Condition Analysis: No major issues have been reported concerning the electrical system.
Regular maintenance should be conducted by a qualified electrical contractor.
Current Repair/
Replacement Cost Estimate: $77,259
2013 95
Depreciation Report
Financial Analysis: No major expenditures have been reported for the access control and
security system. This component is an allowance for ongoing repairs, replacements, and
updates
Potential Deterioration: The access control and security system is subject to general wear
and tear, physical damage, and electrical and mechanical breakdown over time.
Condition Analysis: The access control and security system appears to be performing
well, and shows no signs of damage or disrepair. Ensure regular maintenance is
conducted by a qualified professional in the field.
Current Repair/
Replacement Cost Estimate: $38,080
2013 96
Depreciation Report
2013 97
Depreciation Report
Financial Analysis: No major expenditures have been reported for the life safety systems.
The funds allotted here are designated as a repair and replacement allowance, and should
be utilized in cooperation with a qualified fire protection specialist.
Condition Analysis: The condition of the life safety systems appears to be quite good.
Ongoing maintenance and inspection of these systems is presently undertaken by Mircom
Engineered Systems, and professional monitoring should continue.
Current Repair/
Replacement Cost Estimate: $61,967
2013 98
Depreciation Report
Financial Analysis: No major expenditures have been reported for the common area
baseboard heaters. The provision here is for periodic repair and replacement of the
baseboard heaters, as required.
Condition Analysis: The common area baseboard heaters appear to be in good overall
condition.
Current Repair/
Replacement Cost Estimate: $18,479
2013 99
Depreciation Report
2013 100
Depreciation Report
Site Improvements
Financial Analysis: No major expenditures have been reported for the paving and
walkways. The value included here is for crack repair over time, as well as the application
of a surface treatment (slurry seal) to prolong the life of the driving surfaces (excluding
walkways). Monitor the performance of the paving and walkways regularly, and consider
an adjustment to the figure listed here should degenerating conditions indicate a full
replacement may be necessary.
Potential Deterioration: The paved driving surfaces and walkways are susceptible to de-
icing salt corrosion, impact damage, and freeze-thaw cycles. Typically, however,
deterioration comes from shifting of the base under the paved surface, which may be
caused by large tree roots, seismic activity, or erosion.
Condition Analysis: The paved surfaces appear to be in good overall condition, with no
major issues apparent.
Unit Quantity and Cost Estimates: Unit Quantity: 1,145 sq. ft.
Current Repair/
Replacement Cost Estimate: $10,420
2013 101
Depreciation Report
2013 102
Depreciation Report
Financial Analysis: No major expenditures have been reported for the site services. This
component is an allowance designed to allow for potential failures, and should remain in
the contingency reserve fund past its expected life span if unused.
Current Repair/
Replacement Cost Estimate: $13,400
2013 103
Depreciation Report
Irrigation System
Physical Description: This component includes the exterior irrigation system for the
landscaped grounds, and assumes a full replacement across the landscaped areas.
Financial Analysis: No major expenditures have been reported for the irrigation system
at The Point. This component designates a full replacement, which does not typically
include removal of the old irrigation system, but simply the installation of a new system.
Removal of the existing system, if desired by the strata council, will need to be funded
separately from this report, or requested during an update (once every three years, by
legislation).
Condition Analysis: The irrigation system appears to be in good condition, and no major
issues have been reported.
Unit Quantity and Cost Estimates: Unit Quantity: 1,550 sq. ft.
Current Repair/
Replacement Cost Estimate: $2,201
2013 104
Depreciation Report
Exterior Lighting
Physical Description: This component includes the exterior lighting at The Point,
including light posts and wall-mounted exterior lights.
Financial Analysis: The figure listed here is for gradual replacements with failure or
damage, and does not include a full replacement or aesthetic replacements.
Current Repair/
Replacement Cost Estimate: $4,511
2013 105
Depreciation Report
2013 106
Depreciation Report
Reserve Updates
Physical Description: This component covers updates to the Depreciation Report every 3
years.
Financial Analysis: The funds included for this component cover updates to the
Depreciation Report every 3 years, as per legislation. If a new Depreciation Report is
required, it will need to be budgeted for separately. The estimates included here do not
constitute a quote from Maintenance Operations Program, as pricing may fluctuate over
time.
Current Repair/
Replacement Cost Estimate: $3,500
2013 107
Depreciation Report
The reserve fund estimates have been prepared without regard to the current financial
position of the corporation or the current reserve fund contributions by unit owners, and
as such, they represent the optimum reserve fund operation, which assumes that the
corporation has continuously assessed adequate reserve funding from the beginning.
This Benchmark Analysis is the foundation of the REIC Reserve Fund Planning System, as
it provides the basis for comparison to the actual reserve fund operation. The REIC
Benchmark Analysis provides the standard for reserve fund planning and property
maintenance, and as such, it is a valuable management and maintenance resource
document.
The foregoing program represents the practical application of reserve fund budget
planning and management. When applied, as outlined, the Depreciation Report will cover
anticipated reserve fund expenditures and any contingencies.
Due to rounding automatically executed by our accounting software, there may be minor
discrepancies in the data, which are not deemed statistically significant.
2013 108
Depreciation Report
2013 109
Depreciation Report
In accordance with these estimates, the corporation should have $ 1,402,647 in its reserve
fund at the end of its current fiscal year, and the assessed annual payments or
contributions to the reserve fund by unit owners should be $ 409,582 based on a fully
funded study using the findings of this benchmark analysis.
2013 110
Depreciation Report
The property management company, Baywest Management Corp., prepared the financial
statements, with the June 4th/2012 statement being the one used for the conclusions listed
here.
Exceptions
To the best of our knowledge, no limited common property or common property areas
have been designated for maintenance or repair by the unit owner rather than the Strata
Corporation. Should changes be made regarding maintenance or repair responsibilities,
the professional responsible for updating this report should be informed.
2013 111
Depreciation Report
2013 112
Depreciation Report
The current reserve fund requirement is an estimate of a fully funded reserve fund, based
on the Benchmark calculation.
The reserve fund of BCS 2429 The Point, is showing a moderate shortfall at the end of
the 2013 fiscal year, as shown below:
2013 113
Depreciation Report
Adequacy should not be confused with full-funding, which refers to a sustainable long-
term plan which spreads the cost of replacements evenly over the owners for the
remaining life of the building. Adequacy should also not be confused with the Reserve
Fund Surplus line at the bottom of the 30 Year Cash Flow Projection and Deficiency
Analysis. This line is a measure of success against the Benchmark Analysis, which defines
the stratas requirements under a full-funding model. Being deficient on the reserve Fund
Surplus line does not mean a strata is inadequate, simply that they have not yet reached
full funding.
In our opinion, the current reserve fund and proposed contributions for BCS 2429 The
Point, require adherence to the recommendations listed in this report to remain adequate
for future reserve fund expenditures.
2013 114
Depreciation Report
Cash Flows
These are the regular reserve fund contributions, special assessments, and interest income
based on 1.25% of the opening balance.
Cash Expenditures
These are annual expenditures listed in the categories established by the Depreciation
Report. Records or ledger accounts of these expenditure categories should be kept
showing reserve fund allocations and charges in a chronological order for control and
reference.
Deficiency Analysis
The Reserve Deficiency has been projected by formula, taking into account the inflation
factor, interest rates, and reserve fund expenditures. Therefore, any reserve fund
expenditures will not affect the reserve fund deficiency because such expenditures will
also affect the reserve requirements.
2013 115
Depreciation Report
Schedule C - 30 Year Reserve Fund Cash Flow Projection and Deficiency Analysis
30 Year Projection Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year
Year ending Decem ber 31 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042
OPENING BALANCE 224,587 207,191 277,881 354,879 447,043 552,203 302,251 426,157 577,071 745,155 937,885 1,162,476 1,308,671 1,446,429 1,512,751 694,209 683,735 973,453 518,030 57,429 41,705 760,522 1,627,193 1,217,954 2,065,166 2,948,146 3,836,027 4,734,325 5,413,484 6,338,318
Reserve Fund Contributions 2.50% 60,000 68,100 77,294 87,728 99,571 113,014 128,270 145,587 165,241 187,549 212,868 241,605 274,222 311,241 353,259 400,949 455,077 516,513 586,242 665,384 755,211 857,165 857,165 857,165 857,165 857,165 857,165 857,165 857,165 857,165
Special Assessment
Reserve Fund Interest Income 1.25% 2,807 2,590 3,474 4,436 5,588 6,903 3,778 5,327 7,213 9,314 11,724 14,531 16,358 18,080 18,909 8,678 8,547 12,168 6,475 718 521 9,507 20,340 15,224 25,815 36,852 47,950 59,179 67,669 79,229
Total Cash Resources 287,394 277,881 358,648 447,043 552,203 672,119 434,299 577,071 749,526 942,018 1,162,476 1,418,612 1,599,251 1,775,751 1,884,919 1,103,836 1,147,359 1,502,134 1,110,747 723,531 797,438 1,627,193 2,504,698 2,090,343 2,948,146 3,842,163 4,741,142 5,650,669 6,338,318 7,274,712
TOTAL EXPENDITURES 80,203 0 3,769 0 0 369,868 8,142 0 4,371 4,133 0 109,941 152,822 263,000 1,190,710 420,101 173,906 984,104 1,053,318 681,826 36,916 0 1,286,744 25,177 0 6,136 6,817 237,185 0 5,864,222
CLOSING BALANCE 207,191 277,881 354,879 447,043 552,203 302,251 426,157 577,071 745,155 937,885 1,162,476 1,308,671 1,446,429 1,512,751 694,209 683,735 973,453 518,030 57,429 41,705 760,522 1,627,193 1,217,954 2,065,166 2,948,146 3,836,027 4,734,325 5,413,484 6,338,318 1,410,490
DEFICIENCY ANALYSIS
Reserve Requirem ents 1,402,647 1,322,444 1,748,557 2,176,227 2,613,011 3,055,256 3,133,161 3,573,765 4,028,019 4,483,580 4,945,074 5,416,470 5,783,817 6,112,874 6,335,867 5,633,938 5,693,843 6,000,692 5,501,178 4,926,207 4,715,541 5,147,151 5,621,072 4,814,174 5,258,756 5,734,072 6,209,194 6,689,574 6,945,591 7,441,993 2,080,378
Reserve Fund Surplus -1,115,253 -1,470,675 -1,821,347 -2,165,968 -2,503,053 -2,830,910 -3,147,608 -3,450,948 -3,738,426 -4,007,189 -4,253,993 -4,475,145 -4,666,445 -4,823,116 -4,939,728 -5,010,108 -5,027,239 -4,983,149 -4,868,778 -4,673,836 -4,386,629 -3,993,879 -3,596,220 -3,193,590 -2,785,927 -2,373,168 -1,955,249 -1,532,107 -1,103,675 -669,888
Schedule C - 30 Year Reserve Fund Cash Flow Projection and Deficiency Analysis
2013 116
Depreciation Report
The Strata Council must make informed decisions regarding the state of the major
components at their building in real time. If it is deemed that a major repair or
replacement is needed immediately, it should, and can, be undertaken from funds
earmarked by the Depreciation Report for a different task. These funds can be returned to
the Contingency Reserve Fund at a later date, or the Depreciation Report can be modified
during the update, which takes place at least once every 3 years, as legislated. A needed
repair or replacement should never be postponed because the Depreciation Report does
not list the expenditure for several more years. These funds can also be used for
unexpected common area repairs or replacements, regardless of whether these expenses
are included within the Depreciation Report.
The proposed reserve fund expenditures in the 30 Year Cash Flow Projection are mere
guides in terms of timing, based on the remaining life span analysis. Reserve fund
expenditures should readily be varied to conform to actual management and maintenance
plans, and therefore, they should not be dogmatically interpreted.
The Strata Council is also not bound by the legislation to fund the Depreciation Report to
the full extent defined by the planner. Minimum funding levels are, however, defined in
the legislation (listed below).
Contributions to contingency reserve fund
6.1 For the purposes of section 93 of the Act, the amount of the annual contribution to the contingency reserve fund for a fiscal year,
other than the fiscal year following the first annual general meeting, must be determined as follows:
(a) if the amount of money in the contingency reserve fund at the end of any fiscal year after the first annual general
meeting is less than 25% of the total amount budgeted for the contribution to the operating fund for the fiscal year that
has just ended, the annual contribution to the contingency reserve fund for the current fiscal year must be at least the
lesser of
(i) 10% of the total amount budgeted for the contribution to the operating fund for the current fiscal year,
and
(ii) the amount required to bring the contingency reserve fund to at least 25% of the total amount budgeted
for the contribution to the operating fund for the current fiscal year;
(b) if the amount of money in the contingency reserve fund at the end of any fiscal year after the first annual general
meeting is equal to or greater than 25% of the total amount budgeted for the contribution to the operating fund for the
fiscal year that has just ended, additional contributions to the contingency reserve fund may be made as part of the
annual budget approval process after consideration of the depreciation report, if any, obtained under section 94 of the
Act.
[en. B.C. Reg. 238/2011, Sch. 1, s. 2.]
It should be noted, however, that the Depreciation Report is now required to be included
with the Form B, as is the Strata Corporations current budget. As such, potential
purchasers will know the extent to which the strata has chosen to fund the Depreciation
Report, which may reflect in the sale of the property. Additionally, failure to fund the
Depreciation Report may open the Strata Council to legal liability.
2013 117
Depreciation Report
Recommendations
Based on present financial conditions and the buildings age, the contingency reserve
fund for BCS 2429 The Point, is moderately deficient against the benchmark analysis.
Any deficiencies should be eliminated over time in order to meet adequacy, and ensure
proper funds are in place for major repairs and replacements.
Maintenance Operations Program recommendations, set out below and detailed in this
report, will assist the corporation in achieving and maintaining an adequate reserve fund.
In our opinion, if adhered to, the current reserve fund balance, recommended annual
contributions, and earned investment income will adequately fund immediate and future
reserve fund expenditures.
2. Major repairs and replacements should continue to be recorded in, and funded
from, a contingency reserve fund account.
3. The contingency reserve fund contribution of $ 60,000 per annum in 2013 should
be increased to $ 68,100 per annum in 2014 and thereafter by the amounts
detailed in the cash flow table, each subsequent year.
6. The reserve fund should be reviewed by the strata council every year to ensure
that the underlying assumptions are still valid and that the estimates remain
current. Changes should be catalogued and provided to the Depreciation Report
Planner prior to the legislated 3-year update.
7. The corporation should update the Depreciation Report every three (3) years in
accordance with the provisions of Section 94 of the British Columbia Strata
Property Act, amended 2009, Regulation 43/2000.
2013 118
Depreciation Report
Owner Survey
Maintenance Schedule
2013 119
Depreciation Report
Conditions:
The geographic location of your building will influence the frequency and type of typical
inspections. Driving rain, wind exposure, pollution, humidity, heat, and many others can
all have an impact on building envelope components. Owners should become familiar
with local conditions, and tailor a maintenance inspection and repair program to their
specific location. Seaside properties are particularly at risk, and should be treated
accordingly.
Maintenance Cleaning:
When coupled with a comprehensive system of checks, inspections, and repairs, regular
cleaning can be the hidden asset that will allow your building to most efficiently retain its
value. Clean components are easier to examine, and the cleaning itself will keep
environmental factors (dirt, pollutants, and trees) from damaging the buildings exterior.
Cleaning will also make the property look better, and may be a condition of some product
warranties.
2013 120
Depreciation Report
This person will also distribute photocopies of the necessary forms found in the following
pages, namely:
2013 121
Depreciation Report
Report By
Date
Report #
Component Notes
Roofing
Flashing
Sealants
Cladding
Paint/Stains/Finishes
Windows
Doors
Common Area
Components
Grounds/Landscaping,
Fences/Gates
To be completed by a qualified maintenance representative. Mechanical, Electrical, and Safety Systems should be
regularly examined by a firm specializing in these services.
2013 122
Depreciation Report
Check for damage or obvious failure while cleaning windows and Semi-
Sealants
decks. Look for cracking, bulging, de-bonding, etc. Annually
Check for organic growth too close to the building (keep at least 18
Landscaping of free space between the building and exterior plants). Clear organic Annually
debris from exterior as it appears.
Upon completion of the above reviews, owners should be sure to report any damage or failures to the Maintenance
Coordinator. Maintenance work should be performed through the strata, and should not be undertaken
independently, as existing warranties may be affected by improper modifications or repairs.
2013 123
Depreciation Report
Owner Survey
Date
Problem Locality
Unit #
2013 124
Depreciation Report
Simply record annual costs for maintenance and repair schedules, and forecast future
requirements over the next several years. A new schedule will be provided when the
Depreciation Report is updated (once every three years), to allow for continued tracking.
Maintenance Operations Program has included a recommended frequency, but the strata
should record the actual performed frequency (planned frequency), as well as the cost, to
help create a budget for future years. Tasks that are not applicable can be flagged with an
N/A, or simply left blank. For maintenance or repairs that we have not included, blank
lines are available at the end of the table.
2013 125
Depreciation Report
Maintenance Schedule
Item Recommended Planned Unit Total Year 1 Year 2 Year 3
Frequency Frequency Cost Cost
Overview Inspections
Professional Condition and Maintenance Inspection Annually
Building Envelope Maintenance Walk-about Between
Professional
Inspections
Balconies/Decks
Balcony and Deck Surface and Drain Cleaning Twice per Year
Balcony and Deck Area Stain Removal Annually
Vegetation/Moss Removal Annually
Railing, walls, membrane, vents, soffit sealing Annually
Exterior Closure
Cladding Cleaning Annually
Vegetation Removal Annually
Window and Exterior Door Maintenance (weather Twice per Year
stripping, adjust rollers on sliding doors, adjust
windows and screen to ensure proper clearances,
locks, hinges, stops)
Exterior Window Washing Twice per Year
2013 126
Depreciation Report
Item Recommended Planned Unit Total Year 1 Year 2 Year 3
Frequency Frequency Cost Cost
Exterior Door Cleaning Monthly
Door and Window Frame Sealing Annually
Coating Maintenance on Fences Annually
Roofing
Gutter and Drain Cleaning Monthly
Skylight and other roof sealing Annually
Skylight Cleaning Annually
Chimney Inspection and Cleaning Annually, in the
spring
2013 127
Depreciation Report
Item Recommended Planned Unit Total Year 1 Year 2 Year 3
Frequency Frequency Cost Cost
Fire Safety System Winterization Annually
Fire Safety System Inspection and Testing Annually
Fire Extinguisher Replacement Annually
Emergency Generators Inspection and Testing Annually
Shut-off Valve Testing and Marking of Locations Annually before
winter
Electrical System Inspection and Testing Annually
Elevator Maintenance Service
Contract
Dryer Vent Inspection Annually
Gas Line Inspection (includes all gas appliances) Annually
Mechanical Room and Meter Maintenance Annually
Grounds
Light Fixture Relamping Monthly
Photocell Timer Programming Annually,
before Winter
Mailbox and Intercom Inspection Annually
Drain Clean-out Annually
Foundation Drainage System Clean-out Annually
Podium Area Drain Clearing Annually
Root Barrier and Membrane Inspection of the Annually
Podium Area (include exposure)
Ground and Soil Re-grading (away from fences and Annually
walls)
Irrigation Sprinkler Adjustment and Maintenance Annually
Walkway Cleaning Annually
Walkway Clearing (remove debris, snow) Monthly
Perimeter Foliage Clearing Annually
Irrigation System Winterization Annually,
before Winter
2013 128
Depreciation Report
Item Recommended Planned Unit Total Year 1 Year 2 Year 3
Frequency Frequency Cost Cost
Pest Report Annually
Catch Basin and Trench Drain Grate Adjustment and Annually before
Location Marking Winter
Garden Hose Removal, Drainage and Storage Annually before
Winter
Outdoor Hose-bib Shut-off Annually before
winter
Snow Removal Equipment Service Annually before
winter
Sealing as required Annually
Landscaping (Pruning, tree trimming, replacement) Annually
Lawn Services Weekly
Fence Maintenance Annually
Gate, Lock and Intercom Maintenance Monthly
Totals $ $ $ $
2013 129
Depreciation Report
Addenda Section
2013 130
Depreciation Report
Funding Models
To follow are 5 alternative funding models presented to the strata council, which were
rejected in favour of the funding model chosen for this Depreciation report. Though these
funding models can be used in the event that the strata council decides upon a different
course of action for their Depreciation Report funding, funding model changes should
coincide with an update to the report itself unless made very shortly after the report is
conducted.
2013