Professional Documents
Culture Documents
4. Metric: Effort variance for the phase with respect to initially planned effort for the phase *
5. Metric: Effort variance for the phase with respect to revised planned effort for the phase agreed upon by Customer/Senior Management *
2) Schedule Metrics
1. Metric: Schedule variance for the project with respect to initially planned schedule for the project *
2. Metric: Schedule variance for the project with respect to revised planned schedule for the project agreed upon by Customer/Senior Management *
3. Metric: Schedule variance for the phase with respect to initially planned schedule for the phase *
4. Metric: Schedule variance for the phase with respect to revised planned schedule for the phase calculated after requirements have been frozen and
3) Project Size agreed upon by Customer/Senior Management. *
Metrics 1. Metric: Size variance for the project with respect to initially planned size for the project
2. Metric: Size variance for the project with respect to revised planned size for the project calculated after requirements have been frozen and agreed
4) Productivity & Cost upon by Customer/Senior Management
Metrics 1. Metric: Productivity
2. Metric: Cost Variance for the project
3. Metric: Cost Variance Phase wise
5) Defects Metrics
1. Metric: Defect Density
2. Metric: Phase-wise Defects Introduced and Detected *
3. Metric: Defect Severity Distribution (High/Medium/ Low) *
4. Metric: Defect Detection Effectiveness *
5. Metric: Defect Age *
6) Software Quality
Assurance Metrics 1. Metric: Internal Audit NC Trend, SQA Product Audit Defect Trend *
2. Metric: Internal Audit NC Trend, SQA Product Audit Defect Trend by Process *
7) Requirement
Management Metrics 1. Metric: Changes to requirements
8) Training Metrics
1. Metric: Planned Average Training Days per Person per Annum
2. Metric: Actual Average Training per Person per Annum
3. Metric: Training Effectiveness (Required for Trainning Dept.)
9) Facilities
Management Metrics 1. Metric: Problem Repair Mean Time
2. Metric: System Downtime (For each Server)
3. Metric: Variance in Response to commitments
10) Maintained
Metrics 1. Metric: Meantime to closure *
Remark :
* Required Metrics
Metric Goal ระบุ % Value (สามารถระบุคา ่ เป้ าหมายเป็ นช่วง เช่น 3-5% หรือจะเป็ นการระบุคา
่
แบบน้อยกว่า เช่น น้อยกว่า 5% หรือจะระบุแบบ Software Design Phase นั้นต้อง
น้อยกว่า 20% หรือระบุแยกในแต่ละ Phase เลยก็ได้)
2. Metric: Effort variance for the project with respect to initially planned effort for the project (overall) *
Metric Goal ระบุ %Variance (สามารถระบุคา ่ เป้ าหมายเป็ นช่วง เช่น 3-5% หรือจะเป็ นการระบุคา
่
แบบน้อยกว่า เช่น น้อยกว่า 5%)
3. Metric: Effort variance for the project with respect to latest revised planned effort for the project agreed upon by Customer/Senior Management *
Metric Goal ระบุ %Variance (สามารถระบุคา ่ เป้ าหมายเป็ นช่วง เช่น 3-5% หรือจะเป็ นการระบุคา
่
แบบน้อยกว่า เช่น น้อยกว่า 5%)
4. Metric: Effort variance for the phase with respect to initially planned effort for the phase *
(Not Mandatory for XS Project)
Metric Goal ระบุ %Variance (สามารถระบุคา ่ เป้ าหมายเป็ นช่วง เช่น 3-5% หรือจะเป็ นการระบุคา
่
แบบน้อยกว่า เช่น น้อยกว่า 5% หรือจะระบุแบบ Software Design Phase นั้นต้อง
น้อยกว่า 20% หรือระบุแยกในแต่ละ Phase เลยก็ได้)
Frequency Phase End
Phase Date of End Phase Actual Effort in Phase (Mandays) Initially Planned effort for Phase Value (%)
(Mandays)
1) Project Planning 0.00
2) Project Monitoring and Control 0.00
3) Requirement Analysis 0.00
4) Software Design 0.00
5) Development and Integration 0.00
6) Unit Testing 0.00
7) Module/Integration Testing 0.00
8) System Testing 0.00
9) Acceptance Testing 0.00
10) Installation, Delivery and Implementation 0.00
11) Post Production Support and Maintenance 0.00
12) Project Closure 0.00
5. Metric: Effort variance for the phase with respect to revised planned effort for the phase agreed upon by Customer/Senior Management *
Metric Goal ระบุ %Variance (สามารถระบุคา ่ เป้ าหมายเป็ นช่วง เช่น 3-5% หรือจะเป็ นการระบุคา
่
แบบน้อยกว่า เช่น น้อยกว่า 5% หรือจะระบุแบบ Software Design Phase นั้นต้อง
น้อยกว่า 20% หรือระบุแยกในแต่ละ Phase เลยก็ได้)
Remark :
* Required Metrics
1. Metric: Schedule variance for the project with respect to initially planned schedule for the project *
2. Metric: Schedule variance for the project with respect to revised planned schedule for the project agreed upon by Customer/Senior Management *
3. Metric: Schedule variance for the phase with respect to initially planned schedule for the phase *
(Not mandatory for XS Project)
Metric Goal ระบุ %Variance (สามารถระบุคา ่ เป้ าหมายเป็ นช่วง เช่น 3-5% หรือจะเป็ นการระบุคา
่ แบบน้อย
กว่า เช่น น้อยกว่า 5% หรือจะระบุแบบ Software Design Phase นั้นต้องน้อยกว่า 20% หรือ
ระบุแยกในแต่ละ Phase เลยก็ได้)
Frequency Phase End
Phase Date of End Phase Actual No. of days on Phase Planned No. of days on Phase Value (%)
1) Project Planning 26/1/209 4 4 0.00
2) Project Monitoring and Control 0.00
3) Requirement Analysis 27/2/2009 5 5 0.00
4) Software Design 27/3/2009 19 23 -17.39
5) Development and Integration 3/7/2009 62 78 -20.51
6) Unit Testing 10/7/2009 10 15 -33.33
7) Module/Integration Testing - 0.00
8) System Testing 24/7/2009 10 15 -33.33
9) Acceptance Testing 21/8/2009 20 55 -63.64
10) Installation, Delivery and 01/09/2009 76 60 26.67
Implementation
11) Post Production Support and - 0.00
Maintenance
12) Project Closure 0.00
4. Metric: Schedule variance for the phase with respect to revised planned schedule for the phase calculated after requirements have been frozen and agreed upon by
Customer/Senior Management. *
Metric Goal ระบุ %Variance (สามารถระบุคา ่ เป้ าหมายเป็ นช่วง เช่น 3-5% หรือจะเป็ นการระบุคา
่ แบบน้อย
กว่า เช่น น้อยกว่า 5% หรือจะระบุแบบ Software Design Phase นั้นต้องน้อยกว่า 20% หรือ
ระบุแยกในแต่ละ Phase เลยก็ได้)
Remark :
* Required Metrics
1. Metric: Size variance for the project with respect to initially planned size for the project
Frequency Project Closure
Date Actual size of project Initially planned size of project Value (%)
0.00
2. Metric: Size variance for the project with respect to revised planned size for the project calculated after requirements have
been frozen and agreed upon by Customer/Senior Management
Frequency Project Closure
Date Actual size of project Revised planned size of project Value (%)
0.00
1. Metric: Productivity
Frequency Project Closure
Date Actual Size Actual Effort Value
0.00
Source of data : Size from Estimation sheets, Review Reports/Test Results, Defect Tracking Report
Metric Goal ระบุ Ratio Value (สามารถระบุค่าเป้ าหมายเป็ นช่วง เช่น 3-5 หรือจะเป็ นการระบุค่า
แบบน้อยกว่า เช่น น้อยกว่า 5)
Metric Goal ระบุ % Value (สามารถระบุค่าเป้ าหมายเป็ นช่วง เช่น 3-5% หรือจะเป็ นการระบุค่า
แบบน้อยกว่า เช่น น้อยกว่า 5% หรือ มากกว่า 90%)
4.39
Remark :
* Required Metrics
Frequency Bi-Monthly/Quarterly
Process Audit (No. of NC) Product Audit (No. of Defect)
Date Grand Total %
Major NCs Minor NCs Observation Total Fatal Serious Minor Total
Feb'2009 1 3 1 5 0 0 0 0 5 17.86
Mar'2009 2 3 7 12 0 0 0 0 12 42.86
Apr'2009 0 0 0 0 0 0 0 0 0 0.00
May'2009 0 5 6 11 0 0 0 0 11 39.29
Jun'2009 0 0 0 0 0 0 0 0 0 0.00
Jul'2009 0 0 0 0 0 0 0 0 0 0.00
Aug'2009 0 0 0 0 0 0 0 0 0 0.00
Sep'2009 0 0 0 0 0 0 0 0 0 0.00
Oct'2009 0 0 0 0 0 0 0 0 0 0.00
Nov'2009 0 0 0 0 0 0 0 0 0 0.00
Dec'2009 0 0 0 0 0 0 0 0 0 0.00
Jan'2010 0 0 0 0 0 0 0 0 0 0.00
Feb'2010 0 0 0 0 0 0 0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
Total 3 11 14 28 0 0 0 0 28 100.00
Percentage per severity 10.71 39.29 50.00 100.00 0.00 0.00 0.00 0.00
2. Metric: Internal Audit NC Trend, SQA Product Audit Defect Trend by Process *
Frequency Bi-Monthly/Quarterly
Process Audit (No. of NC) Product Audit (No. of Defect)
Process Grand Total %
Major NCs Minor NCs Observation Total Fatal Serious Minor Total
CEM 1 1 0 1 3.57
CFG 2 2 0 2 7.14
DAR 0 0 0 0.00
EST 1 1 0 1 3.57
FMP 0 0 0 0.00
MET 1 2 3 0 3 10.71
ODI 0 0 0 0.00
PMP 1 3 6 10 0 10 35.71
PQA 2 2 0 2 7.14
PRM 0 0 0 0.00
QCP 3 2 5 0 5 17.86
QMM 0 0 0 0.00
RSK 0 0 0 0.00
SLC 3 3 0 3 10.71
TGL 1 1 0 1 3.57
TRN 0 0 0 0.00
Total 3 11 14 28 0 0 0 0 28 100.00
Remark :
* Required Metrics
Total 0 0 0 0
Remark :
* Required Metrics
Remark :
* Required Metrics