You are on page 1of 44

JUNE-JULY

2017

Summer Training Report

SUBMITTED BY:
JORJI SAM
4th YEAR
B.TECH MAE
ROLL NO-02125603614
DTC, GGSIPU
INDEX

ABOUT NTPC

ABOUT BTPS

BASIC STEPS OF ELECTRICITY GENERATION

RANKINE CYCLE

PLANT AUXILIARY MAINTENANCE

TURBINE MAINTENANCE DEPARTMENT


ABOUT NTPC

NTPC Limited is the largest thermal power generating company of India, Public Sector
Company. It was incorporated in the year 1975 to accelerate power development in the
country as a wholly owned company of the Government of India. At present, Government of
India holds 89.5% of the total equity shares of the company and the balance 10.5% is held by
FIIs, Domestic Banks, Public and others. Within a span of 31 years, NTPC has emerged as a
truly national power company, with power generating facilities in all the major regions of the
country.

NTPC's core business is engineering, construction and operation of power generating plants
and providing consultancy to power utilities in India and abroad.

The total installed capacity of the company is 31134 MW (including JVs) with 15 coal based
and 7 gas based stations, located across the country. In addition under JVs, 3 stations are coal
based & another station uses naphtha/LNG as fuel. By 2017, the power generation portfolio is
expected to have a diversified fuel mix with coal based capacity of around 53000 MW, 10000
MW through gas, 9000 MW through Hydro generation, about 2000 MW from nuclear
sources and around 1000 MW from Renewable Energy Sources (RES). NTPC has adopted a
multi-pronged growth strategy which includes capacity addition through green field projects,
expansion of existing stations, joint ventures, subsidiaries and takeover of stations.
NTPC has been operating its plants at high efficiency levels. Although the company has
18.79% of the total national capacity it contributes 28.60% of total power generation due to
its focus on high efficiency. NTPCs share at 31 Mar 2001 of the total installed capacity of
the country was 24.51% and it generated 29.68% of the power of the country in 2008-09.
Every fourth home in India is lit by NTPC. 170.88BU of electricity was produced by its
stations in the financial year 2005-2006. The Net Profit after Tax on March 31, 2006 was
INR 58,202 million. Net Profit after Tax for the quarter ended June 30, 2006 was INR 15528
million, which is 18.65% more than for the same quarter in the previous financial year.
2005).

NTPC has set new benchmarks for the power industry both in the area of power plant
construction and operations. Its providing power at the cheapest average tariff in the country.
NTPC is committed to the environment, generating power at minimal environmental cost and
preserving the ecology in the vicinity of the plants. NTPC has undertaken massive a
forestation in the vicinity of its plants. Plantations have increased forest area and reduced
barren land. The massive a forestation by NTPC in and around its Ramagundam Power
station (2600 MW) have contributed reducing the temperature in the areas by about 3c.
NTPC has also taken proactive steps for ash utilization. In 1991, it set up Ash Utilization
Division
A graphical overview

Technological Initiatives
Introduction of steam generators (boilers) of the size of 800 MW.
Integrated Gasification Combined Cycle (IGCC) Technology.
Launch of Energy Technology Centre -A new initiative for development of
technologies with focus on fundamental R&D.
The company sets aside up to 0.5% of the profits for R&D.
Roadmap developed for adopting Clean Development.
Mechanism to help get / earn Certified Emission Reduction.

Corporate Social Responsibility


As a responsible corporate citizen NTPC has taken up number of CSR initiatives.
NTPC Foundation formed to address Social issues at national level
NTPC has framed Corporate Social Responsibility Guidelines committing up to
0.5% of net profit annually for Community Welfare.
The welfare of project affected persons and the local population around NTPC
projects are taken care of through well drawn Rehabilitation and Resettlement
policies.
The company has also taken up distributed generation for remote rural areas.

Partnering government in various initiatives


Consultant role to modernize and improvise several plants across the country.
Disseminate technologies to other players in the sector.
Consultant role Partnership in Excellence Programme for improvement of PLF of
15 Power Stations of SEBs.
Rural Electrification work under Rajiv Gandhi Garmin Vidyutikaran.

Environment Management
All stations of NTPC are ISO 14001 certified.
Various groups to care of environmental issues.
The Environment Management Group.
Ash Utilization Division.
Afforestation Group.
Centre for Power Efficiency & Environment Protection.
Group on Clean Development Mechanism.
NTPC is the second largest owner of trees in the country after the Forest department.

JOURNEY OF NTPC

NTPC was set up in 1975 with 100% ownership by the Government


1975 of India. In the last 30 years, NTPC has grown into the largest power
utility in India.

In 1997, Government of India granted NTPC status of Navratna


1997 being one of the nine jewels of India, enhancing the powers to the
Board of Directors.

NTPC became a listed company with majority Government

2004 ownership of 89.5%.

NTPC becomes third largest by Market Capitalization of listed


companies
The company rechristened as NTPC Limited in line with its

2005 changing business portfolio and transforms itself from a thermal


power utility to an integrated power utility.

National Thermal Power Corporation is the largest power


2008 generation company in India. Forbes Global 2000 for 2008 ranked it
411th in the world.

National Thermal Power Corporation is the largest power


2009 generation company in India. Forbes Global 2000 for 2008 ranked it
317th in the world.

NTPC has also set up a plan to achieve a target of 50,000 MW


2012 generation capacity.

NTPC has embarked on plans to become a 75,000 MW company by


2017 2017.

ABOUT BTPS

Badarpur thermal power station started working in 1973 with a single 95 mw unit. There
were 2 more units (95 MW each) installed in next 2 consecutive years. Now it has total five
units with total capacity of 720 MW. Ownership of BTPS was transferred to NTPC with
effect from 01.06.2006 through GOIs Gazette Notification .Given below are the details of
unit with the year they are installed.

Address: Badarpur, New Delhi 110 044


Telephone: (STD-011) - 26949523
Fax: 26949532
Installed Capacity 720 MW
Derated Capacity 705 MW
Location New Delhi
Coal Source Jharia Coal Fields
Water Source Agra Canal
Beneficiary States Delhi
Unit Sizes 3X95 MW
2X210 MW
Units Commissioned Unit I- 95 MW - July 1973
Unit II- 95 MW August 1974
Unit III- 95 MW March 1975
Unit IV - 210 MW December 1978
Unit V - 210 MW - December 1981
Transfer of BTPS to NTPC Ownership of BTPS was transferred to NTPC with
effect from 01.06.2006 through GOIs Gazette
Notification

BASIC STEPS OF ELECTRICITY GENERATION


The basic steps in the generation of electricity from coal involves following steps:
Coal to steam
Steam to mechanical power
Mechanical power to electrical power

COAL TO ELECTRICITY: BASICS


The basic steps in the generation of coal to electricity are shown below:
Coal to Steam
Coal from the coal wagons is unloaded in the coal handling plant. This Coal is transported up
to the raw coal bunkers with the help of belt conveyors. Coal is transported to Bowl mills by
Coal Feeders. The coal is pulverized in the Bowl Mill, where it is ground to powder form.
The mill consists of a round metallic table on which coal particles fall. This table is rotated
with the help of a motor. There are three large steel rollers, which are spaced 120 apart.
When there is no coal, these rollers do not rotate but when the coal is fed to the table it packs
up between roller and the table and ths forces the rollers to rotate. Coal is crushed by the
crushing action between the rollers and the rotating table. This crushed coal is taken away to
the furnace through coal pipes with the help of hot and cold air mixture from P.A. Fan.

P.A. Fan takes atmospheric air, a part of which is sent to Air-Preheaters for heating while a
part goes directly to the mill for temperature control. Atmospheric air from F.D. Fan is heated
in the air heaters and sent to the furnace as combustion air.
Water from the boiler feed pump passes through economizer and reaches the boiler drum.
Water from the drum passes through down comers and goes to the bottom ring header. Water
from the bottom ring header is divided to all the four sides of the furnace.Due to heat and
density difference, the water rises up in the water wall tubes. Water is partly converted
tosteam as it rises up in the furnace. This steam and water mixture is again taken to thee
boiler dr

Water follows the same path while the steam is sent to superheaters for superheating. The
superheaters are located inside the furnace and the steam is superheated (540C) and finally it
goes to the turbine.
Flue gases from the furnace are extracted by induced draft fan, which maintains balance draft
in the furnace (-5 to 10 mm of wcl) with forced draft fan. These flue gases emit their heat

energy to various super heaters in the pent house and finally pass through air-preheaters and
goes to electrostatic precipitators where the ash particles are extracted. Electrostatic
Precipitator consists of metal plates, which are electrically charged. Ash particles are
attracted on to these plates, so that they do not pass through the chimney to pollute the
atmosphere. Regular mechanical hammer blows cause the accumulation of ash to fall to the
bottom of the precipitator where they are collected in a hopper for disposal.

Steam to Mechanical Power


From the boiler, a steam pipe conveys steam to the turbine through a stop valve (which can
be used to shut-off the steam in case of emergency) and through control valves that
automatically regulate the supply of steam to the turbine. Stop valve and control valves are
located in a steam chest and a governor, driven from the main turbine shaft, operates the
control valves to regulate the amount of steam used. (This depends upon the speed of the
turbine and the amount of electricity required from the generator).
Steam from the control valves enters the high pressure cylinder of the turbine, where it passes
through a ring of stationary blades fixed to the cylinder wall. These act as nozzles and direct
the steam into a second ring of moving blades mounted on a disc secured to the turbine shaft.
The second ring turns the shafts as a result of the force of steam. The stationary and moving
blades together constitute a stage of turbine and in practice many stages are necessary, so
that the cylinder contains a number of rings of stationary blades with rings of moving blades
arranged between them. The steam passes through each stage in turn until it reaches the end
of the high-pressure cylinder and in its passage some of its heat energy is changed into
mechanical energy.
The steam leaving the high pressure cylinder goes back to the boiler for reheating and returns
by a further pipe to the intermediate pressure cylinder. Here it passes through another series
of stationary and moving blades.
Finally, the steam is taken to the low-pressure cylinders, each of which enters at the centre
flowing outwards in opposite directions through the rows of turbine blades through an
arrangement called the double flow- to the extremities of the cylinder. As the steam gives
up its heat energy to drive the turbine, its temperature and pressure fall and it expands.
Because of this expansion the blades are much larger and longer towards the low pressure
ends of the turbine.

Mechanical Power to Electrical Power


As the blades of turbine rotate, the shaft of the generator, which is coupled to tha of the
turbine, also rotates. It results in rotation of the coil of the generator, which causes induced
electricity to be produced.

BASIC POWER PLANT CYCLE

A simplified diagram of a thermal power plant


The thermal (steam) power plant uses a dual (vapour+liquid) phase cycle. It is a close cycle
to enable the working fluid (water) to be used again and again. The cycle used is Rankine
Cycle modified to include superheating of steam, regenerative feed water heating and
reheating of steam.
On large turbines, it becomes economical to increase the cycle efficiency by using reheat,
which is a way of partially overcoming temperature limitations. By returning partially
expanded steam, to a reheat, the average temperature at which the heat is added, is increased
and, by expanding this reheated steam to the remaining stages of the turbine, the exhaust
wetness is considerably less than it would otherwise be conversely, if the maximum tolerable
wetness is allowed, the initial pressure of the steam can be appreciably increased.
Bleed Steam Extraction: For regenerative system, nos. of non-regulated extractions is taken
from HP, IP turbine.
Regenerative heating of the boiler feed water is widely used in modern power plants; the
effect being to increase the average temperature at which heat is added to the cycle, thus
improving the cycle efficiency.

FACTORS AFFECTING THERMAL CYCLE EFFICIENCY


Thermal cycle efficiency is affected by following:
Initial Steam Pressure.
Initial Steam Temperature.
Whether reheat is used or not, and if used reheat pressure and temperature.
Condenser pressure.
Regenerative feed water heating.

RANKINE CYCLE

The Rankine cycle is a thermodynamic cycle which converts heat into work. The heat is
supplied externally to a closed loop, which usually uses water as the working fluid. This
cycle generates about 80% of all electric power used throughout the world, including
virtually all solar thermal, biomass, coal and nuclear power plants. It is named after William
John MacquornRankine, a Scottish polymath..

Description
Physical layout of the four main devices used in the Rankine cycle
A Rankine cycle describes a model of the operation of steam heat engines most commonly
found in power generation plants. Common heat sources for power plants using the Rankine
cycle are coal, natural gas, oil, and nuclear.
The Rankine cycle is sometimes referred to as a practical Carnot cycle as, when an efficient
turbine is used, the TS diagram will begin to resemble the Carnot cycle. The main difference
is that a pump is used to pressurize liquid instead of gas. This requires about 1/100th (1%) as
much energy as that compressing a gas in a compressor (as in the Carnot cycle).
The efficiency of a Rankine cycle is usually limited by the working fluid. Without the
pressure going super critical the temperature range the cycle can operate over is quite small,
turbine entry temperatures are typically 565C (the creep limit of stainless steel) and
condenser temperatures are around 30C. This gives a theoretical Carnot efficiency of around
63% compared with an actual efficiency of 42% for a modern coal-fired power station. This
low turbine entry temperature (compared with a gas turbine) is why the Rankine cycle is
often used as a bottoming cycle in combined cycle gas turbine power stations.
The working fluid in a Rankine cycle follows a closed loop and is re-used constantly. The
water vapor and entrained droplets often seen billowing from power stations is generated by
the cooling systems (not from the closed loop Rankine power cycle) and represents the waste
heat that could not be converted to useful work.
Note that cooling towers operate using the latent heat of vaporization of the cooling fluid.
The white billowing clouds that form in cooling tower operation are the result of water
droplets which are entrained in the cooling tower airflow; it is not, as commonly thought,
steam. While many substances could be used in the Rankine cycle, water is usually the fluid
of choice due to its favorable properties, such as nontoxic and unreactive chemistry,
abundance, and low cost, as well as its thermodynamic properties.
One of the principal advantages it holds over other cycles is that during the compression
stage relatively little work is required to drive the pump, due to the working fluid being in its
liquid phase at this point. By condensing the fluid to liquid, the work required by the pump
will only consume approximately 1% to 3% of the turbine power and so give a much higher
efficiency for a real cycle.
The benefit of this is lost somewhat due to the lower heat addition temperature. Gas turbines,
for instance, have turbine entry temperatures approaching 1500C. Nonetheless, the
efficiencies of steam cycles and gas turbines are fairly well matched.

Processes of the Rankine cycle

Ts diagram of a typical Rankine cycle operating between pressures of 0.06bar and 50bar.
There are four processes in the Rankine cycle, each changing the state of the working fluid.
These states are identified by number in the diagram to the right
i. Process 1-2: The working fluid is pumped from low to high pressure, as the fluid is a
liquid at this stage the pump requires little input energy.
ii. Process 2-3: The high pressure liquid enters a boiler where it is heated at constant
pressure by an external heat source to become a dry saturated vapour.
iii. Process 3-4: The dry saturated vapor expands through a turbine, generating power.
This decreases the temperature and pressure of the vapor, and some condensation may
occur.
iv. Process 4-1: The wet vapor then enters a condenser where it is condensed at a
constant pressure and temperature to become a saturated liquid. The pressure and
temperature of the condenser is fixed by the temperature of the cooling coils as the
fluid is undergoing a phase-change.
In an ideal Rankine cycle the pump and turbine would be isentropic, i.e., the pump and
turbine would generate no entropy and hence maximize the net work output. Processes 1-2
and 3-4 would be represented by vertical lines on the Ts diagram and more closely resemble
that of the Carnot cycle.
The Rankine cycle shown here prevents the vapor ending up in the superheat region after the
expansion in the turbine, which reduces the energy removed by the condensers.

Real Rankine cycle (non-ideal) :Rankine cycle with superheat

In a real Rankine cycle, the compression by the pumpand the expansion in the turbine are not
isentropic. In other words, these processes are non-reversible and entropy is increased during
the two processes. This somewhat increases the powerrequired by the pump and decreases the
power generated by the turbine.
In particular the efficiency of the steam turbine will be limited by water droplet formation. As
the water condenses, water droplets hit the turbine blades at high speed causing pitting and
erosion, gradually decreasing the life of turbine blades and efficiency of the turbine. The
easiest way to overcome this problem is by superheating the steam. On the Ts diagram above,
state 3 is above a two phase region of steam and water so after expansion the steam will be
very wet. By superheating, state 3 will move to the right of the diagram and hence produce a
dryer steam after expansion.

Rankine cycle with reheat


In this variation, two turbineswork in series. The first accepts vaporfrom the boilerat high
pressure. After the vapor has passed through the first turbine, it re-enters the boiler and is
reheated before passing through a second, lower pressure turbine. Among other advantages,
this prevents the vapor from condensing during its expansion which can seriously damage the
turbine blades, and improves the efficiency of the cycle.

Regenerative Rankine cycle


The regenerative Rankine cycle is so named because after emerging from the condenser
(possibly as a subcooled liquid) the working fluid is heated by steam tapped from the hot
portion of the cycle. On the diagram shown, the fluid at 2 is mixed with the fluid at 4 (both at
the same pressure) to end up with the saturated liquid at 7. The Regenerative Rankine cycle
(with minor variants) is commonly used in real power stations.
Another variation is where 'bleed steam' from between turbine stages is sent to feedwater
heaters to preheat the water on its way from the condenser to the boiler.

I. PLANT AUXILIARY MAINTENANCE

1. WATER CIRCULATION SYSTEM

Theory of Circulation

Water must flow through the heat absorption surface of the boiler in order that it be
evaporated into steam. In drum type units (natural and controlled circulation), the water is
circulated from the drum through the generating circuits and then back to the drum where the
steam is separated and directed to the super heater. The water leaves the drum through the
down corners at a temperature slightly below the saturation temperature. The flow through
the furnace wall is at saturation temperature. Heat absorbed in water wall is latent heat of
vaporization creating a mixture of steam and water. The ratio of the weight of the water to the
weight of the steam in the mixture leaving the heat absorption surface is called circulation
ratio.

Types of Boiler Circulating System

i. Natural circulation system


ii. Controlled circulation system
iii. Combined circulation system

i. Natural Circulation System

Water delivered to steam generator from feed water is at a temperature well below the
saturation value corresponding to that pressure. Entering first the economizer, it is heated to
about 30-40C below saturation temperature. From economizer the water enters the drum and
thus joins the circulation system. Water entering the drum flows through the down corner and
enters ring heater at the bottom. In the water walls, a part of the water is converted to steam
and the mixture flows back to the drum. In the drum, the steam is separated, and sent to
superheater for superheating and then sent to the high-pressure turbine. Remaining water
mixes with the incoming water from the economizer and the cycle is repeated.

As the pressure increases, the difference in density between water and steam reduces. Thus
the hydrostatic head available will not be able to overcome the frictional resistance for a flow
corresponding to the minimum requirement of cooling of water wall tubes. Therefore natural
circulation is limited to the boiler with drum operating pressure around 175 kg/ cm2.

ii. Controlled Circulation System

Beyond 80 kg/ cm2 of pressure, circulation is to be assisted with mechanical pumps to


overcome the frictional losses. To regulate the flow through various tubes, orifices plates are
used. This system is applicable in the high sub-critical regions (200 kg/ cm2).

2. ASH HANDLING PLANT

The widely used ash handling systems are:


i. Mechanical Handling System
ii. Hydraulic System
iii. Pneumatic System
iv. Steam Jet System

Ash Handling System at Badarpur Thermal Power Station, New Delhi

The Hydraulic Ash handling system is used at the Badarpur Thermal Power Station.

Hydraulic Ash Handling System

The hydraulic system carried the ash with the flow of water with high velocity through a
channel and finally dumps into a sump. The hydraulic system is divided into a low velocity
and high velocity system. In the low velocity system the ash from the boilers falls into a
stream of water flowing into the sump. The ash is carried along with the water and they are
separated at the sump. In the high velocity system a jet of water is sprayed to quench the hot
ash. Two other jets force the ash into a trough in which they are washed away by the water
into the sump, where they are separated. The molten slag formed in the pulverized fuel
system can also be quenched and washed by using the high velocity system. The advantages
of this system are that its clean, large ash handling capacity, considerable distance can be
traversed, absence of working parts in contact with ash.

Fly Ash Collection


Fly ash is captured and removed from the flue gas by electrostatic precipitators or fabric bag
filters (or sometimes both) located at the outlet of the furnace and before the induced draft
fan. The fly ash is periodically removed from the collection hoppers below the precipitators
or bag filters. Generally, the fly ash is pneumatically transported to storage silos for
subsequent transport by trucks or railroad cars.

Bottom Ash Collection and Disposal

At the bottom of every boiler, a hopper has been provided for collection of the bottom ash
from the bottom of the furnace. This hopper is always filled with water to quench the ash and
clinkers falling down from the furnace. Some arrangement is included to crush the clinkers
and for conveying the crushed clinkers and bottom ash to a storage site.

3. WATER TREATMENT PLANT

As the types of boiler are not alike their working pressure and operating conditions vary and
so do the types and methods of water treatment. Water treatment plants used in thermal
power plants used in thermal power plants are designed to process the raw water to water
with a very low content of dissolved solids known as demineralized water. No doubt, this
plant has to be engineered very carefully keeping in view the type of raw water to the thermal
plant, its treatment costs and overall economics.

A water treatment plant


The type of demineralization process chosen for a power station depends on three main
factors:

i. The quality of the raw water.


ii. The degree of de-ionization i.e. treated water quality.
iii. Selectivity of resins.

Water treatment process is generally made up of two sections:

Pretreatment section.
Demineralization section

Pretreatment Section

Pretreatment plant removes the suspended solids such as clay, silt, organic and inorganic
matter, plants and other microscopic organism. The turbidity may be taken as two types of
suspended solid in water; firstly, the separable solids and secondly the non-separable solids
(colloids). The coarse components, such as sand, silt, etc: can be removed from the water by
simple sedimentation. Finer particles, however, will not settle in any reasonable time and
must be flocculated to produce the large particles, which are settle able. Long term ability to
remain suspended in water is basically a function of both size and specific gravity.

Demineralization

This filter water is now used for demineralizing purpose and is fed to cation exchanger bed,
but enroute being first dechlorinated, which is either done by passing through activated
carbon filter or injecting along the flow of water, an equivalent amount of sodium sulphite
through some stroke pumps. The residual chlorine, which is maintained in clarification plant
to remove organic matter from raw water, is now detrimental to action resin and must be
eliminated before its entry to this bed.
A demineralization tank

A DM plant generally consists of cation, anion and mixed bed exchangers. The final water
from this process consists essentially of hydrogen ions and hydroxide ions which is the
chemical composition of pure water. The DM water, being very pure, becomes highly
corrosive once it absorbs oxygen from the atmosphere because of its very high affinity for
oxygen absorption. The capacity of the DM plant is dictated by the type and quantity of salts
in the raw water input. However, some storage is essential as the DM plant may be down for
maintenance. For this purpose, a storage tank is installed from which DM water is
continuously withdrawn for boiler make-up. The storage tank for DM water is made from
materials not affected by corrosive water, such as PVC. The piping and valves are generally
of stainless steel. Sometimes, a steam blanketing arrangement or stainless steel doughnut
float is provided on top of the water in the tank to avoid contact with atmospheric air. DM
water make-up is generally added at the steam space of the surface condenser (i.e., the
vacuum side). This arrangement not only sprays the water but also DM water gets deaerated,
with the dissolved gases being removed by the ejector of the condenser itself.

4. DRAUGHT SYSTEM

There are four types of draught system:


i. Natural Draught
ii. Induced Draught
iii. Forced Draught
iv. Balanced Draught

Natural Draught System

In natural draft units the pressure differentials are obtained have constructing tail chimneys so
that vacuum is created in the furnace. Due to small pressure difference, air is admitted into
the furnace.

A natural draught system

Induced Draft System

In this system, the air is admitted to natural pressure difference and the flue gases are taken
out by means of Induced Draught (I.D.) fans and the furnace is maintained under vacuum.
An induced draught system

Forced Draught System

A set of forced draught (F.D.) fans is made use of for supplying air to the furnace and so the
furnace is pressurized. The flue gases are taken out due to the pressure difference between the
furnace and the atmosphere.

A forced draught system

Balanced Draught System

Here a set of Induced and Forced Draft Fans are utilized in maintaining a vacuum in the
furnace. Normally all the power stations utilize this draft system.

5. INDUSTRIAL FANS

ID Fan

The induced Draft Fans are generally of Axial-Impulse Type. Impeller nominal diameter is of
the order of 2500 mm.The fan consists of the following sub-assemblies:

Suction Chamber
Inlet Vane Control
Impeller
Outlet Guide Vane Assembly

An ID fan

FD Fan

The fan, normally of the same type as ID Fan, consists of the following components:

Silencer
Inlet Bend
Fan Housing
Impeller with blades and setting mechanism

An FD fan

The centrifugal and setting forces of the blades are taken up by the blade bearings. The blade
shafts are placed in combined radial and axial anti-friction bearings, which are sealed off to
the outside. The angle of incidence of the blades may be adjusted during operation. The
characteristic pressure volume curves of the fan may be changed in a large range without
essentially modifying the efficiency. The fan can then be easily adapted to changing
operating conditions.

The rotor is accommodated in cylindrical roller bearings and an inclined ball bearing at the
drive side absorbs the axial thrust.
Lubrication and cooling these bearings is assured by a combined oil level and circulating
lubrication system.

Primary Air Fan

PA Fan if flange-mounted design, single stage suction, NDFV type, backward curved bladed
radial fan operating on the principle of energy transformation due to centrifugal forces. Some
amount of the velocity energy is converted to pressure energy in the spiral casing. The fan is
driven at a constant speed and varying the angle of the inlet vane control controls the flow.
The special feature of the fan is that is provided with inlet guide vane control with a positive
and precise link mechanism.

It is robust in construction for higher peripheral speed so as to have unit sizes. Fan can
develop high pressures at low and medium volumes and can handle hot-air laden with dust
particles.

Primary air fan

6. COMPRESSOR HOUSE

Instrument air is required for operating various dampers, burner tilting, devices, diaphragm
valves, etc: in the 210 MW units. Station air meets the general requirement of the power
station such as light oil atomizing air, for cleaning filters and for various maintenance works.
The control air compressors and station air compressors have been housed separately with
separate receivers and supply headers and their tapping.
A compressor house

Instrument Air System

Control air compressors have been installed for supplying moisture free dry air required for
instrument used. The output from the compressors is fed to air receivers via return valves.
From the receiver air passed through the dryers to the main instrument airline, which runs
along with the boiler house and turbine house of 210 MW units. Adequate numbers of
tapping have been provided all over the area.

Air-Drying Unit

Air contains moisture which tends to condense, and causes trouble in operation of various
devices by compressed air. Therefore drying of air is accepted widely in case of instrument
air. Air drying unit consists of dual absorption towers with embedded heaters for reactivation.
The absorption towers are adequately filled with specially selected silica gel and activated
alumina while one tower is drying the air.
An air drying unit

Service Air Compressor

The station air compressor is generally a slow speed horizontal double acting double stage
type and is arranged for belt drive. The cylinder heads and barrel are enclosed in a
jacket,whih extends around the valve also. The intercooler is provided between the low and
high pressure cylinder which cools the air between tag and collects the moisture that
condenses.

A service air compressor

Air from L.P. cylinder enters at one end of the intercooler and goes to the opposite end
wherefrom it is discharged to the high-pressure cylinder; cooling water flows through the nest
of the tubes and cools the air. A safety valve is set at rated pressure.

Two selector switches one with positions auto load/unload and another with positions auto
start/stop, non-stop have been provided on the control panel of the compressor. In auto start-
stop position, the compressor will start.

II. TURBINE MAINTENANCE DEPARTMENT

TURBINE CLASSIFICATION:

1. Impulse turbine:
In impulse turbine steam expands in fixed nozzles. The high velocity steam from
nozzles does work on moving blades, which causes the shaft to rotate. The essential
features of impulse turbine are that all pressure drops occur at nozzles and not on
blades.
2. Reaction turbine:
In this type of turbine pressure is reduced at both fixed and moving blades. Both
fixed and moving blades act like nozzles. Work done by the impulse effect of steam
due to reverse the direction of high velocity steam.The expansion of steam takes place
on moving blades.

A 95 MW Generator at BTPS, New Delhi

COMPOUNDING:
Several problems occur if energy of steam is converted in single step and so compounding is
done. Following are the type of compounded turbine:
i. Velocity Compounded Turbine:
Like simple turbine it has only one set of nozzles and entire steam pressure drop
takes place there. The kinetic energy of steam fully on the nozzles is utilized in
moving blades. The role of fixed blades is to change the direction of steam jet and
too guide it.
ii. Pressure Compounded Turbine:
This is basically a number of single impulse turbines in series or on the same
shaft.The exhaust of first turbine enters the nozzles of next turbine. The total
pressure drop of steam does not tae on first nozzle ring but divided equally on all
of them.
iii. Pressure Velocity Compounded Turbine:
It is just the combination of the two compounding and has the advantages of
allowing bigger pressure drops in each stage and so fewer stages are necessary.
Here for given pressure drop the turbine will be shorter length but diameter will be
increased.

MAIN TURBINE:
The 210MW turbine is a cylinder tandem compounded type machine comprising of H.P. and
I.P and L.P cylinders. The H.P. turbine comprises of 12 stages the I.P turbine has 11 stages
and the L.P has four stages of double flow. The H.P and I.P. turbine rotor are rigidly
compounded and the I.P. and L.P rotor by lens type semi flexible coupling. All the 3 rotors
are aligned on five bearings of which the bearing number is combined with thrust bearing.
The main superheated steam branches off into two streams from the boiler and passes through
the emergency stop valve and control valve before entering the governing wheel chamber of
the H.P. Turbine. After expanding in the 12 stages in the H.P. turbine then steam is returned
in the boiler for reheating.
The reheated steam from boiler enters I.P. turbine via the interceptor valves and control
valves and after expanding enters the L.P stage via 2 numbers of cross over pipes.
In the L.P. stage the steam expands in axially opposed direction to counteract the thrust and
enters the condenser placed directly below the L.P. turbine. The cooling water flowing
through the condenser tubes condenses the steam and the condensate the collected in the hot
well of the condenser.
The condensate collected the pumped by means of 3x50% duty condensate pumps through
L.P heaters to deaerator from where the boiler feed pump delivers the water to the boiler
through H.P. heaters thus forming a closed cycle.

STEAM TURBINE
A steam turbine is a mechanical device that extracts thermal energy from pressurized steam
and converts it into useful mechanical work.
From a mechanical point of view, the turbine is ideal, because the propelling force is applied
directly to the rotating element of the machine and has not as in the reciprocating engine to be
transmitted through a system of connecting links, which are necessary to transform a
reciprocating motion into rotary motion. Hence since the steam turbine possesses for its
moving parts rotating elements only if the manufacture is good and the machine is correctly
designed, it ought to be free from out of balance forces.
If the load on a turbine is kept constant the torque developed at the coupling is also constant.
A generator at a steady load offers a constant torque. Therefore, a turbine is suitable for
driving a generator, particularly as they are both high-speed machines.
A further advantage of the turbine is the absence of internal lubrication. This means that the
exhaust steam is not contaminated with oil vapour and can be condensed and fed back to the
boilers without passing through the filters. It also means that turbine is considerable saving in
lubricating oil when compared with a reciprocating steam engine of equal power.
A final advantage of the steam turbine and a very important one is the fact that a turbine can
develop many time the power compared to a reciprocating engine whether steam or oil.

OPERATING PRINCIPLES
A steam turbines two main parts are the cylinder and the rotor. The cylinder (stator) is a steel
or cast iron housing usually divided at the horizontal centerline. Its halves are bolted together
for easy access. The cylinder contains fixed blades, vanes and nozzles that direct steam into
the moving blades carried by the rotor. Each fixed blade set is mounted in diaphragms located
in front of each disc on the rotor, or directly in the casing. A disc and diaphragm pair a
turbine stage. Steam turbines can have many stages. A rotor is a rotating shaft that carries the
moving blades on the outer edges of either discs or drums. The blades rotate as the rotor
revolves. The rotor of a large steam turbine consists of large, intermediate and low-pressure
sections.
In a multiple-stage turbine, steam at a high pressure and high temperature enters the first row
of fixed blades or nozzles through an inlet valve/valves. As the steam passes through the
fixed blades or nozzles, it expands and its velocity increases. The high velocity jet of stream
strikes the first set of moving blades. The kinetic energy of the steam changes into
mechanical energy, causing the shaft to rotate. The steam that enters the next set of fixed
blades strikes the next row of moving blades.
As the steam flows through the turbine, its pressure and temperature decreases while its
volume increases. The decrease in pressure and temperature occurs as the steam transmits
energy to the shaft and performs work. After passing through the last turbine stage, the steam
exhausts into the condenser or process steam system.
The kinetic energy of the steam changes into mechanical energy through the impact (impulse)
or reaction of the steam against the blades. An impulse turbine uses the impact force of the
steam jet on the blades to turn the shaft. Steam expands as it passes through thee nozzles,
where its pressure drops and its velocity increases. As the steam flows through the moving
blades, its pressure remains the same, but its velocity decreases. The steam does not expand
as it flows through the moving blades.

STEAM CYCLE
The thermal (steam) power plant uses a dual (vapor+liquid) phase cycle. It is a closed cycle
to enable the working fluid (water) to be used again and again. The cycle used is Rankine
cycle modified to include superheating of steam, regenerative feed water heating and
reheating of steam.

MAIN TURBINE
The 210 MW turbine is a tandem compounded type machine comprising of H.P. and I.P.
cylinders. The H.P. turbines comprise of 12 stages, I.P. turbine has 11 stages and the L.P.
turbine has 4 stages of double flow.
The H.P. and I.P. turbine rotors are rigidly compounded and the L.P. motor by the lens type
semi flexible coupling. All the three rotors are aligned on five bearings of which the bearing
no. 2 is combined with the thrust bearing
The main superheated steam branches off into two streams from the boiler and passes through
the emergency stop valve and control valve before entering the governing wheel chamber of
the H.P. turbine. After expanding in the 12 stages in the H.P. turbine the steam is returned in
boiler for reheating.
The reheated steam for the boiler enters the I.P> turbine via the interceptor valves and control
valves and after expanding enters the L.P. turbine stage via 2 nos of cross-over pipes.
In the L.P. stage the steam expands in axially opposite direction to counteract the trust and
enters the condensers placed below the L.P. turbine. The cooling water flowing throughout
the condenser tubes condenses the steam and the condensate collected in the hot well of the
condenser.
The condensate collected is pumped by means of 3*50% duty condensate pumps through
L.P. heaters to deaerator from where the boiler feed pump delivers the water to boiler through
H.P. heaters thus forming a close cycle.

The Main Turbine


TURBINE CYCLE

Fresh steam from the boiler is supplied to the turbine through the emergency stop valve.
From the stop valves steam is supplied to control valves situated in H.P. cylinders on the
front bearing end. After expansion through 12 stages at the H.P. cylinder, steam flows back to
the boiler for reheating steam and reheated steam from the boiler cover to the intermediate
pressure turbine through two interceptor valves and four control valves mounted on I.P.
turbine.
After flowing through I.P. turbine steam enters the middle part of the L.P. turbine through
cross-over pipes. In L.P. turbine the exhaust steam condenses in the surface condensers
welded directly to the exhaust part of L.P. turbine.

The Turbine Cycle

The selection of extraction points and cold reheat pressure has been done with a view to
achieve a high efficiency. These are two extractors from H.P. turbine, four from I.P. turbine
and one from L.P. turbine. Steam at 1.10 and 1.03 g/sq. cm. Abs is supplied for the gland
sealing. Steam for this purpose is obtained from deaerator through a collection where
pressure of steam is regulated.
From the condenser, condensate is pumped with the help of 3*50% capacity condensate
pumps to deaerator through the low-pressure regenerative equipments.
Feed water is pumped from deaerator to the boiler through the H.P. heaters by means of
3*50% capacity feed pumps connected before the H.P. heaters.

SPECIFICATIONS OF THE TURBINE


Type: Tandem compound 3 cylinder reheated type.
Rated power: 210 MW.
Number of stages: 12 in H.P., 11 in I.P. and 4*2 in L.P. cylinder.
Rated steam pressure: 130 kg /sq. cm before entering the stop valve.
Rated steam temperature: 535C after reheating at inlet.
Steam flow: 670T / hr.
H.P. turbine exhaust pressure: 27 kg /sq. cm., 327C
Condenser back pressure: 0.09 kg /sq. cm.
Type of governing: nozzle governing.
Number of bearing; 5 excluding generator and exciter.
Lubrication Oil: turbine oil 14 of IOC.
Gland steam pressure: 1.03 to 1.05 kg /sq. cm (Abs)
Critical speed: 1585, 1881, 2017.
Ejector steam parameter: 4.5 kg /sq. cm.
Condenser cooling water pressure: 1.0 to 1.1 kg /sq. cm.
Condenser cooling water temperature: 27000 cu. M /hr.
Number of extraction lines for regenerative heating of feed water; seven.

TURBINE COMPONENTS
Casing.
Rotor.
Blades.
Sealing system.
Stop & control valves.
Couplings and bearings.
Barring gear.

TURBINE CASINGS
HP Turbine Casings:
Outer casing: a barrel-type without axial or radial flange.
Barrel-type casing suitable for quick startup and loading.
The inner casing- cylindrically, axially split.
The inner casing is attached in the horizontal and vertical planes in the barrel casing
so that it can freely expand radially in all the directions and axially from a fixed point
(HP- inlet side).

IP Turbine Casing:
The casing of the IP turbine is split horizontally and is of double-shell construction.
Both are axially split and a double flow inner casing is supported in the outer casing
and carries the guide blades.
Provides opposed double flow in the two blade sections and compensates axial thrust.
Steam after reheating enters the inner casing from Top & Bottom.

LP Turbine Casing:
The LP turbine casing consists of a double flow unit and has a triple shell welded
casing.
The shells are axially split and of rigid welded construction.
The inner shell taking the first rows of guide blades is attached kinematically in the
middle shell.
Independent of the outer shell, the middle shell, is supported at four points on
longitudinal beams.
Steam admitted to the LP turbine from the IP turbine flows into the inner casing from
both sides.

ROTORS
HP Rotor:
The HP rotor is machined from a single Cr-Mo-V steel forging with integral discs.
In all the moving wheels, balancing holes are machined to reduce the pressure
difference across them, which results in reduction of axial thrust.
First stage has integral shrouds while other rows have shroudings, riveted to the
blades are periphery.

IP Rotor:
The IP rotor has seven discs integrally forged with rotor while last four discs are
shrunk fit.
The shaft is made of high creep resisting Cr-Mo-V steel forging while the shrunk fit
discs are machined from high strength nickel steel forgings.
Except the last two wheels, all other wheels have shrouding riveted at the tip of the
blades. To adjust the frequency of thee moving blades, lashing wires have been
provided in some stages.

LP Rotor:
The LP rotor consists of shrunk fit discs in a shaft.
The shaft is a forging of Cr-Mo-V steel while the discs are of high strength nickel
steel forgings.
Blades are secured to the respective discs by riveted fork root fastening.
In all the stages lashing wires are provided to adjust the frequency of blades. In the
last two rows, satellite strips are provided at the leading edges of the blades to protect
them against wet-steam erosion.

BLADES
Most costly element of the turbine.
Blades fixed in stationary part are called guide blades/ nozzles and those fitted in
moving part are called rotating/working blades.
Blades have three main parts:
o Aerofoil: working part.
o Root.
o Shrouds.
Shroud are used to prevent steam leakage and guide steam to next set of moving
blades.

VACUUM SYSTEM
This comprises of:
Condenser: 2 for 200 MW unit at the exhaust of LP turbine.
Ejectors: One starting and two main ejectors connected to the condenser locared near
the turbine.
C.W. Pumps: Normally two per unit of 50% capacity.
CONDENSER
There are two condensers entered to the two exhausters of the L.P. turbine. These are surface-
type condensers with two pass arrangement. Cooling water pumped into each condenser by a
vertical C.W. pump through the inlet pipe.
Water enters the inlet chamber of the front water box, passes horizontally through brass tubes
to the water tubes to the water box at the other end, takes a turn, passes through the upper
cluster of tubes and reaches the outlet chamber in the front water box. From these, cooling
water leaves the condenser through the outlet pipe and discharge into the discharge duct.
Steam exhausted from the LP turbine washes the outside of the condenser tubes, losing its
latent heat to the cooling water and is connected with water in the steam side of the
condenser. This condensate collects in the hot well, welded to the bottom of the condensers.

A typical water cooled condensor

EJECTORS
There are two 100% capacity ejectors of the steam eject type. The purpose of the ejector is to
evacuate air and other non-condensating gases from the condensers and thus maintain the
vacuum in the condensers.
The ejector has three compartments. Steam is supplied generally at a pressure of 4.5 to 5 kg
/cm2 to the three nozzles in the three compartments. Steam expands in the nozzle thus giving
a high-velocity eject which creates a low-pressure zone in the throat of the eject. Since the
nozzle box of the ejector is connected to the air pipe from the condenser, the air and pressure
zone. The working steam which has expanded in volume comes into contact with the cluster
of tube bundles through which condensate is flowing and gets condensed thus after aiding the
formation of vacuum. The non-condensing gases of air are further sucked with the next stage
of the ejector by the second nozzle. The process repeats itself in the third stage also and
finally the steam-air mixture is exhausted into the atmosphere through the outlet.

CONDENSATE SYSTEM
This contains the following
i. Condensate Pumps: 3 per unit of 50% capacity each located near condenser hot well.
ii. LP Heater: Normally 4 in number with no.1 located at the upper part of the
condenser and nos. 2,3& 4 around 4m level.
iii. Deaerator; one per unit located around 181 M level in CD bay.

Condensate Pumps
The function of these pumps is to pump out the condensate to the desecrator through ejectors,
gland steam cooler and LP heaters. These pumps have four stages and since the suction is at a
negative pressure, special arrangements have been made for providing sealing. The pump is
generally rated for 160 m3/ hr at a pressure of 13.2 kg/ cm2 .

L.P. Heaters
Turbine has been provided with non-controlled extractions, which are utilized for heating the
condensate, from turbine bleed steam. There are 410 W pressure heaters in which the last
four extractions are used. L.P. Heater-1 has two parts LPH-1A and LPH-1B located in the
upper parts of the condenser A and condenser B, respectively. These are of horizontal type
with shell and tube construction. L.P.H. 2,3 and 4 are of similar construction and they are
mounted in a row of 5m level. They are of vertical construction with brass tubes the ends of
which are expanded into tube plate. The condensate flows in the U tubes in four passes and
extraction steam washes the outside of the tubes. Condensate passes through these four L.P.
heaters in succession. These heaters are equipped with necessary safety valves in the steam
space level indicator for visual level indication of heating steam condensate pressure vacuum
gauges for measurement of steam pressure, etc:
Deaerator
The presence of certain gases, principally oxygen, carbon dioxide and ammonia, dissolved in
water is generally considered harmful because of their corrosive attack on metals, particularly
at elevated temperatures. One of the most important factors in the prevention of internal
corrosion in modern boilers and associated plant therefore, is that the boiler feed water should
be free as far as possible from all dissolved gases especially oxygen. This is achieved by
embodying into the boiler feed system a deaerating unit, whose function is to remove the
dissolved gases from the feed water by mechanical means. Particularly the unit must reduce
the oxygen content of the feed water to a lower value as far as possible, depending upon the
individual circumstances. Residual oxygen content in condensate at the outlet of deaerating
plant usually specified are 0.005/ litre or less.

A Deaerator
PRINCIPAL OF DEAERATION
It is based on following two laws.
Henrys Law
Solubility
The Deaerator comprises of two chambers:
Deaerating column
Feed storage tank
Deaerating column is a spray cum tray type cylindrical vessel of horizontal construction
with dished ends welded to it. The tray stack is designed to ensure maximum contact time as
well as optimum scrubbing of condensate to achieve efficient deaeration. The deaeration
column is mounted on the feed storage tank, which in turn is supported on rollers at the two
ends and a fixed support at the centre. The feed storage tank is fabricated from boiler quality
steel plates. Manholes are provided on deaerating column as well as on feed storage tank for
inspection and maintenance.
The condensate is admitted at the top of the deaerating column flows downwards through the
spray valves and trays. The trays are designed to expose to the maximum water surfaces for
efficient scrubbing to affect the liberation of the associated gases steam enters from the
underneath of the trays and flows in counter direction of condensate. While flowing upwards
through the trays, scrubbing and heating is done. Thus the liberated gases move upwards
alongwith the steam. Steam gets condensed above the trays and in turn heats the condensate.
Liberated gases escapes to atmosphere from the orifice opening meant for it. This opening is
provided with a number of dlflectors to minimize the loss of steam.

FEED WATER SYSTEM


The main equipments coming under this system are:
Boiler feed Pump: Three per unit of 50% capacity each located in the 0 meter level
in the T bay.
High Pressure Heaters: Normally three in number and are situated in the TG bay.
Drip Pumps: generally two in number of 100% capacity each situated beneath the LP
heaters.
Turbine Lubricating Oil System: This consists of the Main Oil Pump (MOP),
Starting Oil Pump (SOP), AC standby oil pumps and emergency DC Oil Pump and
Jacking Oil Pump (JOP). (one each per unit)
Boiler Feed Pump
This pump is horizontal and of barrel design driven by an Electric Motor through a hydraulic
coupling. All the bearings of pump and motor are forced lubricated by a suitable oil
lubricating system with adequate protection to trip the pump if the lubrication oil pressure
falls below a preset value.
The high pressure boiler feed pump is a very expensive machine which calls for a very
careful operation and skilled maintenance. Operating staff must be able to find out the causes
of defect at the very beginning, which can be easily removed without endangering the
operator of the power plant and also without the expensive dismantling of the high pressure
feed pump.

Function
The water with the given operating temperature should flow continuously to the pump under
a certain minimum pressure. It passes through the suction branch into the intake spiral and
from there; it is directed to the first impeller. After leaving the impeller it passes through the
distributing passages of the diffuser and thereby gets a certain pressure rise and at the same
time it flows over to the guide vanes to the inlet of the next impeller. This will repeat from
one stage to the other till it passes through the last impeller and the end diffuser. Thus the
feed water reaching into the discharge space develops the necessary operating pressure.

Booster Pump
Each boiler feed pump is provided with a booster pump in its suction line which is driven by
the main motor of the boiler feed pump. One of the major damages which may occur to a
boiler feed pump is from cavitation or vapor bounding at the pump suction due to suction
failure. Cavitation will occur when the suction pressure of the pump at the pump section is
equal or very near to the vapor pressure of the liquid to be pumped at a particular feed water
temperature. By the use of booster pump in the main pump suction line, always there will be
positive suction pressure which will remove the possibility of cavitation. Therefore all the
feed pumps are provided with a main shaft driven booster pump in its suction line for
obtaining a definite positive suction pressure.

Lubricating Pressure
All the bearings of boiler feed pump, pump motor and hydraulic coupling are force
lubricated. The feed pump consists of two radial sleeve bearings and one thrust bearing. The
thrust bearing is located at the free end of the pump.
High Pressure Heaters
These are regenerative feed waters heaters operating at high pressure and located by the side
of turbine. These are generally vertical type and turbine based steam pipes are connected to
them.
HP heaters are connected in series on feed waterside and by such arrangement, the feed
water, after feed pump enters the HP heaters. The steam is supplied to these heaters to form
the bleed point of the turbine through motor operated valves. These heaters have a group
bypass protection on the feed waterside.
In the event of tube rupture in any of the HPH and the level of condensate rising to dangerous
level, the group protection devices divert automatically the feed water directly to boiler, thus
bypassing all the 3 H.P. heaters.

An HP heater

Turbine Oil Lubricating System


This consists of main oil pump, starting oil pump, emergency oil pump and each per unit.

You might also like