You are on page 1of 13

Project Title : Project No :

2392
Suite 5.23 - 5.26, 5th Floor,Wisma Central, CADANGAN BANGUNAN PERNIAGAAN (INSTITUT PENGAJIAN TINGGI SWASTA TAR UC) Sheet No Rev
SELUAS 62234 METER PERSEGI (15.378 EKAR) DI ATAS SEBAHAGIAN PT 30710 (H.S.D 9836)
Jalan Ampang,50450 Kuala Lumpur.
LOT BARU 106525, MAHKOTA VALLEY DI INDERA MAHKOTA, MUKIM KUALA KUANTAN, 3
Tel : 03-21661992 Fax : 03-21661993 DAERAH KUANTAN PAHANG DARUL MAKMUR Date :

Title :- Design Check UNTUK TETUAN 13-Nov-2017


Summary Table ASRFM Ir.Chai AIM REALITY SDN. BHD.

According to the above calculations, following are the summary table


of the water reticulation design calculations under Peak Flow and Fire Flow:

1) Domestic of pressure head loss = Peak Flow

From To Length Pipe Roughness Design Peak Flow ( Pipe Flow Head Loss
Diameter Coefficeint Flow,Q Q x 2.5 ) Velocity
Node Node (m) (m) c (m3/s) (m3/s) (m/s) (m)
Tapping 1 151.37 0.200 100 0.01730 0.04326 1.37702 2.4488
1 2 111.08 0.200 100 0.01730 0.04326 1.37702 1.7970
2 3 129.92 0.200 100 0.01730 0.04326 1.37702 2.1018
3 4 44.99 0.200 100 0.01730 0.04326 1.37702 0.7278
2 5 67.61 0.200 100 0.01730 0.04326 1.37702 1.0938
5 6 74.57 0.200 100 0.01730 0.04326 1.37702 1.2064
6 7 32.89 0.200 100 0.01730 0.04326 1.37702 0.5321
1 A) Information Of Flow Rate

From To Peak Flow Elev HGL TOTAL Remark


PRESSURE
Node Node (m3/s) (M.ODL) (M.ODL) (M)
Tapping 1 0.04326 23.30 53.511 30.21 +ve head
1 2 0.04326 23.30 51.714 28.41 +ve head
2 3 0.04326 23.30 49.612 26.31 +ve head
3 4 0.04326 23.30 48.885 25.58 +ve head
2 5 0.04326 23.30 50.620 27.32 +ve head
5 6 0.04326 23.30 49.414 26.11 +ve head
6 7 0.04326 23.50 48.882 25.38 +ve head
2) Hydrant of Pressure Head Loss = Average Flow + Fire Flow

Pipe Roughness Design Fire Flow + Pipe Flow


From To Length Head Loss
Diameter Coefficeint Flow,Q Q Velocity
Node Node (m) (m) c (m3/s) (m3/s) (m/s) (m)
Tapping 1 151.37 0.20 100 0.01730 0.04014 1.27761 2.13184
1 8 138.22 0.15 100 0.00000 0.02283 1.29208 2.78299
8 9 59.28 0.15 100 0.00000 0.02283 1.29208 1.19361
9 10 101.00 0.15 100 0.00000 0.02283 1.29208 2.03364
1 11 65.50 0.15 100 0.00000 0.02283 1.29208 1.31885
11 12 90.90 0.15 100 0.00000 0.02283 1.29208 1.83028
11 13 82.77 0.15 100 0.00000 0.02283 1.29208 1.66658
13 14 82.25 0.15 100 0.00000 0.02283 1.29208 1.65611
2A) Hydrant of Pressure Head Loss = Average Flow + Fire Flow

From To Peak Flow Elev HGL TOTAL


PRESSURE Remark
Node Node (m3/s) (M.ODL) (M.ODL) (M)
Tapping 1 0.04014 23.30 53.828 30.53 +ve head
1 8 0.02283 23.30 51.045 27.75 +ve head
8 9 0.02283 23.30 49.852 26.55 +ve head
9 10 0.02283 23.30 47.818 24.52 +ve head
1 11 0.02283 23.30 52.509 29.21 +ve head
11 12 0.02283 23.30 50.679 27.38 +ve head
11 13 0.02283 23.30 50.843 27.54 +ve head
13 14 0.02283 23.30 49.187 25.89 +ve head
Project Title : Project No :
2392
Suite 5.23 - 5.26, 5th Floor,Wisma Central, CADANGAN BANGUNAN PERNIAGAAN (INSTITUT PENGAJIAN TINGGI SWASTA Sheet No Rev
TAR UC) SELUAS 62234 METER PERSEGI (15.378 EKAR) DI ATAS SEBAHAGIAN PT
Jalan Ampang,50450 Kuala Lumpur. 30710 (H.S.D 9836) LOT BARU 106525, MAHKOTA VALLEY DI INDERA MAHKOTA, 1
Tel : 03-21661992 Fax : 03-21661993 MUKIM KUALA KUANTAN, DAERAH KUANTAN PAHANG DARUL MAKMUR Date :

Title :- Design Check UNTUK TETUAN


13-Nov-2017
ASRFM Ir.Chai AIM REALITY SDN. BHD.
CALCULATION DOMESTIC WATER

Total Water consumption per day = 328,870 gsh 0.0173040888 m3/s


Tapping point Pressure = 69.00 m O.D.L

Residual Tapping Pressure = 25.72 m


RL of pipe at Tapping = 43.28 m
Height of supply Level = 0 m

SAMPLE CALCULATION DOMESTIC

1) CALCULATION FROM TAPPING TO NODE 1

a) Normal Flow, Q
Refer to the water reticulation layout plan,
The total length from tapping to node 1 = 151.37 m

where,

Roughness coefficient C, = 100


Diameter of pipe, D = 0.2 m
Normal flow rate, Q = 0.01730409 m3/s
Pipe sectional area, A = 0.03141593 m2
Velocity, V = Q/A = 0.55080626 m/s
RL of pipe at Tapping = 43.28 m
RL of pipe at Node 1 = 37.10 m

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 0.449535 m

Differential IL of pipe at Node 1 = 6.18 m


Residual Tapping pressure = 25.72 m
Hence, the residual head at node 1 = 31.45 m
Residual Pressure at water tank = 31.450 m

Thus the pressure at node 1 > height of supply level = 31.45 > 7.5 ok

b) Peak Flow
NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

Peak Flow, Qp = 2.5 x normal flow (Q)


= 0.043260

where,

Length, L = 151.37 m
Rough coefficient,C = 100
Peak flow rate, Qp = 0.043260 m3/s
Diameter of pipe, D = 0.2 m
Sectional Area, A = 0.03141593 m2
Velocity, V = 1.37701564 m/s
Tapping point pressure = 69.00 m O.D.L
RL of pipe at Tapping = 43.28 m
RL of pipe at Node 1 = 37.10 m

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 2.4488

Differential IL of pipe at Node 1 = 6.18 m


Residual Tapping pressure = 25.72 m
Hence, the residual head at node 1 = 29.45 m
Residual Pressure at water tank = 29.451 m

Thus the pressure at node 1 > height of supply level = 29.45 > 7.5 OK
Project Title : Project No :
2392
Suite 5.23 - 5.26, 5th Floor,Wisma Central, CADANGAN BANGUNAN PERNIAGAAN (INSTITUT PENGAJIAN TINGGI SWASTA Sheet No Rev
TAR UC) SELUAS 62234 METER PERSEGI (15.378 EKAR) DI ATAS SEBAHAGIAN PT
Jalan Ampang,50450 Kuala Lumpur. 30710 (H.S.D 9836) LOT BARU 106525, MAHKOTA VALLEY DI INDERA MAHKOTA, 1
Tel : 03-21661992 Fax : 03-21661993 MUKIM KUALA KUANTAN, DAERAH KUANTAN PAHANG DARUL MAKMUR Date :

Title :- Design Check UNTUK TETUAN


13-Nov-2017
ASRFM Ir.Chai AIM REALITY SDN. BHD.
CALCULATION DOMESTIC WATER
2) CALCULATION FROM NODE 1 TO NODE 2

a) Normal Flow, Q
Refer to the water reticulation layout plan,
The total length from node 1 to node 2 = 111.08 m

where,

Roughness coefficient C, = 100


Diameter of pipe, D = 0.20 m
Normal flow rate, Q = 0.01730409 m3/s
Pipe sectional area, A = 0.03141593 m2
Velocity, V = Q/A = 0.55080626 m/s
RL of pipe at Node 1 = 37.10 m
RL of pipe at Node 2 = 37.10 m
Residual Head at node 1 = 31.45

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 0.329883 m

Differential IL of pipe at Node 2 = 0.00 m


Residual Tapping pressure 1 = 31.45 m
Hence, the residual head at node 2 = 31.12 m
Residual Pressure at water tank = 31.121 m

Residual Pressure at water tank = 31.121 > 7.5m OK

b) Peak Flow
NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

Peak Flow, Qp = 2.5 x normal flow (Q)


= 0.043260

where,

Length, L = 111.08 m
Rough coefficient,C = 100
Peak flow rate, Qp = 0.043260 m3/s
Diameter of pipe, D = 0.20 m
Sectional Area, A = 0.03141593 m2
Velocity, V = 1.37701564 m/s
RL of pipe at Node 1 = 37.10 m
RL of pipe at Node 2 = 37.10 m
Residual Head at node 1 = 29.45 m

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 1.7970

Differential IL of pipe at Node 2 = 0.00 m


Residual Node 1 = 29.45 m
Hence, the residual head at node 2 = 27.65 m

Thus the pressure at node 2 > height of supply level = 27.65 > 7.5 ok
Project Title : Project No :
2392
Suite 5.23 - 5.26, 5th Floor,Wisma Central, CADANGAN BANGUNAN PERNIAGAAN (INSTITUT PENGAJIAN TINGGI SWASTA Sheet No Rev
TAR UC) SELUAS 62234 METER PERSEGI (15.378 EKAR) DI ATAS SEBAHAGIAN PT
Jalan Ampang,50450 Kuala Lumpur. 30710 (H.S.D 9836) LOT BARU 106525, MAHKOTA VALLEY DI INDERA MAHKOTA, 1
Tel : 03-21661992 Fax : 03-21661993 MUKIM KUALA KUANTAN, DAERAH KUANTAN PAHANG DARUL MAKMUR Date :

Title :- Design Check UNTUK TETUAN


13-Nov-2017
ASRFM Ir.Chai AIM REALITY SDN. BHD.
CALCULATION DOMESTIC WATER
3) CALCULATION FROM NODE 2 TO NODE 3

a) Normal Flow, Q
Refer to the water reticulation layout plan,
The total length from node 2 to node 3 = 129.92 m

where,

Roughness coefficient C, = 100


Diameter of pipe, D = 0.20 m
Normal flow rate, Q = 0.01730409 m3/s
Pipe sectional area, A = 0.03141593 m2
Velocity, V = Q/A = 0.55080626 m/s
RL of pipe at Node 2 = 37.10 m
RL of pipe at Node 3 = 23.50 m
Residual Head at node 2 = 31.12 m

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 0.385833 m

Differential IL of pipe at Node 3 = 13.6 m


Residual Tapping pressure 2 = 31.12 m
Hence, the residual head at node 3 = 44.33 m
Residual Pressure at water tank = 44.335 m

Thus the pressure at node 3 > height of supply level = 44.33 > 7.5 ok
Project Title : Project No :
2392
Suite 5.23 - 5.26, 5th Floor,Wisma Central, CADANGAN BANGUNAN PERNIAGAAN (INSTITUT PENGAJIAN TINGGI SWASTA Sheet No Rev
TAR UC) SELUAS 62234 METER PERSEGI (15.378 EKAR) DI ATAS SEBAHAGIAN PT
Jalan Ampang,50450 Kuala Lumpur. 30710 (H.S.D 9836) LOT BARU 106525, MAHKOTA VALLEY DI INDERA MAHKOTA, 1
Tel : 03-21661992 Fax : 03-21661993 MUKIM KUALA KUANTAN, DAERAH KUANTAN PAHANG DARUL MAKMUR Date :

Title :- Design Check UNTUK TETUAN


13-Nov-2017
ASRFM Ir.Chai AIM REALITY SDN. BHD.
CALCULATION DOMESTIC WATER
b) Peak Flow
NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

Peak Flow, Qp = 2.5 x normal flow (Q)


= 0.043260 m3/s

where,

Length, L = 129.92 m
Rough coefficient,C = 100
Peak flow rate, Qp = 0.043260 m3/s
Diameter of pipe, D = 0.20 m
Sectional Area, A = 0.03141593 m2
Velocity, V = 1.37701564 m/s
RL of pipe at Node 2 = 37.10 m
RL of pipe at Node 3 = 23.50 m
Residual Head at node 2 = 27.65 m

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 2.1018

Differential IL of pipe at Node 3 = 13.60 m


Residual Tapping pressure 2 = 27.65 m
Hence, the residual head at node 3 = 39.15 m
Residual Pressure at water tank = 39.152 m

Thus the pressure at node 3 > height of supply level = 39.15 > 7.5 ok

4) CALCULATION FROM NODE 3 TO NODE 4

a) Normal Flow, Q
Refer to the water reticulation layout plan,
The total length from node 3 to node 4 = 44.99 m

where,

Roughness coefficient C, = 100


Diameter of pipe, D = 0.200 m
Normal flow rate, Q = 0.01730409 m3/s
Pipe sectional area, A = 0.03141593 m2
Velocity, V = Q/A = 0.55080626 m/s
RL of pipe at Node 3 = 23.5 m
RL of pipe at Node 4 = 23.4 m
Residual Head at node 3 = 44.33 m

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 0.133610 m

Differential IL of pipe at Node 4 = 0.1 m


Residual Tapping pressure 3 = 44.33 m
Hence, the residual head at node 4 = 44.30 m
Residual Pressure at water tank = 44.301 m

Thus the pressure at node 4 > height of supply level = 44.30 > 7.5 OK

b) Peak Flow
NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

Peak Flow, Qp = 2.5 x normal flow (Q)


= 0.043260 m3/s

where,

Length, L = 44.99 m
Rough coefficient,C = 100
Peak flow rate, Qp = 0.043260 m3/s
Diameter of pipe, D = 0.2 m
Sectional Area, A = 0.03141593 m2
Velocity, V = 1.37701564 m/s
RL of pipe at Node 3 = 23.50 m
RL of pipe at Node 4 = 23.40 m
Residual Head at node 3 = 39.15 m

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 0.7278

Differential IL of pipe at Node 4 = 0.10 m


Residual Tapping pressure 3 = 39.15 m
Hence, the residual head at node 4 = 38.52 m
Residual Pressure at water tank = 38.525 m

Thus the pressure at node 4 > height of supply level = 38.52 > 7.5 OK
Project Title : Project No :
2392
Suite 5.23 - 5.26, 5th Floor,Wisma Central, CADANGAN BANGUNAN PERNIAGAAN (INSTITUT PENGAJIAN TINGGI SWASTA Sheet No Rev
TAR UC) SELUAS 62234 METER PERSEGI (15.378 EKAR) DI ATAS SEBAHAGIAN PT
Jalan Ampang,50450 Kuala Lumpur. 30710 (H.S.D 9836) LOT BARU 106525, MAHKOTA VALLEY DI INDERA MAHKOTA, 1
Tel : 03-21661992 Fax : 03-21661993 MUKIM KUALA KUANTAN, DAERAH KUANTAN PAHANG DARUL MAKMUR Date :

Title :- Design Check UNTUK TETUAN


13-Nov-2017
ASRFM Ir.Chai AIM REALITY SDN. BHD.
CALCULATION DOMESTIC WATER
5) CALCULATION FROM NODE 4 TO NODE 5

a) Normal Flow, Q
Refer to the water reticulation layout plan,
The total length from node 4 to node 5 = 67.61 m

where,

Roughness coefficient C, = 100


Diameter of pipe, D = 0.200 m
Normal flow rate, Q = 0.01730409 m3/s
Pipe sectional area, A = 0.03141593 m2
Velocity, V = Q/A = 0.55080626 m/s
RL of pipe at Node 4 = 23.40 m
RL of pipe at Node 5 = 23.00 m
Residual Head at node 4 = 44.30 m

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 0.200786 m

Differential IL of pipe at Node 5 = 0.4 m


Residual Tapping pressure 4 = 44.30 m
Hence, the residual head at node 5 = 44.50 m
Residual Pressure at water tank = 44.50 m

Thus the pressure at node 5 > height of supply level = 44.50 > 7.5 ok
Project Title : Project No :
2392
Suite 5.23 - 5.26, 5th Floor,Wisma Central, CADANGAN BANGUNAN PERNIAGAAN (INSTITUT PENGAJIAN TINGGI SWASTA Sheet No Rev
TAR UC) SELUAS 62234 METER PERSEGI (15.378 EKAR) DI ATAS SEBAHAGIAN PT
Jalan Ampang,50450 Kuala Lumpur. 30710 (H.S.D 9836) LOT BARU 106525, MAHKOTA VALLEY DI INDERA MAHKOTA, 1
Tel : 03-21661992 Fax : 03-21661993 MUKIM KUALA KUANTAN, DAERAH KUANTAN PAHANG DARUL MAKMUR Date :

Title :- Design Check UNTUK TETUAN


13-Nov-2017
ASRFM Ir.Chai AIM REALITY SDN. BHD.
CALCULATION DOMESTIC WATER
b) Peak Flow
NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

Peak Flow, Qp = 2.5 x normal flow (Q)


= 0.043260 m3/s

where,

Length, L = 67.61 m
Rough coefficient,C = 100
Peak flow rate, Qp = 0.043260 m3/s
Diameter of pipe, D = 0.2 m
Sectional Area, A = 0.03141593 m2
Velocity, V = 1.37701564 m/s
RL of pipe at Node 4 = 23.40 m
RL of pipe at Node 5 = 23.00 m
Residual Head at node 4 = 38.52 m

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 1.0938

Differential IL of pipe at Node 5 = 0.40 m


Residual Tapping pressure 2 = 38.52 m
Hence, the residual head at node 5 = 37.831 m
Residual Pressure at water tank = 37.831 m

Thus the pressure at node 5 > height of supply level = 37.83 > 7.5 OK

6) CALCULATION FROM NODE 5 TO NODE 6

a) Normal Flow, Q
Refer to the water reticulation layout plan,
The total length from node 5 to node 6 = 74.57 m

where,

Roughness coefficient C, = 100


Diameter of pipe, D = 0.200 m
Normal flow rate, Q = 0.01730409 m3/s
Pipe sectional area, A = 0.03141593 m2
Velocity, V = Q/A = 0.55080626 m/s
RL of pipe at Node 5 = 23.0 m
RL of pipe at Node 6 = 22.5 m
Residual Head at node 5 = 44.50 m

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 0.221456 m

Differential IL of pipe at Node 6 = 0.5 m


Residual Tapping pressure 5 = 44.50 m
Hence, the residual head at node 6 = 44.78 m
Residual Pressure at water tank = 44.78 m

Thus the pressure at node 6 > height of supply level = 44.78 > 7.5 ok

b) Peak Flow
NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

Peak Flow, Qp = 2.5 x normal flow (Q)


= 0.043260 m3/s

where,

Length, L = 74.57 m
Rough coefficient,C = 100
Peak flow rate, Qp = 0.043260 m3/s
Diameter of pipe, D = 0.2 m
Sectional Area, A = 0.03141593 m2
Velocity, V = 1.37701564 m/s
RL of pipe at Node 5 = 23.00 m
RL of pipe at Node 6 = 22.50 m
Residual Head at node 5 = 37.83 m

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 1.2064

Differential IL of pipe at Node 6 = 0.50 m


Residual Tapping pressure 5 = 37.83 m
Hence, the residual head at node 6 = 37.12 m
Residual Pressure at water tank = 37.12 m

Thus the pressure at node 6 > height of supply level = 37.12 > 7.5 OK
Project Title : Project No :
2392
Suite 5.23 - 5.26, 5th Floor,Wisma Central, CADANGAN BANGUNAN PERNIAGAAN (INSTITUT PENGAJIAN TINGGI SWASTA Sheet No Rev
TAR UC) SELUAS 62234 METER PERSEGI (15.378 EKAR) DI ATAS SEBAHAGIAN PT
Jalan Ampang,50450 Kuala Lumpur. 30710 (H.S.D 9836) LOT BARU 106525, MAHKOTA VALLEY DI INDERA MAHKOTA, 1
Tel : 03-21661992 Fax : 03-21661993 MUKIM KUALA KUANTAN, DAERAH KUANTAN PAHANG DARUL MAKMUR Date :

Title :- Design Check UNTUK TETUAN


13-Nov-2017
ASRFM Ir.Chai AIM REALITY SDN. BHD.
CALCULATION DOMESTIC WATER
7) CALCULATION FROM NODE 6 TO NODE 7

a) Normal Flow, Q
Refer to the water reticulation layout plan,
The total length from node 6 to node 7 = 32.89 m

where,

Roughness coefficient C, = 100


Diameter of pipe, D = 0.200 m
Normal flow rate, Q = 0.01730409 m3/s
Pipe sectional area, A = 0.03141593 m2
Velocity, V = Q/A = 0.55080626 m/s
RL of pipe at Node 6 = 22.5 m
RL of pipe at Node 7 = 22.5 m
Residual Head at node 6 = 44.78 m

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 0.097676 m

Differential IL of pipe at Node 7 = 0.0 m


Residual Tapping pressure 6 = 44.78 m
Hence, the residual head at node 7 = 44.68 m
Residual Pressure at water tank = 44.68 m

Thus the pressure at node 7 > height of supply level = 44.68 > 7.5 OK

b) Peak Flow
NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

Peak Flow, Qp = 2.5 x normal flow (Q)


= 0.043260 m3/s

where,

Length, L = 32.89 m
Rough coefficient,C = 100
Peak flow rate, Qp = 0.043260 m3/s
Diameter of pipe, D = 0.2 m
Sectional Area, A = 0.03141593 m2
Velocity, V = 1.37701564 m/s
RL of pipe at Node 6 = 22.50 m
RL of pipe at Node 7 = 22.50 m
Residual Head at node 6 = 37.12 m

By using Hazen- Williams formula


Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )
= 0.5321

Differential IL of pipe at Node 7 = 0.00 m


Residual Tapping pressure 6 = 37.12 m
Hence, the residual head at node 7 = 36.59 m
Residual Pressure at water tank = 36.59 m

Thus the pressure at node 7 > height of supply level = 36.59 > 7.5 OK
Project Title : Project No :
2392
CADANGAN BANGUNAN PERNIAGAAN (INSTITUT PENGAJIAN TINGGI SWASTA TAR UC) SELUAS Sheet No Rev
Suite 5.23 - 5.26, 5th Floor,Wisma Central,
62234 METER PERSEGI (15.378 EKAR) DI ATAS SEBAHAGIAN PT 30710 (H.S.D 9836) LOT BARU
Jalan Ampang,50450 Kuala Lumpur. 106525, MAHKOTA VALLEY DI INDERA MAHKOTA, MUKIM KUALA KUANTAN, DAERAH KUANTAN 2
Tel : 03-21661992 Fax : 03-21661993 PAHANG DARUL MAKMUR Date :

Title :- Design Check UNTUK TETUAN


13-Nov-2017
ASRFM Ir.Chai AIM REALITY SDN.
BHD.
CALCULATION FIRE FLOW

SAMPLE CALCULATION FIRE FLOW

Total Water consumption per day = 328,870 gsh


Total Water consumption per day = 0.01730409 m3/s

1) CALCULATION FROM TAPPING TO NODE 1


NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

A) FIRE FLOW + NORMAL FLOW


Refer to the Fire Flow Requirements, this project is
under Class C where light industry Maximum 1 No. of
Hydrant Outlets Used Simultaneously = 1370 litre/min
Fire Flow Qr = 0.02283333 m3/s

Normal flow rate, Q = 0.01730409 m3/s


Fire Flow Rate, Qf = 0.04013742 m3/s
Length, L = 151.37 m
Rough coefficient,C = 100
Diameter of pipe, D = 0.2 m
Sectional Area, A = 0.03141593 m2
Velocity, V = 1.27761383 m/s
Residual Head Presure = 25.72 m (tapping )
RL of pipe at Tapping = 43.28 m
RL of pipe at Node 1 = 37.10 m

By using Hazen- Williams formula

Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )


= 2.1318403747

Differential IL of pipe at Node 1 = 6.180 m


Residual Tapping pressure = 25.72 m
Hence the residual head at node 1 = 29.77 m

Thus the pressure at node 1 > height of supply level hydrant = 32.40> 7.5 m - OK
Project Title : Project No :
2392
CADANGAN BANGUNAN PERNIAGAAN (INSTITUT PENGAJIAN TINGGI SWASTA TAR UC) SELUAS Sheet No Rev
Suite 5.23 - 5.26, 5th Floor,Wisma Central,
62234 METER PERSEGI (15.378 EKAR) DI ATAS SEBAHAGIAN PT 30710 (H.S.D 9836) LOT BARU
Jalan Ampang,50450 Kuala Lumpur. 106525, MAHKOTA VALLEY DI INDERA MAHKOTA, MUKIM KUALA KUANTAN, DAERAH KUANTAN 2
Tel : 03-21661992 Fax : 03-21661993 PAHANG DARUL MAKMUR Date :

Title :- Design Check UNTUK TETUAN


13-Nov-2017
ASRFM Ir.Chai AIM REALITY SDN.
BHD.
CALCULATION FIRE FLOW

2) CALCULATION FROM NODE 1 TO NODE 8


NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

A) FIRE FLOW + NORMAL FLOW


Refer to the Fire Flow Requirements, this project is
under Class C where light industry Maximum 1 No. of
Hydrant Outlets Used Simultaneously = 1370 litre/min
Fire Flow Qr = 0.022833 m3/s

Normal flow rate, Q = 0 m3/s


Fire Flow Rate, Qf = 0.022833 m3/s
Length, L = 138.22 m
Rough coefficient,C = 100
Diameter of pipe, D = 0.15 m
Sectional Area, A = 0.01767146 m2
Velocity, V = 1.29208349 m/s
Residual Head Presure = 29.77 m ( node 1 )
RL of pipe at node 1 = 37.10 m
RL of pipe at Node 8 = 23.30 m

By using Hazen- Williams formula

Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85 )


= 2.7829947258

Differential IL of pipe at Node 8 = 13.80 m


Residual Tapping pressure Node 1 = 29.77 m
Hence, the residual head at node 8 = 40.79 m

Thus the pressure at node 8 > height of supply level hydrant = 29.62 m > 7.5 m - OK
Project Title : Project No :
2392
CADANGAN BANGUNAN PERNIAGAAN (INSTITUT PENGAJIAN TINGGI SWASTA TAR UC) SELUAS Sheet No Rev
Suite 5.23 - 5.26, 5th Floor,Wisma Central,
62234 METER PERSEGI (15.378 EKAR) DI ATAS SEBAHAGIAN PT 30710 (H.S.D 9836) LOT BARU
Jalan Ampang,50450 Kuala Lumpur. 106525, MAHKOTA VALLEY DI INDERA MAHKOTA, MUKIM KUALA KUANTAN, DAERAH KUANTAN 2
Tel : 03-21661992 Fax : 03-21661993 PAHANG DARUL MAKMUR Date :

Title :- Design Check UNTUK TETUAN


13-Nov-2017
ASRFM Ir.Chai AIM REALITY SDN.
BHD.
CALCULATION FIRE FLOW

3) CALCULATION FROM NODE 8 TO NODE 9


NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

A) FIRE FLOW + NORMAL FLOW


Refer to the Fire Flow Requirements, this project is
under Class C where light industry Maximum 1 No. of
Hydrant Outlets Used Simultaneously = 1370 litre/min
Fire Flow Qr = 0.022833 m3/s

Normal flow rate, Q = 0 m3/s


Fire Flow Rate, Qf = 0.022833 m3/s
Length, L = 59.28 m
Rough coefficient,C = 100
Diameter of pipe, D = 0.15 m
Sectional Area, A = 0.01767146 m2
Velocity, V = 1.29208349 m/s
Residual Head Presure = 40.79 m ( node 1)
RL of pipe at node 8 = 23.30 m
RL of pipe at Node 9 = 23.30 m

By using Hazen- Williams formula

Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85


= 1.1935749338

Differential IL of pipe at Node 9 = 0.00 m


Residual Tapping pressure Node 8 = 40.79 m
Hence, the residual head at node 9 = 39.59 m

Thus the pressure at node 9 > height of supply level hydrant = 28.43m > 7.5m - OK

4) CALCULATION FROM NODE 9 TO NODE 10


NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

A) FIRE FLOW + NORMAL FLOW


Refer to the Fire Flow Requirements, this project is
under Class C where light industry Maximum 1 No. of
Hydrant Outlets Used Simultaneously = 1370 litre/min
Fire Flow Qr = 0.022833 m3/s

Normal flow rate, Q = 0 m3/s


Fire Flow Rate, Qf = 0.022833 m3/s
Length, L = 101 m
Rough coefficient,C = 100
Diameter of pipe, D = 0.15 m
Sectional Area, A = 0.01767146 m2
Velocity, V = 1.29208349 m/s
Residual Head Presure = 39.59 m ( node 9 )
RL of pipe at node 9 = 23.30 m
RL of pipe at Node 10 = 23.30 m

By using Hazen- Williams formula

Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85


= 2.0335875221

Differential IL of pipe at Node 10 = 0.00 m


Residual Tapping pressure Node 9 = 39.59 m
Hence, the residual head at node 10 = 37.56 m

Thus the pressure at node 10 > height of supply level hydrant = 26.39m > 7.5m - OK
Project Title : Project No :
2392
CADANGAN BANGUNAN PERNIAGAAN (INSTITUT PENGAJIAN TINGGI SWASTA TAR UC) SELUAS Sheet No Rev
Suite 5.23 - 5.26, 5th Floor,Wisma Central,
62234 METER PERSEGI (15.378 EKAR) DI ATAS SEBAHAGIAN PT 30710 (H.S.D 9836) LOT BARU
Jalan Ampang,50450 Kuala Lumpur. 106525, MAHKOTA VALLEY DI INDERA MAHKOTA, MUKIM KUALA KUANTAN, DAERAH KUANTAN 2
Tel : 03-21661992 Fax : 03-21661993 PAHANG DARUL MAKMUR Date :

Title :- Design Check UNTUK TETUAN


13-Nov-2017
ASRFM Ir.Chai AIM REALITY SDN.
BHD.
CALCULATION FIRE FLOW
5) CALCULATION FROM NODE 1 TO NODE 11
NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

A) FIRE FLOW + NORMAL FLOW


Refer to the Fire Flow Requirements, this project is
under Class C where light industry Maximum 1 No. of
Hydrant Outlets Used Simultaneously = 1370 litre/min
Fire Flow Qr = 0.022833 m3/s

Normal flow rate, Q = 0 m3/s


Fire Flow Rate, Qf = 0.022833 m3/s
Length, L = 65.5 m
Rough coefficient,C = 100
Diameter of pipe, D = 0.15 m
Sectional Area, A = 0.01767146 m2
Velocity, V = 1.29208349 m/s
Residual Head Presure = 29.77 m ( node 11 )
RL of pipe at node 1 = 23.30 m
RL of pipe at Node 11 = 23.30 m

By using Hazen- Williams formula

Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85


= 1.3188117099

Differential IL of pipe at Node 11 = 0.00 m


Residual Tapping pressure Node 1 = 29.77 m
Hence, the residual head at node 11 = 28.45 m

Thus the pressure at node 11 > height of supply level hydrant = 31.09m > 7.5m - OK

6) CALCULATION FROM NODE 11 TO NODE 12


NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

A) FIRE FLOW + NORMAL FLOW


Refer to the Fire Flow Requirements, this project is
under Class C where light industry Maximum 1 No. of
Hydrant Outlets Used Simultaneously = 1370 litre/min
Fire Flow Qr = 0.022833 m3/s

Normal flow rate, Q = 0 m3/s


Fire Flow Rate, Qf = 0.022833 m3/s
Length, L = 90.9 m
Rough coefficient,C = 100
Diameter of pipe, D = 0.15 m
Sectional Area, A = 0.01767146 m2
Velocity, V = 1.29208349 m/s
Residual Head Presure = 28.45 m ( node 11 )
RL of pipe at node 11 = 23.30 m
RL of pipe at Node 12 = 23.30 m

By using Hazen- Williams formula

Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85


= 1.8302287699

Differential IL of pipe at Node 12 = 0.00 m


Residual Tapping pressure Node 11 = 28.45 m
Hence, the residual head at node 12 = 26.62 m

Thus the pressure at node 12 > height of supply level hydrant = 29.25m > 7.5m - OK

7) CALCULATION FROM NODE 11 TO NODE 13


NOTE : Refer to the water reticulation layout plan to determine the node and pipe numbering

A) FIRE FLOW + NORMAL FLOW


Refer to the Fire Flow Requirements, this project is
under Class C where light industry Maximum 1 No. of
Hydrant Outlets Used Simultaneously = 1370 litre/min
Fire Flow Qr = 0.022833 m3/s

Normal flow rate, Q = 0 m3/s


Fire Flow Rate, Qf = 0.022833 m3/s
Length, L = 82.77 m
Rough coefficient,C = 100
Diameter of pipe, D = 0.15 m
Sectional Area, A = 0.01767146 m2
Velocity, V = 1.29208349 m/s
Residual Head Presure = 28.45 m ( node 11 )
RL of pipe at node 11 = 23.30 m
RL of pipe at Node 13 = 23.30 m

By using Hazen- Williams formula

Hf = (10.67 x L x Q1.85)/( D4.87 x C1.85


= 1.6665350416

Differential IL of pipe at Node 13 = 0.00 m


Residual Tapping pressure Node 11 = 28.45 m
Project Title : Project No :
2392
CADANGAN BANGUNAN PERNIAGAAN (INSTITUT PENGAJIAN TINGGI SWASTA TAR UC) SELUAS Sheet No Rev
Suite 5.23 - 5.26, 5th Floor,Wisma Central,
62234 METER PERSEGI (15.378 EKAR) DI ATAS SEBAHAGIAN PT 30710 (H.S.D 9836) LOT BARU
Jalan Ampang,50450 Kuala Lumpur. 106525, MAHKOTA VALLEY DI INDERA MAHKOTA, MUKIM KUALA KUANTAN, DAERAH KUANTAN 2
Tel : 03-21661992 Fax : 03-21661993 PAHANG DARUL MAKMUR Date :

Title :- Design Check UNTUK TETUAN


13-Nov-2017
ASRFM Ir.Chai AIM REALITY SDN.
BHD.
CALCULATION FIRE FLOW
Hence, the residual head at node 13 = 26.78 m

Thus the pressure at node 13 > height of supply level hydrant = 29.42m > 7.5m - OK

You might also like