* Receipt of EPA Authorization Letter = Year 0 (YR 0) Participation in a CMPP would eliminate or delay these requirements at the DD Site
Baseline Performance Standards
for all DD Sites
Implementation begins 30 days after permit coverage is
authorized
Good housekeeping and pollution prevention practices
Illicit
Discharge Organic waste and
Elimination & leaf litter collection
Detection
Phosphorus Reduction Requirements
Achieve the equivalent of a 65% reduction in
phosphorus load from the developed portion of the
Designated Discharge Site (DD Site) through
implementation of any one or combination of the
following:
1. Enhanced non-structural BMPs at the
DD Site
65%
Reduction
2. Structural BMPs (e.g., impervious area in annual
disconnections, infiltration practices, rain gardens, Phosphorus
filtering systems, etc. at the DD Site
Load
3. Participation in a Certified Municipal Phosphorus
Program (CMPP)
Summary of Individual Phosphorus
Reduction Requirements
Preliminary Phosphorus Reduction Plan
submitted to municipality – 2 years
Discontinue
application of
fertilizer
containing
phosphorus
on all
managed
pervious
areas
Example – Condominium Development
PRE-RETROFIT RETROFITS
Land Use: High Density Residential Porous asphalt
18 acre site 2.1 acres of parking lot space
5.8 impervious
Bioretention cell
9.3 managed pervious
2.9 unmanaged pervious Treating rooftop runoff from 7 of 9
buildings
Infiltration rate: Excellent
Current SW mgmt Gravel wetland
Street/Parking lot runoff collection in Treatment of catch basin collected runoff
catch basins - discharged into tributary
Phosphorus-free fertilizer application
Rooftop runoff unmanaged
SW BMPs in place On all managed pervious area
Catch basin cleaning
Street sweeping
Using Appendix D, Attachments 2 and 3, total
From Appendix D, Attachment 1:
annual phosphorus reduction credit from
Phosphorus Load
structural and non-structural BMPs: 12.51
15.45 lb/year
lb/yr
Required Reduction
10.04 lb/year
Example – Shopping Plaza
(pre-retrofit)
Example – Shopping Plaza
(post-retrofit)
Infiltration trench
Discontinue
application of
fertilizer
containing
phosphorus on Curb cuts
all managed
pervious areas
Enhanced
Curb cuts organic waste
and leaf litter
collection
program on all
impervious
Bioretention areas
cell
Example – Shopping Plaza
PRE-RETROFIT RETROFITS
Land Use: Commercial Curb cuts and bioretention on nine existing
5.5 acre site: parking islands
5.02 acres impervious Close off catch basins
0.25 acres managed pervious Allow infiltration of stormwater
0.24 acres unmanaged pervious Infiltration Trenches
Infiltration rate: Good Treating stormwater runoff from site’s storm
Current SW mgmt: drain system prior to discharge to municipal
Street/Parking lot runoff collection in catch system
basins, discharged into municipal storm drain Disconnect rooftop runoff
system Allows longer residence time and some
Rooftop runoff directly connected to storm capture by bioretention
drain system Phosphorus-free fertilizer application
SW BMPs in place: On all managed pervious areas
Catch basin cleaning Enhanced organic waste and leaf litter
Street sweeping collection program
Using Appendix D, Attachment 1:` On all impervious areas, 1/week, April 1
Phosphorus Load: through December 15
11.26 lb/year
Required Reduction: Using Appendix D, Attachments 2 and 3, total
7.32 lb/year annual phosphorus reduction credit from
structural and non-structural BMPs: 12.51
lb/yr
Example – Car Dealership
(pre-retrofit)
Example – Car Dealership
(post-retrofit)
Contact Information:
Mark Voorhees
US EPA Region I
5 Post Office Sq.Suite100
Mail Code OEP06-4
Boston, MA 02109-3912
Phone: (617) 918-1537
Email: Voorhees.mark@epa.gov
Questions and
Discussion