Daily Activity Report

BLCP Outage 2017 Unit#1 Shutdown Project


Date of Daily Activty Report : 12/11/2017
08:00-09:00 09:00-10:00 10:00-11:00 11:00-12:00 13:00-14:00 14:00-15:00 15:00-16:00 16:00-17:00 17:00-18:00 18:00-19:00 19:00-20:00
Weather Report C S S S S S S S C C C
Remarks: Sunny : S Clouded : C Rainy :R Heavy Rains : HR

Item Last day Item Today Item Next day

Piping Activity
1 Continues tube RH fit up & weld inside boiler (LHS top) 12 joint 1 Continues tube RH fit up & weld inside boiler (LHS top) 12 joint 1 Continues tube RH fit up & weld inside boiler (LHS top) 12 joint

2 Continues Tube Instaiiation fit up and weld (RHS top) 12 joint 2 Continues Tube Instaiiation fit up and weld (RHS top) 12 joint 2 Continues Tube Instaiiation fit up and weld (RHS top) 12 joint
3 Continues tube RH fit up & weld inside boiler (Front top) 4 joint. 3 Continues tube RH fit up & weld inside boiler (Front top) 12 joint. 3 Continues tube RH fit up & weld inside boiler (Front top) 12 joint.
4 Continues machine beveling tube RHS/LHS & Front side top.
4 support.)
Continues machine beveling tube RHS/LHS top. (And outside Beveling for try to fit up gride 4 Continues machine beveling tube RHS/LHS & Front side top.
5 Continues spare part tube laydown area & Stock tube (for fit up Tube RH LHS top) (And outside Beveling LHS bottom for preparation fit up gride support.) (And outside Beveling LHS bottom for preparation fit up gride support.)
6 Continues machine beveling tube RHS/LHS top. 5 Continues spare part tube laydown area & Stock tube (for fit up Tube RH LHS top) 5 Continues spare part tube laydown area & Stock tube (for fit up Tube RH LHS top)
7 First fit up gride support LHS No.A06-14700-1101A (68 - 71) 6 Continues First fit up gride support LHS No.A06-14700-1101A (68 - 71) & weld. 4 Joint 6 Continues fit up gride support LHS bottom & weld. 4 joint

Item Position Day Night Today Piping Activity Photo


MANPOWER
1 Site Engineer 1 0 1
2 QA Engineer 2 1 3
3 Safety 2 1 3
4 QA,QC Superviser 2 0 2
5 Superviser 5 3 8
6 Admin Staff 1 0 1
7 Welder 13 7 20
8 Fitter A,B 30 11 41
9 Electricain 1 2 3
10 Fire Watch 5 2 7
11 Store/General 3 0 3
12 Rigger 6 2 8
71 29 100
Piping Activity Photo
Total (Man-Day)
The TJEL manpower combine foe SPC Sub-Contact

Note : Progress Erection Top


No. Description Fit up Weld RT Acc
1 RHS top (145 joints) 88 88 79 75
2 LHS top (145 joints) 87 87 80 74
3 Front side (297 joints) 16 16 11 10

Total 191 191 170 159

Note : Progress Erection Bottom


No. Description Fit up Weld RT Acc
1 RHS bottom (145 joints) 0 0 0 0
2 LHS bottom (145 joints) 4 4 0 0
3 Front side bottom (297 joints) 0 0 0 0

Total 4 4 0 0