Daily Activity Report

BLCP Outage 2017 Unit#1 Shutdown Project


Date of Daily Activty Report : 9/11/2017
08:00-09:00 09:00-10:00 10:00-11:00 11:00-12:00 13:00-14:00 14:00-15:00 15:00-16:00 16:00-17:00 17:00-18:00 18:00-19:00 19:00-20:00
Weather Report S S S S S S R R S S S
Remarks: Sunny : S Clouded : C Rainy :R Heavy Rains : HR

Item Last day Item Today Item Next day

Piping Activity
1 Start Tube Instaiiation fit up and weld (RHS top) 4 joint = team D 1 Continues tube RH fit up & weld inside boiler (LHS top) 6 joint 1 Continues tube RH fit up & weld inside boiler (LHS top) 12 joint

2 Continues Tube Instaiiation fit up and weld (RHS top) 6 joint 2 Continues Tube Instaiiation fit up and weld (RHS top) 6 joint 2 Continues Tube Instaiiation fit up and weld (RHS top) 12 joint
3 Continues cut on RH tubes inside of boiler (Front left top) 30 joint 3 Continues cut on RH tubes inside of boiler (Front left top) 60 joint 3 Continues cut on RH tubes inside of boiler (Front left top) 66 joint finish
4 Continues tube RH fit up & weld inside boiler (LHS top) 6 joint 4 Start tube RH fit up & weld inside boiler (Front top) 3 joint (from middle first) No.143-145 4 Continues tube RH fit up & weld inside boiler (Front top) 4 joint.
5 Continues spare part tube laydown area & Stock tube (for fit up Tube RH LHS top) 5 Continues spare part tube laydown area & Stock tube (for fit up Tube RH LHS top) 5 Continues spare part tube laydown area & Stock tube (for fit up Tube RH LHS top)
6 Continues machine beveling tube RHS/LHS top. 6 Continues machine beveling tube RHS/LHS top. 6 Continues machine beveling tube RHS/LHS top.
7 Preparation plate Try to fit up gride support LHS No.A06-14700-1101A (68 - 71) 7 Continue reparation for fit up gride support LHS No.A06-14700-1101A (68 - 71) 7 Continue reparation for fit up gride support LHS No.A06-14700-1101A (68 - 71)

Item Position Day Night Today Piping Activity Photo


MANPOWER
1 Site Engineer 1 0 1
2 QA Engineer 1 1 2
3 Safety 2 1 3
4 QA,QC Superviser 2 0 2
5 Superviser 7 3 10
6 Admin Staff 1 0 1
7 Welder 14 6 20
8 Fitter A,B 33 10 43
9 Electricain 1 2 3
10 Fire Watch 5 2 7
11 Store/General 4 0 4
12 Rigger 6 0 6
77 25 102
Piping Activity Photo
Total (Man-Day)
The TJEL manpower combine foe SPC Sub-Contact

Note : Progress Erection


No. Description Fit up Weld RT Acc
1 RHS top (145 joints) 50 50 43 36
2 LHS top (145 joints) 43 43 38 33
3 Front side (297 joints) 0 0 0

Total 93 93 81 69

Note : Progress Cut tube


No. Description Joint Cut Balance
1 RHS top 145 145 0
2 LHS top 145 145 0
3 Front side 297 231 66

Total 587 521 66