Section 5.

2
Mechanical Works

Fire Protection and Detection System Design Criteria

Codes and Standards


Work performed under these specifications shall be done in accordance with the following
codes and standards. Unless otherwise specified, the applicable governing edition and
addenda to be used for all references to codes or standards specified herein shall be
interpreted to be the jurisdictionally approved edition and addenda. If a code or standard is
not jurisdictionally mandated, then the current edition and addenda in effect at the date of this
document shall apply:
Table 5.2.6.1-1: Codes and Standards
Work In Accordance With
Overall design Uniform Building By-Laws (UBBL) 1984,
Fire Services Act 1988 & Regulations/ Akta
Perkhidmatan Bomba 1988 & Peraturan-
Peraturan (Act 341), including any specific
directions issued by BOMBA in relation to
the Plant incorporating all amendments up
to 1 January 2006.
BOMBA, NFPA, AHJ, and applicable codes
Fire system equipment NFPA, FM*, UL*, ANSI, ASME, ASTM,
components NEMA, IEC, IEEE, AWS, AWWA, and DOT
Smoke detection IEC, NFPA 70, 72, 90A, and 850
Heat detection IEC, NFPA 70, 72, and 850
Manual pull stations IEC, NFPA 70, 72, 101, and applicable
codes
Indicating devices IEC, NFPA 70, 72, and 850
Sprinkler system NFPA 13, 25 and 850
Water spray fixed system NFPA 15, 25 and 850
Control panel initiating and
indicating devices IEC, NFPA 70, 72, and 850
Deluge piping (if any) ASTM A53 or A106
Pipe thread tolerances NFPA 13 and ANSI B1.20 Pipe Threads
FM-200 system IEC, NFPA 70, 72, 2001; UL; FM
CO2 system IEC, NFPA 12, 70, 72 and 850; UL; FM
Private Fire Service Mains and NFPA 24, 291, FM, UL Standard 246
Their Appurtenances
Extinguishers NFPA 10

TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 31
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

Work In Accordance With


Standpipe & hose reel Hose NFPA 14, FM, UL Standard 246
systems
Rotating lights and Site fire alarm
warning horns IEC, UL, NFPA 70 and 72
Fire alarm system wiring
(initiating devices, notification
appliances, solenoids, signaling
line circuits) IEC, NFPA, AHJ, and applicable codes
Wiring and installation work National Electrical Code NFPA 70 and IEC
Elevator Shutdown ASME A17.1
Fire water pumps, motor NFPA 20, 25, 850, FM, UL, ANSI, ASME,
controllers, engine controllers, DEMA, AWWA, IEC, IEEE, NEMA, and
and all accessories applicable local codes and standards
Fire water pump enclosure NFPA 20, 25, 850, and applicable local
codes and standards
Fire water pump system testing NFPA 20, 25
Standard for the Inspection, NFPA 25
Testing and Maintenance of
Water Based Fire protection
Systems
Standard for Water Tanks for NFPA 22
Private Fire Protection
Life Safety Code NFPA 101
*Equipment supplied shall be listed by Underwriters Laboratories Inc. (UL) or
shall be included in the Approval Guide as published by Factory Mutual (FM)
Engineering. Equipment shall be considered as FM-approved only if it conforms
to the characteristics and limitations of the individual component approvals and
if those components are used in the service intended by the Approval Guide.

NFPA 850 shall be used as a guide for the Plant fire protection design.
Any conflict between referenced codes or standards, or between the standards and these
specifications, shall be referred to the Employer who shall determine which standard or
specification requirements shall govern.

Fire Protection and Detection Systems


Automatic fire protection and detection systems shall be furnished for all buildings, structures,
and specific hazards requiring such protection in accordance with applicable Laws and codes,
in particular the NFPA requirements and Code & Standards referenced in Section 5.2.6.1 of

TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 32
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

the specification. Additionally, specific hazards will be protected with fire suppression and/or
detection systems.
The Contractor shall perform a fire risk analysis to determine all of the forms of fire protection
required and provided in this project.
The following minimum fire detection and protection systems are required for the existing coal
stockyard extension project:
Table 5.2.6.2-1: Fire Protection and Detection Systems
Location Type of Detection Type of Protection
Coal conveyor galleries Linear Heat Detector Wet pipe sprinkler
(fibre optical with
distributed temperature
sensor DTS)
Transfer Stations/Towers Air Sampling type & Heat Wet pipe sprinkler, Standpipe &
Detector Hose System and Extinguisher
Substation ES4 Double interlock system FM200 System and
with Air Sampling type, Extinguisher
Heat or Smoke Detector
Substation ES3 Double interlock system Extension of existing firefighting
with Air Sampling type, system (CO2)
Heat or Smoke Detector

This Section covers the minimum design, shop fabrication, installation and testing
requirements for the fixed protection systems, alarm systems, and portable fire protection
equipment. Fire protection equipment shall be arranged to appropriately protect the Plant and
equipment in the event of fire.
It is not the intention to specify herein all fire protection and detection systems or all details of
design and construction therefore. The Contractor shall ensure that all fire protection and
detection systems required by applicable Laws and codes are provided, and that the
equipment there in has been designed, fabricated, and erected in accordance with the latest
laws and codes.
All equipment and material provided should be new, compatible with existing fire system, free
from defects and of the same type, standard and quality set forth in this document.
The fire detection and protection system to be considered by the Contractor shall be to
minimize the possibility of fire at the Plant. These measures are to fulfil the following
requirements:
Inhibiting the outbreak and spread of fire.
Protection of operating personnel
Early fire detection, warning and extinguishing
Minimizing damage resulting from a fire.

TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 33
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

The Contractor shall meet these requirements by optimizing building and equipment layout
(passive measures) and by providing adequate warning and fire detection and protection
measures (active measures)

Materials
The following materials shall be used in the provision of the fire protection and detection
systems:
Table 5.2.6.3-1: Material Guidelines
Component Material
Piping
Sprinkler/Spray piping ASTM A53, Grade B, galvanized,
(downstream of isolation gate seamless or welded (ERW); or
valve) ASTM A106, Grade B, galvanized.
Minimum Schedule 40
Dry-pipe and pre-action systems ASTM A53, Grade B, galvanized;
(downstream of isolation gate seamless or welded (ERW); ASTM A106,
valve) Grade B, galvanized (no copper or brass
tubing or piping). Minimum Schedule 40
Wet-pipe systems Galvanized piping required for outdoor
systems. Minimum Schedule 40
Dry pilot piping Galvanized ASTM A53, seamless or
welded (ERW), Schedule 80, Grade B
Air piping Minimum 13 mm outside diameter
Piping upstream of the sprinkler Black steel, ASTM A53, Grade B,
and spray systems seamless; or ASTM A106, Grade B,
seamless. Minimum Schedule 40
(Galvanized piping required in outdoor
areas)
Flanges
Flanges Hot-dip galvanized following welding
when connected to galvanized pipe
Piping 50 mm and smaller Screwed or shop welded. (UL or FM
Listed grooved style fittings are
acceptable except where piping is
attached to the turbine pedestal.)
Piping larger than 50 mm Welded flanges or shop welded
connections. (UL or FM Listed grooved
style fittings are acceptable except where
piping is attached to the turbine pedestal.)

TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 34
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

Component Material
Pipe accessories
Dry pilot fittings Cast iron, galvanized, ANSI B16.4 Class
250; or malleable iron, galvanized,
ANSI B16.3 Class 150 with threaded ends
Dry pilot unions Brass to iron seats
Sprinkler and spray fittings ANSI B16.3 or B16.1 malleable iron,
(threaded or flanged: tees, Class 150 (mitered fittings are not
couplings, elbows, caps, and acceptable)
reducers)
Sprinkler and spray fittings Galvanized, ASTM A153; no bushing, slip
(except wet-pipe) type, or clamp-on rubber gasketed fittings
Plugs (sprinkler system) Square head, dissimilar to the fitting to
which they are attached
Gaskets Red rubber sheets, 1.6 mm thick, full
face, ASTM D2000, No. 2AA705A13L14
Thread sealant Teflon ribbon, Optional for gas
suppression piping.
Thread tolerances NFPA 13 and ANSI B1.20.1 pipe threads
Bolts and nuts Steel machine bolts
Plugs Square heads and of a metal dissimilar to
fitting to which they are attached
Piping supports Per NFPA 13 and 15
Supplementary support beams
(pipe support) ASTM A36, fireproof construction
Riser lugs ASME B31.1
Hanger rods Per NFPA 13
Water shields Viking model B-1, or equivalent.
Valves
Gate valves OS&Y type, flanged ends (butterfly valves
are not acceptable)
Control panels (LFAP) NEMA 4
Control panels (MFAP) NEMA 12 (manufacturers standard panel
will be considered in rooms with no water
suppression and not likely to see any
abnormal dust conditions)

TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 35
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

Component Material
Fire water pumps
Pump casing, discharge head, Cast Iron, ASTM A48
suction bell, and pump bowls
Pump impellers Bronze, ASTM B584
Pump shaft Carbon Steel, AISI C1045
Pump shaft sleeves Bronze, ASTM 62
Pump wearing rings Bronze, ASTM B584
Vertical only
Pump column Cast steel, ASTM A120, hot-dipped
galvanized
Wearing rings Bronze, ASTM B584
Shaft and shaft enclosing tube AISI Type 416 stainless steel
Bearings Cutless rubber
Shaft sleeves AISI Type 304 stainless steel
Suction strainer Bronze
All bolting AISI Type 316 stainless steel

Notwithstanding the above, the Contractor shall verify that the Materials prescribed are

components.

Test Requirements
This testing is to be considered part of the C 7.3, and
all associated costs shall be in accordance with the Contract. The following tests, including
such other tests as may be required by the relevant fire authorities, shall be conducted in
accordance with the specified source, and in accordance with such procedures as may be
required by the fire authorities:

Tests In Accordance With Conducted By


Testing and system NFPA 11,13, 14, 15 and 16, 25, Contractor
acceptance of water based 291 and applicable building code
fire protection systems
Testing and system NFPA 12 or 2001 (as applicable), Contractor
acceptance of gaseous fire and applicable building code
protection systems

TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 36
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

Tests In Accordance With Conducted By


Testing and system NFPA 70 and 72, and applicable Contractor
acceptance of fire alarm building code
system
Fire water pump Shop Test NFPA 20, NFPA 25 Contractor
Fire water pump Field NFPA 20, NFPA 25, and local Contractor
Acceptance Testing codes/standards
Entire System Applicable NFPA and building codes Contractor

Sprinkler and Spray Systems


The fire protection equipment shall be arranged to adequately protect the Transfer Stations,
coal conveyor galleries and equipment in the event of fire.
An occupant warning system to be installed to provide adequate warning to notify the fire
alarm.
The piping shall be arranged with adequate slope and valved vents and drains so as to be
completely drainable.
Special emphasis shall be given to the design of the fire suppression systems to prevent water
supply and dry pilot piping and nozzles from interfering with required Plant repairs or routine
maintenance.
Valves installed between alarm initiating devices intended to signal activation of a system and
the fire suppression system shall be supervised.
An occupant warning system to be installed to provide adequate warning to notify the fire
alarm.

Inert Gas Fire Suppression System


For control rooms, common equipment room, switch breaker, and other areas that are
anticipated to be manned normally, a totally flooding high pressure inert gas fire suppression
system shall be provided. The inert gas type shall be FM200, however contractor may propose
a better type of inert gas.
The inert gas used shall have zero ozone depletion potential, zero global warming potential,
non-toxic or with high level of safety to human beings, does not cause any trouble in visibility
and for industrial use.
Double interlock system with Air sampling type and smoke detectors are to be used to activate
the inter gas fire suppression system.
The system should comprise of nozzles, Air sampling type, heat or some detectors, alarm
bells, discharge nozzles and piping, wiring in conduit, storage tanks complete with all
necessary valves and fittings, local gas control panels complete with batteries and charge,
automatic electrical devices, manual key switch, warning lights, alarm bells ad signs.
The system shall be designed and capable to cover multiple zones with a single cylinder
station having a volume of agent required for the largest zone.

TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 37
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

The system shall be internationally recognised by Underwriters Laboratories (UL), National


Fire Protection (NFPA) and Environment Protection Agency (EPA).

FM 200 Fire suppression System


Application:
ES4 Substation
Acceptable Standards
The design, equipment, installation, testing and maintenance of the Clean Agent Suppression
System shall be in accordance with the applicable requirements set forth in the latest edition
of the following codes and standards
1) NFPA No. 2001 - Clean Agent Fire Extinguishing Systems
2) NFPA No. 70 - National Electrical Code
3) NFPA No. 72 - Standard For Protective Signaling
4) Factory Mutual Approval Guide
5) UL Listings
6) Requirements of the Authority Having Jurisdiction (AHJ).
B. The standards listed, as well as all other applicable codes, standards, and good engineering
practices shall be used as "minimum" design standards.
System Requirements
All Works shall be as per required by Local Fire Authority or statutory authorities having
jurisdiction over this Works. Pipes and nozzles selection calculations for approval should be
submitted prior to installation.
The installation shall be designed for extinguishing of fire, involving electrical equipment
hazards and generally to the requirements of NFPA. The quantity of extinguishing agent shall
be shown in the drawings.
The system shall be based on total flooding principle with time delay of 30 seconds with all
safety measures to be considered.
The system should comprise of nozzles, heat or smoke detectors, alarm bells, discharge
nozzles and piping, wiring in conduit, storage tanks complete with all necessary valves and
fittings, local control panels complete with batteries and charge, automatic electrical devices,
manual key switch, , warning lights, alarm bells and signs.
Indicator signal from the local control panel shall be relayed to the MFAP at the existing Central
Control Room (CCR).
A. The system shall be a Total Flood FM-200 Suppression System.
B. The system shall provide a FM-200 minimum design concentration of 7.2% by
volume for Class A hazards and 9.0% by volume for Class B hazards, in all areas
and/or protected spaces, at the minimum anticipated temperature within the protected
area. System design shall not exceed 10.5% for normally occupied spaces, adjusted
for maximum space temperature anticipated, with provisions for room evacuation
before agent release.
TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 38
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

C. The system shall be complete in all ways. It shall include all mechanical and
electrical installation, all detection and control equipment, agent storage containers,
FM-200 agent, discharge nozzles, pipe and fittings, manual release and abort stations,
audible and visual alarm devices, auxiliary devices and controls, shutdowns, alarm
interface, caution advisory signs, functional checkout and testing, training and all other
operations necessary for a functional, UL Listed and/or FM approved FM-200 Clean
Agent Suppression System.
D. Provide two (2) inspections during the first year of service. Inspections shall be
made at 6-month intervals commencing when the system is first placed into normal
service.
E. The general contractor shall be responsible for sealing and securing the protected
spaces against agent loss and/or leakage during the 10-minute "hold" period.
F. The system(s) shall be actuated by a combination of ionization and/or photoelectric
detectors installed for maximum area coverage of 250 sq. ft. (23.2 m 2) per detector,
inboth the room, underfloor and above ceiling protected spaces. If the airflow is one
air change per minute, photoelectric detectors only shall be installed for maximum area
coverage of 125 sq. ft. (11.6 m2) per detector. (Ref. NFPA No. 72.)
G. Detectors shall be Cross-Zoned detection requiring two detectors to be in alarm
before release.
H. Automatic operation of each protected area shall be as follows:
1) Actuation of one (1) detector, within the system, shall:
a) Illuminate the "ALARM" lamp on the control panel face.
b) Energize an alarm bell and/or an optional visual indicator.
c) Transfer auxiliary contacts which can perform auxiliary system functions
such as: i) Operate door holder/closures on access doors, ii) Transmit a
signal to a fire alarm system, iii) Shutdown HVAC equipment.
d) Light an individual lamp on an optional annunciator.
2) Actuation of a 2nd detector, within the system, shall:
a) Illuminate the "PRE-DISCHARGE" lamp on the control panel face.
b) Energize a pre-discharge horn or horn/strobe device.
c) Shut down the HVAC system and/or close dampers.
d) Start time-delay sequence (not to exceed 60 seconds).
e) System abort sequence is enabled at this time.
f) Light an individual lamp on an optional annunciator.
3) After completion of the time-delay sequence, the FM-200 Clean Agent system shall
discharge and the following shall occur:
a) Illuminate a "SYSTEM FIRED" lamp on the control panel face.

TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 39
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

b) Shutdown of all power to high-voltage equipment


c) Energize a visual indicator(s) outside the hazard in which the discharge
occurred.
d) Energize a "System Fired" audible device. (Optional)
4) The system shall be capable of being actuated by manual discharge devices located
at each hazard exit. Operation of a manual device shall duplicate the sequence
description above except that the time delay and abort functions shall be bypassed.
The manual discharge station shall be of the electrical actuation type and shall be
supervised at the main control panel.

Fixed Carbon Dioxide Gas suppression system


Application:
ES3 Substation
Acceptable Standards
The design, equipment, installation, testing and maintenance of the CO2 Fire suppression
System shall be in accordance with the applicable requirements set forth in the latest edition
of the following codes and standards
A. National Fire Protection Association (NFPA):
1. NFPA 12 Standard on Carbon Dioxide Extinguishing Systems
2. NFPA 70 National Electrical Code
3. NFPA 72 Standard For Protective Signalling Systems
B. Underwriters Laboratories, Inc. (UL) and Underwriters Laboratories of Canada (ULC)
Fire Protection Equipment Directory
C. Factory Mutual (FM) Approval Guide
D. Requirements of the Authority Having Jurisdiction (AHJ)
The standards listed, as well as all other applicable codes, standards, and good engineering
practices shall be used as "minimum" design standards.
System Requirements
System design shall be total flood providing a minimum of 34% design concentration
throughout the entire protected area.
Sequence of operation
A. Activation of any single detector in any detection zone shall:
1. Cause audio and visual pre-discharge alarms to operate.
2. Transmit an alarm signal to remote monitoring or building alarm panel.
3. Operate auxiliary contacts for HVAC shutdowns and automatic dampers
4. Initiate a mechanical/pneumatic time delay to sound prior to CO2 release.
B. Upon completion of the time delay the carbon dioxide system shall:

TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 40
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

1. Cause a discharge alarm to be activated.


2. Energize control actuator for carbon dioxide cylinders releasing CO2.
Control panel Autopulse control system
The control panel shall be an AUTOPULSE system and shall communicate with and control
the following types of equipment used to make up the system: heat detectors, manual release,
alarm notification appliances, releasing components and other system controlled devices.
Heat detectors
Rate compensated heat detectors shall be supplied. Maximum spacing shall be 250 ft 2 (23.3
m2) per detector.
Indicating Appliances
Explosion-proof horn shall be provided in protected area OR Alarm horn strobe shall be
provided in protected area.
Manual pull station
Explosion-proof manual pull station shall be provided at each exit OR Manual pull station shall
be provided at each exit.
Carbon Dioxide storage cylinders
Cylinder Assembly:
Steel construction with red epoxy finish and equipped with a pressure seat-type
CV-98 valve.
Cylinder sizes shall be 35 lb (15.9 kg), 50 lb (22.7 kg), 75 lb (34.0 kg), 100 lb (45.4
kg), or 120 lb (54.4 kg) capacity.
Pneumatic time delay
Pneumatic time delay shall be provided to delay discharge of carbon dioxide.
Pneumatic pressure operated siren shall be located in protected space to sound for 30
seconds prior to discharge.
Supervised mechanical lockout
Installer shall provide a supervised mechanical lockout valve installed in the discharge line to
prevent discharge of CO2 into the protected space. Control panel must display a supervisory
signal when valve is closed.
Cylinder bracket
Each cylinder assembly shall be furnished with a bracket made from welded steel. The bracket
shall hold the cylinders in a saddle with a front bracket piece that secures the cylinders. The
brackets shall be modular in design to allow added bracketing or stacking of cylinders
depending on installation requirements.
Cylinder brackets shall be UL/ULC listed and/or FM approved for use with the carbon dioxide
system as manufactured by Tyco Fire Protection Products.
Valve actuators

TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 41
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

Electric valve actuators shall be of brass construction and stackable design with swivel
connections to allow removal of actuators for maintenance or testing.
Discharge hose/check valve
When manifolding, all cylinder assemblies shall include a flexible discharge hose and check
valve for connection to the manifold inlet.
All hose/check valves shall be UL/ULC listed and/or FM approved for use with the CV-98
carbon dioxide valves as manufactured by Tyco Fire Protection Products.
Discharge nozzles
A. Designed to direct discharge of carbon dioxide in a liquid or gaseous state.
B. Orifice size determined by flow rate and system design required.
C. Standard nozzles to be natural brass or painted red.
D. Nozzle quantity and placement shall be in compliance with the ANSUL Design,
Installation, Recharge and Maintenance Manual (Part No. 427604).
All Works shall be as per NFPA 12 including test and components required by Local Fire
Authority or statutory authorities having jurisdiction over this Works. Pipes and nozzles
selection calculations for approval should be submitted prior to installation.
The extension / installation shall be designed for extinguishing of fire, involving electrical
equipment hazards and generally to the requirements of NFPA. The quantity of extinguishing
agent shall be shown in the drawings.
The system shall be based on total flooding principle with time delay of 30 seconds with all
safety measures to be considered.
The system should comprise of nozzles, heat or smoke detectors, air sampling system, alarm
bells, discharge nozzles and piping, wiring in conduit, CO2 storage tanks complete with all
necessary valves and fittings, CO2 local control panels complete with batteries and charge,
automatic electrical devices, manual key switch, fire curtains, warning lights, alarm bells and
signs.
Indicator signal from the CO2 local control panel shall be relayed to the MFAP at the existing
Central Control Room (CCR).

Local Fire Alarm Panel (LFAP)


Local fire alarm panels shall be furnished and installed at each of the Transfer Stations to
supervise and annunciate fire protection system conditions. All local control panels shall be
capable of operation as a stand-alone system and compatible with the Site-wide existing main
fire.
Enclosures subject to potential water spray or environmental conditions not designed for by
the manufacturer shall be within a NEMA 4 enclosure. When a NEMA rated enclosure is
required, the system shall adopt and maintain the listings and/or approvals specified by NEMA.
Internal devices shall be factory wired to terminal blocks. When a manufacturer's panel is
used, a junction box shall be located near the panel to house the terminal blocks. When a
NEMA rated enclosure is supplied, sufficient space shall be allocated to conveniently locate
the terminal blocks on the back or bottom of the enclosure. Lightning protection shall be

TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 42
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

supplied on all circuits entering or leaving the structures or buildings as minimally required per
NFPA 70, Article 800. Components for lightning protection shall be installed in a dedicated
junction box.
Each local fire alarm panel shall continuously monitor its associated fire protection and
detection system(s) for fire alarms, supervisory trouble signals, and circuit trouble signals.
Upon receipt of a fire alarm, the given panel shall activate appropriate system valves, auxiliary
relay, and a fire alarm bell in the area or zone affected. Upon receipt of a trouble or supervisory
alarm, the panel shall activate individual alarm indicating lamps on the panel and a trouble
horn at or near the panel. Trouble and supervisory signals shall be distinctive, i.e., the mixing
of two or more signals on one circuit is not allowed.
Upon receipt of any fire alarm, each local panel shall activate a pair of normally closed,
electrically isolated contacts or send the information via network which will be used for
operating remote alarms in the CCR. Contractor shall modify and update the existing Main
Fire Alarm Panel (MFAP) in the CCR complete with interfacing with the new LFAPs and other
necessary Works for the proper integration of the new system with the existing system.

Fire Detection and Alarm Systems


Each independent fire detection system shall be addressable and designed to provide
adequate fire detection and annunciation in each of the areas protected. Each detection
control panel shall continuously monitor detection systems for fire or trouble condition and
activate the appropriate fire or trouble alarm(s) as required. These detection and alarm
functions shall be performed independently of any other Plant equipment or facility.
The activation of any fire detector shall initiate a fire alarm condition at the appropriate Local
Fire Alarm Panel (LFAP) and the Main Fire Alarm Panel (MFAP) located in the CCR.
A fire alarm system shall be furnished in accordance with local building codes and NFPA
requirements. The fire alarm system shall be designed in accordance with the requirements
of NFPA 72. Fire alarm signals shall be processed to a central supervising station located in
the CCR. Signals shall include indications of water flow, fire alarm, and equipment status, as
appropriate. Standalone local fire alarm control panels shall be provided as appropriate
throughout the Site area, and shall communicate via network wired in a loop configuration.

Main Fire Alarm Panel (MFAP)


Contractor shall modify and update the existing MFAP in the CCR complete with interfacing
with the new LFAPs and other necessary Works for the proper integration of the new system
with the existing system.
If no spare capacity is available in the existing MFAP, contractor shall provide a new
addressable MFAP adjacent to the existing MFAP in the CCR.
The Contractor shall furnish and install the MFAP in accordance with all codes and standards
to annunciate trouble, supervisory, and fire alarm signals from all fire protection and detection
systems provided for the Plant.
An annunciator panel integral to or located beside the MFAP shall contain lamps that are
easily viewable under all conditions, to annunciate distinctive alarm, trouble, and supervisory
conditions; terminal blocks for all external circuits (for MFAP and remote annunciator); and
push-button controls to start each fire water pump. Each lamp and switch shall have a distinct

TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 43
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

label located adjacent to the component. Space on the panel shall be supplied for a minimum
of ten (10) future suppression or detection systems.

Dedicated contacts shall be supplied for the DCS to monitor the MFAP. A separate contact
shall be supplied for general alarm, general trouble, and general supervisory conditions.
Failure of MFAP operation must not impair the operation of local control panels.
The panel shall have a minimum of ten (10) spare alarm zones requiring only field wiring for
future use.

BOMBA Fire Alarm Panel (BFAP)


Contractor shall modify and update the existing BFAP at the existing guardhouse complete
with interfacing with the MFAP in the CCR and other necessary Works for the proper
interconnection of both the panels.
If no spare capacity is available in the existing BFAP, contractor shall provide a new BFAP
adjacent to the existing panel at the existing guardhouse.
The BFAP shall consist of indicator panels, a repeater of MFAP, a printer, LED facial and LCD
workstation for the control system.
Any necessary interface terminals for a signal from the MFAP on the BFAP shall be made
available by the Contractor.

Manual Firefighting Equipment


A complement of portable fire extinguishers rated for Class A, B, C and E fires shall be
furnished and located throughout all buildings within the Plant in accordance with the
applicable Laws and codes, in particular NFPA 10 requirements. Additionally, portable CO2
extinguishers should be located in areas containing sensitive electrical equipment, such as
the substation.
A standpipe & hose system shall be furnished at the transfer stations in accordance with the
local building codes, NFPA 14 recommendations, and standard industry practice. Choice of
Class I, Class II, or Class III systems should be made by a fire risk evaluation. Hose stations
shall be complete with hose cabinet, hose, hose rack and nozzle. Hose cabinets shall be
marked to indicate the contents.

Firefighting Water Supply


The firefighting water supply for this project shall be tapped from the existing supply. This
extension work shall be designed in accordance with NFPA 850 recommendations.
Any additional water supply for the fire protection system to the extension, if installed, is to be
re-calculated and design based on the requirement of NFPA 13, 14 & 22.

Fire Water Distribution System


Sectional gate valves shall be furnished in the yard piping for isolation to minimize concurrent
impact to both automatic and manual suppression systems serving a given area in the event
of a single break in the underground piping. Buried sectional gate valves shall be furnished
with post indicators or roadway boxes, depending upon their location and potential

TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 44
CONVEYOR SYSTEM ( LEXPRO P1 )
Section 5.2
Mechanical Works

interference with traffic. Hydrants shall be supplied with header isolation gate valves. The
hydrants shall be located in strategic areas at maximum intervals of approximately 90 m along
the buried yard loop or branch line piping, and at maximum intervals of 150 m in remote areas.
This distribution of hydrants shall comply with the relevant Laws and codes.
Interior fire protection loops shall be provided with at least two valved connections to the yard
main with appropriate sectional control valves on the interior loop.
Fire main connections for standpipes shall be arranged so that a fire main break can be
isolated without interrupting service in the fire water distribution system simultaneously to both
fixed protection and hose connections protecting the same hazard or area.

Waste Water Treatment System


The existing waste water treatment system including its auxiliary equipment/parts shall be
inspected and to be used by the Contractor for the Project. As described in Section 4.2.4.2
(4), the Contractor shall be responsible for conducting a water balance study to confirm the
capacity of the existing waste water treatment system in handling the additional waste water
to be generated from the new bypass conveyor system, taking into account the requirements
of the relevant local authorities. The Contractor may need to provide a new waste water
treatment plant if required, subject to the findings of this study.
All waste and effluent water shall be treated in waste water treatment plant (WWTP) to the
parameter limits of Standard B of the Fifth Schedule as stipulated in the Environmental Quality
(Industrial Effluents) Regulation, 2009, P.U. (A) 434/2009 or its latest edition prior to discharge
to any waterway.

Wastewater Treatment and Disposal

5.2.8.1.1 Wastewater Collection and Treatment


Refer to Section 4.2.4.2 for more information. Sumps are significant levels of solids;
accumulation is expected and the collection shall be designed to accommodate such solids
accumulation and to facilitate periodic removal of solids. Each wastewater collection sump
shall be a concrete sump with two 100 percent capacity sump pumps capable of operating in
parallel. These sump pumps shall transfer the collected wastewater to either the existing
industrial wastewater storage pond or temporary storage ponds as indicated. The flow
diagrams and system definition provided for the wastewater collection and treatment system
shall be used as guides for design and equipment specification. The concept drawing for the
modification of wastewater treatment systems in Package 1 is included in Section 6.1-34.
Underground wastewater piping shall be HDPE wherever possible. If operating conditions
prevent HDPE from being used underground, carbon steel shall be used. Above ground piping
shall be HDPE or carbon steel. Underground piping shall be used to the greatest extent
possible.

Lifting Equipment

General Requirements
The design of lifting and handling facilities shall conform to the appropriate international
standards and Malaysian Statutory requirements for cranes, lifts and scaffolding.
TENDER NO.: LBT/CS/PROC/EPC/Tender/2017/1 REVISION NO: 1 DATE: 11 July 2017

TITLE: LEKIR BULK TERMINAL EXPANSION PROJECT PACKAGE 1 - DEDICATED BYPASS


PAGE NO: 45
CONVEYOR SYSTEM ( LEXPRO P1 )