You are on page 1of 7

Construction of the Seikan Undersea Tunnel--II.

Execution of the Most Difficult Sections


Kazuhisa Hashlmoto and Yutaka Tanabe

Abstract--This paper describes the three main problems associated with the R~stma~---Cet article dicrit les trois problkmes principaux qui Jurent rencontris
difficult sections of the work which were encountered and for which solutions were lots des travaux de construction des parties diffwiles du tunnel de Seikan et done les
found during construction of the Seikan Tunnel: (1) the excavation of squeezing solutionsfurent trouvles sur place. On peut citer: l'excavation du sol en compression
ground; (2) water inflow accidents; and (3) the excavations of unconsolidated plastique, les accidents d~ fi l'eau surgissante, et les excavations des zones non
zones. Squeezing ground, which appeared in the F-lOfault with an earth pressure consolidies. Le sol en compression plastique qui apparut daus la faille F 10 avec
as high as 2 MPa, was excavated employing spring line drifts and the short bench une pressionjasqu'a 2 MPa fut excuvi gl l'aide de lignes d'entrainement fi ressort et
method with steel pipe supportsfilled with reinforcing hoop-shaped steel bars and fi l'aide de la mlthode de la plateforme courte. Cette mithode utilise des supports
grouted with a high*strength mortar. The most serious water inflow incident fairs de tuyaux d'acier remplis d'arceaux de renforcement en acier cimentis ensemble
(maximum rate of 70 m3/min.) occurred in the service tunnel on the Hokkaido side par un mortier de grande rlsistance. La vague d'eau surgissante la plus importante,
in May 1976, causing inundation of 3 km of the service tunnel and 1.5 km of the avec un dlbit de 70 nil~rain, apparut daus le tunnel de service du cdti de Hokkaido
main tunnel. By correctlyjudging the situation and making strenuous efforts over en mai 1976 et, causa une inondation de 3 km dans le tunnel de service et de 1,5 km
the next 5.4 months, the remedial work which included water drainage--was dans le tunnel principal. Grdce fi une ~valuation correcte de la situation et fi des
safely completed. There were no fatalities or serious injuries resulting from the efforts importants pendant 5,4 mois, la phase de rlparation qui comprit le drainage
accident. The unconsolidated soft sand layer of the Kuromatsunai Formation, de l'eau fut achevle sans danger. II n'eut pas defatalitls ou de blessures slrieuses
which existed in the middle of the Tsugaru Straits, was excavated without any risultant de l'accideut. Les sables non-consolidis et mous de la formation
water inflow accidents. This was accomplished with the aide of water-seal grouting Kuromatsunai qui existaient au milieu des ddtroits de Tsugaru furvnt excavls sans
and by carrying out construction procedures with care. Although different measures aueun problkme d'eau surgissante. Cette phase fut accomplie en bouchant les
were required for each problem, the difficulties were overcome by careful infiltrations d'eau et en procldant avec soin tout au long de la construction. Bien que
investigation and construction management. de difflrentes mesuresfurent requisent pour chaque problkme, les difficultis furent
surmontles ~ l'aide d'examens attentifs et une gestion soign~e de la construction.

Introduction Geological Conditions (2) Approximately 620 m of the Tappi


he Seikan Undersea Tunnel is Section, between 21.590 and 22.210 km
The geology at the site of the Seikan
T probably the most ambitious
engineering project ever under-
Undersea Tunnel consisted
sedimentary rock, volcanic rock and
of
on the Honshu side (undersea section).
(3) 1284 m of the Yoshioka Section,
between 32.676 and 33.960 km along the
taken. Compared to ordinary mountain pyroclastic rock belonging to Neogene.
tunnelling, the main feature of the Seikan F-10 fault on the Hokkaido side (under-
The geology can be classified into three
Undersea Tunnel is its unprecedented sea section).
areas: (1) The Hokkaido side area con-
length under straits with great depth and O f the zones of squeezing ground
sists of sedimentary rock such as tuff and
a boundless source of sea water. I f a vast encountered, the third zone, along the
mudstone; (2) the middle area of the
volume of sea water had flowed into the F-10 fault, was the most serious in terms
Tsugaru Straits consists of relatively soft
tunnel continuously, it would have been of pressure and length. The following
and poorly consolidated tuffaceous mud-
impossible to complete the Seikan describes the details of the construction
stone (called the Kuromatsunai Forma-
Undersea Tunnel. Therefore, accurate procedures adopted in that zone.
tion); and (3) in the Honshu side area,
investigation, sufficient grouting and The excavation of the service tunnel in
there are tuff-breccia and andesite-type
careful control of the excavation were the Yoshioka Section was started using a
rocks (Fig. 1).
essential. tunnel boring machine (IHI-840) in
For the most part, the unconfined
However, many factors--such as May 1970. As the excavation progressed,
compressive strength of rocks ranged
water pressure with maximum value of the excavation became very difficult in
between 5 and 100 MPa, while poorly
2.4 MPa, poorly consolidated weak zones the weak tufts at nearly 33.750 km.
consolidated or altered rock frequently
and squeezing ground--made the tunnel Therefore, excavation by the tunnel bor-
showed strengths of approx. 2 MPa.
construction extremely difficult. ing machine had to be given up at 33.650
Although it was predicted from the
This paper describes the very difficult km and was replaced with a Roadheader
initial geological survey that nine large
parts of the tunnel construction that were machine (MRH-S40K), which is used in
faults existed in the Tsugaru Straits, it
encountered during the excavation of ordinary mechanical excavation.
turned out that the F-10 fault was the
squeezing ground, the treatment of water The geological structure comprised
biggest obstruction in the Seikan Under-
inflow accidents and the excavation of alternate strata of mudstone and tuff of
sea Tunnel construction work.
poorly consolidated zones. the Kunnui Formation. As the excava-
tion approached the F-10 fault, rather
Excavation of Squeezing Ground altered clayey lapilli tuff was encoun-
Kazuhisa Hashimoto is Project Manager of tered and marked splitting, squeezing
The following are sections where
the Construction Works Joint Venture for the and heaving occurred at the face. As
squeezing ground was particularly abun-
North Undersea Section (Hokkaido Side) of countermeasures against the foregoing,
dant along the total length (53.850 km)
the Seikan Tunnel. Present address: Aza heavier supports were used, the support
of the Seikan Undersea Tunnel:
Yoshioka, Fukushima-cho, Matsumae-gun, spacing was shortened, strut members
Hokkaido, Japan. Yutaka Tanabe is Mana- (1) Approximately 800 m of the were employed, and the shotcrete thick-
ger, Technical Consulting Section, Civil Sanyoshi Section, between 4.450 and ness was increased.
Engineering Dept, Jaisei Corporation, Tokyo, 5.250 km on the Honshu site (land At the location of greatest earth press-
Japan. section). ure, the excavation of the service tunnel

Tt~'~lling and U~l~tgroundS[~* T~lmology, Vol. 1, No. 3/4, pp. 373-379, 1986. 0866-7798/86 $3.00+.00
Printed in Great Britain. ~) 1986 Pergamon Journals Ltd. 373
Total length of tunnel 53. 8 5 0 k m
Length of underleo portion 23, 300 km
Honshu side Hokkaido side
300~
200 "1

100q
t J 4 - -

. _" "
-200
-100 t Kh2
-300 B$ BI
-400
(m) I
15 20 25 30 35 40 (km)
, , ~ I ~ , ~ , I ~ , , , I . . . . I , J , , I ~ , , ~ I ,

Kuromotsunai Formation
Yokumo Formation Basalt,
Rhyolite
Andesite
I KunnuiFormation
----- Fault, Unconformity

Fukuyama Formation

Figure 1. Geological map of the Seikan undersea tunnel.


was carried out by means of a circular Actually, the excavation was carried Water Inrushlng Accidents
short bench method, with supports out using four steel support systems
(H200X200X8X12) erected at intervals depending on the geological conditions; During the construction of Seikan
of 0.5 m; and the thickness of the namely (H-250x250x9x14), plain 10- Undersea Tunnel, there were four acci-
shotcrete was increased to 0.25 m. The in. pipe support without reinforcement, dents involving serious flooding (see
excavation of the zone of squeezing 10- and 12-in. pipe supports reinforced Table 1).
ground along the F-10 fault was com- with hoop-shaped steel bars and high- The first accident occurred in Febru-
pleted at 32.676 km. However, there was strength mortar. However, as the settle- ary 1969, at the 1223 m point in the
water inflow in the service tunnel with a ment and the deformation of the sup- Tappi inclined shaft. The maximum
maximum flow rate of 1lma/min at the ports of upper half-section increased due volume of water inflow at the time was 16
32.747 km point in January 1974. to the deterioration of the ground, this m3/min; 196 m of the section was
As the geological conditions had been method again had to be modified at the flooded, but only a 15-m section was
confirmed from the experience of the 33.223 km point. Thereafter, the circular buried by the collapsed debris. It was
service tunnel, the excavation method of short bench method was employed with restored seven months afterward by
the main tunnel was changed from the circular spring line drifts (Fig. 2). draining and performing grouting to stop
original bottom heading method to the The excavation of the two small circu- the seepage of water.
side drift method at the 33.960 km point. lar drift headings were advanced along The second accident occurred in Janu-
However, because the geological condi- the spring lines of the main tunnel and ary 1974 at the 32.747 km point in the
tions deteriorated more and more as the backfilled with concrete. The objective of southbound Yoshioka service tunnel.
excavation progressed, the excavation this method was to provide a solid This point is located immediately after
method was changed to the circular short foundation for supports to prevent settle- the F-10 fault. The maxinmm volume of
bench method from the 33.708 km point. ment and deformation of the upper half water inflow was 1lm3/min; the flooded
This method had already been used section until the lining of the entire section was about 880 m long and the
successfully in squeezing serpentine rock circular section had been completed. buried section was 60 m long. As a
at the site of the Shin Noborikawa tunnel This method was employed in two remedial method, two ahernatives--(1)
on the Shekishyo line in Hokkaido, with sections of the main tunnel, one of which keeping to the original route or (2)
the purpose of constructing the lining as was 298 m long (33.223-32.925 kin) and excavating a detour service tunnel--were
quickly as possible. on the F-10 fault; the other was 147.5 m considered. As it was found that a large
As the maximum earth pressure acting long (32.6925-32.840 km) and adjacent amount of squeezing ground existed on
on the main tunnel was assumed to be to the section of the service tunnel where the detour route, the first alternative was
about 1.5--2.0 MPa from the results of the water inflow took place (see Fig. 3). adopted. It took 12 months to arrive at
in-situ measurements in the service tun- the point where the water inrushing had
nel, a new support system to bear this Shotcrete was used for the primary
lining, of thickness 0.25-0.35 m, and occurred, because of the considerable
earth pressure was developed. This sys- time consumed by carrying out a survey
tem involved the use of a heavier and placed immediately after the excavation.
The secondary lining, with a thickness of by boring from behind the bulkhhead,
more rigid support system to resist the grouting, and consolidating the collapsed
strong squeezing pressure. Based on the 0.70-0.90 m, was formed from reinforced
concrete. section.
numerous test results, 12-in. steel pipe
supports containing reinforcing hoop- Because of the many zones of squeez- The third accident occurred in Decem-
shaped bars grouted with high strengh ing ground and the water inflows it took ber 1974, at the 16.890 km point in the
mortar to improve ridigity were installed approx. 6 yr for the main tunnel to be northbound Tappi service tunnel. The
and showed an axial strength of 9.8 MN advanced through the above two sec- maximum water inflow was 6m:~/min.
at a strain of 3%. tions.

374 TUNNELLINGAND UNDERGROUNDSPACE TECHNOLOGY Volume 1, Number 3/4, 1986


Erecto iumbo Monorail hoisl Shotcrete moChine
plont

Section A Section B Section C Section D Section E

12.,pipe support Erector jumbo Drill jumbo for bench

Figure 2. Circular short bench method with spring line drifts.

K.-l,l,3 : Kunnui Fomation


Plan
Fv : Fukuyamo Formation
Point of water inrushinll [ 32,747 Kin)

/ / '
"~~~!,,..je__~ Lair / Ms. I f . O i l Service tunnel
' Tf Br \ \ "~,,~-~ ~ - - - ~ "~ ~ zF------------...e. '~ ''
. " ,': ~-_'~ I ,Y i . . . . . ~ ~ i', ~ J,, ~' ' . '
'

7601
Profile
- ,<,.,
K n- i iSdy Tf ~ n i
F ~ K n . 3 L I T f
_-" _ Main tunnel

~ n-I Kn-Z
~ MS. Tf. olt ~ IvlS'II "uil O0I

Cz : Circular short bench method.


C i : Circular short bench method with spring line drifts,

Figure 3. Geological map (32.500-33.700 km).


Although the 130-m-long flooded section The fourth accident occurred in May of the service tunnel showed a series of
was comparatively small in scale, the 1976, at the 31.668 km point in the stable strata consisting mainly of lapilli
buried section was as long as 70 m. service tunnel of the Yoshioka side. The tuff, a weak pyroclastic sediment. The
Following the drainage operation, maximum volume of water, inflow was 70 excavation progressed rather smoothly
exploratory boring was conducted, and m3/min and the sections of 3015 m of the with repeated grouting. The pilot tunnel
the results showed that the detour route service tunnel and 1459 m of the main was then being driven 287 m in advance
for the tunnel was possible. It took about tunnel were flooded. This was the most of the service tunnel and was also prog-
six months for the excavation of the serious flooding ever encountered on the ressing smoothly, with no noticeable
detour tunnel to reach the position cor- project (see Fig. 4). Advance boring to water inrushing.
responding to the water inflow. examine the geological conditions ahead

Volume 1, Number 3/4, 1986 TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY 375
Table 1. Water inflow accidents.

Water inflow
rate (mS/min) Total water Volume of Time required Method
Inflow collapeed debris Buried section for recovery employed
Section Date maximum final (ms) (ms) (m) (months) far recovery Geology

Tappi r Andesite
inclined shaft 1969.4.21 16 5.3 5300 300 15 6.3 grouting (Fault)

Tappi grounting Tuff.Basalt


service tunnel 1974.12.5 6 3.6 1600 1300 70 5.6 diversion (Fault)

Yoshioka J
service tunnel 1974.1.8 11 0.3 9000 1100 60 11.6 grouting Tuff. (Fault)

Yoshioka grouting Lapilli Tuff.


service tunnel 1976.5.6 70 16.0 121 000 1000 5.4 diversion (Fault)

~ Hokkaido side

I ~. .~ Flooded section 3.015m ., [ - I l/

11 ii.. io. F-I- .... I _...,.. "ii d71


I I I1.- ,o,1 - il //
,>,,Ollu.,,,i

~T-- ~ n
aiP
u
r ~station

Figure 4. Profile at the time (water inrushing (May 1976).

At about 3 a.m. on May 6, 1976, water Judging by the conditions observed, it decided to construct a bypass tunnel 60
inflow of about 0.03 m3/min near the face was considered that if a pump station m from the original route, on the oppo-
of the service tunnel suddenly increased were installed about 3 km behind the site side of the main tunnel. By October
to about 0.5 m3/min. Within about 30 point of water inflow the advance of the 15, 1976, the bypass tunnel had reached
min. the inflow rate had reached as much water line could be maintained at this a point beside the point of the water
as 4 m3/min. Since the service tunnel had point; thus, a station with a capacity of inflow; and, on January 31, 1977, the
a downward gradient of 12/1000, the 32 m3/min was provided. This installa- bypass tunnel rejoined the original route
tunnel was gradually inundated from the tion was completed before 10.30 p.m. on of the service tunnel at a point 148 m
face. Thanks to emergency pumping May 9, 1976, and, soon after the pump- ahead of the water inrushing point (Fig.
facilities, the advance of the flood water ing started, the water level achieved 5).
could be temporarily stopped and main- equilibrium. Although this water inrushing acci-
tained at a position 100 m from the On May 15, 1976, a full-scale pump- dent was the largest in scale when
collapsed face. ing operation was started in which three compared with the previous three, fortu-
The reinforcing of the pumping facil- mobile pumps and two floating facilities nately it was overcome without any
ties continued until about 2.45 p.m., were moved in intervals of about 80 m; injury to the workforce.
when suddenly, with a tremendous roar, and on June 24, 1976, the point was Despite the precautions taken in the
the water inflow increased to as much as reached at which the collapse could be excavation--such as investigation of the
70 m3/min. To prevent water inflow from confirmed. After constructing a bulkhead geological and groundwater conditions
going further into the tunnel a temporary behind this point, grouting was carried by advance boring and careful
dam was made from cement bags, but as out in order to fill the void left by the grouting--inrushing occurred, making
water overflowed the dam workers had to collapse, which extended 75 m from the us reflect on whether we should have
be evacuated. face, been more or less optimistic in our
At about 5.00 a.m. on the morning of Based on the results of exploratory judgments. As counter-measures, grout-
May 7, 1976, as the water began to flow boring conducted from behind the bulk- ing criteria were reconsidered and the
into the main tunnel through the con- head, and in consideration of the time draining equipment was reinforced.
necting gallery and the rate of water required and the cost of construction to The construction of the main tunnel at
inflow also decreased, the advance of the excavate along the original line or, alter- points where water inrushing had occur-
water in the service tunnel slowed down. natively, to drive a bypass tunnel, it was red was carried out by the side drift

376 TUNNELLINGAND UNDERGROUNDSPACE TECHNOLOGY Volume I, Number 3/4, 1986


Plan

,,

- ~,... .~, .~ .~,. :~ *, .~,.

*- * Y -. \ . bk--,, . I - -

., y" i. \:' \ v '..


\":" +,- " Profile .......
/, ..
,., ', "" r - "~, :: ,' :: "" ~ -~,- , .~. ~. "'
... , ., ,,..

' , ,-,'v ~ -~

-" - .. x " ~ ' " ~,. "~'. .~ ~ ~ . '~.. ..'~ = ~ : Boring


~ >,. .~, ;" :" :, .. ~ : Lapilli Tuff
~/ :. '-" .x L ~ ". ~" ~ : Sandy Tuff
~/" :;. ' - - . z //// ~. ~" ~ : T u f f Breccia
[77;7] : F o u l t

Figure 5. Geological map of the diversion tunnel route.

method, in which the face of the side drift gradient of 3/1000 and, for the large As regards the main tunnel, it was
was brought close to the face of the upper section of the main tunnel, special care confirmed that the "degraded mudstone"
half of the main tunnel, and the grouting had to be exercised in grouting and formation existed continuously over a
from both faces was carried out excavation. length of 480 m, between 25.530 and
prudently. The fault zone was finally Of special note is that only the pilot 26.010 km, owing to the fact that the
traversed (Fig. 6). tunnel and the main tunnel were tunnel crossed this formation obliquely
The points that these serious water designed to be excavated in the central due to its unfavorable inclination and
inflow accidents have in common are part of the undersea section, since the strike. Actually, the formation was only
that the sections of the service tunnel pilot tunnel would also serve the role of 25 m thick.
were comparatively small i.e. 18--20m2; service tunnel (see Fig. 1). Based on experience with the pilot
and that, because the tunnel had a After the F-I fault near the 30.100 km tunnel, the grouting time required for the
downward gradient, the debris of col- point on the Yoshioka side, the lower main tunnel was assumed to be too long
lapse was not washed away. Rather, the part of the Kuromatsunai Formation was to be tolerated, if only ordinary grouting
collapsed area blocked the water adv- excavated for about 1200 m. The excava- from the cutting face were employed.
ance with rock and fine material from tion, progressed well, with no difficulties. Therefore, it was decided that sup-
layers above, so that the volume of the The Kuromatsunai Formation reap- plementary grouting work should be
water inrushing decreased gradually. If peared around the 27.120 km point as carried out from the pilot tunnel in order
the inflows had occurred in a tunnel with part of a syncline, with its axis near the to execute more intensive grouting. The
an upward gradient or in a main tunnel 25.710 km point and stretching over a excavation was carried out carefully by
with a larger section, the situation would distance of about 4000 m. Also, the the side drift method. Immediately after
have been quite different. formation called "degraded mudstone" the excavation, shotcrete of 0.1 m thick-
(consisting mainly of alternating sandy ness was placed and 4.0 m-long rock
mudstone and tuffaceous sandy mud- bolts were installed in order to stabilize
Excavation of Unconsolidated
stone) appeared for about 700 m between the ground. At the same time, measure-
Sandy Ground
26.110 and 25.410 km (Fig. 7). As the ments of convergence, stress in the rock-
From the results of the preliminary formation contained only 15--20%, of bolts and ground displacement were
geological survey, it was known that the fine grains and had an inferior uncon- carried out.
central section of the straits consisted of fined compressive strength of 2 MPa, As precautions against water
poorly consolidated sandy mudstone cal- high permeability and water content, the inrushing and consequent total flooding
led the Kuromatsunai Formation. The borings collapsed easily and grouting of the tunnel during excavation, steel
Kuromatsunai Formation was also found was not very effective in reducing ground flood gates capable of resisting a water
on land. Because rock tests revealed that water flow. In the case of the pilot pressure of 2.7 MPa were installed in the
the formation had a low unconfined tunnel, which encountered only the pilot tunnel and in each of the connecting
compressive strength of about 5 MPa lower part of the "degraded mudstone" galleries between the pilot tunnel and
and high porosity, it was assumed that formation, 15 months were necessary to main tunnel. Other measures included
the cut-off of water inflow would be cover a distance of 420 m because of the taking great care in the excavation of the
difficult. The section of the tunnel in the time-consuming grouting work. main tunnel. The sequence of tunneling
middle part of the straits had an upward was controlled so that the excavation of

Volume I, Number 3/4, 1986 TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY 377
Plon

Service tunnel

3~ K 600 + 650 800 - . ~ Main tunnel

Profile

31K600 Moin tunnel

Figure 6. Execution of grouting around the fault.

:Tuffoceous sondy Mudstone

Plon ~ : Sondy Tuff


\

' it' ~ ~ "d "I . . . . . : " I ,I I - - -~--.,'~,,,~ I I " ~ i ~ ~, -

25K600m 5 K 700 m 25K800m 2~900m 26~000m ~K lOOm Hokkoidoside


Honshu side
Profile

16

Profile
tb I&
_T.Third
13
=1o9e 7,5m

IF I" Fi,.; .,G 4~,.-j


12
[ It }0 9 8 ? G $

Section
4 3 Z t N u n ~ e r of g r o u t i n g

I t ~- " ';=~"'-
~... - - ~
--I.~Zj~'.j
4R --~-
_j
~ ~.o! ,o-,
~ tunnel
_2

6I

Figure 7. Geological map and execution of the grouting.

378 TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY V o l u m e l, N u m b e r 3/4, 1986


adjacent construction lots would not be "degraded mudstone" formation section experienced and the many years required
finished until the execution of the side of the main tunnel. [] to complete the Seikan Undersea Tun-
drifts and arch section for them had been nel, I am proud to have had the oppor-
completed. Adjoining lots were kept tunity to participate in this big project as
separate by leaving 25 m of ground
Acknowledgements an engineer. I wish to thank all those
between them unexcavated to serve as This paper describes some of the who were involved in this project; and,
natural flood gate. It took 40 months-- engineering difficulties experienced in particularly, I am grateful for the efforts
from March 1981 to the beginning of the construction of the Seikan Undersea made by members of the Japan Railway
August 1984---to break through this Tunnel. Because of the many hardships Construction Public Corporation.

Volume 1, Number 3/4, 1986 TUNNELLINGAND UNDERGROUNDSPACE TECHNOLOGY 379

You might also like