You are on page 1of 21

before October 31, 1989; 2 and the other dated August 12,

1989, for the installation of electrical, water and hydrant


G.R. No. 96283 February 25, 1992 systems at the plant site, commanding a price of P12.1
million and requiring completion thereof one month after
CHUNG FU INDUSTRIES (PHILIPPINES) INC., its
civil works have been finished. 3
Directors and Officers namely: HUANG KUO-
CHANG, HUANG AN-CHUNG, JAMES J.R. CHEN, However, respondent Roblecor failed to complete the work
TRISTAN A. CATINDIG, VICENTE B. AMADOR, despite the extension of time allowed it by Chung Fu.
ROCK A.C. HUANG, JEM S.C. HUANG, MARIA Subsequently, the latter had to take over the construction
TERESA SOLIVEN and VIRGILIO M. DEL when it had become evident that Roblecor was not in a
ROSARIO, petitioners, position to fulfill its obligation.
vs. Claiming an unsatisfied account of P10,500,000.00 and
unpaid progress billings of P2,370,179.23, Roblecor on
COURT OF APPEALS, HON. FRANCISCO X.
May 18, 1990, filed a petition for Compulsory Arbitration
VELEZ (Presiding Judge, Regional Trail Court of
with prayer for Temporary Restraining Order before
Makati [Branch 57]) and ROBLECOR PHILIPPINES,
respondent Regional Trial Court, pursuant to the
INC., respondents.
arbitration clause in the construction agreement. Chung Fu
moved to dismiss the petition and further prayed for the
quashing of the restraining order.
ROMERO, J.:
Subsequent negotiations between the parties eventually led
This is a special civil action for certiorari seeking to annul to the formulation of an arbitration agreement which,
the Resolutions of the Court of Appeals* dated October among others, provides:
22, 1990 and December 3, 1990 upholding the Orders of
July 31, 1990 and August 23, 1990 of the Regional Trial 2. The parties mutually agree that the arbitration shall
Court of Makati, Branch 57, in Civil Case No. 90-1335. proceed in accordance with the following terms and
Respondent Court of Appeals affirmed the ruling of the conditions:
trial court that herein petitioners, after submitting
themselves for arbitration and agreeing to the terms and xxx xxx xxx
conditions thereof, providing that the arbitration award d. The parties mutually agree that they will abide by the
shall be final and unappealable, are precluded from decision of the arbitrator including any amount that may
seeking judicial review of subject arbitration award. be awarded to either party as compensation, consequential
It appears that on May 17, 1989, petitioner Chung Fu damage and/or interest thereon;
Industries (Philippines) (Chung Fu for brevity) and private e. The parties mutually agree that the decision of the
respondent Roblecor Philippines, Inc. (Roblecor for short) arbitrator shall be final and unappealable. Therefore, there
forged a construction agreement 1 whereby respondent shall be no further judicial recourse if either party
contractor committed to construct and finish on December disagrees with the whole or any part of the arbitrator's
31, 1989, petitioner corporation's industrial/factory award.
complex in Tanawan, Tanza, Cavite for and in
consideration of P42,000,000.00. In the event of disputes f. As an exception to sub-paragraph (e) above, the parties
arising from the performance of subject contract, it was mutually agree that either party is entitled to seek judicial
stipulated therein that the issue(s) shall be submitted for assistance for purposes of enforcing the arbitrator's award;
resolution before a single arbitrator chosen by both parties.
xxx xxx xxx 4
Apart from the aforesaid construction agreement, Chung
Fu and Roblecor entered into two (2) other ancillary (Emphasis supplied)
contracts, to wit: one dated June 23, 1989, for the Respondent Regional Trial Court approved the arbitration
construction of a dormitory and support facilities with a agreement thru its Order of May 30, 1990. Thereafter,
contract price of P3,875,285.00, to be completed on or
Engr. Willardo Asuncion was appointed as the sole and that "there shall be no further judicial recourse if either
arbitrator. party disagrees with the whole or any part of the
arbitrator's award."
On June 30, 1990, Arbitrator Asuncion ordered petitioners
to immediately pay respondent contractor, the sum of Second
P16,108,801.00. He further declared the award as final and
unappealable, pursuant to the Arbitration Agreement Respondent Court of Appeals and trial Judge gravely
precluding judicial review of the award. abused their discretion and/or exceeded their jurisdiction,
as well as denied due process and substantial justice to
Consequently, Roblecor moved for the confirmation of petitioner, by not vacating and annulling the award dated
said award. On the other hand, Chung Fu moved to remand 30 June 1990 of the Arbitrator, on the ground that the
the case for further hearing and asked for a reconsideration Arbitrator grossly departed from the terms of the parties'
of the judgment award claiming that Arbitrator Asuncion contracts and misapplied the law, and thereby exceeded
committed twelve (12) instances of grave error by the authority and power delegated to him. (Rollo, p. 17)
disregarding the provisions of the parties' contract.
Allow us to take a leaf from history and briefly trace the
Respondent lower court denied Chung Fu's Motion to evolution of arbitration as a mode of dispute settlement.
Remand thus compelling it to seek reconsideration
therefrom but to no avail. The trial court granted Because conflict is inherent in human society, much effort
Roblecor's Motion for Confirmation of Award and has been expended by men and institutions in devising
accordingly, entered judgment in conformity therewith. ways of resolving the same. With the progress of
Moreover, it granted the motion for the issuance of a writ civilization, physical combat has been ruled out and
of execution filed by respondent. instead, more specific means have been evolved, such as
recourse to the good offices of a disinterested third party,
Chung Fu elevated the case via a petition for certiorari to whether this be a court or a private individual or
respondent Court of Appeals. On October 22,1990 the individuals.
assailed resolution was issued. The respondent appellate
court concurred with the findings and conclusions of Legal history discloses that "the early judges called upon
respondent trial court resolving that Chung Fu and its to solve private conflicts were primarily the arbiters,
officers, as signatories to the Arbitration Agreement are persons not specially trained but in whose morality,
bound to observe the stipulations thereof providing for the probity and good sense the parties in conflict reposed full
finality of the award and precluding any appeal therefrom. trust. Thus, in Republican Rome, arbiter and judge (judex)
were synonymous. The magistrate or praetor, after noting
A motion for reconsideration of said resolution was filed down the conflicting claims of litigants, and clarifying the
by petitioner, but it was similarly denied by respondent issues, referred them for decision to a private person
Court of Appeals thru its questioned resolution of designated by the parties, by common agreement, or
December 3, 1990. selected by them from an apposite listing (the album
judicium) or else by having the arbiter chosen by lot. The
Hence, the instant petition anchored on the following judges proper, as specially trained state officials endowed
grounds: with own power and jurisdiction, and taking cognizance of
First litigations from beginning to end, only appeared under the
Empire, by the so-called cognitio extra ordinem." 5
Respondents Court of Appeals and trial Judge gravely
abused their discretion and/or exceeded their jurisdiction, Such means of referring a dispute to a third party has also
as well as denied due process and substantial justice to long been an accepted alternative to litigation at common
petitioners, (a) by refusing to exercise their judicial law. 6
authority and legal duty to review the arbitration award, Sparse though the law and jurisprudence may be on the
and (b) by declaring that petitioners are estopped from subject of arbitration in the Philippines, it was nonetheless
questioning the arbitration award allegedly in view of the recognized in the Spanish Civil Code; specifically, the
stipulations in the parties' arbitration agreement that "the provisions on compromises made applicable to arbitrations
decision of the arbitrator shall be final and unappealable"
under Articles 1820 and 1821.7 Although said provisions In recognition of the pressing need for an arbitral
were repealed by implication with the repeal of the machinery for the early and expeditious settlement of
Spanish Law of Civil Procedure, 8 these and additional disputes in the construction industry, a Construction
ones were reinstated in the present Civil Code. 9 Industry Arbitration Commission (CIAC) was created by
Executive Order No. 1008, enacted on February 4, 1985.
Arbitration found a fertile field in the resolution of labor-
management disputes in the Philippines. Although early In practice nowadays, absent an agreement of the parties to
on, Commonwealth Act 103 (1936) provided for resolve their disputes via a particular mode, it is the
compulsory arbitration as the state policy to be regular courts that remain the fora to resolve such matters.
administered by the Court of Industrial Relations, in time However, the parties may opt for recourse to third parties,
such a modality gave way to voluntary arbitration. While exercising their basic freedom to "establish such
not completely supplanting compulsory arbitration which stipulation, clauses, terms and conditions as they may
until today is practiced by government officials, the deem convenient, provided they are not contrary to law,
Industrial Peace Act which was passed in 1953 as morals, good customs, public order or public policy." 12 In
Republic Act No. 875, favored the policy of free collective such a case, resort to the arbitration process may be spelled
bargaining, in general, and resort to grievance procedure, out by them in a contract in anticipation of disputes that
in particular, as the preferred mode of settling disputes in may arise between them. Or this may be stipulated in a
industry. It was accepted and enunciated more explicitly in submission agreement when they are actually confronted
the Labor Code, which was passed on November 1, 1974 by a dispute. Whatever be the case, such recourse to an
as Presidential Decree No. 442, with the amendments later extrajudicial means of settlement is not intended to
introduced by Republic Act No. 6715 (1989). completely deprive the courts of jurisdiction. In fact, the
early cases on arbitration carefully spelled out the
Whether utilized in business transactions or in employer- prevailing doctrine at the time, thus: ". . . a clause in a
employee relations, arbitration was gaining wide contract providing that all matters in dispute between the
acceptance. A consensual process, it was preferred to parties shall be referred to arbitrators and to them alone is
orders imposed by government upon the disputants. contrary to public policy and cannot oust the courts of
Moreover, court litigations tended to be time-consuming, Jurisdiction." 13
costly, and inflexible due to their scrupulous observance of
the due process of law doctrine and their strict adherence But certainly, the stipulation to refer all future disputes to
to rules of evidence. an arbitrator or to submit an ongoing dispute to one is
valid. Being part of a contract between the parties, it is
As early as the 1920's, this Court declared: binding and enforceable in court in case one of them
In the Philippines fortunately, the attitude of the courts neglects, fails or refuses to arbitrate. Going a step further,
toward arbitration agreements is slowly crystallizing into in the event that they declare their intention to refer their
definite and workable form. . . . The rule now is that unless differences to arbitration first before taking court action,
the agreement is such as absolutely to close the doors of this constitutes a condition precedent, such that where a
the courts against the parties, which agreement would be suit has been instituted prematurely, the court shall
void, the courts will look with favor upon such amicable suspend the same and the parties shall be directed
arrangements and will only with great reluctance interfere forthwith to proceed to arbitration. 14
to anticipate or nullify the action of the arbitrator. 10 A court action may likewise be proven where the arbitrator
That there was a growing need for a law regulating has not been selected by the parties. 15
arbitration in general was acknowledged when Republic Under present law, may the parties who agree to submit
Act No. 876 (1953), otherwise known as the Arbitration their disputes to arbitration further provide that the
Law, was passed. "Said Act was obviously adopted to arbitrators' award shall be final, unappealable and
supplement not to supplant the New Civil Code on executory?
arbitration. It expressly declares that "the provisions of
chapters one and two, Title XIV, Book IV of the Civil Article 2044 of the Civil Code recognizes the validity of
Code shall remain in force." 11 such stipulation, thus:
Any stipulation that the arbitrators' award or decision shall accordance with law or within the scope of his authority?
be final is valid, without prejudice to Articles 2038, 2039 How may the power of judicial review be invoked?
and 2040.
This is where the proper remedy is certiorari under Rule
Similarly, the Construction Industry Arbitration Law 65 of the Revised Rules of Court. It is to be borne in mind,
provides that the arbitral award "shall be final and however, that this action will lie only where a grave abuse
inappealable except on questions of law which shall be of discretion or an act without or in excess of jurisdiction
appealable to the Supreme Court." 16 on the part of the voluntary arbitrator is clearly shown. For
"the writ of certiorari is an extra-ordinary remedy and that
Under the original Labor Code, voluntary arbitration certiorari jurisdiction is not to be equated with appellate
awards or decisions were final, unappealable and jurisdiction. In a special civil action of certiorari, the
executory. "However, voluntary arbitration awards or Court will not engage in a review of the facts found nor
decisions on money claims, involving an amount even of the law as interpreted or applied by the arbitrator
exceeding One Hundred Thousand Pesos (P100,000.00) or unless the supposed errors of fact or of law are so patent
forty-percent (40%) of the paid-up capital of the and gross and prejudicial as to amount to a grave abuse of
respondent employer, whichever is lower, maybe appealed discretion or an exces de pouvoir on the part of the
to the National Labor Relations Commission on any of the arbitrator." 21
following grounds: (a) abuse of discretion; and (b) gross
incompetence." 17 It is to be noted that the appeal in the Even decisions of administrative agencies which are
instances cited were to be made to the National Labor declared "final" by law are not exempt from judicial
Relations Commission and not to the courts. review when so warranted. Thus, in the case of Oceanic
Bic Division (FFW), et al. v. Flerida Ruth P. Romero, et
With the subsequent deletion of the above-cited provision al., 22 this Court had occasion to rule that:
from the Labor Code, the voluntary arbitrator is now
mandated to render an award or decision within twenty . . . Inspite of statutory provisions making "final" the
(20) calendar days from the date of submission of the decisions of certain administrative agencies, we have taken
dispute and such decision shall be final and executory after cognizance of petitions questioning these decisions where
ten (10) calendar days from receipt of the copy of the want of jurisdiction, grave abuse of discretion, violation of
award or decision by the parties. 18 due process, denial of substantial justice or erroneous
interpretation of the lawwere brought to our attention . .
Where the parties agree that the decision of the arbitrator . 23 (Emphasis ours).
shall be final and unappealable as in the instant case, the
pivotal inquiry is whether subject arbitration award is It should be stressed, too, that voluntary arbitrators, by the
indeed beyond the ambit of the court's power of judicial nature of their functions, act in a quasi-judicial
review. capacity. 24 It stands to reason, therefore, that their
decisions should not be beyond the scope of the power of
We rule in the negative. It is stated explicitly under Art. judicial review of this Court.
2044 of the Civil Code that the finality of the arbitrators'
award is not absolute and without exceptions. Where the In the case at bar, petitioners assailed the arbitral award on
conditions described in Articles 2038, 2039 and 2040 the following grounds, most of which allege error on the
applicable to both compromises and arbitrations are part of the arbitrator in granting compensation for various
obtaining, the arbitrators' award may be annulled or items which apparently are disputed by said petitioners:
rescinded. 19 Additionally, under Sections 24 and 25 of the
Arbitration Law, there are grounds for vacating, modifying 1. The Honorable Arbitrator committed grave error in
or rescinding an arbitrator's award. 20 Thus, if and when failing to apply the terms and conditions of the
the factual circumstances referred to in the above-cited Construction Agreement, Dormitory Contract and
provisions are present, judicial review of the award is Electrical Contract, and in using instead the "practices" in
properly warranted. the construction industry;

What if courts refuse or neglect to inquire into the factual


milieu of an arbitrator's award to determine whether it is in
2. The Honorable Arbitrator committed grave error in several items, he exceeded his powers all of which
granting extra compensation to Roblecor for loss of would have constituted ground for vacating the award
productivity due to adverse weather conditions; under Section 24 (d) of the Arbitration Law.

3. The Honorable Arbitrator committed grave error in But the respondent trial court's refusal to look into the
granting extra compensation to Roblecor for loss due to merits of the case, despite prima facie showing of the
delayed payment of progress billings; existence of grounds warranting judicial review,
effectively deprived petitioners of their opportunity to
4. The Honorable Arbitrator committed grave error in prove or substantiate their allegations. In so doing, the trial
granting extra compensation to Roblecor for loss of court itself committed grave abuse of discretion. Likewise,
productivity due to the cement crisis; the appellate court, in not giving due course to the petition,
5. The Honorable Arbitrator committed grave error in committed grave abuse of discretion. Respondent courts
granting extra compensation to Roblecor for losses should not shirk from exercising their power to review,
allegedly sustained on account of the failed coup d'tat; where under the applicable laws and jurisprudence, such
power may be rightfully exercised; more so where the
6. The Honorable Arbitrator committed grave error in objections raised against an arbitration award may
granting to Roblecor the amount representing the alleged properly constitute grounds for annulling, vacating or
unpaid billings of Chung Fu; modifying said award under the laws on arbitration.

7. The Honorable Arbitrator committed grave error in WHEREFORE, the petition is GRANTED. The
granting to Roblecor the amount representing the alleged Resolutions of the Court of Appeals dated October 22,
extended overhead expenses; 1990 and December 3, 1990 as well as the Orders of
respondent Regional Trial Court dated July 31, 1990 and
8. The Honorable Arbitrator committed grave error in August 23, 1990, including the writ of execution issued
granting to Roblecor the amount representing expenses for pursuant thereto, are hereby SET ASIDE. Accordingly,
change order for site development outside the area of this case is REMANDED to the court of origin for further
responsibility of Roblecor; hearing on this matter. All incidents arising therefrom are
reverted to the status quo ante until such time as the trial
9. The Honorable Arbitrator committed grave error in
court shall have passed upon the merits of this case. No
granting to Roblecor the cost of warehouse No. 2;
costs.
10. The Honorable Arbitrator committed grave error in
SO ORDERED.
granting to Roblecor extra compensation for airduct
change in dimension;

11. The Honorable Arbitrator committed grave error in


granting to Roblecor extra compensation for airduct
plastering; and

12. The Honorable Arbitrator committed grave error in


awarding to Roblecor attorney's fees.

After closely studying the list of errors, as well as


petitioners' discussion of the same in their Motion to
Remand Case For Further Hearing and Reconsideration
and Opposition to Motion for Confirmation of Award, we
find that petitioners have amply made out a case where the
voluntary arbitrator failed to apply the terms and
provisions of the Construction Agreement which forms
part of the law applicable as between the parties, thus
committing a grave abuse of discretion. Furthermore, in
granting unjustified extra compensation to respondent for
G.R. No. 143581 January 7, 2008 plant. The monthly rental was PhP 322,560 commencing
on January 1, 1998 with a 10% annual increment clause.
KOREA TECHNOLOGIES CO., LTD., petitioner, Subsequently, the machineries, equipment, and facilities
vs. for the manufacture of LPG cylinders were shipped,
HON. ALBERTO A. LERMA, in his capacity as delivered, and installed in the Carmona plant. PGSMC
Presiding Judge of Branch 256 of Regional Trial Court paid KOGIES USD 1,224,000.
of Muntinlupa City, and PACIFIC GENERAL STEEL
MANUFACTURING CORPORATION, respondents. However, gleaned from the Certificate4 executed by the
parties on January 22, 1998, after the installation of the
DECISION plant, the initial operation could not be conducted as
PGSMC encountered financial difficulties affecting the
VELASCO, JR., J.:
supply of materials, thus forcing the parties to agree that
In our jurisdiction, the policy is to favor alternative KOGIES would be deemed to have completely complied
methods of resolving disputes, particularly in civil and with the terms and conditions of the March 5, 1997
commercial disputes. Arbitration along with mediation, contract.
conciliation, and negotiation, being inexpensive, speedy
For the remaining balance of USD306,000 for the
and less hostile methods have long been favored by this
installation and initial operation of the plant, PGSMC
Court. The petition before us puts at issue an arbitration
clause in a contract mutually agreed upon by the parties issued two postdated checks: (1) BPI Check No. 0316412
stipulating that they would submit themselves to dated January 30, 1998 for PhP 4,500,000; and (2) BPI
arbitration in a foreign country. Regrettably, instead of Check No. 0316413 dated March 30, 1998 for PhP
4,500,000.5
hastening the resolution of their dispute, the parties
wittingly or unwittingly prolonged the controversy. When KOGIES deposited the checks, these were
Petitioner Korea Technologies Co., Ltd. (KOGIES) is a dishonored for the reason "PAYMENT STOPPED." Thus,
on May 8, 1998, KOGIES sent a demand letter6 to
Korean corporation which is engaged in the supply and
installation of Liquefied Petroleum Gas (LPG) Cylinder PGSMC threatening criminal action for violation of Batas
manufacturing plants, while private respondent Pacific Pambansa Blg.22 in case of nonpayment. On the same
General Steel Manufacturing Corp. (PGSMC) is a date, the wife of PGSMCs President faxed a letter dated
domestic corporation. May 7, 1998 to KOGIES President who was then staying
at a Makati City hotel. She complained that not only did
On March 5, 1997, PGSMC and KOGIES executed a KOGIES deliver a different brand of hydraulic press from
Contract1 whereby KOGIES would set up an LPG that agreed upon but it had not delivered several
Cylinder Manufacturing Plant in Carmona, Cavite. The equipment parts already paid for.
contract was executed in the Philippines. On April 7, 1997,
the parties executed, in Korea, an Amendment for Contract On May 14, 1998, PGSMC replied that the two checks it
No. KLP-970301 dated March 5, 19972 amending the issued KOGIES were fully funded but the payments were
terms of payment. The contract and its amendment stopped for reasons previously made known to KOGIES.7
stipulated that KOGIES will ship the machinery and On June 1, 1998, PGSMC informed KOGIES that PGSMC
facilities necessary for manufacturing LPG cylinders for was canceling their Contract dated March 5, 1997 on the
which PGSMC would pay USD 1,224,000. KOGIES ground that KOGIES had altered the quantity and lowered
would install and initiate the operation of the plant for the quality of the machineries and equipment it delivered
which PGSMC bound itself to pay USD 306,000 upon the to PGSMC, and that PGSMC would dismantle and transfer
plants production of the 11-kg. LPG cylinder samples. the machineries, equipment, and facilities installed in the
Thus, the total contract price amounted to USD 1,530,000. Carmona plant. Five days later, PGSMC filed before the
On October 14, 1997, PGSMC entered into a Contract of Office of the Public Prosecutor an Affidavit-Complaint
Lease3 with Worth Properties, Inc. (Worth) for use of for Estafa docketed as I.S. No. 98-03813 against Mr. Dae
Worths 5,079-square meter property with a 4,032-square Hyun Kang, President of KOGIES.
meter warehouse building to house the LPG manufacturing
On June 15, 1998, KOGIES wrote PGSMC informing the 9,000,000 covered by the checks for failing to completely
latter that PGSMC could not unilaterally rescind their install and make the plant operational; and that KOGIES
contract nor dismantle and transfer the machineries and was liable for damages amounting to PhP 4,500,000 for
equipment on mere imagined violations by KOGIES. It altering the quantity and lowering the quality of the
also insisted that their disputes should be settled by machineries and equipment. Moreover, PGSMC averred
arbitration as agreed upon in Article 15, the arbitration that it has already paid PhP 2,257,920 in rent (covering
clause of their contract. January to July 1998) to Worth and it was not willing to
further shoulder the cost of renting the premises of the
On June 23, 1998, PGSMC again wrote KOGIES plant considering that the LPG cylinder manufacturing
reiterating the contents of its June 1, 1998 letter plant never became operational.
threatening that the machineries, equipment, and facilities
installed in the plant would be dismantled and transferred After the parties submitted their Memoranda, on July 23,
on July 4, 1998. Thus, on July 1, 1998, KOGIES instituted 1998, the RTC issued an Order denying the application for
an Application for Arbitration before the Korean a writ of preliminary injunction, reasoning that PGSMC
Commercial Arbitration Board (KCAB) in Seoul, Korea had paid KOGIES USD 1,224,000, the value of the
pursuant to Art. 15 of the Contract as amended. machineries and equipment as shown in the contract such
that KOGIES no longer had proprietary rights over them.
On July 3, 1998, KOGIES filed a Complaint for Specific And finally, the RTC held that Art. 15 of the Contract as
Performance, docketed as Civil Case No. 98-1178 against amended was invalid as it tended to oust the trial court or
PGSMC before the Muntinlupa City Regional Trial Court any other court jurisdiction over any dispute that may arise
(RTC). The RTC granted a temporary restraining order between the parties. KOGIES prayer for an injunctive
(TRO) on July 4, 1998, which was subsequently extended writ was denied.10 The dispositive portion of the Order
until July 22, 1998. In its complaint, KOGIES alleged that stated:
PGSMC had initially admitted that the checks that were
stopped were not funded but later on claimed that it WHEREFORE, in view of the foregoing consideration,
stopped payment of the checks for the reason that "their this Court believes and so holds that no cogent reason
value was not received" as the former allegedly breached exists for this Court to grant the writ of preliminary
their contract by "altering the quantity and lowering the injunction to restrain and refrain defendant from
quality of the machinery and equipment" installed in the dismantling the machineries and facilities at the lot and
plant and failed to make the plant operational although it building of Worth Properties, Incorporated at Carmona,
earlier certified to the contrary as shown in a January 22, Cavite and transfer the same to another site: and therefore
1998 Certificate. Likewise, KOGIES averred that PGSMC denies plaintiffs application for a writ of preliminary
violated Art. 15 of their Contract, as amended, by injunction.
unilaterally rescinding the contract without resorting to
arbitration. KOGIES also asked that PGSMC be restrained On July 29, 1998, KOGIES filed its Reply to Answer and
from dismantling and transferring the machinery and Answer to Counterclaim.11 KOGIES denied it had altered
equipment installed in the plant which the latter threatened the quantity and lowered the quality of the machinery,
to do on July 4, 1998. equipment, and facilities it delivered to the plant. It
claimed that it had performed all the undertakings under
On July 9, 1998, PGSMC filed an opposition to the TRO the contract and had already produced certified samples of
arguing that KOGIES was not entitled to the TRO since LPG cylinders. It averred that whatever was unfinished
Art. 15, the arbitration clause, was null and void for being was PGSMCs fault since it failed to procure raw materials
against public policy as it ousts the local courts of due to lack of funds. KOGIES, relying on Chung Fu
jurisdiction over the instant controversy. Industries (Phils.), Inc. v. Court of Appeals,12 insisted that
the arbitration clause was without question valid.
On July 17, 1998, PGSMC filed its Answer with
Compulsory Counterclaim9 asserting that it had the full After KOGIES filed a Supplemental Memorandum with
right to dismantle and transfer the machineries and Motion to Dismiss13 answering PGSMCs memorandum of
equipment because it had paid for them in full as stipulated July 22, 1998 and seeking dismissal of PGSMCs
in the contract; that KOGIES was not entitled to the PhP counterclaims, KOGIES, on August 4, 1998, filed its
Motion for Reconsideration14 of the July 23, 1998 Order In the meantime, on October 19, 1998, the RTC denied
denying its application for an injunctive writ claiming that KOGIES urgent motion for reconsideration and directed
the contract was not merely for machinery and facilities the Branch Sheriff to proceed with the inspection of the
worth USD 1,224,000 but was for the sale of an "LPG machineries and equipment in the plant on October 28,
manufacturing plant" consisting of "supply of all the 1998.19
machinery and facilities" and "transfer of technology" for a
total contract price of USD 1,530,000 such that the Thereafter, KOGIES filed a Supplement to the Petition20 in
dismantling and transfer of the machinery and facilities CA-G.R. SP No. 49249 informing the CA about the
would result in the dismantling and transfer of the very October 19, 1998 RTC Order. It also reiterated its prayer
plant itself to the great prejudice of KOGIES as the still for the issuance of the writs of prohibition, mandamus and
unpaid owner/seller of the plant. Moreover, KOGIES preliminary injunction which was not acted upon by the
points out that the arbitration clause under Art. 15 of the CA. KOGIES asserted that the Branch Sheriff did not have
Contract as amended was a valid arbitration stipulation the technical expertise to ascertain whether or not the
under Art. 2044 of the Civil Code and as held by this machineries and equipment conformed to the
Court in Chung Fu Industries (Phils.), Inc.15 specifications in the contract and were properly installed.

In the meantime, PGSMC filed a Motion for Inspection of On November 11, 1998, the Branch Sheriff filed his
Things16 to determine whether there was indeed alteration Sheriffs Report21 finding that the enumerated machineries
of the quantity and lowering of quality of the machineries and equipment were not fully and properly installed.
and equipment, and whether these were properly installed.
The Court of Appeals affirmed the trial court and
KOGIES opposed the motion positing that the queries and
declared
issues raised in the motion for inspection fell under the
the arbitration clause against public policy
coverage of the arbitration clause in their contract.
On May 30, 2000, the CA rendered the assailed
On September 21, 1998, the trial court issued an Order (1) Decision22 affirming the RTC Orders and dismissing the
granting PGSMCs motion for inspection; (2) denying
petition for certiorari filed by KOGIES. The CA found that
KOGIES motion for reconsideration of the July 23, 1998 the RTC did not gravely abuse its discretion in issuing the
RTC Order; and (3) denying KOGIES motion to dismiss assailed July 23, 1998 and September 21, 1998 Orders.
PGSMCs compulsory counterclaims as these Moreover, the CA reasoned that KOGIES contention that
counterclaims fell within the requisites of compulsory the total contract price for USD 1,530,000 was for the
counterclaims. whole plant and had not been fully paid was contrary to
On October 2, 1998, KOGIES filed an Urgent Motion for the finding of the RTC that PGSMC fully paid the price of
Reconsideration17 of the September 21, 1998 RTC Order USD 1,224,000, which was for all the machineries and
granting inspection of the plant and denying dismissal of equipment. According to the CA, this determination by the
PGSMCs compulsory counterclaims. RTC was a factual finding beyond the ambit of a petition
for certiorari.
Ten days after, on October 12, 1998, without waiting for
the resolution of its October 2, 1998 urgent motion for On the issue of the validity of the arbitration clause, the
reconsideration, KOGIES filed before the Court of CA agreed with the lower court that an arbitration clause
Appeals (CA) a petition for certiorari18 docketed as CA- which provided for a final determination of the legal rights
G.R. SP No. 49249, seeking annulment of the July 23, of the parties to the contract by arbitration was against
1998 and September 21, 1998 RTC Orders and praying for public policy.
the issuance of writs of prohibition, mandamus, and
On the issue of nonpayment of docket fees and non-
preliminary injunction to enjoin the RTC and PGSMC attachment of a certificate of non-forum shopping by
from inspecting, dismantling, and transferring the PGSMC, the CA held that the counterclaims of PGSMC
machineries and equipment in the Carmona plant, and to were compulsory ones and payment of docket fees was not
direct the RTC to enforce the specific agreement on required since the Answer with counterclaim was not an
arbitration to resolve the dispute. initiatory pleading. For the same reason, the CA said a
certificate of non-forum shopping was also not required.
Furthermore, the CA held that the petition for certiorari f. NOT GRANTING THE RELIEFS AND REMEDIES
had been filed prematurely since KOGIES did not wait for PRAYED FOR IN HE (SIC) PETITION AND,
the resolution of its urgent motion for reconsideration of INSTEAD, DISMISSING THE SAME FOR
the September 21, 1998 RTC Order which was the plain, ALLEGEDLY "WITHOUT MERIT."23
speedy, and adequate remedy available. According to the
CA, the RTC must be given the opportunity to correct any The Courts Ruling
alleged error it has committed, and that since the assailed The petition is partly meritorious.
orders were interlocutory, these cannot be the subject of a
petition for certiorari. Before we delve into the substantive issues, we shall first
tackle the procedural issues.
Hence, we have this Petition for Review on Certiorari
under Rule 45. The rules on the payment of docket fees for
counterclaims
The Issues and cross claims were amended effective August 16,
Petitioner posits that the appellate court committed the 2004
following errors: KOGIES strongly argues that when PGSMC filed the
a. PRONOUNCING THE QUESTION OF OWNERSHIP counterclaims, it should have paid docket fees and filed a
OVER THE MACHINERY AND FACILITIES AS "A certificate of non-forum shopping, and that its failure to do
QUESTION OF FACT" "BEYOND THE AMBIT OF A so was a fatal defect.
PETITION FOR CERTIORARI" INTENDED ONLY We disagree with KOGIES.
FOR CORRECTION OF ERRORS OF JURISDICTION
OR GRAVE ABUSE OF DISCRETION AMOUNTING As aptly ruled by the CA, the counterclaims of PGSMC
TO LACK OF (SIC) EXCESS OF JURISDICTION, AND were incorporated in its Answer with Compulsory
CONCLUDING THAT THE TRIAL COURTS Counterclaim dated July 17, 1998 in accordance with
FINDING ON THE SAME QUESTION WAS Section 8 of Rule 11, 1997 Revised Rules of Civil
IMPROPERLY RAISED IN THE PETITION BELOW; Procedure, the rule that was effective at the time the
Answer with Counterclaim was filed. Sec. 8 on existing
b. DECLARING AS NULL AND VOID THE counterclaim or cross-claim states, "A compulsory
ARBITRATION CLAUSE IN ARTICLE 15 OF THE counterclaim or a cross-claim that a defending party has at
CONTRACT BETWEEN THE PARTIES FOR BEING the time he files his answer shall be contained therein."
"CONTRARY TO PUBLIC POLICY" AND FOR
OUSTING THE COURTS OF JURISDICTION; On July 17, 1998, at the time PGSMC filed its Answer
incorporating its counterclaims against KOGIES, it was
c. DECREEING PRIVATE RESPONDENTS not liable to pay filing fees for said counterclaims being
COUNTERCLAIMS TO BE ALL COMPULSORY NOT
compulsory in nature. We stress, however, that effective
NECESSITATING PAYMENT OF DOCKET FEES AND August 16, 2004 under Sec. 7, Rule 141, as amended by
CERTIFICATION OF NON-FORUM SHOPPING; A.M. No. 04-2-04-SC, docket fees are now required to be
d. RULING THAT THE PETITION WAS FILED paid in compulsory counterclaim or cross-claims.
PREMATURELY WITHOUT WAITING FOR THE As to the failure to submit a certificate of forum shopping,
RESOLUTION OF THE MOTION FOR PGSMCs Answer is not an initiatory pleading which
RECONSIDERATION OF THE ORDER DATED requires a certification against forum shopping under Sec.
SEPTEMBER 21, 1998 OR WITHOUT GIVING THE 524 of Rule 7, 1997 Revised Rules of Civil Procedure. It is
TRIAL COURT AN OPPORTUNITY TO CORRECT
a responsive pleading, hence, the courts a quo did not
ITSELF; commit reversible error in denying KOGIES motion to
e. PROCLAIMING THE TWO ORDERS DATED JULY dismiss PGSMCs compulsory counterclaims.
23 AND SEPTEMBER 21, 1998 NOT TO BE PROPER
Interlocutory orders proper subject of certiorari
SUBJECTS OF CERTIORARI AND PROHIBITION
FOR BEING "INTERLOCUTORY IN NATURE;"
Citing Gamboa v. Cruz,25 the CA also pronounced that While the October 2, 1998 motion for reconsideration of
"certiorari and Prohibition are neither the remedies to KOGIES of the September 21, 1998 RTC Order relating to
question the propriety of an interlocutory order of the trial the inspection of things, and the allowance of the
court."26 The CA erred on its reliance compulsory counterclaims has not yet been resolved, the
on Gamboa. Gamboa involved the denial of a motion to circumstances in this case would allow an exception to the
acquit in a criminal case which was not assailable in an rule that before certiorari may be availed of, the petitioner
action for certiorari since the denial of a motion to quash must have filed a motion for reconsideration and said
required the accused to plead and to continue with the trial, motion should have been first resolved by the court a quo.
and whatever objections the accused had in his motion to The reason behind the rule is "to enable the lower court, in
quash can then be used as part of his defense and the first instance, to pass upon and correct its mistakes
subsequently can be raised as errors on his appeal if the without the intervention of the higher court."30
judgment of the trial court is adverse to him. The general
rule is that interlocutory orders cannot be challenged by an The September 21, 1998 RTC Order directing the branch
appeal.27 Thus, in Yamaoka v. Pescarich Manufacturing sheriff to inspect the plant, equipment, and facilities when
Corporation, we held: he is not competent and knowledgeable on said matters is
evidently flawed and devoid of any legal support.
The proper remedy in such cases is an ordinary appeal Moreover, there is an urgent necessity to resolve the issue
from an adverse judgment on the merits, incorporating in on the dismantling of the facilities and any further delay
said appeal the grounds for assailing the interlocutory would prejudice the interests of KOGIES. Indeed, there is
orders. Allowing appeals from interlocutory orders would real and imminent threat of irreparable destruction or
result in the sorry spectacle of a case being subject of a substantial damage to KOGIES equipment and
counterproductive ping-pong to and from the appellate machineries. We find the resort to certiorari based on the
court as often as a trial court is perceived to have made an gravely abusive orders of the trial court sans the ruling on
error in any of its interlocutory rulings. However, where the October 2, 1998 motion for reconsideration to be
the assailed interlocutory order was issued with grave proper.
abuse of discretion or patently erroneous and the remedy
of appeal would not afford adequate and expeditious relief, The Core Issue: Article 15 of the Contract
the Court allows certiorari as a mode of redress.28 We now go to the core issue of the validity of Art. 15 of
Also, appeals from interlocutory orders would open the the Contract, the arbitration clause. It provides:
floodgates to endless occasions for dilatory motions. Thus, Article 15. Arbitration.All disputes, controversies, or
where the interlocutory order was issued without or in differences which may arise between the parties, out of or
excess of jurisdiction or with grave abuse of discretion, the in relation to or in connection with this Contract or for the
remedy is certiorari.29 breach thereof, shall finally be settled by arbitration in
The alleged grave abuse of discretion of the respondent Seoul, Korea in accordance with the Commercial
court equivalent to lack of jurisdiction in the issuance of Arbitration Rules of the Korean Commercial Arbitration
the two assailed orders coupled with the fact that there is Board. The award rendered by the arbitration(s) shall
no plain, speedy, and adequate remedy in the ordinary be final and binding upon both parties concerned.
course of law amply provides the basis for allowing the (Emphasis supplied.)
resort to a petition for certiorari under Rule 65. Petitioner claims the RTC and the CA erred in ruling that
Prematurity of the petition before the CA the arbitration clause is null and void.

Neither do we think that KOGIES was guilty of forum Petitioner is correct.


shopping in filing the petition for certiorari. Note that Established in this jurisdiction is the rule that the law of
KOGIES motion for reconsideration of the July 23, 1998 the place where the contract is made governs. Lex loci
RTC Order which denied the issuance of the injunctive contractus. The contract in this case was perfected here in
writ had already been denied. Thus, KOGIES only the Philippines. Therefore, our laws ought to govern.
remedy was to assail the RTCs interlocutory order via a Nonetheless, Art. 2044 of the Civil Code sanctions the
petition for certiorari under Rule 65.
validity of mutually agreed arbitral clause or the finality Being an inexpensive, speedy and amicable method of
and binding effect of an arbitral award. Art. 2044 provides, settling disputes, arbitrationalong with mediation,
"Any stipulation that the arbitrators award or decision conciliation and negotiationis encouraged by the
shall be final, is valid, without prejudice to Articles 2038, Supreme Court. Aside from unclogging judicial dockets,
2039 and 2040." (Emphasis supplied.) arbitration also hastens the resolution of disputes,
especially of the commercial kind. It is thus regarded as
Arts. 2038,31 2039,32 and 204033 abovecited refer to the "wave of the future" in international civil and
instances where a compromise or an arbitral award, as commercial disputes. Brushing aside a contractual
applied to Art. 2044 pursuant to Art. 2043,34 may be agreement calling for arbitration between the parties would
voided, rescinded, or annulled, but these would not be a step backward.
denigrate the finality of the arbitral award.
Consistent with the above-mentioned policy of
The arbitration clause was mutually and voluntarily agreed encouraging alternative dispute resolution methods, courts
upon by the parties. It has not been shown to be contrary to should liberally construe arbitration clauses. Provided such
any law, or against morals, good customs, public order, or clause is susceptible of an interpretation that covers the
public policy. There has been no showing that the parties asserted dispute, an order to arbitrate should be granted.
have not dealt with each other on equal footing. We find Any doubt should be resolved in favor of arbitration.40
no reason why the arbitration clause should not be
respected and complied with by both parties. In Gonzales Having said that the instant arbitration clause is not against
v. Climax Mining Ltd.,35 we held that submission to public policy, we come to the question on what governs an
arbitration is a contract and that a clause in a contract arbitration clause specifying that in case of any dispute
providing that all matters in dispute between the parties arising from the contract, an arbitral panel will be
shall be referred to arbitration is a contract.36 Again in Del constituted in a foreign country and the arbitration rules of
Monte Corporation-USA v. Court of Appeals, we likewise the foreign country would govern and its award shall be
ruled that "[t]he provision to submit to arbitration any final and binding.
dispute arising therefrom and the relationship of the parties
is part of that contract and is itself a contract."37 RA 9285 incorporated the UNCITRAL Model law
to which we are a signatory
Arbitration clause not contrary to public policy
For domestic arbitration proceedings, we have particular
The arbitration clause which stipulates that the arbitration agencies to arbitrate disputes arising from contractual
must be done in Seoul, Korea in accordance with the relations. In case a foreign arbitral body is chosen by the
Commercial Arbitration Rules of the KCAB, and that the parties, the arbitration rules of our domestic arbitration
arbitral award is final and binding, is not contrary to public bodies would not be applied. As signatory to the
policy. This Court has sanctioned the validity of arbitration Arbitration Rules of the UNCITRAL Model Law on
clauses in a catena of cases. In the 1957 case of Eastboard International Commercial Arbitration41 of the United
Navigation Ltd. v. Juan Ysmael and Co., Inc.,38 this Court Nations Commission on International Trade Law
had occasion to rule that an arbitration clause to resolve (UNCITRAL) in the New York Convention on June 21,
differences and breaches of mutually agreed contractual 1985, the Philippines committed itself to be bound by the
terms is valid. In BF Corporation v. Court of Appeals, we Model Law. We have even incorporated the Model Law in
held that "[i]n this jurisdiction, arbitration has been held Republic Act No. (RA) 9285, otherwise known as the
valid and constitutional. Even before the approval on June Alternative Dispute Resolution Act of 2004 entitled An Act
19, 1953 of Republic Act No. 876, this Court has to Institutionalize the Use of an Alternative Dispute
countenanced the settlement of disputes through Resolution System in the Philippines and to Establish the
arbitration. Republic Act No. 876 was adopted to Office for Alternative Dispute Resolution, and for Other
supplement the New Civil Codes provisions on Purposes, promulgated on April 2, 2004. Secs. 19 and 20
arbitration."39 And in LM Power Engineering Corporation of Chapter 4 of the Model Law are the pertinent
v. Capitol Industrial Construction Groups, Inc., we provisions:
declared that:
CHAPTER 4 - INTERNATIONAL COMMERCIAL
ARBITRATION
SEC. 19. Adoption of the Model Law on International arbitration unless it finds that the arbitration agreement is
Commercial Arbitration.International commercial null and void, inoperative or incapable of being performed.
arbitration shall be governed by the Model Law on
International Commercial Arbitration (the "Model Law") (2) Foreign arbitral awards must be confirmed by the
adopted by the United Nations Commission on RTC
International Trade Law on June 21, 1985 (United Nations Foreign arbitral awards while mutually stipulated by the
Document A/40/17) and recommended for enactment by parties in the arbitration clause to be final and binding are
the General Assembly in Resolution No. 40/72 approved not immediately enforceable or cannot be implemented
on December 11, 1985, copy of which is hereto attached as
immediately. Sec. 3543 of the UNCITRAL Model Law
Appendix "A". stipulates the requirement for the arbitral award to be
SEC. 20. Interpretation of Model Law.In interpreting the recognized by a competent court for enforcement, which
Model Law, regard shall be had to its international origin court under Sec. 36 of the UNCITRAL Model Law may
and to the need for uniformity in its interpretation and refuse recognition or enforcement on the grounds provided
resort may be made to the travaux preparatoriesand the for. RA 9285 incorporated these provisos to Secs. 42, 43,
report of the Secretary General of the United Nations and 44 relative to Secs. 47 and 48, thus:
Commission on International Trade Law dated March 25, SEC. 42. Application of the New York Convention.The
1985 entitled, "International Commercial Arbitration: New York Convention shall govern the recognition and
Analytical Commentary on Draft Trade identified by enforcement of arbitral awards covered by said
reference number A/CN. 9/264." Convention.
While RA 9285 was passed only in 2004, it nonetheless
The recognition and enforcement of such arbitral awards
applies in the instant case since it is a procedural law shall be filed with the Regional Trial Court in accordance
which has a retroactive effect. Likewise, KOGIES filed its with the rules of procedure to be promulgated by the
application for arbitration before the KCAB on July 1, Supreme Court. Said procedural rules shall provide that
1998 and it is still pending because no arbitral award has
the party relying on the award or applying for its
yet been rendered. Thus, RA 9285 is applicable to the enforcement shall file with the court the original or
instant case. Well-settled is the rule that procedural laws authenticated copy of the award and the arbitration
are construed to be applicable to actions pending and agreement. If the award or agreement is not made in any of
undetermined at the time of their passage, and are deemed the official languages, the party shall supply a duly
retroactive in that sense and to that extent. As a general certified translation thereof into any of such languages.
rule, the retroactive application of procedural laws does
not violate any personal rights because no vested right has The applicant shall establish that the country in which
yet attached nor arisen from them.42 foreign arbitration award was made in party to the New
York Convention.
Among the pertinent features of RA 9285 applying and
incorporating the UNCITRAL Model Law are the xxxx
following:
SEC. 43. Recognition and Enforcement of Foreign
(1) The RTC must refer to arbitration in proper cases Arbitral Awards Not Covered by the New York
Convention.The recognition and enforcement of foreign
Under Sec. 24, the RTC does not have jurisdiction over arbitral awards not covered by the New York Convention
disputes that are properly the subject of arbitration shall be done in accordance with procedural rules to be
pursuant to an arbitration clause, and mandates the referral promulgated by the Supreme Court. The Court may, on
to arbitration in such cases, thus: grounds of comity and reciprocity, recognize and enforce a
SEC. 24. Referral to Arbitration.A court before which non-convention award as a convention award.
an action is brought in a matter which is the subject matter SEC. 44. Foreign Arbitral Award Not Foreign Judgment.
of an arbitration agreement shall, if at least one party so A foreign arbitral award when confirmed by a court of a
requests not later than the pre-trial conference, or upon the foreign country, shall be recognized and enforced as a
request of both parties thereafter, refer the parties to
foreign arbitral award and not as a judgment of a foreign set aside, reject, or vacate a foreign arbitral award on
court. grounds provided under Art. 34(2) of the UNCITRAL
Model Law. Secs. 42 and 45 provide:
A foreign arbitral award, when confirmed by the Regional
Trial Court, shall be enforced in the same manner as final SEC. 42. Application of the New York Convention.The
and executory decisions of courts of law of the Philippines New York Convention shall govern the recognition and
enforcement of arbitral awards covered by said
xxxx Convention.
SEC. 47. Venue and Jurisdiction.Proceedings for The recognition and enforcement of such arbitral awards
recognition and enforcement of an arbitration agreement or shall be filed with the Regional Trial Court in accordance
for vacations, setting aside, correction or modification of with the rules of procedure to be promulgated by the
an arbitral award, and any application with a court for Supreme Court. Said procedural rules shall provide that
arbitration assistance and supervision shall be deemed as the party relying on the award or applying for its
special proceedings and shall be filed with the Regional enforcement shall file with the court the original or
Trial Court (i) where arbitration proceedings are authenticated copy of the award and the arbitration
conducted; (ii) where the asset to be attached or levied agreement. If the award or agreement is not made in any of
upon, or the act to be enjoined is located; (iii) where any of the official languages, the party shall supply a duly
the parties to the dispute resides or has his place of certified translation thereof into any of such languages.
business; or (iv) in the National Judicial Capital Region, at
the option of the applicant. The applicant shall establish that the country in which
foreign arbitration award was made is party to the New
SEC. 48. Notice of Proceeding to Parties.In a special York Convention.
proceeding for recognition and enforcement of an arbitral
award, the Court shall send notice to the parties at their If the application for rejection or suspension of
address of record in the arbitration, or if any part cannot be enforcement of an award has been made, the Regional
served notice at such address, at such partys last known Trial Court may, if it considers it proper, vacate its
address. The notice shall be sent al least fifteen (15) days decision and may also, on the application of the party
before the date set for the initial hearing of the application. claiming recognition or enforcement of the award, order
the party to provide appropriate security.
It is now clear that foreign arbitral awards when confirmed
by the RTC are deemed not as a judgment of a foreign xxxx
court but as a foreign arbitral award, and when confirmed,
are enforced as final and executory decisions of our courts SEC. 45. Rejection of a Foreign Arbitral Award.A party
of law. to a foreign arbitration proceeding may oppose an
application for recognition and enforcement of the arbitral
Thus, it can be gleaned that the concept of a final and award in accordance with the procedures and rules to be
binding arbitral award is similar to judgments or awards promulgated by the Supreme Court only on those grounds
given by some of our quasi-judicial bodies, like the enumerated under Article V of the New York Convention.
National Labor Relations Commission and Mines Any other ground raised shall be disregarded by the
Adjudication Board, whose final judgments are stipulated Regional Trial Court.
to be final and binding, but not immediately executory in
the sense that they may still be judicially reviewed, upon Thus, while the RTC does not have jurisdiction over
the instance of any party. Therefore, the final foreign disputes governed by arbitration mutually agreed upon by
arbitral awards are similarly situated in that they need first the parties, still the foreign arbitral award is subject to
to be confirmed by the RTC. judicial review by the RTC which can set aside, reject, or
vacate it. In this sense, what this Court held in Chung Fu
(3) The RTC has jurisdiction to review foreign arbitral Industries (Phils.), Inc. relied upon by KOGIES is
awards applicable insofar as the foreign arbitral awards, while
final and binding, do not oust courts of jurisdiction since
Sec. 42 in relation to Sec. 45 of RA 9285 designated and these arbitral awards are not absolute and without
vested the RTC with specific authority and jurisdiction to
exceptions as they are still judicially reviewable. Chapter 7 PGSMC has remedies to protect its interests
of RA 9285 has made it clear that all arbitral awards,
whether domestic or foreign, are subject to judicial review Thus, based on the foregoing features of RA 9285,
on specific grounds provided for. PGSMC must submit to the foreign arbitration as it bound
itself through the subject contract. While it may have
(4) Grounds for judicial review different in domestic misgivings on the foreign arbitration done in Korea by the
and foreign arbitral awards KCAB, it has available remedies under RA 9285. Its
interests are duly protected by the law which requires that
The differences between a final arbitral award from an the arbitral award that may be rendered by KCAB must be
international or foreign arbitral tribunal and an award confirmed here by the RTC before it can be enforced.
given by a local arbitral tribunal are the specific grounds or
conditions that vest jurisdiction over our courts to review With our disquisition above, petitioner is correct in its
the awards. contention that an arbitration clause, stipulating that the
arbitral award is final and binding, does not oust our courts
For foreign or international arbitral awards which must of jurisdiction as the international arbitral award, the
first be confirmed by the RTC, the grounds for setting award of which is not absolute and without exceptions, is
aside, rejecting or vacating the award by the RTC are still judicially reviewable under certain conditions
provided under Art. 34(2) of the UNCITRAL Model Law. provided for by the UNCITRAL Model Law on ICA as
For final domestic arbitral awards, which also need applied and incorporated in RA 9285.
confirmation by the RTC pursuant to Sec. 23 of RA Finally, it must be noted that there is nothing in the subject
87644 and shall be recognized as final and executory Contract which provides that the parties may dispense with
decisions of the RTC,45 they may only be assailed before the arbitration clause.
the RTC and vacated on the grounds provided under Sec.
25 of RA 876.46 Unilateral rescission improper and illegal

(5) RTC decision of assailed foreign arbitral award Having ruled that the arbitration clause of the subject
appealable contract is valid and binding on the parties, and not
contrary to public policy; consequently, being bound to the
Sec. 46 of RA 9285 provides for an appeal before the CA contract of arbitration, a party may not unilaterally rescind
as the remedy of an aggrieved party in cases where the or terminate the contract for whatever cause without first
RTC sets aside, rejects, vacates, modifies, or corrects an resorting to arbitration.
arbitral award, thus:
What this Court held in University of the Philippines v. De
SEC. 46. Appeal from Court Decision or Arbitral Los Angeles47 and reiterated in succeeding cases,48 that the
Awards.A decision of the Regional Trial Court act of treating a contract as rescinded on account of
confirming, vacating, setting aside, modifying or infractions by the other contracting party is valid albeit
correcting an arbitral award may be appealed to the Court provisional as it can be judicially assailed, is not applicable
of Appeals in accordance with the rules and procedure to to the instant case on account of a valid stipulation on
be promulgated by the Supreme Court. arbitration. Where an arbitration clause in a contract is
The losing party who appeals from the judgment of the availing, neither of the parties can unilaterally treat the
court confirming an arbitral award shall be required by the contract as rescinded since whatever infractions or
breaches by a party or differences arising from the contract
appellate court to post a counterbond executed in favor of
the prevailing party equal to the amount of the award in must be brought first and resolved by arbitration, and not
accordance with the rules to be promulgated by the through an extrajudicial rescission or judicial action.
Supreme Court. The issues arising from the contract between PGSMC and
Thereafter, the CA decision may further be appealed or KOGIES on whether the equipment and machineries
reviewed before this Court through a petition for review delivered and installed were properly installed and
under Rule 45 of the Rules of Court. operational in the plant in Carmona, Cavite; the ownership
of equipment and payment of the contract price; and
whether there was substantial compliance by KOGIES in Anent the July 23, 1998 Order denying the issuance of the
the production of the samples, given the alleged fact that injunctive writ paving the way for PGSMC to dismantle
PGSMC could not supply the raw materials required to and transfer the equipment and machineries, we find it to
produce the sample LPG cylinders, are matters proper for be in order considering the factual milieu of the instant
arbitration. Indeed, we note that on July 1, 1998, KOGIES case.
instituted an Application for Arbitration before the KCAB
in Seoul, Korea pursuant to Art. 15 of the Contract as Firstly, while the issue of the proper installation of the
amended. Thus, it is incumbent upon PGSMC to abide by equipment and machineries might well be under the
its commitment to arbitrate. primary jurisdiction of the arbitral body to decide, yet the
RTC under Sec. 28 of RA 9285 has jurisdiction to hear and
Corollarily, the trial court gravely abused its discretion in grant interim measures to protect vested rights of the
granting PGSMCs Motion for Inspection of Things on parties. Sec. 28 pertinently provides:
September 21, 1998, as the subject matter of the motion is
under the primary jurisdiction of the mutually agreed SEC. 28. Grant of interim Measure of Protection.(a) It
arbitral body, the KCAB in Korea. is not incompatible with an arbitration agreement for a
party to request, before constitution of the tribunal,
In addition, whatever findings and conclusions made by from a Court to grant such measure. After constitution
the RTC Branch Sheriff from the inspection made on of the arbitral tribunal and during arbitral proceedings, a
October 28, 1998, as ordered by the trial court on October request for an interim measure of protection, or
19, 1998, is of no worth as said Sheriff is not technically modification thereof, may be made with the arbitral or to
competent to ascertain the actual status of the equipment the extent that the arbitral tribunal has no power to act
and machineries as installed in the plant. or is unable to act effectivity, the request may be made
with the Court. The arbitral tribunal is deemed
For these reasons, the September 21, 1998 and October 19, constituted when the sole arbitrator or the third arbitrator,
1998 RTC Orders pertaining to the grant of the inspection who has been nominated, has accepted the nomination and
of the equipment and machineries have to be recalled and written communication of said nomination and acceptance
nullified. has been received by the party making the request.
Issue on ownership of plant proper for arbitration (b) The following rules on interim or provisional relief
Petitioner assails the CA ruling that the issue petitioner shall be observed:
raised on whether the total contract price of USD Any party may request that provisional relief be granted
1,530,000 was for the whole plant and its installation is against the adverse party.
beyond the ambit of a Petition for Certiorari.
Such relief may be granted:
Petitioners position is untenable.
(i) to prevent irreparable loss or injury;
It is settled that questions of fact cannot be raised in an
original action for certiorari.49 Whether or not there was (ii) to provide security for the performance of any
full payment for the machineries and equipment and obligation;
installation is indeed a factual issue prohibited by Rule 65.
(iii) to produce or preserve any evidence; or
However, what appears to constitute a grave abuse of
discretion is the order of the RTC in resolving the issue on (iv) to compel any other appropriate act or omission.
the ownership of the plant when it is the arbitral body (c) The order granting provisional relief may be
(KCAB) and not the RTC which has jurisdiction and conditioned upon the provision of security or any act or
authority over the said issue. The RTCs determination of omission specified in the order.
such factual issue constitutes grave abuse of discretion and
must be reversed and set aside. (d) Interim or provisional relief is requested by written
application transmitted by reasonable means to the Court
RTC has interim jurisdiction to protect the rights of or arbitral tribunal as the case may be and the party against
the parties whom the relief is sought, describing in appropriate detail
the precise relief, the party against whom the relief is in consideration of the specific features of international
requested, the grounds for the relief, and the evidence arbitration.
supporting the request.
In the recent 2006 case of Transfield Philippines, Inc. v.
(e) The order shall be binding upon the parties. Luzon Hydro Corporation, we were explicit that even "the
pendency of an arbitral proceeding does not foreclose
(f) Either party may apply with the Court for assistance in resort to the courts for provisional reliefs." We explicated
implementing or enforcing an interim measure ordered by this way:
an arbitral tribunal.
As a fundamental point, the pendency of arbitral
(g) A party who does not comply with the order shall be proceedings does not foreclose resort to the courts for
liable for all damages resulting from noncompliance, provisional reliefs. The Rules of the ICC, which governs
including all expenses, and reasonable attorney's fees, paid the parties arbitral dispute, allows the application of a
in obtaining the orders judicial enforcement. (Emphasis party to a judicial authority for interim or conservatory
ours.) measures. Likewise, Section 14 of Republic Act (R.A.)
Art. 17(2) of the UNCITRAL Model Law on ICA defines No. 876 (The Arbitration Law) recognizes the rights of any
party to petition the court to take measures to safeguard
an "interim measure" of protection as:
and/or conserve any matter which is the subject of the
Article 17. Power of arbitral tribunal to order interim dispute in arbitration. In addition, R.A. 9285, otherwise
measures known as the "Alternative Dispute Resolution Act of
2004," allows the filing of provisional or interim measures
xxx xxx xxx with the regular courts whenever the arbitral tribunal has
no power to act or to act effectively.50
(2) An interim measure is any temporary measure,
whether in the form of an award or in another form, by It is thus beyond cavil that the RTC has authority and
which, at any time prior to the issuance of the award by jurisdiction to grant interim measures of protection.
which the dispute is finally decided, the arbitral tribunal
orders a party to: Secondly, considering that the equipment and machineries
are in the possession of PGSMC, it has the right to protect
(a) Maintain or restore the status quo pending and preserve the equipment and machineries in the best
determination of the dispute; way it can. Considering that the LPG plant was non-
operational, PGSMC has the right to dismantle and
(b) Take action that would prevent, or refrain from taking
transfer the equipment and machineries either for their
action that is likely to cause, current or imminent harm or
protection and preservation or for the better way to make
prejudice to the arbitral process itself;
good use of them which is ineluctably within the
(c) Provide a means of preserving assets out of which a management discretion of PGSMC.
subsequent award may be satisfied; or
Thirdly, and of greater import is the reason that
(d) Preserve evidence that may be relevant and material to maintaining the equipment and machineries in Worths
the resolution of the dispute. property is not to the best interest of PGSMC due to the
prohibitive rent while the LPG plant as set-up is not
Art. 17 J of UNCITRAL Model Law on ICA also grants operational. PGSMC was losing PhP322,560 as monthly
courts power and jurisdiction to issue interim measures: rentals or PhP3.87M for 1998 alone without considering
the 10% annual rent increment in maintaining the plant.
Article 17 J. Court-ordered interim measures
Fourthly, and corollarily, while the KCAB can rule on
A court shall have the same power of issuing an interim
motions or petitions relating to the preservation or transfer
measure in relation to arbitration proceedings, irrespective
of the equipment and machineries as an interim measure,
of whether their place is in the territory of this State, as it
yet on hindsight, the July 23, 1998 Order of the RTC
has in relation to proceedings in courts. The court shall
allowing the transfer of the equipment and machineries
exercise such power in accordance with its own procedures
given the non-recognition by the lower courts of the
arbitral clause, has accorded an interim measure of
protection to PGSMC which would otherwise been
irreparably damaged.

Fifth, KOGIES is not unjustly prejudiced as it has already


been paid a substantial amount based on the contract.
Moreover, KOGIES is amply protected by the arbitral
action it has instituted before the KCAB, the award of
which can be enforced in our jurisdiction through the RTC.
Besides, by our decision, PGSMC is compelled to submit
to arbitration pursuant to the valid arbitration clause of its
contract with KOGIES.

PGSMC to preserve the subject equipment and


machineries

Finally, while PGSMC may have been granted the right to


dismantle and transfer the subject equipment and
machineries, it does not have the right to convey or
dispose of the same considering the pending arbitral
proceedings to settle the differences of the parties.
PGSMC therefore must preserve and maintain the subject
equipment and machineries with the diligence of a good
father of a family51 until final resolution of the arbitral
proceedings and enforcement of the award, if any.

WHEREFORE, this petition is PARTLY GRANTED, in


that:

(1) The May 30, 2000 CA Decision in CA-G.R. SP No.


49249 is REVERSED and SET ASIDE;

(2) The September 21, 1998 and October 19, 1998 RTC
Orders in Civil Case No. 98-117
are REVERSED and SET ASIDE;

(3) The parties are hereby ORDERED to submit


themselves to the arbitration of their dispute and
differences arising from the subject Contract before the
KCAB; and

(4) PGSMC is hereby ALLOWED to dismantle and


transfer the equipment and machineries, if it had not done
so, and ORDERED to preserve and maintain them until
the finality of whatever arbitral award is given in the
arbitration proceedings.

No pronouncement as to costs.

SO ORDERED.
G.R. No. 141833 March 26, 2003 Because of the dispute, petitioner filed with the Regional
Trial Court (RTC) of Makati (Branch 141) a
LM POWER ENGINEERING Complaint10 for the collection of the amount representing
CORPORATION, petitioner, the alleged balance due it under the Subcontract. Instead of
vs. submitting an Answer, respondent filed a Motion to
CAPITOL INDUSTRIAL CONSTRUCTION Dismiss,11 alleging that the Complaint was premature,
GROUPS, INC., respondent. because there was no prior recourse to arbitration.
PANGANIBAN, J.: In its Order12 dated September 15, 1987, the RTC denied
Alternative dispute resolution methods or ADRs -- like the Motion on the ground that the dispute did not involve
arbitration, mediation, negotiation and conciliation -- are the interpretation or the implementation of the Agreement
encouraged by the Supreme Court. By enabling parties to and was, therefore, not covered by the arbitral clause.13
resolve their disputes amicably, they provide solutions that After trial on the merits, the RTC14 ruled that the take-over
are less time-consuming, less tedious, less confrontational, of some work items by respondent was not equivalent to a
and more productive of goodwill and lasting relationships.1 termination, but a mere modification, of the Subcontract.
The latter was ordered to give full payment for the work
The Case
completed by petitioner.
Before us is a Petition for Review on Certiorari2 under
Rule 45 of the Rules of Court, seeking to set aside the Ruling of the Court of Appeals
January 28, 2000 Decision of the Court of Appeals3 (CA) On appeal, the CA reversed the RTC and ordered the
in CA-GR CV No. 54232. The dispositive portion of the referral of the case to arbitration. The appellate court held
Decision reads as follows: as arbitrable the issue of whether respondents take-over of
"WHEREFORE, the judgment appealed from is some work items had been intended to be a termination of
REVERSED and SET ASIDE. The parties are ORDERED the original contract under Letter "K" of the Subcontract. It
to present their dispute to arbitration in accordance with ruled likewise on two other issues: whether petitioner was
their Sub-contract Agreement. The surety bond posted by liable under the warranty clause of the Agreement, and
[respondent] is [d]ischarged."4 whether it should reimburse respondent for the work the
latter had taken over.15
The Facts
Hence, this Petition.16
On February 22, 1983, Petitioner LM Power Engineering
Corporation and Respondent Capitol Industrial The Issues
Construction Groups Inc. entered into a "Subcontract In its Memorandum, petitioner raises the following issues
Agreement" involving electrical work at the Third Port of for the Courts consideration:
Zamboanga.5
"A
On April 25, 1985, respondent took over some of the work
contracted to petitioner.6 Allegedly, the latter had failed to Whether or not there exist[s] a controversy/dispute
finish it because of its inability to procure materials.7 between petitioner and respondent regarding the
interpretation and implementation of the Sub-Contract
Upon completing its task under the Contract, petitioner Agreement dated February 22, 1983 that requires prior
billed respondent in the amount of recourse to voluntary arbitration;
P6,711,813.90.8Contesting the accuracy of the amount of
advances and billable accomplishments listed by the "B
former, the latter refused to pay. Respondent also took
refuge in the termination clause of the Agreement.9 That In the affirmative, whether or not the requirements
clause allowed it to set off the cost of the work that provided in Article III 1 of CIAC Arbitration Rules
petitioner had failed to undertake -- due to termination or regarding request for arbitration ha[ve] been complied
take-over -- against the amount it owed the latter. with[.]"17
The Courts Ruling it owed petitioner? (3) How much were the advances and
billable accomplishments?
The Petition is unmeritorious.
The resolution of the foregoing issues lies in the
First Issue: interpretation of the provisions of the Agreement.
Whether Dispute Is Arbitrable According to respondent, the take-over was caused by
Petitioner claims that there is no conflict regarding the petitioners delay in completing the work. Such delay was
interpretation or the implementation of the Agreement. in violation of the provision in the Agreement as to time
Thus, without having to resort to prior arbitration, it is schedule:
entitled to collect the value of the services it rendered "G. TIME SCHEDULE
through an ordinary action for the collection of a sum of
money from respondent. On the other hand, the latter "[Petitioner] shall adhere strictly to the schedule related to
contends that there is a need for prior arbitration as the WORK and complete the WORK within the period set
provided in the Agreement. This is because there are some forth in Annex C hereof. NO time extension shall be
disparities between the parties positions regarding the granted by [respondent] to [petitioner] unless a
extent of the work done, the amount of advances and corresponding time extension is granted by [the Ministry
billable accomplishments, and the set off of expenses of Public Works and Highways] to the CONSORTIUM."20
incurred by respondent in its take-over of petitioners
work. Because of the delay, respondent alleges that it took over
some of the work contracted to petitioner, pursuant to the
We side with respondent. Essentially, the dispute arose following provision in the Agreement:
from the parties ncongruent positions on whether certain
provisions of their Agreement could be applied to the "K. TERMINATION OF AGREEMENT
facts. The instant case involves technical discrepancies that "[Respondent] has the right to terminate and/or take
are better left to an arbitral body that has expertise in those over this Agreement for any of the following causes:
areas. In any event, the inclusion of an arbitration clause in
a contract does not ipso facto divest the courts of xxx xxx xxx
jurisdiction to pass upon the findings of arbitral bodies,
because the awards are still judicially reviewable under 6. If despite previous warnings by [respondent],
certain conditions.18 [petitioner] does not execute the WORK in accordance
with this Agreement, or persistently or flagrantly neglects
In the case before us, the Subcontract has the following to carry out [its] obligations under this Agreement."21
arbitral clause:
Supposedly, as a result of the "take-over," respondent
"6. The Parties hereto agree that any dispute or conflict as incurred expenses in excess of the contracted price. It
regards to interpretation and implementation of this sought to set off those expenses against the amount
Agreement which cannot be settled between [respondent] claimed by petitioner for the work the latter accomplished,
and [petitioner] amicably shall be settled by means of pursuant to the following provision:
arbitration x x x."19
"If the total direct and indirect cost of completing the
Clearly, the resolution of the dispute between the parties remaining part of the WORK exceed the sum which would
herein requires a referral to the provisions of their have been payable to [petitioner] had it completed the
Agreement. Within the scope of the arbitration clause are WORK, the amount of such excess [may be] claimed by
discrepancies as to the amount of advances and billable [respondent] from either of the following:
accomplishments, the application of the provision on
termination, and the consequent set-off of expenses. 1. Any amount due [petitioner] from [respondent] at the
time of the termination of this Agreement."22
A review of the factual allegations of the parties reveals
that they differ on the following questions: (1) Did a take- The issue as to the correct amount of petitioners advances
over/termination occur? (2) May the expenses incurred by and billable accomplishments involves an evaluation of the
respondent in the take-over be set off against the amounts manner in which the parties completed the work, the extent
to which they did it, and the expenses each of them Being an inexpensive, speedy and amicable method of
incurred in connection therewith. Arbitrators also need to settling disputes,24 arbitration -- along with mediation,
look into the computation of foreign and local costs of conciliation and negotiation -- is encouraged by the
materials, foreign and local advances, retention fees and Supreme Court. Aside from unclogging judicial dockets,
letters of credit, and taxes and duties as set forth in the arbitration also hastens the resolution of disputes,
Agreement. These data can be gathered from a review of especially of the commercial kind.25 It is thus regarded as
the Agreement, pertinent portions of which are reproduced the "wave of the future" in international civil and
hereunder: commercial disputes.26 Brushing aside a contractual
agreement calling for arbitration between the parties would
"C. CONTRACT PRICE AND TERMS OF PAYMENT be a step backward.27
xxx xxx xxx Consistent with the above-mentioned policy of
"All progress payments to be made by [respondent] to encouraging alternative dispute resolution methods, courts
[petitioner] shall be subject to a retention sum of ten should liberally construe arbitration clauses. Provided such
percent (10%) of the value of the approved quantities. Any clause is susceptible of an interpretation that covers the
claims by [respondent] on [petitioner] may be deducted by asserted dispute, an order to arbitrate should be
[respondent] from the progress payments and/or retained granted.28 Any doubt should be resolved in favor of
amount. Any excess from the retained amount after arbitration.29
deducting [respondents] claims shall be released by Second Issue:
[respondent] to [petitioner] after the issuance of [the Prior Request for Arbitration
Ministry of Public Works and Highways] of the Certificate
of Completion and final acceptance of the WORK by [the According to petitioner, assuming arguendo that the
Ministry of Public Works and Highways]. dispute is arbitrable, the failure to file a formal request for
arbitration with the Construction Industry Arbitration
xxx xxx xxx Commission (CIAC) precluded the latter from acquiring
"D. IMPORTED MATERIALS AND EQUIPMENT jurisdiction over the question. To bolster its position,
petitioner even cites our ruling in Tesco Services
"[Respondent shall open the letters of credit for the Incorporated v. Vera.30 We are not persuaded.
importation of equipment and materials listed in Annex E
hereof after the drawings, brochures, and other technical Section 1 of Article II of the old Rules of Procedure
data of each items in the list have been formally approved Governing Construction Arbitration indeed required the
by [the Ministry of Public Works and Highways]. submission of a request for arbitration, as follows:
However, petitioner will still be fully responsible for all "SECTION. 1. Submission to Arbitration -- Any party to a
imported materials and equipment. construction contract wishing to have recourse to
"All expenses incurred by [respondent], both in foreign arbitration by the Construction Industry Arbitration
and local currencies in connection with the opening of the Commission (CIAC) shall submit its Request for
Arbitration in sufficient copies to the Secretariat of the
letters of credit shall be deducted from the Contract Prices.
CIAC; PROVIDED, that in the case of government
xxx xxx xxx construction contracts, all administrative remedies
available to the parties must have been exhausted within
"N. OTHER CONDITIONS 90 days from the time the dispute arose."
xxx xxx xxx Tesco was promulgated by this Court, using the foregoing
provision as reference.
"2. All customs duties, import duties, contractors taxes,
income taxes, and other taxes that may be required by any On the other hand, Section 1 of Article III of the new
government agencies in connection with this Agreement Rules of Procedure Governing Construction Arbitration
shall be for the sole account of [petitioner]."23 has dispensed with this requirement and recourse to the
CIAC may now be availed of whenever a contract
"contains a clause for the submission of a future covers the dispute between the parties in the present case,
controversy to arbitration," in this wise: either of them may compel the other to arbitrate.36

"SECTION 1. Submission to CIAC Jurisdiction An Since petitioner has already filed a Complaint with the
arbitration clause in a construction contract or a RTC without prior recourse to arbitration, the proper
submission to arbitration of a construction dispute shall be procedure to enable the CIAC to decide on the dispute is to
deemed an agreement to submit an existing or future request the stay or suspension of such action, as provided
controversy to CIAC jurisdiction, notwithstanding the under RA 876 [the Arbitration Law].37
reference to a different arbitration institution or arbitral
body in such contract or submission. When a contract WHEREFORE, the Petition is DENIED and the assailed
contains a clause for the submission of a future Decision AFFIRMED. Costs against petitioner.
controversy to arbitration, it is not necessary for the parties SO ORDERED.
to enter into a submission agreement before the claimant
may invoke the jurisdiction of CIAC."

The foregoing amendments in the Rules were formalized


by CIAC Resolution Nos. 2-91 and 3-93.31

The difference in the two provisions was clearly explained


in China Chang Jiang Energy Corporation (Philippines) v.
Rosal Infrastructure Builders et al.32 (an extended
unsigned Resolution) and reiterated in National Irrigation
Administration v. Court of Appeals,33 from which we quote
thus:

"Under the present Rules of Procedure, for a particular


construction contract to fall within the jurisdiction of
CIAC, it is merely required that the parties agree to submit
the same to voluntary arbitration Unlike in the original
version of Section 1, as applied in the Tesco case, the law
as it now stands does not provide that the parties should
agree to submit disputes arising from their agreement
specifically to the CIAC for the latter to acquire
jurisdiction over the same. Rather, it is plain and clear that
as long as the parties agree to submit to voluntary
arbitration, regardless of what forum they may choose,
their agreement will fall within the jurisdiction of the
CIAC, such that, even if they specifically choose another
forum, the parties will not be precluded from electing to
submit their dispute before the CIAC because this right has
been vested upon each party by law, i.e., E.O. No. 1008."34

Clearly, there is no more need to file a request with the


CIAC in order to vest it with jurisdiction to decide a
construction dispute.

The arbitral clause in the Agreement is a commitment on


the part of the parties to submit to arbitration the disputes
covered therein. Because that clause is binding, they are
expected to abide by it in good faith.35 And because it

You might also like