VALORIZACION N 02 DE AVANCE DE OBRA

PERIODO DEL 03 AL 31 DE JULIO

OBRA "CREACION DEL SERVICIO DE TRANSITABILIDAD DEL CAMINO VECINAL TRAMOS: VISTA ALEGRE-SAN JUAN DE MANTARO,
LLACTAPATA-02 DE MAYO, CCOCHAPATA-LAGUNA ALLCCACCOCHA, CCOCHAPATA-POTRERO, MAYUNMARCA-CURVA
HUECCUNTUYUCC, MUTUYPUCRU-TUPACANCHA, DISTRITO DE ANDAB
EJECUTA MUNICIPALIDAD DISTRITAL DE ANDABAMBA
RESIDENTE ING. LUIS A. MERINO LIZANA FECHA DE PRESENTACION : 8/7/2017
INSPECTOR ING. ROMEL E. SANCHEZ CHOQUE PLAZO DE EJECUCION : 60 dias calendarios

VALORIZACION
ITEM DESCRIPCION TOTAL SALDO
ANTERIOR ACTUAL ACUMULADO
01 TRAMO01:VISTA ALEGRE - S.J. MANTARO 202,897.13 0.00 169,898.40 169,898.40 32,998.73
02 TRAMO 02:LLACCTAPATA . DOS DE MAYO 52,129.36 0.00 34,429.96 34,429.96 17,699.39
03 TRAMO 03:CCOCHAPATA - LAGUNA ALLCC 95,684.28 74,172.16 0.00 74,172.16 21,512.11
04 TRAMO 04:CCOCHAPATA - POTRERO 33,863.62 18,047.10 0.00 18,047.10 15,816.51
05 TRAMO 05:MAYUNMARCA - CURVA HUECC 129,911.11 0.00 111,941.87 111,941.87 17,969.24
06 TRAMO 06:MUTUYPUCRU - TUPACANCHA 158,853.79 81,738.07 0.00 81,738.07 77,115.72
07 GASTOS GENERALES 50,500.45 13,046.80 23,720.27 36,767.07 13,733.38
08 PRESUPUESTO TOTAL 723,839.74 187,004.13 339,990.50 526,994.63 196,845.08
09 % AVANCE FISICO 100.00% 25.84% 46.97% 72.81% 27.19%
VALORIZACION N 03 DE AVANCE DE OBRA
PERIODO DEL 03 AL 31 DE JULIO
11/19/2017
OBRA "CREACION DEL SERVICIO DE TRANSITABILIDAD DEL CAMINO VECINAL TRAMOS: VISTA ALEGRE-SAN JUAN DE MANTARO, LLACTAPATA-02 DE MAYO, FECHA DE PRESENTACION : 8/7/2017
CCOCHAPATA-LAGUNA ALLCCACCOCHA, CCOCHAPATA-POTRERO, MAYUNMARCA-CURVA HUECCUNTUYUCC, MUTUYPUCRU-TUPACANCHA, DISTRITO DE
ANDAB PLAZO DE EJECUCION : 60 dias calendarios
EJECUTA MUNICIPALIDAD DISTRITAL DE ANDABAMBA
RESIDENTE ING. LUIS A. MERINO LIZANA
INSPECTOR ING. ROMEL E. SANCHEZ CHOQUE

VALORIZACIN
SALDO
ITEM DESCRIPCION UND. MET. P.U. PARCIAL ANTERIOR ACTUAL ACUMULADO
MET. VAL. % MET. VAL. % MET. VAL. % MET. VAL. %
01 TRAMO01:VISTA ALEGRE - S.J. MANTARO 202,897.13
01.01 OBRAS PROVISIONALES 580.00
01.01.01 CARTEL DE IDENTIFICACION PARA LA OBRA GLB 1.00 580.00 580.00 - - 0.00% 1.00 580.00 100.00% 1.00 580.00 100.00% - - 0.00%
01.02 OBRAS PRELIMINARES 4,185.44
01.02.01 TRAZO Y REPLANTEO EN CARRETERA KM 6.22 672.90 4,185.44 - - 0.00% 5.55 3,734.60 89.23% 5.55 3,734.60 89.23% 0.67 450.84 10.77%
01.03 MOVIMIENTO DE TIERRAS 198,131.69
01.03.01 EXCAVACION EN EXPLANACIONES EN MATERIAL SUELTO m3 59,678.22 3.32 198,131.69 - - 0.00% 49,874.64 165,583.80 83.57% 49,874.64 165,583.80 83.57% 9,803.58 32,547.89 16.43%
02 TRAMO 02:LLACCTAPATA . DOS DE MAYO 52,129.36
02.01 OBRAS PRELIMINARES 1,110.29
02.01.01 TRAZO Y REPLANTEO EN CARRETERA KM 1.65 672.90 1,110.29 - - 0.00% 1.28 861.31 77.58% 1.28 861.31 77.58% 0.37 248.97 22.42%
02.02 MOVIMIENTO DE TIERRAS 51,019.07
02.02.01 EXCAVACION EN EXPLANACIONES EN MATERIAL SUELTO m3 15,367.19 3.32 51,019.07 - - 0.00% 10,111.04 33,568.65 65.80% 10,111.04 33,568.65 65.80% 5,256.15 17,450.42 34.20%
03 TRAMO 03:CCOCHAPATA - LAGUNA ALLCCACCOCHA 95,684.28
03.01 OBRAS PRELIMINARES 1,971.60
03.01.01 TRAZO Y REPLANTEO EN CARRETERA KM 2.93 672.90 1,971.60 2.31 1,554.40 78.84% - - 0.00% 2.31 1,554.40 78.84% 0.62 417.20 21.16%
03.02 MOVIMIENTO DE TIERRAS 93,712.68
03.02.01 EXCAVACION EN EXPLANACIONES EN MATERIAL SUELTO m3 28,226.71 3.32 93,712.68 21,872.82 72,617.76 77.49% - - 0.00% 21,872.82 72,617.76 77.49% 6,353.89 21,094.91 22.51%
04 TRAMO 04:CCOCHAPATA - POTRERO 33,863.62
04.01 OBRAS PRELIMINARES 962.25
04.01.01 TRAZO Y REPLANTEO EN CARRETERA KM 1.43 672.90 962.25 0.96 645.98 67.13% - - 0.00% 0.96 645.98 67.13% 0.47 316.26 32.87%
04.02 MOVIMIENTO DE TIERRAS 32,901.37
04.02.01 EXCAVACION EN EXPLANACIONES EN MATERIAL SUELTO m3 9,910.05 3.32 32,901.37 5,241.30 17,401.12 52.89% - - 0.00% 5,241.30 17,401.12 52.89% 4,668.75 15,500.25 47.11%
05 TRAMO 05:MAYUNMARCA - CURVA HUECCUNTUYUCC 129,911.11
05.01 OBRAS PRELIMINARES 2,186.93
05.01.01 TRAZO Y REPLANTEO EN CARRETERA KM 3.25 672.90 2,186.93 - - 0.00% 2.85 1,917.77 87.69% 2.85 1,917.77 87.69% 0.40 269.16 12.31%
05.02 MOVIMIENTO DE TIERRAS 127,724.18
05.02.01 EXCAVACION EN EXPLANACIONES EN MATERIAL SUELTO m3 38,471.14 3.32 127,724.18 - - 0.00% 33,139.79 110,024.10 86.14% 33,139.79 110,024.10 86.14% 5,331.35 17,700.08 13.86%
06 TRAMO 06:MUTUYPUCRU - TUPACANCHA 158,853.79
06.01 OBRAS PRELIMINARES 4,158.52
06.01.01 TRAZO Y REPLANTEO EN CARRETERA KM 6.18 672.90 4,158.52 3.16 2,126.36 51.13% - - 0.00% 3.16 2,126.36 51.13% 3.02 2,032.16 48.87%
06.02 MOVIMIENTO DE TIERRAS 154,695.27
06.02.01 EXCAVACION EN EXPLANACIONES EN MATERIAL SUELTO m3 46,594.96 3.32 154,695.27 23,979.43 79,611.71 51.46% - - 0.00% 23,979.43 79,611.71 51.46% 22,615.53 75,083.56 48.54%
COSTO DIRECTO 673,339.29 173,957.33 316,270.23 490,227.57 183,111.71
GASTOS GENERALES 7.50% 50,500.45 13,046.80 23,720.27 36,767.07 13,733.38
COSTO DE OBRA 723,839.74 187,004.13 339,990.50 526,994.63 196,845.08
AVANCE % 100.00% 25.84% 46.97% 72.81% 27.19%