You are on page 1of 20

Central Irrigation Development Division No.

1, Mahottari
Earth Work Calculation Sheet

Name of the project :- Aurahi Irrigation Project


Name of the Canal :-Main canal
Chainage Cutting Filling Length Cut Volume Fill Volume Balance Total Cut Volume
Area m Av. Area m2 Area m Av. Area (m) Cu. M. Cu. M. Volume Cu. M.
0+000 3.33 0.53
0+500 0.00 1.67 1.43 0.98 500.00 832.50 490.00 0.00 832.50
1+000 0.98 0.49 0.14 0.79 500.00 245.00 392.50 147.50 392.50
1+500 0.83 0.91 0.51 0.33 500.00 452.50 162.50 0.00 452.50
2+000 0.00 0.42 0.53 0.52 500.00 207.50 260.00 52.50 260.00
2+500 1.56 0.78 0.16 0.35 500.00 390.00 172.50 0.00 390.00
3+000 1.57 1.57 0.39 0.28 500.00 782.50 137.50 0.00 782.50
3+500 0.00 0.79 4.99 2.69 500.00 392.50 1345.00 952.50 1345.00
4+000 1.10 0.55 0.53 2.76 500.00 275.00 1380.00 1105.00 1380.00
4+500 0.38 0.74 0.45 0.49 500.00 370.00 245.00 0.00 370.00
TOTAL 3947.50 4585.00 2257.50 6205.00
Central Irrigation Development Division No. 1, Mahottari
1. DETAILED ESTIMATE OF SIDE INTAKE

S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earth work in excavation
For foundation in ordinary soil, U/S 2 7.45 1.50 1.75 39.11 m
U/S 1 4.25 4.00 1.75 29.75 m
D/S 1 8.90 3.00 1.75 46.73 m
For gabion foundation (launching) U/S 1 12.50 6.00 0.50 37.50 m
D/S 1 6.10 3.00 0.50 9.15 m
Total 162.24 162.24 m
2 Earthwork for backfilling (1/3 of
excavation) 54.08 54.08 m

3 PCC (1:3:6),
Base (with return), U/S 2 7.45 1.5 0.6 13.41 m
1 4.25 3.00 0.60 7.65 m
D/S (with return) 1 8.90 2.00 0.60 10.68 m
U/S Floor 1 3.00 2.73 0.40 3.28 m3 , B = (4.46+1)/2=2.73
1 3.25 1.00 0.50 1.63 m3 , H = (0.6+0.4)/2=0.5
Triangular portion 0.5 1.00 0.15 0.15 0.01 m
Crest 1 1.00 0.75 0.55 0.41 m
Glacis 1 3.00 1.00 0.50 1.50 m3 , H = (0.6+0.4)/2=0.5
D/S Floor 5 5.00 1.00 0.50 12.50 m3 H = (0.6+0.4)/2=0.5
U/S Cutoff 1 4.46 0.40 1.00 1.78 m
D/S Cutoff 1 1.00 0.40 1.00 0.40 m
Triangular portion 0.5 1.00 0.40 0.30 0.06 m
U/S Wall 2 11.70 0.85 2.10 41.77 m3 B = (0.4+1.3)/2=0.85
D/S Wall 2 8.90 0.55 1.40 13.71 m3 B = (0.3+0.8)/2=0.55
Step 1 0.95 0.30 0.30 0.09 m
1 0.95 0.30 0.60 0.17 m
1 0.95 0.30 0.90 0.26 m
SubTotal 109.30 108.01 m
Deduction wearing coat -1.29
Total 108.01
4 PCC for RCC (1:2:4)
Operating slab 1 2.60 1.60 0.20 0.83 m3 (1.2+2x.7=2.6)
Breast wall 1 1.00 0.15 0.50 0.08 m
wearing coat 1 8.60 1.00 0.15 1.29
Total 2.20 2.20 m
5 M/S bar @0.4% of RCC 2.63x0.4% 28.48 28.48 Kg
6 Formwork
Foundation, U/S 2 4.25 0.60 5.10 m2
U/S 4 7.45 0.60 17.88 m2
D/S 2 8.9 0.60 10.68 m2
U/S Cutoff 2 4.46 1.00 8.92 m2
D/S Cutoff 2 1.00 1.00 2.00 m2
Wall, U/S 2 11.7 1.5 35.10 m2
D/S 2 8.90 1.40 24.92 m2
Operating slab, bottom 1 1.00 1.20 1.20 m2
Side 4 1.20 0.70 3.36 m2
Total 109.16 109.16 m2
7 Steel gate (1.30 x0.7) 1 1.30 0.70 0.91 0.91 m2
8 Gabion work
U/S (3 x 1.5 x 0.5) 1 12.00 6.00 0.50 36.00 m
D/S 1 6.00 3.00 0.50 9.00 m
Total 45.00 45.00 m
Supplying & Weaving of gabion box
9 (3x1.5x0.5) 20 270.00 270.00 m2 20x13.5 =270

2. DETAILED ESTIMATE OF GUIDE BUND

S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks

1 a)Earthwork inexcavation in, U/S & D/S


Guide bund 2 48 4.4 1.2 506.88 506.88 m

2 Earthwork for for filling in embankment


Guide bund 2 48.00 4.4 1.2 506.88 506.88 m
3 Gabion work
a. Guide bund
In river bed for launching, U/S & D/S
(3x1.5x0.75) 2 48.00 4.50 0.75 324.00 m
In slope (2x1x0.3) 2 48.00 2.00 0.30 57.60 m
Total 381.60 381.60 m
Guide bund
Supplying & Weaving of gabion
4
Slope(2x1x0.3)box 96 5.8m2/no 556.80 m2 96x15.75 =580.8
Launching 96 15.75m2/no 1512.00 m2 96x15.75 =1512
2068.80 2068.80

Estimated by Checked by Recommended by Approved by


Central Irrigation Development Division No. 1, Mahottari

3. DETAILED ESTIMATE OF OVERFLOW WEIR FOR DRAIN CROSSING

S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 a.Earth work in excavation in foundation

u/s cutoff 1 17.00 0.40 1.00 6.80 m3 B = (0.5+0.3)/2 =0.4


d/s cutoff 1 17.00 0.40 1.00 6.80 m3 B = (0.5+0.3)/2=0.4
u/s launching 1 22.10 4.50 0.50 49.73 m
d/s launching 1 22.10 3.00 0.50 33.15 m
Floor 1 25.00 17.00 0.75 318.75 m3 H = (1+0.5)/2=0.75
u/s retaining wall 1 10.16 2.40 1.00 24.38 m
d/s retaining wall 1 14.84 2.40 1.00 35.62 m
Return wall, u/s & d/s 4 2.55 2.40 1.00 24.48 m
Head Regulator
Wall 2 7.80 5.60 0.80 69.89 m
d/s cutoff 1 4.00 0.40 1.50 2.40 m
Launching 1 4.00 3.00 0.50 6.00 m
Return wall, d/s 2 1.50 1.00 0.80 2.40 m
Sob-Total 580.39 m
b.Launching & Slope 1 75.00 6.00 0.50 225.00 m
Total 805.39 805.39 m
2 Earthwork in back filling
a.cutoff & Head Regulator 193.46 m3 1/3 of E/W in excav.
b.Launching & Slope 1 25.00 5.00 3.00 375.00 m
Total 568.46 568.46 m
3 P.C.C. (1:3:6)
u/s cutoff 1 22.10 0.40 1.00 8.84 m3 B = (0.5+0.3)/2=0.4
d/s cutoff 1 22.10 0.40 1.50 13.26 m3 B =(0.5+0.3)/2=0.4
u/s floor 1 17.00 3.05 0.30 15.56
Weir portion (Sloping portion) 1 17.00 1.60 0.40 10.88 m
Crest portion 1 17.00 0.70 0.60 7.14 m
Glacis 1 7.80 17.00 0.95 125.97 m3 H = (.6+1.3)/2=.95
d/s floor 1 11.50 17.00 0.85 166.18 m3 H = (1.3+0.4)/2=0..85
Base slab, u/s wall 2 10.16 2.40 0.60 29.26 m
Base slab d/s wall 2 14.84 2.20 0.60 39.18 m
Stem, u/s 2 10.16 1.20 3.20 78.03 m3 B = (0.4+2)/2=1.2
Stem, d/s 2 14.84 1.20 3.55 126.44 m
Return wall, u/s & d/s (Base slab) 4 2.55 2.40 0.60 14.69 m
u/s return wall (stem) 2 2.55 1.20 3.20 19.58 m3 B = (0.4+2)/2=1.2
d/s return wall (stem) 2 2.55 1.20 3.55 21.73 m
P.C.C. Head Regulator
Base slab 1 6.15 5.60 0.80 27.55 m
Base slab. u/s slope 1 1.65 2.25 0.60 2.23 m
d/s cutoff 1 4.00 0.40 1.50 2.40 m
Return 2 1.50 1.20 0.80 2.88 m
Wall, d/s 2 6.15 0.55 1.40 9.47 m3 B = (0.3+0.8)/2=0.55
Wall, u/s 2 1.65 0.55 1.40 2.54 m3 B = (0.3+0.8)/2=0.55
u/s slope portion 1 1.62 1.00 0.40 0.65 m
Crest 1 1.00 0.50 0.60 0.30 m
Glacis 1 1.00 2.05 0.60 1.23 m3 H = (0.6+0.6)/2=0.6
d/s floor 1 1.00 4.10 0.50 2.05 m3 H = (0.6+0.4)/2=0.5
d/s raised portion 0.5 1.00 0.40 0.50 0.10 m
Step 1 1.50 0.30 0.20 0.09 m
Step 1 1.00 0.30 0.20 0.06 m
Step 1 0.50 0.30 0.20 0.03 m
For Hume pipe support 2 0.60 0.30 1.00 0.36 m
Sub-Total 728.66 m
Deduction of wearing coat -50.62
Total 678.04 678.04 m
4 R.C.C.1:2;4
Operating platform
Slab 1 1.20 1.60 0.20 0.38 m
Parapet 2 1.20 0.20 0.80 0.38 m3 RCC
Breast wall 1 1.00 0.15 1.30 0.20 m
wearing coat 1 19.85 17.00 0.15 50.62
Total 51.58 51.58 m

5 PCC(1:5:10) for blinding 1 17.00 2.60 1.00 44.20 44.20 m (.6+4.6)/2=2.6

5 Quantity of MS bar@0.4% of 126.61 30.24 30.24 Kg


6 Steel gate, 1.3 x 0.7 1 1.30 0.70 0.91 0.91 m2

Estimated by Checked by Recommended by Approved by


Central Irrigation Development Division No. 1, Mahottari

S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
7 Formwork
u/s cutoff 1 16.00 1.00 16.00 m2

u/s cutoff, side 2 0.40 1.00 0.80 m2


d/s cutoff, side 2 0.40 1.50 1.20 m2
side 1 17.00 0.40 6.80 m2
d/s floor 2 11.50 0.85 19.55 m2 H = (1.3+0.4)/2=0.85
Base slab (wall), u/s 2 10.16 0.60 12.19 m2
Side 2 2.25 0.60 2.70 m2
d/s 2 14.84 0.60 17.81 m2
Side 2 2.25 0.60 2.70 m2
Stem, u/s 2 10.16 3.20 65.02 m2
Side, u/s 2 1.20 3.20 7.68 m2 L= (2+0.4)/2=1.2
Stem d/s 2 14.84 3.55 105.36 m2
Side, d/s 2 1.20 3.55 8.52 m2 L= (2+0.4)/2=1.2
Return portion 8 2.55 0.60 12.24 m2
Side 2 2.55 3.55 18.11 m2
Side 2 2.55 3.20 16.32 m2
H/R portion
Base Slab 2 6.15 0.80 9.84 m2
Side 2 5.60 0.80 8.96 m2
Slope portion 2 1.65 0.60 1.98 m2
2 2.25 0.60 2.70 m2
Stem 4 6.15 1.50 36.90 m2
5 1.65 3.20 26.40 m2
2 0.40 1.50 1.20 m2
slab base 1 1.20 1.60 1.92
Parapet 2 1.20 0.20 0.48
side 2 1.60 0.50 1.60
Breast wall 2 1.60 1.20 3.84
Total 408.82 408.82 m2
8 60 cm dia. Hume pipe NP2 3 2.50 7.50 7.50 rm
9 Rubber seal 2 25.00 50.00 rm
Rubber seal 1 17.00 17.00 rm
Total 67.00 67.00 rm
10 Gabion work
H/R portion,d/s (2x1x0.30) 1 4.00 3.00 0.30 3.60 m
u/s weir (3 x1.5 x 0.5) 1 21.00 3.00 0.50 31.50 m3
d/s weir (3 x1.5 x 0.5) 1 21.00 4.50 0.50 47.25 m
Guide bund launching, u/s+ d/s bed3*1.5* 1 75.00 3.00 0.50 112.50 m
Slope portion (3 x 1.5 x .3) 1 75.00 3.00 0.30 67.50 m
Total 262.35 262.35 m
11 a. Weaving of gabion box (2x1x0.3) 6 5.8/no 34.80 m2 6x5.8 = 34.80
b. '' '' " (3x1.5x0.5) 85 85/no 1147.50 m2 85x13.5 = 1147.5
c. " " " (3x1.5x0.3) 50 50/no 585.00 m2 50x11.7 = 585.00
Total 1767.30 1767.30 m2

Estimated by Checked by Recommended by Approved by


Central Irrigation Development Division No. 1, Mahottari

4. DETAILED ESTIMATE OF DIVISION BOX WITH ROAD CROSSING

S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earthwork in excav. for foundation
Canal portion, Total length 1 11.50 2.80 1.00 32.20 m
Return wall 8 1.00 1.40 1.00 11.20 m
Total 43.40 43.40 m
2 Backfill, 1/3 of excavtion 1 14.47 14.47 m
3 P.C.C. (1:2:4)
Canal portion wall m
Base 1 11.50 2.80 0.80 25.76 m
Superstructure 2 11.50 0.60 1.50 20.70 m
Return wall 8 1.00 1.40 0.40 4.48 m
Return wall 8 1.00 0.70 1.90 10.64 m
Parapet 2 1.80 0.30 0.40 0.43 m
Cutoff 4 1.00 0.30 0.40 0.48 m
Canal bed 1 13.80 1.00 0.20 2.76 m
Total 65.25 65.25 m
4 P.C.C. (1:2:4) for R.C.C.
Slab 1 5.00 1.80 0.20 1.80 1.80 m
5 Steel @ 1% of 1.8 m3 141.30 141.30 Kg
6 Formwork for RCC
Slab, Bottom 1 5.00 1.00 5.00 m2
Side 2 5.00 0.20 2.00 m2
Side 2 1.80 0.20 0.72 m2
Canal portion, wall
Outer face 2 11.50 2.30 52.90 m2
Side 2 2.80 0.80 4.48 m2
Innerface 2 11.50 1.50 34.50 m2
Return wall 16 1.00 2.30 36.80 m2
Side 16 1.40 0.40 8.96 m2
Side 16 0.70 1.90 21.28 m2
Total 166.64 166.64 m2

5. DETAILED ESTIMATE OF HUME PIPE CULVERT (3 Nos)

S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earthwork in excav. In foundation
Headwall 2 1.00 0.75 0.70 1.05 m3
Wing wall 4 3.00 0.75 0.70 6.30 m3
u/s cutoff + d/s cutoff 2 1.00 0.30 0.40 0.24 m3
Support wall for collar joint 1 1.00 0.50 0.70 0.35 m3
Total 7.94 23.82 m3
2 Backfill, 1/3 of excavation 2.65 m3
Earth filling on pipe 1 4.40 5.00 0.45 9.90 m3
Total 12.55 37.64
3 PCC (1:3:6)
Headwall 2 1.00 0.75 0.20 0.30 m3
Wing wall 4 3.00 0.75 0.20 1.80 m3
u/s cutoff + d/s cutoff 2 1.00 0.30 0.40 0.24 m3
Support wall for collar joint 1 1.00 0.50 0.20 0.10 m3
Superstructure
Headwall 2 1.00 0.53 2.00 2.10 m3 B=(0.75+0.3)/2 = 0.53
Wing wall 4 3.00 0.53 2.00 12.60 m3 B=(0.75+0.3)/2 = 0.53
Support wall for collar joint 1 1.00 0.50 1.15 0.58 m3
Concreting for pipe embeding 1 5.00 1.00 1.00 5.00
Total 22.72 68.15 m3
Deduction for hume pipe 3 0.21 m3
Qt after dedu 22.51 67.52 m3
4 RCC Hume pipe 40 cm dia. 2 2.50 5.00 15.00 rm
5 Formwork
Inner +outer face 4 8.00 1.75 56.00 m2
Side 4 0.53 1.75 3.68 m2 L= (0.75+0.3)/2 =0.53
Total 59.68 179.03 m2

Estimated by Checked by Recommended by Approved by


Central Irrigation Development Division No. 1, Mahottari

6. DETAILED ESTIMATE OF DIVISION BOX (3 Nos)

S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earthwork in excavation 1 11.00 4.80 0.80 42.24 126.72 m3
2 Earthwork in backfill, 1/3 of excav 1 14.08 42.24 m3
3 PCC 1:2:4
Wall, base 1 4.30 2.80 0.80 9.63 m3
Return 4 1.00 0.90 0.80 2.88 m3
Return 2 1.15 0.90 0.80 1.66 m3
u/s& d/s cutoff 2 1.00 0.30 0.50 0.30 m3
Superstructure 1 4.30 0.60 1.30 3.35 m3 B = (0.4+0.8)/2 =0.6
Return 4 1.00 0.65 1.30 3.38 m3 B = (0.9+0.4)/2 =0.65
Return 2 1.15 0.65 1.30 1.94 m3
Profile wall 2 4.80 0.30 0.50 1.44 m3
Profile wall 4 1.60 0.95 1.30 7.90 B= (1.6+0.3)/2 = 0.95
Total 32.49 97.47 m3
4 Dry Stone pitching
Bed 1 6.20 1.00 0.30 1.86 m3
Side 2 6.20 1.85 0.30 6.88 m3
Total 8.74 26.23 m3
5 Formwork
Wall 2 4.30 0.80 6.88 m2
Wall 2 2.80 0.80 4.48 m2
Return 8 1.00 0.80 6.40 m2
Return 8 1.00 1.30 10.40 m2
Return 4 1.15 1.30 5.98 m2
Profile wall 2 4.80 0.50 4.80 m2
Side 4 0.90 1.30 4.68 m2
Wall, Outerface+Innerface 1 24.00 1.30 31.20 m2
Total 74.82 224.46 m2

7. DETAILED ESTIMATE OF VRB (2 Nos)

S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earthwork in excavation 1 11.00 4.80 0.80 42.24 84.48 m3
2 Earthwork in backfilling, 1/3 of excav 1 14.08 28.16 m3
3 PCC (1:2:4)
Abutment wall, d/s 1 3.60 2.80 0.80 8.06 m3
Return 4 1.00 0.90 0.80 2.88 m3
Superstructure 2 3.60 0.60 1.30 5.62 m3
Return 4 1.00 0.60 1.30 3.12 m3
Profile wall 2 4.80 0.30 0.50 1.44 m3
Profile wall 4 1.60 0.95 1.30 7.90 m3
Cutoff 2 1.00 0.30 0.50 0.30 m3
Parapet 2 1.80 0.40 0.30 0.43 m3
Total 29.76 59.51 m3
4 Dry Stone pitching
Bed 1 6.40 1.00 0.30 1.92 m3
Side 2 6.40 1.85 0.30 7.10 m3
Total 9.02 18.05 m3
5 Formwork
Base 2 3.60 0.80 5.76 m2
Base 2 2.80 0.80 4.48 m2
Return 8 1.00 0.80 6.40 m2
Return 4 0.90 0.80 2.88 m2
Abutment wall, Outerface 1 11.60 1.30 15.08 m2
Innerface 1 8.40 1.30 10.92 m2
For RCC 1 4.40 1.00 4.40 m2
Side 2 4.40 0.30 2.64 m2
Side 2 1.80 0.30 1.08 m2
Total 53.64 107.28 m2
6 PCC (1:2:4) for RCC
Slab 1 4.40 1.80 0.30 2.38 4.75 m2
7 MS bar for RCC@1.25% 1 233.15 466.29 Kg

Estimated by Checked by Recommended by Approved by


Central Irrigation Development Division No. 1, Mahottari

8. DETAILED ESTIMATE OF 0.50 m FALL (8 Nos)

S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earth work in excavation in foundation
u/s cutoff 1 1.00 0.45 0.60 0.27 m 3

u/s floor 1 1.50 1.20 0.30 0.54 m3


u/s wing wall 2 0.75 0.60 0.30 0.27 m3
u/s Abt. wall 2 1.75 0.60 0.30 0.63 m3
crest wall 1 1.00 0.50 0.80 0.40 m3
u/s floor 1 2.50 3.00 0.60 4.50 m3
d/s floor 1 1.70 2.40 0.40 1.63 m3
d/s cutoff wall 1 1.00 0.30 0.35 0.11 m3
boulder pitching bed 1 3.00 1.20 0.50 1.80 m3
side slope 2 3.40 1.56 0.50 5.30 m3
d/s cutoff wall 1 1.20 0.60 0.70 0.50 m3
Total 15.96 127.64 m3
2 Earth work for back fill
1/3 of Earth work excavation 0.33 5.27 42.12 m3
3 P.C.C. in 1:3:6 CM
u/s cutoff wall 1 1.00 0.45 0.20 0.09 m3
u/s wing wall 2 0.75 0.60 0.30 0.27 m3
u/s Abt. Wall 2 1.75 0.60 0.30 0.63 m3
u/s crest wall 1 1.00 0.50 0.65 0.33 m3
d/s floor 1 2.50 3.00 0.60 4.50 m3
d/s floor 1 1.70 2.40 0.40 1.63 m3
d/s cutoff wall 1 1.00 0.30 0.35 0.11 m3
d/s wing wall 2 0.85 0.60 0.40 0.41 m3
d/s cutoff wall 1 1.00 0.60 0.20 0.12 m3
Superstructure 0.00 m3
u/s wing wall 2 0.75 0.40 0.70 0.42 m3
u/s Abt. Wall 2 1.75 0.55 0.70 1.35 m3
d/s Abt. Wall 2 1.25 0.55 1.35 1.86 m3
d/s Abt. Wall 2 1.00 0.55 1.10 1.21 m3
d/s Abt. Wall 2 2.50 0.90 0.70 3.15 m3
d/s wing wall 2 0.75 0.40 0.70 0.42 m3
Total 16.48 131.87 m3
4 Brick work in 1:4 CM
wall 1 3.70 0.25 0.50 0.46 m3
wall 2 3.40 0.25 0.50 0.85 m3
Total 1.31 10.50 m3
5 Dry boulder pitching
d/s bed 1 3.00 1.00 0.30 0.90 m3
side slope 2 3.40 1.56 0.30 3.18 m3
Total 4.08 32.66 m3
6 Form work
Inside :crest wall 1 1.20 1.40 1.68 m2
crest wall 1 1.20 0.80 0.96 m2
u/s wing wall 2 1.25 0.70 1.75 m2
u/s Abt. Wall 2 1.75 0.70 2.45 m2
d/s Abt. Wall 2 1.25 1.35 3.38 m2
d/s Abt. Wall 2 1.00 1.10 2.20 m2
d/s Abt. Wall 2 1.95 0.70 2.73 m2
d/s wing wall 2 1.25 0.70 1.75 m2
outside : u/s wing wall 2 1.75 0.75 2.63 m2
d/s Abt. Wall 2 1.25 1.70 4.25 m2
d/s Abt. Wall 2 1.00 1.45 2.90 m2
d/s Abt. Wall 2 1.95 0.75 2.93 m2
d/s Abt. Wall 2 0.75 0.75 1.13 m2
d/s Abt. Wall 2 0.30 1.45 0.87 m2
Total 31.59 252.72 m2

9. DETAILED ESTIMATE OF LINING OF CANAL

S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earth work in excavation
Bed 1 100 1.4 0.2 28 m3
Wall 2 100 0.5 1.2 120 m3
Total 148 148.00 m3
2 E/W in cutting in canal reshaping
WUA PART As per calculation sheet 6205.00 m3
2 E/W in backfilling, 1/3 of excav. 1 49.33 49.33 m3
3 P.C.C. for R.C.C. (1:2:4)
Bed 1 100 1.4 0.15 21 m3
Wall 2 100 1 0.1 20 m3
Total 41 41 m3
4 Formwork 2 100 1.15 230 230 m2
5 MS bar @ 0.5% of R.C.C. 1 1609.25 1609.25 Kg

Estimated by Checked by Recommended by Approved by


Central Irrigation Development Division No. 1, Mahottari
ABSTRACT OF COST

Name of Project: Aurahi Irrigation Project, Dhanusha


Name of Work:- Construction of Side Intake
RATE/UNIT,
S.N. DETAILS OF WORK UNIT QUANTITY AMOUNT REMARKS
NRs
Earth work in excavation in
1 m 3
162.24 95.35 15469.71
foundation
2 Earth work for back fill m3 54.08 34.05 1841.63
3 P.C.C. work in 1:3:6 m3 108.01 3972.07 429009.98
4 R.C.C. work in 1:2:4 m3 2.20 4856.80 10670.40
Supply, fitting and fixing of steel
5 m2 0.91 30000.00 27300.00
gate all complete(size 1.3x.7)
M/S bar cutting,bending &binding
6 mt 0.03 59781.49 1702.56
all complete.
7 Filling boulder in gabion box m 3
45.00 975.55 43899.63
Supply 10 S.W.G.wire and weaving
gabion box with double knotted
8 m2 270.00 154.15 41620.19
mesh size 10 cm x10 cm.all
complete.
9 Form work m2 109.16 153.09 16711.63
10 Dewatering during construction job L.S. L.S. 30000.00
Total 618225.74

ABSTRACT OF COST

Name of Project: Aurahi Irrigation Project, Dhanusha


Name of Work:- Construction of Gabion Weir & Guide Bund
S.N. DETAILS OF WORK UNIT QUANTITY RATE AMOUNT REMARKS
Earth work in excavation in soft
1 m 506.88 95.35 48332.15
clay &silty soil
2 Earth work in filling in embankment m 506.88 68.11 34522.96
3 Filling boulder in gabion box m 381.60 975.55 372268.87
Supply 10 S.W.G.wire and weaving
gabion box with double knotted
4 m2 2068.80 154.15 318903.13
mesh size 10 cm x10 cm.all
complete.
Total 774027.11

ABSTRACT OF COST

Name of Project: Aurahi Irrigation Project, Dhanusha


Name of Work:- Construction of Drain Crossing Overflow Weir
S.N. DETAILS OF WORK UNIT QUANTITY RATE AMOUNT REMARKS
Site clearance before and after
1 construction. LS 25000.00
Earth work in excavation in
2 805.39 95.35 76796.03
foundation m
3 Earth work for back fill m3 568.46 34.05 19358.70
4 P.C.C. work in 1:3:6 m3 678.04 3972.07 2693235.79
5 R.C.C. work in 1:2:4 m3 51.58 4856.80 250516.38
6 P.C.C. work in 1:5:10 m3 44.20 3129.04 138303.52
Supply, fitting and fixing of steel
7 m2 0.91 30000.00 27300.00
gate all complete(size 1.3x.7)
M/S bar cutting,bending &binding
8 mt 0.03 59781.49 1807.68
all complete.
9 Filling boulder in gabion box m3 262.35 975.55 255934.85
Supply 10 S.W.G.wire and weaving
gabion box with double knotted
10 m2 1767.30 154.15 272427.25
mesh size 10 cm x10 cm.all
complete.
11 Form work m2 408.82 153.09 62587.95
Supply and fitting fixing of Rubber
12 rm 67.00 700.00 46900.00
seal all complete.
13 60mm dia. R.C.C. Hume Pipe rm 7.50 1493.50 11201.24
Total 3881369.41
ABSTRACT OF COST

Name of Project: Aurahi Irrigation Project, Dhanusha


Name of Work:- Construction of Division Box with Road Crossing
S.N. DETAILS OF WORK UNIT QUANTITY RATE AMOUNT REMARKS
Earth work in excavation in
1 m3 43.40 95.35 4138.29
foundation
2 Earth work for back fill m3 14.47 34.05 492.65
3 P.C.C. work in 1:3:6 m3 65.25 3972.07 259185.28
4 R.C.C. work in 1:2:4 m3 1.80 4856.80 8742.25
M/S bar cutting,bending &binding
5 mt 0.14 59781.49 8447.12
all complete.
6 Form work m 2
166.64 153.09 25511.42
Total 306517.01

ABSTRACT OF COST
Name of Project: Aurahi Irrigation Project, Dhanusha
Name of Work:- Construction of Pipe Culvert (4 Nos)
S.N. DETAILS OF WORK UNIT QUANTITY RATE AMOUNT REMARKS
Earth work in excavation in
1 m3 23.82 95.35 2271.29
foundation
2 Earth work for back fill m3 37.64 34.05 1281.81
3 P.C.C. work in 1:3:6 m3 67.52 3972.07 268174.06
4 Form work m2 179.03 153.09 27407.48
5 40mm dia. R.C.C. Hume Pipe rm 15.00 979.96 14699.42
Total 313834.06

ABSTRACT OF COST
Name of Project: Aurahi Irrigation Project, Dhanusha
Name of Work:- Construction of Division Box (3Nos)
S.N. DETAILS OF WORK UNIT QUANTITY RATE AMOUNT REMARKS
Earth work in excavation in soft
1 m 3
126.72 95.35 12083.04
clay &silty soil
2 Earth work for back fill m3 42.24 34.05 1438.46
3 P.C.C. work in 1:3:6 m3 97.47 3972.07 387151.35
4 Form work m2 224.46 153.09 34363.26
5 Dry boulder pitching m3 26.23 1289.68 33823.20
6 Total 468859.30

ABSTRACT OF COST
Name of Project: Aurahi Irrigation Project, Dhanusha
Name of Work:- Construction of V.R.B. in Canal (2 Nos)
S.N. DETAILS OF WORK UNIT QUANTITY RATE AMOUNT REMARKS
Earth work in excavation in soft
1 m3 84.48 95.35 8055.36
clay &silty soil
2 Earth work for back fill m3 28.16 34.05 958.97
3 P.C.C. work in 1:3:6 m3 59.51 3972.07 236385.62
4 R.C.C. work in 1:2:4 m3 4.75 4856.80 23079.53
M/S bar cutting,bending &binding
5 mt 0.47 59781.49 27875.51
all complete.
6 Form work m 2
107.28 153.09 16423.82
7 Dry boulder pitching m3 18.05 1289.68 23276.18
Total 336054.99
ABSTRACT OF COST
Name of Project: Aurahi Irrigation Project, Dhanusha
Name of Work:- Construction of Fall Structures, 0.5m (8Nos)
S.N. DETAILS OF WORK UNIT QUANTITY RATE AMOUNT REMARKS
Earth work in excavation in
1 m3 127.64 95.35 12170.76
foundation
2 Earth work for back fill m3 42.12 34.05 1434.41
3 P.C.C. work in 1:3:6 m3 131.87 3972.07 523796.40
4 Brick work in 1:4 CM m3 10.50 4290.08 45045.84
5 Form work m2 252.72 153.09 38689.67
6 Dry boulder pitching m3 32.66 1289.68 42119.98
Total 663257.05

ABSTRACT OF COST
Name of Project: Aurahi Irrigation Project, Dhanusha
Name of Work:- Construction of Canal (Main & Branch)
S.N. DETAILS OF WORK UNIT QUANTITY RATE AMOUNT REMARKS
Earth work in excavation in soft
1 m3 148.00 95.35 14112.13
clay &silty soil
2 Earth work in cutting in canal. m3 6205.00 82.92 514487.58
Earth work in filling in embankment
3 m3 0.00 68.11 0.00
4 Earth work for back fill m3 49.33 34.054375 1680.02
5 R.C.C. work in 1:2:4 m3 41.00 4856.80 199128.97
6 M/S bar cutting,bending &binding mt 1.61 59781.49 96203.36
7 all
Formcomplete.
work m2 230.00 153.09 35211.40
Total 860823.45
SUMMARY OF COST OF AURAHI IRRIGATION PROJECT
(Component-wise)
S.N. Description of work Unit Quantity Amount (NRs) Remarks
1 Side Intake no 1 618225.74
2 Gabion weir & Guide bund no 1 774027.11
3 Drain crossing overflow weir no 1 3881369.41
4 Division box with road crossing no 1 306517.01
5 Pipe culvert no 3 313834.06
6 Division box no 3 468859.30
7 V.R.B. no 2 336054.99
8 0.5 m Fall no 8 663257.05
9 Canal works/Lining Km 0.1 860823.45
Sub total 8222968.12
Vat @ 13 % 1002102.47
Contingencies @ 5% 411148.41
Sub Total 9636219.00
i Environmental Protection Works @ 1% 82000.00
ii Institutional Development Works 40000.00
iii Establishment and Miscellaneous Works 50000.00
vi Pre-construction survey Works 40000.00
Grand Total 9848219.00
SUMMARY OF QUANTITY & COST
DRAIN CROSSING OVER DIV.BOX WITH
SIDE INTAKE (1 GUIDE BUND PIPE CULVERT DIVISION BOX V.R.B. (2
S.N. DETAILS OF WORK UNIT RATE FLOW WEIR (1 ROAD CROSSING DROP (8 Nos) Canal Works/Lining TOTAL
Nos) (1 Nos) (3 Nos) (3Nos) Nos)
Nos) (1 Nos)
Amt Amt Amt Amt Amt Amt Amt Amt Amt Amt
NRs/Unit Qty Qtty Qtty Qtty Qtty Qtty Qtty Qtty Qtty Qtty
NRs NRs NRs NRs NRs NRs NRs NRs NRs NRs
Site clearance before and after
1 25,000.00 L.S. 25000.00
construction.
Earth work in excavation in soft clay
2 m3 95.35 506.88 48332.15 126.72 12083.04 84.48 8055.36 148.00 14112.13 866.08 82582.68
&silty soil
Earth work in cutting in canal
3
reshaping
WUA Contribution m3 82.92 6205.00 514487.58 6205.00 514487.58
4 Earth work in filling in embankment m3 68.11 506.88 34522.96 0.00 0.00 506.88 34522.96
Earth work in excavation in
5 m3 95.35 162.24 15469.71 805.39 76796.03 43.40 4138.29 23.82 2271.29 127.64 12170.76 1162.49 110846.08
foundation
6 Earth work for back fill m3 34.05 54.08 1841.63 568.46 19358.70 14.47 492.65 37.64 1281.81 42.24 1438.46 28.16 958.97 42.12 1434.41 49.33 1680.02 836.50 28486.64
7 P.C.C. work in 1:3:6 m3 3972.07 108.01 429009.98 678.04 2693235.79 65.25 259185.28 67.52 268174.06 97.47 387151.35 59.51 236385.62 131.87 523796.40 1207.67 4796938.48
8 R.C.C. work in 1:2:4 m3 4856.80 2.20 10670.40 51.58 250516.38 1.80 8742.25 4.75 23079.53 41.00 199128.97 101.33 492137.53
9 P.C.C. in 1:5:10 m3 3129.04 44.20 138303.52 44.20 138303.52
10 Brick work in 1:4 CM m3 4290.08 10.50 45045.84 10.50 45045.84
Supply, fitting and fixing of steel
11 m2 30000 0.91 27300.00 0.91 27300.00 1.82 54600.00
gate all complete(size 1.3x.7)
M/S bar cutting,bending &binding all
12 mt 59781.49 0.03 1702.56 0.03 1807.68 0.14 8447.12 0.47 27875.51 1.61 96203.36 2.28 136036.25
complete.
13 Filling boulder in gabion box m3 975.55 45.00 43899.63 381.60 372268.87 262.35 255934.85 688.95 672103.36
Supply 10 S.W.G.wire and weaving
gabion box with double knotted
14 m2 154.15 270.00 41620.19 2068.80 318903.13 1767.30 272427.25 4106.10 632950.57
mesh size 10 cm x10 cm.all
complete.
15 Form work m2 153.09 109.16 16711.63 408.82 62587.95 166.64 25511.42 179.03 27407.48 224.46 34363.26 107.28 16423.82 252.72 38689.67 230.00 35211.40 1678.11 256906.63
16 Dry boulder pitching m3 1289.68 26.23 33823.20 18.05 23276.18 32.66 42119.98 76.93 99219.35
Supply and fitting fixing of Rubber
17 rm 700 67.00 46900.00 67.00 46900.00
seal all complete.
18 R.C.C. Hume Pipe
a) 40cm dia rm 979.96 15.00 14699.42 15.00 14699.42
b)60cmdia rm 1493.50 7.50 11201.24 7.50 11201.24
19 Dewatering during construction job L.S. 30000.00 L.S. 30000.00
8222968.12
Total 618225.74 774027.11 3881369.41 306517.01 313834.06 468859.30 336054.99 663257.05 860823.45 8222968.12
VAT @ 13% 1002102.47
Contingencies @ 5% 411148.41
Sub-Total 1413250.88
i Environmental Protection Works about@ 1% 82000
ii Institutional Development Works 40000
iii Establishment and Miscellaneous Works 50000
vi Pre-construction survey Works 40000
Grand Total 9848219.00

Estimated by Checked by Recommended by Approved by


Central Irrigation Development Division No. 1, Mahottari
SUMMARY OF COST
(Component-wise)
Name of Project:- Aurahi Irrigation Project
Name of Work:- Construction of Intake, Canal and Structures
S.N. Description of work Quantity Unit Amount (NRs) Remarks
1 Side Intake 1 no 618225.74
2 Gabion weir & Guide bund 1 no 774027.11
3 Drain crossing overflow weir 1 no 3881369.41
4 Division box with road crossing 1 no 306517.01
5 Pipe culvert 3 no 313834.06
6 Division box 3 no 468859.30
7 V.R.B. 2 no 336054.99
8 0.5 m Fall 8 no 663257.05
9 Canal works/Lining 0.1 Km 860823.45
Sub total 8222968.12
Vat @ 13 % 1002102.47
Contingencies @ 5% 411148.41
Sub Total 9636219.00
i Environmental Protection Works @ 1% 82000.00
ii Institutional Development Works 40000.00
iii Establishment and Miscellaneous Works 50000.00
vi Pre-construction survey Works 40000.00
Grand Total 9848219.00
Say 9861000.00

Estimated by Checked by Recommended by Aprroved by


Central Irrigation Development Division No. 1, Mahottari
ABSTRACT OF COST
Name of Project: Aurahi Irrigation Project, Dhanusha

Name of Work:- Side Intake, Overflow weir and Canal Structures

S.N. DETAILS OF WORK DIV.BO


DRAIN
SIDE X WITH
GUIDE CROSSING PIPE DIVISIO V.R.B. DROP
INTAKE ROAD Canal TOTAL
UNIT BUND OVER FLOW CULVERT N BOX (2 (8 RATE NRs. AMOUNT NRs.
(1 CROSSI Works/Lining QUANTITY
(1 Nos) WEIR (4 Nos) (3Nos) Nos) Nos)
Nos) NG (1
(1 Nos)
Nos)
Site clearance before and after
1 job L.S. L.S. 25000.00
construction.

2 Earth work in excavation in soft m3 506.88 126.72 84.48 148.00 866.08 95.35 82582.68
clay &silty soil
3 Earth work in cutting in canal.
WUA Contribution m3 6205.00 6205.00 82.92 514487.58
4 Earth work in filling in m3 506.88 0.00 506.88 68.11 34522.96
embankment
Earth work in excavation in
5 m3 162.24 805.39 43.40 23.82 127.64 1162.49 95.35 110846.08
foundation
6 Earth work for back fill m3 54.08 568.46 14.47 37.64 42.24 28.16 42.12 49.33 836.50 34.05 28486.64
7 P.C.C. in 1:3:6 m3 108.01 678.04 65.25 67.52 97.47 59.51 131.87 1207.67 3972.07 4796938.48
8 R.C.C. work in 1:2:4 m3 2.20 51.58 1.80 4.75 41.00 101.33 4856.80 492137.53
9 P.C.C. in 1:5:10 m3 44.20 44.20 3129.04 138303.52
10 Brick work in 1:4 CM m3 10.50 10.50 4290.08 45045.84
Supply, fitting and fixing of steel
11 m 2
0.91 0.91 1.82 30000.00 54600.00
gate all complete(size 1.3x.7)

12 M/S bar cutting,bending &binding mt 0.028 0.03 0.14 0.47 1.61 2.28 59781.49 136036.25
all complete.
13 Filling boulder in gabion box m3 45.00 381.60 262.35 688.95 975.55 672103.36
Supply 10 S.W.G.wire and
weaving gabion box with double
14 m2 270.00 2068.80 1767.30 4106.10 154.15 632950.57
knotted mesh size 10 cm x10
cm.all complete.
15 Form work m2 109.16 408.82 166.64 179.03 224.46 107.28 252.72 230.00 1678.11 153.09 256906.63
16 Dry boulder pitching m3 26.23 18.05 32.66 76.93 1289.68 99219.35
17 Supply and fitting fixing of Rubber rm 67.00 67.00 700.00 46900.00
seal all complete.
18 R.C.C. HUME PIPE
a) 40mm dia rm 15.00 15.00 979.96 14699.42
b)60mmdia rm 7.50 7.50 1493.50 11201.24
19 Dewatering during construction job 100000 L.S. L.S. 30000.00
Sub-Total (Cost) 618226 774027.114 3881369.41 306517 313834.0571 468859 336054.99 663257.05 860823.45 8222968.12
VAT @ 13% 1002102.47
Contingencies @ 5% 411148.41
Sub-Total 9636219.00
i Environmental Protection Works about@ 1% 82000.00
ii Institutional Development Works 40000.00
iii Establishment and Miscellaneous Works 50000.00
vi Pre-construction survey Works 40000.00
Grand Total 9848219.00
Say 9861000.00
ABSTRACT OF COST
Name of Project: Aurahi Irrigation Project, Dhanusha
Name of Work:- Construction of Side Intake, Overflow weir and canal structures

RATE,
S.N. DETAILS OF WORK UNIT QUANTITY AMOUNT, NRs.
( NRs)

1 Site clearance before and after construction. job L.S. L.S. 25000.00
2 Earth work in excavation in soft clay &silty soil m3 866.08 95.35 82582.68
3 Earth work in filling in embankment m3 506.88 68.11 34522.96
4 Earth work in excavation in foundation m3 1162.49 95.35 110846.08
5 Earth work for back fill m3 836.50 34.05 28486.64
6 P.C.C. in 1:3:6 m3 1207.67 3972.07 4796938.48
7 R.C.C. work in 1:2:4 m3 101.33 4856.80 492137.53
8 P.C.C. in 1:5:10 m3 44.20 3129.04 138303.52
9 Brick work in 1:4 CM m3 10.50 4290.08 45045.84
Supply, fitting and fixing of steel gate all complete(size
10 m2
1.3x.7) 1.82 30000.00 54600.00
11 M/S bar cutting,bending &binding all complete. mt 2.28 59781.49 136036.25
12 Filling boulder in gabion box m3 688.95 975.55 672103.36
Supply 10 S.W.G.wire and weaving gabion box with
13 m2
double knotted mesh size 10 cm x10 cm.all complete. 4106.10 154.15 632950.57
14 Form work m2 1678.11 153.09 256906.63
15 Dry boulder pitching m3 76.93 1289.68 99219.35
16 Supply and fitting fixing of Rubber seal all complete. rm 67.00 700.00 46900.00
17 R.C.C. HUME PIPE
a) 40cm dia rm 15.00 979.96 14699.42
b)60cmdia rm 7.50 1493.50 11201.24
18 Dewatering during construction job L.S. L.S. 30000.00
Sub-Total 7708480.55
WUA Contribution

1 Earth work in cutting in canal. m3 6205.00 82.92 514487.58


Sub-Total 514487.58
Total 8222968.12
i Environmental Protection Works @ 1% 82000.00
ii Institutional Development Works 40000.00
iii Establishment and Miscellaneous Works 50000.00
iv Pre-construction survey Works 40000.00
Sub-Total 212000.00
Contingencies @ 5% 411148.41
VAT @ 13% 1002102.47
Grand-Total 9848219.00
Say 98,61,000
In words NRs Nintyeight lacs sixty one thousand only
Estimated by: Checked by: Recommended by: Approved by:
Central Irrigation Development Division No. 1, Mahottari
ABSTRACT OF COST
Name of Project: Aurahi Irrigation Project, Dhanusha

Name of Work:- Side Intake, Overflow weir and Guide bund

Package No.: 1

S.N. DETAILS OF WORK UNIT Quantity RATE (NRs) Amount (NRs)

Site clearance before and after


1 25000.00
construction. L.S.
2 Earth work in excavation in soft clay m3 506.88000 95.35225 48332.15
&silty soil
3 Earth work in filling in embankment m3 506.88000 68.10875 34522.96
Earth work in excavation in foundation
4 m3 967.63050 95.35225 92265.75

5 Earth work for back fill m3 622.54350 34.05438 21200.33


6 P.C.C. work in 1:3:6 m3 786.05075 3972.06640 3122245.77
7 R.C.C. work in 1:2:4 m3 53.77750 4856.80407 261186.78
8 P.C.C. in 1:5:10 m3 44.20000 3129.04 138303.52
Supply, fitting and fixing of steel gate
9 m2 1.82000 30000.00000 54600.00
all complete(size 1.3x.7)
10 M/S bar cutting,bending &binding all Kg 58.71800 59.78149 3510.25
complete.
11 Filling boulder in gabion box m3 688.95000 975.5474 672103.36
Supply 10 S.W.G.wire and weaving
12 gabion box with double knotted mesh m2 4106.10000 154.14884 632950.57
size 10 cm x10 cm.all complete.
13 Form work m2 517.98 153.093 79299.58
Supply and fitting fixing of Rubber seal
14 rm 67.00000 700.00000 46900.00
all complete.
15 R.C.C. Hume Pipe
a)60cmdia rm 7.50000 1493.4991 11201.24
16 Dewatering during construction job L.S. 30000.00
Sub-Total 5273622.27
VAT @ 13% 685570.89
Subtotal 5959193.16
Contingencies @ 5% 263681.11
Total 6222874.27
Say 6222500.00

Estimated by: Checked by: Recommended by: Approved by:


Central Irrigation Development Division No. 1, Mahottari
ABSTRACT OF COST
Name of Project: Aurahi Irrigation Project, Dhanusha
Name of Work:- Construction of Canal &Canal
structures (Pipe culvert, Division box, VRB &
Drop)

Package No.: 2
RATE Amount
S.N. DETAILS OF WORK UNIT Quantity
(NRs) (NRs)
Earth work in excavation in soft clay
1 m3 359.20 95.35
&silty soil 34250.53
Earth work in excavation in
2 m3 194.86 95.35
foundation 18580.34

3 m3 213.96 34.05
Earth work for back fill 7286.31

4 m3
421.62 3972.07
P.C.C. work in 1:3:6 1674692.71

5 m3 47.55 4856.80
R.C.C. work in 1:2:4 230950.75
6 Brick work in 1:4 CM m3
10.50 4290.08 45045.84
M/S bar cutting,bending &binding all
7 mt 2.22 59781.49
complete. 132526.00
8 Form work m2
1160.13 153.09 177607.04

9 m3 76.93 1289.68
Dry boulder pitching 99219.35
10 R.C.C. Hume Pipe
a) 40cm dia rm 15.00 979.96 14699.42

Sub -Total 2434858.28


B:-Non Payable
Earth work in excavation in soft clay 6205.00 82.92
1 m3
&silty soil for canal reshaping 514487.58
Total(A+B) 2949345.86
Contingencies @5% 147467.29
VAT @ 13% 316531.58
Total 3413344.73
Say NRs. 3426500.00

Estimated by Checked by Recommended by Approved by


GOVERNMENT OF NEPAL
MINISTRY OF WATER RESOURCES
DEPARTMENT OF IRRIGATION
CENTRAL REGIONAL IRRIGATION DIRECTORATE
Central Irrigation Development Division 1, Mahottari
Medium Irrigation Project

FORM FOR APPROVAL OF PROJECT AND COST ESTIMATES

1 Project Aurahi Irrigation Project, Sakhuwa Mahendranagar, 1,8, 9, Dhanusha


2 Description of work Construction of Side Intake, overflow weir & Canal Structures
3 Estimated Amount 9861000
4 Certified:
a. The drawings and measurements of the proposed work are based on field verification.
b. The design and estimate of the proposed work is based on departmental norms and general
engineering principles in practice.

c. The proposed estimate is prepared on the basis of approved rate and rate analysis norms.
d. All the numbers and arithmetical calculations carried out in this estimate are correct.

.................... ....................
Submitted by: Checked by:
(Sub Engineer) (Engineer)

5 Recommended (CRID, Lalitpur):


The submitted cost estimates, drawings are correct in accordance with the approved
departmental norms and follow the general engineering principles in practice; hence is
recommended for approval.

6 Recommended (Department of Irrigation):


The submitted cost estimates, drawings are correct in accordance with the approved
departmental norms and follow the general engineering principles in practice; hence is
recommended for approval.

7 Approved:
For this work, the drawings and an amount of NRs. ... is approved.

....................
(Officer-in-charge)

You might also like