You are on page 1of 2

(BILL OF QUANTITY) 

Name of work :‐ Maintenance and Renewal works of NH‐91 of Ghaziabad – Aligarh section (km 23.8 
to  140.200)of state of UP  

S.No Item of work Unite Quantity Rate Amount


.

1. Filling and repairing of pot holes with 22.4-53 Cum 200


mm stone ballast by B.U.S.G. method including
cost of all material labour and T&P etc. required
for proper completion of work all as per
directions of Engineer in Charge
2. Patch repair with premix material including cost Cum 150
of material, tack coat, roller & other necessary
T&P i.e. required for proper completion of work
as per direction of Engineer in Charge
3. Providing and laying of stress absorbing Sqm 2400
membrane over a cracked road surface,
with crack width below 6 mm after cleaning
using CRMB-55 bitumen mixed bitumen,
sprayed at the rate of 9 Kg per 10 sqm and
spreading 5.6 mm crushed stone
aggregates @ 0.11 cum per 10 sqm with
hydraulic chip spreader, sweeping the
surface for uniform spreading of aggregate
and surface finished to conform to clause
902 including supply of all material, labour,
T&P as per required for proper compaction
work as per direction of Engineer in
charge.
4. Providing and applying tack coat @ 2.0kg/10 Sqm. 131,000
sqm on the prepared surface with bitumen
emulsion using emulsion pressure distributor
including cleaning of surface, supply of all
materials, labour, machinery, and T&P etc. all
complete as required for proper completion of
work as per specification No.503 of MoRT&H
specification for Road and Bridge Works (Latest
Edition), all complete, as per direction of
Engineer-in-change.
5. Providing and laying bituminous macadam- Cum. 200
50mm thick compacted comprising of graded
crushed stone grading II as per table 500-4 and
of approved quarry conforming to tests as per
MoRT&H specification table no. 500-3
premixed with a maximum of 3.5% Bitumen of
grade 60/70 by weight in computerized Hot mix
plant laid with pavers finisher, compacted with
vibratory and static rollers simultaneously
including supply of all material, labor,
machinery, and T&P etc. all complete required
for proper completion of work as per
specification No.504 of MoRT&H specification
for Road and Bridge (Latest Edition, all
complete), as per direction of Engineer-in-
change.
6. Providing and laying 25mm thick compacted Cum 3000
Semi Dense Bituminous concrete on prepared
surface with specified graded stone aggregates
of approved quarry conforming to test specified
in table 500-14 and of grading II as per table on
500-15 of MoRT&H latest specification,
premixed with crumb rubber modified bitumen
grade-55 for wearing course @ maximum 5%
by weight of mix, as per approved job mix
formula in computerized hot mix plant laid with
pavers finisher, compacted with vibratory and
static rollers simultaneously including cost all
material, labor, machinery and T&P all
complete required for proper completion of
work as per specification No.508 MoRT&H
specification for Road and Bridge Works (Latest
Edition) all complete, as per direction of
Engineer-in-change.
7. Providing. Fitting and fixing mild steel railing Rm 78
complete as per drawing and technical
specifications.
8. Repair of steel railing to bring it to the original Rm 120
shape. It is assumed that the damage to the
steel railing is to the extent of 10 percent.
MoRT&H Specification No.1623
9. Providing and laying of hot applied Sqm. 625
thermoplastic paint of 2.5 mm thickness of
uniform finish with thermoplastic paint
conforming to BS 3262 (Part-1) 1989, with
machine of Bituminous surface in white/yellow
colour and super imposed with reflect rising
glass beads conforming to BS 7088, including
cleaning the surface of all dirt, seals, oils,
grease and foreign material and spraying of
reflect rising glass beads @ 250 gm/sqm,
guarding, barricading, etc. al complete including
all taxes as per direction of Engineer- in-change
and as per specification NO. 803 MORT&H
specification for road and bridge work (latest
edition)
 