PROPOSED CONVERSION AND SUBDIVISION MIXED

DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL


ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS,
PENAMPANG, SABAH
PROJECT TITLE

MONTHLY PROGRESS REPORT 14

PERIOD : 1ST MAY 31ST MAY 2016

CLIENT : MEGACITY DEVELOPMENT SDN. BHD.

CONSULTANTS

ARCHITECT : ARKITEK TM

CIVIL & STRUCTURAL ENGINEER : GEO-EXCEL CONSULTANTS SDN. BHD.


: JURUTER PERUNDING BUMIREKA.

MECHANICAL & ELECTRICAL : IP CONSULTANTS SDN. BHD.

QUANTITY SURVEYOR : CE TECHNICAL SERVICES SDN. BHD.

SUBMITTED BY
MAIN CONTRACTOR : BINA PYK (SABAH) SDN BHD
PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH

CLIENT MEGACITY DEVELOPMENT SDN BHD


NO 1A, LORONG DELAPAN MR MICHAEL CHIN
88300 KOTA KINABALU.
TEL : 088-311111
FAX : 088-726111
CONSULTANTS
ARCHITECT ARKITEK TM
NO 2, LORONG IKAN LAIS AR YEE TAH MIN
JALAN MAT SALLEH, TANJUNG ARU MR PETER LIN
P.O. BOX 16135, 88869 KOTA KINABALU, SABAH. MR FOR WEIHAN
TEL: 088-236245
FAX: 088-214902

CIVIL & GEO-EXCEL CONSULTANTS SDN BHD


STRUCTURAL 66-3, JALAN RADIN TENGAH, IR CHONG CHEE MENG
ENGINEER BANDAR BARU SRI PETALING, MR KWAN YUNFATT
57000 KUALA LUMPUR
TEL: 03-9058 8735/36
FAX: 03-9058 8739
JURUTERA PERUNDING BUMIREKA
LOT 27-2, 2ND FLOOR, BLOCK C, IR BENNY SONG
BUNDUSAN COMMERCIAL CENTRE, MS HII
JALAN BUNDUSAN, 88300 KOTA KINABALU
TEL: 088-713150
FAX: 088-713015

MECHANICAL & IP CONSULTANTS SDN BHD


ELECTRICAL 3RD FLOOR, LOT NO 88, JALAN GAYA IR JENNY KOO
ENGINEER P.O. BOX 22417 MR YAP KIM LEONG
88000 LUYANG KOTA KINABALU, SABAH.
TEL: 088-252230
FAX: 088-230242

QUANTITY CE TECHNICAL SERVICES SDN BHD


SURVEYOR SUITE 10, 8TH FLOOR WISMA PERINDUSTRIAN MR EDWARD VUN
JALAN ISTIADAT, LIKAS MDM MARIA
88400, KOTA KINABALU
TEL : 088-236148
FAX : 088-246149

MAIN BINA PYK (SABAH) SDN BHD MR KHOO SOON POH


CONTRACTOR LOT C10, BLOCK C, LORONG CYBER SQUARE 2 MR JASON LIEW
CYBER SQUARE, JALAN LINTAS, KEPAYAN MR FRANCIS LIEW
88200 KOTA KINABALU MR RICKEY SOH SWEE LOONG
TEL : 088-220060 MR SIAK HUAT SENG
FAX : 088-220070
PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH

CONTENTS
1 PROJECT SUMMARY

2 ORGANIZATION CHART

3 MASTER WORK PROGRAMME

4 WORK & FINANCIAL PROGRESS S-CURVE

5 SUMMARY OF WORKDONE

6 LABOUR FORCE CHART

7 WEATHER CHART

8 REQUEST FOR INFORMATION SUMMARY

9 CONSULTANT INSTRUCTION SUMMARY

10 NON CONFORMANCE REPORT SUMMARY

11 VARIATION ORDER

12 MATERIAL ON SITE

13 SITE PLAN

14 SITE PROGRESS PHOTOGRAPHS

15 SAFETY REPORT
PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH

PROJECT SUMMARY

PROJECT NAME PROPOSED CONVERSION AND SUBDIVISION MIXED


DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF LINTAS ROAD,
PENAMPANG SABAH, MALAYSIA.

FOR MESSR MEGACITY DEVELOPMENT SDN BHD

DEVELOPER MEGACITY DEVELOPMENT SDN BHD

ARCHITECT ARKITEK TM

CIVIL & STRUCTURAL GEO-EXCEL CONSULTANTS SDN BHD


CONSULTANT
JURUTERA PERUNDING BUMIREKA

MECHANICAL & IP CONSULTANTS SDN BHD


ELECTRICAL CONSULTANT

QUANTITY SURVEYOR CE TECHNICAL SERVICES SDN BHD

MAIN CONTRACTOR BINA PYK (SABAH) SDN BHD

DATE OF COMMENCEMENT 1ST JUNE 2014

DATE OF COMPLETION 20TH OCTOBER 2016

CONTRACT PERIOD 29 MONTH

REPORT DATE 31ST MAY 2016

DAYS [AHEAD/(DELAY)] 12 DAYS


PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL ON NT.
2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH

PROJECT ORGANISATION CHART


Reference Number : PYK/LIDO/G/OC/04-15/01

Client
Mega City Development Sdn. Bhd. Quantity Surveyor
Mr. Michael Chin CE Technical Services Sdn. Bhd.
HP: 019 - 812 2678 Mr. Edward Vun
Tel: 6088 - 311 111 HP: 013 - 850 8148
Fax: 6088 - 726 111 Tel: 6088 - 236 148
michael@megacitydevelopment.com
Fax: 6088 - 246 149
cetechservices03@gmail.com

ARCHITECT

C & S ENGINEER Arkitek TM M & E ENGINEER


Ar. Yee Tah Min
IP Consultants Sdn. Bhd.
Geo-Excel Consultants Sdn. Bhd. HP: 019 - 810 0240
Ir. Jenny Koo
Ir. Chong Chee Meng Tel: 6088 - 236 245
HP: 016 - 835 1011
HP: 012 - 827 8891 Fax: 6088 - 214 902
Tel: 6088 - 252 230
arkitektm@yahoo.com
Tel: 603 - 9058 8735/36 Fax: 6088 - 230 242
Fax: 603 - 9058 8739 ipcosb@gmail.com
c2_meng@yahoo.com Mr. For Wei Han
HP: 016 - 832 5365
Mr. Yap Kim Leong
weihan@megacitydevelopment.com
Jurutera Perunding Bumireka HP: 016 - 832 2278
Ir. Benny Song klyap@megacitydevelopment.com
HP: 012 - 827 8891 MAIN CONTRACTOR
Tel: 6088 - 713 150
Fax: 6088 - 713 015 BINA PYK Sdn. Bhd.
bumireka@gmail.com Mr. Francis Liew
HP: 016 - 232 2288
Mr. Kwan Tel: 6088 - 220 060
HP: 016 - 832 1391 Fax: 6088 - 220 070
yfkwan@megacitydevelopment.com projectsabah.pyk@gmail.com

Mr. Siak Huat Seng


HP: 016 - 810 9281
michaelsiak@gmail.com
PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND
RESIDENTIAL ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH

SITE ORGANISATION CHART


Reference Number : PYK/LIDOA/HQ/G/OC/09-15/01

BINA PYK SDN BHD


CONTACT US
HQ TEL : +603 - 7980 7236
FAX : +603 - 7980 7234

DIRECTORS KK TEL : +6088 - 220 060


FAX : +6088 - 220 070
MR KHOO SOON POH MR JASON LIEW MOBILE : +6016 - 810 7781

PROJECT DIRECTOR SITE TEL : +6088 - 739 711


MR FRANCIS LIEW FAX : +6088 - 738 711
016 - 232 2288
projectsabah.pyk@gmail.com

PROJECT MANAGER
MR RICKEY SOH SWEE LOONG
016 - 222 8919 QS
SAFETY OFFICER rickysoh.pyk@gmail.com
OSH PERDANA MR ANDERSON YAP
MR CYRIL DARYL CONSTRUCTION MANAGER 016 - 833 8264
017 - 821 9322 MR SIAK HUAT SENG anderson.pyk@gmail.com
Darylcyril@gmail.com 016 - 810 9281
michaelsiak@gmail.com

STRUCTURE COORDINATOR STRUCTURAL ENGINEER ARCHITECTURE COORDINATOR M&E COORDINATOR


MR SYLVESTER HARRY GINTANAU MS CHARLISA ANNIE CHARLES MR STANLEY LAPIS MR KENNETH LYE
016 - 860 0828 016 - 888 9960 016 - 888 9256 016 - 333 7571
sylvesterhg.pyk@gmail.com charlisa.pyk@gmail.com stanleylapis.pyk@gmail.com kenneth.pyk@gmail.com
STRUCTURAL SUPERVISOR STRUCTURAL COORDINATOR SENIOR ARCHITECTURAL ARCHITECTURAL COORDINATOR
MR MOHD. KHADZRIN AFI MR ANUAR BIN WASIMIN SUPERVISOR MR MOHD JAFRI
016 - 888 4900 016 - 810 4845 MR LAU PENG KAM 016 - 810 4192
afe.pyk@gmail.com anuar.pyk@gmail.com 016 - 810 8492 jafribunot.pyk@gmail.com
SENIOR SAFETY SUPERVISOR STRUCTURAL SUPERVISOR INFRASTRUCTURE COORDINATOR JUNIOR SAFETY SUPERVISOR
MR JOSEPH PARDI MR JULLSON BIN GITOM MR PETER PARDI
016 - 810 6081
MR WALTER LIM 016 - 810 8982
016 - 810 0208
joseph.pyk@gmail.com jullson.pyk@gmail.com 016 - 810 4175 peter.pyk@gmail.com

STRUCTURAL & ARCHITECTURAL WORKS


CONTRACTOR / SPECIALIST
CONCRETOR CARPENTER BAR BENDER
EVERBEST m&e services RIGAP MAJU WX STEEL CONSTRUCTION
MR LIEW CHEE WAH MR LEE AH LEONG MR NG WEN XIONG
010 - 226 6621 016 - 386 0291 012 - 285 2515
MASONRY PLASTER CEILING & SKIM COAT WORKS
EVERBEST m&e services CREATIVE PLASTER
MR LIEW CHEE WAH MR LIM YEW HUAT
010 - 226 6621 016 - 668 7351
PAINTING WORKS IRON WORKS SANITARYWARES SUPPLIER ALUMINIUM & GLAZING WORKS
UNI DECOR YU SENG IRAS BUMI INSPIRE CONTRACTOR
MR SO CHAI THIAM MR YAP SAW NAM MR BILLY LIAW MR DANNY CHONG
019 - 334 7815 016 - 837 1997 016 - 833 9897 019 - 851 8420
decor_spray@hotmail.com yusengcon@hotmail.com irasbumi@yaho.com chongnyetfan@gmail.com

LAMINATED FLOOR BOARD WATER PROOFING TILE SUPPLIER


MY FLOORING RNC TECHNOLOGY (SABAH) IMAGE STONE DECOR (S)
MR ALEX LOO MR TAM YOON MENG MDM JENNY LEE
016 - 831 9211 012 - 205 7608 016 - 830 8751
myflooringkk@yahoo.com ymtam13@gmail.com Ljn1608lee@yahoo.com

MECHANICAL & ELECTRICAL CONTRACTOR

VERTICAL TRANSPORTATION
FIRE PROTECTION SYSTEM
ELECTRICAL & TELEPHONE MS ELEVATOR
CARD ACCESS, PUBLIC ADDRESS, TYL FIRE FIGHTING MS EUNICE
VIDEO INTERCOM, CCTV, PABX, COLD WATER & 012 - 370 3117
SANITARY PLUMBING & RWDP MR TAN YIN LIANG
BARRIER GATE & HD-SMATV 016 - 290 1688 yitmk@msee.com.my

SAJA CAHAYA KINTA SEJATI yltan5370@yahoo.com


MR BOBEN JELOSON
MR FO YING FOH MR LEONG WING FOCK 019 - 884 4871
019 - 821 4030 019 - 222 4696 boben@msee.com.my
sajasb@yahoo.com wfleong168@gmail.com AIR CONDITIONAL SYSTEM
kintasb@gmail.com SWIMMING POOL SYSTEM
MR CHRISTOPHER PANG EVERBEST m&e services
012 - 282 1138 MR LIEW CHEE WAH
chrisphy@hotmail.com 010 - 226 6621 BORNEO WATERLAND
robertliew88@gmail.com MR SEAN WONG
vincentteo74@yahoo.com 017 - 220 6765
PROPOSED CONVERSION AND SUBDIVISION OF MIXED DEVELOPMENT OF COMMERCIAL AND SERVICED APARTMENT WITH STRATA TITLES TO BE APPLIED FOR ON NT. 213190044 (NT. 4602) OFF JALAN LINTAS, PENAMPANG, SABAH.

Main Contract - 2 - Preliminary Master Programme - After Piling Contractor Hand Over Date: 16-11-2014
2014 2015 2016
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 Month 13 Month 14 Month 15 Month 16 Month 17 Month 18 Month 19 Month 20 Month 21 Month 22 Month 23 Month 24 Month 25 Month 26 Month 27 Month 28 Month 29
Item Task
Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40 W41 W42 W43 W44 W45 W46 W47 W48 W49 W50 W51 W52 W53 W54 W55 W56 W57 W58 W59 W60 W61 W62 W63 W64 W65 W66 W67 W68 W69 W70 W71 W72 W73 W74 W75 W76 W77 W78 W79 W80 W81 W82 W83 W84 W85 W86 W87 W88 W89 W90 W91 W92 W93 W94 W95 W96 W97 W98 W99 W100W101W102W103W104W105W106W107W108W109W110W111W112W113W114W115 W116

1 Site Survey / Setting Out 5 5


2 Erect Tower Crane 2 2 2 2 2

3 Structure - Amber Tower ONLY


3.1 Podium Structure (L1-5) 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
3.2 Level 6 - Transfer Beam 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
3.3 Tower Shear Wall 3.3 3.3 3.3
3.4 Tower Structure (L7-24) 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 1.3
3.5 Penthouse Structure (L25-26) 1.7 1.7 1.7 1.7 1.7 1.7
4 Architectural - Amber Podium
4.1 Power Floating to Car Park Flooring 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
4.2 Setting Out & Brickwall 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.5
4.3 M&E Concealed Works 1 1 1 1 1 1 1 1 1 1
4.4 RWDP 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
4.5 Erect Door Frame & Window Sub-frame 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
4.6 Internal Plastering / Skim Coat 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
4.7 External Plastering 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.8
4.8 Staircase Railing 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 1.2
4.9 Staircase Nosing Tile 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
4.10 Painting 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.8
4.11 Door Panel & Inner Frame Installation 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
4.12 Installation Fittings & Fixture 2.5 2.5 2.5 2.5
4.13 Shop Lot Finishes 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.9
4.14 Car Park Lobbies Finishes 1..251..261..271..281..291..301..311..32
4.15 Grand Lobby ID Works 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8
5 Architectural - Amber Tower
5.1 Shear Wall Setting Out & Brickwall 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.4
5.2 M&E Concealed Works 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.1
5.3 RWDP 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.1
5.4 Erect Door Frame & Window Sub-frame 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.1
5.5 Internal Plastering / Skim Coat 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
5.6 External Plastering 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
5.7 Bathroom Waterproofing 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
5.8 Tiling 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.1 0.3 0.3 0.3 0.3 0.3 0.3 0.3
5.9 Ceiling 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.1
5.10 Counter Top Finished 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4
0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.3
5.11 Shower Screen 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
5.12 Balcony Glass Railing 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
5.13 Balcony Waterproofing 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.8
5.14 Door Panel & Inner Frame Installation 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6
5.15 Laminated Flooring 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.8
5.16 Painting 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.4
5.17 Staircase Railing 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.5
5.18 Staircase Nosing Tile 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
5.19 Installation Fittings & Fixture 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.9
5.20 Corridor & Refuse Bin Finishes 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.9
5.21 Lift Lobbies Finishes 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
5.22 External Louvre Screen 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6
6 Roof Top
6.1 Roof Structure 1.7 1.7 1.7 1.7 1.7 1.7
6.2 Lift Motor Room 2.5 2.5 2.5 2.5
6.3 Metal Roofing 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1
6.4 Upper Roof Structure 2 2 2 2 2
6.5 Mason Works 1.7 1.7 1.7 1.7 1.7 1.7
6.6 Flat Roof Waterproofing 2.5 2.5 2.5 2.5
6.7 Roof Top Finishes 1.4 1.4 1.4 1.4 1.4 1.4 1.4

7 Structure - Ruby Tower ONLY


7.1 Podium Structure 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
7.2 Level 6 - Transfer Beam 1.7 1.7 1.7 1.7 1.7 1.7
7.3 Level 6 Swimming Pool 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
7.4 Tower Shear Wall 3.3 3.3 3.3
7.5 Tower Structure 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4
7.6 Penthouse Structure 1.7 1.7 1.7 1.7 1.7 1.7
8 Architectural - Ruby Podium
8.1 Power Floating to Car Park Flooring 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
8.2 Setting Out & Brickwall 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.9
8.3 M&E Concealed Works 1 1 1 1 1 1 1 1 1 1
8.4 RWDP 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6
8.5 Erect Door Frame & Window Sub-frame 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
8.6 Internal Plastering / Skim Coat 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.6
8.7 External Plastering 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6
8.8 Staircase Railing 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
8.9 Staircase Nosing Tile 2.5 2.5 2.5 2.5
8.10 Painting 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.8
8.11 Door Panel & Inner Frame Installation 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
8.12 Installation Fittings & Fixture 2.5 2.5 2.5 2.5
8.13 Shop Lot Finishes 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.9
8.14 Car Park Lobbies Finishes 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
8.15 Grand Lobby ID Works 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8
8.16 External Wall Composite Panelling 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6
9 Architectural - Ruby Tower
9.1 Shear Wall Setting Out & Brickwall 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.4
9.2 M&E Concealed Works 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.1
9.3 RWDP 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.1
9.4 Erect Door Frame & Window Sub-frame 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.1
9.5 Internal Plastering / Skim Coat 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
9.6 External Plastering 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
9.7 Bathroom Waterproofing 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
9.8 Tiling 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.1 0.3 0.3 0.3 0.3 0.3 0.3 0.3
9.9 Ceiling 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.1
9.10 Counter Top Finished 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4
0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.3
9.11 Shower Screen 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
9.12 Balcony Glass Railing 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
9.13 Balcony Waterproofing 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.8
9.14 Door Panel & Inner Frame Installation 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6
9.15 Laminated Flooring 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.8
9.16 Painting 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.4
9.17 Staircase Railing 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.4
9.18 Staircase Nosing Tile 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
9.19 Installation Fittings & Fixture 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.9
9.20 Corridor & Refuse Bin Finishes 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.9
9.21 Lift Lobbies Finishes 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
9.22 External Louvre Screen 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6
10 Roof Top
10.1 Roof Structure 1.7 1.7 1.7 1.7 1.7 1.7
10.2 Lift Motor Room 2.5 2.5 2.5 2.5
10.3 Metal Roofing 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1
10.4 Upper Roof Structure 2 2 2 2 2
10.5 Mason Works 1.7 1.7 1.7 1.7 1.7 1.7
10.6 Flat Roof Waterproofing 2.5 2.5 2.5 2.5
10.7 Roof Top Finishes 1.4 1.4 1.4 1.4 1.4 1.4 1.4
11 Common Facility & Function Room
11.1 Swimming Pool Finishes 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.9
11.2 Pool Terrace 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.9
11.3 Gym Room 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
11.4 Reading Room 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
11.5 Indoor Playground 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
11.6 Theater Room 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
11.7 Management Office 1.7 1.7 1.7 1.7 1.7 1.7
11.8 Court Yard 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
11.9 Guard House 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
11.10 Bin Center x x x x x x x x x x

12 M&E Services
12.1 Low Voltage Services 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0 0 0 0 0 0 0
12.2 Street Lighting 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.3
12.3 Extra Low Voltage 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0 0 0 0 0 0 0
12.4 Plumbing & Sanitary Services 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0 0 0 0 0 0 0
12.5 Fire Protection Services 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0 0 0 0 0 0 0
12.6 Mechanical Services 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0 0 0 0 0 0 0
12.7 Air Cond Services 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0 0 0 0 0 0 0

13 Infra Structure
13.1 Electrical Reticulation
13.2 SESB Room
13.3 Telephone Infra
13.4 Water Reticulation
13.5 Sewerage System
13.6 Drainage
13.7 Road & Road Kerb

7.9 9 4 2 2 2 2 2 2.5 2.5 2.5 2.5 2.5 3.5 3.5 3.5 3.7 3.7 4.9 4.8 4.4 4.4 6.4 5.4 3.3 3.3 7.2 8.4 8.7 5.6 5.9 6.5 6.5 7.3 9.3 7.6 8.3 8.4 9.4 9.7 9.2 11 11 13 13 12 8.5 8.6 8.3 6.2 6.8 6.1 6.4 6.4 7.3 7.9 6.9 9.6 8.5 8.9 11 11 11 9.7 14 13 17 20 19 20 20 21 21 24 18 20 21 19 20 21 21 21 20 23 19 19 17 15 17 17 17 15 11 12 13 12 11 14 13 14 15 12 12 12 12 7.4 7.4 7.4 7.5 5.8 5.8 5.8 5.8 0.5 0.5 0.3
* Note:- This programme is subjected to piling contractor hand over date CHRISTMAS CNY CHRISTMAS CNY TODAY Prepare by:-
Bina PYK (Sabah) Sdn Bhd
23 7.8 9.8 13 17 20 22 27 31 36 45 43 27 28 34 42 64 81 83 81 85 71 65 48 52 50 34 25 7.3

### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
PROPOSED CONVERSION AND SUBDIVISION OF MIXED DEVELOPMENT OF COMMERCIAL AND SERVICED APARTMENT WITH STRATA TITLES TO BE APPLIED FOR ON NT. 213190044 (NT. 4602) OFF JALAN LINTAS, PENAMPANG, SABAH.

Main Contract - 2 - SITE POSSESION Master Programme WITH EOT - After Piling Contractor Hand Over Date: 16-11-2014

2014 2015 2016


Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 Month 13 Month 14 Month 15 Month 16 Month 17 Month 18 Month 19 Month 20 Month 21 Month 22 Month 23 Month 24 Month 25 Month 26 Month 27 Month 28 Month 29
Item Task
Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40 W41 W42 W43 W44 W45 W46 W47 W48 W49 W50 W51 W52 W53 W54 W55 W56 W57 W58 W59 W60 W61 W62 W63 W64 W65 W66 W67 W68 W69 W70 W71 W72 W73 W74 W75 W76 W77 W78 W79 W80 W81 W82 W83 W84 W85 W86 W87 W88 W89 W90 W91 W92 W93 W94 W95 W96 W97 W98 W99 W100 W101 W102 W103 W104 W105 W106 W107 W108 W109 W110 W111 W112 W113 W114 W115 W116

1 Site Survey / Setting Out


2 Erect Tower Crane TC1 TC2
3 Structure - Amber Tower ONLY
3.1 Podium Structure (L1-5)
3.2 Level 6 - Transfer Beam
3.3 Tower Shear Wall
3.4 Tower Structure (L7-24)
3.5 Penthouse Structure (L25-26)
4 Architectural - Amber Podium
4.1 Power Floating to Car Park Flooring
4.2 Setting Out & Brickwall
4.3 M&E Concealed Works
4.4 RWDP Stack Fittings
4.5 Erect Door Frame & Window Sub-frame
4.6 Internal Plastering / Skim Coat
4.7 External Plastering
4.8 Staircase Railing Painting
4.9 Staircase Nosing Tile
4.10 Painting
4.11 Door Panel & Inner Frame Installation
4.12 Installation Fittings & Fixture
4.13 Shop Lot Finishes
4.14 Car Park Lobbies Finishes
4.15 Grand Lobby ID Works
5 Architectural - Amber Tower
5.1 Shear Wall Setting Out & Brickwall
5.2 M&E Concealed Works
5.3 RWDP Stack Fittings
5.4 Erect Door Frame & Window Sub-frame
5.5 Internal Plastering / Skim Coat After Brickworks
5.6 External Plastering After Roof Top Structure
5.7 Bathroom Waterproofing After Wall Plastering
5.8 Tiling After Water Proofing
5.9 Ceiling After Wall Tiling
5.10 Counter Top Finished After Bathroom Wall Tiling & Ceiling
5.11 Shower Screen After Ceiling & Cleaning
5.12 Balcony Glass Railing After External Plastering
5.13 Balcony Waterproofing After External Plastering
5.14 Door Panel & Inner Frame Installation After External Plastering
5.15 Laminated Flooring After Door Panel & Window Installed
5.16 Painting Primer
5.17 Staircase Railing
5.18 Staircase Nosing Tile
5.19 Installation Fittings & Fixture After Door Installation
5.20 Corridor & Refuse Bin Finishes
5.21 Lift Lobbies Finishes
5.22 External Louvre Screen
6 Roof Top
6.1 Roof Structure
6.2 Lift Motor Room
6.3 Metal Roofing
6.4 Upper Roof Structure
6.5 Mason Works
6.6 Flat Roof Waterproofing
6.7 Roof Top Finishes
7 Structure - Ruby Tower ONLY
7.1 Podium Structure
7.2 Level 6 - Transfer Beam
7.3 Level 6 Swimming Pool
7.4 Tower Shear Wall
7.5 Tower Structure
7.6 Penthouse Structure
8 Architectural - Ruby Podium
8.1 Power Floating to Car Park Flooring
8.2 Setting Out & Brickwall
8.3 M&E Concealed Works
8.4 RWDP Stack
8.5 Erect Door Frame & Window Sub-frame
8.6 Internal Plastering / Skim Coat
8.7 External Plastering
8.8 Staircase Railing
8.9 Staircase Nosing Tile
8.10 Painting
8.11 Door Panel & Inner Frame Installation
8.12 Installation Fittings & Fixture
8.13 Shop Lot Finishes
8.14 Car Park Lobbies Finishes
8.15 Grand Lobby ID Works
8.16 External Wall Composite Panelling
9 Architectural - Ruby Tower
9.1 Shear Wall Setting Out & Brickwall
9.2 M&E Concealed Works
9.3 RWDP Stack Fittings
9.4 Erect Door Frame & Window Sub-frame
9.5 Internal Plastering / Skim Coat After Brickworks
9.6 External Plastering After Roof Top Structure
9.7 Bathroom Waterproofing After Wall Plastering
9.8 Tiling After Water Proofing
9.9 Ceiling After Wall Tiling
9.10 Counter Top Finished After Bathroom Wall Tiling & Ceiling
9.11 Shower Screen After Ceiling & Cleaning
9.12 Balcony Glass Railing After External Plastering
9.13 Balcony Waterproofing After External Plastering
9.14 Door Panel & Inner Frame Installation After External Plastering
9.15 Laminated Flooring After Door Panel & Window Installed
9.16 Painting Primer
9.17 Staircase Railing
9.18 Staircase Nosing Tile
9.19 Installation Fittings & Fixture After Door Installation
9.20 Corridor & Refuse Bin Finishes
9.21 Lift Lobbies Finishes
9.22 External Louvre Screen
10 Roof Top
10.1 Roof Structure
10.2 Lift Motor Room
10.3 Metal Roofing
10.4 Upper Roof Structure
10.5 Mason Works
10.6 Flat Roof Waterproofing
10.7 Roof Top Finishes
11 Common Facility & Function Room
11.1 Swimming Pool Finishes
11.2 Pool Terrace
11.3 Gym Room
11.4 Reading Room
11.5 Indoor Playground
11.6 Theater Room
11.7 Management Office
11.8 Court Yard
11.9 Guard House
11.10 Bin Center
12 M&E Services
12.1 Low Voltage Services
12.2 Street Lighting Concealed Works Fittings
12.3 Extra Low Voltage
12.4 Plumbing & Sanitary Services
12.5 Fire Protection Services
12.6 Mechanical Services
12.7 Air Cond Services
13 Infra Structure
13.1 Electrical Reticulation
13.2 SESB Room
13.3 Telephone Infra
13.4 Water Reticulation
13.5 Sewerage System
13.6 Drainage
13.7 Road & Road Kerb

* Note:- This programme is subjected to piling contractor hand over date Prepare by:-
TODAY CHRISTMAS CNY

Bina PYK (Sabah) Sdn Bhd


PROPOSED CONVERSION AND SUBDIVISION OF MIXED DEVELOPMENT OF COMMERCIAL AND SERVICED APARTMENT WITH STRATA TITLES TO BE APPLIED FOR ON NT. 213190044 (NT. 4602) OFF JALAN LINTAS, PENAMPANG, SABAH.

Main Contract - 2 - Preliminary Master Programme (Rev 1) Date: 29-4-2015


2014 2015 2016
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 Month 13 Month 14 Month 15 Month 16 Month 17 Month 18 Month 19 Month 20 Month 21 Month 22 Month 23 Month 24
Item Task
Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40 W41 W42 W43 W44 W45 W46 W47 W48 W49 W50 W51 W52 W53 W54 W55 W56 W57 W58 W59 W60 W61 W62 W63 W64 W65 W66 W67 W68 W69 W70 W71 W72 W73 W74 W75 W76 W77 W78 W79 W80 W81 W82 W83 W84 W85 W86 W87 W88 W89 W90 W91 W92 W93 W94 W95 W96

1 Site Survey / Setting Out


2 Erect Tower Crane
3 Structure - Amber Tower ONLY
3.1 Podium Structure (L1-5)
3.2 Level 6 - Transfer Beam
3.3 Tower Shear Wall
3.4 Tower Structure (L7-24)
3.5 Penthouse Structure (L25-26)
4 Architectural - Amber Podium
4.1 Power Floating to Car Park Flooring
4.2 Setting Out & Brickwall
4.3 M&E Concealed Works
4.4 RWDP Stack Fittings
4.5 Erect Door Frame & Window Sub-frame
4.6 Internal Plastering / Skim Coat
4.7 External Plastering
4.8 Staircase Railing
4.9 Staircase Nosing Tile
4.10 Painting
4.11 Door Panel & Inner Frame Installation
4.12 Installation Fittings & Fixture
4.13 Shop Lot Finishes
4.14 Car Park Lobbies Finishes
4.15 Grand Lobby ID Works
5 Architectural - Amber Tower
5.1 Shear Wall Setting Out & Brickwall
5.2 M&E Concealed Works
5.3 RWDP Stack Fittings
5.4 Erect Door Frame & Window Sub-frame
5.5 Internal Plastering / Skim Coat After Brickworks
5.6 External Plastering After Roof Top Structure
5.7 Bathroom Waterproofing After Wall Plastering
5.8 Tiling After Water Proofing
5.9 Ceiling After Wall Tiling
5.10 Counter Top Finished After Bathroom Wall Tiling & Ceiling
5.11 Shower Screen After Ceiling & Cleaning
5.12 Balcony Glass Railing After External Plastering
5.13 Balcony Waterproofing After External Plastering
5.14 Door Panel & Inner Frame Installation After External Plastering
5.15 Laminated Flooring After Door Panel & Window Installed
5.16 Painting Primer
5.17 Staircase Railing
5.18 Staircase Nosing Tile
5.19 Installation Fittings & Fixture After Door Installation
5.20 Corridor & Refuse Bin Finishes
5.21 Lift Lobbies Finishes
5.22 External Louvre Screen
6 Roof Top
6.1 Roof Structure
6.2 Lift Motor Room
6.3 Metal Roofing
6.4 Upper Roof Structure
6.5 Mason Works
6.6 Flat Roof Waterproofing
6.7 Roof Top Finishes
7 Structure - Ruby Tower ONLY
7.1 Podium Structure
7.2 Level 6 - Transfer Beam
7.3 Level 6 Swimming Pool
7.4 Tower Shear Wall
7.5 Tower Structure
7.6 Penthouse Structure
8 Architectural - Ruby Podium
8.1 Power Floating to Car Park Flooring
8.2 Setting Out & Brickwall
8.3 M&E Concealed Works
8.4 RWDP Stack
8.5 Erect Door Frame & Window Sub-frame
8.6 Internal Plastering / Skim Coat
8.7 External Plastering
8.8 Staircase Railing
8.9 Staircase Nosing Tile
8.10 Painting
8.11 Door Panel & Inner Frame Installation
8.12 Installation Fittings & Fixture
8.13 Shop Lot Finishes
8.14 Car Park Lobbies Finishes
8.15 Grand Lobby ID Works
8.16 External Wall Composite Panelling
9 Architectural - Ruby Tower
9.1 Shear Wall Setting Out & Brickwall
9.2 M&E Concealed Works
9.3 RWDP Stack Fittings
9.4 Erect Door Frame & Window Sub-frame
9.5 Internal Plastering / Skim Coat After Brickworks
9.6 External Plastering After Roof Top Structure
9.7 Bathroom Waterproofing After Wall Plastering
9.8 Tiling After Water Proofing
9.9 Ceiling After Wall Tiling
9.10 Counter Top Finished After Bathroom Wall Tiling & Ceiling
9.11 Shower Screen After Ceiling & Cleaning
9.12 Balcony Glass Railing After External Plastering
9.13 Balcony Waterproofing After External Plastering
9.14 Door Panel & Inner Frame Installation After External Plastering
9.15 Laminated Flooring After Door Panel & Window Installed
9.16 Painting Primer
9.17 Staircase Railing
9.18 Staircase Nosing Tile
9.19 Installation Fittings & Fixture After Door Installation
9.20 Corridor & Refuse Bin Finishes
9.21 Lift Lobbies Finishes
9.22 External Louvre Screen
10 Roof Top
10.1 Roof Structure
10.2 Lift Motor Room
10.3 Metal Roofing
10.4 Upper Roof Structure
10.5 Mason Works
10.6 Flat Roof Waterproofing
10.7 Roof Top Finishes
11 Common Facility & Function Room
11.1 Swimming Pool Finishes
11.2 Pool Terrace
11.3 Gym Room
11.4 Reading Room
11.5 Indoor Playground
11.6 Theater Room
11.7 Management Office
11.8 Court Yard
11.9 Guard House
11.10 Bin Center
12 M&E Services
12.1 Low Voltage Services
12.2 Street Lighting Concealed Works Fittings
12.3 Extra Low Voltage
12.4 Plumbing & Sanitary Services
12.5 Fire Protection Services
12.6 Mechanical Services
12.7 Air Cond Services
12.8 Swimming Pool Specialist
12.9 Vertical Transportation Services
13 Infra Structure
13.1 Electrical Reticulation
13.2 SESB Room
13.3 Telephone Infra
13.4 Water Reticulation
13.5 Sewerage System
13.6 Drainage
13.7 Road & Road Kerb
13.8 Fecing

* Note:- This programme is subjected to piling contractor hand over date Prepare by:-

Bina PYK (Sabah) Sdn Bhd


LIDO AVENUE
93,591,588.57

Planned Workdone Amount (1) Actual Workdone Amount (2)


Construction
Period Monthly Monthly
'S' Curve (Months)
% Adjustment for
'S' Curve
Cummulative
Amount
Monthly Net
Amount
Cummulative
Amount
Monthly Net
Amount
0 - - - -
1 1.95% 1.95% 1,822,236.23 1,822,236.23 1,081,631.90 1,081,631.90
100.00 2 2.62% 0.67% 2,449,379.86 627,143.64 1,680,422.21 598,790.31
Millions

3 3.46% 0.84% 3,236,509.12 787,129.26 2,939,923.36 1,259,501.15


4 4.56% 1.10% 4,263,616.81 1,027,107.69 4,959,731.60 2,019,808.24
90.00 5 6.01% 1.45% 5,623,494.60 1,359,877.78 6,487,310.16 1,527,578.56
6 7.75% 1.74% 7,255,347.93 1,631,853.34 8,776,034.08 2,288,723.92
7 9.64% 1.88% 9,019,189.41 1,763,841.48 12,094,170.22 3,318,136.14
8 11.92% 2.29% 11,160,596.95 2,141,407.54 14,217,651.43 2,123,481.21
80.00
9 14.56% 2.63% 13,622,375.71 2,461,778.75 17,894,111.93 3,676,460.50
10 17.62% 3.06% 16,490,917.90 2,868,542.19 18,726,937.56 832,825.63
11 21.42% 3.80% 20,051,397.91 3,560,480.01 21,904,976.27 3,178,038.71
70.00 12 25.08% 3.65% 23,469,490.71 3,418,092.80 23,111,163.76 1,206,187.49
13 27.42% 2.35% 25,665,693.33 2,196,202.62 26,432,326.07 3,321,162.31
14 29.81% 2.39% 27,904,292.14 2,238,598.81 28,564,358.05 2,132,031.98
60.00 15 32.71% 2.90% 30,617,648.28 2,713,356.14 30,309,785.69 1,745,427.64
16 36.31% 3.60% 33,986,145.54 3,368,497.26 34,412,176.23 4,102,390.54
Contract Value

17 41.75% 5.44% 39,075,288.16 5,089,142.62 39,720,477.88 5,308,301.65


50.00 18 48.64% 6.89% 45,520,308.92 6,445,020.76 47,514,065.39 7,793,587.51
(RM)

19 55.73% 7.09% 52,160,512.14 6,640,203.22 52,523,541.59 5,009,476.20


20 62.64% 6.90% 58,622,331.39 6,461,819.25 59,514,395.27 6,990,853.68
Planned
21 69.91% 7.27% 65,428,919.66 6,806,588.27 63,546,078.07 4,031,682.80
40.00
22 75.96% 6.05% 71,090,410.84 5,661,491.18 68,892,329.95 5,346,251.88
Series2 23 81.55% 5.60% 76,328,340.08 5,237,929.25 72,415,746.97 3,523,417.02
24 85.63% 4.08% 80,143,997.16 3,815,657.07 81,437,043.00 9,021,296.03
30.00 25 90.06% 4.43% 84,289,224.61 4,145,227.45
26 94.33% 4.27% 88,285,665.43 3,996,440.82
27 97.25% 2.91% 91,013,420.28 2,727,754.85
20.00 28 99.38% 2.13% 93,010,840.76 1,997,420.48
29 100.00% 0.62% 93,591,588.57 580,747.81

10.00

-
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

Construction Period
(Months)

Construction Period (Months) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 29

Planned Workdone Series 1 (RM)


Monthly Cummulative Amount (mil) 1.82 2.45 3.24 4.26 5.62 7.26 9.02 11.16 13.62 16.49 20.05 23.47 25.67 27.90 30.62 33.99 39.08 45.52 52.16 58.62 65.43 71.09 76.33 80.14 84.29 88.29 91.01 93.59
Monthly Net Amount (mil) 1.82 0.63 0.79 1.03 1.36 1.63 1.76 2.14 2.46 2.87 3.56 3.42 2.20 2.24 2.71 3.37 5.09 6.45 6.64 6.46 6.81 5.66 5.24 3.82 4.15 4.00 2.73 0.58
Actual Workdone Series 2 (RM)
Monthly Cummulative Amount (mil) 1.08 1.68 2.94 4.96 6.49 8.78 12.09 14.22 17.89 18.73 21.90 23.11 26.43 28.56 30.31 34.41 39.72 47.51 52.52 59.51 63.55 68.89 72.42 81.44
Monthly Net Amount (mil) 1.08 0.60 1.26 2.02 1.53 2.29 3.32 2.12 3.68 0.83 3.18 1.21 3.32 2.13 1.75 4.10 5.31 7.79 5.01 6.99 4.03 5.35 3.52 9.02
Overall Progress Of Workdone 1% 2% 3% 5% 7% 9% 13% 15% 19% 20% 23% 25% 28% 31% 32% 37% 42% 51% 56% 64% 68% 74% 77% 87%
Ahead/Delay in % of value -1.26% -1.31% -0.51% 1.19% 0.92% 1.62% 3.29% 3.27% 4.56% 2.39% 1.98% -0.38% 0.82% 0.71% -0.33% 0.46% 0.69% 2.13% 0.39% 0.95% -2.01% -2.35% -4.18% 1.38%
Ahead/Delay in number of day (ave) -11 -11 -4 10 8 14 29 28 40 21 17 -3 7 6 -3 4 6 19 3 8 -18 -20 -36 12
Periodic Table For Site Progress
(Lido Avenue)
Commencement Date 1st JUNE 2014
Date (Today) 31st MAY 2016
%
Overall Percentage of Work Done 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 87
Structural 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 100
Architectural 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 95
Mechanical & Electrical Services 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 79
Infrastructure 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 75

Scheduled of Percentage Work Done 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 84

Progress of Percentage Work Done 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 87

Schedule Ahead/Delay (Numbers of Day) 10 Days

Completion Date 30th APRIL 2016


Extended Of Time (Days) 204 Days

Completion Date with EOT 20th OCTOBER 2016


LABOUR FORCE SCHEDULE
Lido Avenue
BINA PYK (Sabah) SDN BHD

PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH
Date:

Month MAY 2016


Week Week 1 Week 2 Week 3 Week 4
Item Description
Day Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue
Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

1 Site staffs 3 20 20 20 20 20 20 7 20 20 20 20 20 20 8 20 20 20 20 20 20 4 20 20 20 20 20 20 3 3 3
2 General worker 10 89 79 73 74 83 81 48 83 84 84 83 81 79 63 90 79 84 79 87 83 33 82 90 93 98 79 94 61 10 10
3 Concretor
4 Carpenter 0 9 9 9 9 9 9 0 9 9 9 9 9 9 0 9 9 9 9 9 9 0 9 9 9 9 9 9 0 0 0
5 Bar-bender 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 0 0
6 Screeding 0 2 2 2 2 2 2 0 2 2 2 2 2 2 0 2 2 2 2 2 2 0 2 2 2 2 2 2 0 0 0
7 Plasterer
8 Bricks layer
9 Power float floor hardener
10 Tiler 0 16 16 16 16 16 16 0 16 16 16 16 16 16 0 16 16 16 16 16 16 0 16 16 16 16 16 16 0 0 0
11 Steel work 0 5 5 5 5 5 5 0 5 5 5 5 5 5 0 5 5 5 5 5 5 0 5 5 5 5 5 5 0 0 0
12 Marble installer
13 Skim coat 0 3 3 3 3 3 3 0 3 3 3 3 3 3 0 3 3 3 3 3 3 0 3 3 3 3 3 3 0 0 0
14 Plaster Ceiling installer 0 14 14 14 14 14 14 0 14 14 14 14 14 14 0 14 14 14 14 14 14 0 14 14 14 14 14 14 0 0 0
15 Timber flooring 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 0 0
16 Curtain wall & glazing 0 24 24 24 24 24 24 0 24 24 24 24 24 24 0 24 24 24 24 24 24 0 24 24 24 24 24 24 0 0 0
17 Carpentry & ironmongery 0 10 10 10 10 0 10 10 10 10 10 10 0 10 0 10 10 10 10 0 10 0 10 10 10 10 0 10 10 0 0
18 Rain water down pipe installer
19 Painter 0 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43
20 Plumber 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15
21 Air-Conditioning installer 0 5 5 5 5 5 5 0 5 5 5 5 5 5 0 5 5 5 5 5 5 0 5 5 5 5 5 5 0 0 0
22 Electrician 0 35 35 35 35 35 35 0 35 35 35 35 35 35 0 35 35 35 35 35 35 0 35 35 35 35 35 35 0 0 0
23 Fire Protection installer 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 0 0
24 Swimming pool
25 Lift installer 0 16 16 16 16 16 16 0 16 16 16 16 16 16 0 16 16 16 16 16 16 0 16 16 16 16 16 16 0 0 0
26 Security 2 2 2 2 3 2 2 2 2 2 2 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

30 332 322 316 317 316 324 125 326 327 327 328 314 322 131 313 302 307 302 320 326 97 325 333 336 341 312 337 134 73 73
Architect Request For Information Summary

Date Descriptions Status Remark


13/11/2013 LA/RFI/ARC/01 REPLIED
26/9/2014 LA/RFI/ARC/02 REPLIED
23/11/2015 LA/RFI/ARC/03 Submission of proposed rainwater downpipe PENDING
16/2/2016 LA/RFI/ARC/04 Level 15 type C1, dry yard finishes REPLIED
16/2/2016 LA/RFI/ARC/05 Concrete kerb height for U Channel for level 26 & 27 REPLIED
19/2/2016 LA/RFI/ARC/06 Entrance finish level type C1 Ruby & Amber level 15 REPLIED
4/3/2016 LA/RFI/ARC/07 Store room partition and door position for ruby penthouse C L25 PENDING
4/3/2016 LA/RFI/ARC/08 Window schedule for ruby penthouse C Level 26 PENDING
17/3/2016 LA/RFI/ARC/09 Type of ceiling and height for Ruby & Amber Penthouse A,B,C PENDING
17/3/2016 LA/RFI/ARC/10 Detail of grille doors for CO2 compartment, ground floor PENDING
22/3/2016 LA/RFI/ARC/11 Car park marking and necessary signages (Internal) PENDING
22/3/2016 LA/RFI/ARC/12 Car park marking and necessary signages (External) PENDING
C&S Request For Information Summary

Date Descriptions Status Approval Approval Date


13/11/2013 LA/RFI/C&S/01 REPLIED
2/6/2014 LA/RFI/C&S/05 REPLIED
26/9/2014 LA/RFI/C&S/08 REPLIED
20/10/2014 LA/RFI/C&S/09 REPLIED
22/10/2014 LA/RFI/C&S/10 REPLIED
31/10/2014 LA/RFI/C&S/11 REPLIED
13/11/2014 LA/RFI/C&S/12 REPLIED
15/11/2014 LA/RFI/C&S/13 REPLIED
5/12/2014 LA/RFI/C&S/14 REPLIED
8/12/2014 LA/RFI/C&S/15 REPLIED
10/12//2014 LA/RFI/C&S/16 REPLIED
6/1/2015 LA/RFI/C&S/17 REPLIED
19/1/2015 LA/RFI/C&S/18 REPLIED
28/1/2015 LA/RFI/C&S/19 REPLIED
18/4/2015 LA/RFI/C&S/20 REPLIED
25/4/2015 LA/RFI/C&S/21 PENDING
29/4/2015 LA/RFI/C&S/22 REPLIED
12/5/2015 LA/RFI/C&S/23 REPLIED
3/7/2015 LA/RFI/C&S/24 REPLIED
9/7/2015 LA/RFI/C&S/25 REPLIED
15/10/2015 LA/RFI/C&S/26 REPLIED
22/10/2015 LA/RFI/C&S/27 REPLIED
6/11/2015 LA/RFI/C&S/28 REPLIED
7/11/2015 LA/RFI/C&S/29 REPLIED
9/11/2015 LA/RFI/C&S/30 REPLIED
12/11/2015 LA/RFI/C&S/31 REPLIED
24/11/2015 LA/RFI/C&S/32 REPLIED
24/11/2015 LA/RFI/C&S/33 REPLIED
27/11/2015 LA/RFI/C&S/34 REPLIED
27/11/2015 LA/RFI/C&S/35 REPLIED
30/11/2015 LA/RFI/C&S/36 REPLIED
2/12/2015 LA/RFI/C&S/37 REPLIED
3/12/2015 LA/RFI/C&S/38 REPLIED
5/12/2015 LA/RFI/C&S/39 REPLIED
7/12/2015 LA/RFI/C&S/40 REPLIED
10/12/2015 LA/RFI/C&S/41 (Prepared by Mr. Kenneth Lye) REPLIED
17/12/2015 LA/RFI/C&S/42 (Prepared by Mr. Kenneth Lye) REPLIED
19/12/2015 LA/RFI/C&S/43 REPLIED
8/1/2016 LA/RFI/C&S/44 (Prepared by Mr. Kenneth Lye) REPLIED
19/1/2016 LA/RFI/C&S/45 REPLIED
16/2/2016 LA/RFI/C&S/46 REPLIED
17/2/2016 LA/RFI/C&S/47 REPLIED
7/3/2016 LA/RFI/C&S/48 REPLIED
21/3/2016 LA/RFI/C&S/49 REPLIED
29/3/2016 LA/RFI/C&S/50 REPLIED
31/3/2016 LA/RFI/C&S/51 REPLIED
7/4/2016 LA/RFI/C&S/52 REPLIED
12/4/2016 LA/RFI/C&S/53 REPLIED
24/5/2016 LA/RFI/C&S/54 (Prepared by Mr. Kenneth Lye) REPLIED
M&E Request For Information Summary

Date Descriptions Status Approval Approval Date


13/11/2013 LA/RFI/M&E/01(REV) REPLIED
15/11/2013 LA/RFI/M&E/02 REPLIED
19/2/2014 LA/RFI/M&E/03 REPLIED
13/11/2015 LA/RFI/M&E/04_Confirmation of Fresh Air Motor REPLIED
13/11/2015 LA/RFI/M&E/05_Basin Position change at Ruby Block, Level 6, Changing Room. REPLIED

16/11/2015 LA/RFI/M&E/06_Conceal of CO2 Fire Alarm Panel at Ground Floor. REPLIED BY Letter Ref. No. 21st January, 2016
23/11/2015 LA/RFI/M&E/07_Propose of Sanitary & RWDP for Level 25 to RG2 ARCHITECT
REPLIED ATM/52P12/MC/
23/11/2015 LA/RFI/M&E/08_A/C Copper & Drain Pipe Routing at Level 6, Type A. REPLIED
23/11/2015 LA/RFI/ARC/03_Propose of RWDP for Level 25 to RG2. REPLIED
27/11/2015 LA/RFI/M&E/09_Submission of Ventilation Fan Catalogue for Approval (Iras REPLIED
Bumi) for Ruby Block, Level 6, Type A.
27/11/2015 LA/RFI/M&E/10_Shower installation at Window position at Ruby Block, Level 6, REPLIED
Male Changing Room.
28/11/2015 LA/RFI/M&E/11_Confirmation of Air Cond & Compressor position for Level 25, REPLIED
Penthouse.
7/12/2015 LA/RFI/M&E/12_Seek for A/C c/w piping Information at Level 15, Ruby Type A REPLIED
(Extension Unit) and Amber Type C (Additional Unit).
11/12/2015 LA/RFI/M&E/13_Seek for advise at the installation of Floor Trap, basin and W.C REPLIED
piping at Level 15, Ruby Type A, additional of Powder Room.
15/12/2015 LA/RFI/M&E/14_Seek for advise at the installation of Fireman Switch, Fireman REPLIED
Intercom, Hose Rell, Wet Riser System from Level 25 to 27, Ruby and Amber
Block.
5/1/2016 LA/RFI/M&E/15_Seek for confirmation for the capacity of Exhaust Fan Motor & REPLIED
Control Panel at Basement, Pump Room.
5/1/2016 LA/RFI/M&E/16_Submission of Exhaust Fan Motor & Air Grille Catalogue for REPLIED
Staircase Ventilation System
18/1/2016 LA/RFI/M&E/17_Seek for External Telephone Manhole confirmation. REPLIED
18/1/2016 LA/RFI/M&E/18_Seek for Air Craft Lighting height confirmation. REPLIED
19/1/2016 LA/RFI/M&E/19_Seek for Air Cond compressor position at Level 6, Public Toilet, REPLIED
Multi Purpose Hall, Children Playground and Gym Room.
25/1/2016 LA/RFI/M&E/20_Seek for W.C sanitary piping installation whether using S-Trap REPLIED
or P-Trap at Level 6, Changing Room.
25/1/2016 LA/RFI/M&E/20_Seek for W.C sanitary piping installation whether using S-Trap REPLIED
or P-Trap at Level 6, Changing Room.
1/3/2016 LA/RFI/M&E/21_Arrangement of PA System, CCTV System & Fire Alarm Panel at REPLIED
Ground Floor, Fire Control Room.
4/3/2016 LA/RFI/M&E/22_Bath Tub dimension at Ruby, Penthouse A, Master Bathroom. REPLIED
12/3/2016 LA/RFI/M&E/23-1_Bath Tub dimensionConfirmation of Solar Hot Water piping REPLIED
system at Ruby, Penthouse A, Master Bathroom.
LA/RFI/M&E/23-2_Additional Water Tap at Ruby, Penthouse A&B, Roof Garden.

15/3/2016 LA/RFI/M&E/24_Confirmation of Tissue Holder position for Typical Unit type REPLIED
A,B,C,D,E & F toilet.
18/3/2016 LA/RFI/M&E/25_Proposed of Bath Tub mixer position c/w dimension for REPLIED
approval.
18/3/2016 LA/RFI/M&E/26_Proposed of Spare Cold & Hot water piping at Ruby, Penthouse REPLIED
Type B and Penthouse Type A c/w dimension for approval.
18/3/2016 LA/RFI/M&E/27_Submission of MIMIC Diagram Layout for approval. REPLIED
1/4/2016 LA/RFI/M&E/28_Confirmation of Penthouse Type A, B & C Electrical Layout REPLIED
Version.
24/5/2016 LA/RFI/M&E/29_Propose of MATV Antena & Astro Satelite position for PENDING
confirmation.
24/5/2016 LA/RFI/M&E/30_Propose of Jacuzzi Air Switch Button position for confirmation. PENDING
ARKITEK TM
LIST OF ARCHITECT I NSTRUCTION ;

DATE REF NO. A.I. NO SUBJECTS


13/08/14 ATM/52P12/MC/8675 No. 1 To omit the parapet wall.
Wall for the compartments must be up to the
17/09/14 ATM/52P12/MC/8678 No. 2
soffit.

06/11/14 ATM/52P12/MC/8838 No. 3 Change of unit design.


19/12/14 ATM/52P12/MC/8900 No. 4 To thicken the 150mm Genset.
30/01/15 ATM/52P12/MC/9047 No. 5 Main Corridor Ceiling Finishes.
30/01/15 ATM/52P12/MC/9051 No. 6 Staircase 4 Window SW9 change size.
10/02/15 ATM/52P12/MC/9060 No. 7 Relocation of Staircase 1a.
06/08/15 ATM/52P12/MC/9611 No. 8 To Waterproof MSB Room Ceiling Slab.
18/08/15 ATM/52P12/MC/9657 No. 9 Sanitary Compartment Reduce In Size.

Type A Unit Enlargement and Water Tank Room


18/08/15 ATM/52P12/MC/9658 No. 10
at Level 15, Ruby Block.
SUMMARY OF C&S ENGINEER INSTRUCTION

E.I No. Date Correspondence No. Instruction Details VO Status/Remark


1 17/6/2014 SK301/EI NO 1 No bending and hacking is permitted No

2 18/8/2014 SK301/EI NO 2 Carry out core test on column 15/B No

3 5/9/2014 SK301/EI NO 3 All grade 40 concrete for column to use 3/4" granite aggregate No

4 12/9/2014 SK301/EI NO 4 Comment on striking formwork for 2A floor beam No

5 23/9/2014 SK301/EI NO 5 Informing to remove loose concrete on column C12 and call for inspection before No
performing any concrete activity
6 30/6/2015 JPB/15-166/EI/01 On wire mesh BRC Type CQ No Replied

7 7/7/2015 JPB/15-166/EI/02 On wire mesh BRC Type CQ No For Info

8 10/7/2015 JPB/15-166/EI/03 Method Statement for Shear Wall SW9 at Ruby Block L6 Type B Zone 3 No Replied

9 20/10/2015 JPB/15-166/EI/04 Swimming Pool Formwork - Beam SVB5 450 x 900/1500/1650/1500 No Replied
IP CONSULTANTS
LIST OF E NGINEER'S I NSTRUCTION :

DATE REF NO. E.I. NO SUBJECTS


V.O Orders No. 1- Additional Works for the
IPC/12.03/Memo/2014- Change of External Tel Manhole JRC7 & JB30
23/06/14 No. 1
06/190(Vol.14)
from 2 Way Ducts to 4 Way Ducts.
V.O Orders No. 2 - Additional Water Tap Point
11/07/14 IPC/12.03/Memo/2014-07/288 No. 2
for Dry Kitchen.
05/09/14 IPC/12.03/Memo/2014-08/411 No. 3 V.O Orders No. 3 - Air-Cond unit
V.O No. 4 - Additional Works for the Card Access
IPC/12.03/Memo/2014-
08/10/14 No. 4 System at Lift Lobby 1&2, Grd Flr and Staircase
06/458(Vol.5)
1&4, 6th Flr.
IPC/12.03/Memo/2014- V.O No. 5 - Amendment for the CCTVs system at
08/10/14 No. 5
06/459(Vol.5) Lift Lobby 1&2 and Guard House.
V.O Orders No. 6 - Additional Up Down Lighting
07/11/14 IPC/12.03/Memo/2014-11/849 No. 6
for Grd Floor
IPC/12.03/Memo/2014- V.O No. 7 - Omission of 6th-24th Floor Corridor
09/11/14 No. 7
06/857(Vol.6) Light.
IPC/12.03/Memo/2014- Re-Subbmission for the Material Sample Board
12/11/14 No. 7
11/482(Vol.6) of all M&E Services
IPC/12.03/Memo/2014- Changes of the Height of Acoustic Door for
05/12/14 No. 8
12/873(Vol.6) Genset Room.
V.O No. 9 - Reverse Lift#1 Opening Direction
26/01/15 IPC/12.03/Memo/2015-01/15 No. 9
from Ground to 5th Floor.
xxx No. 10 EI deleted as confirmed by IPC, Ms. Nik
11/06/15 IPC/12.03/Memo/2015-06/142 No. 11 Fresh Air at Staircase 2&3 and Lift Lobby.
Changes and Reduction of Car Park 2x36W
15/09/15 IPC/12.03/Memo/2015-09/205 No. 12
Light Fittings - 1st Floor to 5th Floor
Changes of Conceal GI Conduits for "KELUAR"
15/09/15 IPC/12.03/Memo/2015-09/206 No. 13 Signage & Emergency Light to High Impact
Heavy Duty Type UPVC Conduit.
xxx No. 14 EI deleted as confirmed by IPC, Ms. Nik
Additional of M&E Points as Indicated on
15/09/15 IPC/12.03/Memo/2015-09/208 No. 15
Attachment Layout (Ruby Tower-L15 Type A)
Additional SSO, SMATV, Lighting and Switches
15/09/15 IPC/12.03/Memo/2015-09/209 No. 16 points & Relocate and Extend Cold Water
Supply & Drain Pipe (Amber L13 Type E)
To reduce Fresh Air Ventilation Fans capacity at
14/09/15 IPC/12.03/Memo/2015-09/210 No. 17
5th Floor High Level (2 nos.)
Additional of M&E Points as Indicated on
23/11/15 IPC/12.03/Memo/2015-09/208 No. 18
Attachment Layout (Ruby Tower-L15 Type A)
Omission of Downlight and carpark fluorescent
15/02/16 IPC/12.03/Memo/2016-02/19 No. 19
light fittings.
Amber Block, Level 15, Type C1 Electrical
17/02/16 IPC/12.03/Memo/2016-02/20 No. 20
System drawing.
SUMMARY OF NON - CONFORMANCE REPORT (C&S)

NCR No. Date Correspondence No. Details Status/Remark


1 3/8/2015 LA - NCR - 001 Poor casting quality at Amber Level 6 & 7 Closed
2 23/10/2015 LA - NCR - 002 Major honeycomb at Level 17 Zone 2 SW22 Closed
3 2/11/2015 LA - NCR - 003 Poor casting quality at Ruby L22 - 23 Type C Closed
4 21/4/2016 JPB/15-166/NCR/01 Poor Compaction for Drainage and Road Works Closed
SUMMARY OF NON - CONFORMANCE REPORT (M & E)

NCR No. Date Correspondence No. Details Status/Remark


1 3/8/2015 IPC/LIDO/NCR/001 Missing point for fire alarm at Amber level 8 & Ruby level 11 and 12 Closed
2 9/9/2015 IPC/LIDO/NCR/002 Unacceptable installation of cold water pipe at Amber, Level 12, Type E. Closed
3 9/9/2015 IPC/LIDO/NCR/003 Unacceptable installation of conduit at level 6 & 7 Staircase 1 & 2. (Fire) Closed
PROPOSED CONVERSION AND SUBDIVISION OF MIXED DEVELOPMENT OF COMMERCIAL AND
SERVICED APARTMENT WITH STRATA TITLES TO BE APPLIED FOR ON NT. 213190044 (NT. 4602) OFF
JALAN LINTAS, PENAMPANG, SABAH.
PACKAGE 2
Variation Order List
No Element Reference no V.O No
PODIUM
1 LEVEL 6 STRUCTURE REDESIGN client verbal instruction V.O No. 1.1
2 ADDITIONAL RWDP AT LEVEL 6 client verbal instruction V.O No. 1.2

TOWER
ADDITIONAL FLOOR TRAP FOR LEVEL 6 TO ROOF GARDEN
1 client verbal instruction V.O No 2.1
2 UPGRADE FIRE DOOR VENEER SURFACE client verbal instruction V.O No 2.2
3 ADDITIONAL U CHANNEL AT BALCONY RAILING AREA engineer revise drawings V.O No 2.3
4 ADDITIONAL SWING DOOR client verbal instruction V.O No 2.4
5 RUBY STRUCTURE ADJUSTMENT AT LEVEL 26-27 engineer revise drawings V.O No 2.5
6 ADDITIONAL BOXUP AT LEVEL 24 TO CONCEAL PIPE client verbal instruction V.O No 2.6
7 ADDITIONAL PLASTER CEILING BOARD AT LEVEL 25-27 client verbal instruction V.O No 2.7
ADDITIONAL PLASTER CEILING BOARD AT GF GRAND
8 LOBBY AND LEVEL 24 client verbal instruction V.O No 2.8
PROPOSED CONVERSION AND SUBDIVISION OF MIXED DEVELOPMENT OF
COMMERCIAL AND SERVICED APARTMENT WITH STRATA TITLES TO BE
APPLIED FOR ON NT. 213190044 (NT. 4602) OFF JALAN LINTAS, PENAMPANG,
SABAH.
INFRASTRUCTURE WORKS LIST

No Element

DRAINAGE WORKS
1 internal drainage C20P drain insite boundry
2 External drainage outsite boundry - Modify extention of entrance bridge
3 dirt and soil cart away with lorry transport for drainage and road work

ROAD WORKS
1 Premix road
2 Texture imprint concrete
3 Road marking
4 Provisional addition works

FENCING WORKS
1 Fencing site boundary

SEWERAGE WORKS
1 200mm DI pipe from pump sump to external main
2 250mm DI pipe sewer pipe and 1300 PE pump station
3 250mm sewerage pipe encasement
4 Pipe jacking

WATER RECTICULATION WORKS


1 150mm MSCL pipe and pillar hydrant works

PILING WORKS
1 Piling works for sewer lines, drainage and bin center foundation
2 Piling works for bridge foundation and external drain cover
3 New piling works for sewer lines, drainage and bin center foundation

***Upgrade and change of spec by MCD


PROPOSED CONVERSION AND SUBDIVISION OF MIXED DEVELOPMENT OF COMMERCIAL AND
SERVICED APARTMENT WITH STRATA TITLES TO BE APPLIED FOR ON NT. 213190044 (NT. 4602) OFF
JALAN LINTAS, PENAMPANG, SABAH.
Progress Claim No. 25
Summary List Of Material On Site Date : 26th May 2016
Package - 2
Quantity
Unit Balance Addition Used for Bal. On
Item Description
B/F Per D/N the month Site C/F

1 R8 MT 2.00 2.00
2 R10 MT 2.02 2.02
3 Y10 MT 6.02 7.14 2.00 11.16
4 Y12 MT 8.96 5.12 4.00 10.08
5 Y16 MT 2.30 2.30
6 A6 PCS 16.00 12.00 4.00
7 A7 PCS 167.00 150.00 17.00
8 A8 PCS 59.00 40.00 19.00
9 B6 PCS 182.00 170.00 12.00
10 B7 PCS 108.00 88.00 20.00
11 B8 PCS 33.00 26.00 7.00
CUBIC
12 River sand 406.00 43.00 300.00 149.00
YARD
13 Brick PCS 6,000.00 4,000.00 9,500.00 500.00
14 Supracoat external coat BAG 1,041.00 240.00 1,111.00 170.00
15 Bostik Fixall BAG 407.00 200.00 599.00 8.00
16 Maxiflex BAG 1,264.00 1,950.00 2,999.00 215.00
17 Tile adhesive BAG 76.00 50 26.00
18 Cement BAG 2,056.00 1,100.00 2,999.00 157.00
19 3/8" chipping TON 177 120.23 199 97.91
20 Fine mortar base grey BAG 203 170 33.00
21 Plaster finish grey BAG 331 50.00 290 91.00
22 Finish 300 BAG 200 150 50.00
23 Door leaf; 830x2350mm; D1 NO 40.00 40.00 0.00
24 Door leaf; 1500x2425mm; D2 NO 1.00 1.00 0.00
25 Door leaf; 675x2055mm; D4 NO 71.00 71.00 0.00
26 Door leaf; 600x2125mm; D5 NO 1.00 1.00 0.00
27 Door leaf; 830x2058mm; D3 NO 52.00 49.00 3.00
28 Door leaf; 1100x2425mm; D7 NO 2.00 2.00 0.00
29 Fire door leaf; 1200x2425mm; FD2 NO 69.00 65.00 4.00
30 Fire door leaf; 1111x2045mm; FD3 NO 3.00 3.00 0.00
31 Fire door leaf; 1411x2045mm; FD1c NO 23.00 20.00 3.00
32 Fire door leaf; 614x2045mm; FD2c NO 16.00 10.00 6.00
33 Fire door leaf; 814x2045mm; FD2b NO 6.00 6.00 0.00
34 Fire door leaf; 910x2045mm; FD2a NO 38.00 30.00 8.00
35 Fire door leaf; 1711x2345mm; FD1 NO 6.00 6.00 0.00
36 Fire door leaf; 1711x2345mm; FD1a NO 7.00 7.00 0.00
GROUND FLOOR PLAN
PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH

SITE PROGRESS PHOTOGRAPHS

View A

View B
PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH

SITE PROGRESS PHOTOGRAPHS

View C

View D
PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH

SITE PROGRESS PHOTOGRAPHS


PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH

SITE PROGRESS PHOTOGRAPH


PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH
PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH

SITE PROGRESS PHOTOGRAPH