CONSULTANTS
ARCHITECT : ARKITEK TM
SUBMITTED BY
MAIN CONTRACTOR : BINA PYK (SABAH) SDN BHD
PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH
CONTENTS
1 PROJECT SUMMARY
2 ORGANIZATION CHART
5 SUMMARY OF WORKDONE
7 WEATHER CHART
11 VARIATION ORDER
12 MATERIAL ON SITE
13 SITE PLAN
15 SAFETY REPORT
PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH
PROJECT SUMMARY
ARCHITECT ARKITEK TM
Client
Mega City Development Sdn. Bhd. Quantity Surveyor
Mr. Michael Chin CE Technical Services Sdn. Bhd.
HP: 019 - 812 2678 Mr. Edward Vun
Tel: 6088 - 311 111 HP: 013 - 850 8148
Fax: 6088 - 726 111 Tel: 6088 - 236 148
michael@megacitydevelopment.com
Fax: 6088 - 246 149
cetechservices03@gmail.com
ARCHITECT
PROJECT MANAGER
MR RICKEY SOH SWEE LOONG
016 - 222 8919 QS
SAFETY OFFICER rickysoh.pyk@gmail.com
OSH PERDANA MR ANDERSON YAP
MR CYRIL DARYL CONSTRUCTION MANAGER 016 - 833 8264
017 - 821 9322 MR SIAK HUAT SENG anderson.pyk@gmail.com
Darylcyril@gmail.com 016 - 810 9281
michaelsiak@gmail.com
VERTICAL TRANSPORTATION
FIRE PROTECTION SYSTEM
ELECTRICAL & TELEPHONE MS ELEVATOR
CARD ACCESS, PUBLIC ADDRESS, TYL FIRE FIGHTING MS EUNICE
VIDEO INTERCOM, CCTV, PABX, COLD WATER & 012 - 370 3117
SANITARY PLUMBING & RWDP MR TAN YIN LIANG
BARRIER GATE & HD-SMATV 016 - 290 1688 yitmk@msee.com.my
Main Contract - 2 - Preliminary Master Programme - After Piling Contractor Hand Over Date: 16-11-2014
2014 2015 2016
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 Month 13 Month 14 Month 15 Month 16 Month 17 Month 18 Month 19 Month 20 Month 21 Month 22 Month 23 Month 24 Month 25 Month 26 Month 27 Month 28 Month 29
Item Task
Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40 W41 W42 W43 W44 W45 W46 W47 W48 W49 W50 W51 W52 W53 W54 W55 W56 W57 W58 W59 W60 W61 W62 W63 W64 W65 W66 W67 W68 W69 W70 W71 W72 W73 W74 W75 W76 W77 W78 W79 W80 W81 W82 W83 W84 W85 W86 W87 W88 W89 W90 W91 W92 W93 W94 W95 W96 W97 W98 W99 W100W101W102W103W104W105W106W107W108W109W110W111W112W113W114W115 W116
12 M&E Services
12.1 Low Voltage Services 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0 0 0 0 0 0 0
12.2 Street Lighting 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.3
12.3 Extra Low Voltage 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0 0 0 0 0 0 0
12.4 Plumbing & Sanitary Services 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0 0 0 0 0 0 0
12.5 Fire Protection Services 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0 0 0 0 0 0 0
12.6 Mechanical Services 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0 0 0 0 0 0 0
12.7 Air Cond Services 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0 0 0 0 0 0 0
13 Infra Structure
13.1 Electrical Reticulation
13.2 SESB Room
13.3 Telephone Infra
13.4 Water Reticulation
13.5 Sewerage System
13.6 Drainage
13.7 Road & Road Kerb
7.9 9 4 2 2 2 2 2 2.5 2.5 2.5 2.5 2.5 3.5 3.5 3.5 3.7 3.7 4.9 4.8 4.4 4.4 6.4 5.4 3.3 3.3 7.2 8.4 8.7 5.6 5.9 6.5 6.5 7.3 9.3 7.6 8.3 8.4 9.4 9.7 9.2 11 11 13 13 12 8.5 8.6 8.3 6.2 6.8 6.1 6.4 6.4 7.3 7.9 6.9 9.6 8.5 8.9 11 11 11 9.7 14 13 17 20 19 20 20 21 21 24 18 20 21 19 20 21 21 21 20 23 19 19 17 15 17 17 17 15 11 12 13 12 11 14 13 14 15 12 12 12 12 7.4 7.4 7.4 7.5 5.8 5.8 5.8 5.8 0.5 0.5 0.3
* Note:- This programme is subjected to piling contractor hand over date CHRISTMAS CNY CHRISTMAS CNY TODAY Prepare by:-
Bina PYK (Sabah) Sdn Bhd
23 7.8 9.8 13 17 20 22 27 31 36 45 43 27 28 34 42 64 81 83 81 85 71 65 48 52 50 34 25 7.3
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
PROPOSED CONVERSION AND SUBDIVISION OF MIXED DEVELOPMENT OF COMMERCIAL AND SERVICED APARTMENT WITH STRATA TITLES TO BE APPLIED FOR ON NT. 213190044 (NT. 4602) OFF JALAN LINTAS, PENAMPANG, SABAH.
Main Contract - 2 - SITE POSSESION Master Programme WITH EOT - After Piling Contractor Hand Over Date: 16-11-2014
* Note:- This programme is subjected to piling contractor hand over date Prepare by:-
TODAY CHRISTMAS CNY
* Note:- This programme is subjected to piling contractor hand over date Prepare by:-
10.00
-
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
Construction Period
(Months)
PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH
Date:
1 Site staffs 3 20 20 20 20 20 20 7 20 20 20 20 20 20 8 20 20 20 20 20 20 4 20 20 20 20 20 20 3 3 3
2 General worker 10 89 79 73 74 83 81 48 83 84 84 83 81 79 63 90 79 84 79 87 83 33 82 90 93 98 79 94 61 10 10
3 Concretor
4 Carpenter 0 9 9 9 9 9 9 0 9 9 9 9 9 9 0 9 9 9 9 9 9 0 9 9 9 9 9 9 0 0 0
5 Bar-bender 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 0 0
6 Screeding 0 2 2 2 2 2 2 0 2 2 2 2 2 2 0 2 2 2 2 2 2 0 2 2 2 2 2 2 0 0 0
7 Plasterer
8 Bricks layer
9 Power float floor hardener
10 Tiler 0 16 16 16 16 16 16 0 16 16 16 16 16 16 0 16 16 16 16 16 16 0 16 16 16 16 16 16 0 0 0
11 Steel work 0 5 5 5 5 5 5 0 5 5 5 5 5 5 0 5 5 5 5 5 5 0 5 5 5 5 5 5 0 0 0
12 Marble installer
13 Skim coat 0 3 3 3 3 3 3 0 3 3 3 3 3 3 0 3 3 3 3 3 3 0 3 3 3 3 3 3 0 0 0
14 Plaster Ceiling installer 0 14 14 14 14 14 14 0 14 14 14 14 14 14 0 14 14 14 14 14 14 0 14 14 14 14 14 14 0 0 0
15 Timber flooring 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 0 0
16 Curtain wall & glazing 0 24 24 24 24 24 24 0 24 24 24 24 24 24 0 24 24 24 24 24 24 0 24 24 24 24 24 24 0 0 0
17 Carpentry & ironmongery 0 10 10 10 10 0 10 10 10 10 10 10 0 10 0 10 10 10 10 0 10 0 10 10 10 10 0 10 10 0 0
18 Rain water down pipe installer
19 Painter 0 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43 43
20 Plumber 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15
21 Air-Conditioning installer 0 5 5 5 5 5 5 0 5 5 5 5 5 5 0 5 5 5 5 5 5 0 5 5 5 5 5 5 0 0 0
22 Electrician 0 35 35 35 35 35 35 0 35 35 35 35 35 35 0 35 35 35 35 35 35 0 35 35 35 35 35 35 0 0 0
23 Fire Protection installer 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 8 8 8 8 8 8 0 0 0
24 Swimming pool
25 Lift installer 0 16 16 16 16 16 16 0 16 16 16 16 16 16 0 16 16 16 16 16 16 0 16 16 16 16 16 16 0 0 0
26 Security 2 2 2 2 3 2 2 2 2 2 2 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
30 332 322 316 317 316 324 125 326 327 327 328 314 322 131 313 302 307 302 320 326 97 325 333 336 341 312 337 134 73 73
Architect Request For Information Summary
16/11/2015 LA/RFI/M&E/06_Conceal of CO2 Fire Alarm Panel at Ground Floor. REPLIED BY Letter Ref. No. 21st January, 2016
23/11/2015 LA/RFI/M&E/07_Propose of Sanitary & RWDP for Level 25 to RG2 ARCHITECT
REPLIED ATM/52P12/MC/
23/11/2015 LA/RFI/M&E/08_A/C Copper & Drain Pipe Routing at Level 6, Type A. REPLIED
23/11/2015 LA/RFI/ARC/03_Propose of RWDP for Level 25 to RG2. REPLIED
27/11/2015 LA/RFI/M&E/09_Submission of Ventilation Fan Catalogue for Approval (Iras REPLIED
Bumi) for Ruby Block, Level 6, Type A.
27/11/2015 LA/RFI/M&E/10_Shower installation at Window position at Ruby Block, Level 6, REPLIED
Male Changing Room.
28/11/2015 LA/RFI/M&E/11_Confirmation of Air Cond & Compressor position for Level 25, REPLIED
Penthouse.
7/12/2015 LA/RFI/M&E/12_Seek for A/C c/w piping Information at Level 15, Ruby Type A REPLIED
(Extension Unit) and Amber Type C (Additional Unit).
11/12/2015 LA/RFI/M&E/13_Seek for advise at the installation of Floor Trap, basin and W.C REPLIED
piping at Level 15, Ruby Type A, additional of Powder Room.
15/12/2015 LA/RFI/M&E/14_Seek for advise at the installation of Fireman Switch, Fireman REPLIED
Intercom, Hose Rell, Wet Riser System from Level 25 to 27, Ruby and Amber
Block.
5/1/2016 LA/RFI/M&E/15_Seek for confirmation for the capacity of Exhaust Fan Motor & REPLIED
Control Panel at Basement, Pump Room.
5/1/2016 LA/RFI/M&E/16_Submission of Exhaust Fan Motor & Air Grille Catalogue for REPLIED
Staircase Ventilation System
18/1/2016 LA/RFI/M&E/17_Seek for External Telephone Manhole confirmation. REPLIED
18/1/2016 LA/RFI/M&E/18_Seek for Air Craft Lighting height confirmation. REPLIED
19/1/2016 LA/RFI/M&E/19_Seek for Air Cond compressor position at Level 6, Public Toilet, REPLIED
Multi Purpose Hall, Children Playground and Gym Room.
25/1/2016 LA/RFI/M&E/20_Seek for W.C sanitary piping installation whether using S-Trap REPLIED
or P-Trap at Level 6, Changing Room.
25/1/2016 LA/RFI/M&E/20_Seek for W.C sanitary piping installation whether using S-Trap REPLIED
or P-Trap at Level 6, Changing Room.
1/3/2016 LA/RFI/M&E/21_Arrangement of PA System, CCTV System & Fire Alarm Panel at REPLIED
Ground Floor, Fire Control Room.
4/3/2016 LA/RFI/M&E/22_Bath Tub dimension at Ruby, Penthouse A, Master Bathroom. REPLIED
12/3/2016 LA/RFI/M&E/23-1_Bath Tub dimensionConfirmation of Solar Hot Water piping REPLIED
system at Ruby, Penthouse A, Master Bathroom.
LA/RFI/M&E/23-2_Additional Water Tap at Ruby, Penthouse A&B, Roof Garden.
15/3/2016 LA/RFI/M&E/24_Confirmation of Tissue Holder position for Typical Unit type REPLIED
A,B,C,D,E & F toilet.
18/3/2016 LA/RFI/M&E/25_Proposed of Bath Tub mixer position c/w dimension for REPLIED
approval.
18/3/2016 LA/RFI/M&E/26_Proposed of Spare Cold & Hot water piping at Ruby, Penthouse REPLIED
Type B and Penthouse Type A c/w dimension for approval.
18/3/2016 LA/RFI/M&E/27_Submission of MIMIC Diagram Layout for approval. REPLIED
1/4/2016 LA/RFI/M&E/28_Confirmation of Penthouse Type A, B & C Electrical Layout REPLIED
Version.
24/5/2016 LA/RFI/M&E/29_Propose of MATV Antena & Astro Satelite position for PENDING
confirmation.
24/5/2016 LA/RFI/M&E/30_Propose of Jacuzzi Air Switch Button position for confirmation. PENDING
ARKITEK TM
LIST OF ARCHITECT I NSTRUCTION ;
3 5/9/2014 SK301/EI NO 3 All grade 40 concrete for column to use 3/4" granite aggregate No
5 23/9/2014 SK301/EI NO 5 Informing to remove loose concrete on column C12 and call for inspection before No
performing any concrete activity
6 30/6/2015 JPB/15-166/EI/01 On wire mesh BRC Type CQ No Replied
8 10/7/2015 JPB/15-166/EI/03 Method Statement for Shear Wall SW9 at Ruby Block L6 Type B Zone 3 No Replied
9 20/10/2015 JPB/15-166/EI/04 Swimming Pool Formwork - Beam SVB5 450 x 900/1500/1650/1500 No Replied
IP CONSULTANTS
LIST OF E NGINEER'S I NSTRUCTION :
TOWER
ADDITIONAL FLOOR TRAP FOR LEVEL 6 TO ROOF GARDEN
1 client verbal instruction V.O No 2.1
2 UPGRADE FIRE DOOR VENEER SURFACE client verbal instruction V.O No 2.2
3 ADDITIONAL U CHANNEL AT BALCONY RAILING AREA engineer revise drawings V.O No 2.3
4 ADDITIONAL SWING DOOR client verbal instruction V.O No 2.4
5 RUBY STRUCTURE ADJUSTMENT AT LEVEL 26-27 engineer revise drawings V.O No 2.5
6 ADDITIONAL BOXUP AT LEVEL 24 TO CONCEAL PIPE client verbal instruction V.O No 2.6
7 ADDITIONAL PLASTER CEILING BOARD AT LEVEL 25-27 client verbal instruction V.O No 2.7
ADDITIONAL PLASTER CEILING BOARD AT GF GRAND
8 LOBBY AND LEVEL 24 client verbal instruction V.O No 2.8
PROPOSED CONVERSION AND SUBDIVISION OF MIXED DEVELOPMENT OF
COMMERCIAL AND SERVICED APARTMENT WITH STRATA TITLES TO BE
APPLIED FOR ON NT. 213190044 (NT. 4602) OFF JALAN LINTAS, PENAMPANG,
SABAH.
INFRASTRUCTURE WORKS LIST
No Element
DRAINAGE WORKS
1 internal drainage C20P drain insite boundry
2 External drainage outsite boundry - Modify extention of entrance bridge
3 dirt and soil cart away with lorry transport for drainage and road work
ROAD WORKS
1 Premix road
2 Texture imprint concrete
3 Road marking
4 Provisional addition works
FENCING WORKS
1 Fencing site boundary
SEWERAGE WORKS
1 200mm DI pipe from pump sump to external main
2 250mm DI pipe sewer pipe and 1300 PE pump station
3 250mm sewerage pipe encasement
4 Pipe jacking
PILING WORKS
1 Piling works for sewer lines, drainage and bin center foundation
2 Piling works for bridge foundation and external drain cover
3 New piling works for sewer lines, drainage and bin center foundation
1 R8 MT 2.00 2.00
2 R10 MT 2.02 2.02
3 Y10 MT 6.02 7.14 2.00 11.16
4 Y12 MT 8.96 5.12 4.00 10.08
5 Y16 MT 2.30 2.30
6 A6 PCS 16.00 12.00 4.00
7 A7 PCS 167.00 150.00 17.00
8 A8 PCS 59.00 40.00 19.00
9 B6 PCS 182.00 170.00 12.00
10 B7 PCS 108.00 88.00 20.00
11 B8 PCS 33.00 26.00 7.00
CUBIC
12 River sand 406.00 43.00 300.00 149.00
YARD
13 Brick PCS 6,000.00 4,000.00 9,500.00 500.00
14 Supracoat external coat BAG 1,041.00 240.00 1,111.00 170.00
15 Bostik Fixall BAG 407.00 200.00 599.00 8.00
16 Maxiflex BAG 1,264.00 1,950.00 2,999.00 215.00
17 Tile adhesive BAG 76.00 50 26.00
18 Cement BAG 2,056.00 1,100.00 2,999.00 157.00
19 3/8" chipping TON 177 120.23 199 97.91
20 Fine mortar base grey BAG 203 170 33.00
21 Plaster finish grey BAG 331 50.00 290 91.00
22 Finish 300 BAG 200 150 50.00
23 Door leaf; 830x2350mm; D1 NO 40.00 40.00 0.00
24 Door leaf; 1500x2425mm; D2 NO 1.00 1.00 0.00
25 Door leaf; 675x2055mm; D4 NO 71.00 71.00 0.00
26 Door leaf; 600x2125mm; D5 NO 1.00 1.00 0.00
27 Door leaf; 830x2058mm; D3 NO 52.00 49.00 3.00
28 Door leaf; 1100x2425mm; D7 NO 2.00 2.00 0.00
29 Fire door leaf; 1200x2425mm; FD2 NO 69.00 65.00 4.00
30 Fire door leaf; 1111x2045mm; FD3 NO 3.00 3.00 0.00
31 Fire door leaf; 1411x2045mm; FD1c NO 23.00 20.00 3.00
32 Fire door leaf; 614x2045mm; FD2c NO 16.00 10.00 6.00
33 Fire door leaf; 814x2045mm; FD2b NO 6.00 6.00 0.00
34 Fire door leaf; 910x2045mm; FD2a NO 38.00 30.00 8.00
35 Fire door leaf; 1711x2345mm; FD1 NO 6.00 6.00 0.00
36 Fire door leaf; 1711x2345mm; FD1a NO 7.00 7.00 0.00
GROUND FLOOR PLAN
PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH
View A
View B
PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH
View C
View D
PROJECT TITLE: PROPOSED CONVERSION AND SUBDIVISION MIXED DEVELOPMENT OF COMMERCIAL AND RESIDENTIAL
ON NT. 2131900044 (NT.4602), OFF JALAN LINTAS, PENAMPANG, SABAH