Construction of Faculty of Education Complexes in Pakistan

Al-Shafi Enterprises EA Consulting Pvt. Ltd.


Daily Construction Report
T.O. No. AID-391-TO-13-00004
Commencement Date: March 02, 2015
Date 02/5/2015

Islamia
Site Name
University Bahawalpur

Owner USAID Task Order No. AID 391-TO-13-00004

Subcontract No. Subcontractor Al-Shafi Enterprises

Daily Job Report # Work Day # 62

Day of Week saturday Weather

Time Weather Temperature

0800 Hrs. Sunny Temp. 27oC

1400 Hrs. Sunny Temp. 39oC


Name & Designation Time In Time out

Jameel shafi sahib, Tahir Shafi, and Engr naeem sahib. 11:00am 1:00pm
Visitors At Site

Visitor Remarks

Subcontractor Staff & Labor Details


Designation No. Work Hours Designation No. Work Hours

Site In-charge 1 8 Procurement Manager 0 0

QC Supervisor - - Purchaser - -

Site Supervisor 2 8 Store Keeper 1 8

Surveyor 2 8 Driver 1 8

HSE Inspector 1 8 Office Boy 1 8

Store Incharge 1 8 Security Guard 4 8 Each


Worker Trade No Work Hours Extent of Work (complete description of days activity)
1. Surface cleaning of footing for layout.
2. Spacer casting.
Labor 13 8 each 3. Layout marking.
4. Masnory for water tank.
5. Housekeeping

Page 1 of 4
Construction of Faculty of Education Complexes in Pakistan
Al-Shafi Enterprises EA Consulting Pvt. Ltd.
Daily Construction Report
6.Shifting of material

Mason 01 8 Each 1. Masonry work of curing tank.

Carpenter 01 8 -

Surveyor helper 02 8each Grid Marking for layout

Electrician 01 8 Office maintenance & connection of water pumps.


8 each
scaffolder 2 Repairing of Hard Barication
3
Steel fixer 8 each. Steel cut & bend plateform preparation, steel cutting & bending.
nil
Verbal
Directives

Detail of Inspections Carried out Status


nil

Material Received at Site Qty. Supplier


Admixture received at site. 2 drums. Fospak.

Work Idle
Tool & Plant @ Site Description of Operation of Equipment
Hours Hours
Auto Level nil
Theodolite 8 layout of footing & column.
Concrete Mixer - -
Machine
Wheel Barrows 9 no Material shifting & backfilling
Generator Standby Power Source
Water Pump 3 No 3x8=24 Water for plaster, Curing and sprinkling at site.
Bottle Necks Revised Construction Schedule ,Availability of Purchaser
And Medic Man for site, Permanent Emergency Vehicle. Mix Design Approval.
(ASE need to expedite above mentioned things for the sake of progress. Comments By RE EA
Next Day Plan:
1. Layout for footing.
2. Material shifting.
3. Construction of water reservoir.
4. Spacer casting.
5. Surface cleaning of lean for layout.

Page 2 of 4
Construction of Faculty of Education Complexes in Pakistan
Al-Shafi Enterprises EA Consulting Pvt. Ltd.
Daily Construction Report
6. Steel cutting , bending & fixing..
7. Housekeeping.
Next week plan:
1: concrete spacers.
2. Construction of water pond for concreting
3. Stack yard shifting to west side
4. Steel cutting/bending for footing.
5. Grid Marking and Layout of footing (complete and verified by consultant)
6. Construction of pathways, labor camp facilities like Toilet and veranda etc.
7. Grinding and welding to improve steel shuttering plates alignments for footing and columns.
8. Construction of water reservoir.
Material Demand:

1.Cement crush, sand as per mix design.(Qty Already demanded through email)
2. Standby Mixer machine
3. FDT apparatus for backfill testing
4. Small Roller compactor (1.5-2 ton capacity)
5. Steel Cut/Bend Machine (Immediate Requirement)

Labor Demand:

1.Formwork preparation and fixing party

Prepared By: Reviewed By: Received By:

Muhammad Zubair Zaib Shahid EA Consulting


QA/QC Engineer ASE Site Incharge ASE Representative

Page 3 of 4
Construction of Faculty of Education Complexes in Pakistan
Al-Shafi Enterprises EA Consulting Pvt. Ltd.
Daily Construction Report

Page 4 of 4