You are on page 1of 11

Structural Assessment, Denis McMullan and

Analysis, and Douglas Bond

Rehabilitation of a
Masonry Aqueduct
To avoid future arch
collapse, engineers
had to determine the
failure mechanism of
this Maryland aqueduct.

Fig. 1. Catoctin aqueduct,


Lander, Maryland, collapsed The failure of stone masonry arches has been studied
center and western arches,
1973. The berm parapet and
extensively but mainly for the development of analytical
upstream spandrel wall had
failed earlier. Note the railings
modeling methods for bridges carrying vehicles.1 This paper
bent in downstream direction, studies the collapse of a stone masonry arch aqueduct that carried boats across
indicating predominate flood Catoctin Creek on the Chesapeake and Ohio (C&O) Canal near Lander,
effects coming from tributaries Maryland (Fig. 1). Among the inherent design flaws were the deterioration of
and not the adjacent Potomac
the waterproofing system and the arrangement of unequal arch spans, both of
River. Courtesy of the C&O
Canal National Historical Park which contributed to the collapse. The reconstruction of the aqueduct included
Archives. reusing existing stones and developing methods for measuring and accurately
locating the recovered ring stones in the arches. Similar substantially intact
aqueducts of the same period on the C&O Canal, as well as aqueducts on other
canals, were studied to understand the historic building techniques, deterioration
from environmental effects, and causes of structural distress that can occur in
these structures.
18
Analysis and rehabilitation of a masonry aqueduct

Background The Catoctin aqueduct was con- Fig. 2. Typical cross section for aqueducts
on the C&O Canal: 1. Railing. 2. Towpath
structed between 1832 and 1834.7
parapet. 3. Trunk floor. 4. Trunk of aqueduct.
Aqueducts were first used to transport It was designed by Thomas F. Purcell,
5. Rubble fill. 6. Arch barrel. 7. Extrados of
water for drinking, bathing, and irri- constructed by Tracey and Doug- arch. 8. Berm parapet. 9. Water table. 10.
gation. The Canal du Midi in France, las Contractors, and was the third Keystone. 11. Ring stones. 12. Pier. 13. Spring
built between 1666 and 1681, is one of aqueduct constructed along the canal line. 14. Spandrel wall. 15. Coping stones.
the first European aqueducts used for after the Seneca and the Monocacy 16. Pilaster. 17. Bullnose. 18. Abutment. 19.
navigation.2 Navigation aqueducts are aqueducts.8 Wing wall. Courtesy of C&O Canal National
essentially bridges that carry water-filled Historical Park.
canals instead of roads. Figure 2 is an
artists rendering of a C&O Canal aque-
duct with notes identifying features and
components. The rendering contains
some inaccuracies (the most significant
being that it shows the trunk floor as
a full stone layer across the aqueduct,
which does not exist on any excavated
aqueducts). In general, though, the
drawing gives a very good illustration of
a typical aqueduct on the C&O Canal.
Construction of the C&O Canal began
in 1828 in Little Falls, Maryland, just
outside of the District of Columbia, and
included 11 stone aqueducts designed
to carry the canal and boats across the
major river tributaries that drain into
the Potomac River along the canals
route.3 The canal depended on the
Potomac for its water supply, which was
both an advantage and a liability since
the river is prone to severe and frequent
flooding; between 1828 and 1996 the
canal was flooded 144 times.4 The need
to keep the level of the canal close to
the level of the river and to keep the
river tributaries navigable required care- When the Catoctin aqueduct collapsed Description of the
ful attention to canal elevations. on October 30, 1973, the highly popu- Aqueduct
lar towpath was also severed, and the
Now a park operated by the National section from Mile Post 50.9 at Lock The Catoctin aqueduct is 130 feet long
Park Service, the C&O Canal extends 29 to Mile Post 55.0 at Lock 30, a dis- and 33 feet wide and has a waterway
184.5 miles from Georgetown in Wash- tance of four miles, was closed. Park width of 20 to 21 feet. It is comprised
ington, D.C., to Cumberland, Mary- users were forced to make an eight-mile of three arches: one central elliptical
land5; in many places the park is only detour along county roads. In 1974 a arch spanning 40 feet, flanked by two
a few hundred yards wide. The canal precast concrete pedestrian bridge was semi-circular arches, each spanning 20
operated as a commercial transportation installed by the John Driggs Company feet.11 In plan the aqueduct stood at an
artery until 1924. The owner at that over the creek adjacent to the remains angle to the canal, such that the canal
time, the Baltimore and Ohio (B&O) of the aqueduct.9 This bridge lasted curved sharply into each end. This
Railroad, had no interest in continuing only until October 1976, when it was arrangement gave it the nickname of
operations. Ownership was transferred destroyed in a flood. A Bailey bridge crooked aqueduct.12 It was an impres-
to the U.S. government in 1938. The spanning the abutments of the aqueduct sive, elegant structure with shallow
canal came under the jurisdiction of the was installed in 1980 but at the expense arches and excellent ashlar-faced stone-
National Park Service when the Chesa- of introducing a visually intrusive ele- work. The ring stones, which have a
peake and Ohio Canal National Histori- ment into a natural and historically sen- raised rock-face finish surrounded by a
cal Park was created in 1971.6 sitive environment.10 narrow, flat margin, vary in height, with
the maximum at the spring line and
19
APT BULLETIN JOURNAL OF PRESERVATION TECHNOLOGY / 46:4 2015

Fig. 3. Typical C&O Canal nership involving Coyle and a patent for
aqueduct cross section. resin cement.18 Test pits excavated in
Drawing by Denis McMullan.
the trunk for the reconstruction project
in 1998 revealed a partial layer of this
resin cement at the floor level.
An 1870 Board report to the canal com-
pany stated that water was being kept
in the canal over the winter, causing
ice to form in cracks in the stonework
and expand, breaking the bond of the
cement and resulting in loose stones.19
In addition, the ice forming on the sur-
face of the water was most likely forcing
out the thinner and lighter berm para-
pet. The berm parapet was 5 feet wide,
as compared to the towpath parapet,
which was from 7 to 8 feet wide.
Since the water in the canal was not
always emptied for the winter due to
a lack of proper maintenance, forces
tapering to a minimum at the apex of guiderail was installed on the canal side. generated by pockets of water freezing
the arch. The graceful appearance of the Timber rub rails were installed on the inside the rubble fill or by the water
aqueduct also resulted from the minimal inside face of the towpath parapet walls in the aqueduct would have been very
vertical dimensions from the bottom of to protect the boats. large.20 Over the course of several years,
the water trunk to the top of the arches these expansion forces would lead to
and to the low rise-to-span ratio of the the significant movement of the parapet
central elliptical arch.
Maintenance History stones and cracking of the arch barrel.
A serious leak occurred at one of the Between 1852 and 1905, Maryland
The arches were supported on stone
abutments of the aqueduct in the spring suffered six severe winters, with low
piers and abutments. The solid cut stone
of 1834, after water was introduced temperatures ranging from -5F in 1852
in the piers stopped at the intersection
in 1833. The chief engineer, Charles to -40F in 1902. In 1857 all rivers in
of the extrados of the arches. Above
B. Fisk, installed a temporary wooden Maryland and Virginia froze over, and
the arches and inside the interior span-
trunk to allow continued operation in 1905 there were 22 continuous days
drel walls the aqueduct was filled with
of the canal. In 1835 a wing wall col- when the temperature never rose above
lower quality stone of varying sizes,
lapsed, necessitating another temporary 0F.21
commonly referred to as rubble stone.
The mortar mixed in with the rubble wooden trunk.15 According to Super- In 1873 there were further reports of
fill contained hydraulic cement, prob- intendent W. S. Elgin, the collapse was deteriorating conditions at the aque-
ably from the Shepherdstown Potomac caused by heavy laden boats from duct. In 1877, 1886, and 1889 devastat-
Cement Mill at Shepherdstown, West time to time run[n]ing against the ing floods caused further damage. The
Virginia (originally part of Virginia).13 sides.16 The alignment of the aqueduct flood damage was so severe in 1889
Since hydraulic cement caused the mor- may have made it difficult for boats to that the canal company was forced into
tar to set underwater, it was critical enter the aqueduct without hitting the receivership and was taken over by the
to the watertightness of the locks and parapets. B&O Railroad.22
canals (Fig. 3). The persistent leaking prompted Fisk
The spandrel stones were 12 to 18 to use a new product called Ameri- Assessment of
can Cement, patented by Thomas C.
inches in depth with a regular pattern
Coyle, to rebuild the trunk of the
Contemporary
of header stones roughly 4 feet deep
tying the spandrel stones to the rubble- aqueduct.17 The term rebuild probably Aqueducts
stone fill. The exposed stone was a good meant to coat the inside of the trunk.
Nine hundred and twenty-four barrels To fully understand nineteenth-century
quality granite brought by the B&O construction methods and the challenges
Railroad from the Ellicott Mills quarry of this cement were used in the project.
This product contained resin and tar and problems specific to masonry-
(originally called Patapsco) near Balti- arch aqueducts, particularly those that
more.14 A beautiful wrought-iron rail- and must have been applied hot, as
there were costs for using kettles. Legal employed elliptical arches, it was impor-
ing, ornamented with scrolls and finials, tant to study other aqueducts of the
was installed on the towpath parapet records from a Baltimore County court
in 1838 mention a dissolution of a part- same period, both on the C&O Canal
along the river side, and a wooden mule and in other countries.
20
Analysis and rehabilitation of a masonry aqueduct

Fig. 4. Elevation, plans, and section


of Whitworth aqueduct over the
River Inny, County Longford, Ireland,
1814. Courtesy of Waterways
Ireland.

Fig. 5. Monocacy aqueduct,


Montgomery County, Maryland,
1998. Arch barrel showing
longitudinal cracks under the berm
parapet prior to stabilization and
restoration in 2010. Red arrows
indicate two of the temporary tie
rods, which were installed under
the arches to arrest the transverse
movement of the spandrel walls
and barrel arches; note also that
the cracks are wider at the apex.
Photograph by Denis McMullan.

Traditionally, English and Irish canal cal arch span that is larger than the two
aqueducts were waterproofed using a equal elliptical side spans. They are the
thick layer of clay, but supporting the only aqueducts on the C&O Canal that
weight of this construction made these have elliptical arches and a combination
structures deep and heavy. An 1814 of different arch spans. A slight flatten-
engineering drawing of a nineteenth- ing of the center arch and one of the
century aqueduct obtained from the side arches is noticeable on the Antie-
archives of Waterways Ireland shows tam aqueduct, but the arches appear to
the elevation and cross section of the be stable.
Whitworth aqueduct, which spans the
Normally an engineering assessment
River Inny in County Longford, Ireland.
of an aqueduct or any structure would
The drawing illustrates the depth of
have the benefit of evaluating most or
clay fill and the use of battered spandrel
all of the structure. However, in the
walls to resist the internal lateral earth
case of the Catoctin aqueduct, only a Other common problems on the C&O
and hydraulic pressures. The parapets
portion of the east arch remained. This aqueducts are bulges in spandrel walls
are equal in width on each side and, at
was examined but could provide only measuring up to 10 inches, lateral slid-
8 feet, significantly wider than the berm
limited information. Consequently, ing of spandrel walls of up to 2 inches
parapets on the C&O Canal. The Whit-
historic photographs and reports by the over the ring stones, settlement along
worth aqueduct, like many Irish and
original canal engineers and of struc- the middle of the coping stones of up
English aqueducts, is still intact and car-
tural defects common on other C&O to 3 inches, and outward deflection or
rying water and canal boats (Fig. 4).23
Canal aqueducts surveyed by the author tilting of the parapets by as much as
The designers of the C&O aqueducts formed the basis for the assessment. The 4 inches. Individual arch barrel stones
elected not to use the traditional layer of most prevalent indications of structural protrude six inches or more from many
thick clay for waterproofing, choosing distress on the C&O aqueducts are arches, and there is often a significant
instead to depend on the waterproof- large longitudinal cracks under berm loss of mortar in the longitudinal joints
ing properties of the natural hydraulic parapets and smaller longitudinal cracks of the arches but not in the transverse
cement, which is referred to in some his- under towpath parapets (Fig. 5). Cracks joints, where the mortar is held in posi-
torical records as water cement. They as wide as 4 inches have been recorded tion by the compression forces of the
also lined the bottom of the trunk with by the author; they usually run the full arch. Many arches have multiple cracks
wood planking, probably as an addi- length of the arches and decrease in that have been filled with mortar and
tional waterproofing measure.24 width as they move towards the spring concrete in the past. Historic photo-
line. Large icicles have been observed graphs of the Catoctin aqueduct also
The Antietam aqueduct on the C&O
hanging from the numerous cracks in show significant stone damage at the
Canal is comparable to the Catoctin
the soffit of the arch barrels. spring line of the elliptical arch and the
aqueduct in that it has a center ellipti-
21
APT BULLETIN JOURNAL OF PRESERVATION TECHNOLOGY / 46:4 2015

Fig. 6. Catoctin aqueduct,


showing sagging central arch,
n.d. Courtesy of the C&O Canal
National Historical Park Archives.

Fig. 7. Analytical collapse model.


Drawing by Denis McMullan.

and resistant to weathering in contrast


to the softer adjacent mylonitic rock,
which is more susceptible to weathering
and scour forces. All of the foundations
of the aqueduct are bearing on the hard
west pier, possibly indicating crush- large deformations and collapse of the greenstone except the east side of the
ing failure of the arch stones. Test pits arches (Fig. 6). west pier. The voids under this pier are
excavated by the author in the trunk of consistent with its bearing on the softer
After the Catoctin collapsed, the
the Monocacy aqueduct and coring in mylonite rock.
C&O Canal National Historical Park
the Conococheague aqueduct revealed
retrieved as many stones as possible Historic photographs of the Catoctin
a loss of the original cement matrix in
from the creek and buried them nearby aqueduct indicate that initially the berm
the rubble fill, with only tightly packed
for safekeeping and for future use. They parapet and upstream spandrel wall
gravel and sand remaining. There were
also retrieved bent and broken railings failed, followed by the center and west
also numerous voids, especially over
and stored them on-site, partially hid- arch.30 The berm parapet failure is com-
cracks in the arch barrel. Testing indi-
den in the undergrowth.26 mon on many of the C&O aqueducts.
cated that the sand contained elements
of deteriorated hydraulic lime mortar. Of the 11 stone aqueducts, 7 have lost
Test openings in the parapets of the Structural Assessment their berm parapets and upstream
Monocacy aqueduct revealed that the spandrel walls.
walls are constructed as two separate The structural assessment of the Cato-
ctin aqueduct began with an investi- A major problem at the Catoctin
wythes with rubble fill between each
gation of the bearing strata and the aqueduct was the arrangement of the
face. There were also voids and pockets
foundations of the piers and abutments. arches: the smaller semi-circular arches
of silt. Voids indicated loss of material,
A geotechnical investigation indicated on either side of the longer elliptical
probably through the large cracks in the
that the abutment and east pier were arch introduced unbalanced, horizontal
arch barrel. The silt most likely accu-
founded on solid rock with a rock mass forces in the structure, resulting in an
mulated from many years of being over-
quality (RMQ) of good to excellent overturning moment on the piers. Anal-
topped by river flooding.
with unconfined compressive strength ysis by the author shows that the unbal-
values of 7,317 to 15,502 pounds per anced horizontal thrust from the differ-
Collapse of the square inch.27 Divers in scuba gear ence in the two span lengths produces a
Catoctin Aqueduct conducted an underwater investiga- horizontal resultant force of 41 kips per
tion, which revealed erosion of the foot acting at the top of the piers. This
The center elliptical arch of the Catoctin rock at the interface with the west pier results in an overturning moment on the
aqueduct had had a pronounced sag at foundation stones.28 The potential for piers that causes tension on the one side
least as early as the 1940s. The berm scouring of the rock under the piers and of the pier. Masonry cannot resist sig-
parapet had collapsed by 1954. The abutments was investigated by a geolo- nificant tensile stresses, and, as a result,
elliptical arch continued to sag until gist from the Maryland State Highway the compressive forces redistribute and
October 30, 1973, when it fell during a Authority, who identified the rock as cause increased bearing pressure on the
local flood and also caused the collapse alternating layers of metadiabase (green- opposite side. The maximum bearing
of the west arch.25 It is the only C&O stone-metamorphosed basaltica lava) stress along one edge of the pier founda-
aqueduct arch to have exhibited such and mylonite.29 The greenstone is hard tion was 45 kips per square foot, a rela-
22
Analysis and rehabilitation of a masonry aqueduct

tively high value, especially considering more of the structure was lost, forces in Reuse salvaged original stones to the
that the west pier was partially founded the arch stones increased; hinges formed maximum extent possible.
on a softer vein of rock. in the elliptical arch; and the first signs
Replace ring stones in their original
of sagging would have been notice-
A computer analysis indicated that as locations on the arches.
able. Eventually the longitudinal cracks
more load was transferred to the arches
were large enough to cause the loss of Replace spandrel stones in their
from the deteriorating stone fill, hinges
the weaker and thinner upstream berm original pattern and coursing but not
would form in the arch and at the
parapet. Impact from floating debris location. Use historic photographs to
spring point.31 Hinge formation would
no doubt accelerated the process. Once identify coursing sequence.
cause deflection of the arch and a redis-
the berm parapet and upstream parapet
tribution of the compression forces. The Replace coping stones in their original
wall were gone, the interior of the struc-
arch would probably stabilize in this position.
ture was exposed to further deteriora-
condition due to the ability of the gran-
tion and loss of material. The inherent Ensure the long-term stability and
ite to withstand very high compressive
unbalanced forces most likely caused durability of the center elliptical arch.
forces. Granite compressive strengths
the west pier to move, resulting in a col-
can range from 15,000 to 36,000 In order to achieve long-term stability,
lapse of the arch.
pounds per square inch; however, in this durability and reliability, the restored
case one pier would most likely rotate structure needed to be capable of resist-
and the adjacent semi-circular arch Rehabilitation Design ing water intrusion, freeze-thaw effects,
would push upwards. Eventually the and Construction internal hydraulic pressure from future
granite stones at the spring line would re-watering of the canal, and impacts
fail in compression, or one pier foun- The rehabilitation process followed from boats.
dation would move to the point that National Park Service policies including
a mechanism would form, causing the the Secretary of the Interiors Standards The options of rebuilding the ellipti-
collapse of the arch. The deflected shape and Guidelines for Archeology and cal arch in stone or reinforced concrete
determined from the computer analysis Historic Preservation. In particular, the were considered carefully. Using stone
was similar to the profile of the aque- choice of objectives and options for the would have been the more historically
duct prior to collapse. The analysis indi- rehabilitation of the Catoctin aqueduct accurate solution, but there was a con-
cated the lifting up of the west arch and was subjected to a formal NPS Value cern about the stability of the elliptical
the tilting of the west pier. The location Analysis for the purpose of achiev- geometry and the practical ability to
of the hinges is not the same, but this ing essential functions at the lowest ensure long-term compression in this
is probably because of the unknown life-cycle cost consistent with required arch.
influence of the mortar fill on the arch performance, reliability, quality, safety,
Using concrete in an historic structure
behavior (Figs. 6 and 7). resource protection, sustainability, and
can result in compatibility problems,
quality visitor experience.32
Initially, compressive forces in the ellip- primarily because each material will
tical arch were shared by the arch stones From this process, the C&O Canal behave differently during changes in
and the mortared fill in combination National Historical Park determined temperature and when subjected to
with the stiffening effect of the parapets. that the following items were required: loading. Temperature-change move-
The compression in the arch barrel in ments are proportional to the materials
the direction of the span creates consid- R
 estore the missing center arch, west coefficient of thermal expansion. In this
erable friction forces between the stones arch, and the berm side of the east case, the coefficients of thermal expan-
that resist transverse lateral forces. This arch, including the berm and towpath sion of the granite is 4.4 x 10-6 per F,
system is effective provided that the fill parapets and railings. while the concrete has values ranging
maintains its integrity. However, in this R
 estore the west pier and the missing from 4.32 to 5.02 x10-6 per F. These
case, persistent leaking, freeze-thaw upstream section of the east pier while values are so close that little thermal
cycles, and the loss of cement matrix ensuring that the west pier was on a differential movement will occur. Differ-
weakened the fill. The internal hydrau- solid foundation. Both piers needed to ential movement can also occur due to
lic pressure increased with the growing be capable of resisting the unbalanced different responses to stress. The stress
number and size of the voids, and this horizontal loading from the center deformation will be proportional to the
pressure, in combination with impacts arch. modulus of elasticity of the material.
from boats, eventually overcame the The modulus of elasticity of the gran-
transverse frictional resisting force S tabilize and repair the remaining east ite is in the range of 2,900 to 8,700 kips
between the stones, causing the longitu- arch, including the stone fill. per square inch; for the concrete the
dinal cracks in the arch barrels. range is 2,800 to 3,600 kips per square
R
 epair all voids in the bedrock under
inch. Due to low stress values in the
As additional stone fill was lost, expan- abutments and piers. Anchor piers to
structure and to similar elasticity prop-
sive pressures increased, leading to a rock.
erties, little internal differential move-
reduction in the integrity of the fill. As ments were expected from stress. With
23
APT BULLETIN JOURNAL OF PRESERVATION TECHNOLOGY / 46:4 2015

saturation of the fill and the potential


for freeze-thaw damage. In addition,
gravel, due to its lower density, would
have increased the buoyancy of the
aqueduct when flooded and reduced the
safety factor against uplift and lateral
movement.35 Instead, a low-strength
concrete with a 28-day strength of
2,500 pounds per square inch was
used. The transverse tensile capacity
was enhanced by connecting the stone
ties with the continuous cage of epoxy-
coated reinforcing, in effect tying the
two faces together (Fig. 8).
The first step in the construction proj-
ect was to install coffer dams around
the east and west piers and the west
Fig. 8. Cross section of the decided that concrete arches provided abutment. The remains of the west pier
rehabilitated Catoctin aqueduct. the best value consistent with the objec- were removed, and the bedrock was
Note that mostly existing stones
tives and policies. examined for soundness. Weak rock
were used on downstream side,
and mostly new stones used on was removed. Debris was removed
The guidelines of the NPS and of the
upstream side. Also note stainless- under the edges of the east and west
American Concrete Institute for durabil-
steel dowels connecting stones abutments. The east pier and the rock
ity of concrete were followed; the guide-
to concrete fill. Drawing by Denis were examined for soundness and voids.
McMullan. lines called for a water-cement ratio
Several voids that required repair were
less than 0.45, compressive strength
discovered; in one case under the west
of 4,500 pounds per square inch at 28
abutment, concrete underpinning was
days, 6 percent air content, and 70 per-
negligible thermal differential move- needed. A new reinforced-concrete west
cent cementitious content using Type 2
ment and minor stress deformations,
cement (moderate sulphate resistance).33
there will be very minor internal separa-
All reinforcing bars were epoxy coated;
One of the keys to
tion forces. These forces can be easily
resisted by the stainless-steel dowel bars
they were designed and detailed for a successful reconstruction
minimum of two inches of cover, low
connecting the granite to the concrete. of the historic arches
stress levels for small crack widths, and
In a similar analysis, the concrete fill
adequate space around the bars for was the ability to make
used to extend the east arch was shown
ease of installation and good concrete
to have very similar properties to the small adjustments to the
compaction. Coating reinforcing bars
original mortared rubble stone fill in
with epoxy for additional protection formwork in the field to
this arch.
from harmful road salts has been a very
The concrete arch, in addition to being common practice in bridge construction match the irregular profile
20 percent less expensive, offered a pre- for many years, but in retrospect epoxy
dictable structural behavior, strength, coating the bars for the arch was prob-
of the original arches.
ductility and durability that would ably of little value. Recent testing has
pier and an extended east pier were
assure the longevity of the structure. shown that there is little to be gained
installed with anchor rods inserted into
by the use of epoxy coatings.34 Low-
The soffit of the concrete arch could the rock sufficient to resist the eccentric
carbon, galvanized, or stainless-steel
have been faced with stone to main- forces. Stone facing was constructed as
bars should be used if necessary. The
tain the original appearance under the a permanent form and attached to the
corrosion potential at the aqueduct will
arches, but there were concerns about poured concrete fill with stainless-steel
not be high, since only occasional main-
the long-term ability of the connection anchors. The existing remains of the
tenance or emergency vehicles will use
between the stone and the concrete to east pier were grouted and pinned to
the aqueduct. Salt will not be applied to
withstand impact from large tree trunks the rock.
the trunk bed, and the structure is not
swept downstream during flooding.
in a marine environment. The salvaged aqueduct stones were
Imprinting the soffit of the concrete
sorted into piles on wood blocking
arch or coloring the concrete to look A mortared stone fill to replicate the
based on their types; however, many
like stone were also considered, but, original was not considered sufficiently
original stones were not found. Each
eventually, the honest expression of durable. Gravel was also considered as
salvaged stone was identified by type:
concrete was preferred. The NPS a fill material; however, it would allow
24
Analysis and rehabilitation of a masonry aqueduct

voussoirs (ring stones), keystones, crete arch. The spandrel stones were Fig. 9. Measuring device for arch
stones, 2011. Photograph by Dan
spring stones, arch barrel, parapets, laid on top of the ring stones in their
Copenhaver, C&O Canal National
coping stones, spandrel stones, and historically correct pattern and in the Historical Park.
water table. In order to further identify same coursing but not necessarily in the
the ring stones as to arch and placement same location. The concrete arch was
within the arch, accurate measurements placed using small lifts to avoid displac-
of each stone were necessary. Obtaining ing the ring and spandrel stones. The
consistent measurements proved dif- stones from the inside faces of the para-
ficult because each stone had been hand pets were differentiated from those on
cut and had weathered over the last the outside spandrel walls by rub marks
170 years, causing rounded edges and from canal boats or bolt holes. Once a
uneven surfaces. A device was devel- level surface had been achieved at the
oped by C&O Canal NHP personnel top of the arch, the parapet stones were
that significantly improved the consis- installed, and concrete fill placed inside
tency of the measurements regardless of the finished cut stones. It was possible
who was taking the dimensions (Fig. 9). to replace towpath coping stones in the
original position due to the presence of
Once the stones were measured, they
iron clamps and other markings on the
were assembled graphically in a digital
stones. Over 450 original stones were
model by the author to determine their
used in the rehabilitation. Stones that
probable original position within the
could not be used were buried on site
arch. This modeling required extensive
to preserve them for future generations.
trial and error until a reasonable model
Granite from the Mason Quarry in
could be generated. Then a full-size,
Mason, New Hampshire, was used for
rigid-foam version of each stone was
the new stone. Although the new stone
fabricated by the C&O Canal NHP
looks quite different beside the original
and fitted together using the computer-
stone, it will blend in over time (Fig. 10).
generated arches and historic photo-
graphs to help identify the stones. Miss- The top of the concrete fill was sloped
ing stones were identified and recorded, from the center of the aqueduct to each
and their dimensions determined. This end, where site drains carry water out-
process enabled detailed construction side the canal prism. The historic floor
drawings to be produced for every miss- construction of the aqueduct would
ing stone showing its dimensions, finish, have been timber planking, but main-
and location. tenance considerations led to the use of
Fig. 10. New ring stone in place,
a concrete slab scored to represent the
One of the keys to successful recon- 2011. Photograph by Denis
planking. McMullan.
struction of the historic arches was the
ability to make small adjustments to
the formwork in the field to match the Historic Railing
irregular profile of the original arches.
This capability allowed the formwork The original wrought-iron railing pick-
for the east arch upstream addition ets were set in holes drilled into the cop-
and for the west arch to match the ing stones approximately 6 inches from
curvature of the existing portions of the edge of the stone and set at 8 inches
the arches. The contractor utilized a on center. They were set in lead. Due
custom-designed, steel formwork system to a combination of rust and freezing
with hydraulic jacks at 3 feet on center water expanding in the hole, the origi-
that could be individually adjusted. The nal coping stones had cracked along
new and original stones fit together well the line of the posts, and the edges of
and required only minor adjustments. the coping stones had fallen off. The
The hydraulic jacks also permitted the canal company had made repairs by
controlled release of the formwork to setting the railings farther back from
allow the compression forces to transfer the edge of the parapet stones and sup-
gradually to the arch. ported them with metal straps wrapped
over the parapets. Furthermore, during
The ring stones were held in place with floods, the railings caught debris, caus-
stainless-steel anchors attached to the ing the coping stones to be pulled off
rear of the stones and cast into the con- the parapet and into the river.
25
APT BULLETIN JOURNAL OF PRESERVATION TECHNOLOGY / 46:4 2015

Fig. 11. Catoctin aqueduct after


rehabilitation was completed,
2011. Photograph by George E.
Lewis, Jr.

restoration of historic locks, aqueducts,


and buildings. He has over 35 years
of experience in historic preservation.
He can be reached at dmcmullan@
mcmse.com.

Doug Bond, P.E., is vice president of


McMullan & Associates and a regis-
tered professional engineer in 14 states.
He has a MS in civil engineering from
Virginia Polytechnic Institute and State
University in Blacksburg, Virginia, and
has more than 28 years of experience
in structural investigations, design, and
Some changes to the design of the origi- Conclusion construction of historic structures. He
nal railing were thus necessary. The new can be reached at dbond@mcmse.com.
railing needed to be removed quickly Work on the Catoctin aqueduct was
in the event of a flood warning, and completed in 2011 and appears to have
the pickets spaced closer together to weathered several floods and freezing
Acknowledgements
comply with the International Building temperatures well. This project was made possible through an
Code safety requirements. In order to allocation of American Recovery and Reinvest-
The C&O NHP assigned an experienced ment Act (ARRA) funding, along with funds
be rapidly demountable, the railing was
stonemason and construction engineer raised by Catoctin Aqueduct Restoration Fund,
designed in sections, with each section
to oversee all quality control at the site. Inc., and The Community Foundation of Fred-
being 5 feet 4 inches long and having erick County. Additional funding came from
Their involvement and the selection of
14 pickets at 4 inches on center; each individuals, families, corporations, the C&O
a highly qualified contractor, Corman
section was lapped over the end of the Canal Association, Tourism Reinvestment in
Construction, Inc., and their masonry
adjacent section. None of the sections Promotion and Product Program Development
subcontractor, Lorton Stone, LLC, were grants from the Tourism Council of Frederick
could be removed without removing the
critical to ensuring satisfactory comple- County, Maryland Heritage Areas Author-
first section, then the second section,
tion of the structure (Fig. 11). ity, a State of Maryland Bond Bill, and funds
and so on. The first section was locked
received through the Maryland State Highway
in position. Staff at the C&O Canal The Catoctin aqueduct had failed as Administrations Transportation Enhancement
NHP demonstrated that they could a result of a combination of factors: Program. The Catoctin Aqueduct Adopt-
remove the entire railing in less than an unbalanced arrangement of arches, A-Stone Program also raised money for the
one hour. unreliable waterproofing techniques, project.
weak arch geometry, and a soft layer
The posts and sleeves set into the stones
were stainless steel; the finials were
in the bedrock under the west pier. The Notes
failure to use a layer of clay as water-
cast iron, and the remaining scrolls and 1. T. G. Hughes and M. J. Blackler, A Review
proofing appears to have been a serious
plates were carbon steel. The scrolls, of UK Masonry Arch Assessment Methods,
misjudgment in the original design and
finials, and pickets matched the size Proceedings of the Institution of Civil Engi-
is a common problem in all of the C&O neers-Structures and Buildings 122, No. 3
and shape of the original railing. All
Canal aqueducts. The method devel- (1997). T. Boothby, Load Rating of Masonry
elements were cleaned to commercial
oped for this project to measure and Arch Bridges, Journal of Bridge Engineering
blast clean standards of the Society for
locate recovered stones in ring arches 6, No. 2 (March 2001): 79-86.
Protective Coatings-Sophisticated Paint
will be useful in future arch restoration 2. L. T. C. Rolt, From Sea to Sea: Illustrated
Endorsement (SSPC-SPE) with a mini-
projects. History of Canal du Midi, rev. by David
mum blast profile of 1 mils. The rail-
Edwards-May (Grenoble, France: Euro
ings received one primer coat of high- mapping, 1994).
solids epoxy and a finish coat of black Denis McMullan, P.E., is president of
aliphatic polyurethane paint, all applied McMullan & Associates and a regis- 3. Barry Mackintosh, C&O Canal, The Mak-
tered professional engineer in 27 states. ing of a Park (Washington, D.C.: U.S. Dept. of
in the shop under controlled conditions. the Interior, 1991).
He has an MS in structural engineering
from George Washington University 4. Donald R. Shaffer, We are again in the
and specializes in the preservation and midst of trouble: Flooding on the Potomac

26
Analysis and rehabilitation of a masonry aqueduct

River and the Struggle for the Sustainability of 13. Thomas F. Hahn and Emory L. Kemp, Highway Authority, Memorandum to Andrzej
the Chesapeake and Ohio Canal, 1982-1996, Cement Mills along the Potomac River, Insti- Kosicki, Asst. Division Chief OBD Bridge
Scope of Work #11, Cooperative Agreement tute for History of Technology and Industrial Hydraulics, Nov. 2, 2006, re: Catoctin Aque-
CA 3040-4-9001, prepared for the Chesapeake Archeology Monograph Series, vol. II, no. duct Scour Evaluation, Frederick County,
and Ohio Canal National Historical Park, 1 (Morgantown: West Virginia Univ. Press, Lander, Maryland.
National Park Service, July 1997, Appendix B. 1994), 45-50. 30. Photographs, C&O Canal National His-
5. National Park Service, Handbook 142, 14. Secretary of War, letter transmitting torical Park, National Park Service, Dept. of
Chesapeake and Ohio Canal, A Guide to records from John J. Abert, James Kearney, the Interior, C&O Canal NHP Library, Hag-
Chesapeake and Ohio Canal National His and William Gibbs McNeill regarding C&O erstown, Md., through the courtesy of Karen
torical Park, Maryland, District of Colum- Canal plan, construction, costs, and actual M. Gray.
bia and West Virginia (Washington, D.C.: condition. H. R. Rep. No. 94-23 at 414 (1834) 31. Limit State:RING, University of Sheffield,
National Park Service Div. of Publications, (Committee on Roads and Canals, Chesapeake UK. Limit State:RING, a computer program
1991): 22, 37. and Ohio Canal). that can be used to analyze stone masonry
6. Mackintosh, 21, 140. 15. Unrau, 10-11. arches, uses the rigid block method of analy-
sis, which idealizes a masonry arch structure as
7. Harlan D. Unrau, Historic Structure 16. Unrau, 25.
an assemblage of rigid blocks and uses compu-
Report, The Catoctin Aqueduct, with Novem- 17. Unrau, 13. tational limit analysis methods to analyze the
ber 2011 Afterword, Restoration of the Aque-
18. http://www.mdarchives.state.md.us collapse state only.
duct, 2010-2011, Hagerstown, Md., March
1976. /msa/refserv/quickref/html/ba_bcequity.html, 32. National Park Service Value Analysis Files,
through the courtesy of Karen M. Gray, C&O http://www.nps.gov/dscw/design_vafiles.htm,
8. On January 7, 1832, the C&O Canal Com- National Historical Park Librarian, accessed accessed Jan. 29, 2015.
pany Board of Directors resolved that Thomas Sept. 21, 2006.
Purcell and Alfred Cruger should design the 33. National Park Service Preservation Brief
Catoctin aqueduct. Purcell was the more senior 19. Unrau, 14. #15, Preservation of Historic Concrete,
engineer, having been the resident engineer on 20. Ibid. http://www.nps.gov/tps/how-to-preserve
the First Residency (Georgetown). The min- /briefs/15-concrete.htm, accessed Jan. 25,
21. National Weather Service, National Oce-
utes state: Resolved -- That the dam, across 2015. American Concrete Institute, 318-14:
anic and Atmospheric Administration, http://
the river next below Harpers ferry and the Building Code Requirements for Structural
www.weather.gov/media/lwx/climate.html,
Aqueduct across Catoctin Creek, be let at the Concrete and Commentary, 2014.
accessed Dec. 1, 2014.
Office of the Company, on the 1st day of Feb- 34. Virginia Polytechnic Institute and State
ruary [1832], and that proposals be received 22. Mackintosh, 2. University and Virginia Transportation
therefor, until the 31st day of January [1832]; 23. Peter Graham, Civil Engineer, Waterways Research Council, Final Report: Field Perfor-
Resolved -- That the Engineers aforesaid [i.e. Ireland, email message to Denis McMullan, mance of Epoxy-Coated Reinforcing Steel in
Cruger and Purcell] prepare and submit to Jan. 27, 2015. There are currently 43 aque- Virginia Bridge Decks, VTRC 00-R16, Char-
this Board, at its next meeting, the plan of a ducts of various ages and spans still in use in lottesville, Va., Feb. 2000.
suitable Dam, across the Potomac, at the posi- Ireland.
tion, hereto selected, near Harpers ferry, and 35. K. M. Hulet, C. C. Smith, and M. Gilbert,
for the Aqueduct across Catoctin Creek. On 24. Wm. G. McNeill, Report on the Condition Load-carrying Capacity of Flooded Masonry
January 14, 1832, those plans were adopted of the Chesapeake and Ohio Canal (Boston, Arch Bridges, Proceedings of the Institution
by the Board. Proceedings of the President and 1833), reprinted in H. R. Rep. No. 94-23 at of Civil Engineers Bridge Engineering 159
Directors, Chesapeake and Ohio Canal Com- 149 (1834) (Committee on Roads and Canals, (2006): 97-103.
pany, 1831-1833, National Archives, Record Chesapeake and Ohio Canal).
Group 79, Entry 182, Vol. 3, Jan. 7, 1832, 50, 25. Unrau, 16.
55, courtesy of Robert J. Kapsch. Proceedings
26. William Failor, Superintendent, Antietam-
of the President and Directors, Chesapeake
C&O Canal Group, U.S. Dept. of the Interior,
and Ohio Canal Co., 1831-1833, National
Memorandum Nov. 6, 1973, to Dale B. Sipes,
Archives, Record Group 79, Entry 182, Vol. 3,
Chief of Maintenance. C&O Canal National
Feb. 25, 1832, 78.
Historical Park, National Park Service, Dept.
9. Dale B. Sipes, Chief of Maintenance, Antie- of the Interior, C&O Canal NHP Library,
tam-C&O Canal Group, National Park Ser- Hagerstown, Md., through the courtesy of
vice, Report on the Collapse of Catoctin Aque- Karen M. Gray.
duct on October 30, 1973, 1, 3. U.S. Dept. of
27. Specialized Engineering, Subsurface Explo-
Interior, Memorandum, May 28, 1974, Donald
ration and Geotechnical Evaluation, Catoctin
S. Marley, Chief, Division of Construction
Creek Aqueduct, Frederick County, Maryland,
Specifications and Contract Awards, Denver
report prepared for McMullan & Associates,
Service Center, National Park Service, to Chief, The APT Bulletin is published by the
Inc., June 17, 2009.
Division of Property Management and General Association of Preservation Technology, an
Services, Washington Office. 28. W. J. Castle, PE, & Associates, P.C.,
interdisciplinary organization dedicated to
Underwater Inspection and Evaluation of
10. Frederick Post, Jan. 18, 1980. the practical application of the principles and
Catoctin Aqueduct Over Catoctin Creek,
11. Unrau, 8-9. Lander, Maryland, report prepared for techniques necessary for the care and wise
McMullan & Associates, Inc., Sept., 2006. use of the built environment. A subscription
12. Thomas H. Hahn, Towpath Guide to the
Chesapeake & Ohio Canal: Georgetown (Tide- to the Bulletin and free online access to
29. Larry R. Bolt, Asst. Division Chief, Engi-
lock) to Cumberland (York, Pa.: American past articles are member benefits. For more
neering Geology Division, Maryland State
Canal and Transportation Center, 1990), 88. information please visit www.apti.org.
27
APT BULLETIN JOURNAL OF PRESERVATION TECHNOLOGY / 46:4 2015

28

You might also like