You are on page 1of 44

THE BOARD OF ENGINEERS MALAYSIA LEMBAGA JURUTERA MALAYSIA

CONCRETE DURABILITY PROVISIONS IN DESIGN


CODES: ARE THEY REALLY ADEQUATE?

FAILURE OF STRUCTURES

LESSONS LEARNED FROM HIGHLAND TOWERS

ROUTE TO BE AN ACCREDITED CHECKER

THE WTO AND THE SOUTH: IMPLICATIONS AND


KDN PP11720/9/2003 ISSN 0128-4347 VOL.21 MARCH-MAY 2004 RM10.00 RECENT DEVELOPMENTS (PART 1)

FORENSIC
ENGINEERING
JU
A
AG

RU
MB

TE
LE

RA

M A L AY S I A
6 President’s Message
Editor’s Note

contents
JU
A
AG

RU
MB

TE
LE

RA 8 Announcement
M A L AY S I A

Volume 21 March-May 2004

Cover Feature
9 Concrete Durability Provisions In Design Codes:
Are They Really Adequate?
14 Failure Of Structures
21 Lessons Learned From Highland Towers

Guidelines
28 Route To Be An Accredited Checker

12 Update
30 Asian And Pacific Decade Of Disabled Persons
2003-2012

Engineering & Law


16 31 Work Programme – A Contractual Perspective
(Part 1)

Feature
39 Best Management Practices On Soil Erosion And

42 Sediment Control In The Construction Industry


(Part 2)
46 The WTO And The South: Implications And
Recent Developments (Part 1)

Health
46
54 Detox For Health

BULETIN INGENIEUR 4
President’s Message
No one would want to see a structure collapse
or fail, but the fact remains that failures do occur.
When a structure collapses, the finger is invariably
pointed at the structural engineer. But what is
needed in the first place is to determine the exact
KDN PP11720/9/2003 ISSN 0128-4347 VOL. 21 MARCH-MAY 2004 cause of the failure through forensic engineering.
Members of the Board of Engineers Malaysia The goal of a forensic programme is to positively
(BEM) 2003/2004
identify the sequence of events leading to ultimate
President failure.
YBhg. Tan Sri Dato’ Ir. Hj Zaini Omar

Registrar
Within the broad field of engineering, the practice of forensic
Ir. Ashari bin Mohd Yakub engineering involves the investigation of failures of buildings,
Secretary structures, pipelines, foundations, airplanes, manufacturing equipment,
Ir. Dr. Judin bin Abdul Karim
vehicles, bridges, flood control facilities, and other engineered products.
Members of BEM
YBhg. Tan Sri Dato’ Ir. Md Radzi bin Mansor Forensic engineers examine broken parts and bring together a list of
YBhg. Datuk Ir. Santhakumar Sivasubramaniam
YBhg. Dato’ Ir. Dr. Hj. Abdul Rashid bin Maidin
probable failure mechanisms to be investigated. The final step in
YBhg. Datu Ir. Hubert Thian Chong Hui forensic engineering is to use analytical and testing tools to confirm
YBhg. Dato’ Ir. Ashok Kumar Sharma
YBhg. Datuk Ir. Md Sidek bin Ahmad the findings of fact.
YBhg. Datuk Ir. Hj. Keizrul Abdullah
YBhg. Dato’ Ir. Kok Soo Chon A number of difficulties can arise when litigation commences if
Ir. Ho Jin Wah
Ir. Yim Hon Wa the cause of failure has not been investigated adequately. Where there
Ir. Prof. Ow Chee Sheng
Ir. Mohd Aman bin Hj Idris
is an overriding need to consider the cause of an engineering failure,
Ir. Hj. Abu Bakar bin Che’ Man fire or other scientific problem, there is considerable merit in engaging
Ir. Prof. Abang Abdullah bin Abang Ali
Tuan Hj. Basar bin Juraimi a forensic engineer or scientist to consider the cause in isolation. The
Ar. Paul Lai Chu
forensic engineer becomes an expert witness in support of the findings.
Editorial Board
A good forensic engineer will investigate any incident in a structured,
Advisor
YBhg. Tan Sri Dato’ Ir. Hj Zaini Omar
scientific manner. He will be skilled in collecting and recording evidence
in a manner that will withstand scrutiny.
Chairman
YBhg Datuk Ir. Shanthakumar Sivasubramaniam There is a need to develop this area of forensic engineering as an
Editor expert consultancy service.
Ir. Fong Tian Yong

Members
YBhg. Dato’ Ir. Ashok Kumar Sharma
Ir. Prof. Madya Dr. Eric Goh Kok Hoe
Ir. Prof. Ishak bin Abdul Rahman
Ir. Prof. Dr. Ruslan Hassan
Ir. Prof. Dr. K. S. Kannan
Ir. Nitchiananthan Balasubramaniam
Ir. Mustaza bin Hj. Salim
Ir. Md Amir bin Kasim TAN SRI DATO’ Ir. HJ. ZAINI BIN OMAR
Ir. Dr Lee Say Chong President
Ir. Chan Boon Teik
Ir. Choo Kok Beng BOARD OF ENGINEERS MALAYSIA
Publication Officer
Pn. Nik Kamaliah bt. Nik Abdul Rahman

Assistant Publication Officer


Pn. Che Asiah bt. Mohamad Ali

Design and Production


Inforeach Communications Sdn Bhd
Editor’s Note
Buletin Ingenieur is published by the Board of
Engineers Malaysia (Lembaga Jurutera Malaysia)
and is distributed free of charge to registered
The introduction of extra pages in the December
Professional Engineers. 2003 issue has attracted positive comments from our
The statements and opinions expressed in this readers. The Publication Committee will continue to
publication are those of the writers.
focus on policy, guidelines, good practices, issues and
BEM invites all registered engineers to contribute
articles or send their views and comments to the
general information related to the engineering
following address: profession.
Publication Committee In view of the new structure of contents, there was
Lembaga Jurutera Malaysia,
Tingkat 17, Ibu Pejabat JKR a proposal to change the name of the publication as the name ‘buletin’
Kompleks Kerja Raya Malaysia,
Jalan Sultan Salahuddin
may not adequately convey the contents anymore. Readers are welcome
50580 Kuala Lumpur to forward their views and suggestions to the Publication Committee.
Tel: 03-2698 0590 Fax: 03-2692 5017
E-mail: bem1@jkr.gov.my publication@bem.org.my
Web site: http://www.bem.org.my
Ir. Fong Tian Yong
Advertising/Subscriptions
Subscription Form is on page 52
Editor
Advertisement Form is on page 53

BULETIN INGENIEUR 6
Announcement

International Conference on
“Planning, Design and
Construction of Hardened and Publication
Protective Facilities” Calendar
Event Calendar

(HARDFAC 2004)
Date: April 14 – 16, 2004
The following list is the
Venue: Hyatt Saujana Hotel, Subang Publication Calendar for
Organiser: Science and Technology the year 2004. While we
Research Institute for Defence (STRIDE), normally seek contributions
Ministry of Defence from experts for each
Contact: conference@ihsanteam.com special theme, we are also
Fee: RM1550 pleased to accept articles
relevant to themes listed.
ASEAN Australian Engineering
Conference 2004 Please contact the Editor or
Date: May 26-28, 2004 the Publication Officer in
Venue: Sutera Harbour Convention Centre, advance if you would like
Kota Kinabalu to make such contributions
Organisers: IEM & Institution of or to discuss details and
Engineers Australia deadlines.
Contact Person: Ms. Liz Khoo, Eric Pringle
Associates Public Relations Sdn Bhd June 2004: WATER
Tel: 603-2161 7144 September 2004: ENVIRONMENT
Fax: 603-2161 8209 December 2004: STRUCTURES
E-mail: epapr@epapr.com.my

Registration As
JU
A
AG

RU
MB

Accredited CPD
TE
LE

RA

Course Provider M A L AY S I A

With the implementation of a newly


approved Continuing Professional Development
(CPD) Programme, which is in line with a
provision of the amended Engineers Act (2002),
the Board of Engineers Malaysia (BEM) invites JURUTERA PERUNDING LC
potential out-sourced and accredited course
providers (including those providing in-house SDN. BHD.
training courses/programmes) to register with
the BEM. Mechanical & Electrical
Consulting Engineers
For details of registration, please refer to the
BEM’s CPD Policy, Guidelines for CPD Course 130C, Jalan Thamby Abdullah, Brickfields,
Providers and Course Endorsement requirements G.P.O. Box 12538, 50782 Kuala Lumpur,
which can be obtained from the office of the Tel : 22749900, 22749895, 22749896
BEM. The Application Form is also available upon
request.

BULETIN INGENIEUR 8
cover feature
Concrete Durability
Provisions In Design Codes:
Are They Really Adequate?
By Ir. Dr. Lim Char Ching,
Senior Assistant Director, Forensic Engineering Unit,
PWD Malaysia

I
n the 1930s, when the boom in concrete construction potential durability of concrete, it cannot be a generally
began, it was generally believed that concrete valid criterion for several reasons. For example, the
structures typically designed for a design life of 50 compressive strength of a concrete cube or cylinder
years or so would actually last much longer with constitutes the mean value of a property of an entire cross-
little or no maintenance. However, that belief was section of the specimen, whereas concrete durability is
squashed when reports of premature deterioration of governed primarily by the properties of the concrete cover
concrete in tunnels, marine structures and bridge decks (covercrete). Concretes of the same strength grade may
were made known. It has become a worldwide problem differ in their durability resistance against chloride
today. The widespread premature deterioration and penetration, carbonation and sulphate attack. Now, it is
durability issues affecting many concrete structures have generally accepted that concrete durability is largely
eroded public confidence in the use of concrete as a governed by the resistance of concrete cover to the ingress
construction material. It is now prudent to critically re- of aggressive media. So, the emphasis should be on the
assess the provisions in design codes on concrete means of achieving a good quality concrete cover or ‘skin’
durability. of the structure.

CODE REQUIREMENTS ON DURABILITY Cracks versus Durability


Cracks are inherently present in concrete due to
In the present design codes, durability requirements overstress, environmental effects and chemical reactions.
for concrete structures are largely based on the These cracks may range from wide and deep cracks on
conventional method of specifying arbitrarily certain the concrete surface, down to microcracks at the
limiting values e.g. concrete grade, minimum cement aggregate-cement paste interface in the concrete. Although
content, maximum water-cement ratio, cover thickness, these cracks do not generally affect the structural capacity,
and maximum structural crack width. This so-called they are rather harmful from the viewpoint of durability.
deemed-to-satisfy approach of specifying for concrete When the cracks are limited in number and size, they
“durability” frequently yields concrete performance that are discontinuous and do not pose any direct effect on
is not always satisfactory. Chloride-induced corrosion of the durability of concrete. However, with time, they have
reinforcement continues to represent the single largest the potential of becoming continuous (or interconnected)
cause of deterioration of concrete structures worldwide. and enlarged under the influence of stress or due to
Based on substantial data available from field performance, leaching. These interconnected cracks can serve as main
exposure trials and laboratory tests on concrete, many conduits for transport of harmful external ions and gases
researchers are convinced that the current code into the concrete. Concrete, thus, becomes vulnerable to
requirements do not provide adequate resistance to the processes of deterioration, as it gradually loses its
chlorides, even when properly implemented. In the light watertightness in the course of its service life.
of current research, the deemed-to-satisfy rule for concrete Shrinkage cracks are often limited through the use of
“durability” in the present codes can be challenged. a larger quantity of steel reinforcement, as permitted in
many codes. Mehta (1997) believed that this simply
Strength versus Durability transforms the wider surface cracks into many finer cracks
In many codes and specifications, the compressive and microcracks in the concrete. The microcracks and
strength of concrete is often used as a criterion for pores can form an interconnected pathway for ingress of
durability. Though it may give some indication of the aggressive substances into the concrete.

BULETIN INGENIEUR 9
8
cover feature
Table 1 : Interplay between Crack Width and Concrete Cover on Durability its durability performance in a marine
environment. A value of Wcr/C not
Crack Concrete exceeding 0.005 is recommended.
Width Cover Remarks
(mm) (mm)
DESIGNING CONCRETE TO LAST

Example 1: A and B having different crack width but Durability of concrete structures in
Structure A 0.3 60 same concrete cover. hostile environments have been the
Structure B 0.2 60 B is more durable than A.
concern of practising engineers
worldwide. While there has been an
Example 2: A and B having same crack width but
Structure A 0.3 60 different concrete cover. immense progress in the
Structure B 0.3 40 A is more durable than B. understanding of the causes of, and
solutions to problems found in
Example 3: A and B having different crack width and concrete structures in recent years, the
Structure A 0.3 60 concrete cover. subject is not well recognised.
Structure B 0.1 40 Which is more durable, A or B? Concrete structures can be designed
and built to last for many generations.
This noble aspiration can be achieved
Crack Width Limits by engineers, utilising state-of-the-art knowledge in
It has been well established that corrosion of concrete technology.
reinforcements in concrete is dependent on crack width
and cover thickness, amongst other factors. For durability, The Concept Of Service Life
many codes would specify 0.3 mm as limiting crack width The concept of service life prediction for concrete
for reinforced concrete structures. For marine exposure, structures is now becoming an area of increasing interest
the minimum concrete cover given in the codes may range for engineers. In this respect, durability of concrete plays
from 40 mm to 60 mm. Assuming other factors being the an important role. Prediction models have been developed
same, Table 1 illustrates the interplay between crack width to predict and quantify structural service life based on
and cover on concrete durability. material resistance and environmental loads. The service
Examples 1 and 2 illustrate a comparison of a single life of a structure is defined as the period of time after
parameter (either crack width or cover) on concrete installation until such time when costly repair becomes
durability. In both cases, the comparison is straight necessary.
forward. Example 3 illustrates a comparison between both For concrete structures in marine environments, the
crack width and cover on concrete durability. In this resistance of concrete to chloride-induced corrosion largely
case, the assessment of concrete durability becomes controls its long-term durability performance. Concrete
complicated. deterioration due to chloride-induced corrosion can be
It should be pointed out that crack width and cover represented by a simple service life model consisting of
thickness are inter-dependent. For a given stress level in an initiation stage and a propagation stage, shown in
the steel bar and keeping other variables constant, crack Figure 1.
width increases with cover thickness. Nowadays, high The initiation stage is the time from initial exposure
tensile bars with yield strength of 460 MPa and above are until depassivation of steel in concrete. This is largely
commonly used as reinforcements in concrete. In this dependent on the rate at which chlorides penetrate into
case, crack width larger than expected may develop when concrete. The propagation stage is the time from the onset
a large cover is adopted. Of course, 0.3 mm crack width
can still be achieved with a large cover, provided the steel
is designed with much lower stress than permitted. In
Degree of
this case, optimum use of high tensile bars as Corrosion
reinforcements in concrete is not achieved. in Steel
The influence of both parameters, surface crack width Acceptable Limit

(Wcr) and cover thickness (C), should be considered in


totality, i.e., one dependent on the other. This is in contrast
with the durability requirements given in many design
codes, in which surface crack width and cover provisions
are recommended to be independent of the other.
Lim et al (2000) proposed the crack width-to-cover Initiation Period Propagation Period
ratio (Wcr/C) as an indicator for assessing durability
Service Life
performance of a cracked reinforced concrete in a marine
environment. He concluded that it is desirable to minimise
Wcr/C of a cracked reinforced concrete in order to enhance Figure 1 : Service Life Prediction Model

BULETIN INGENIEUR 10
cover feature
of steel corrosion until a specified acceptable “deterioration type of blended cement concrete may be suitable for
limit” in concrete has been reached, e.g. first visible one application but not for the other. Selective usage of
cracking on the concrete surface or first spalling. these materials is recommended.
Many engineers have associated service life of concrete
structures primarily with the initiation stage, to maintain Performance-based Specification
structural safety and serviceability, acceptable appearance, Present specifications for concrete works are largely
and without having to incur unforeseen high costs for method-based, in that they describe how works should be
repair. Currently, some concrete structures around the carried out on site, e.g., placing and curing of fresh
world have been designed using this concept, e.g. the Great concrete. The acceptance criteria for concrete at site are
Belt Link Bridge in Denmark with 100 years of service solely based on tests carried out on “specially” prepared
life! It is foreseen that within the next few years, specimens of fresh concrete. The specification “assumes”
reliability-based service life designs may be incorporated that the workmanship in preparing the test specimens
in today’s ordinary design procedures for concrete would be the same as that in the works. This assumption
structures. is seldom true. Furthermore, the test specimens are
subjected to a controlled curing regime and environmental
Blended Cement Technology condition, compared with the concrete placed at site. It is
The term ‘blended cement’ is used to include both obvious that the quality of hardened concrete in the
the products of blending of one or more mineral structure is generally different from the test specimens.
admixtures with an Ordinary Portland Cement (OPC). The The method-based specification has been proven to be
process of blending can be achieved either by inter- inadequate in addressing durability issues affecting
grinding the mineral admixture(s) with cement clinker, concrete structures. The specification cannot guarantee
or by blending the mineral admixture(s) with OPC. a satisfactory “performance” of hardened concrete in the
The wide range of binder systems, namely, Portland structure.
cements and blended cements available in many parts A concrete structure designed for a specific service
of the world provides opportunities for the best concrete life should be complemented with a performance-based
to be chosen for a particular environment. Fly ash, slag specification. This is to ensure that the hardened concrete
and silica fume are the three commonly available mineral “performs” in an environment for which it is expected to
admixtures used in blended cements. With proper meet the service life requirement. The specification should
dosage, these blends can be effective in enhancing the focus on tests to be carried out on in-situ hardened
performance of concrete in high chloride and sulphate concrete. The test results should become the basis for
conditions. They have been found to improve the accepting or rejecting the concrete at site. Improved
resistance of concrete to chloride penetration and to performance-based specifications are being developed in
reduce corrosion rate of steel reinforcement. many countries. However, suitable short-term
Improvements of the order of three to five times are not “performance” tests necessary for such specifications are
uncommon. Blended cements also showed great potential not yet available.
in reducing expansion and loss of strength of concrete
exposed to sulphate condition.
The use of blended cement concrete has been
recognised by most national standards and codes of
practice on concrete structures. In general, fly ash and
slag are used in blended cements for durability and long-
term engineering properties. Silica fume is used when
both early age engineering properties and durability are
needed. The common dosages of these mineral
admixtures vary between 20 and 40% for fly ash, between
35 and 80% for slag and five and 10% for silica fume.
The optimum dosages are obviously dependent upon
specific technical requirements and cost consideration
relevant to a particular application.
In the past, the lack of knowledge in blended cement
technology had resulted in structures with premature
deterioration. Today, it is possible to tailor-make
improved quality concrete using blended cement
technology for many applications. Blended cement
concrete has proven worldwide to enhance workability
of fresh concrete and durability properties of hardened
concrete. However, blended cement concretes also have
their disadvantages and limitations too. A particular

BULETIN INGENIEUR 11
cover feature

CONCLUSION improved quality concrete for most applications. A good


knowledge of blended cement technology is necessary to
Concrete structures exposed to marine environments ensure its full potential in being utilised for making durable
have been found to suffer mainly from corrosion of the concrete.
reinforcing steel. It is necessary for engineers to
understand the importance and mechanisms of chloride- REFERENCES
induced corrosion of steel in concrete. The effect of the
quality of concrete on the resistance to chloride [1] Mehta, P.K. (1997), ‘Durability-Critical Issues for
penetration, chloride threshold and corrosion rate of the the Future’, Concrete International, pp. 27-33.
reinforcing steel are critical in determining the service [2] Rostam, S. (1996), ‘High Performance Concrete
life of structures in this environment. The concept of Cover - Why It is Needed and How to Achieve It
service life prediction for concrete structures is becoming in Practice’, Construction and Building Materials,
an area of increasing interest for engineers. Therefore, a Vol. 10, No. 5, pp. 407-421.
good understanding of the concept and its application in [3] Sarja, A. (1996), ‘Towards Practical Durability
structural design is essential to ensure that optimum Design of Concrete Structures’, Proceedings of
concrete performance is achieved before a costly repair the 7th Int. Conference on Durability of Building
to the structure becomes necessary. Materials and Components, Edited by C.
When designing concrete for durability performance, Sjostrom, Sweden, pp. 1237-1247.
attention must be paid to both the performance standards [4] Rostam, S. and Shiessl, P. (1993), ‘Next
required as well as selecting a set of compatible compliance Generation Design Concepts for Durability and
criteria. This is to ensure that the hardened concrete Performance of Concrete Structures’, Proceedings
“performs” in an environment for which it is expected to of the 6th International Conference on Durability
meet the service life requirement. The specifications should of Building Materials and Components, Japan.
focus on tests to be carried out on in-situ hardened [5] RILEM Technical Committee 130-CSL (1996),
concrete. The test results should become the basis for ‘Durability Design of Concrete Structures’, Edited
accepting or rejecting the concrete at site. Improved by Sarja, A. and Vesikari, E., E & FN SPON.
performance-based specifications are being developed. [6] Lim, C.C., Gowripalan, N. and Sirivivatnanon,
However, suitable short-term “performance” tests V., ‘Chloride Diffusivity of Concrete Cracked in
necessary for such specifications are not yet available. Flexure’, Cement and Concrete Research, Vol. 30,
With the availability of mineral admixtures in many No. 5, pp. 725-730, May 2000. BEM
parts of the world, it is now possible to tailor-make

B U L E T I N I N G E N I E U R 12
cover feature

Failure Of Structures
By Ir. Tee Horng Hean, B.Eng. (Hons), MSc (Eng.), MBA, M.I.E.M.

A structural engineer’s dream is to design structures which are fit for their intended uses. No engineer
would want to see a structure collapse or fail, unless that engineer is an engineer researching in
causes of failure. Some common causes of structural failure are discussed in this paper. This paper is
not intended to discredit any parties (architects, engineers, developers, advertisers, etc.) and as such,
some photographs may appear doctored to protect the anonymity of the parties involved. The intention
of writing this paper is to jog the young engineer’s memory on the importance of engineering
fundamentals, and failure to observe these engineering fundamentals taught in school could be disastrous.

M
any young engineers have never witnessed
structural failure. A structural failure may
have adverse consequences on the parties
involved in the construction of the structure.
For instance, a former school bus driver brought up a
negligence suit against a contractor who constructed a
unipole tower, which collapsed on his bus while he was
driving at the junction of Jalan Segambut and Jalan
Kuching (NSTP, March 6 2001). According to the findings,
the unipole could only withstand a wind speed of 19.2
metres per second and in Kuala Lumpur, wind speeds of
as high as 35.5 metres per second have been recorded
(NSTP, March 6 2001). The best remedy for young
engineers, if in doubt of their design criteria and to avoid
any structural failure, is to ascertain the facts from reliable
sources.

What Is A Structure?

Basically, a structure is a system for transferring loads Photo 1: A tall tree with buttresses
from one place to another and nature can show examples
of structures that support loads (Seward, 1998, p.2).
Professor Harry H. West also noted that structure describes
much of what is seen in nature such as a fern leaf, an oak
tree, shrub with ribbed branches, spider webs, etc. (West,
1993, p.4). A tall tree in a rainforest, for instance, forms
buttresses (see Photo 1). A structural engineer would
definitely know that by forming these buttresses, the huge
moments (a form of force that causes bending) induced at
the base of the tree can be resisted, and as such, this
cantilever-tree can grow to a considerable height to resist
the force imposed by winds.
Engineers do make use of this phenomenon and it is
quite common to see them adopting stiffeners to resist
certain amounts of moment at a stanchion base, for
instance (see Photo 2). If engineers adopt structural
engineering knowledge, why is it that there is still failure
of structures? Some of the causes of structural failure are
discussed in the following topics. Photo 2: A stanchion with a stiffener

B U L E T I N I N G E N I E U R 14
cover feature
Photo 3: A typical ‘continuous’ hoarding system

Underestimating Loads Photo 4: A sheared off bolt with the size of one’s
thumbnail
Sometimes, designers may underestimate the load that
would be imposed upon their structure when the structure
is in operation. A good example is the unipole structure
that collapsed as described earlier. The unipole structure
could only withstand wind pressures of not exceeding q
= 0.613 x 19.22 = 226N/m2 but in the area where the
collapse of the unipole occurred, wind pressures of as
high as q = 0.613 x 35.52 = 773N/m2 have been recorded.
Various structural elements are likely to be overstressed
when designers underestimate the load that would be
imposed on their designed structure. Consequently, their
structure is susceptible to collapse.

Connections

Surprisingly, research has shown that 30% of structural


failures are caused by defective detailed design of the
joints between structural members (Seward, 1998, p.232).
For instance, a simple system of hoarding with structural
elements being connected with undersized bolts may look
perfectly sturdy (see Photo 3). However, due to the use of Photo 5: A small bolt used to connect structural elements
undersized bolts (see Photo
4 and Photo 5), connecting
the horizontal and vertical
structural members, the bolts
were sheared off, causing the
horizontal elements to be
disconnected and resulting in
the cantilever effect (see
Figure 1). Bearing in mind
that in a ‘cantilever’ system,
the stress intensity
experienced by the structure
can be as large as four times
of that of the ‘continuous’
system.
This is precisely what
happened to this hoarding
and since the bolts were
sheared off, the domino Figure 1: Change of structural system due to sheared bolt

BULETIN INGENIEUR 15
cover feature
effect of excessive
bending of the steel
hoarding sheet (see Photo
6), the structural members
being subjected to
excessive bending and the
footing being pulled off
the ground (see Photo 7)
occurred.
In short, failure of
connections can lead to a
change in the structural
system, and in turn, have
adverse domino effects.

Photo 6: Failure of a
simple hoarding
structure

Photo 7: A footing being


pulled off the ground

Inconsistent Design, Detailing And Construction

A structural engineer deals with numbers in his


structural design, which may be Greek to a layman, a
draughtsperson or even the contractor. In order to
communicate his design to the contractor, structural
drawings are produced. At times, the structural engineer
may not be the one producing the structural drawings
but his draughtsperson would be the one drafting it.
Somehow or rather, miscommunication may occur and
designs do not tally with the drawings. There may be
times when young engineers may draft the drawings but
drafted them incorrectly. It is quite common to note
that engineers analyse a reinforced concrete structure
as a pin-joint or simply supported but in his or her detail,
a fixed support is being provided. The consequence of Photo 8: A pin-joint
proceeding with construction would be similar as that
of the hoarding where a change of structural system may
occur. For instance, a lamppost when properly fixed to the
A good example of a pin-joint can be seen in a see- ground (see Photo 9), is perfectly sturdy and most
saw (see Photo 8). engineers would analyse the lamp-post as a fixed

BULETIN INGENIEUR 16
cover feature
cantilever. But due to improper detailing or construction, Not Considering Elements In Contact With Structure
this lamp-post behaved like a pin-joint (similar to the
see-saw) and some lateral force had induced the collapse When columns are supported by relatively small
of the lamp-post (see Photo 10 and Photo 11). footings and the soil surrounding the footings is of
compressible soil, a structural engineer should analyse
the columns as pin-jointed (Winter & Nilson, 1979, p.392).
Similarly, if the soil surrounding the footings is stiff and
incompressible, then the structural engineer should analyse
the columns as fixed.

Photo 9: A lamp-post

Photo 12: A collapsed signboard

Photo 10: A collapsed lamp-post

Photo 13: Close-up view of footing of Photo 12

Structural engineers would analyse a signboard,


assuming it to be fixed but sometimes, due to the soil
conditions, it is not possible to have a fixed joint. For
instance, one would analyse this signboard as fixed (see
Photo 12), but due to the fact that the soil is soft and
compressible, after a heavy shower and due to strong wind
forces the footing of this signboard can easily be pulled
out when the post is not adequately penetrated into the
ground (see Photo 13). The strong wind has imposed a
Photo 11: Lamp-post not properly fixed to the ground stress that is higher than that allowed by the soil, and
(Close-up of Photo 10) consequently, the footing behaved as a pin-joint.

BULETIN INGENIEUR 17
cover feature
Similarly, the following signboard was erected in soft
and compressible soil and consequently, excessive
deflection is experienced and one could easily pull down
the whole signboard without much effort (see Photo 14
and Photo 15).
Following the above argument, we can deduce that if
a structural element were to be anchored into a brick-
wall, it is considered fixed so long as the stresses
transferred to the brick-wall at the joint do not exceed
the stress of the brick. On the other hand, if the applied
force on the structural element is excessive, causing the
stresses transferred to the brick-wall at the joint to exceed
the allowable stress of the brick, this element now behaves
like a pin-joint (similar to the see-saw). This is one of Photo 16: Collapse of a signboard
the aspects often overlooked and has to be taken into
consideration in structural engineering designs. metres collapsed after a gust of strong wind (see Photo
16). A rough free body diagram of this structure is shown
in Figure 2.
After running a simple structural analysis on the above
structure by applying a wind force with a speed of 35.5
metres per second, it was noted that the structure would
not have collapsed if undersized angles were not used.
From the site condition, it was observed that the angles
gave way and experienced excessive twisting and buckling
(see Photo 17).

Photo 14: A deflected signboard

Photo 17: Twisting and buckling of undersized angles

Photo 15: Soft and compressible soil (Close-up of Photo 14)

Providing Undersized Members

Though it seldom happens, there are times when


undersized members are used. These undersized members
would most definitely experience excessive stress. When
certain structural members cannot withstand the forces
that are imposed upon them, the structure would be
imminent of collapse. For instance, the following
signboard measuring approximately 20 metres by 16.5 Figure 2: Free body diagram of signboard

BULETIN INGENIEUR 18
cover feature
Lack Of Maintenance

Many people have the misconception that structures


do not need any maintenance. This is totally incorrect.
Whatever the structures are made of, whether steel, timber
or reinforced concrete, they need constant maintenance.
Steel structures, for instance, are susceptible to corrosion
while timber structures can be destroyed by a colony of
termites. Without maintaining a structure, slowly but
surely, defects would occur. If these defects are left
unattended, it would lead to further serious defects and
in the end, a structural collapse may be possible due to
the weakening of the structural members.

Overlooking The Third Dimension


Figure 3: Change of structural system
Every single object, be it a ball, a car or a structure,
Due to the fact that the angles failed, the above can move in three different directions, namely left to right,
structural system changed from a triangular frame (see up to down and backward to forward. All structures,
Figure 3) to a cantilever. except for space frames, can be analysed and designed by
The change of the structural system has caused the
simplifying them into two-dimensional structures. There
cantilever to experience a high bending stress near the
may be the possibility that engineers can overlook one of
footing. This high bending stress cannot be resisted by
the welding provided between the I-beam and the baseplate the three dimensions. When this occurs, the structure is
(see Photo 18), and consequently, the toppling of the only structurally sound in two dimensions but can fail in
signboard occurred. Besides that, this high stress has the third dimension.
caused the web of the I-beam to tear (see Photo 19).
Constructing An Unstable (Mechanism) Structure

There are times when a structure is erected but is


unstable. This is especially frequent in roof trusses. Many
a time, the centre line of the structural members do not
meet and thus, forming a structural system which is not a
truss. For instance, the following structural framework
(see Photo 20) was constructed and it was noted that there
was no triangulation of the framework, which was of
necessity for roof trusses. The structure looked sturdy
when erected. Even when the roofing sheets were installed
(see Photo 21), the structure still looked stable.
Unfortunately, during the monsoon season, heavy rain
and strong wind were inevitable and they both imposed
additional load on the structure, which consequently
collapsed (see Photo 22). Most textbooks on structural
Photo 18: The weld between the I-beam and baseplate
mechanics would note that most trusses would require a
gave way
system of triangulation in order for the structure to be
stable, and in this case (see Photo 20), the collapsed
structure did not have any form of triangulation system.

Not Consulting An Engineer

Obviously, this point needs no explanation whatsoever.


There are times when constructors would defy the
instructions of engineers and proceed with construction,
without realising that they could be constructing a
collapse-prone structure.
Worst of all, there are owners who never even engage
a structural engineer but ‘copy’ the sizes of a structure
from another construction site to erect their own. This
Photo 19: Tearing of I-beam’s web can be very dangerous as the site conditions vary.

BULETIN INGENIEUR 19
cover feature

Photo 20: An unstable


timber truss structure
without proper
triangulation system

Photo 21: Roofing


sheets installed to
timber frame

Photo 22: Collapse of


timber structure

Conclusion

The paper discussed only some of the common factors REFERENCES


as to why structures fail. There can be lots of other factors
including minor mistakes such as dimensioning a
structural member longer than it is supposed to be, using Harry, H. West, 1993, Fundamentals of Structural
the wrong units (imperial/metric), not following the Analysis, John Wiley & Sons, New Jersey.
construction drawings, mixing of high tensile and mild
NSTP, 6 March 2001, New Straits Times Press,
steel reinforcements for reinforced concrete structures,
March 19 Decision by Court on Negligence Suit,
reducing the lever arm of a reinforced concrete structural
[Online], Available from URL: http: //www.lexis-
element when workers step on the steel reinforcements,
nexis.com/universe [Accessed: 18 November
providing inadequate anchorage length for reinforcement
2003]
bars, etc. which can lead to structural failure. The other
cause of possible failure in the structure is misuse of the Seward, D., 1998, Understanding Structures –
erected structure. One of the best ways for young engineers Analysis, Materials, Design, Second Edition,
to avoid making the mistakes discussed in this paper is to MacMillian, Hampshire.
ascertain the facts from reliable sources.
The fundamentals of engineering should be applied in Winter, G. & Nilson, A. H., Design of Concrete
the design of all engineering structures. Overlooking the Structures, Ninth Edition, McGraw Hill, New
design of even a minute part of a structure such as York. BEM
connections can be disastrous.

BULETIN INGENIEUR 20
cover feature
Lessons Learned From
Highland Towers
By Murgan D. Maniam, Pengarah Undang-Undang, Majlis Perbandaran Pulau Pinang

Architects and engineers owe a professional obligation to the public and their profession to
conduct themselves and practise their profession in accord with ethical standards. Local authorities
are also required to act reasonably and in accordance with the law.
Clients and the public place trust and confidence in the competence and skills of the professional
architects and engineers. Generally, both the professionals depend on the personal confidence of
the client in their technical competence; and the confidence of the public at large in the integrity
and ethical conduct of the professions as a whole.
It is the purpose of this paper to examine the decision of the High Court and the Court of
Appeal in respect of the roles played by the architect, engineer, developer and the local authority
in the development of the Highland Towers, and to learn the observations and rulings of the two
courts to give a greater insight and understanding of their respective roles.

H
ighland Towers, as is collectively known, The 10 Defendants were as follows:
consisted of three blocks of apartments known
as Blocks 1, 2 and 3. It was constructed (i) 1st Defendant - Developer
between 1975 and 1978. Directly behind the
three blocks was a steep slope. A stream (‘the east stream’) (ii) 2nd Defendant - Draftsman who was engaged
by the developer as the
originating upslope from the Metrolux land flowed across
Architect for the project
part of the slope.
On Saturday, December 11, 1993, about 15 years later,
(iii) 3rd Defendant - 2 nd Defendant’s brother
after 10 days of continuous rainfall, a landslide occurred engaged by the 1st Defendant
resulting in the collapse of Block 1. Forty-eight people as the Engineer for the project
were recorded dead. Immediately after the collapse of
Block 1, the residents of Blocks 2 and 3 were prevented (iv) 4th Defendant - Majlis Perbandaran
from entering their apartments by MPAJ for fear of the Ampang Jaya
instability of these two buildings. A few days later, they
were allowed in but only to collect their personal (v) 5th Defendant - Arab-Malaysian Bank –
valuables. At that time, their apartments were looted owner of 50 lots of bungalow
and subsequently vandalized. land directly at the rear of
Seventy-three owners and occupiers of the Blocks 2 Highland Towers
and 3 apartments brought an action against 10 defendants
(vi) 6th Defendant - Tropic - company that carried
in negligence, nuisance, strict liability under the rule in
out clearing works on the 5th
Rylands v. Fletcher and breach of statutory duty. The
Defendant’s land in 1992
Plaintiffs alleged inter alia that they had been unable to
re-occupy Blocks 2 and 3 emanating from the collapse of (vii) 7th Defendant - owner of Metrolux land (the
Block 1, as the result of MPAJ’s pre and post-collapse higher land adjacent to the 5th
acts and omissions. Defendant’s land)

B U L E T I N I N G E N I E U R 21
cover feature
(viii) 8th Defendant - Project Manager for the 7th The Plaintiffs alleged that the 2nd Defendant had held
Defendant and was in charge himself out to be a suitably qualified, competent and skilled
of the development of the person to design, prepare and sign architectural and other
Metrolux land. building plans. In the performance of this task, the 2nd
Defendant has breached a common law duty of care to
(ix) 9th Defendant - Selangor State Government the Plaintiffs to take reasonable care and diligence in
ensuring that:
(x) 10th Defendant - Director of Lands and Mines,
Selangor
(i) the drainage required and rubble walls and the
earthworks were adequately and properly
JUDGMENT OF THE HIGH COURT
designed, supervised during its construction and
in compliance with the requirements as set by
The High Court found the 1st, 2nd, 3rd, 4th, 5th, 7th and 8th
the authorities;
Defendants liable and apportioned liability in the following
percentages :
(ii) by the same acts or omissions, the 2nd Defendant
(i) 1st Defendant - 15% had created a nuisance on the hill slope behind
Highland Towers.
(ii) 2nd Defendant - 10%
The 2nd Defendant argued that he did not owe such
(iii) rd
3 Defendant - 10% duty of care to the Plaintiffs. Furthermore, even if such
duty of care exists, it was not breached. He explained
(iv) 4th Defendant - 15% that he was only engaged to design the three apartment
blocks and was never involved in the design, supervision
(v) 5th Defendant - 30% and construction of drains, rubble walls and earthworks
within and outside of Highland Towers site; he submitted
(vi) 7th & 8th Defendants - 20% that the 1st Defendant (Developer) carried out these works.
He played no part in them. He also submitted that the
After due consideration, the court ruled that the intervening acts of the 4th, 5th, 7th and 8th Defendants in
landslide that brought down Block 1 was a rotational altering the condition of the area caused the collapse of
retrogressive slide emanating from the high wall behind
Block 1 and exempted from liability.
the second tier car park. The High Court also decided
A building draftsman is only permitted under the
that Block 1 had collapsed due to a landslide caused
Architect’s Act 1967 to design buildings of no more than
primarily by water which emanated from the damaged
two storeys in height and limited floor space. In this case,
pipe culvert, and the inadequate and unattended drains
on the 5th Defendant’s land. each block of Highland Towers consisted of 12 storeys
The judgment of the High Court has since been reported with a built area far exceeding that allowed for a building
as Steven Phoa Cheng Loon & Ors v Highland Properties draftsman to undertake. The 2nd Defendant managed to
Sdn. Bhd. & Ors (2000) 4 MLJ 200. induce a relevant Government department to grant him a
‘specially authorised person’ status under a repealed
LIABILITY OF THE 2ND DEFENDANT – THE ARCHITECT enactment (the Architect Ordinance 1951) which he
claimed entitled him to summit and oversee construction
The 2nd Defendant was an Architectural Draftsman. works of three apartment blocks.
He drew and submitted the layout plans for and on behalf The court held that this would make no difference to
of the 1st Defendant. The 2nd Defendant knew that he was the duty of care the 2nd Defendant owed. James Foong J
not a fully qualified and registered architect. When the said:
layout plan was approved subject to conditions, the 2nd
Defendant prepared and submitted the building plans. ‘When this Defendant had represented himself as a
The 2nd Defendant, whilst submitting the layout plans qualified architect to all and sundry, as displayed by
and building plans, had held himself out as a registered
his actions, then he must be judged according to the
architect. The local authority, by some error on their part
character he had assumed.’
in not checking the 2nd Defendant’s credentials had in
fact permitted him to submit such plans.
The extent of his duty, said the judge:
CF was issued for the three blocks on the following dates:

(i) Block 1 - 29.9.1978 ‘Is primarily to his client because he has a contractual
relationship with him. But in law, an architect is
(ii) Block 2 - 6.11.1981 also liable to anyone who is sufficiently proximate
and whom the architect could foresee that his act
(iii) Block 3 - 24.5.1985 and/or omission would cause damage to that person.

BULETIN INGENIEUR 22
cover feature
….. At the time when this Defendant exercised his the 2nd Defendant was engaged to build cannot be
duty as an architect for the Highland Towers project, maintained.
he must have foreseen that the apartments he built The court held that a claim for pure economic loss can
would be sold, and purchasers, their servants and or be maintained against a Defendant, and therefore ruled
agents would be occupying them. ….. he must have that the Plaintiffs’ claim for negligence and nuisance is
or ought to have them in contemplation when he established against the 2nd Defendant.
was directing his mind to his acts and/or omissions.’
LIABILITY OF THE 3RD DEFENDANT – THE ENGINEER
By this, a duty of care existed between the 2nd
Defendant and the Plaintiffs. The 3rd Defendant was a qualified civil engineer. The
The 2nd Defendant had also argued that he had no 2 Defendant appointed the 3rd Defendant, who was his
nd

responsibility for the drainage or earthworks or anything brother, to be the consulting engineer for Highland Towers.
else beyond the design and supervision of construction Initially, the 3rd Defendant’s scope of works was restricted
of the apartment blocks. To this, the judge held: to the structural aspect of the three blocks. But
subsequently, the 3rd Defendant was engaged by the 1st
‘I think the 2 nd Defendant is under a serious Defendant to submit proposals over the drainage of the
misapprehension that an architect is engaged just area. His drainage plan was approved. He was also
to design and supervise the construction of a building retained by the 1st Defendant to design and supervise the
and need not bother with the surrounding area where construction of two retaining walls on the Highland Towers
the building is to be erected. Surely the primary site.
consideration for the construction of any building, The Plaintiffs claimed that the 3rd Defendant was
or structure for that matter, besides the aesthetics negligent for the following reasons:
aspect, is the safety of the building. To achieve this,
the condition of the land on which the building is to (i) designing unsuitable foundations;
be built as well as those in the vicinity must be
considered and evaluated, particularly if it has (ii) lack of care and concern of the hill and slope;
potential adverse effects to the building planned.’
(iii) issuing a notice to the authorities confirming the
‘…… He must ensure that no soil from the hill slope drainage works was completed when only a
would come crashing down on his designs. …..’ fraction of it was done.

‘…… the 2nd Defendant did foresee the danger of not By the above acts of preparing, designing and
exercising his professional skill, care and diligence supervising the construction of Highland Towers and the
in attending to the initial and basic factors regarding drainage system of the Highland Towers site, he was
drainage and the stability of the hill slope. As an negligent and had caused nuisance to them.
architect, or someone who represented himself as The 3rd Defendant had used rail piles welded together
one, he must have foreseen the dangers that if no as foundation to support the three apartment blocks. This
proper, adequate and sufficient drainage system and type of piles, which was considered inferior to concrete
retention walls were built, there would be danger to piles, was accepted in the engineering and building
the buildings erected below. Yet he neglected this industry to support high-rise buildings at the material
basic duty. The intervening acts of the third parties time. Thus, no fault can be attributed to the 3rd Defendant
may not be foreseen by him, but if a proper, adequate in using the rail piles as he was only adhering to the
and sufficient drainage system and retaining walls accepted professional practice at that time.
were implemented and erected, then the collapse of However, there was lack of consideration by the 3rd
Block 1 may not even have occurred.’ Defendant to the hill and the slope directly behind the
three blocks. The court ruled that the 3rd Defendant should
On the facts, the court found the 2nd Defendant had have reasonably foreseen the danger of a landslide
breached his duty of care to the Plaintiffs. The 2nd producing a lateral load against the foundation of the
Defendant was held to have ‘failed in his duty as an building. For this, he should have exercised care to either
architect and had also refused to comply with the design and construct a foundation to accommodate the
requirements imposed by the authorities on the drainage lateral load or ensure that the slope was reasonably stable.
of the area. Besides that, he had also colluded with the Failure to do so is a breach of his duty of care he owes to
1st and 3rd Defendants (Developer and Engineer) to obtain the Plaintiffs since his duty was to ensure the safety of
CF for the three apartment blocks of the Highland Towers the buildings he designed and built.
without fulfilling the conditions as set out by the 4th The 3rd Defendant’s attempt to deny liability on the
Defendant (MPAJ). ground that he relied on the 1st Defendant to ensure that
The 2nd Defendant argued that the Plaintiffs’ claim other retaining walls were constructed properly was
for pure economic loss i.e. compensation to make good unsuccessful. The judge found that it was encumbent
the defective building or for a replacement thereof which upon the 3rd Defendant to enquire and ascertain whether

BULETIN INGENIEUR 23
cover feature
the work was that of a qualified professional and what its to remind this Defendant that he has to live out the
impact might be on the safety of his own building. The rest of his life knowing truly well that he had
judge agreed with a passage from the judgment of Bingham contributed to the tragedy of Highland Towers.’
LJ in the case of Eckersley v. Binnie (1988) 18 Con LR 1
@ p.80 The 3rd Defendant was found liable in negligence
and nuisance.
‘…… a professional man should command the corpus
of knowledge which forms part of the professional LIABILITY OF THE 1ST DEFENDANT – THE DEVELOPER
equipment of the ordinary member of his profession.
He should not lag behind other ordinarily assiduous The Plaintiffs claimed the 1st Defendant liable in negligence
and intelligent members of his profession in knowledge for the following reasons:
of new advances, discoveries and developments in his
field. He should have such awareness as an ordinarily (i) Not employing reasonably fit, competent, skilled
competent practitioner would have of the deficiencies and qualified persons to design, draw, sign and
in his knowledge and the limitations of his skill. He submit architectural and engineering drawings
should be alert to the hazards and the risk inherent and plans for the construction of Highland Towers
in any professional task he undertakes to the extent and the hill slope behind it;
that other ordinarily competent members of the
profession would be alert. He must bring to any (ii) Not vetting through their appointments to ensure
professional task he undertakes no less expertise, skill, that they are competent and possess such skill
and care than other ordinarily competent members of for the task they are employed to undertake which
his profession would bring, but need bring no more. involves enquiries and investigations into their
The standard is that of the reasonable average. The credentials and qualifications;
law does not require of a professional man that he be
a paragon combining the qualities of polymath and (iii) Constructing insufficient and inadequate
prophet.’ retaining walls on the Arab-Malaysian land and
the Highland Towers site without considering the
Although the drainage plan was approved by the surrounding terrain, soil condition and drainage
authorities, it was not fully implemented by the 1st requirement;
Defendant. The reasons offered by the 3rd Defendant for
this failure were: (iv) Constructing drains that were insufficient to effect
proper and adequate drainage of water run-offs
(i) shortage of financial resources of the 1 st on the slope and those originating from the East
Defendant; Stream;

(ii) the need to bring down the road level to fit the (v) Diversion of the East Stream from its natural path
drains; and to the pipe culvert which ran horizontally across
the hill slope directly above the three blocks;
(iii) prohibition on rock blasting in the area
(vi) Obtaining CF to occupy the three blocks when
Nevertheless, the court ruled that whatever the excuse the drainage system in the Highland Towers site
may be, it did not entitle and warrant the 3rd Defendant to and the Arab-Malaysian land was incomplete.
issue a notice to the authorities stating that the entire
approved drainage proposal was implemented when only The court relied upon the dictum of Lord Finlay LC in
10% was completed. This was a gross violation of his Greenock Corp. v. Caledonian Rly Co. (1917)AC 556 which
duty of care which, as a consultant engineer for the three is quoted by Abdul Hamid FJ in the Federal Court case of
blocks, he owes to the Plaintiffs as purchasers of Highland Seong Fatt Sawmills Sdn. Bhd. v. Dunlop Malaysia
Towers, particularly when this approved drainage system Industries Sdn. Bhd. (1984) 1 MLJ 286 @ p 291.
was so fundamental to the safety of the building. The
judge issued a powerful condemnation by saying as ‘It is the duty of anyone who interferes with the course
follows: of the stream to see that the works which he substitutes
for the channel provided by nature are adequate to
‘I have reiterated my strong sentiments against this carry off the water brought down even by extraordinary
type of attitude of professionals whose only rainfall, and if damage results from the deficiency of
consideration is to guard and secure their own interest the substitute which he has provided for the natural
rather than their duties and obligations to those closely channel, he will be liable.’
affected and the public on which so much faith and
reliance are placed on them to carry out their The court exonerated the 1st Defendant from the
professional duties. I need not elaborate further except allegation that they were responsible for the negligence

BULETIN INGENIEUR 24
cover feature
of their consultants after appointment. The court held and not just confined only to the structure, and after the
that the 1st Defendant would only be liable if the works Highland Towers was erected, to ascertain drainage
involved were ‘of an extra hazardous nature’ which was requirement in the area was adequate to ensure slope
not the case here. stability behind Block 1. Subsequent to the collapse of
The court held that the 1st Defendant were liable in Block 1, measures should have been taken to prevent
negligence and nuisance. recurrence of the tragedy to Blocks 2 and 3.
The court found that MPAJ owed a duty of care to the
LIABILITY OF THE 4TH DEFENDANT – Plaintiffs and that this duty had been breached resulting
MAJLIS PERBANDARAN AMPANG JAYA (MPAJ) in damages.
Upon establishing that MPAJ was negligent, the High
The High Court held MPAJ liable in respect of the Court was influenced by Sec.95(2) of the SDB Act 1974,
following : which provided an immunity to the Plaintiffs’ claims and
the passage in Dr. Abdul Hamid Abdul Rashid & Anor v.
(i) At the planning and design stage of Highland Jurusan Malaysia Consultant & Ors (1997) 3 MLJ 546:
Towers, MPAJ had not taken reasonable care, skill
and diligence in checking the plans submitted to ‘If there is any fear that this approach may encumber
ascertain whether they are reasonably fit for the the local authorities to pay out substantial claims
purpose it was intended for. This included matters due to their negligence in granting approvals or
relating to water courses, streams and rivers in inspecting building works, there is s 95 of the Street,
the vicinity of the Highland Towers site, Arab Drainage & Building Act 1974 (Act 133) which
Malaysian land and the surroundings which were prohibits such authorities to be sued.’
under the jurisdiction of MPAJ.
In discussing the above Sec. 95(2), the High Court
(ii) At the construction stage of the Highland Towers, pointed that Parliament can create an exemption from
MPAJ failed to exercise reasonable care, skill and liability for certain acts committed by local authorities
diligence to ensure the drainage system and the and its officers. James Foong J said:
rubble walls on Arab Malaysian land were
adequately provided for and/or constructed in a ‘It is my view that s 95(2) of the 1974 Act is just
workman-like manner before the issuance of the such a piece of legislation to exempt the local authority
Certificate of Fitness to the three apartment and its officer from negligent act related to and
blocks; connected with certain specified activities. In our
case, since the acts of the 4th Defendant found to be
(iii) MPAJ failed to maintain and upgrade drains and negligent by this court are within those specified
rubble walls on Highland Towers site and Arab activities under s 95(2) of the 1974 Act, immunity
Malaysian land, and to provide adequate drainage applies to the 4th Defendant.
requirement to water courses, streams and rivers
after the Highland Towers was constructed; Further, the High Court explained that Sec. 95(2) covers
situations:
(iv) MPAJ failed to take remedial measures to remove,
rectify and/or minimise the hazards posed on the (i) ‘whatsoever arising out of building or other works
Arab-Malaysian land and the surroundings after carried out’ by the 4th Defendant in accordance
the collapse of Block 1; with the provision of the said Act.

(v) MPAJ failed to prevent vandalism and theft at (ii) ‘or by reason of the fact that such building works
Blocks 2 and 3 in the aftermath of the collapse or the plans thereof are subject to inspection and
of Block 1; approval’.

(vi) MPAJ failed to maintain the East Stream which The acts of negligence of which MPAJ was accused of
was under its jurisdiction; inter alia, approval of plans, inspection and issue of CF
were all covered by this immunity. Thus Sec. 95(2) applies
According to the court, MPAJ owes a duty of care to to acts/omissions committed by MPAJ pre-collapse.
the Plaintiffs to use reasonable care, skill and diligence to However, the immunity could not cover the post- collapse
ensure that the hill slope and the drainage thereon were actions of MPAJ and for these, they were liable.
properly accommodated before approving building or MPAJ had undertaken to prepare a master drainage
other related plans, and during construction stage, to plan to ensure the safety of Blocks 2 and 3. After a period
comply with and to ensure the implementation of the of one year, there was no sight or news of such a plan.
drainage system. Then, when Certificate of Fitness was MPAJ offered no explanation as to why its promise was
applied for, there should be proper and thorough inspection not met. Thus, MPAJ was held liable for post-collapse
on whether the buildings so built were safe in all aspects management of the situation which included failure to

BULETIN INGENIEUR 25
cover feature
prevent vandalism and theft in Blocks 2 and 3 as well as matters that must be addressed. These are the pre-collapse
failure to produce the master drainage plan. MPAJ was and post-collapse liability.
also liable in nuisance by reason of its failure to maintain The Court of Appeal observed that assuming that there
properly a stream which formed part of the drainage was a duty on the 4th Defendant (MPAJ) to act in a
system of the area. particular manner towards the property of the Plaintiffs
post-collapse, such duty must find its expression in public
JUDGMENT OF THE COURT OF APPEAL and not private law. Accordingly, if there had been a
failure on the part of MPAJ to do or not to do something
The 1st, 2nd, 6th, 9th and 10th Defendants did not appeal as a public authority, the proper method is to proceed by
against the decision of the High Court. The 3rd, 4th, 5th, 7th way of application for judicial review. Thus the High
and 8th Defendants appealed against that decision. Court’s finding that MPAJ was liable for negligence after
MPAJ filed an appeal to the Court of Appeal against the collapse was set aside.
the whole decision of the High Court except that part Next, the Court of Appeal looked at the pre-collapse
which decided that MPAJ was not liable for all pre- position. The Plaintiffs submitted that Sec. 95(2) did not
collapse acts by virtue of Sec. 95 of the SDB. apply to the facts as MPAJ had directed the East Stream
Although the High Court excluded liability for pre- to be diverted from its natural course. The carrying out
collapse acts on the part of MPAJ on the basis of Sec. of these works created a danger to the Plaintiff’s property.
95(2) of the SDB, MPAJ had raised the grounds of appeal Accordingly, this is not a case of inspection or approval
in the Court of Appeal that independently of Sec. 95(2) of of building or other works or the plans thereof. This is a
the SDB, MPAJ had not been negligent at all because : case where a danger was expressly created by MPAJ. The
Court of Appeal agreed with this submission and set aside
(i) at the planning and design stage, MPAJ had relied the indemnity granted to MPAJ by the High Court for
on the skill and diligence of the Architect (2nd negligence before the collapse.
Defendant) who submitted those plans as well as The Court of Appeal ruled that there is no proposition
the various Government agencies which vetted of law that a local authority such as MPAJ may never
those plans. owe a common duty of care to the third party. It all
depends on the particular circumstances. The kind of
(ii) at the construction stage of the Highland Towers, harm that was foreseeable by the 5th Defendant was equally
MPAJ had relied on the skill and diligence of the foreseeable by the MPAJ. Upon the evidence and the
1st, 2nd and 3rd Defendants to supervise the said relevant principles, it was clear that MPAJ, as a reasonable
construction and had relied on the Certificates local authority must have foreseen the danger created by
of the Architect (2nd Defendant) that all the works diverting the East Stream would probably be a landslide
had been completed in compliance with the of the kind that happened and that in such event resultant
approved plans. harm, including financial loss of the kind suffered by the
Plaintiffs would occur.
(iii) the Highland Towers and the surrounding areas, The Court of Appeal dismissed the appeals of the 3rd,
after completion and after Certificate of Fitness 5 , 7th and 8th Defendants and affirmed the apportionment
th

had been issued, had been maintained by the 1st of liability made by the High Court amongst the
Defendant. Defendants.
The judgment of the Court of Appeal has since been
(iv) the drains in Highland Towers and the Arab reported as Arab- Malaysian Finance Bhd. v Steven Phoa
Malaysian land were never in the control of Cheng Loon & Ors (2003) 1 MLJ 567. It appears that the
MPAJ. Court of Appeal has departed from the clear finding of
fact by the High Court that it was the 1st Defendant who
(v) the East-Stream was diverted from its natural diverted the East-Stream and substituted their own finding
course by the 1st Defendant as found by the High that it was MPAJ who diverted the East-Stream.
Court. Furthermore, although the High Court made a very clear
finding of fact that it was the 1st Defendant who diverted
(vi) the drainage of the Highland Towers and the the East-Stream, the Court of Appeal declared that it was
Arab-Malaysian land was functioning effectively MPAJ that diverted the East-Stream. The Court of Appeal
until the 5th Defendant took over the Arab- held that MPAJ owed a common law duty of care to the
Malaysian land. Plaintiffs to avoid pure economic loss. It also held that
MPAJ is a Joint Tortfeasor along with the other Defendants.
(vii) at no time did the Plaintiffs complained to MPAJ It was argued that at all material times, MPAJ did not
of the dangers of the state of the drains in the have qualified people to deal with planning application.
Highland Towers and the Arab-Malaysian land. The role of MPAJ was that of an intermediary by
forwarding that application to the respective departments,
In considering the appeal of MPAJ against liability, district technical departments e.g. JKR, Health, State
the Court of Appeal ruled that there are two separate Planning Departments and other authorities relating to

BULETIN INGENIEUR 26
cover feature
that particular application. There was clear evidence also argued that local authorities enjoyed blanket
that MPAJ had relied upon the skill of the Architect (2nd immunity in law in respect of anything done in the exercise
Defendant), the Engineer (the 3rd Defendant) and the of the planning functions. Thus it can be said, that the
Developer (1st Defendant) as well as the checking of the Court of Appeal had erred in relying on Kane as a basis
accuracy of the said plans by the relevant departments for depriving MPAJ the indemnity afforded by Sec.95(2)
(the 9th and 10th Defendants). The High Court held that of the SDB.
Sec. 95(2) SDB protected MPAJ for all acts of MPAJ pre-
collapse, including the checking of the accuracy of the CONCLUSION
plans submitted and the failure to detect any danger in
the said plans. The judgments of the High Court and the Court of
However, the Court of Appeal held that Sec. 95(2) SDB Appeal cannot be lightly regarded. They discuss the causes
does not apply to the facts of the present case since MPAJ of the collapse of Block 1 which may arise from a variety
had directed that the East-Stream be diverted from its of circumstances. Every architect, engineer and developer
natural course and that such an act of MPAJ was caught must never allow an unsafe condition to persist or develop
by the doctrine of Kane v New Forest District Council at the construction site. They should also ensure at all
(2001) 2 All ER 914. In Kane, the local authority times that there is no threat to public health and welfare
specifically required the footpath to be created. In the and remember two assets which are vital to the practice
present case, it was the 3rd Defendant on behalf of the 1st of their profession – their integrity and their ability.
Defendant who submitted the plans relating to the drains On February 6th, 2004, the Federal Court has granted
to be implemented on the 5th Defendant’s land. In Kane, MPAJ leave to appeal to the Federal Court on four main
all the parties including the local authorities were aware issues inter alia whether Sec. 95(2) of the SDB is wide
that the construction of the footpath would be dangerous. enough to provide immunity to a local authority in
Despite the said knowledge of danger, the local authority approving the diversion of a stream and in failing to detect
went ahead with the construction of the footpath. any danger or defect in the building and drainage plans
However, in the present case, the drainage plan was relating to the development submitted by the architect
conveyed by MPAJ to JPS. JPS recommended approval and/or engineer on behalf of a developer.
of the drainage plan. Thus the issue of danger in the Local authorities will welcome the decision of the
present case did not arise at all. Federal Court as it would put to rest the debate as to
Furthermore, in Kane there was no equivalent statutory whether Sec.95(2) of the SDB provides absolute immunity
provision such as Sect. 95(2) of the SDB. In Kane, it was or qualified immunity.

SUMMARY

The decisions of the High Court and the Court of Appeal confirmed that architects and engineers have a duty
to secure the safety, health and welfare of the public in the performance of their professional services.
The architects and engineers owe a duty to exercise the skill, care and diligence which may reasonably be
expected of a person of ordinary competence, measured by the professional standard of the time. Thus an
architect’s and engineer’s general inexperience and lack of knowledge do not furnish a valid excuse for unprofessional
conduct.
The architects and engineers are to be judged by the professional standards prevailing at the time the work
was done, not by what may be known or accepted at a later date, or what may be seen only with the benefit of
hindsight.
The courts emphasised that every architect and engineer owe a duty to third parties to ensure that they are
sufficiently qualified to undertake the assignments for which they accept professional responsibility. The architects
and engineers must also know when to seek a competent specialist in areas outside their expertise.
In this case, the Court of Appeal was unable to see how MPAJ could possibly escape liability for requiring the
diversion of the East Stream. This infers that a local authority should not direct or do anything to make the site
dangerous; otherwise it will be liable.
Although the courts did not discuss in the ground of the Judgment the certification given by the architects and
engineers on the plans submitted by them to exonerate MPAJ, these professionals’ duty must always be reflected
on the plans, by requiring the architects and engineers to certify that they are responsible for supervising the
construction of the project to ensure that it is built in accordance with the approved plans, specifications and
drawings.
The local authorities should be entitled to rely on the certificate executed by the architects and engineers and
to hold them responsible for the structural design, safety and supervision of the project. This would enable the
architects and engineers to retain control over the design and erection procedures so as to be able to advise the
contractor of any special construction or safety consideration. BEM

BULETIN INGENIEUR 27
guidelines

Route To Be
An Accredited Checker
By Accredited Checker Committee, Board of Engineers Malaysia

INTRODUCTION

The guidelines herein are to assist Professional Engineers seeking registration as Accredited Checkers in
geotechnical and/or structural engineering works. They are in furtherance of Section 10B of the
Registration of Accredited Checker, Registration of Engineers (Amendment) Act 2002 [Act A1158].

QUALIFICATIONS FOR REGISTRATION AS AN ACCREDITED CHECKER

Any person applying for registration as an Accredited Checker shall:


i) be a Professional Engineer registered under the Act in the civil, structural or geotechnical engineering
discipline;
ii) have at least 10 years’ relevant practical experience in the design or construction of buildings;
iii) have adequate experience in one of the following:
a) Geotechnical
1) Foundations;
2) Retaining Systems and Reinforced Soil Structures; and
3) Slope Engineering and Embankments
b) Structural
1) Buildings exceeding five storeys;
2) Buildings of unconventional construction with spans exceeding 10 metres; and
3) Buildings that will result in complex interactions with existing buildings

iv) by virtue of his/her ability and standing in the profession, or specialised knowledge or practical
experience in civil, structural or geotechnical engineering he/she is deserving of such registration,
provided that
a) during the period of seven years immediately preceding the date of his/her application, he/she has
been engaged in geotechnical or structural design after registration as a Professional Engineer; and
b) for a continuous period of one year immediately preceding the date of his/her application,
he/she has gained such practical experience in the relevant field in Malaysia; and

v) have attended and passed the interview conducted by the Accredited Checkers Committee.

APPLICATION FOR REGISTRATION

Applications shall:
i) be made in Form B3;
ii) be accompanied by true copies of documentary evidence showing that the applicant possesses the
necessary qualifications and the practical experience;
iii) be accompanied by three copies of relevant design report done by him/her; and
iv) be accompanied by a processing fee of RM50 per application in money order/bank draft/cheque
made payable to the Board of Engineers Malaysia

REGISTRATION

a) Registration Fee

A registration fee of RM300 will be charged for those who have attended and passed the interview.

B U L E T I N I N G E N I E U R 28
guidelines
b) Renewal Fee

Every Accredited Checker desirous of renewing his/her registration under the Act shall:
i) submit to the Board an application for renewal in Form H on or before January 31st of the year
following the year of the expiration of his/her registration;
ii) submit the payment in money order, bank draft or cheque made payable to the Board of Engineers
Malaysia; and
iii) have paid up his/her annual renewal fee as Professional Engineer.

The annual renewal fee is:

Category A: Those below 60 years old RM200


Category B: Those 60 years and above RM100

REMOVAL FROM THE REGISTER

Section 16 of the Registration of Engineers (Amendment) Act 2002 [Act A1158] provides for the removal
from the Register, the name and other particulars of:

a) any registered Engineer who has died;


b) any registered Engineer , other than a Graduate Engineer, or Engineering consultancy practice who
has failed to renew his or its registration within one month of the expiry of the registration;
c) any registered Engineer whose registration has been cancelled under paragraph 15(1A)(d); or
d) any registered Engineer whose registration has been effected by reason of any mistake or error made
by the Board in considering his application for registration.

APPEALS

All appeals shall be submitted to the Appeal Board, Board of Engineers Malaysia (constituted under
Section 20, Registration of Engineers (Amendment) Act 2002 [Act A1158]).

FLOWCHART OF THE ROUTE TO BE


AN ACCREDITED CHECKER

Be a registered Professional Engineer under the Registration of Engineers Act 1967 in


the civil, structural or geotechnical engineering discipline.

HAS
● Minimum 10 years’ relevant practical experience in the design or construction of
buildings.
● Minimum seven years’ experience in geotechnical or structural design after
registration as Professional Engineer
● Minimum one year experience in the relevant field gained in Malaysia.

Attended the Interview conducted by Accredited Checkers Committee

AND PASSED

Accredited Checker
BEM

B U L E T I N I N G E N I E U R 29
Update

Asian And Pacific Decade Of Disabled Persons 2003-2012

Biwako Millennium
Framework For Action
Submitted by Ooi Kah Hooi

I
n May 2002, ESCAP adopted the resolution
“Promoting an inclusive, barrier-free and rights-
based society for people with disabilities in the Asian
and Pacific regions in the 21 st century”. The
resolution also proclaimed the extension of the Asian and
Pacific Decade of Disabled Persons 1993-2002, for another
decade, 2003-2012. (6) Access to information and communications, including
In October 2002, Governments at the High-level information, communication and assertive
Intergovernmental Meeting to Conclude the Asian and technologies.
Pacific Decade of Disabled Persons 1993-2002, adopted
the “Biwako Millennium Framework for Action towards (7) Poverty alleviation through social security and
an Inclusive, Barrier-free and Rights-based Society for livelihood programmes.
Persons with Disabilities in Asia and the Pacific” as the
regional policy guideline for the new decade. (8) Highlights of item (5) : Access to built environment
The “Biwako Millennium Framework” outlines issues, and public transport.
action plans and strategies towards an inclusive, barrier-
free and rights-based society for persons with disabilities. Inaccessibility to the built environment, including
To achieve the goal, the framework identifies seven public transport systems, is still the major barrier for
priority areas for action, in which critical issues, targets persons with disabilities. This problem will only be
with specific timeframe and actions are specified. In all, exacerbated, as the number of older people with
21 targets and 17 strategies supporting the achievement disabilities increases in the region. Universal design
of all the targets are identified. approaches benefit all people in society, including
The new decade (2003-2012) will ensure the paradigm older persons, pregnant women and parents with
shift from a charity-based approach to a rights-based young children. Its economic benefits have been
approach to protect the civil, cultural, economic, political legitimised, yet substantive initiatives at policy level
and social rights of persons with disabilities. have not been taken. Three targets are set to improve
To pursue the targets and strategies, consultations with the situation:
and involvement of civil societies, inter alia, self-help
organisations and concerned NGOs are essential. ● The Government should adopt and enforce
The following summarises the seven priority areas accessibility standards for planning of public
for action, the targets, strategies, timeframe and facilities, infrastructure and transport, including
supporting/monitoring mechanisms. those in rural/ agricultural contexts.

(1) Self-help organisations of persons with disabilities ● Existing public transport systems and all new and
and related family and parent associations. renovated public transport systems should be
made accessible as soon as practicable.
(2) Women with disabilities.
● All international and regional funding agencies
(3) Early detection, early intervention and education. for infrastructure development should include
universal and inclusive design concepts in their
(4) Training and employment, including self- loan/grant award criteria.
employment.
For further information, please refer to www.unescap.org/
(5) Access to built environment and public transport. sps/disability.htm BEM

B U L E T I N I N G E N I E U R 30
engineering & law
Work Programme -
A Contractual Perspective
Part 1
By Ir. Harbans Singh K.S., B.E (Mech) S’pore, P.E., C.Eng,
LLB(Hons) London, CLP, DipICArb.

I
n all the frequently encountered methods of contract EXPRESS CONTRACT PROVISIONS
procurement employed locally in the engineering and
construction industry, the contractor is responsible Express contract provisions governing various aspects
for both the method and the sequencing of working. of the contractor’s obligations pertaining to the ‘Work
To enable these goals to be achieved, the contractor must Programme’ are included in a number of local forms of
programme the works accordingly; hence the generation conditions of contract, namely:
of a document labelled ‘Work Programme’, ‘Programme
of Works’ or simply ‘Programme’. Its importance for the ● Sub-clauses 3.4 to 3.6: PAM ’98 Form (‘With Quantities’
proper management of the construction process cannot and ‘Without Quantities’) Editions;
be denied. In parallel, its use as a tool for the efficient
administration of the contract by the employer also cannot ● Clause 5 4: CIDB Standard Form of Contract For
be underestimated. Therefore, it is not surprising that its Building Works (2000 Edition); and
preparation and submission has grown from a mere
administrative step to a serious contractual obligation on ● Clause 7 5: IEM Conditions of Contract For Mechanical
the part of the contractor in contemporary practice; breach and Electrical Works (IEM.ME 1/94 Form)
of which obligation has assumed consequences of a very
grave nature 1. The other common forms e.g. JKR 203 and 203A,
IEM.CE 1/89, etc. have no such express stipulations.
In view of its immense importance in every such However, in contracts employing such forms, the
endeavour, this paper has been penned with an aim of requirements pertaining to the ‘Work Programme’ are
exposing practitioners to the pertinent contractual as well normally included in the ‘Preliminaries’ Section of the
as the attendant procedural requirements vis-à-vis the Bills of Quantities, etc.; a practice which is being replaced
topic of work programme. Though constrained by the by the use of express contract provisions. 6
length of the article permitted by the publisher, the author
nevertheless will attempt to address the main areas of FORM
concern so as to adequately cover the topic in hand.
There are no hard and fast rules governing the form
DEFINITION AND MEANING the work programme must be in. The eventual form to be
adopted for such a programme is usually dictated by three
In an ‘An Engineering Contract Dictionary’ 2, the term main factors, such as:
‘programme’ has been defined as:
● The size and complexity of the works under the
‘A schedule or chart showing stages in a scheme of contract;
work. Reference in Conditions of Contract to programme
inevitably means the contractor’s programme being his
sequence for execution of the works ….’
1. As reflected in the various express contractual provisions.
Sundra Rajoo 3 sums up the meaning of the term ‘Work 2. By Vincent Powell-Smith at P 500.
Programme’ as: 3. In ‘The Malaysian Standard Form of Building Contract’ [2nd
Edn.] at P 81.
4. Entitled ‘Work Programme and Method Statement’.
‘A graphic representation of the detailed sequence of 5. Termed ‘Programme’.
work activities and mobilisation of resources towards that 6. See also Glenlion Construction Ltd. v The Guinness Trust
sequence of activities. It represents the contractor’s plan (1987) 39 BLR 89 for the effect of such ‘non-contractual’
of proceeding for the work …..’ provisions.

B U L E T I N I N G E N I E U R 31
engineering & law
● The extent to which the details e.g. the activities, ● Clause 7.1: IEM.ME 1/94 Form 8 stipulates:
sequence of activities, etc. are to be shown; and
‘The contractor shall submit to the Engineer for his
● Any express stipulations in the contract pertaining approval the Programme which shall include the following:
to the form to be adopted.
(a) the sequence and timing in which the contractor
In practice, the common forms of such programmes proposes to carry out the works (including the
that are encountered include: design, manufacture, delivery to site, erection,
testing and commissioning)
● Simple Bar charts;
(b) the times when submission and approval of the
● Gannt charts; contractor’s drawings are required

● Critical Path Analysis (CPA); 7 (c) the times by which the contractor requires the
Employer:
● Project Evaluation Review Techniques (PERT);
(i) to furnish any drawings or information;
● Project Network charts;
(ii) to provide access to site;
● Project Activity Flow charts;
(iii) to have completed any necessary civil
engineering or building work (including
● Multi-Level Project Scheduling (MLPS);
foundations for the plant), to be provided by
the Employer; and
● Work Breakdown Structure (WBS);
(iv) to have obtained any way leaves, consents and
● Programmes involving particular software e.g.
approvals necessary for the construction of the
‘Primivera’, ‘Microsoft Project’, etc. works, for which the Employer is responsible’

Depending upon the particular project involved in a Reviewing the said provisions, the following summary
specific case, a typical application may necessitate a can be drawn:
number of the above forms for both overall and detailed
programming. ● If possible, the preferable content of the required work
programme should be expressly stipulated; a classic
CONTENT example being clause 7.1 IEM.ME 1/94 Form;

As for the form, there are currently no guidelines ● Notwithstanding the existence of any express provision,
available locally spelling out the expected contents of the contractor is obliged to prepare and submit as
the work programme. Much is left to the contractor to detailed a programme as possible to meet the broad
decide based on his experience, bearing in mind the purposes of the document i.e. to identify the activities,
purpose of the programme in the context of the particular sequence of activities and the critical milestones vis-
circumstances of the contract works being undertaken. à-vis the works under the contract. A master
Where the conditions of contract expressly stipulate the programme should be prepared for the overall works
specific contents required, these should be adhered to. and separate individual programmes for each section,
Examples of such express provisions include the phase, block or system, as appropriate;
following:
● Each programme should detail out the following as a
● Clause 5.1(a): CIDB 2000 Edition Form which reads: minimum:

‘…. the contractor shall, not later than Date of (a) The principal activities;
Commencement submit for the approval of the
Superintending officer: (b) The sequence of such activities;

(a) a works programme related to the Time for (c) The timing of such activities;
Completion, clearly identifying the sequence, logic
and critical path in which he proposes to carry out
7. Also called the ‘Critical Path Method’ (CPM)
the works, including the various work activities and 8. I.E.M. Conditions of Contract For Mechanical and
milestones to be achieved ….’ Electrical Works.

BULETIN INGENIEUR 32
engineering & law
(d) The identification of the critical activities 9 and the management) is to set down the timing of the contractor’s
critical path; requirements for site access, information, drawings and
nominations, for the guidance of the contract
(e) Important milestones vis-à-vis submittals by the administrator, and it is for the reasonableness of these
contractor necessary to achieve completion by the requirements, in relation to the date for completion that
date of completion e.g. the contract administrator checks and approves the
programme submitted ….’
i) Times of submission of shop/fabrication
drawings, etc. In ‘Hudson’s Building and Engineering Contracts’ 13,
ii) Times of submission of method statements such purposes have been lucidly explained to the following
iii) Times of submission of samples, etc.; and effect:

(f) Important milestones for the employer/contract ‘The purpose of contractual requirements for a
administrator to meet to enable the contractor to programme to be supplied by the contractor is often
achieve completion by the date of completion misunderstood, and is primarily to enable its owner or
stipulated in the contract e.g. his Architect/Engineer to plan their own arrangements
for giving possession, supplying information and working
i) Times by which the various submittals e.g. drawings, and coordinating the work of other contractors
drawings, samples, etc. need to be approved; or nominated sub-contractors, and only secondarily for
use in connection with the contractor’s extension of time
ii) Times by which works under P.C. Sums 10 need applications or monetary claims, or to impose additional
to be awarded; time obligations on it’.

iii) Times by which possession and/or access to Hence, analysing the above explanations, the following
the whole and/or various sections of the site principal purposes can be identified:
need to be given to the contractor;
● As for the contractor, the main purposes in preparing
iv) Times by which the employer needs to furnish the work programme are:
the contractor with necessary approvals 11,
further details and/or information under the (a) For his own construction management purposes;
contract;
(b) To meet his obligations under the contract
v) Times by which the employer needs to obtain pertaining to the submission of such document; 14
and provide the contractor with any necessary
easements, way leaves, etc. in connection with (c) To monitor his work progress under the contract; 15
the works; and
(d) To plan his cash flow;
vi) Miscellaneous milestones to be satisfied by the
employer so as not to hinder the contractor in (e) To justify any application for an extension of time
carrying out and/or completing the works. to the contract due to disruption of his progress;
and
● In approaching this subject, one should be mindful of
the fact that the actual content of a particular work (f) To use as a basis of claiming any monetary
programme is also influenced by the method of contract compensation e.g. loss and/or expense due to
procurement adopted. Hence, it is therefore inevitable disruption of his progress, etc.
that the content of a ‘Package Deal’ type of work
programme will materially differ from that under the
traditional contracting route.
9. Inclusive of the relevant ‘float’ time.
PURPOSE OF SUBMISSION 10. I.e. involving Nominated Sub-contractors.
11. Including consents, decisions, etc.
The purposes of submission of the work programme 12. See ‘Construction Law in Singapore and Malaysia’ [2nd Edn.]
are explained in various manners by different at P 298.
authorities/practitioners. Robinson and Lavers 12 have 13. [11th Edn. 1995] by Prof. Wallace at P 1129 as reproduced
in ‘The Malaysian Standard Form of Building Contract’ [2nd
aptly summed up these purposes in the following words:
Edn.] by Sundra Rajoo at P 81.
14. Especially if there are express stipulations to this effect e.g.
‘The primary use and importance of work programme clause 5.1 CIDB Form, etc.
(other than in the contractor’s own construction 15. And for the progress of his sub-contractors, suppliers, etc.

BULETIN INGENIEUR 33
engineering & law
● On the employer’s side, the primary purposes for the (h) To assist in the preparation of the facilities
submission of the work programme are to enable the management plan; and
employer/contract administrator to plan their own
arrangements for: (i) Such other purposes necessary and incidental to
the completion of works, taking over and eventual
(a) Giving necessary site possession and/or access to use and operation by the employer.
the contractor to enable him to commence and
proceed with the works under the contract; ● Just as for the content, the purposes of the work
programme are influenced by the method of contract
(b) Preparing and supplying information, working procurement adopted in a particular case. As an
example, the main purposes of a work programme are
drawings details, etc. necessary for the contractor
of a lesser importance in contracts undertaken along
to proceed with the works;
the ‘package deal’ route 17 because unlike traditional
general contracts, the contract administrator for a
(c) Giving necessary approvals, consents and decisions
‘package deal’ type of contract is not obliged to supply
in time to enable works to proceed as planned;
details, information, etc. nor undertake the necessary
coordination. Hence, one should be mindful of such
(d) Obtaining relevant easements, way leaves, etc. in matters in dealing with the instant subject.
connection with the works for the purposes of the
contract; and TIME FOR SUBMISSION

(e) Appointing Nominated Sub-Contractors, third party Unless otherwise stipulated, the contractor is obliged
contractors, etc. in time so as not to disrupt the to submit the work programme within a reasonable period
contractor’s progress. after the award of the contract; at the latest being the
date of the site possession meeting. Much as it is desired
● In addition to the above primary purposes, the contract to solicit such a programme as early as possible, the
administrator requires the work programme for use in prevailing local practice reflects the general lackadaisical
connection with such collateral purposes as: attitude of most contractors to this matter, whereby one
is not likely to sight a proper programme being produced
(a) To aid the cost planner in gauging the contractor’s and submitted until well after site possession has been
cash profile for the project and preparing cash given.
projections to ensure that the employer’s obligations In instances where express provisions have been
under the contract as to payment are met; included in the conditions of contract governing the issue
of work programme, they generally stipulate the time
(b) To use as a basis of monitoring the contractor’s frame for the submission of such documents. Examples
progress; include:

● Sub-clause 3.4 of the PAM ’98 Form (‘With Quantities’


(c) In deciding whether there is a basis of determining
and ‘Without Quantities’) Editions states:
the contractor’s employment on the ground, where
provided for, that the contractor has defaulted in
‘Within fourteen (14) days upon the issue of the letter
not proceeding ‘regularly and diligently with the
of acceptance, the contractor without charge to the
works’; 16
Employer, shall provide the Architect with two copies
of the work programme for the execution of the works’
(d) To evaluate the contractor’s application for
extension of time due to disruption of progress of ● CIDB Form (2000) Edition in Sub-clause 5.1 stipulates:
works;
‘Following the Letter of Award, and without prejudice
(e) To evaluate the contractor’s application for to any requirement to do so earlier in his tender or the
monetary claims in connection with disruption of other contract documents, the contractor shall, not later
progress e.g. claims for extended preliminaries, loss than the Date of Commencement, submit for the
and/or expense, etc.; approval by the Superintending Officer

(f) For general contract administration and (a) a works programme ………’
coordination of the works of all contractors, sub-
contractors and third parties on site;
16. See Clause 25.1(ii) PAM ’98 Form ‘With Quantities’ Edition
for example.
(g) To aid in the preparation of the employer’s handing 17. See ‘The ICE Design and Construct Contract: A
over and migration plan; Commentary’ by B. Eggleston at P 125.

BULETIN INGENIEUR 34
engineering & law
Hence, it can be noted that the usual time frames STATUS OF THE PROGRAMME
expressly stipulated in such forms fix the time for
submission according to the formulae as set out here Notwithstanding attempts being made to include
below: express provisions circumscribing various facets of the
contractor’s work programme, this document remains
● Following the letter of award 18 i.e. within a reasonable primarily a tool for the contractor to plan his method and
period of its issue; sequencing of his works under the contract. This is echoed
in the following extract from ‘Engineering Law and the
● Within a definite period of the issue of the letter of ICE Contracts’: 22
award e.g. fourteen (14) days in the PAM ’98 Form,
etc.; ‘The programme, for example, is not contractual in
the same sense as the specification, since neither the
● Not later than the date of commencement of the works contractor nor the employer is bound by it. The
under the contract e.g. Clause 51 CIDB Form, etc.; programme is what it is – a document indicating the
intention of the contractor at the time he furnishes it as
● Within any other period stipulated in the contractor’s to how he intends to programme his works’.
tender offer and/or other documents constituting the
contract e.g. Clause 51 CIDB Form, etc. A similar sentiment is reflected by Roger Knowles in
his lucid explanation for the said approach to the following
FAILURE TO SUBMIT PROGRAMME effect:

The consequences of the failure to submit the ‘The programme is usually intended to be a flexible
programme are dictated generally by the formula as set document. If the contractor gets behind, say due to the
out hereunder: insolvency of a sub-contractor, he would normally expect
to revise the programme in an attempt to make up for lost
● Where there are no express contractual provisions vis- time. For this reason, programmes are rarely listed as
à-vis the submissions of the programme, there can contract documents. It is the requirement of most contracts
accordingly be no sanctions and the contractor cannot that obligations provided for in contract documents must
be stopped from commencing with the works under be carried out to the letter. With a programme containing
the contract. However, he may compromise his right some hundred or more activities, compliance for start and
to receive necessary approvals, consents, information, finish date for each without the possibility of revision
etc. in time; would be impractical. For this reason, programmes should
not be contract documents’ 23
● In the event the conditions of contract contain express
provisions on the requirement for the submission of The general legal position vis-à-vis the status of the
the programme, the contractor’s failure to do so would work programme can be summed up as follows:
be a breach of contract on his part. The contractual
remedies available to the employer for such default ● If the programme is called for at the tendering stage
may include: and is accepted by the employer, it becomes
contractually binding: Yorkshire Water Authority v
a) Any remedy expressly spelt out in the conditions Sir Alfred McAlpine and Son (Northern) Ltd. 24
of contract itself e.g. sub-clause 5.5 CIDB Form
(2000 Edition). ● However, if the programme comes into existence after
the contract has been made, it is not a contract
b) Ordering suspension of works i.e. if there is an document 25 unless the parties expressly agree to
express clause pertaining to suspension and refusing otherwise.
the contractor’s costs on the ground that the
programme was ‘necessary for the proper execution
or for the safety of the works’ 19
18. Synonymous with the Letter of Acceptance.
c) Activating the determination procedure on the 19. See ‘The ICE Design and Construct Contract: A Commentary’
ground that the contractor was ‘persistently in by B. Eggleston at P 128.
20. Ibid i.e. if such an express clause is in the contract.
breach of his obligations under the contract’ 20, or
21. E.g. clause 25.1(vi) PAM ’98 Form (‘With Quantities’) Edn.
where the default persists following written 22. (4th Edn. 1991) by M.W. Abrahamson at P 79
instructions from the contract administrator, on the 23. In ‘100 Contractual Problems and Their Solutions’ at P 70
ground that the contractor ‘has persistently refused 24. [1986] 32 BLR 114.
or failed to comply with a written instruction from 25. See ‘The ICE Design and Construct Contract: A
the contract administrator’ 21 Commentary’ by B. Eggleston at P 126.

BULETIN INGENIEUR 35
engineering & law
To dispel any doubts as to the status of the programme, 5. The appointment of nominated sub-
most standard forms of conditions of contract include contractors,26 third party contractors, etc.;
specially drafted clauses to this effect; common examples
being: 6. The undertaking of specific obligations for the
purposes of the contract e.g. delivery of employer
● Sub-clause 3.5: Work Programme Not Part or furnished materials, etc.
Incorporated into Contract Documents - PAM ’98 Form
(‘With Quantities’ and ‘Without Quantities’) Editions. In carrying out such assessments, the contract
administrator must be wary of the effect of the approval
● Sub-Clause 5.2: Work Programme and Method of such programme and the contractual duties being
Statement Not Part of Contract Document - CIDB imposed on the contract administrator/employer thereof.
Standard Form of Contract For Building Works
II. The Response
(2000 Edition)

Following the above-mentioned review, the contract


Where the contract is silent as to the status of such
administrator must respond within a reasonable
document e.g. IEM.ME 1/94 Form, resort must be made to
period 27 of receipt of the work programme by either:
the general legal position as stipulated hereabove.
● Approving/Accepting the programme in writing,
THE APPROVAL PROCESS
or

I. Assessment ● Rejecting/Disapproving the programme in


writing, giving reasons
Upon receipt of the work programme from the
contractor, the contract administrator has to carry ● Withholding approval by requesting for further
out the necessary checks or assessments to ensure information
that the document submitted:
If the contract administrator fails to respond
● Complies with the governing express contract within either the stipulated period or within a
stipulations; reasonable period (i.e. if none is stipulated) from
the date of receipt of the contractor’s submission,
● The form is acceptable; then the work programme is deemed to have been
approved or accepted by the contract
● The contents reflect the contractual requirements administrator 28.
and they are sufficient and complete as to the
identification of the work activities, the sequencing III. Approval
of the work activities, the relevant milestones, etc.;
Synonymous with ‘Acceptance’, approval of the
● The critical activities and the critical path have been work programme invokes the following effects:
identified;
● It signifies the contract administrator’s
● The programming of the works is not ‘optimistic’ ‘agreement with the proposed order or sequence
but realistic; of working in the work programme’ 29
● ‘The approved work programme may be taken
● The target dates/milestones set for the contract into account in any dispute for determining a
administrator/employer as to matters such as listed reasonable order or sequence for supplying any
outstanding information or details to the
hereunder are reasonable:
contractor, or for giving possession of the site
by the employer’ 30
1. The supply of drawings, information, details, etc.

2. The provision of site possession and/or access; 26. Including the ordering of the works under
‘Provisional Sums’.
3. The giving of necessary approvals, consents, 27. Unless expressly stipulated e.g. 14 days per clause 5.3 CIDB
Form (2000 Edn.), etc.
decisions, etc.
28. See Sub-clause 5.3(c) CIDB Form (2000 Edn.) and also Mackay
v Dick (1880-81) 6 App. Case 251.
4. The obtaining of the relevant easements, way 29. See Sub-clause 5.3(a) CIDB Form (2000 Edn.).
leaves, etc. 30. See Sub-clause 5.3(b) CIDB Form (2000 Edn.).

BULETIN INGENIEUR 36
engineering & law
This is normally subject to the express caveat For the sake of clarity and to avoid possible
to the effect that the approval of the programme misconstruction, it may be prudent to include such
by the contract administrator shall not relieve the a provision in the contract so that the parties are
contractor or the employer from any obligation aware from the very beginning as to the likely
under the contract 31 e.g. consequences of such an eventuality.

● In relation to the time for completion; or V. Withholding Approval

● As to a reasonable time for giving or receiving A third option available to the contract
further information; or administrator following an assessment of the work
programme is to withhold approval. This may be
32
● For giving possession of the site, etc. necessitated by factors such as:

As to the mode of communicating the approval, ● Lack of clarity of the contents;


unless it is stipulated expressly to the contrary, the
accepted practice is to have this in writing. ● Lack of sufficiency of information supplied;

IV. Rejection/Disapproval ● Disagreement with the reasonableness of the


milestones set vis-à-vis the employer’s and/or
In the event the contract administrator finds contractor’s obligations; and
the submission unacceptable, he may reject it
together with the reasons for the rejection and may ● Miscellaneous matters having a material impact
require the contractor to: on the programme 34

● make the necessary amendments; and Hence, the contract administrator may withhold
approval and request further information from the
● resubmit the programme for re-consideration. contractor; such information comprising
principally: 35
This approach is reaffirmed in Clause 5.4 of the
CIDB Form (2000 Edn.) which states: ● Further clarification;

‘In the event the works programme…….is ● Substantiation;


disapproved by the Superintending Officer, then the
contractor shall make such further submissions as ● Satisfaction on reasonableness having regard to
may be required until approval is obtained’ the contractor’s obligations; and

It is pertinent to note that neither a time frame ● Miscellaneous matters having a material impact
for resubmission nor the number of resubmissions on the programme.
is stipulated; merely that the contractor must
resubmit until approval is obtained. Such requests for information should be in
writing, and the contractor should be given a
The next question that begs an answer is as to reasonable time to respond. It is important to bear
the effect of the failure to secure approval of the in mind the reasons behind such an exercise; an
programme on the commencement of work. abuse of the process for trivial reasons in an attempt
Although most standard conditions of contracts fail to procrastinate or delay the approval process may
to expressly address this matter, a useful guidance constitute ‘mal-administration’ of the contract with
is afforded by Clause 5.5 33 of the CIDB Form (2000 dire consequences. BEM
Edn.) in the following manner:

‘The Contractor may commence execution of


the works pending approval of the work
31. E.g. Clause 7.3 IEM.ME 1/94 Form.
programme…….by the Superintending Officer. 32. See Sub-clause 5.3(b) CIDB Form (2000 Edn.).
However, the grounds of any approval may be taken 33. Entitled ‘Start of Work Without Approval’.
into account in determining any dispute as to a 34. E.g. issues to do with ‘Float Time’, ‘Optimistic
reasonable sequence or order for giving possession Programme’, etc.
of the site, or for supplying supplementary drawings 35. See ‘The ICE Design and Construct Contract:
A Commentary’ by B. Eggleston at P 129.
or details or information’

BULETIN INGENIEUR 37
feature
Best Management Practices On
Soil Erosion And Sediment Control
In The Construction Industry Part 2
By Tew Kia Hui, Director/Soil Erosion Research Consultant, VT Soil Erosion Research & Consultancy

INCORPORATING BEST scheduling techniques should be Shrubs and trees must be


MANAGEMENT PRACTICES compared with other less effective adequately watered, fertilised, and
FOR EROSION AND erosion and sediment controls to pruned if needed. Grass may need to
SEDIMENT CONTROL achieve a cost-effective balance. be watered and mowed too.
However, permanent and
Specific BMPs should be ■ Preservation of temporary vegetation may not be
incorporated for common Existing Vegetation appropriate in dry periods without
construction activities that result in Carefully planned preservation of irrigation. Fertiliser requirements
erosion of construction sites and the existing vegetation minimises the may have the potential to create
generation of sediment, which impact potential of removing or injuring stormwater pollution if improperly
waterways and off-site properties. existing trees, shrubs, and/or grass applied.
Recommended erosion and that serve as erosion controls.
sediment control measures for Corridors of vegetation act as ■ Mulching
construction sites are summarised in buffer zones to separate disturbed Mulching is a temporary ground
Table 2 in relation to BMP objectives, land from an adjacent watercourse, covering that protects the soil from
and this information is suitable for protected forest, or other sensitive rainfall impacts, increases infiltration,
inclusion in the ESCP. areas. Leaving a clearly marked conserves moisture around trees,
buffer zone around these unique areas shrubs, and seedings, prevents
Site Planning Considerations will help to preserve them, as well as compaction and cracking of soil, and
benefiting from their natural erosion aids the growth of seedings and plants
■ Scheduling prevention and trapping by holding the seeds, fertilisers and
Defined as sequencing the characteristics. topsoil in place until growth occurs.
construction project to reduce the The inspection and maintenance
amount and duration of soil exposed requirements for protection of
to erosion by wind, rain, runoff, and vegetation are low and there is little
vehicle tracking. Proper sequencing cost associated with preserving
of construction activities should be existing vegetation if properly
incorporated into the schedule of planned during the project design.
every construction project. However, Aesthetic benefits may also enhance
use of other more costly yet less property values.
effective erosion and sedimentation
controls may often be reduced Vegetative Stabilisation
through proper construction
sequencing. ■ Seeding and Planting Mulching can be used either to
The approach would be to Seeding of grass and planting of temporarily or permanently stabilise
integrate into existing land contours trees, shrubs and ground covers cleared or freshly seeded areas. Types
as far as practicable, incorporate provide long-term stabilisation of soil. of mulches include organic materials,
existing natural areas, avoid rainy Grass may also be planted for straw, wood chips, bark or other wood
periods, practise erosion and sediment temporary stabilisation. It is fibres, decomposed granite and
control all year round, minimise the appropriate for site stabilisation - both gravel. A variety of mats of organic
extent of soil exposed at any one time during and after construction - in any or inorganic materials and chemical
and also carry out trenching graded or cleared areas where stabilisation may be used with
operations. construction activities have ceased, mulches.
This procedure may increase other open space, cut and fill areas, steep Mulch prevents erosion by
construction costs due to reduced slopes, spoil stockpiles, vegetated protecting the soil surface and
economies of scale in performing site swales, landscape corridors and fostering growth of new seedings that
grading. The cost-effectiveness of stream banks. do not stabilise by themselves.

B U L E T I N I N G E N I E U R 39
feature
Table 2: Erosion and sediment control measures and objectives
BMP OBJECTIVES

Control Internal
Disturbed Area
Disturbed Area
Contain Waste
Standard

Numbers

Project Slopes
Housekeeping
Practise Good
Drawing

and Channels

Control Site
Perimeter
Minimise

Stabilise

Erosion
BMP CATEGORY

Site Planning Considerations


Scheduling √ √ √ √ √ √ √
Preservation of Existing Vegetation √ √ √ √
Vegetative Stabilisation
Seeding and Planting √ √
Mulching √ √
Physical Stabilisation
Geotextiles and Mats √ √
Dust Control √ √ √ √
Temporary Waterway Crossing √ √ √ √
Construction Road Stabilisation √ √ √ √
Construction Access Stabilisation √ √ √ √
Diversion of Runoff
Earth Bank √ √ √ √
Diversion Channel √ √ √
Slope Drain √
Flow Velocity Reduction
Drainage Outlet Protection √
Check Dam √
Sediment Trapping / Filtering
Sediment Fence √ √
Sand Bag Barrier √ √ √
Brush or Rock Filter √ √ √
Drainage Inlet Protection √ √
Sediment Traps √
Sediment Basins √

Organic mulch materials such as absorb and hold moisture near the soil applied in clearing and grading
straw, wood chips, bark and wood surface. Additionally, mattings may activities, construction vehicle traffic
fibre are most effective where re- be used alone or with mulch during on unpaved roads, drilling and
vegetation will be provided by the establishment of protective cover blasting activities, sediment tracking
reseeding. The choice of mulch on critical slopes. onto paved roads, soil and debris
should be based on the size of the Mattings are typically suited for storage stockpiles, batch drop from
area, site slopes, surface conditions permanent site stabilisation, but may front end loaders and areas with
(such as hardness and moisture), weed be used for temporary or permanent unstabilised soil. Final grading/site
growth and availability of mulch stabilisation of highly erosive soils. stabilisation usually is sufficient to
materials. Mattings may be applied to disturbed control post-construction dust
However, the limitation is that soils and where existing vegetation sources.
organic mulches are not permanent has been removed. Installation costs for water/
erosion control measures. Mulches Mattings, on the other hand, are chemical dust suppression are low, but
tend to lower the soil surface more costly than other BMPs, limiting annual costs may be quite high since
temperature, and may delay their use to areas where other BMPs these measures are effective for only
germination of some seeds. are ineffective (e.g. channels, steep a few hours to a few days.
slopes). They may also delay seed The limitations include watering
Physical Stabilisation germination, due to reduction in soil prevents dust only for a short period
temperature. and they should be applied daily (or
■ Geotextiles and Mats more often) to be effective, and over-
Mattings are made of natural or ■ Dust Control watering may cause erosion.
synthetic material, which are used to Dust control measures are used to
temporarily or permanently stabilise stabilise soil from wind erosion and ■ Temporary Waterway Crossing
soil. Mattings reduce erosion from reduce dust generated by construction A temporary access waterway
rainfall impact, hold soil in place, and activities. They are suitable to be crossing is a temporary culvert, ford,

B U L E T I N I N G E N I E U R 40
feature
or bridge placed across a waterway erosion, but significantly speeds on- Earth banks are typically used to
to provide access for construction site work, avoids instances of divert concentrated runoff through
purposes for a period of less than one immobilised equipment and delivery disturbed areas into another BMP (e.g.
year. Temporary access crossings are vehicles, and generally improves site a sediment trap or basin), to divert
not intended to be used by the general efficiency and working conditions runoff away from disturbed or
public. during adverse weather. unstable slopes, to divert runoff from
The roadway however, must be off-site and undisturbed areas around
removed or paved when construction disturbed areas, and as containment
is complete. Certain chemical for construction materials and wastes.
stabilisation methods may cause The on-site banks should remain in
stormwater or soil pollution and place until the disturbed areas are
should not be used. permanently stabilised and must
safely convey anticipated flood flows.
■ Construction Access Banks should not be used for
Stabilisation drainage areas greater than four
A stabilised construction access is hectares, or along slopes greater than
a stabilised pad of aggregate 10%. For larger areas, more
underlain with filter cloth located at permanent drainage structures should
The purpose of a temporary any point where traffic will be be built.
crossing is to provide a safe, erosion- entering or leaving a construction site
free access point across a waterway from or to a public right-of-way, ■ Diversion Channel
for construction equipment. An street, alley, footpath or parking area. Temporary diversion channels
engineer should establish minimum Stabilising the site entrance may be used to divert offsite runoff
standards and specifications for the significantly reduces the amount of around the construction site, divert
design, construction, maintenance sediment (dust and mud) tracked off- runoff from stabilised areas around
and removal of the structure. site, especially if a wash rack is disturbed areas, and direct runoff into
Crossings may be necessary to prevent incorporated for removing caked-on sediment traps or basins. Diversion
construction equipment from causing sediment. channels should be installed when the
erosion of the waterway and tracking Applications include all points of site is initially graded and remain in
of pollutants into the waterway. construction entry and exit from the place until permanent BMPs are
However, the temporary waterway site and unpaved areas where installed and/or slopes are stabilised.
crossings may be an expensive sediment tracking occurs from the site Diversion channels are
measure for a temporary onto paved roads. This access should appropriate for diverting any upslope
improvement and require other BMPs be used in conjunction with street runoff around unstabilised or
to minimise soil disturbance during sweeping on the adjacent public right- disturbed areas of the construction
installation and removal. of-way and it requires periodic top site in order to prevent slope failures,
dressing with additional stones. prevent damage to adjacent property,
■ Construction Road Stabilisation prevent erosion and sediments into
Access roads, subdivision roads, Diversion of Runoff waterways, increase the potential for
parking areas, and other on-site infiltration and divert sediment-laden
vehicle transportation routes should ■ Earth Bank runoff into trapping devices.
be stabilised immediately after A temporary earth bank is a However, they must conform to local
grading, and frequently maintained temporary beam or ridge of floodplain management requirements.
to prevent erosion and control dust. compacted soil used to divert runoff
Areas which are graded for or channel water to a desired location, ■ Slope Drain
construction vehicle transport and thereby reducing the potential for A slope drain is a temporary pipe
parking purposes are especially erosion and off-site sedimentation. or lined channel to drain the top of a
susceptible to erosion and dust. The Earth banks may also be used to divert slope to a stable discharge point at
exposed soil surface is continually runoff from off-site and from the bottom of a slope without causing
disturbed, leaving no opportunity for undisturbed areas away from erosion. It is typically used in
vegetative stabilisation. Such areas disturbed areas, and to divert sheet combination with an earth bank or
also tend to collect and transport flows away from unprotected slopes. diversion channel at the top of the
surface runoff. During wet weather, An earth bank does not in itself slope.
they often become muddy quagmires, control erosion or remove sediment A slope drain is effective because
which generate significant quantities from runoff; it prevents erosion by it prevents runoff from flowing
of sediment that may pollute nearby directing runoff to an erosion control directly down a slope by confining
streams or be transported off-site on device such as a sediment trap or all of the runoff into a channel or
the wheels of construction vehicles. basin, or directing runoff away from enclosed pipe. However, the
Dirt roads can become so unstable an erosive area. Temporary earth maximum drainage area per slope
during wet weather that they are banks should not adversely impact drain is two hectares. Larger areas
virtually unusable. adjacent properties and must conform would require a paved chute, rock
Efficient construction road to any local floodplain management lined channel, or additional pipes.
stabilisation not only reduces on-site regulations. Other limitations are that the clogged

B U L E T I N I N G E N I E U R 42
feature
slope drains will force water around for support. Sediment fences trap stormwater drain, drop inlet, or kerb
the pipe and cause slope erosion, and sediment by intercepting and inlet which prevents excessive
failure of the slope drain can result detaining small amounts of sediment sediment from entering stormwater
in flooding and severe erosion. from disturbed areas during drainage systems prior to permanent
construction operations in order to stabilisation.
Flow Velocity Reduction promote sedimentation behind the All on-site stormwater inlets
fence and decrease the velocity of low receiving sediment-laden runoff
■ Drainage Outlet Protection flows (up to 15 l/s) in swales and small should be protected, either by
Drainage outlet protection is a diversion channels. covering the inlet or promoting
physical device composed of rock, Sediment fences are generally sedimentation upstream of the inlet.
grouted riprap, or concrete rubble effective in locations where the flow Off-site inlets should be protected in
which is placed at the outlet of a is concentrated, and are only areas where construction activity
culvert, conduit or channel to prevent applicable for sheet overland flows tracks sediment onto paved areas or
scour of the soil caused by high flow and not to be used in streams, where inlets receive runoff from
velocities, and to absorb flow energy channels, or any places where the disturbed areas.
to produce non-erosive velocities. flow is concentrated, and in locations Drainage inlet protection is
Rock outlet protection is effective where ponded water may cause recommended only for drainage areas
when the rock is sized and placed flooding. smaller than 0.4 hectares, unless a
properly. When this is accomplished, sediment trap first intercepts the
rock outlets do much to limit erosion ■ Sand Bag Barrier runoff. However, ponding will occur
at pipe outlets. Rock size should be Stacking sand bags along a level at a protected inlet, with possible
increased for high velocity flows. The contour creates a barrier, which short-term flooding.
best results are obtained when sound, detains sediment-laden water by
durable, angular rock is used. ponding upstream of the barrier water, ■ Sediment Traps
However, large storms often wash thereby promoting sedimentation. A sediment trap is a small
away rock outlet protections and Sand bags provide a semi-permeable temporary ponding area, usually with
leave the area susceptible to erosion. barrier in potentially wet areas and a gravel outlet, formed by excavation
Sediment captured by the rock outlet are more permanent than sediment and/or construction of an earth
protection will be difficult to remove fences. They also allow for easy on- embankment. Its purpose is to collect
without removing the rock. site relocation to meet changing needs and store sediment from sites cleared
during construction. and/or graded during construction. It
■ Check Dam is intended for use on small catchment
A check dam is a small temporary Sand bag barriers are most costly, areas with no unusual drainage
dam constructed across a diversion but typically more durable, having a features, where construction will be
channel or swale. Check dams reduce longer useful life than other barriers completed in a reasonably short
the velocity of concentrated and may be used in drainage areas period of time. It should help in
stormwater flows, therefore reducing up to two hectares. removing coarse sediment from
erosion of the diversion channel or runoff. The trap is a temporary
swale and promoting sedimentation ■ Brush or Rock Filter measure with a design life of
behind the dam. If properly anchored, A rock filter berm is made of rock, approximately six months, and is to
brush or rock filter berms may be used with diameter between 20 to 75 mm, be maintained until the site area is
for check dams. placed along a level contour where permanently protected against
Check dam is primarily used in sheet flow may be detained and erosion by vegetation and/or
small channels in steep terrain, where ponded to promote sedimentation. A structures.
velocities exceed 0.6 m/s, in brush barrier is composed of brush Intended for use in any disturbed
preventing erosion by reducing the (usually obtained during the site area less than two hectares, and the
velocity of channel flow in small clearing) wrapped in filter cloth and sediment traps only remove coarse
intermittent channels and temporary anchored to the toe of the slope. If sediment (medium silt size and larger).
swales. Check dam is to be used only properly anchored, brush or rock
in small open channels, which drain filters may be used as a check dam ■ Sediment Basins
an area of four hectares or less and for sediment trapping and velocity A sediment basin is a structure
not to be used in streams, or in lined reduction. formed by excavation and/or
or vegetated channels. Rock filter berms should only be construction of an embankment
applied to drainage areas not across a waterway or other suitable
Sediment Trapping/Filtering exceeding two hectares, but if there locations to collect and store sediment
is insufficient storage space, runoff from sites cleared and/or graded
■ Sediment Fence will pond at upstream of the filter, during construction for extended
A sediment fence is a temporary possibly causing flooding in the area. periods of time before re-
sediment barrier consisting of filter establishment of permanent
fabric stretched across and attached ■ Drainage Inlet Protection vegetation and/or construction of
to supporting posts, entrenched, and, Drainage inlet protection consists permanent drainage structures. It is
depending upon the strength of the of a sediment filter or an impounding intended to trap sediment before it
fabric used, backed by a wire fence area around or upstream of a leaves the construction site. The basin

B U L E T I N I N G E N I E U R 43
feature
is a temporary measure (with a design of specific mitigation measures impacts posed by soil erosion and
life of 12 to 18 months) and is to be imposed for the control of soil sedimentation could be effectively
maintained until the site area is erosion and sedimentation during the prevented or minimised.
permanently protected against pre-construction, construction and Last but not least, mutual
erosion, or a permanent detention post-construction phases. The responsibilities and commitment by
basin or water quality control introduction of a more both the approving authorities and
structure is constructed. comprehensive Urban Stormwater the respective project proponents
Management Manual for Malaysia by should also be emphasised in order
DID has also outlined the BMPs on to ensure the soil erosion and
erosion and sediment control to sedimentation issues arising from the
better manage and mitigate the construction activities could be
erosion and sedimentation issues. effectively controlled and minimised
Therefore, with proper enforcement for the benefits and interests of all
and implementation of these parties concerned and the general
requirements, the dangers and public at large.

REFERENCES

(1) Asian Development Bank, 1986. Environmental Guidelines for


Sediment basins are suitable for
Selected Infrastructure Projects, Infrastructure Department, Asian
nearly all types of construction
projects. Wherever possible, sediment Development Bank, Manila, Philippines.
basins should be constructed before (2) Beasley, R. P., 1972. Erosion and Sediment Pollution Control, lowa
clearing and grading work begins. State Univ. Press, USA.
They are applied at the outlet of all (3) Department of Environment, 1996. Guidelines for Prevention and
disturbed catchment areas greater Control of Soil Erosion and Siltation in Malaysia, Kuala Lumpur,
than two hectares or at the outlet of Malaysia.
smaller disturbed catchment areas, as (4) Department of Irrigation and Drainage Malaysia, 2000. Urban
necessary.
Stormwater Management Manual for Malaysia, Kuala Lumpur,
However, sites with very fine
sediment (fine silt and clay) may Malaysia.
require longer detention times for (5) Hosoyomada, K. and Roslan, Z. A., 1989. On the application of
effective sediment removal. Basins USLE concerned with the prediction of Soil Erosion Loss, Publication
in excess of certain depth and storage in the JSIDRE, Japan.
volume criteria must also meet State (6) Public Works Department Malaysia, 1995. The Environmental Impact
and/or Federal dam safety criteria. Assessment of Highway / Road Projects, Road Branch, Kuala Lumpur,
Malaysia.
CONCLUSION
(7) Roslan, Z. A. and Tew, K. H., 22 - 25 August 1995. “Erosion Study
Soil erosion and sedimentation in Cameron Highlands”, Malaysian Science and Technology Congress
arising out of construction activities ‘95, Perdanasiswa, Universiti Malaya, Kuala Lumpur, Malaysia.
has posed a persistent threat to the (8) Roslan, Z. A., Amir Hashim, M. K. and Tew, K. H., 25 - 26 March
environment, and cases of prolonged 1996. “Water-Soil Erosion Features in Cameron Highlands”, World
and uncontrolled erosion would lead Water Day Seminar 1996, Allson Klana Resort, Seremban, Negeri
to untoward incidences such as Sembilan Darul Khusus, Malaysia.
landslides and mudslides. It has also
(9) Roslan, Z. A., Bakri, D. and Tew, K. H., 25- 27 November 1996.
led to the cumulative effects of
siltation and sedimentation as well as “Assessment of Soil Erodibility Potential in Malaysia - A case study”,
the shallowing of riverbeds and water 14th Conference of Asean Federation of Engineering Organization,
courseways, thus prompting flash and Malacca, Malaysia.
regular floods in low-lying areas. (10) Rubber Research Institute of Malaysia, 1980. Soil Erosion and
Fully aware of the impact of soil Conservation in Peninsular Malaysia, Kuala Lumpur.
erosion, the Government has initiated (11) Tew, K. H., 1999. Production of Malaysian Soil Erodibility Nomograph
a number of measures to minimise
in relation to Soil Erosion Issues, Selangor, Malaysia.
and control soil erosion resulting from
road construction and land (12) Roslan, Z. A. and Tew, K. H., 1999. Compilation of Presented Research
development projects. The mandatory Papers on Soil Erosion Issues in Malaysia – 2nd Edition, Selangor,
requirements of the EIA, EMP and Malaysia.
ESCP have now been formally (13) Wischmeier, W. H. and Smith, D. D., 1965. “Predicting rainfall erosion
documented as guidelines for losses - a guide to conservation planning”, USDA, Agriculture
construction activities. These Handbook No. 537, USA. BEM
guidelines also specify the proposal

B U L E T I N I N G E N I E U R 44
feature

The WTO And The South:


Implications And Recent
Developments Part 1

By Martin Khor, Director, Third World Network

T
he newest and perhaps most arrangements among developing issues beyond trade into other areas
important phenomenon in countries (such as ASEAN, SADC and such as intellectual property,
the globalisation process is Mercusor) have also emerged or are investment and investment measures,
the emergence of trade evolving. and the environment, the WTO is no
agreements as key instruments of However, the WTO is by far the longer only a “trade” organisation.
economic liberalisation and as most important institution for “Trade” in the context of the
mechanisms used by the major evolving and implementing trade multilateral system has become a code
countries to have disciplines and rules agreements. The Uruguay Round word to include all issues that have
placed on developing countries for a vastly expanded the scope of the come or may come under the purview
wide range of issues. Trade multilateral trade system so that it no of the WTO. Moreover, the WTO
agreements, that are legally binding longer deals only with the conduct agreements have the most significant
and have strong enforcement of trade in manufactures. Its scope implications for non-economic
capability, have become the matters; for example, the WTO
most important vehicle for service agreement and the
disseminating and specific agreements on
implementing economic and communications and
social policies across the world; information technology will
policies that have been planned have far reaching effects on the
by the few developed countries culture of countries around the
for developing countries to world.
follow. The World Trade The vastly increased scope
Organisation, which is the of “trade agreements” through
organisation of the multilateral the Uruguay Round and now
trading system, has in fact beyond it to the current
become the main vehicle of negotiations in the WTO on a
choice for industrialised new package of issues have
countries in organising and tremendous significance for the
enforcing global economic shaping of national economic
governance. and social policies, for the
At the regional level, trade expanded to cover trade in scope of development options,
agreements are also proliferating. agriculture, trade and investment in concerns over equity and
NAFTA is a prototype of a regional services, and beyond trade issues into marginalisation, and on national
legally-binding agreement involving intellectual property rights and sovereignty. It is thus crucial to
North and South countries, and its investment measures. Moreover, it understand the meaning and
model may be extended to South directed that the new issue of trade mechanics of this new era of trade
America. APEC is another model with and environment be discussed at agreements.
both North and South countries, but committee level in the WTO. The The conclusion of the Uruguay
without being ruled by a legally- changeover from the old GATT to the Round (UR) was heralded in the
binding agreement. The European new WTO with expanded powers and mainstream global media as a major
Community is, of course, the main jurisdiction marked the arrival of the triumph for the international
example of a legally-binding regional age of trade agreements in a new economy and a boon for all countries.
agreement among developed phase of the globalisation of policy It is clear, however, that the results
countries. Regional trade making. Owing to the extension of are at best mixed for some developing

B U L E T I N I N G E N I E U R 46
feature
countries, and for many others, It would be very difficult, if not areas of obligations for the majors are
especially the poorer countries, the UR impossible, for a developing country ambiguous and vague, while those
is likely to have an overall negative member to change the WTO rules or relating to developing countries are
effect that will further drain their to avoid compliance of obligations. specific and quite onerous such as in
economic resources. For all South The disciplines of the WTO are legally the field on TRIPS, where the original
countries, the Round will also binding on present and future purpose of intellectual property rights
foreclose a wide range of development Governments. Once the WTO (namely, rewarding innovation while
options. agreements come into force, it would ensuring disclosure and sharing of
In a sense, the UR complements be difficult for a present Government knowledge for enabling further
what structural adjustment to have economic policies relating to innovation) has now been overtaken
programmes (SAP) are achieving. The foreign trade, investment, sectoral by attempts to cater to the greed of
Round will lead to a very significant policies in services and agriculture, the corporations and safeguarding
external liberalisation of many sectors or technology policy (vis-à-vis their investments through monopoly
and facets of the domestic economy intellectual property rights) that are rentier incomes.”
of all the developing country in violation of WTO rules. Moreover, A recent and comprehensive study
members of the WTO. Structural the rules are binding on future by B.L. Das (1997) concludes that the
adjustment affects about 80 indebted Governments as well. Thus, should a UR “has been a unique negotiation
developing countries facing present opposition party have a in which most of the concessions have
repayment problems. Should some of different economic programme, it been made by developing countries
these countries get out of debt crisis would find it difficult or impossible without getting anything but meagre
and no longer require SAP loans, or to implement it (should it come to concessions in return. It is not because
should there be a change of power) if this were to contradict the the negotiators or trade policy
Government or Government policies, WTO rules. In this way, policy options officials of developing countries
the SAP can be changed or reversed. have been significantly narrowed for ignored the interests of their
However, once a country’s a country’s policies would have to be countries…. The results are in fact
Government has signed on to the UR made or changed within the characterised by the massive gaps
agreements and enters the WTO, the boundaries of what is permissible by between the economic and political
country is obliged to follow the WTO the WTO agreements. strengths of developed and
rules. Domestic laws and policies in developing countries.” The study
a wide range of areas have to be analyses the severe overall imbalance
changed to bring them in line with in concessions made by South and
these rules. According to several North countries, and how the recent
analyses, the UR agreements will trend in WTO enhances the
severely restrict or constrain the imbalance. It then examines the
possible policy options in many areas. imbalance and deficiencies in various
Non-compliance of the rules can areas: the dispute settlement system,
result in complaints being brought market access, balance of payments
against a country, and the threat of The Imbalanced And Inequitable and safeguards, subsidies and
trade penalties and retaliation Outcome Of The Uruguay Round dumping, specific sectors like
through measures affecting trade and agriculture and textiles, the new
other activities. Owing to the “single The UR negotiations that gave issues of services, and IPRs, neo-
undertaking” nature of having to sign birth to the WTO resulted in a package protectionism and commitment from
on to all the multilateral agreements of agreements that were, on the developed countries.
of the Round and to the “integrated whole, imbalanced and inequitable in Referring to the WTO agreements,
dispute settlements system”, countries favour of developed vis-à-vis Nayyar (1995) states: “It would seem
also risk having cross-sectoral developing countries. Various aspects that the institutional framework for
retaliation. At the extreme, non- of the asymmetries and disadvantages globalisation is characterised by a
compliance can also lead to expulsion to developing countries have been striking asymmetry. National
from the WTO and thus, the loss of brought out in several studies boundaries should not matter for
the automatic “most favoured nation” (Raghavan 1990, 1995; Das 1996, trade flows and capital flows but
status granted to a WTO member by 1997; South Centre 1995; Dubey should be clearly demarcated for
all other members. The WTO system 1995; Nayyer 1995; G. Cora 1995; technology flows and labour flows.
has thus a powerful system for Shahin 1996). It follows that the developing
obtaining compliance from member According to Raghavan (1995): countries would provide access to
countries. It is the organisation with “From the perspective of developing technology and would accept capital
the strongest bite in getting its countries generally (and more so of mobility without a corresponding
legally-binding rules enforced. Thus, their poor and disadvantaged provision for labour mobility. This
signing on to a WTO is a very serious sections), the new trade order under asymmetry, particularly that between
undertaking. In contrast, signing on WTO has more negative than positive the free movement of capital and
to a UN Declaration - even a UN features. And while it could be unfree (sic) movement of labour
Declaration of over 100 heads of beneficial as a rule-based system across national boundaries, lies at the
Governments - has little enforcement (depending on how the major heart of the inequality in the rules of
possibility and becomes only a moral industrialised countries implement it the game for globalisation in the late
commitment. in letter and spirit), the rules in some twentieth century. These new rules,

BULETIN INGENIEUR 47
feature
which serve the interests of services, investments and intellectual South to learn and use new
transnational corporations in the property rights. Up to then, GATT’s technologies.
process of globalisation, are explicit jurisdiction was only in keeping the The North’s motives of
as an integral part of a multilateral rules in trade of manufactured goods. introducing “trade-related intellectual
regime of discipline.” The Southern countries were rightly property rights” (TRIPs) in the Round
A significant critique of the UR concerned that the North was were to enable their firms to capture
outcome was also made in 1994 by interested in liberalising economic more profits through monopolistic
Luis Fernanda Jaramillo, then areas in which they had an advantage, higher prices and through royalties
Chairman of the Group of 77 in New where their corporations could and the sale of technology products,
York and Colombia’s permanent penetrate and capture new markets and to place stiff barriers, preventing
representative to the United Nations. which till then had been relatively the technological development of
In a speech after the Round’s protected by Southern Governments. potential new rivals from the South.
conclusion, he stated: “The The Northern push in TRIPs
Uruguay Round is proof again that proved that “free trade” and
the developing world continues to “liberalisation” were only nice
be sidelined and rejected when it slogans waved to move the Round
comes to defining areas of vital forward. The reality was
importance for their survival. The “liberalisation if it benefits me,
Third World confined itself to a role protectionism if it benefits me,
of passive spectator of the what counts is my commercial
decisions adopted…. The countries interest.”
of the Third World have been put Although in the early and
in a situation in which they already middle stages of the Round, several
paid the price of accepting the new Third World countries (including
terms in different areas of interest the influential India and Brazil) put
for the industrialised countries, up a stiff resistance to the Northern
without obtaining in exchange push and interpretation of the
satisfactory conditions of market This was certainly the case in “new areas”, by the final two years
access…. According to some estimates, services, a fast-expanding sector, with the Southern fight had melted, and
the industrialised countries, which transnational enterprises ranging in the end, the Round adopted texts
make up only 20% of the GATT from banking and insurance to to protect IPRs, liberalised services
membership, will appropriate 70% of motion pictures eagerly waiting for and prohibited trade-related
the additional income that will be the removal of barriers to their investment measures. All three issues
generated by the implementation of advance into Third World markets. have thus become integrated with
the UR. It would seem that this does The negotiations over “trade- trade in manufactured and
not allow one to conclude that the related investment measures” (TRIMs) agricultural goods, and all now fall
UR will translate into a positive were similarly initiated by the North under the jurisdiction of the WTO.
balance to developing countries…. to pressurise Third World In effect, the UR has most
Unquestionably, the developing Governments to give up their powers benefited the transnational
countries are the losers both to impose conditions on the entry and corporations. The “free trade” so
individually and collectively.” operations of foreign companies. The much bandied around by the
“liberalisation” of investments would proponents of the Round has come
The Uruguay Round’s clearly benefit the North, where most to mean, in reality, the vastly
Combination Of Liberalisation transnational companies are based. expanded freedom and powers of
And Protectionism The South was concerned that with transnational corporations to trade
only weak restrictions permitted to be and invest in most countries of the
It is a mistaken notion that the placed on these big corporations, the world, whilst correspondingly
UR was set up to promote overall smaller-scale domestic businesses Governments now have significantly
liberalisation. As pointed by Nayyar, may not survive the onslaught of reduced powers to restrict their
the main asymmetry in the Round’s foreign investments. operations, and at the same time,
results was the liberalisation of those On the other hand, when it came these corporations have “freedom”
areas which are of benefit to the major to the subject of technology transfer, from potential new competitors
countries whilst protectionism was the North took an aggressive anti- whose possibilities to develop
given a major boost in the area of liberalisation stance and instead technologically are now curbed by
technology and IPRs, and the pushed for all GATT members to intellectual property provisions in
liberalisation of labour services compulsorily introduce a standard set TRIPs. The big companies, which
(proposed by some developing of national laws to protect were the powerful lobbies behind the
countries) was unacceptable to the “intellectual property rights”. Since Northern Governments propelling
North. most patents are owned by the Round from start to end, have
When the Round began in 1986, transnational companies, this in effect won many more rights without
many Third World countries were meant the legal protection of having to meet new obligations.
strongly resisting the Northern technological monopoly by these Indeed, previous obligations they
countries’ push to expand GATT’s Northern-owned firms, and a drastic have had to observe are now
powers into new areas such as curtailment of possibilities by the dropped.

BULETIN INGENIEUR 48
feature
Outcome Of WTO Agreements For placed to take advantage of the UR’s The UR also for the first time
Developing Countries opportunities. He added: “In fact, the brought services into GATT, and
opportunities for LDCs stemming liberalisation of services will be an
On the whole, the Round has from the Uruguay Round are expected important part of WTO’s agenda.
benefited the rich industrial nations to be indirect and would perhaps Although the framework of the
and some developing countries materialise in the long run. In Services Agreement does not oblige
(mainly the more advanced ones), contrast, the challenges arising out of countries to conduct blanket
whilst many countries (especially the it are more immediate.” This, he said, liberalisation, as liberalisation will be
LDCs and weaker economies) have was due to four reasons - erosion of on the basis of a listing of positive
lost out. It is simply not true that “we preferences; limited number of offers, there will, of course, in reality
are all gainers, there are no losers”, exportable items resulting in their be far increased pressures for
as some leading proponents of the inability to participate effectively in liberalisation. In many Third World
Round would have it. Some have global trade; higher prices for import countries, the services sector is
gained more than others, and many of food, pharmaceuticals and essential relatively shielded, and local
(especially the poorest countries) have capital goods; and increased enterprises in banking, insurance,
not gained at all but may well suffer administrative cost of compliance trade, the media and professional
severe loss to their economic with their UR obligations. services have been able to develop. It
standing. In exchange for some uneven is feared that under the pressures of
The UR outcome is expected to benefits in the UR, the South as a liberalisation, the Northern TNCs
bring some benefits to those whole has had to make major involved in services will make further
developing countries able to take concessions, especially in agreeing to inroads on, and in some countries,
advantage of certain changes. A bring in the new issues of services, may come to dominate some of the
lowering of Northern countries’ investment measures and intellectual services.
industrial tariffs will benefit those property rights, into the GATT/WTO The South’s collective loss was
Southern countries with a system. most acutely felt in the agreement on
manufacturing export capacity. The TRIPS, through which countries are
planned phasing out of the multifibre obliged to introduce IPR legislation
arrangement will have positive effects similar to Northern standards. This
on textile-exporting Southern will hinder Southern countries’
countries (However, textile-exporting indigenous technological
developing countries are disappointed development. It should be noted that
and frustrated that owing to en- the present industrial countries did
loading of the implementation not have patent or IPR laws, or laws
schedules of developed countries, the as strict as will now be imposed
benefits accrue mainly at the end of through TRIPs, during their
the 10-year phase-out period). The industrialising period, and this
reduction of agricultural subsidies enabled them to incorporate
would improve the market access of technology designs originating from
those Southern countries that export abroad in their local systems. It will
agricultural products. also give rise to increasing technical
These benefits will mainly accrue payments such as royalties and
to the better-off developing countries licence fees to TNCs owning most of
that already have an export capacity. For particular groups of Southern the world’s patents.
The weaker countries (especially the countries, the UR will also result in The new IPR regime will also have
least developed countries) would not specific problems. For instance, the significant impact on raising the
be able to benefit, or to benefit much agriculture agreement could have prices of many products. By
from these. Several countries severe negative effects on some Third restricting competition, the IPR rules
(especially Africa and Indonesia) are World countries. Most of them will enable some companies to jack
projected to suffer absolute losses as (excepting the least developed up prices of their products far beyond
a result from the Round agreements. countries) will also have to reduce costs, and thus, earn rents in terms
The benefits (which fall significantly domestic subsidies to farmers and of monopoly revenues and profits.
short of what had been requested by remove non-tariff controls on This is clearly seen in the case of
the developing countries) will also agricultural products, converting computer software. Also, most Third
take a long time (10 to 20 years) to these to tariffs and then progressively World countries have exempted
come on stream, whilst the problems reducing these tariffs. This will impose agriculture, medicines and other
of compliance are already being felt competition on the domestic farm essential products and processes from
by developing countries, especially sector. Farmers unable to compete their national patent laws, but with
the poorer ones. The LDCs will be with cheaper imports may not survive. the passage of TRIPs, everything is
particularly hit. At the UNCTAD’s Agricultural liberalisation will also subject to IPRs unless explicitly
Trade and Development Board session raise world food prices, which may exempted. The prices of medicines are
in October 1996, the Secretary of the benefit food exporters, but about 100 expected to shoot up in many
Bangladesh Commerce Ministry, Mr. Third World food importers will face countries, and foreign drug sales will
Farouk, speaking on behalf of the LDC a higher food import bill and are likely increase rapidly at the expense of
group, said the LDCs are not yet well to be the biggest UR losers. local products.

BULETIN INGENIEUR 49
feature
The TRIPs agreement also opens and greater linkages to the domestic Committee on Trade and
the door to patenting of life forms economy and that protects the Environment. There have been strong
such as micro-organisms and balance of payments. Just as attempts by some Northern
modified genetic materials, thus significant is that once the area of Governments (especially the U.S. and
providing the boost in incentives so “investment” has been brought into France), under pressure from trade
much desired by the biotechnology the ambit of the WTO, even if only in unions, to link trade to labour
industry. Many environmentalists are relation to investment measures standards in the WTO. It is likely that
concerned that this will be detrimental (which had already been part of the a wide range of other issues, such as
to the global environment, as the GATT rules), it could easily be human rights, tax systems and
present lack of controls and predicted that the Northern cultural behaviour will also be sought
accountability in biotechnology Governments would soon resume to be linked to trade measures in the
research and application will likely their pressures to bring in the whole WTO in future.
accelerate bio-diversity loss and could body of “investment policy per se” The linking of issues to the
threaten natural ecosystems. into the WTO framework. This has possibility of sanctions under the
For plant varieties, TRIPs do now happened, with the current device of attaching a “trade-related”
permit countries the option to either intense pressures by the North to prefix to the chosen topics was
introduce patents or an alternative establish a new multilateral successfully used in the UR to inject
“effective” sui generis system of investment agreement in the WTO. IPRs (through a trade-related
intellectual property protection for a intellectual property rights
trial period of four years, after which agreement) and investment issues
the agreement will be reviewed. Many (through a trade-related investment
farmers’ groups (especially in India, measures agreement) into the GATT/
where huge farmers’ demonstrations WTO system. The justification for
and rallies have been held against introducing these issues was that
GATT) and environmentalists are they are “related to trade.” In fact,
concerned that in the end, Third the real objective was to link chosen
World farmers will be disallowed the issues to the threat of “trade
traditional practice of saving seed for retaliation and penalties” for non-
the next season’s planting (if the seed compliance of disciplines. The device
used is under the intellectual of bringing in new topics by alleging
protection of a company) but forced that they are trade-related has
to purchase the seeds. continued to be used in on-going
In the next few years, these WTO negotiations. In fact, the
farmers and their supporters may pretence of being directly trade-
argue the case for a sui generis system related is no longer even necessary
to protect their rights as an alternative and may unnecessarily restrict the
to corporate intellectual property Dangers Of The Proliferation Of scope of the issues being introduced.
rights. It will be interesting what the “Trade-related Issues” The prefix “trade-related” has now
Northern Governments and the WTO been dropped in proposals for these
consider to be “effective” in protecting In the recent post-UR period, the new issues, which are now sought
intellectual property rights. developed countries have intensified to be brought into the trade arena
In the area of TRIMs, the most the pressures to incorporate more through simply using the word “and”,
important point is that national and more issues, which are to their as in “trade and environment”, “trade
policies relating to foreign advantage, into the WTO. Developing and labour standards” and “trade and
investments have also now begun to countries, on the other hand, are investment.”
come under the ambit of the GATT/ unprepared individually or as a The device of linking trade to
WTO system. Originally, the Northern group, for these new negotiations. It other issues (when the intention is
countries proposed that foreign is likely that the WTO will be used really to link the dispute settlement
companies be given automatic “right for implementing more new rules system of the WTO to new policy
to establishment” or “commercial that would be detrimental to the areas) is being increasingly used for
presence”. This would have given interests of the South, unless officials the purpose of further opening up
rights to foreign companies that were and political leaders in developing Third World economies or to reduce
attained by colonisers through war countries prepare themselves much their competitiveness in the scramble
and bloodshed in the colonial era. better and defend their interests more for world market shares. The WTO
Eventually, the objections of some effectively in the current and future could also be used as an instrument
developing countries prevailed. In the WTO negotiations. to shift a great portion in the WTO
final TRIMs agreement, “investment The Northern Governments plan forum. Indeed, it is precisely because
measures” such as local content to link trade (and the possible use of the South is so weak in the WTO
(obliging foreign firms to use at least trade measures and sanctions as arena, coupled with the fact that the
a specified minimal amount of local enforcement mechanisms) to several WTO carries the power of “bite” in
inputs) will be phased out. This, of economic and non-economic issues the form of trade retaliation
course, has serious enough in ways that are to their advantage. mechanisms that this institution has
implications in terms of prohibiting Trade and environment are already been chosen as a vehicle to institute
measures that promote local industry being negotiated under the WTO’s reforms favourable to the North. BEM

BULETIN INGENIEUR 50
health

Detox For Health


Courtesy of iSmile Magazine, Sept/Oct 2003 issue

Naturopaths believe that the body is self-healing and self-repairing. However, it cannot fight diseases
if the body is filled with toxins and deficient in nutrients. To prevent the onset of degenerative
lifestyle diseases, the logical step is to detoxify and replenish the body with proper nutrients.

A
fter running 5,000 km, the black oil in our Prolonged emotional stress and lack of rest and exercise
car has to be flushed out and replaced with can also contribute to the production and accumulation of
new oil. If not, the engine can get clogged toxins in the body.
and the car may cease running. When it comes As toxins build up in the body, cell destruction begins.
to the human body, it cannot be denied that many of us Proper function of the body tissues and organs is slowed
clog our digestive system with too much food, as well as down. The body degenerates and symptoms of diseases begin
processed food and drinks which carry toxins from to appear. The signs of toxic accumulation appear differently
chemicals, preservatives and additives. Depending on the in each person and there are various stages in the toxic build-
level of toxicity, doctors in naturopathy believe that the up process (see table).
body will emit signs from the simple fever and constipation
to the more serious heart and liver diseases. Spring Cleaning The Liver & Colon
cleaning or flushing toxins out of the body would be a How does one remove the toxins? Detoxification has its
logical step in preventing the development of chronic roots in ancient and current methods of natural cleansing of
diseases. the body. Dr. Tan’s DRP is based on her research into various
‘Toxins and nutritional deficiency are the root causes therapies and guidance from her mentor, the late Dr. Costa
of diet and lifestyle related diseases. The two are related Deir, a medical doctor and naturopath. The 7-day DRP calls
and enhance one another,’ says Dr. Lynn Tan, doctor in for a strict diet of freshly made juices and
naturopathy. Dr. Tan has designed a 7-day Detoxification a regime of time-specific cleansing and
& Rejuvenation Programme (DRP) which helps one to tissue-building drinks. Cleansing herbal
remove toxins and rebuild health without drugs. Since drinks and coffee enemas are the
the 1990s, several thousands people have tried the ‘cleaning agents’ to remove toxins
programme and found it beneficial for health. from the colon and liver. Dead cells
Naturopathy follows the principles of working in line and toxins are removed from the body
with nature. The body is believed to be self-healing and through skin scrubbing, discharge of
self-repairing, provided it is given the right natural coffee enemas and normal bowel
nutrition. movements.
Coffee enema is an
How Toxins Build Up In Our Body essential part of the
Toxins can come from polluted air and the highly liver detoxification
processed food and impure water which we put into our process. It has been
bodies. They are also generated from within the body. researched back in
Consumption of excessive food and processed food takes a the 1920s when
toll on our digestive and waste elimination systems. Poorly German scientists
digested food passes through the intestinal tract sluggishly, experimented and
causing fermentation and putrefaction, which in turn reported that boiled
produces toxins that are re-absorbed into the blood stream coffee solutions,
through the intestinal walls. when administered

B U L E T I N I N G E N I E U R 54
health
rectally in experiment animals, tend to stimulate the Starting Anew
production of bile which detoxifies the liver and restores After detoxification and
it to its normal functions. replenishing, a new healthy
The boiled coffee solution has to be retained in the diet to avoid future toxin
gut and enters the liver via the colon, causing two effects. build-up makes sense. A
Firstly, it stimulates the production of bile which detoxifies guide for healthy diet and
the liver. Secondly, it stimulates the production of an lifestyle includes:
enzyme called Gluthathione S. Transferase (GST) which
helps to remove free radicals in the blood. All the body’s ● Take at least 75% raw
blood passes through the liver every three minutes. The food, with fresh fruit in the
blood therefore gets detoxified as it passes through this morning and 50% raw
‘caffeinated’ liver. vegetables for lunch and
The effects of the detoxification are clearly visible as dinner
what comes out during bowel movements are black, gooey, ● Eat fruit on an empty stomach; do not mix fruit with
rubber encrustations. other food
● Get predigested protein and other nutrients daily from
fresh yogurt and flaxseed oil
Rebuilding And Balancing
● Drink a minimum of 8 glasses of distilled water, honey-
But throwing out toxins is not enough. The body’s
apple cider vinegar cocktail for fresh juices anytime of
proper chemical balance - nutritional, hormonal and
the day, but not during meals.
metabolic - must be restored so that the body can heal
● Take wholesome, natural, organic, non-
itself. Under the DRP, rebuilding nutrition comes in the
processed and unrefined food
form of health-building foods such as spirulina, green
● Develop a habit of taking your rest
food, flaxseed oil and raw honey.
preferably by 10 p.m.
Rejuvenation will appear in many forms such as feeling
● Exercise using a rebounder (trampoline)
more energetic, losing weight and getting a clearer skin
daily.
complexion. Printed testimonials from several people ● Think only whatever is true, noble, just,
acknowledge that the DRP has proven to be beneficial for and of good virtue and praiseworthy
those with health problems such as high blood pressure,
hormonal imbalance, migraine, diabetes and arthritis. Distilled water is recommended as this water is close
A note of caution is that it is important for those to nature, following the hydrological cycle. The sun heats
currently on prescribed medications not to stop during water on earth. Water evaporates, condenses and becomes
the course of the detoxification programme. The clouds. Then it rains and the cycle repeats itself.
medication can be readjusted following the results of the Is there an alternative to expensive organic greens and
detoxification and the doctor’s advice. health-building food? It is a matter of perception. We can
spend less on other things like clothing and eating out.
We cannot really eat large quantities of
fruits and vegetables. Organic health food
Development Of Chronic & Degenerative Diseases
may increase your expenses by RM50 or
RM100 per month. But compare this with
the healthcare bill if you get sick and
hospitalised.
In reality, many Malaysians will not
be disciplined enough to change their
Degeneration
Chronic Heart disease, diet drastically. The habits of eating
Migraine, gout, stroke, diabetes, ‘yummy’ food and eating out are very
arthritis, high kidney disease, entrenched. Exceptions would be those
blood pressure, gall bladder who are suffering from a certain disease
Poor Health skin problems, disease, serious
Tiredness, back ache, arthritis and gout, and those who have recovered from years
blocked nose, ulcers, asthma, serious skin of ill health. There is hope yet to prevent
overweight, hormonal problems, the onset of degenerative diseases if we
headaches, imbalance, impotence, liver improve our eating habits and carry out
lower back sinusitis, problem, multiple
Elimination pain, skin premature sclerosis, cancer a detoxification programme once or
Inflammation,
Inflammation, blemishes, piles,
blemishes, piles, ageing twice a year. BEM
discharge,
discharge, constipation
fever,
fever, colds
colds.
iSmile is a bimonthly health and self-
improvement magazine. It is available in
leading bookstores and news stands
throughout Malaysia.
Source: Healthy Living Guide by Dr. Lynn Tan

B U L E T I N I N G E N I E U R 55

You might also like