Professional Documents
Culture Documents
Ref: MS-PI-CSD-007
(Revision 0)
Aug 2017
Methodology Statement for Backfill of Power Intake
1. /Profile
EL.1011.5~EL.1032
96434m EL.1020
EL.1020~EL.1032
Backfilling rock muck mainly refers to EL.1011.5~EL.1032 inside and
outside the tower and the quantity of the backfill in power intake is about
96434m. The backfilling rock muck of power intake is divided into three
stages.The 1st stage backfill will be done from EL.1011.5 to EL.1020.0,the 1nd
stage backfill will be done from EL.1020.0 to EL.1032.0,and the 3rd stage
backfill will be done in the left and right retaining wall of power intake.
2. / Compilation Basis
3. /Construction Layout
EL.1020.0~EL.1032.0
1# 1:1.4
During the 1st stage backfilling,the material of backfilling will be
transported by truck from aggregate field to power intake,and then the material
and equipment will be transported to the working face by truck or tower crane
and cage.The temporary backfilling will be done at the the right of the power
intake 6# from EL.1011.5~EL.2010.0,to form the temporary road which is
connecting R9 road.The temporary backfilling rock muck will be removed and
backfill plain concrete C20.
The backfilling of 2nd stage is from EL.1020.0~EL.1032.0 and will be
completed from left to right of power intake.
The slope of 1:1.4 will be reserved on the left side of power intake 1#
concrete retaining wall,and the 3rd stage backfilling will be completed after the
retaining wall is completed.
4.1 / General
1m
7d 1m
100mm 400mm
400mm
1900Kg/m35mm 22% 25%
Prior to backfilling, forms shall be removed and the areas cleaned of trash
and debris. Backfilling adjacent to concrete structures 1 m and over in height,
shall not commence before 7 days from the time the concrete was cast. The
material to be placed within 1 m of the structure shall contain no material
greater than 100 mm and other position should not be more than 40cm. In
order to ensure the particle size of backfill material,a sieve need be maked for
the backfilling in power intake.
The backfilling rock muck should be layered compacted,and the layer
thickness of paving is 40 cm. The compaction density of rock muck should be
no less than 1900Kg/m3,the content of fine particle below 5mm should be less
than 22% and the porosity should be less than 25%.
The testing data and compaction effect must be accepted by the Owners
Engineer before the next stage of construction
4.2 / The Construction of Backfilling
The backfilling rock muck of power intake should be layered and the
thickness of each layer of ballast loose laying 40 cm.The pave leveling shall be
done by a bulldozer, and some uneven parts should be made up with fine
stones.
4 6
2m 10
4.3.1 / Manpower
The manpower deployment please refer to Table 4.4-1:
1 /Supervisors 3
2 /Bulldozer operators 4
3 / Excavator operators 4
4 /Roller operators 2
7 /Surveyors 4
8 /Electricians 2
9 /Mechanical technicians 2
10 /Laboratory technicians 6
11 /Causal laborers 16
Total 57
4.3.2 / Equipment
Major equipment deployment for backfilling please refer to Table 4.4-2:
2 18t Unit 1
Roller compactor
3 Unit 2
Excavator
4 25t Unit 6
Dumper trucks
5 Unit 1
Frog hammer
8
8