PROJECT REPORT %

15 16 17 18 19 20 21 22
OCTOBER 2017
23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14
NOVEMBER 2017
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1-2 3-4 5-6 8-9 10-11 12-13
DECEMBER 2017
15-16 17-18 19-20
99.80 99.80
%
98.65 99.22
98.07
96.92

LOGO
100 92.90
94.05
95.20
100
91.18
90.03
88.30 88.88
87.73
90 83.13
84.28
85.43
86.58
90
81.98
80.26
78.55
80 75.11
76.83
80
Job ID : BLCP
73.39
71.68
69.96
70 64.81
66.52
68.24
70
Project : MAJOR SHUTDOWN UNIT 1
63.09
61.37
59.65
60 55.08
56.22
57.37
58.51
60
54.00 53.94
52.80
51.08
50 50.00
46.49
48.79 50
Location : BLCP
45.00
44.78
43.00
42.48
40 36.74
39.03
39.00 40
34.44 34.00
32.00
30 29.26
29.00
31.56
30.00 30
Plan to Finish : 15 December 2017
26.39
24.09 25.00
23.00
20 21.22
20.00 20
17.77
16.00
14.90
10 10.87
9.00
13.00
10
8.00

Preparation By : Prasong Singthom


6.28
6.00 7.00
5.15
5.00 5.71
5.50
4.58
4.00
3.44
3.00
2.29
2.00
1.15
0 0.00
0

COMPLETE OCTOBER 2017 NOVEMBER 2017 DECEMBER 2017


responsible JOB DESCRIPTION START FINISH ACTUAL Duration % ACTUAL
% 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Plan 15/10/2017 0.57 0.57 0.57 0.57 2.28
Install Scaffolding and Remove 18/10/2017 18/10/2017 4 100%
Actual 15/10/2017
Plan 18/10/2017 0.57 0.57 0.57 0.57 0.57 2.85
Remove Skin Casing & seal box 22/10/2017 22/10/2017 5 100%
Actual 18/10/2017
Plan 22/10/2017 0.57 0.57 0.57 1.72
Remove of refractory 24/10/2017 24/10/2017 5 100%
Actual 22/10/2017
Plan 22/10/2017 0.57 0.57 0.57 1.72
Vacuum Truck clean 24/10/2017 24/10/2017 3 100%
Actual 22/10/2017
Plan 23/10/2017 0.57 0.57 1.15
Setting of temporary support 24/10/2017 24/10/2017 2 100%
Actual 23/10/2017
Plan 24/10/2017 0.57 0.57 0.57 0.57 0.57 0.57
Temporary monorail setting 29/10/2017 29/10/2017 6 100%
Actual 24/10/2017
Plan 23/10/2017 0.57 0.57 0.57 0.57 0.57 0.57
PH Tube Cutting 28/10/2017 28/10/2017 6 100%
Actual 23/10/2017
Plan 25/10/2017 0.57 0.57 0.57 0.57 0.57 0.57 0.57
RH Tube Beveling 31/10/2017 31/10/2017 7 100%
Actual
Plan 4/11/2017 0.57 0.57 0.57 0.57 0.57 0.57
RH Tube Cutting ( Furance inside ) 13/11/2017 1/11/2017 6 41%
Actual
Plan 4/11/2017 0.57 0.57 0.57 0.57 0.57 0.57
Tube Remove to outside 13/11/2017 1/11/2017 6 41%
Actual
Plan 1/11/2017 0.57 0.57 0.57 0.57 0.57 0.57 0.57
Tube Beveling 7/11/2017 1211/2017 7 5%
Actual
Plan 3/11/2017 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57
New 1ry RH tube Carry in 27/11/2017 3/11/2017 25 6%
Actual
Plan 4/11/2017 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57
RH Tube Fit up & Weld (TOP) 27/11/2017 1/11/2017 24 5%
Actual
Plan 15/11/2017 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57
RH Tube Fit up & Weld (Bottom) 2/12/2017 26
Actual
Plan 23/10/2017 0.57 0.57 0.57 0.57
Inspection Hole Cutting 26/10/2017 26/10/2017 4 100%
Actual 23/10/2017
Plan 5/12/2017 0.57
HDR Inside Cleaning/Bore scope 5/12/2017 1
Actual
Plan 6/12/2017 0.57 0.57
Fit up and welding for nozzle end cap 7/12/2017 2
Actual
Plan 7/12/2017 0.57 0.57 0.57 0.57
Installation Refractory 10/12/2017 4
Actual
Plan 10/12/2017 0.57 0.57
Skin casing reinstallation 11/12/2017 2
Actual
Plan 11/12/2017 0.57 0.57 0.57 0.57
Insulation & Lagging Restoration 14/12/2017 4
Actual
Plan 15/10/2017 0.57 0.57 0.57 1.72
Scaffolding setting 17/10/2017 17/10/2017 3 100%
Actual 15/10/2017
Plan 23/10/2017 0.57 0.57
Removal of Insulation header and pipe 24/10/2017 24/10/2017 2 100%
Actual 23/10/2017
Plan 24/10/2017 0.57 0.57 0.57
Cut off plug 26/10/2017 26/10/2017 3 100%
Actual 24/10/2017
Plan 26/10/2017 0.57 0.57 0.57 0.57 0.57 0.57
Fit-up & welding for new bypass line pipe 31/10/2017 6
Actual
Plan 31/10/2017 0.57 0.57 0.57 0.57
Remove the additional seismic quide 3/11/2017 4
Actual
Plan 3/11/2017 0.57 0.57 0.57 0.57
Installation of insulation 6/11/2017 4
Actual
Plan 6/11/2017 0.57 0.57 0.57
Removal of scaffolding 8/11/2017 3
Actual
0.006 174
PERCENTAGE OF PLANNING 1.15 1.14 1.14 1.14 0.57 0.57 0.57 1.72 2.87 4.02 2.87 3.45 2.87 2.30 2.87 2.30 2.87 2.30 2.30 3.45 2.29 1.72 2.29 2.29 1.72 1.14 1.14 1.14 1.14 1.14 1.14 1.72 1.72 1.72 1.72 1.72 1.72 1.72 1.72 1.72 1.72 1.72 1.72 1.72 1.15 1.15 1.15 1.15 1.15 0.57 0.57 1.15 1.15 1.72 1.15 1.15 1.72 1.15 0.57 0.57 0.57 0.00
PERCENTAGE OF ACTUAL
ACCUMULATIVE OF PLANNING 1.15 2.29 3.44 4.58 5.15 5.71 6.28 8.00 10.87 14.90 17.77 21.22 24.09 26.39 29.26 31.56 34.44 36.74 39.03 42.48 44.78 46.49 48.79 51.08 52.80 53.94 55.08 56.22 57.37 58.51 59.65 61.37 63.09 64.81 66.52 68.24 69.96 71.68 73.39 75.11 76.83 78.55 80.26 81.98 83.13 84.28 85.43 86.58 87.73 88.30 88.88 90.03 91.18 92.90 94.05 95.20 96.92 98.07 98.65 99.22 99.80 99.80
ACCUMULATIVE OF ACTUAL 0.00 2.00 3.00 4.00 5.00 5.50 6.00 7.00 9.00 13.00 16.00 20.00 23.00 25.00 29.00 30.00 32.00 34.00 39.00 43.00 45.00 50.00 54.00