Professional Documents
Culture Documents
construction method
weather dependence; investment cost and labour intensity of usage of formwork; construction speed;
requirements regarding durability; connection steel supporting structure and concrete deck; temporary support
provisions; extra reinforcement for connecting prefab - in situ parts.
erection method
stress distribution: desired erection of the concrete deck
Often, preceding the application of the concrete deck, the entire steel structure, including dowels, is placed. Due
to the high labour cost versus material cost, it is desirable to aim at a low work intensive steel structure instead of
a structure that is optimal as to material use. The consequence is that the number of additional provisions, such as
cross frames and stiffening plates, is limited to a minimum. An extra advantage is that the total conservation
surface is reduced and inspection becomes easier. With regard to the application of the concrete roadway, the
following major construction methods can be distinguished:
a. in situ poured
b. use of prefab deck elements (full or half depth precast)
c. longitudinal sliding of concrete deck elements over steel girders
Fig. 33. Example of scaffolding using traditional timber beam / plate elements .
Dr. A. Romeijn 16
steel-concrete bridges - 2004
Tempory scaffolding construction: supported by the lower flange of the steel structure
The scaffolding is supported by the steel main construction. The simplest way of applying the concrete is the
method by which the roadway is poured in parts and the scaffolding is moved on every time.
Fig. 37.
The use of profiled sheets which will not be removed after finishing
the concrete deck.
Dr. A. Romeijn 17
steel-concrete bridges - 2004
Fig. 38.
Example of scaffolding by using prefab concrete elements.
Advantages are the relatively short construction time, manufacturing in the shop, variances in the sequence of
placing the prefab elements and the sequence of connecting the steel-concrete.
Manufacturing in shop means good quality, improved working environment for the workers, reduced man-hours
outdoors and less trafic interference.
Disadvantages are the concentrated location of shear connections (so-called shear pockets), the reinforcement to
link-up the prefab elements, dimension tolerances and splice between steel and concrete.
Fig. 40.
Sliding of concrete deck panels; studs connected
afterwards.
Cross-section between Cross-section at spacing
spacings
Dr. A. Romeijn 18
steel-concrete bridges - 2004
Both alternatives have the disadvantage that the sequence, in which the roadway is constructed, is difficult to
vary. and the connection steel-concrete can only be activated after the entire roadway has been placed.
Dr. A. Romeijn 19