Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
MILESTONES
CNM0000060 60kV OHL -MC 0 13JAN11A 0 100
CNM0000080 CPF Ready for First Energization 0 28FEB11A 0 100
GASIN RFGI (Step 1A/1B Up to No load test TK3) 0 31MAR12 0 0 0
MC Ready For Gas In Plant (Step 2) 0 03MAY12 0 0 2
RFSU Ready for Start Up (Start Wet Gas in CPF) 0 31MAY12 0 0 0
PAC Provisional Acceptance Certificate 0 31JUL12 0 0 0
PRE-COMMISSIONING
PC00000000 CPF - PRECOMMISSIONING 594* 13OCT10A 28MAY12 125* 50 12
COMMISSIONING
CN00000000 CPF - COMMISSIONING 467* 01MAR11A 09JUN12 137* 40 14
COMMISSIONING/ START-UP
SU00000000 START-UP With DRY GAS 91* 18MAR12 16JUN12 91* 0 0
SU00000002 START-UP With WET GAS 55* 31MAY12 24JUL12 55* 0 0
SU00000003 PERFORMANCE TEST 7* 25JUL12 31JUL12 7* 0 0
10 - MLE CPF
General
CONSTRUCTION
CO00000070 CPF Mechanical (Hot works) 0 24JAN12* 0 0 250
CO00000050 MLE CPF Roof/Cladding&STeel Structures 188 25JAN12 30JUL12 188 0 62
CO00000010 MLE CPF Civil works 250 25JAN12 30SEP12 250 0 0
20 - Separation
2001 - Separation
Step 2: Gas in Plant
CONSTRUCTION
CO20000060 2001 Electrical Cables laying 20 16FEB11A 25FEB12 32 95 37
CO20000090 2001 Instrument Cable Laying [Secondary] 20 16FEB11A 29FEB12 36 96 37
CO20000070 2001 Electrical Cable Connection 20 02APR11A 29FEB12 36 86 37
Motor Control Station
CO20000080 2001 Electrical Equipments installation 20 10FEB12 29FEB12 20 0 37
CO20000020 2001 Piping & Supports Installation 20 30OCT10A 03MAR12 39 98 0
CO20000030 2001 Piping Hydrotest 20 26MAR11A 17MAR12 53 54 0
CO20000100 2001 Field Instruments installation 20 13NOV11A 17MAR12 53 68 20
CO20000130 2001 Painting works 20 24APR11A 28MAR12 64 90 16
CO20000120 2001 Insulation works 20 12MAR12 31MAR12 20 0 34
PRE-COMMISSIONING
PC20010080 2001 Electrical (Cables, Motors) 5 17SEP11A 08MAR12 44 85 36
PC20010070 2001 Piping Systems: Blowing / Reinst 49 26JUL11A 06APR12 73 55 0
PC20010090 2001 Instrumentation 29 09SEP11A 13APR12 80 1 0
PC20010012 2001 Scrubber VD-20-01 Internal Inspection + Box up 7 07APR12* 13APR12 7 0 0
PC20010020 2001 Air Cooler Exchanger GC-20-01 7 07APR12 13APR12 7 0 0
PC20010014 2001 Pig Receiver VM20-05 Internal Inspection+Box up 2 12APR12 13APR12 2 0 0
PC20010SMC 2001 Sub System MC - 2001 0 13APR12 0 0 0
COMMISSIONING
CN20010040 2001 Air Cooler Fans (8) Run in (Load Test) 7 14APR12 20APR12 7 0 163
CN20010010 2001 Piping Systems: leak test (25) 14 14APR12 27APR12 14 0 0
CN20010020 2001 Loop Checks & Functional Test (68) 14 14APR12 27APR12 14 0 7
CN20010045 2001 Piping Systems: Inerting 7 28APR12 04MAY12 7 0 0
CN2001RSFU 2001 Sub System RFSU - 2001 0 04MAY12 0 0 0
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
22 - Oil Handling
2201 - Oil Storage, Pumping & Metering
Step 2: Gas in Plant
CONSTRUCTION
CO22010120 2201 Shelter pumps erection 1 06MAR11A 03MAR12 39 0 35
CO22010040 2201 Electrical Cable laying 7 01NOV11A 31MAR12 67 0 18
CO22010130 2201 Sheds & roofing/Cladding 1 04MAR12 31MAR12 28 0 35
CO22010100 2201 Electrical equipment 7 25MAR12 31MAR12 7 0 25
CO22010030 2201 Electrical Cable Connection and Tests 128 27NOV11A 07APR12 74 0 18
CO22010060 2201 Equipment Installation 88 19JAN11A 14APR12 81 0 0
CO22010090 2201 Piping & Supports Erection 139 19FEB11A 14APR12 81 0 0
CO22010110 2201 Piping Hydrotest 1 04DEC11A 28APR12 95 0 0
CO22010150 2201 Painting works 491 21AUG10A 08MAY12 53 0 15
CO22010080 2201 Instrument Installation 28 15APR12 12MAY12 28 0 35
CO22010160 2201 Insulation works 428 14AUG10A 15MAY12 53 0 15
PRE-COMMISSIONING
PC22010090 2201 Electrical (Cables, Motors) 7 08OCT11A 07APR12 74 20 18
PC22010080 2201 Piping Systems: Blowing & Reinst 51 31JUL11A 14APR12 81 55 0
PC22010010 2201 Storage Tanks RA-22-03A/B; RL-22-04 33 11MAR12 14APR12 35 0 0
PC22010020 2201 Oil Degassing Boot VD-22-01 8 07APR12 14APR12 8 0 0
PC22010099 2201 Instrumentation 15 09SEP11A 21APR12 88 1 11
PC22010030 2201 Pumps PA-22-04A/B; 05A/B; 06A/B 15 07APR12 21APR12 15 0 0
PC22010040 2201 Fiscal Metering Package UJ-22-01 8 15APR12 22APR12 8 0 13
PC22010SMC 2201 Sub-System MC - 2201 0 22APR12 0 0 13
COMMISSIONING
CN22010140 2201 MV Ele Motors (4) no load test 4 22APR12 25APR12 4 0 33
CN22010150 2201 LV Ele Motors (2) no load test 2 26APR12 27APR12 2 0 33
CN22010130 2201 Loop Checks & Functional Test 20 26DEC11A 28APR12 95 1 21
CN22010190 2201 Fiscal Metering Package Commissioning 7 23APR12 29APR12 7 0 154
CN22010160 2201 Pumps: final allignement and coupling 14 22APR12 05MAY12 14 0 0
CN22010120 2201 Piping Systems: leak test 14 06MAY12 19MAY12 14 0 0
CN22010155 2201 Piping System: Inerting 10 20MAY12 30MAY12 11 0 0
CN2201RFSU 2201 Sub-System RFSU - 2201 0 30MAY12 0 0 0
24 - Gas Treatment
2401 - Gas Treatment
Step 2: Gas in Plant
CONSTRUCTION
CO24010090 2401 Piping & Support erection 95 30OCT10A 29FEB12 36 0 196
CO24010050 2401 Electrical Cable Laying 30 16FEB11A 29FEB12 36 0 214
CO24010100 2401 Piping Hydrotest 1 27MAR11A 07MAR12 43 0 196
CO24010120 2401 Final Painting works 1 01NOV10A 14MAR12 50 0 196
CO24010030 2401 Instrument Cable Laying [Secondary] 20 03MAR11A 17MAR12 53 0 19
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 2 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
25 - Gas Conditioning
2501 - Gas Conditioning
Step 2: Gas in Plant
CONSTRUCTION
CO25010110 2501 Cold Liquid Pumps [PA-25-01 A/B] 57 22MAR11A 25FEB12 32 0 161
Without Lines of UK-25-04 A/B
CO25010090 2501 Piping & Supports Erection 150 30OCT10A 29FEB12 36 0 24
Without Lines of UK-25-04 A/B
CO25010140 2501 Piping Hydrotest 1 24APR11A 21MAR12 57 0 24
CO25010050 2501 Instrument Cable Laying [Secondary] 129 20FEB11A 24MAR12 60 0 190
TO BE CONFIRMED
CO25010060 2501 Equipment Installation [UK-25-04 A/B] 10 24MAR12* 02APR12 10 0 123
Without connectipon to UK-25-04 A/B
CO25010080 2501 Instrument Installation 72 20FEB11A 21APR12 88 0 162
TO BE CONFIRMED
CO25010070 2501 Steel Structure of Shelter [UK-25-04 A/B] 15 03APR12 22APR12 20 0 123
CO25010120 2501 Shelters Roofing/Cladding installation 15 05MAR12 30APR12 57 0 153
CO25010150 2501 Piping & Support erection [UK-25-04A/B] 15 10APR12 30APR12 21 0 123
CO25010160 2501 Piping Hydrotest [UK-25-04A/B] 21 17APR12 07MAY12 21 0 142
TO BE CONFIRMED
CO25010040 2501 Cable Laying [UK-25-04 A/B] 14 26APR12 09MAY12 14 0 142
CO25010170 2501 Electrical Equip [UK-25-04A/B] 5 05MAY12 09MAY12 5 0 144
TO BE CONFIRMED
CO25010030 2501 Cable Connection and Tests [UK-25-04 A/B] 14 28APR12 11MAY12 14 0 142
TO BE CONFIRMED
CO25010130 2501 Instrument Installation after [UK-25-04 A/B] 21 01MAY12 21MAY12 21 0 132
TO BE CONFIRMED
CO25010100 2501 Lighting Shelter [UK-25-04 A/B] 30 01MAY12 30MAY12 30 0 123
CO25010190 2501 Final Painting Works 20 24MAY11A 14JUN12 142 0 108
CO25010180 2501 Insulation Works 20 04SEP11A 21JUN12 149 0 101
PRE-COMMISSIONING
PC25010010 2501 Deethaniser CX-25-01 21 31DEC11A 28FEB12 35 45 53
PC25010020 2501 Pressure Vessels VD-25-02/03/04 7 29FEB12 06MAR12 7 0 53
PC25010060 2501 Reboiler GA-25-04 7 07MAR12 13MAR12 7 0 53
PC25010100 2501 Electrical (Cables, Motors) 7 18MAR12 24MAR12 7 0 42
PC25010095 2501 Hydrojetting Drying/Inerting leak test 30 21FEB12 31MAR12* 40 0 0
PC25010085 2501 Pumps PA-25-01A/B 7 18MAR12 31MAR12 14 0 30
PC25010050 2501 Plate Heat Exchangers GG-25-02/03/05 7 25MAR12 31MAR12 7 0 35
PC25010090 2501 Piping Systems: Blowing & Reinst 32 20JUL11A 07APR12 74 30 14
PC25010110 2501 Instrumentation 21 09SEP11A 21APR12 88 1 14
PC2501ASMC 2501 Sub System MC - 2501 [Partial] 0 21APR12 0 0 14
TO BE CONFIRMED
PC25010080 2501 Turbo Expander/Recompressor Packages 21 25MAR12 01MAY12* 38 0 0
TO BE CONFIRMED
PC25010103 2501 Electrical (Cables) 8 01APR12 08MAY12 38 0 31
TO BE CONFIRMED
PC25010083 2501 Automatic Magnetic Bearing Panels ED-25-04A/B 7 08APR12 15MAY12 38 0 24
TO BE CONFIRMED
PC25010093 2501 Instrumentation UK-25-04 A/B 8 08APR12 15MAY12 38 0 24
TO BE CONFIRMED
PC2501BSMC 2501 Sub System MC - 2501 [Final] 0 15MAY12 0 0 24
COMMISSIONING
CN25010030 2501 MV Ele Motors (2) no load test 3 27MAR12 31MAR12 5 0 31
CN25010050 2501 Pumps: final allignement and coupling 4 01APR12 04APR12 4 0 30
CN250ARFSU 2501 Sub System RFSU - 2501 [Partial] 0 04APR12 0 0 30
TO BE CONFIRMED
CN25010070 2501 Turbo Expander/Recompressor Train1 13 22APR12 04MAY12 13 0 48
CN25010020 2501 Loop Checks & Functional Test 35 26DEC11A 15MAY12 112 3 30
TO BE CONFIRMED
CN25010080 2501 Turbo Expander/Recompressor Train2 13 16MAY12 28MAY12 13 0 24
TO BE CONFIRMED
CN2501RFSU 2501 Sub System RFSU - 2501 [Final] 0 28MAY12 0 0 24
27 - Gas Handling
2701 - Gas Compression and Metering
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO27010090 2701 Piping & Supports erection 72 28OCT10A 29FEB12 36 98 -6
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 3 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
28 - Gas Sweetening
2801 - Gas Sweetening
Step 2: Gas in Plant
CONSTRUCTION
CO28010050 2801 Instrument Cable Laying [Secondary] 68 22SEP11A 29FEB12 36 93 41
CO28010090 2801 Piping & Support Erection 83 21OCT10A 03MAR12 39 97 17
CO28010040 2801 Electrical Cable Laying 47 20JUL11A 03MAR12 39 99 54
CO28010100 2801 Equipment Installation [Pupms] 75 06APR11A 10MAR12 46 100 56
CO28010030 2801 Electrucal Cable Connection 40 16NOV11A 10MAR12 46 96 54
CO28010110 2801 Piping Hydrotest 1 06JUL11A 17MAR12 53 37 17
CO28010140 2801 Instrument Cabinet installation 1 13APR11A 24MAR12 60 95 17
CO28010080 2801 Field Instrument Installation 30 01OCT11A 24MAR12 60 65 17
CO28010130 2801 Painting works 1 21OCT10A 28APR12 95 82 33
CO28010120 2801 Insulation works 1 15JUN11A 12MAY12 109 37 33
PRE-COMMISSIONING
PC28010080 2801 Electrical (Cables, Motors) 14 08OCT11A 12MAR12 48 10 54
PC28010011 2801 Columns CA-28-01; CE-28-01 14 12NOV11A 17MAR12 53 35 45
PC28010010 2801 Incinerator Package UF-28-01 21 24DEC11A 17MAR12 53 50 26
PC28010030 2801 Pressure Vessels VN-28-01; VD-28-02/03/04/05 20 27FEB12 17MAR12 20 0 49
PC28010060 2801 Filters MB-28-01/02/03/04 15 03MAR12 17MAR12 15 0 49
PC28010050 2801 Pumps; PA-28-01A/B; 2A/B; 3A/B; 4A/B; 5A/B; 6A/B 14 04MAR12 17MAR12 14 0 49
PC28010032 2801 Pressure Vessel VA-28-01; VD-28-01 10 08MAR12 17MAR12 10 0 49
PC28010034 2801 Reboiler GA-28-01 6 12MAR12 17MAR12 6 0 45
PC28010042 2801 Air Cooler Exchangers GC-28-01/02 4 14MAR12 17MAR12 4 0 49
PC28010040 2801 Plate Heat Exchanger GB-28-01 4 18MAR12 21MAR12 4 0 45
PC28010090 2801 Instrumentation 21 09SEP11A 26MAR12 62 0 17
PC28010070 2801 Piping Systems: Blowing/Drying & Reinst 92 26JUL11A 07APR12 74 48 28
PC28010SMC 2801 Sub System MC - 2801 0 07APR12 0 0 28
COMMISSIONING
CN28010030 2801 MV Ele Motors (2) no load test 4 18MAR12 21MAR12 4 0 61
CN28010040 2801 LV Ele Motors (10) no load test 7 18MAR12 24MAR12 7 0 79
CN28010050 2801 Air Cooler Fans (6) Load test 7 18MAR12 24MAR12 7 0 82
CN28010070 2801 Incinerator Package Commissioning 21 18MAR12 07APR12 21 0 68
CN28010060 2801 Pumps: final allignement and coupling 21 25MAR12 14APR12 21 0 58
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 4 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 5 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
33 - LPG Handling
3301 - LPG Storage, Pumping & Metering
Step 2: Gas in Plant
CONSTRUCTION
CO33010090 3301 Piping & Supports Erection 139 16FEB11A 17MAR12 53 84 2
CO33010070 3301 Equipment Installation 88 09MAR11A 17MAR12 53 98 2
CO33010040 3301 Electrcal Cable Laying 123 06APR11A 17MAR12 53 98 33
CO33010100 3301 Sheds, Roofing/Cladding 139 01JUL11A 17MAR12 53 5 49
CO33010030 3301 Electrical Cable Connections 128 27JUL11A 24MAR12 60 35 31
CO33010060 3301 Electrical equipments (LMCS) 14 11MAR12 24MAR12 14 0 38
CO33010110 3301 Piping Hydrotest 1 24AUG11A 31MAR12 67 20 2
CO33010080 3301 Field Instrument Installation 52 01SEP11A 21APR12 88 47 14
CO33010050 3301 Instrument Cable Laying [Secondary] 105 28SEP11A 21APR12 88 55 14
CO33010120 3301 Painting works 1 16FEB11A 11MAY12 108 78 36
CO33010130 3301 Inslation works 1 14APR12 18MAY12 35 0 36
PRE-COMMISSIONING
PC33010080 3301 Piping Systems: Blowing/Drying & Reinst 72 25AUG11A 14APR12 81 10 2
PC33010010 3301 Storage Spheres RD-33-01A; RD-33-02 16 30MAR12 14APR12 16 0 2
PC33010099 3301 Instrumentation 21 09SEP11A 21APR12 88 1 14
PC33010090 3301 Electrical (Cables, Motors) 14 08OCT11A 21APR12 88 20 10
PC33010030 3301 Pumps PA-33-02A/B/C; PA-33-03A/B 10 15APR12 28APR12 14 0 7
PC33010040 3301 Fiscal Metering Package UJ-33-01 15 15APR12 28APR12 14 0 28
PC33010SMC 3301 Sub-System MC - 3301 0 28APR12 0 0 7
COMMISSIONING
CN33010130 3301 Loop Checks & Functional Test 22 26DEC11A 21APR12 88 1 63
CN33010142 3301 Air Blowers (7) load Test 3 22APR12 24APR12 3 0 10
CN33010120 3301 Piping Systems: leak test 17 15APR12 28APR12 14 0 40
CN33010141 3301 LV Ele Motors (2) no load test 3 29APR12 01MAY12 3 0 39
CN33010140 3301 MV Ele Motors (3) no load test 4 29APR12 02MAY12 4 0 45
CN33010170 3301 Piping Systems: Inerting 16 29APR12 14MAY12 16 0 40
CN33010160 3301 Pumps: final allignement and coupling 21 02MAY12 15MAY12 14 0 39
CN33010190 3301 Fiscal Metering Package Commissioning 31 29APR12 26MAY12 28 0 28
CN3301RFSU 3301 Sub-System RFSU - 3301 0 26MAY12 0 0 28
35 - Condensate Handling
3501 - Condensate Storage, Pumping & Metering
Step 2: Gas in Plant
CONSTRUCTION
CO35010090 3501 Piping & Supports Erection 139 23FEB11A 31MAR12 67 83 14
CO35010060 3501 Equipment Installation 88 09MAR11A 31MAR12 67 97 14
CO35010050 3501 Instrument Cable Laying [Secondary] 128 28SEP11A 31MAR12 67 45 70
CO35010040 3501 Electrical Cable Laying 123 08JUN11A 07APR12 74 88 23
CO35010070 3501 Steel Structures & Shelters 139 14JUL11A 07APR12 74 96 63
CO35010075 3501 Shelter Sheeds & Roofing/Cladding 1 14JUL11A 07APR12 74 5 63
CO35010030 3501 Electrical Cable Connections 128 27JUL11A 12APR12 79 40 23
CO35010100 3501 Electrical equipments install. [LMCS] 21 23MAR12 12APR12 21 0 23
CO35010095 3501 Piping Hydrotest 139 20JUL11A 14APR12 81 23 14
CO35010080 3501 Field Instrument Installation 52 01SEP11A 25APR12 92 44 59
CO35010110 3501 Painting works 1 08MAR11A 08JUN12 136 88 15
PRE-COMMISSIONING
PC35010040 3501 Piping Systems: Blowing/Drying & Reinst 62 25AUG11A 14APR12 81 25 14
PC35010060 3501 Instrumentation 31 09SEP11A 14APR12 81 1 56
PC35010050 3501 Electrical (Cables, Motors) 30 08OCT11A 14APR12 81 20 21
PC35010010 3501 Storage Tanks RA-35-01A/B; RL-35-02 21 01APR12* 21APR12 21 0 14
PC35010020 3501 Pumps PA-35-01A/B; 02A/B; 03A/B 7 15APR12 21APR12 7 0 14
PC35010030 3501 Fiscal Metering Package UJ-35-01 14 15APR12 28APR12 14 0 35
PC35010012 3501 Condensate Degassing Boot VD-35-01 14 22APR12 05MAY12 14 0 35
PC35010SMC 3501 Sub-System MC - 3501 0 05MAY12 0 0 35
COMMISSIONING
CN35010140 3501 MV Ele Motors (2) no load test 4 22APR12 25APR12 4 0 14
CN35010142 3501 LV Ele Motors (4) no load test 4 22APR12 25APR12 4 0 19
CN35010130 3501 Loop Checks & Functional Test 21 26DEC11A 28APR12 95 1 56
CN35010160 3501 Pumps: final allignement and coupling 15 01MAY12 15MAY12 15 0 14
CN35010190 3501 Fiscal Metering Package Commissioning 21 29APR12 19MAY12 21 0 134
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 6 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
41 - Heating System
4101 - Hot Oil Storage
Step 2: Gas in Plant
CONSTRUCTION
CO41010095 4101 Piping & Supports Erection 129 29DEC10A 03MAR12 39 96 2
CO41010060 4101 Equipment Installations 98 27JAN11A 03MAR12 39 97 2
CO41010040 4101 Electrical Cable Laying 20 18JUN11A 03MAR12 39 97 40
CO41010090 4101 Shelter Sheds covering & Roofing/Cladding 28 28JAN12* 03MAR12 36 6 49
CO41010030 4101 Electrical Cable Connection 20 17SEP11A 10MAR12 46 55 40
CO41010105 4101 Piping Hydrotest 1 16MAR11A 17MAR12 53 23 2
CO41010050 4101 Instrument Cable Laying [Secondary] 61 24SEP11A 24MAR12 60 66 9
CO41010110 4101 Painting works 1 05FEB11A 31MAR12 67 76 14
CO41010070 4101 Instrument cabinets installation 20 16APR11A 31MAR12 67 82 14
CO41010080 4101 Field Instrument Installation 40 26MAR11A 07APR12 74 31 2
CO41010100 4101 Analyzer & Accessories install. 1 24SEP11A 07APR12 74 9 7
CO41010120 4101 Insulation works 1 15JUN11A 14APR12 81 48 7
PRE-COMMISSIONING
PC41010010 4101 Hot Oil Storage Tank VN-41-02 7 04MAR12 10MAR12 7 0 25
PC41010020 4101 Drum VD-41-01 7 04MAR12 10MAR12 7 0 17
PC41010100 4101 Electrical (Cables, Motors, Heaters) 14 04MAR12 17MAR12 14 0 33
PC41010098 4101 Pupms PA-41-02, PA-41-03 7 11MAR12 17MAR12 7 0 17
PC41010090 4101 Piping Systems: Blowing/Drying & Reinst 144 26JUL11A 31MAR12 67 25 2
PC41010110 4101 Instrumentation 21 09SEP11A 31MAR12 67 1 21
PC41010SMC 4101 Sub System MC - 4101 0 31MAR12 0 0 21
COMMISSIONING
CN41010040 4101 LV Ele Motors (2) no load test 2 16MAR12 17MAR12 2 0 33
CN41010050 4101 Pumps: final allignement and coupling 2 18MAR12 19MAR12 2 0 33
CN41010070 4101 Drying Heaters 10 18MAR12 27MAR12 10 0 25
CN41010010 4101 Piping Systems: leak test (51) 7 01APR12 07APR12 7 0 10
CN41010060 4101 Piping Systems: Inerting 4 08APR12 11APR12 4 0 10
CN41010020 4101 Loop Checks & Functional Test 14 25MAR12 14APR12 21 0 7
CN4101RFSU 4101 Sub System RFSU -4101 0 14APR12 0 0 7
Sheet 7 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
4301 - HP Flare
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC43010098 4301 Piping Systems: Blowing & Reinst 30 28JUL11A 17MAR12 53 55 -2
PC43010010 4301 KO Drums VD-43-02 14 24SEP11A 17MAR12 53 40 28
PC43010083 4301 Flare Packages UF-43-02 21 26FEB12 17MAR12 21 0 7
COMMISSIONING
CN43010100 4301 Flare Package Commissioning 7 11MAR12 17MAR12 7 0 28
CN43010010 4301 Piping Systems: leak test 14 18MAR12 31MAR12 14 0 11
CN43010060 4301 Piping Systems: Inerting 3 01APR12 03APR12 3 0 11
Step 2: Gas in Plant
PRE-COMMISSIONING
PC43010110 4301 Instrumentation 14 09SEP11A 17MAR12 53 1 5
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 8 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
4303 - LP Flare
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC43030310 4303 KO Drums VD-43-01 14 01JUN11A 17MAR12 53 60 28
PC43030360 4303 Piping Systems: Blowing & Reinst 54 22JUN11A 17MAR12 53 60 5
PC43030380 4303 Instrumentation 22 09SEP11A 17MAR12 53 1 5
PC43030330 4303 Flare Packages UF-43-01 21 26FEB12 17MAR12 21 0 21
PC43030350 4303 Flare Blowers KF-43-01A/B 14 04MAR12 17MAR12 14 0 25
PC43030370 4303 Electrical (Cables, Motors, Heaters) 22 17SEP11A 31MAR12 67 85 8
PC43030340 4303 Pumps PA-43-01A/B 14 17DEC11A 31MAR12 67 20 8
PC43030320 4303 Filter MA-43-01A/B 7 25MAR12 31MAR12 7 0 14
PC43030SMC 4303 Sub System MC - 4303 0 31MAR12 0 0 14
COMMISSIONING
CN43030350 4303 Flare Blowers (no. 2) load test 3 18MAR12 20MAR12 3 0 25
CN43030320 4303 Loop Checks & Functional Test 7 18MAR12 24MAR12 7 0 5
CN43030310 4303 Piping Systems: leak test 14 18MAR12 31MAR12 14 0 11
CN43030330 4303 LV Ele Motors (2) no load test 2 01APR12 02APR12 2 0 8
CN43030360 4303 Piping Systems: Inerting 3 01APR12 03APR12 3 0 11
CN43030340 4303 Pumps: final allignement and coupling 4 03APR12 06APR12 4 0 8
CN43030370 4303 Flare Package Commissioning 15 08APR12 14APR12 7 0 0
CN4303RFSU 4303 Sub System RFSU - 4303 0 14APR12 0 0 0
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 9 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 10 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 11 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 12 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 13 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
62 - Diesel System
Diesel System
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO62000090 6200 Piping Hydrotest 39 16JUL11A 03MAR12 39 47 0
CO62000040 6200 Electrical cable laying 113 10SEP11A 03MAR12 39 91 13
CO62000100 6200 Electrical cable connections 40 09APR11A 17MAR12 53 33 13
CO62000080 6200 Instrument cable laying [Secondary] 113 24SEP11A 17MAR12 53 66 3
CO62000050 6200 Painting Works 10 19MAR11A 24MAR12 60 89 0
CO62000070 6200 Field Instrument installation 68 18JUN11A 24MAR12 60 78 3
CO62000060 6200 Insulation works 28 11MAR12 07APR12 28 0 0
Sheet 14 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 15 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
PC70020040 7002 Fire Alarm Control Panel (FACP) 14 25FEB11A 10MAR11A 0 100
PC70020030 7002 VESDA System 7 04MAR12* 10MAR12 7 0 7
PC70020SMC 7002 Sub-System MC - 7002 0 10MAR12 0 0 7
COMMISSIONING
CN70020010 7002 FACP Commissioning 6 10MAR11A 15MAR11A 0 100
CN70020030 7002 F&G Loop Checks 16 15MAR11A 24MAR11A 0 100
CN70020040 7002 F&G Functional Tests and SAT 10 21MAR11A 24MAR11A 0 100
CN70020050 7002 VESDA System 10 11MAR12 24MAR12 14 0 7
CN7002RFSU 7002 Sub-System RFSU - 7002 0 24MAR12 0 0 7
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 16 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 17 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
77 - HVAC System
HVAC Sub-Systems
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO77000060 7700 Electrical cabel laying 160 05FEB11A 10MAR12 46 94 0
CO77000070 7700 Electrical cable connections 1 22OCT11A 17MAR12 53 82 0
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 18 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 19 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
COMMISSIONING
CN81010030 8101 MV Swichgear EM-81-01-Energization & Tests 2 09APR11A 23DEC11A 0 100
CN81010040 8101 MV Earth.Swgs EY-81-01A/B - Energization & Tests 2 09APR11A 23DEC11A 0 100
CN8101RFSU 8101 Sub System RFSU - 8101 0 24DEC11A 0 100
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 20 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 21 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 22 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
COMMISSIONING
CN82580010 8258 External Lighting System Sat. SS TUCO - Comm 4 15JAN12A 25JAN12A 0 100
CN82580020 8258 Ext. Lighting Sys Sat. SS TUCO - Lux Measurement 8 08APR12 15APR12 8 0 45
CN8258RFSU 8258 Sub-System RFSU - 8258 0 15APR12 0 0 45
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 23 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
COMMISSIONING
CN85020020 8502 CCB - Battery Banks - Commissioning 15 25AUG11A 24SEP11A 0 100
CN85020030 8502 CCB - Distrib. Boards/Panels - Energiz & Tests 15 17SEP11A 24SEP11A 0 100
CN85020010 8502 CCB - Main AC UPS 5C0-EK-85-01 - 15 17SEP11A 25JAN12A 0 100
CN8502RFSU 8502 Sub-System RFSU - 8502 0 25JAN12A 0 100
86 - Telecom System
86CP - Telecomm Subsystems at CPF
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO86000010 8600 Electrical cable laying 1 07MAY11A 03MAR12 39 100 37
CO86000020 8600 Electrical cable connections 1 18MAY11A 10MAR12 46 69 37
CO86000030 8600 Laying of F.O. cables & Tele Cable Address 1 15JAN11A 17MAR12 53 96 37
CO86000050 8600 Batteries install. for Telec, Alarms, Radio link 1 08JUN11A 31MAR12 67 80 25
CO86000040 8600 TETRA Towers @ CPF 1 23MAR11A 14APR12 81 10 25
CO86000080 8600 CCTV System equipment installation 1 15JUN11A 25APR12 92 73 0
CO86000070 8600 Telecomm Equipments installation 1 20APR11A 30APR12 97 70 0
CO86000060 8600 Telecomm Cables connections 1 18AUG11A 30APR12 97 53 0
PRE-COMMISSIONING
PC86110020 8600 CPF - FO Backbone System - Precom. 15 01AUG11A 25NOV11A 0 100
PC86390120 8600 CPF - Hot Line System - Precom. 15 01AUG11A 09DEC11A 0 100
PC86450040 8600 CPF - LAN Core Switch - Precomm. 15 27NOV11A 10DEC11A 0 100
PC86400090 8600 CPF - LAN System - Precom. 15 24SEP11A 03MAR12 39 90 81
PC86260050 8600 CPF - PAGA Buildings System - Precom. 15 01MAR12* 14MAR12 14 0 70
PC86030030 8600 CPF - TETRA (UHF) System - Precom. 15 15APR12 28APR12 14 0 25
PC86280040 8600 CPF - Telephone System (PABX) - Precom. 15 24SEP11A 30APR12 97 50 23
PC86070080 8600 CPF - CCTV Security System - Precom. 15 26APR12 09MAY12 14 0 0
PC86270060 8600 CPF - PAGA Field System - Precom. 15 01MAY12 14MAY12 14 0 0
PC86060070 8600 CPF - CCTV Process System - Precom. 15 10MAY12 23MAY12 14 0 0
PC86100022 8600 CPF - VHF fixed radio System - Precom. 15 15MAY12 28MAY12 14 0 0
PC86CP0SMC 8600 Sub-System MC - 86CP [CPF] 0 28MAY12 0 0 2
COMMISSIONING
CN86450110 8600 CPF - LAN Core Switch - Comm. 14 11DEC11A 24DEC11A 0 100
CN86110020 8600 CPF - FO Backbone/SDH System - Comm. 15 01MAR12* 07MAR12 7 0 84
CN86390100 8600 CPF - Hot Line System - Comm. 15 04MAR12* 10MAR12 7 0 81
CN86400090 8600 CPF - LAN System - Comm. 15 04MAR12 10MAR12 7 0 81
CN86260050 8600 CPF - PAGA Buildings System - Comm. 15 15MAR12 21MAR12 7 0 70
CN86030030 8600 CPF - TETRA (UHF) System - Comm. 15 29APR12 05MAY12 7 0 25
CN86280040 8600 CPF - Telephone System (PABX) - Comm. 15 01MAY12 07MAY12 7 0 23
CN86070080 8600 CPF - CCTV Security System - Comm. 15 10MAY12 16MAY12 7 0 7
CN86270060 8600 CPF - PAGA Field System - Comm. 15 15MAY12 21MAY12 7 0 9
CN86060070 8600 CPF - CCTV Process System - Comm. 15 24MAY12 30MAY12 7 0 0
CN86110030 8600 CPF - VHF fixed radio System - Comm. 14 29MAY12 30MAY12 2 0 0
CN86CPRFSU 8600 Sub-System RFSU - 86CP [CPF] 0 30MAY12 0 0 0
87 - Instrument System
ICSS Sub-Systems
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO87000050 8700 Cable Laying and Connections [Multicables] 88 08JAN11A 29FEB12 36 98 51
CO87000070 8700 Instruments Cabinets installation 1 26FEB11A 29FEB12 36 99 51
CO87000030 8700 ELICS Server Panels & RTU installation 1 19FEB11A 24MAR12 60 95 18
CO87000040 8700 J-Box installation 1 05FEB11A 31MAR12 67 79 34
CO87000060 8700 Electrical connection execution 1 24SEP11A 31MAR12 67 14 34
COMMISSIONING
CNM0000200 8700 ICSS Ready for Loop Check 0 01JAN12A 0 100
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 24 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
Step 3 : Balance
COMMISSIONING
CN87020010 8702 ESD Commiss. and SAT 186 26DEC11A 29JUN12 157 0 2
CN87020020 8702 SubSystem RFSU - 8702 [Fianl] 0 29JUN12 0 0 2
8712 - ELICS
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC87120030 8712 ELICS - Precom. 38 24SEP11A 31MAR12 67 90 18
PC87120040 8712 Sub-System MC - 8712 0 31MAR12 0 0 35
COMMISSIONING
CN87120010 8712 ELICS - Commis. 21 11MAR12 31MAR12 21 0 18
CN87120020 8712 ELICS - SAT 72 01APR12 12MAY12 42 0 18
CN8712RFSU 8712 Sub-System RFSU - 8712 0 12MAY12 0 0 18
88 - Earthing System
88 - Earthing System - CPF
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO88000010 8800 Earthing Systems erection 100 04APR10A 30APR12 97 90 5
20 - OFFPLOT
13 - Wellhead System (production)
1310 - Wellhead MLE-11
Step 2: Gas in Plant
PRE-COMMISSIONING
PC13100050 1310 8" Flowline 7 17SEP11A 24SEP11A 0 100
PC13100020 1310 Piping Systems: Flushing/Blowing/Reinst 10 17SEP11A 23DEC11A 0 100
PC13100030 1310 Electrical 10 08OCT11A 25JAN12A 0 100
PC13100040 1310 Instrumentation 10 07JAN12A 17MAR12 53 20 16
PC13100010 1310 Wellhead Control Panel 115-UW-13-11+Oil Flushing 6 11MAR12 24MAR12 14 0 16
PC13100SMC 1310 Sub System MC - 1310 0 24MAR12 0 0 61
COMMISSIONING
CN13100020 1310 Loop Checks & Functional Test 6 24MAR12 30MAR12 7 0 61
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 25 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
18 - Manifold (production)
1801 - 24" Trunkline M5-CPF
Step 2: Gas in Plant
PRE-COMMISSIONING
PC18010020 1801 24" Trunkline M5-CPF 18 08OCT11A 31MAR12 67 90 35
PC18010SMC 1801 Sub-System MC - 1801 0 31MAR12 0 0 35
COMMISSIONING
CN1801RFSU 1801 Sub-System RFSU - 1801 0 31MAR12 0 0 104
COMMISSIONING
CN81070030 8107 Pump Motor Panel Energization 3 07MAR12 08MAR12 2 0 5
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 26 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
86 - Telecom System
86OP - Telecomm Subsystems - Off Plot
Step 2: Gas in Plant
PRE-COMMISSIONING
PC86150010 86OP Off-Plot - FO Backbone Manifolds&Wells - Precom. 15 02JUL11A 12AUG11A 0 100
PC86250030 86OP Off-Plot - FO Backbone LES 104 - Precomm. 0 17DEC11A 0 100
PC86050031 86OP Off-Plot - M6 - TETRA (UHF) System - Precom. 15 01APR12* 14APR12 14 0 13
PC86250020 86OP Off-Plot - FO Backbone Water Wells - Precom. 15 24SEP11A 28APR12 95 40 6
PC86OP0SMC 86OP Sub-System MC - 86OP [OFF-PLOT] 0 28APR12 0 0 6
COMMISSIONING
CN86150010 86OP Off-Plot - FO Backbone Manifolds & Wells - Comm. 14 04MAR12 10MAR12* 7 0 204
CN86050031 86OP Off-Plot - TETRA (UHF) System - Comm. 16 15APR12 21APR12 7 0 13
CN86250020 86OP Off-Plot - FO Backbone Water Wells - Comm. 16 22APR12 28APR12 7 0 6
CN86OPRFSU 86OP Sub-System RFSU - 86OP [OFF-PLOT] 0 28APR12 0 0 6
87 - Instrument System
8710 - SCADA System Manifold M5 & Wells
Step 2: Gas in Plant
PRE-COMMISSIONING
PC87100040 8710 RTU/PLC - Manifolds & Wells Precom. 45 26JAN12* 10MAR12 45 0 3
PC87100SMC 8710 Sub System MC - 8710 0 10MAR12 0 0 204
COMMISSIONING
CN87100030 8710 RTU/PLC - Manifolds & Wells Commis. 10 22MAR12 28MAR12 7 0 3
CN8710RFSU 8710 Sub System RFSU - 8710 0 28MAR12 0 0 3
88 - Earthing System
8810 - Earthing Off-Plot Manifold M5
Step 2: Gas in Plant
PRE-COMMISSIONING
PC88100010 8810 Earthing System Manifold M5 - Precom. 11 12NOV11A 25NOV11A 0 100
PC88100SMC 8810 Sub-System MC - 8810 0 25NOV11A 0 100
COMMISSIONING
CN8810RFSU 8810 Sub-System RFSU - 8810 0 25NOV11A 0 100
30 - EXPORT PIPELINES
27 - Gas Handling
2702 - Gas Export Pipeline
Step 0 : 30" PL Gas in
PRE-COMMISSIONING
PC27020060 2702 Passive Shelter Installation (7Nos) 31 08JUL11A 24SEP11A 0 100
PC27020070 2702 Water Filiing on each passive Shelter 27 08JUL11A 24SEP11A 0 100
PC27020080 2702 Electrical panels + batteries 29 08JUL11A 24SEP11A 0 100
PC27020090 2702 TLC Panel + RTU 28 08JUL11A 24SEP11A 0 100
PC27020020 2702 30" Export Pipeline drying 27 10JUL11A 02DEC11A 0 100
PC27020030 2702 BVSs (6) - Precom 32 10JUL11A 02DEC11A 0 100
PC27020040 2702 Pig Launching Area @ CPF - Precom 6 27AUG11A 02DEC11A 0 100
PC27020050 2702 Pig Receiving Area @ GT - Precom 6 17SEP11A 02DEC11A 0 100
PC27020100 2702 Pig receiv @GT 6 17SEP11A 02DEC11A 0 100
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 27 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
33 - LPG Handling
3303 - LPG Export Pipeline
Step 3 : Balance
PRE-COMMISSIONING
PC33030030 3303 BVSs (6) - Precom 20 20JUL11A 06JAN12A 0 100
PC33030020 3303 12" Export Pipeline drying 10 20JUL11A 17MAR12 53 95 49
PC33030040 3303 Pig Launching Area @ CPF - Precom 10 27AUG11A 17MAR12 53 95 49
PC33030050 3303 Pig Receiving Area @ GT - Precom 10 17SEP11A 17MAR12 53 95 49
PC33030SMC 3303 Sub-System MC - 3303 0 17MAR12 0 0 49
COMMISSIONING
CN33030160 3303 BVSs (6) - Comm 23 18MAR12 09APR12 23 0 86
CN3330RFSU 3303 Sub-System RFSU - 3303 0 09APR12 0 0 86
86 - Telecom System
86EP - Telecomm - Export Pipelines
Step 2: Gas in Plant
PRE-COMMISSIONING
PC86140050 86EP EPL - FO Backbone P/L CPF - MLN - Precom. 15 20JUL11A 12AUG11A 0 100
PC86120040 86EP EPL - FO Backbone P/L CPF G.T. - Precom. 31 01JUL11A 25NOV11A 0 100
PC86290100 86EP EPL - PABX - P/L CPF - G.T. - Precomm. 31 12NOV11A 25NOV11A 0 100
PC86130010 86EP EPL - FO Backbone P/L CPF - H.B. - Precom. 15 20JUL11A 15MAR12 51 95 69
PC86300020 86EP EPL - PABX - P/L CPF - H.B. - Precom. 15 20JUL11A 15APR12 82 80 38
PC86010070 86EP EPL - UHF TETRA Radio - P/L CPF - G.T. - Precom. 15 16APR12 30APR12* 15 0 23
PC86020030 86EP EPL - UHF TETRA Radio - P/L CPF - H.B. - Precom. 15 01MAY12 15MAY12* 15 0 8
PC86EP0SMC 86EP Sub-System MC - 86EP [EXPORT P/LINES] 0 15MAY12 0 0 15
COMMISSIONING
CN86120040 86EP EPL - FO Backbone P/L CPF G.T. - Comm. 30 26OCT11A 25JAN12A 0 100
CN86140080 86EP EPL - FO Backbone P/L CPF - MLN - Comm. 7 26OCT11A 25JAN12A 0 100
CN86290010 86EP EPL - PABX - P/L CPF - G.T. - Comm. 30 26NOV11A 25JAN12A 0 100
CN86130060 86EP EPL - FO Backbone P/L CPF - H.B. - Comm. 7 16MAR12 22MAR12 7 0 69
CN86300040 86EP EPL - PABX - P/L CPF - H.B. - Comm. 7 16APR12 22APR12 7 0 38
CN86010070 86EP EPL - UHF TETRA Radio - P/L CPF - G.T. - Comm. 7 01MAY12 07MAY12 7 0 23
CN86020030 86EP EPL - UHF TETRA Radio - P/L CPF - H.B. - Comm. 7 16MAY12 22MAY12 7 0 8
CN86EPRFSU 86EP Sub-System RFSU - 86EP [EXPORT P/LINES] 0 22MAY12 0 0 8
87 - Instrument System
8704 - SCADA System For P/L CPF-GT
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC87040020 8704 RTU/PLC - EPL to GT Tie-in (1), BVSs(6) Precom. 31 15JUL11A 02DEC11A 0 100
PC87040SMC 8704 Sub System MC - 8704 0 02DEC11A 0 100
COMMISSIONING
CN87040010 8704 SCADA System - EPL to GT Commis. 7 26SEP11A 31MAR12 67 50 0
CN8704RFSU 8704 Sub System RFSU - 8704 0 31MAR12 0 0 0
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 28 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4
88 - Earthing System
8836- Earthing BVS Export pipeline CPF-GT
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC8836010 8836 Earthing 21 05JUL11A 25JUL11A 0 100
PC88360SMC 8836 Sub-System MC - 8836 0 25JUL11A 0 100
COMMISSIONING
CN8836020 8836 Earthing system BVS RFSU 0 25JUL11A 0 100
60 - COMMISSIONING/ START UP
MLE COMMISSIONING/ START UP
Commissioning/ Start-Up
Step 1A/1B: Up to TK1 Gas Turbine solo Run
COMMISSIONING/ START-UP
SU00000007 COSU 30" Gas P/L Gas-In (50-60 bar) 14 18MAR12* 31MAR12 14 0 0
SU00000010 COSU FG Syst. Gas-in (minimum 40 bar) 14 01APR12* 14APR12 14 0 0
SU00000020 COSU Flares (4) and Blow Down Syst. Start-Up 12 15APR12* 26APR12 12 0 0
SU00000030 COSU Close Drain Syst. & Burning Pit Start-Up 12 20APR12* 01MAY12 12 0 0
SU00000040 COSU Hot Oil Heaters (2) Dry-Out 12 22APR12* 03MAY12 12 0 0
SU00000050 COSU Hot Oil Syst. Start-Up 12 24APR12* 05MAY12 12 0 0
Ready For Start Up
SU00000060 COSU Gas Turbines (3) Solo Run (no load test) 14 24APR12* 07MAY12 14 0 0
Step 2: Gas in Plant
COMMISSIONING/ START-UP
SU00000070 COSU Gas Section - Leak Test with gas (20 bar) 17 05MAY12* 21MAY12 17 0 0
SU00000075 COSU Liquid Section - Leak Test with gas (20 bar) 17 06MAY12* 22MAY12 17 0 0
SU00000160 COSU Start Introduce Wet Gas in CPF 0 31MAY12 0 0 0
SU00000095 COSU Sales Gas Compr.s Trains Start-Up (Load test) 24 18MAY12* 10JUN12 24 0 0
SU00000097 COSU Inlet Process Section - Leak Test (70 bar) 21 23MAY12* 12JUN12 21 0 0
SU00000100 COSU Regeneration System Start-Up 7 08JUN12* 14JUN12 7 0 0
SU00000140 COSU Stabilizer Off Gas Compressor Start-Up 7 10JUN12* 16JUN12 7 0 0
SU00000110 COSU Dehydration System Start-Up 7 15JUN12* 21JUN12 7 0 0
SU00000139 COSU CO2 Removal System Start-Up 7 15JUN12* 21JUN12 7 0 0
SU00000150 COSU Gathering Syst. Start-Up (70 bar) - MLE11(M5) 37 31MAY12* 23JUN12 24 0 0
SU00000120 COSU Start Cooling Down by JT Valve 7 19JUN12* 25JUN12 7 0 0
TO BE CONFIRMED
SU00000130 COSU Turbo Expander Start-Up 7 22JUN12* 28JUN12 7 0 0
SU00000170 COSU Stabilizer Column/Reboiler Start-Up 7 24JUN12* 30JUN12 7 0 0
SU00000135 COSU Dehetanizer Column/Reboiler Start-Up 7 27JUN12* 03JUL12 7 0 0
SU00000138 COSU Process Gas Stable Condition Reached 0 03JUL12 0 0 89
SU00000180 COSU Debutanizer Column/Reboiler Start-Up 7 01JUL12* 07JUL12 7 0 0
SU00000185 COSU First Liquid Production (Off Spec) 0 07JUL12* 0 0 0
SU00000190 COSU Reach Plant On Spec Conditions (25% Turndown) 7 08JUL12* 14JUL12 7 0 0
SU00000210 COSU 30" Gas P/L Filling (Ready for Export) 27 24JUN12* 20JUL12 27 0 0
SU00000220 COSU Increase Feed up to Design Conditions 11 14JUL12* 24JUL12 11 0 0
Step 3 : Balance
COMMISSIONING/ START-UP
SU00000212 COSU 14" Condensate P/L Filling (Ready for Export) 20 27JUN12* 16JUL12 20 0 0
SU00000216 COSU 18" Oil P/L Filling (Ready for Export) 20 27JUN12* 16JUL12 20 0 0
SU00000214 COSU 12" LPG P/L Filling (Ready for Export) 14 05JUL12* 18JUL12 14 0 0
SU00000230 COSU Performance Test (Based on the No. wells avail.) 7 25JUL12* 31JUL12 7 0 0
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013
Sheet 29 of 29