2012 2013

Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

MLE - Systems/SubSystems Schedule


00 - GENERAL
General

MILESTONES
CNM0000060 60kV OHL -MC 0 13JAN11A 0 100
CNM0000080 CPF Ready for First Energization 0 28FEB11A 0 100
GASIN RFGI (Step 1A/1B Up to No load test TK3) 0 31MAR12 0 0 0
MC Ready For Gas In Plant (Step 2) 0 03MAY12 0 0 2
RFSU Ready for Start Up (Start Wet Gas in CPF) 0 31MAY12 0 0 0
PAC Provisional Acceptance Certificate 0 31JUL12 0 0 0
PRE-COMMISSIONING
PC00000000 CPF - PRECOMMISSIONING 594* 13OCT10A 28MAY12 125* 50 12
COMMISSIONING
CN00000000 CPF - COMMISSIONING 467* 01MAR11A 09JUN12 137* 40 14
COMMISSIONING/ START-UP
SU00000000 START-UP With DRY GAS 91* 18MAR12 16JUN12 91* 0 0
SU00000002 START-UP With WET GAS 55* 31MAY12 24JUL12 55* 0 0
SU00000003 PERFORMANCE TEST 7* 25JUL12 31JUL12 7* 0 0

10 - MLE CPF
General

CONSTRUCTION
CO00000070 CPF Mechanical (Hot works) 0 24JAN12* 0 0 250
CO00000050 MLE CPF Roof/Cladding&STeel Structures 188 25JAN12 30JUL12 188 0 62
CO00000010 MLE CPF Civil works 250 25JAN12 30SEP12 250 0 0

20 - Separation
2001 - Separation
Step 2: Gas in Plant
CONSTRUCTION
CO20000060 2001 Electrical Cables laying 20 16FEB11A 25FEB12 32 95 37
CO20000090 2001 Instrument Cable Laying [Secondary] 20 16FEB11A 29FEB12 36 96 37
CO20000070 2001 Electrical Cable Connection 20 02APR11A 29FEB12 36 86 37
Motor Control Station
CO20000080 2001 Electrical Equipments installation 20 10FEB12 29FEB12 20 0 37
CO20000020 2001 Piping & Supports Installation 20 30OCT10A 03MAR12 39 98 0
CO20000030 2001 Piping Hydrotest 20 26MAR11A 17MAR12 53 54 0
CO20000100 2001 Field Instruments installation 20 13NOV11A 17MAR12 53 68 20
CO20000130 2001 Painting works 20 24APR11A 28MAR12 64 90 16
CO20000120 2001 Insulation works 20 12MAR12 31MAR12 20 0 34
PRE-COMMISSIONING
PC20010080 2001 Electrical (Cables, Motors) 5 17SEP11A 08MAR12 44 85 36
PC20010070 2001 Piping Systems: Blowing / Reinst 49 26JUL11A 06APR12 73 55 0
PC20010090 2001 Instrumentation 29 09SEP11A 13APR12 80 1 0
PC20010012 2001 Scrubber VD-20-01 Internal Inspection + Box up 7 07APR12* 13APR12 7 0 0
PC20010020 2001 Air Cooler Exchanger GC-20-01 7 07APR12 13APR12 7 0 0
PC20010014 2001 Pig Receiver VM20-05 Internal Inspection+Box up 2 12APR12 13APR12 2 0 0
PC20010SMC 2001 Sub System MC - 2001 0 13APR12 0 0 0
COMMISSIONING
CN20010040 2001 Air Cooler Fans (8) Run in (Load Test) 7 14APR12 20APR12 7 0 163
CN20010010 2001 Piping Systems: leak test (25) 14 14APR12 27APR12 14 0 0
CN20010020 2001 Loop Checks & Functional Test (68) 14 14APR12 27APR12 14 0 7
CN20010045 2001 Piping Systems: Inerting 7 28APR12 04MAY12 7 0 0
CN2001RSFU 2001 Sub System RFSU - 2001 0 04MAY12 0 0 0

21 - Oil Treatment and Stabilization


2101 - Crude Treatment and Separation
Step 2: Gas in Plant
CONSTRUCTION
CO21010100 2101 Erection of KB-21-01&02A/B 22 05FEB11A 21FEB12 28 98 44
CO21010060 2101 Equipment Erection 57 30OCT10A 29FEB12 36 100 24
CO21010160 2101 Instruments cabinets (UCP) 50 12MAR11A 29FEB12 36 95 52
CO21010040 2101 Electrical Cable Laying 15 17SEP11A 29FEB12 36 87 24
CO21010030 2101 Electrical Cable Connection 15 05NOV11A 29FEB12 36 54 27
Motor Control Station
CO21010110 2101 Electrical equip installation 39 26JAN12 04MAR12 39 16 27
CO21010050 2101 Instrument Cable Laying [Secondary] 98 24SEP11A 07MAR12 43 93 24
CO21010120 2101 Piping & Supports erection 36 13AUG11A 20MAR12 56 98 0
CO21010090 2101 Piping Hydrotest 134 02JUL11A 03APR12 70 42 0
CO21010080 2101 Instrument cable laying 77 02APR11A 08APR12 75 81 13
CO21010150 2101 Painting works 1 24APR11A 10APR12 77 74 21
CO21010140 2101 Insulation works 1 11JUN11A 14APR12 81 52 21

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Run Date 22FEB12 18:27 PCC2 Sheet 1 of 29


Early Bar
SONATRACH / FCP - ALGERIA Date Revision CheckedApproved
Target (MLE) MENZEL LEDJMET EAST PROJECT 20APR11Rev. A - Aouak.M/ Mirko B. A. MoreaG. Proiett
Precommissioning,
Progress Bar 15OCT11Rev. B - A. Morea/ R. BugatA. MoreaG. Proiett
Commissioning and Start-Up Schedule Rev. C
Critical Activity 12FEB12Rev. C - A. Morea/ R. BugaA. MoreaG. Proiett
Primavera Systems, Inc. ***Time Now with COD 25-01-2012***
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

CO21010130 2101 Field Instruments installation 20 26NOV11A 17APR12 84 25 4


PRE-COMMISSIONING
PC21010022 2101 Stab. Offgas Compressors KB-21-01A/B; 02A/B 36 12NOV11A 23FEB12 30 70 44
PC21010018 2101 Air Cooler Exchangers GC-21-03; 04A/B; 07A/B 7 01MAR12 07MAR12 7 0 24
PC21010019 2101 Heat Exchangers GA-21-01; 02A/B/C/D 7 01MAR12 07MAR12 7 0 34
PC21010010 2101 Condensate Stabilizer CB-21-01 10 31DEC11A 19MAR12 55 30 17
PC21010012 2101 Pressure Vessels VA-21-01/07; VG-21-03A/B; 06A/B 7 13MAR12 19MAR12 7 0 22
PC21010014 2101 Coalescer VJ-21-02 7 18MAR12 24MAR12 7 0 17
PC21010016 2101 Filters MA-21-01A/B 7 18MAR12 24MAR12 7 0 17
PC21010030 2101 Electrical (Cables, Motors & Heaters) 7 12NOV11A 31MAR12 67 20 0
PC21010024 2101 Piping Systems: Blowing/Drying & Reinst 90 04JUL11A 10APR12 77 50 0
PC21010040 2101 Instrumentation 21 09SEP11A 21APR12 88 20 0
PC21010SMC 2101 Sub System MC - 2101 0 21APR12 0 0 14
COMMISSIONING
CN21010030 2101 MV Ele Motors (2) no load test 3 01APR12 07APR12 7 0 0
CN21010060 2101 Air Cooler Fans (18) load test 7 01APR12 07APR12 7 0 0
CN21010020 2101 Loop Checks & Functional Test 26 26DEC11A 28APR12 95 2 0
CN21010110 2101 Offgas Compressor Train1 Commissioning 21 08APR12 28APR12 21 0 0
CN21010010 2101 Piping Systems: leak test (97) 18 11APR12 28APR12 18 0 0
CN21010120 2101 Offgas Compressor Train2 Commissioning 21 15APR12 05MAY12 21 0 0
CN21010070 2101 Piping Systems: Inerting 7 29APR12 05MAY12 7 0 0
CN2101RSFU 2101 Sub System RFSU - 2101 0 05MAY12 0 0 0

22 - Oil Handling
2201 - Oil Storage, Pumping & Metering
Step 2: Gas in Plant
CONSTRUCTION
CO22010120 2201 Shelter pumps erection 1 06MAR11A 03MAR12 39 0 35
CO22010040 2201 Electrical Cable laying 7 01NOV11A 31MAR12 67 0 18
CO22010130 2201 Sheds & roofing/Cladding 1 04MAR12 31MAR12 28 0 35
CO22010100 2201 Electrical equipment 7 25MAR12 31MAR12 7 0 25
CO22010030 2201 Electrical Cable Connection and Tests 128 27NOV11A 07APR12 74 0 18
CO22010060 2201 Equipment Installation 88 19JAN11A 14APR12 81 0 0
CO22010090 2201 Piping & Supports Erection 139 19FEB11A 14APR12 81 0 0
CO22010110 2201 Piping Hydrotest 1 04DEC11A 28APR12 95 0 0
CO22010150 2201 Painting works 491 21AUG10A 08MAY12 53 0 15
CO22010080 2201 Instrument Installation 28 15APR12 12MAY12 28 0 35
CO22010160 2201 Insulation works 428 14AUG10A 15MAY12 53 0 15
PRE-COMMISSIONING
PC22010090 2201 Electrical (Cables, Motors) 7 08OCT11A 07APR12 74 20 18
PC22010080 2201 Piping Systems: Blowing & Reinst 51 31JUL11A 14APR12 81 55 0
PC22010010 2201 Storage Tanks RA-22-03A/B; RL-22-04 33 11MAR12 14APR12 35 0 0
PC22010020 2201 Oil Degassing Boot VD-22-01 8 07APR12 14APR12 8 0 0
PC22010099 2201 Instrumentation 15 09SEP11A 21APR12 88 1 11
PC22010030 2201 Pumps PA-22-04A/B; 05A/B; 06A/B 15 07APR12 21APR12 15 0 0
PC22010040 2201 Fiscal Metering Package UJ-22-01 8 15APR12 22APR12 8 0 13
PC22010SMC 2201 Sub-System MC - 2201 0 22APR12 0 0 13
COMMISSIONING
CN22010140 2201 MV Ele Motors (4) no load test 4 22APR12 25APR12 4 0 33
CN22010150 2201 LV Ele Motors (2) no load test 2 26APR12 27APR12 2 0 33
CN22010130 2201 Loop Checks & Functional Test 20 26DEC11A 28APR12 95 1 21
CN22010190 2201 Fiscal Metering Package Commissioning 7 23APR12 29APR12 7 0 154
CN22010160 2201 Pumps: final allignement and coupling 14 22APR12 05MAY12 14 0 0
CN22010120 2201 Piping Systems: leak test 14 06MAY12 19MAY12 14 0 0
CN22010155 2201 Piping System: Inerting 10 20MAY12 30MAY12 11 0 0
CN2201RFSU 2201 Sub-System RFSU - 2201 0 30MAY12 0 0 0

2202 - Oil Storage


Step 2: Gas in Plant
PRE-COMMISSIONING
PC22020250 2202 Piping Systems: Blowing & Reinst 7 27AUG11A 19MAY12 116 45 28
PC22020270 2202 Instrumentation 12 09SEP11A 19MAY12 116 1 28
PC22020210 2202 Storage Tanks RA-22-03C; RA-22-05 7 06MAY12 19MAY12 14 0 28
PC22020SMC 2202 Sub-System MC - 2202 0 19MAY12 0 0 42
COMMISSIONING
CN22020210 2202 Piping Systems: leak test 8 20MAY12 02JUN12 14 0 28
CN22020220 2202 Loop Checks & Functional Test 9 20MAY12 02JUN12 14 0 28
CN2202RFSU 2202 Sub-System RFSU - 2202 0 02JUN12 0 0 28

24 - Gas Treatment
2401 - Gas Treatment
Step 2: Gas in Plant
CONSTRUCTION
CO24010090 2401 Piping & Support erection 95 30OCT10A 29FEB12 36 0 196
CO24010050 2401 Electrical Cable Laying 30 16FEB11A 29FEB12 36 0 214
CO24010100 2401 Piping Hydrotest 1 27MAR11A 07MAR12 43 0 196
CO24010120 2401 Final Painting works 1 01NOV10A 14MAR12 50 0 196
CO24010030 2401 Instrument Cable Laying [Secondary] 20 03MAR11A 17MAR12 53 0 19

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 2 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

CO24010080 2401 Field Instrument Installation 38 19FEB12 17MAR12 28 0 41


CO24010040 2401 Electrical Equipments Installation 10 08MAR12 17MAR12 10 0 197
CO24010110 2401 Insulation works 1 10APR11A 18MAR12 54 0 196
PRE-COMMISSIONING
PC24010100 2401 Instrumentation 21 09SEP11A 03MAR12 39 20 62
PC24010080 2401 Piping Systems: Drying & Reinst (70) 52 20JUL11A 10MAR12 46 80 0
PC24010020 2401 Pressure Vessels VK-24-02A/B/C; VA-24-03 14 26FEB12 10MAR12 14 0 7
PC24010030 2401 Coalescer VJ-24-01 7 04MAR12 10MAR12 7 0 7
PC24010040 2401 Filters MA-24-02A/B 7 04MAR12 10MAR12 7 0 7
PC24010070 2401 Regeneration Gas Compressors KA-24-01A/B 21 26FEB12 17MAR12 21 0 0
PC24010050 2401 Air Cooler Exchanger GC-24-02 7 11MAR12 17MAR12 7 0 44
PC24010060 2401 Heat Exchangers GA-24-01A/B/C/D; GA-24-03A/B 7 11MAR12 17MAR12 7 0 0
PC24010090 2401 Electrical (Cables, Motors & Heaters) 7 18MAR12 24MAR12 7 0 19
PC24010SMC 2401 Sub System MC - 2401 0 24MAR12 0 0 41
COMMISSIONING
CN24010020 2401 Loop Checks & Functional Test 24 26DEC11A 24MAR12 60 2 41
CN24010140 2401 MV Ele Motors (2) no load test 4 25MAR12 28MAR12 4 0 19
CN24010160 2401 Air Cooler Fans (6) Load Test 4 25MAR12 28MAR12 4 0 37
CN24010010 2401 Piping Systems: leak test (52) 14 18MAR12 31MAR12 14 0 0
CN24010180 2401 Regeneration Gas Compressor Train1 12 29MAR12 09APR12 12 0 19
CN24010170 2401 Piping Systems: Inerting 14 01APR12 14APR12 14 0 0
CN24010190 2401 Regeneration Gas Compressor Train2 12 04APR12 15APR12 12 0 19
CN24010165 2401 Loading of Molecular Sieve 21 15APR12 04MAY12 20 0 0
CN2401RFSU 2401 Sub System RFSU - 2401 0 04MAY12 0 0 0

25 - Gas Conditioning
2501 - Gas Conditioning
Step 2: Gas in Plant
CONSTRUCTION
CO25010110 2501 Cold Liquid Pumps [PA-25-01 A/B] 57 22MAR11A 25FEB12 32 0 161
Without Lines of UK-25-04 A/B
CO25010090 2501 Piping & Supports Erection 150 30OCT10A 29FEB12 36 0 24
Without Lines of UK-25-04 A/B
CO25010140 2501 Piping Hydrotest 1 24APR11A 21MAR12 57 0 24
CO25010050 2501 Instrument Cable Laying [Secondary] 129 20FEB11A 24MAR12 60 0 190
TO BE CONFIRMED
CO25010060 2501 Equipment Installation [UK-25-04 A/B] 10 24MAR12* 02APR12 10 0 123
Without connectipon to UK-25-04 A/B
CO25010080 2501 Instrument Installation 72 20FEB11A 21APR12 88 0 162
TO BE CONFIRMED
CO25010070 2501 Steel Structure of Shelter [UK-25-04 A/B] 15 03APR12 22APR12 20 0 123
CO25010120 2501 Shelters Roofing/Cladding installation 15 05MAR12 30APR12 57 0 153
CO25010150 2501 Piping & Support erection [UK-25-04A/B] 15 10APR12 30APR12 21 0 123
CO25010160 2501 Piping Hydrotest [UK-25-04A/B] 21 17APR12 07MAY12 21 0 142
TO BE CONFIRMED
CO25010040 2501 Cable Laying [UK-25-04 A/B] 14 26APR12 09MAY12 14 0 142
CO25010170 2501 Electrical Equip [UK-25-04A/B] 5 05MAY12 09MAY12 5 0 144
TO BE CONFIRMED
CO25010030 2501 Cable Connection and Tests [UK-25-04 A/B] 14 28APR12 11MAY12 14 0 142
TO BE CONFIRMED
CO25010130 2501 Instrument Installation after [UK-25-04 A/B] 21 01MAY12 21MAY12 21 0 132
TO BE CONFIRMED
CO25010100 2501 Lighting Shelter [UK-25-04 A/B] 30 01MAY12 30MAY12 30 0 123
CO25010190 2501 Final Painting Works 20 24MAY11A 14JUN12 142 0 108
CO25010180 2501 Insulation Works 20 04SEP11A 21JUN12 149 0 101
PRE-COMMISSIONING
PC25010010 2501 Deethaniser CX-25-01 21 31DEC11A 28FEB12 35 45 53
PC25010020 2501 Pressure Vessels VD-25-02/03/04 7 29FEB12 06MAR12 7 0 53
PC25010060 2501 Reboiler GA-25-04 7 07MAR12 13MAR12 7 0 53
PC25010100 2501 Electrical (Cables, Motors) 7 18MAR12 24MAR12 7 0 42
PC25010095 2501 Hydrojetting Drying/Inerting leak test 30 21FEB12 31MAR12* 40 0 0
PC25010085 2501 Pumps PA-25-01A/B 7 18MAR12 31MAR12 14 0 30
PC25010050 2501 Plate Heat Exchangers GG-25-02/03/05 7 25MAR12 31MAR12 7 0 35
PC25010090 2501 Piping Systems: Blowing & Reinst 32 20JUL11A 07APR12 74 30 14
PC25010110 2501 Instrumentation 21 09SEP11A 21APR12 88 1 14
PC2501ASMC 2501 Sub System MC - 2501 [Partial] 0 21APR12 0 0 14
TO BE CONFIRMED
PC25010080 2501 Turbo Expander/Recompressor Packages 21 25MAR12 01MAY12* 38 0 0
TO BE CONFIRMED
PC25010103 2501 Electrical (Cables) 8 01APR12 08MAY12 38 0 31
TO BE CONFIRMED
PC25010083 2501 Automatic Magnetic Bearing Panels ED-25-04A/B 7 08APR12 15MAY12 38 0 24
TO BE CONFIRMED
PC25010093 2501 Instrumentation UK-25-04 A/B 8 08APR12 15MAY12 38 0 24
TO BE CONFIRMED
PC2501BSMC 2501 Sub System MC - 2501 [Final] 0 15MAY12 0 0 24
COMMISSIONING
CN25010030 2501 MV Ele Motors (2) no load test 3 27MAR12 31MAR12 5 0 31
CN25010050 2501 Pumps: final allignement and coupling 4 01APR12 04APR12 4 0 30
CN250ARFSU 2501 Sub System RFSU - 2501 [Partial] 0 04APR12 0 0 30
TO BE CONFIRMED
CN25010070 2501 Turbo Expander/Recompressor Train1 13 22APR12 04MAY12 13 0 48
CN25010020 2501 Loop Checks & Functional Test 35 26DEC11A 15MAY12 112 3 30
TO BE CONFIRMED
CN25010080 2501 Turbo Expander/Recompressor Train2 13 16MAY12 28MAY12 13 0 24
TO BE CONFIRMED
CN2501RFSU 2501 Sub System RFSU - 2501 [Final] 0 28MAY12 0 0 24

27 - Gas Handling
2701 - Gas Compression and Metering
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO27010090 2701 Piping & Supports erection 72 28OCT10A 29FEB12 36 98 -6

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 3 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

CO27010170 2701 Electrical Cable connection 1 30MAR11A 29FEB12 36 100 62


CO27010180 2701 Electrcal Equipment Installation 1 01JUL11A 29FEB12 36 100 62
CO27010040 2701 Instrument Cable Laying [Secondary] 10 16FEB11A 03MAR12 39 100 59
CO27010070 2701 Sales Gas Compressor Pack. Train1 0 03MAR12* 0 0 16
CO27010130 2701 Piping Hydrotest 72 15JUN11A 14MAR12 50 28 -6
CO27010140 2701 Metering Skid 1 08MAR11A 17MAR12 53 85 17
CO27010080 2701 Field Instrument Installation 91 30MAR11A 31MAR12 67 17 -9
CO27010160 2701 Painting works 1 28OCT10A 21APR12 88 71 19
CO27010150 2701 Insulation works 1 15JUN11A 30APR12 97 36 17
PRE-COMMISSIONING
PC27010020 2701 Air Cooler Exchangers GC-27-01A/B/C; 02A/B/C 18 01JUL11A 29FEB12 36 95 66
PC27010060 2701 Electrical (Cables, Motors, Heaters) 10 17SEP11A 04MAR12 40 85 62
PC27010050 2701 Piping Systems: Blowing/Drying & Reinst 91 01JUN11A 21MAR12 57 53 2
PC27010011 2701 Pressure Vessels VG-27-01A/B/C; VG-27-02A/B/C 14 05NOV11A 24MAR12 60 80 42
PC27010070 2701 Instrumentation 10 09SEP11A 04APR12 71 60 31
PC27010030 2701 Sales Gas Compressor Package Train1 45 14JUL11A 12APR12 79 90 4
PC2701ASMC 2701 Sub System MC - 2701 [Partial - 1st TK] 0 12APR12 0 0 23
COMMISSIONING
CN27010055 2701 Air Cooler Fans (24) Load Test 14 26JUL11A 10MAR12 46 80 68
CN27010010 2701 Piping Systems: Tightness test (90) 7 25MAR12 31MAR12 7 0 43
CN27010050 2701 Piping Systems: Inerting 4 01APR12 04APR12 4 0 43
CN27010020 2701 Loop Checks & Functional Test 20 31JUL11A 11APR12 78 30 36
CN27010060 2701 Sales Gas Compressor Package Train1 Commis. 30 17SEP11A 19APR12 86 35 4
Step 2: Gas in Plant
CONSTRUCTION
CO27010100 2701 Sales Gas Compressor Pack. Train3 0 07APR12* 0 0 20
CO27010110 2701 Sales Gas Compressor Pack. Train2 0 28APR12* 0 0 5
PRE-COMMISSIONING
PC27010040 2701 Fiscal Metering Package UJ-27-01 14 22MAR12 04APR12 14 0 13
PC27010034 2701 Sales Gas Compressor Package Train3 33 08OCT11A 12APR12 79 80 15
PC27010042 2701 Piping Systems: Blowing/Drying & Reinst 30 22MAR12 18APR12 28 0 2
PC27010032 2701 Sales Gas Compressor Package Train2 45 07JAN12A 03MAY12 100 14 2
PC27010SMC 2701 Sub System MC - 2701 [Final] 0 03MAY12 0 0 2
COMMISSIONING
CN27010090 2701 Sales Gas Compressor Package Train3 Commis. 26 26OCT11A 19APR12 86 30 15
CN27010110 2701 Piping Systems: Tightness test (90) 7 19APR12 02MAY12 14 0 2
CN27010100 2701 Fiscal Metering Package Commissioning 30 05APR12 04MAY12 30 0 13
CN27010115 2701 Loop Checks & Functional Test 20 05APR12 04MAY12 30 0 13
CN27010080 2701 Sales Gas Compressor Package Train2 Commis. 23 18APR12 10MAY12 23 0 5
CN27010120 2701 Piping Systems: Inerting 4 03MAY12 15MAY12 13 0 2
CN2701RFSU 2701 Sub System RFSU - 2701[Final] 0 15MAY12 0 0 2

28 - Gas Sweetening
2801 - Gas Sweetening
Step 2: Gas in Plant
CONSTRUCTION
CO28010050 2801 Instrument Cable Laying [Secondary] 68 22SEP11A 29FEB12 36 93 41
CO28010090 2801 Piping & Support Erection 83 21OCT10A 03MAR12 39 97 17
CO28010040 2801 Electrical Cable Laying 47 20JUL11A 03MAR12 39 99 54
CO28010100 2801 Equipment Installation [Pupms] 75 06APR11A 10MAR12 46 100 56
CO28010030 2801 Electrucal Cable Connection 40 16NOV11A 10MAR12 46 96 54
CO28010110 2801 Piping Hydrotest 1 06JUL11A 17MAR12 53 37 17
CO28010140 2801 Instrument Cabinet installation 1 13APR11A 24MAR12 60 95 17
CO28010080 2801 Field Instrument Installation 30 01OCT11A 24MAR12 60 65 17
CO28010130 2801 Painting works 1 21OCT10A 28APR12 95 82 33
CO28010120 2801 Insulation works 1 15JUN11A 12MAY12 109 37 33
PRE-COMMISSIONING
PC28010080 2801 Electrical (Cables, Motors) 14 08OCT11A 12MAR12 48 10 54
PC28010011 2801 Columns CA-28-01; CE-28-01 14 12NOV11A 17MAR12 53 35 45
PC28010010 2801 Incinerator Package UF-28-01 21 24DEC11A 17MAR12 53 50 26
PC28010030 2801 Pressure Vessels VN-28-01; VD-28-02/03/04/05 20 27FEB12 17MAR12 20 0 49
PC28010060 2801 Filters MB-28-01/02/03/04 15 03MAR12 17MAR12 15 0 49
PC28010050 2801 Pumps; PA-28-01A/B; 2A/B; 3A/B; 4A/B; 5A/B; 6A/B 14 04MAR12 17MAR12 14 0 49
PC28010032 2801 Pressure Vessel VA-28-01; VD-28-01 10 08MAR12 17MAR12 10 0 49
PC28010034 2801 Reboiler GA-28-01 6 12MAR12 17MAR12 6 0 45
PC28010042 2801 Air Cooler Exchangers GC-28-01/02 4 14MAR12 17MAR12 4 0 49
PC28010040 2801 Plate Heat Exchanger GB-28-01 4 18MAR12 21MAR12 4 0 45
PC28010090 2801 Instrumentation 21 09SEP11A 26MAR12 62 0 17
PC28010070 2801 Piping Systems: Blowing/Drying & Reinst 92 26JUL11A 07APR12 74 48 28
PC28010SMC 2801 Sub System MC - 2801 0 07APR12 0 0 28
COMMISSIONING
CN28010030 2801 MV Ele Motors (2) no load test 4 18MAR12 21MAR12 4 0 61
CN28010040 2801 LV Ele Motors (10) no load test 7 18MAR12 24MAR12 7 0 79
CN28010050 2801 Air Cooler Fans (6) Load test 7 18MAR12 24MAR12 7 0 82
CN28010070 2801 Incinerator Package Commissioning 21 18MAR12 07APR12 21 0 68
CN28010060 2801 Pumps: final allignement and coupling 21 25MAR12 14APR12 21 0 58
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 4 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

CN28010020 2801 Loop Checks & Functional Test 21 27MAR12 16APR12 21 0 17


CN28010100 2801 Piping Systems: Tightness test (96) 14 08APR12 21APR12 14 0 54
CN28010110 2801 Amine Circuits Degreasing+Packing looding 33 27MAR12 25APR12 30 0 17
CN28010120 2801 Piping Systems: Inerting 18 26APR12 13MAY12 18 0 17
CN28010115 2801 System Filling and Circulation with Amine 15 14MAY12 28MAY12 15 0 17
CN2801RFSU 2801 Sub System RFSU - 2801 0 28MAY12 0 0 17

30 - Mercury and H2S Removal


3001 - Mercury and H2S Removal
Step 2: Gas in Plant
CONSTRUCTION
CO30010090 3001 Piping & Support Erection 144 10FEB11A 03MAR12 39 90 0
CO30010100 3001 Piping Hydrotest 1 18AUG11A 24MAR12 60 31 0
CO30010050 3001 Instrument Cable Laying [Secondary] 30 22SEP11A 14APR12 81 65 20
CO30010080 3001 Field Instrument Installation 39 26OCT11A 14APR12 81 35 20
CO30010120 3001 Painting works 1 25MAY11A 23APR12 90 66 4
CO30010110 3001 Insulation works 1 15JUN11A 03MAY12 100 41 1
PRE-COMMISSIONING
PC30010022 3001 H2S Removal Pressure Vessels MB-30-02A/B 14 09MAR12 22MAR12 14 0 9
PC30010020 3001 Mercury Guard Pressure Vessel MB-30-01 7 16MAR12 22MAR12 7 0 9
PC30010050 3001 Filters MA-30-03A/B 7 16MAR12 22MAR12 7 0 9
PC30010060 3001 Coalescer VJ-30-01 7 16MAR12 22MAR12 7 0 9
PC30010090 3001 Piping Systems: Blowing/Drying & Reinst 77 30MAY11A 07APR12 74 28 0
PC30010110 3001 Instrumentation 32 09SEP11A 14APR12 81 1 20
PC30010SMC 3001 Sub System MC - 3001 0 14APR12 0 0 20
COMMISSIONING
CN30010010 3001 Piping Systems: leak test (33) 7 01APR12 07APR12 7 0 0
CN30010020 3001 Loop Checks & Functional Test 10 05APR12 14APR12 10 0 20
CN30010070 3001 Loading of Mercury Guard (Gas) Bed 10 08APR12 17APR12 10 0 0
CN30010080 3001 Loading of H2S Removal Beds 14 18APR12 01MAY12 14 0 0
CN30010060 3001 Piping Systems: Inerting 3 02MAY12 04MAY12 3 0 0
CN3001RFSU 3001 Sub System RFSU - 3001 0 04MAY12 0 0 0

32 - Debutanizer/LPG Treatment & Condens. Recov.


3201 - Debutanizer/LPG Treatment & Condens Recov
Step 2: Gas in Plant
CONSTRUCTION
CO32010090 3201 Piping & Supports Erection 149 19JAN11A 03MAR12 39 88 0
CO32010040 3201 Electrical Cable laying 20 21SEP11A 10MAR12 46 94 12
PA-32-01A/B; PA-32-02A/B
CO32010070 3201 Equipment installation 20 23MAR11A 17MAR12 53 82 27
CO32010110 3201 Piping Hydrotest 149 06JUL11A 17MAR12 53 22 0
CO32010100 3201 Electrical equipments (LMCS) 20 12OCT11A 17MAR12 53 36 12
CO32010030 3201 Electrical Cable connections 20 26OCT11A 17MAR12 53 53 12
CO32010080 3201 Field Instrument Installation 30 22JUN11A 07APR12 74 29 23
CO32010050 3201 Instrument Cable Laying [Secondary] 30 22SEP11A 07APR12 74 69 23
CO32010060 3201 Analyzers & Accessories Install. 98 26OCT11A 07APR12 74 27 23
CO32010120 3201 Painting works 1 30MAR11A 28APR12 95 76 1
CO32010130 3201 Insulation works 1 30MAR11A 03MAY12 100 40 1
PRE-COMMISSIONING
PC32010010 3201 Debutanizer CX-32-01 21 31DEC11A 24MAR12 60 30 27
PC32010090 3201 Piping Systems: Blowing/Drying & Reinst 165 30JUL11A 31MAR12 67 40 0
PC32010020 3201 Pressure Vessels VA-32-02; VD-32-01; VD-32-03 7 30MAR12 05APR12 7 0 15
PC32010022 3201 LPG Treating Vessels VK-32-04A/B 7 30MAR12 05APR12 7 0 15
PC32010032 3201 LPG Mercury Guard Vessel MB-32-03 7 30MAR12 05APR12 7 0 15
PC32010042 3201 Air Cooler Exchangers GC-32-01/02/03 7 30MAR12 05APR12 7 0 0
PC32010050 3201 Heat Exchangers GA-32-01/;GA-32-04A/B 7 30MAR12 05APR12 7 0 29
PC32010060 3201 Reboiler GA-32-02 7 30MAR12 05APR12 7 0 29
PC32010110 3201 Instrumentation 21 09SEP11A 07APR12 74 1 23
PC32010087 3201 Pumps PA-32-01A/B; PA-32-02A/B; PA-32-03A/B 21 18MAR12 07APR12 21 0 2
PC32010100 3201 Electrical (Cables, Motors) 14 30MAR12 08APR12 10 0 0
PC32010085 3201 Filters MA-32-01; MA-32-02A/B 7 08APR12 14APR12 7 0 16
PC32010SMC 3201 Sub System MC - 3201 0 14APR12 0 0 20
COMMISSIONING
CN32010042 3201 Air Cooler Fans (26) load Test 7 06APR12 12APR12 7 0 22
CN32010030 3201 MV Ele Motors (2) no load test 4 09APR12 12APR12 4 0 0
CN32010032 3201 LV Ele Motors (4) no load test 3 13APR12 15APR12 3 0 0
CN32010052 3201 Pumps: final allignement and coupling 21 10APR12 16APR12 7 0 0
CN32010020 3201 Loop Checks & Functional Test 28 22MAR12 18APR12 28 0 16
CN32010070 3201 Loading of Molecular Sieves 14 06APR12 19APR12 14 0 15
CN32010080 3201 Loading of Mercury Guard (LPG) Bed 10 10APR12 19APR12 10 0 15
CN32010010 3201 Piping Systems: leak test (76) 17 17APR12 26APR12 10 0 0
CN32010060 3201 Piping Systems: Inerting 26 27APR12 04MAY12 8 0 0
CN3201RFSU 3201 Sub System RFSU - 3201 0 04MAY12 0 0 0

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 5 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

33 - LPG Handling
3301 - LPG Storage, Pumping & Metering
Step 2: Gas in Plant
CONSTRUCTION
CO33010090 3301 Piping & Supports Erection 139 16FEB11A 17MAR12 53 84 2
CO33010070 3301 Equipment Installation 88 09MAR11A 17MAR12 53 98 2
CO33010040 3301 Electrcal Cable Laying 123 06APR11A 17MAR12 53 98 33
CO33010100 3301 Sheds, Roofing/Cladding 139 01JUL11A 17MAR12 53 5 49
CO33010030 3301 Electrical Cable Connections 128 27JUL11A 24MAR12 60 35 31
CO33010060 3301 Electrical equipments (LMCS) 14 11MAR12 24MAR12 14 0 38
CO33010110 3301 Piping Hydrotest 1 24AUG11A 31MAR12 67 20 2
CO33010080 3301 Field Instrument Installation 52 01SEP11A 21APR12 88 47 14
CO33010050 3301 Instrument Cable Laying [Secondary] 105 28SEP11A 21APR12 88 55 14
CO33010120 3301 Painting works 1 16FEB11A 11MAY12 108 78 36
CO33010130 3301 Inslation works 1 14APR12 18MAY12 35 0 36
PRE-COMMISSIONING
PC33010080 3301 Piping Systems: Blowing/Drying & Reinst 72 25AUG11A 14APR12 81 10 2
PC33010010 3301 Storage Spheres RD-33-01A; RD-33-02 16 30MAR12 14APR12 16 0 2
PC33010099 3301 Instrumentation 21 09SEP11A 21APR12 88 1 14
PC33010090 3301 Electrical (Cables, Motors) 14 08OCT11A 21APR12 88 20 10
PC33010030 3301 Pumps PA-33-02A/B/C; PA-33-03A/B 10 15APR12 28APR12 14 0 7
PC33010040 3301 Fiscal Metering Package UJ-33-01 15 15APR12 28APR12 14 0 28
PC33010SMC 3301 Sub-System MC - 3301 0 28APR12 0 0 7
COMMISSIONING
CN33010130 3301 Loop Checks & Functional Test 22 26DEC11A 21APR12 88 1 63
CN33010142 3301 Air Blowers (7) load Test 3 22APR12 24APR12 3 0 10
CN33010120 3301 Piping Systems: leak test 17 15APR12 28APR12 14 0 40
CN33010141 3301 LV Ele Motors (2) no load test 3 29APR12 01MAY12 3 0 39
CN33010140 3301 MV Ele Motors (3) no load test 4 29APR12 02MAY12 4 0 45
CN33010170 3301 Piping Systems: Inerting 16 29APR12 14MAY12 16 0 40
CN33010160 3301 Pumps: final allignement and coupling 21 02MAY12 15MAY12 14 0 39
CN33010190 3301 Fiscal Metering Package Commissioning 31 29APR12 26MAY12 28 0 28
CN3301RFSU 3301 Sub-System RFSU - 3301 0 26MAY12 0 0 28

3302 - LPG Storage


Step 2: Gas in Plant
PRE-COMMISSIONING
PC33020240 3302 Piping Systems: Blowing/Drying & Reinst 31 26NOV11A 28APR12 95 17 34
PC33020210 3302 Storage Spheres RD-33-01B/C 25 15APR12 09MAY12 25 0 2
PC33020260 3302 Instrumentation 21 10MAY12 30MAY12 21 0 2
PC33020SMC 3302 Sub-System MC - 3302 0 30MAY12 0 0 35
COMMISSIONING
CN33020210 3302 Piping Systems: leak test 10 29APR12 19MAY12 21 0 34
CN33020270 3302 Piping Systems: Inerting 12 20MAY12 31MAY12 12 0 34
CN33020230 3302 Loop Checks & Functional Test 30 31MAY12 29JUN12 30 0 2
CN3302RFSU 3302 Sub-System RFSU - 3302 0 29JUN12 0 0 5

35 - Condensate Handling
3501 - Condensate Storage, Pumping & Metering
Step 2: Gas in Plant
CONSTRUCTION
CO35010090 3501 Piping & Supports Erection 139 23FEB11A 31MAR12 67 83 14
CO35010060 3501 Equipment Installation 88 09MAR11A 31MAR12 67 97 14
CO35010050 3501 Instrument Cable Laying [Secondary] 128 28SEP11A 31MAR12 67 45 70
CO35010040 3501 Electrical Cable Laying 123 08JUN11A 07APR12 74 88 23
CO35010070 3501 Steel Structures & Shelters 139 14JUL11A 07APR12 74 96 63
CO35010075 3501 Shelter Sheeds & Roofing/Cladding 1 14JUL11A 07APR12 74 5 63
CO35010030 3501 Electrical Cable Connections 128 27JUL11A 12APR12 79 40 23
CO35010100 3501 Electrical equipments install. [LMCS] 21 23MAR12 12APR12 21 0 23
CO35010095 3501 Piping Hydrotest 139 20JUL11A 14APR12 81 23 14
CO35010080 3501 Field Instrument Installation 52 01SEP11A 25APR12 92 44 59
CO35010110 3501 Painting works 1 08MAR11A 08JUN12 136 88 15
PRE-COMMISSIONING
PC35010040 3501 Piping Systems: Blowing/Drying & Reinst 62 25AUG11A 14APR12 81 25 14
PC35010060 3501 Instrumentation 31 09SEP11A 14APR12 81 1 56
PC35010050 3501 Electrical (Cables, Motors) 30 08OCT11A 14APR12 81 20 21
PC35010010 3501 Storage Tanks RA-35-01A/B; RL-35-02 21 01APR12* 21APR12 21 0 14
PC35010020 3501 Pumps PA-35-01A/B; 02A/B; 03A/B 7 15APR12 21APR12 7 0 14
PC35010030 3501 Fiscal Metering Package UJ-35-01 14 15APR12 28APR12 14 0 35
PC35010012 3501 Condensate Degassing Boot VD-35-01 14 22APR12 05MAY12 14 0 35
PC35010SMC 3501 Sub-System MC - 3501 0 05MAY12 0 0 35
COMMISSIONING
CN35010140 3501 MV Ele Motors (2) no load test 4 22APR12 25APR12 4 0 14
CN35010142 3501 LV Ele Motors (4) no load test 4 22APR12 25APR12 4 0 19
CN35010130 3501 Loop Checks & Functional Test 21 26DEC11A 28APR12 95 1 56
CN35010160 3501 Pumps: final allignement and coupling 15 01MAY12 15MAY12 15 0 14
CN35010190 3501 Fiscal Metering Package Commissioning 21 29APR12 19MAY12 21 0 134

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 6 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

CN35010120 3501 Piping Systems: leak test 11 16MAY12 26MAY12 11 0 14


CN35010170 3501 Piping Systems: Inerting 14 27MAY12 09JUN12 14 0 14
CN3501RFSU 3501 Sub-System RFSU - 3501 0 09JUN12 0 0 14

41 - Heating System
4101 - Hot Oil Storage
Step 2: Gas in Plant
CONSTRUCTION
CO41010095 4101 Piping & Supports Erection 129 29DEC10A 03MAR12 39 96 2
CO41010060 4101 Equipment Installations 98 27JAN11A 03MAR12 39 97 2
CO41010040 4101 Electrical Cable Laying 20 18JUN11A 03MAR12 39 97 40
CO41010090 4101 Shelter Sheds covering & Roofing/Cladding 28 28JAN12* 03MAR12 36 6 49
CO41010030 4101 Electrical Cable Connection 20 17SEP11A 10MAR12 46 55 40
CO41010105 4101 Piping Hydrotest 1 16MAR11A 17MAR12 53 23 2
CO41010050 4101 Instrument Cable Laying [Secondary] 61 24SEP11A 24MAR12 60 66 9
CO41010110 4101 Painting works 1 05FEB11A 31MAR12 67 76 14
CO41010070 4101 Instrument cabinets installation 20 16APR11A 31MAR12 67 82 14
CO41010080 4101 Field Instrument Installation 40 26MAR11A 07APR12 74 31 2
CO41010100 4101 Analyzer & Accessories install. 1 24SEP11A 07APR12 74 9 7
CO41010120 4101 Insulation works 1 15JUN11A 14APR12 81 48 7
PRE-COMMISSIONING
PC41010010 4101 Hot Oil Storage Tank VN-41-02 7 04MAR12 10MAR12 7 0 25
PC41010020 4101 Drum VD-41-01 7 04MAR12 10MAR12 7 0 17
PC41010100 4101 Electrical (Cables, Motors, Heaters) 14 04MAR12 17MAR12 14 0 33
PC41010098 4101 Pupms PA-41-02, PA-41-03 7 11MAR12 17MAR12 7 0 17
PC41010090 4101 Piping Systems: Blowing/Drying & Reinst 144 26JUL11A 31MAR12 67 25 2
PC41010110 4101 Instrumentation 21 09SEP11A 31MAR12 67 1 21
PC41010SMC 4101 Sub System MC - 4101 0 31MAR12 0 0 21
COMMISSIONING
CN41010040 4101 LV Ele Motors (2) no load test 2 16MAR12 17MAR12 2 0 33
CN41010050 4101 Pumps: final allignement and coupling 2 18MAR12 19MAR12 2 0 33
CN41010070 4101 Drying Heaters 10 18MAR12 27MAR12 10 0 25
CN41010010 4101 Piping Systems: leak test (51) 7 01APR12 07APR12 7 0 10
CN41010060 4101 Piping Systems: Inerting 4 08APR12 11APR12 4 0 10
CN41010020 4101 Loop Checks & Functional Test 14 25MAR12 14APR12 21 0 7
CN4101RFSU 4101 Sub System RFSU -4101 0 14APR12 0 0 7

4102 -Hot Oil Collection Network


Step 2: Gas in Plant
PRE-COMMISSIONING
PC41010030 4102 Drum VD-41-03 1 04MAR12 04MAR12 1 0 74
PC41010080 4102 Air Cooler Exchangers GC-41-01/02 7 04MAR12 10MAR12 7 0 39
PC41010050 4102 Hot Oil Heaters FA-41-01/02 30 17FEB12 17MAR12 30 0 25
PC41010083 4102 Waste Heat Recovery Unit GW-41-02A 13 04MAR12 17MAR12 14 0 61
PC41010060 4102 Filter MA-41-01 7 18MAR12 24MAR12 7 0 54
PC41010040 4102 Piping Systems: Blowing/Drying & Reinst 25 07MAR12 31MAR12 25 0 6
PC41010088 4102 Pumps PA-41-01A/B/C/D 14 18MAR12 31MAR12 14 0 17
PC41010086 4102 Waste Heat Recovery Unit GW-41-02C 14 08APR12 21APR12 14 0 26
PC41010084 4102 Waste Heat Recovery Unit GW-41-02B 14 29APR12 12MAY12 14 0 5
PC41020SMC 4102 Sub System MC - 4102 0 12MAY12 0 0 5
COMMISSIONING
CN41010090 4102 Air Cooler Fans (12) Load Test 3 11MAR12 13MAR12 3 0 39
CN41010030 4102 MV Ele Motors (4) no load test 4 01APR12 04APR12 4 0 17
CN41020020 4102 Piping Systems: leak test () 15 24MAR12 07APR12 15 0 6
CN41020010 4102 Piping Systems: Inerting 10 08APR12 17APR12 10 0 6
CN41020030 4102 Loop Checks & Functional Test 14 08APR12 21APR12 14 0 2
With TK Train 1
CN410ARFSU 4102 Sub System RFSU - 4102 [Partial] 0 21APR12 0 0 2
With All TKs Trains
CN410BRFSU 4102 Sub System RFSU - 4102 [Final] 0 12MAY12 0 0 5

42 - Chemical Injection System


4201 - Methanol Injection
Step 2: Gas in Plant
CONSTRUCTION
CO42010090 4201 Piping & Supports Erection 88 04DEC10A 24MAR12 60 79 6
PB-42-01/ RG-42-01/ UZ-42-02-03-04-05
CO42010110 4201 Equipment installations 1 12MAR11A 24MAR12 60 77 8
CO42010040 4201 Electrical Cable Laying 10 16JUL11A 31MAR12 67 40 20
CO42010050 4201 Instrument Cable Laying [Secondary] 25 24SEP11A 31MAR12 67 66 27
CO42010070 4201 Electrical equipment instllations 10 12NOV11A 31MAR12 67 43 27
CO42010100 4201 Piping Hydrotest 1 20AUG11A 07APR12 74 24 6
CO42010030 4201 Electrical Cable Connections 10 22OCT11A 07APR12 74 37 20
CO42010080 4201 Field Instrument Installation 16 18JUN11A 14APR12 81 73 20
CO42010120 4201 Painting works 1 05MAR11A 19APR12 86 78 1
CO42010130 4201 Insulation works 1 11JUN11A 03MAY12 100 86 1
PRE-COMMISSIONING
PC42010110 4201 Instrumentation 7 09SEP11A 24MAR12 60 1 27
PC42010090 4201 Piping Systems: Blowing/Drying & Reinst 26 24DEC11A 07APR12 74 10 6
PC42010010 4201 Methanol Injection Package UZ-42-02 5 03APR12 07APR12 5 0 13
PC42010100 4201 Electrical (Cables, Motors) 7 08APR12 14APR12 7 0 20
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 7 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

PC42010SMC 4201 Sub System MC - 4201 0 14APR12 0 0 20


COMMISSIONING
CN42010010 4201 Piping Systems: leak test (42) 8 08APR12 15APR12 8 0 19
CN42010100 4201 Methanol Injection Package Commissioning 9 08APR12 16APR12 9 0 13
CN42010020 4201 Loop Checks & Functional Test 7 08APR12 21APR12 14 0 13
CN42010110 4201 Methanol First Filling 5 17APR12 21APR12 5 0 13
CN4201RFSU 4201 Sub System RFSU - 4201 0 21APR12 0 0 13

4202 - Corrosion inhibitor Injection


Step 2: Gas in Plant
PRE-COMMISSIONING
PC42020110 4202 Instrumentation 7 09SEP11A 24MAR12 60 1 27
PC42020012 4202 Corrosion Inhibitor Injection Package UZ-42-03 5 03APR12 07APR12 5 0 13
PC42020090 4202 Piping Systems: Blowing/Drying & Reinst 26 20MAR12 14APR12 26 0 6
PC42020100 4202 Electrical (Cables, Motors) 7 08APR12 14APR12 7 0 20
PC42020SMC 4202 Sub System MC - 4202 0 14APR12 0 0 20
COMMISSIONING
CN42020020 4202 Loop Checks & Functional Test 7 08APR12 21APR12 14 0 13
CN42020010 4202 Piping Systems: leak test (42) 8 15APR12 22APR12 8 0 12
CN42020070 4202 Corrosion Inibitor Injection Pack. Commissioning 9 15APR12 23APR12 9 0 6
CN42020120 4202 Corrosion Inhibitor First Filling 5 24APR12 28APR12 5 0 6
CN4202RFSU 4202 Sub System RFSU - 4202 0 28APR12 0 0 6

4203 - Antifoam Injection


Step 2: Gas in Plant
PRE-COMMISSIONING
PC42030110 4203 Instrumentation 7 09SEP11A 07APR12 74 1 13
PC42030014 4203 Antifoam Injection Package UZ-42-04 5 24DEC11A 07APR12 74 50 1
PC42030100 4203 Electrical (Cables, Motors) 7 08APR12 14APR12 7 0 20
PC42030090 4203 Piping Systems: Blowing/Drying & Reinst 26 25MAR12 21APR12 28 0 6
PC42030SMC 4203 Sub System MC - 4203 0 21APR12 0 0 13
COMMISSIONING
CN42030020 4203 Loop Checks & Functional Test 7 08APR12 21APR12 14 0 13
CN42030080 4203 Antifoam Injection Package Commissioning 26 08APR12 28APR12 21 0 1
CN42030010 4203 Piping Systems: leak test (42) 8 22APR12 28APR12 7 0 6
CN42030130 4203 Antifoam First Filling 5 29APR12 03MAY12 5 0 1
CN4203RFSU 4203 Sub System RFSU - 4203 0 03MAY12 0 0 1

4204 - Hypoclorite Injection


Step 2: Gas in Plant
PRE-COMMISSIONING
PC42040110 4204 Instrumentation 7 09SEP11A 07APR12 74 1 13
PC42040016 4204 Hypoclorite Injection Package UZ-42-05 5 01APR12 07APR12 7 0 1
PC42040100 4204 Electrical (Cables, Motors) 7 08APR12 14APR12 7 0 20
PC42040090 4204 Piping Systems: Blowing/Drying & Reinst 26 25MAR12 21APR12 28 0 6
PC42040SMC 4204 Sub System MC - 4204 0 21APR12 0 0 13
COMMISSIONING
CN42040020 4204 Loop Checks & Functional Test 7 08APR12 21APR12 14 0 13
CN42040090 4204 Hypoclorite Injection Package Commissioning 26 08APR12 28APR12 21 0 1
CN42040010 4204 Piping Systems: leak test (42) 8 22APR12 28APR12 7 0 6
CN42040140 4204 Hypoclorite First Filling 5 29APR12 03MAY12 5 0 1
CN4204RFSU 4204 Sub System RFSU - 4204 0 03MAY12 0 0 1

43 - Flare Vent and Blow Down System


Flare Vent and Blow Dowon Sub-Systems
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
Subjet ARH
CO43000070 4300 Piping & Support Erection 62 16OCT10A 03MAR12 39 98 27
PA-43-01/02/03/04 & FE-43-08A/B
CO43000100 4300 Equipment installations 1 08JAN11A 03MAR12 39 95 14
CO43000050 4300 Instrument Cable Laying [Secondary] 96 16APR11A 17MAR12 53 96 -2
CO43000040 4300 Electrical Cable laying 52 28MAY11A 17MAR12 53 92 14
CO43000090 4300 Piping Hydrotest 83 30JUL11A 17MAR12 53 29 -2
CO43000080 4300 Field Instrument Installation 42 26MAR11A 24MAR12 60 35 -2
CO43000120 4300 Electrical equipment installation 1 23JUL11A 24MAR12 60 33 7
CO43000110 4300 Electrical Cable connections 1 01JUN11A 31MAR12 67 69 7
CO43000130 4300 Painting works 1 25JAN10A 07APR12 74 88 13
CO43000140 4300 Insulation works 1 11JUN11A 21APR12 88 4 13

4301 - HP Flare
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC43010098 4301 Piping Systems: Blowing & Reinst 30 28JUL11A 17MAR12 53 55 -2
PC43010010 4301 KO Drums VD-43-02 14 24SEP11A 17MAR12 53 40 28
PC43010083 4301 Flare Packages UF-43-02 21 26FEB12 17MAR12 21 0 7
COMMISSIONING
CN43010100 4301 Flare Package Commissioning 7 11MAR12 17MAR12 7 0 28
CN43010010 4301 Piping Systems: leak test 14 18MAR12 31MAR12 14 0 11
CN43010060 4301 Piping Systems: Inerting 3 01APR12 03APR12 3 0 11
Step 2: Gas in Plant
PRE-COMMISSIONING
PC43010110 4301 Instrumentation 14 09SEP11A 17MAR12 53 1 5

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 8 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

PC43010100 4301 Electrical (Cables, Motors, Heaters) 14 17SEP11A 17MAR12 53 80 15


PC43010088 4301 Pumps PA-43-02A/B 7 17DEC11A 31MAR12 67 20 8
PC43010060 4301 Filter MA-43-02A/B 7 25MAR12 31MAR12 7 0 35
PC43010SMC 4301 Sub System MC - 4301 0 31MAR12 0 0 35
COMMISSIONING
CN43010040 4301 LV Ele Motors (2) no load test 2 01APR12 02APR12 2 0 8
CN43010050 4301 Pumps: final allignement and coupling 4 03APR12 06APR12 4 0 8
CN43010020 4301 Loop Checks & Functional Test 20 18MAR12 07APR12 21 0 7
CN4301RFSU 4301 Sub System RFSU - 4301 0 07APR12 0 0 7

4302 - Cold HP Flare


Step 2: Gas in Plant
PRE-COMMISSIONING
PC43020190 4302 Instrumentation 21 09SEP11A 24MAR12 60 1 20
PC43020170 4302 Piping Systems: Blowing & Reinst 21 25JUL11A 31MAR12 67 63 13
PC43020180 4302 Electrical (Cables, Motors, Heaters) 21 17SEP11A 31MAR12 67 85 21
PC43020120 4302 KO Drums VD-43-03 14 24SEP11A 31MAR12 67 40 30
PC43020150 4302 Pumps PA-43-03A/B 7 17DEC11A 31MAR12 67 20 30
PC43020140 4302 Flare Packages UF-43-03 21 11MAR12 31MAR12 21 0 27
PC43020160 4302 Flar Drums Heaters FE-43-08-A/B 14 18MAR12 31MAR12 14 0 183
PC43020130 4302 Filter MA-43-05A/B 7 25MAR12 31MAR12 7 0 34
PC43020SMC 4302 Sub System MC - 4301 0 31MAR12 0 0 34
COMMISSIONING
CN43020140 4302 LV Ele Motors (2) no load test 2 01APR12 02APR12 2 0 28
CN43020150 4302 Pumps: final allignement and coupling 4 03APR12 06APR12 4 0 28
CN43020170 4302 Flare Package Commissioning 7 07APR12 13APR12 7 0 21
CN43020130 4302 Loop Checks & Functional Test 21 25MAR12 14APR12 21 0 20
CN43020120 4302 Piping Systems: leak test 14 01APR12 14APR12 14 0 13
CN43020160 4302 Piping Systems: Inerting 7 15APR12 21APR12 7 0 13
CN4302RFSU 4302 Sub System RFSU - 4301 0 21APR12 0 0 13

4303 - LP Flare
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC43030310 4303 KO Drums VD-43-01 14 01JUN11A 17MAR12 53 60 28
PC43030360 4303 Piping Systems: Blowing & Reinst 54 22JUN11A 17MAR12 53 60 5
PC43030380 4303 Instrumentation 22 09SEP11A 17MAR12 53 1 5
PC43030330 4303 Flare Packages UF-43-01 21 26FEB12 17MAR12 21 0 21
PC43030350 4303 Flare Blowers KF-43-01A/B 14 04MAR12 17MAR12 14 0 25
PC43030370 4303 Electrical (Cables, Motors, Heaters) 22 17SEP11A 31MAR12 67 85 8
PC43030340 4303 Pumps PA-43-01A/B 14 17DEC11A 31MAR12 67 20 8
PC43030320 4303 Filter MA-43-01A/B 7 25MAR12 31MAR12 7 0 14
PC43030SMC 4303 Sub System MC - 4303 0 31MAR12 0 0 14
COMMISSIONING
CN43030350 4303 Flare Blowers (no. 2) load test 3 18MAR12 20MAR12 3 0 25
CN43030320 4303 Loop Checks & Functional Test 7 18MAR12 24MAR12 7 0 5
CN43030310 4303 Piping Systems: leak test 14 18MAR12 31MAR12 14 0 11
CN43030330 4303 LV Ele Motors (2) no load test 2 01APR12 02APR12 2 0 8
CN43030360 4303 Piping Systems: Inerting 3 01APR12 03APR12 3 0 11
CN43030340 4303 Pumps: final allignement and coupling 4 03APR12 06APR12 4 0 8
CN43030370 4303 Flare Package Commissioning 15 08APR12 14APR12 7 0 0
CN4303RFSU 4303 Sub System RFSU - 4303 0 14APR12 0 0 0

4304 - ATM Flare


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC43040470 4304 Instrumentation 14 09SEP11A 24MAR12 60 1 5
PC43040455 4304 Piping Systems: Blowing & Reinst 21 12JUL11A 31MAR12 67 45 9
PC43040460 4304 Electrical (Cables, Motors, Heaters) 14 17SEP11A 31MAR12 67 85 11
PC43040410 4304 KO Drums VD-43-04 14 24SEP11A 31MAR12 67 30 183
PC43040450 4304 Pumps PA-43-04A/B 14 17DEC11A 31MAR12 67 20 13
PC43040440 4304 Flare Packages UF-43-03 21 11MAR12 31MAR12 21 0 17
PC43040445 4304 Flare Blowers KF-43-04A/B 14 18MAR12 31MAR12 14 0 17
PC43040420 4304 Filter MA-43-03A/B 7 25MAR12 31MAR12 7 0 19
PC43040SMC 4304 Sub System MC - 4304 0 31MAR12 0 0 19
COMMISSIONING
CN43040420 4304 Loop Checks & Functional Test 7 25MAR12 31MAR12 7 0 5
CN43040430 4304 LV Ele Motors (2) no load test 2 01APR12 02APR12 2 0 11
CN43040445 4304 Flare Blowers (no. 2) load test 2 01APR12 02APR12 2 0 17
CN43040440 4304 Pumps: final allignement and coupling 3 03APR12 05APR12 3 0 11
CN43040410 4304 Piping Systems: leak test 14 01APR12 07APR12 7 0 9
CN43040450 4304 Piping Systems: Inerting 3 08APR12 10APR12 3 0 9
CN43040460 4304 Flare Package Commissioning 14 01APR12 14APR12 14 0 5
CN4304RFSU 4304 Sub System RFSU - 4304 0 14APR12 0 0 5

4305 - Burn Pit


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC43050570 4305 Instrumentation 19 09SEP11A 24MAR12 60 1 5

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 9 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

PC43050560 4305 Electrical (Cables) 21 12JUL11A 31MAR12 67 95 7


PC43050550 4305 Piping Systems: Blowing & Reinst 21 24SEP11A 31MAR12 67 50 4
PC43050510 4305 Filter MA-43-04A/B 7 17DEC11A 31MAR12 67 25 19
PC43050530 4305 Burn Pit Package UF-43-04 14 17DEC11A 31MAR12 67 10 13
PC43050SMC 4305 Sub System MC - 4305 0 31MAR12 0 0 19
COMMISSIONING
CN43050510 4305 Piping Systems: leak test 14 01APR12 07APR12 7 0 4
CN43050550 4305 Piping Systems: Inerting 2 08APR12 09APR12 2 0 4
CN43050520 4305 Loop Checks & Functional Test 21 25MAR12 14APR12 21 0 5
CN43050560 4305 Burn pit Package Commissioning 6 10APR12 15APR12 6 0 4
CN4305RFSU 4305 Sub System RFSU - 4305 0 15APR12 0 0 4

44 - Oil Water Treatment System


4401 - Oil Water Treatment
Step 2: Gas in Plant
CONSTRUCTION
CO44010090 4401 Piping & Supports Erection 78 05FEB11A 03MAR12 39 90 13
CO44010040 4401 Electrical Cable Laying 20 13AUG11A 03MAR12 39 32 35
CO44010060 4401 Equipment Installation 20 23JUL11A 10MAR12 46 79 35
CO44010030 4401 Electrical Cable Connections 20 19NOV11A 10MAR12 46 13 35
CO44010070 4401 Electrical equipment installation 14 26FEB12 10MAR12 14 0 35
CO44010100 4401 Piping Hydrotest 1 24AUG11A 17MAR12 53 20 13
CO44010050 4401 Instrument cable laying [Secondary] 98 24SEP11A 24MAR12 60 66 41
CO44010080 4401 Field Instrument Installation 20 25JUN11A 31MAR12 67 30 34
CO44010110 4401 Painting works 1 05MAR11A 07APR12 74 93 13
CO44010120 4401 Insulation works 1 11JUN11A 21APR12 88 27 13
PRE-COMMISSIONING
PC44010110 4401 Instrumentation 22 09SEP11A 17MAR12 53 1 20
PC44010100 4401 Electrical (Cables, Motors) 22 25FEB12 17MAR12 22 0 28
PC44010098 4401 Piping Systems: Flushing/Blowing/Reinst 17 03DEC11A 24MAR12 60 11 13
PC44010083 4401 API & Tilted Plate Separator Package UO-44-01 14 11MAR12 24MAR12 14 0 13
PC44010010 4401 Produce Water Separator VA-44-01 7 18MAR12 24MAR12 7 0 13
PC44010SMC 4401 Sub System MC - 4401 0 24MAR12 0 0 27
COMMISSIONING
CN44010040 4401 LV Ele Motors (4) no load test 3 02APR12 04APR12 3 0 13
CN44010050 4401 Pumps: final allignement and coupling 5 04APR12 08APR12 5 0 13
CN44010010 4401 Piping Systems: leak test (16) 9 25MAR12 14APR12 21 0 20
CN44010100 4401 Collection Pit RG-44-01 Filling with water 11 03APR12 16APR12 14 0 18
CN44010020 4401 Loop Checks & Functional Test 14 25MAR12 21APR12 28 0 13
CN44010110 4401 Pumps Run-in 10 08APR12 21APR12 14 0 13
CN4401RFSU 4401 Sub System RFSU - 4401 0 21APR12 0 0 13

45 - Fuel Gas System


4501 - HP Fuel Gas
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO45010070 4501 Piping & Supports Erection 100 04DEC10A 29FEB12 36 98 0
CO45010030 4501 Electrical equipment installation [LMCS] 10 17SEP11A 29FEB12 36 95 10
CO45010050 4501 Instrument cable laying [Secondary] 68 09APR11A 10MAR12 46 31 7
CO45010090 4501 Piping Hydrotest 100 30JUL11A 14MAR12 50 31 0
CO45010060 4501 Painting works 72 26FEB11A 19MAR12 55 84 0
CO45010080 4501 Field Instrument Installation 21 18JUN11A 22MAR12 58 38 0
CO45010110 4501 Insulation works 25 11JUN11A 31MAR12 67 33 0
PRE-COMMISSIONING
PC45010110 4501 Instrumentation 16 09SEP11A 29FEB12 36 1 17
PC45010050 4501 Tyristor Control Panel EC-45-01 7 01MAR12 07MAR12 7 0 10
PC45010090 4501 Piping Systems: Blowing/Drying & Reinst 56 01JUL11A 18MAR12 54 25 0
PC45010010 4501 Pressure Vessels VD-45-01/02 7 12MAR12 18MAR12 7 0 0
PC45010020 4501 Filters MA-45-01A/B 7 12MAR12 18MAR12 7 0 0
PC45010100 4501 Electrical (Heat Tracing) 16 17SEP11A 31MAR12 67 70 0
PC45010SMC 4501 Sub System MC - 4501 0 31MAR12 0 0 0
COMMISSIONING
CN45010050 4501 Tyristor Control Panel Commissioning 21 08MAR12 21MAR12 14 0 10
CN45010010 4501 Piping Systems: leak test (55) 11 19MAR12 25MAR12 7 0 0
CN45010020 4501 Loop Checks & Functional Test 21 18MAR12 31MAR12 14 0 0
CN45010060 4501 Piping Systems: Inerting 11 25MAR12 31MAR12 7 0 0
CN4501RFSU 4501 Sub System RFSU - 4501 0 31MAR12 0 0 0

50 - Source Water System


Water Wells SubSystems
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO50000140 5000 Equipment Installation [CPF] 1 05FEB11A 29FEB12 36 95 9
CO50000070 5000 Piping & Support Erection [CPF] 100 12FEB11A 29FEB12 36 100 9
CO50000040 5000 Electrical cable laying [CPF] 10 28MAY11A 29FEB12 36 98 37
CO50000080 5000 Instrumentation works [Source Water Wells] 16 04JUN11A 29FEB12 36 97 1
CO50000100 5000 Instrumentation Works [CPF] 10 18JUN11A 29FEB12 36 30 37
CO50000030 5000 Electrical Cable Connection [CPF] 10 01JUN11A 04MAR12 40 88 47

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 10 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

CO50000090 5000 Piping Hydrotest [CPF+LES 104] 100 23JUL11A 14MAR12 50 31 9


CO50000150 5000 Painting works [CPF + Source Water Wells] 1 07MAY11A 18APR12 85 79 2
CO50000160 5000 Insulation works [CPF + Souce Water Wells] 1 11JUN11A 02MAY12 99 78 2

5001 - Water Well LS-104


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC50010120 5001 Instrumentation [LES 104] 14 09SEP11A 29FEB12 36 1 1
PC50010110 5001 Electrical (Cables & Motors) [LES 104] 7 24SEP11A 29FEB12 36 80 66
PC50010100 5001 Piping Systems: Flushing/Reinst [LES104] 21 07JUL11A 03MAR12 39 65 8
PC50010055 5001 Pump PS-50-01A [LES 104] 10 23FEB12 03MAR12 10 0 8
PC50050060 5001 Filters MB-50-01A 4 29FEB12 03MAR12 4 0 8
PC50010SMC 5001 Sub-System MC - 5001 0 03MAR12 0 0 63
COMMISSIONING
CN50010040 5001 Pump: final allignement and coupling 2 04MAR12 05MAR12 2 0 8
CN50010050 5001 Pump PS-50-01A Run in 2 09MAR12 10MAR12 2 0 5
CN50010010 5001 Loop Checks & Functional Test [LES 104] 5 01MAR12 14MAR12 14 0 1
CN50010060 5001 Source Water System Commissioning 2 15MAR12 16MAR12 2 0 1
CN5001RFSU 5001 Sub-System RFSU - 5001 0 16MAR12 0 0 1

5002 - Water Well MLE-107


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC50020120 5002 Instrumentation [MLE 107] 14 09SEP11A 24MAR12 60 1 14
PC50020110 5002 Electrical (Cables & Motors) [MLE 107] 7 18MAR12 24MAR12 7 0 190
PC50020100 5002 Piping Systems: Flushing/Reinst [MLE 107] 21 17DEC11A 31MAR12 67 30 12
PC50020060 5002 Filters MB-50-01B 4 28MAR12 31MAR12 4 0 12
PC50020055 5002 Pump PS-50-01B [MLE 107] 7 01APR12 07APR12 7 0 12
PC50020SMC 5002 Sub-System MC - 5002 0 07APR12 0 0 176
COMMISSIONING
CN50020210 5002 Loop Checks & Functional Test 8 25MAR12 07APR12 14 0 14
CN50020240 5002 Pump: Final Allignement and coupling 2 06APR12 07APR12 2 0 14
CN50020250 5002 Pump PS-50-01B Run In 2 08APR12 09APR12 2 0 12
CN50020260 5002 Sorce Water System Commissioning 2 10APR12 11APR12 2 0 12
CN5002RFSU 5002 Sub-System RFSU - 5002 0 11APR12 0 0 12

5003 - Water Well MLE-105


Step 2: Gas in Plant
PRE-COMMISSIONING
PC50030120 5003 Instrumentation 7 09SEP11A 21APR12 88 1 6
PC50030110 5003 Electrical (Cables & Motors) 7 15APR12 21APR12 7 0 13
PC50030100 5003 Piping Systems: Flushing/Reinst [MLE105] 14 17DEC11A 28APR12 95 10 2
PC50030055 5003 Pump PS-50-01C 7 22APR12 28APR12 7 0 2
PC50030SMC 5003 Sub-System MC - 5003 0 28APR12 0 0 6
COMMISSIONING
CN50030310 5003 Loop Checks & Functional Test 7 22APR12 28APR12 7 0 6
CN50030340 5003 Pump: final allignement and coupling 2 29APR12 30APR12 2 0 2
CN50030350 5003 Pump PS-50-01C Run in [MLE 105] 2 01MAY12 02MAY12 2 0 2
CN5003RFSU 5003 Sub-System RFSU - 5003 0 02MAY12 0 0 2

5004 - Water Well MLE-106


Step 2: Gas in Plant
PRE-COMMISSIONING
PC50040120 5004 Instrumentation 13 09SEP11A 21APR12 88 1 6
PC50040110 5004 Electrical (Cables & Motors) 13 08APR12 21APR12 14 0 13
PC50040100 5004 Piping Systems: Flushing/Reinst [MLE 106] 21 17DEC11A 28APR12 95 10 2
PC50040055 5004 Pump PS-50-01D 6 22APR12 28APR12 7 0 2
PC50040SMC 5004 Sub-System MC - 5004 0 28APR12 0 0 6
COMMISSIONING
CN50040410 5004 Loop Checks & Functional Test 7 22APR12 28APR12 7 0 6
CN50040440 5004 Pump: final allignement and coupling 2 29APR12 30APR12 2 0 2
CN50040450 5004 Pump PS-50-01D Run in [MLE 106] 2 01MAY12 02MAY12 2 0 2
CN5004RFSU 5004 Sub-System RFSU - 5004 0 02MAY12 0 0 2

5005 - Raw Water Storage


Step 2: Gas in Plant
PRE-COMMISSIONING
PC50050110 5005 Electrical (Cables & Motors) 14 27FEB12 11MAR12 14 0 47
PC50050120 5005 Instrumentation 14 09SEP11A 14MAR12 50 1 37
PC50050100 5005 Piping Systems: Flushing/Reinst 21 17DEC11A 28MAR12 64 15 30
PC50050020 5005 Storage Tank RB-50-01 7 22MAR12 28MAR12 7 0 30
PC50050055 5005 Pumps PA-50-02 A/B 7 22MAR12 28MAR12 7 0 30
PC50050SMC 5005 Sub-System MC - 5005 0 28MAR12 0 0 37
COMMISSIONING
CN50050510 5005 Loop Checks & Functional Test 7 15MAR12 28MAR12 14 0 37
CN50050530 5005 LV Ele Motors (2) no load test 2 29MAR12 04APR12 7 0 30
CN50050545 5005 Tank filling with water from wells 4 26APR12 02MAY12 7 0 2
CN5005RFSU 5005 Sub-System RFSU - 5005 0 02MAY12 0 0 2

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 11 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

53 - Potable Water System


Potable Water SubSytems
Step 2: Gas in Plant
CONSTRUCTION
CO53000050 5300 Instrument Cable Laying [Secondary] 59 24SEP11A 23MAR12 59 73 50
CO53000090 5300 Piping & Supports Erection 160 02FEB11A 24MAR12 60 87 2
CO53000060 5300 Equipment Installation 129 09FEB11A 24MAR12 60 91 2
CO53000040 5300 Electrical Cable Laying 159 28MAY11A 24MAR12 60 97 16
CO53000030 5300 Electrical Cable Connections 164 01JUN11A 31MAR12 67 56 16
CO53000095 5300 Piping Hydrotest 160 20AUG11A 07APR12 74 23 2
CO53000070 5300 Painting works 45 26FEB11A 05MAY12 102 79 2
CO53000080 5300 Field Instruments Installation 40 28SEP11A 05MAY12 102 40 14
CO53000100 5300 Insulation works 68 11JUN11A 19MAY12 116 40 2

5301- Water Filtration & Reverse Osmosis Package


Step 2: Gas in Plant
PRE-COMMISSIONING
PC53010090 5301 Instrumentation 28 09SEP11A 21APR12 88 1 30
PC53010080 5301 Electrical (Cables & Motors) 21 12NOV11A 21APR12 88 20 2
PC53010050 5301 Pumps PA-53-01/06/08-A/B/C/D; PA53-07A/B 21 01APR12 21APR12 21 0 2
PC53010070 5301 Piping Systems: Flushing/Reinst 35 27AUG11A 28APR12 95 30 2
PC53010020 5301 Tanks RB-53-01-A/B; RB-53-03 35 25MAR12 28APR12 35 0 16
PC53010010 5301 Reverce Osmosis Sys UZ-53-01/A/B/C/D 21 08APR12 28APR12 21 0 23
PC53010012 5301 Filters & Vessel MB-53-01//02/03-A/B/C/D 21 08APR12 28APR12 21 0 23
PC53010SMC 5301 Sub System MC - 5301 0 28APR12 0 0 23
COMMISSIONING
CN53010040 5301 Loop Checks & Functional Test 14 08APR12 21APR12 14 0 30
CN53010050 5301 LV Ele Motors (18) no load test 4 22APR12 28APR12 7 0 2
CN53010052 5301 Pumps: final allignement and coupling 14 29APR12 05MAY12 7 0 2
CN53010055 5301 Tank RB-53-03-filling with water 7 06MAY12 12MAY12 7 0 19
CN53010060 5301 Pumps Run-in - Recycle Mode 14 06MAY12 12MAY12 7 0 2
CN53010065 5301 Service Water network : service test 14 13MAY12 19MAY12 7 0 2
CN5301RFSU 5301 Sub-System RFSU - 5301 0 19MAY12 0 0 2

5302 - Potable Water


Step 2: Gas in Plant
PRE-COMMISSIONING
PC53020090 5302 Instrumentation 28 09SEP11A 21APR12 88 1 0
PC53020080 5302 Electrical (Cables & Motors) 28 25MAR12 21APR12 28 0 0
PC53020020 5302 Pumps PA-53-02A/B; 04A/B; 05A/B 21 01APR12 21APR12 21 0 0
PC53020010 5302 Tanks RB-53-02A/B & 53-04 38 25MAR12 28APR12 35 0 155
PC53020070 5302 Piping Systems: Flushing/Reinst 35 25MAR12 28APR12 35 0 2
PC53020012 5302 Vessel VN-53-01 21 08APR12 28APR12 21 0 155
PC53020050 5302 U.V. & Chiller Package 21 08APR12 28APR12 21 0 155
PC53020SMC 5302 Sub-System MC- 5302 0 28APR12 0 0 155
COMMISSIONING
CN53020050 5302 LV Ele Motors (6) no load test 5 22APR12 26APR12 5 0 0
CN53020052 5302 Pumps: final allignement and coupling 14 26APR12 02MAY12 7 0 0
CN53020040 5302 Loop Checks & Functional Test 14 22APR12 05MAY12 14 0 14
CN53020060 5302 Pumps Run-in - Recycle Mode 14 03MAY12 09MAY12 7 0 0
CN53020055 5302 Tank RB-53-02-filling with water 10 10MAY12 19MAY12 10 0 0
CN53020065 5302 Service Water network : service test 14 15MAY12 21MAY12 7 0 0
CN5302RFSU 5302 Sub-System RFSU - 5302 0 21MAY12 0 0 0

5303 - Chemical Injection


Step 2: Gas in Plant
PRE-COMMISSIONING
PC53030010 5303 Drums VD-53-01; 53-02; 53-03; 53-04; 53-05 16 17MAR12* 01APR12 16 0 9
PC53030090 5303 Instrumentation 28 09SEP11A 21APR12 88 1 2
PC53030080 5303 Electrical (Cables & Motors) 21 01APR12 21APR12 21 0 2
PC53030012 5303 Pumps PB-53-01A/B/C/D; 53-06A/B/C/D; 53-06E 16 06APR12 21APR12 16 0 2
PC53030020 5303 Pumps PB-53-02A/B/C/D; 53-02E 16 06APR12 21APR12 16 0 2
PC53030050 5303 Pumps PB-53-03A/B/C/D 16 06APR12 21APR12 16 0 2
PC53030070 5303 Pumps PB-53-04A/B/C/D; 05A/B/C/D 13 09APR12 21APR12 13 0 2
PC53030SMC 5303 Sub-System MC- 5303 0 21APR12 0 0 162
PC53030100 5303 Piping Systems: Flushing/Reinst 50 10MAR12 28APR12 50 0 2
COMMISSIONING
CN53030040 5303 Loop Checks & Functional Test 14 15APR12 28APR12 14 0 23
CN53030050 5303 Pumps:final allignement and coupling 21 22APR12 05MAY12 14 0 2
CN53030070 5303 Piping System: leak test 11 29APR12 05MAY12 7 0 2
CN53030060 5303 Pumps Load Test 18 06MAY12 15MAY12 10 0 2
CN53030065 5303 Service Water network : service test 18 06MAY12 19MAY12 14 0 2
CN5303RFSU 5303 Sub-System RFSU - 5303 0 19MAY12 0 0 2

5304 - Drinking Water


Step 2: Gas in Plant
PRE-COMMISSIONING
PC53040090 5304 Instrumentation 28 09SEP11A 21APR12 88 1 0
PC53040080 5304 Electrical (Cables & Motors) 28 25MAR12 21APR12 28 0 0

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 12 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

PC53040050 5304 Pumps PA-53-02A/B; PA53-04A/B; PA-53-05A/B 14 08APR12 21APR12 14 0 0


PC53040070 5304 Piping Systems: Flushing/Reinst 35 25MAR12 28APR12 35 0 14
PC53040012 5304 Drinking Water Chiller Package UO-53-04 14 15APR12 28APR12 14 0 16
PC53040020 5304 Tanks & Drum RB-53-02A/B; 53-04; VN-53-01 14 15APR12 28APR12 14 0 23
PC53040SMC 5304 Sub-System MC- 5304 0 28APR12 0 0 23
COMMISSIONING
CN53040050 5304 LV Ele Motors (6) no load test 6 21APR12 26APR12 6 0 0
CN53040040 5304 Loop Checks & Functional Test 25 01APR12 28APR12 28 0 23
CN53040052 5304 Pumps: final allignement and coupling 6 25APR12 30APR12 6 0 0
CN53040060 5304 Pumps Run-in - Recycle Mode 7 01MAY12 07MAY12 7 0 0
CN53040055 5304 Tank RB-53-04 filling with water 12 08MAY12 14MAY12 7 0 0
CN53040065 5304 Drinking Water network: service test 7 15MAY12 21MAY12 7 0 0
CN5304RFSU 5304 Sub-System RFSU - 5304 0 21MAY12 0 0 0

56 - Open Drain System


5601 - Open Drain
Step 2: Gas in Plant
CONSTRUCTION
CO56010090 5601 UG Piping erection 78 22JUL10A 17MAR12 53 99 0
CO56010080 5601 UG Piping Hydrotest 66 04NOV11A 31MAR12 67 92 0
CO56010070 5601 Painting works 20 16FEB11A 19APR12 86 56 0
PRE-COMMISSIONING
PC56010070 5601 Piping Systems: Flushing & Reinst 31 12NOV11A 31MAR12 67 30 19
PC56010SMC 5601 Sub System MC - 5601 0 31MAR12 0 0 19
COMMISSIONING
CN5601RFSU 5601 Sub System RFSU - 5601 0 19APR12 0 0 0

57 - Closed Drain System


Close Drain Sub-Systems
Step 2: Gas in Plant
CONSTRUCTION
CO57000060 5700 Equipment Installation (pumps) 10 19MAR11A 03MAR12 39 98 12
CO57000040 5700 Electrical Cable Laying 22 08OCT11A 03MAR12 39 85 12
CO57000095 5700 Piping & Supports erection 119 16OCT10A 04MAR12 40 99 0
CO57000030 5700 Electrical Cable Connections 22 13APR11A 10MAR12 46 69 12
CO57000105 5700 Piping Hydrotest 1 07MAY11A 14MAR12 50 31 0
CO57000080 5700 Field Instrument Installation 10 29JUN11A 21MAR12 57 38 7
CO57000070 5700 Painting works 104 29JAN11A 07APR12 74 82 0
CO57000090 5700 Insulation works 28 23MAR12 19APR12 28 0 0

5701 - Closed Drain (UP TO 150C)


Step 2: Gas in Plant
PRE-COMMISSIONING
PC57010090 5701 Instrumentation 14 09SEP11A 29FEB12 36 1 30
PC57010080 5701 Electrical (Cables, Motors) 15 25FEB12 10MAR12 15 0 12
PC57010050 5701 Pumps PA-57-01A/B 6 04MAR12 10MAR12 7 0 12
PC57010070 5701 Piping Systems: Flushing/Blowing/Reinst 31 17SEP11A 14MAR12 50 21 0
PC57010030 5701 Drum VD-57-01 6 11MAR12 16MAR12 6 0 12
PC57010SMC 5701 Sub System MC - 5701 0 16MAR12 0 0 14
COMMISSIONING
CN57010030 5701 LV Ele Motors (2) no load test 2 24MAR12 25MAR12 2 0 7
CN57010035 5701 Pumps: final allignement and coupling 3 26MAR12 28MAR12 3 0 7
CN57010020 5701 Loop Checks & Functional Test 10 22MAR12 31MAR12 10 0 7
CN57010048 5701 Drums filling with water 7 29MAR12 04APR12 7 0 0
CN57010050 5701 Pumps (2) Run in with water 3 05APR12 07APR12 3 0 0
CN57010052 5701 Drum Drainage 2 08APR12 09APR12 2 0 0
CN57010060 5701 Closed Warm Drain Network: Inerting 3 10APR12 12APR12 3 0 7
CN57010005 5701 Closed Warm Drain Network: Air gross leak test 10 10APR12 19APR12 10 0 0
CN5701RFSU 5701 Sub System RFSU - 5701 0 19APR12 0 0 0

5702 - Closed Cold Drain


Step 2: Gas in Plant
PRE-COMMISSIONING
PC57020050 5702 Pumps PA-57-02A/B 6 16FEB12 22FEB12 7 0 42
PC57020030 5702 Drum VD-57-02 4 23FEB12 26FEB12 4 0 53
PC57020090 5702 Instrumentation 14 09SEP11A 29FEB12 36 1 34
PC57020070 5702 Piping Systems: Flushing/Blowing/Reinst 43 17SEP11A 29FEB12 36 14 31
PC57020080 5702 Electrical (Cables, Motors) 14 16FEB12 29FEB12 14 0 34
PC57020SMC 5702 Sub System MC - 5702 0 29FEB12 0 0 50
COMMISSIONING
CN57020048 5702 Drums filling with water 3 01MAR12 03MAR12 3 0 211
CN57020030 5702 LV Ele Motors (2) no load test 2 05MAR12 06MAR12 2 0 31
CN57020035 5702 Pumps: final allignement and coupling 3 07MAR12 09MAR12 3 0 31
CN57020020 5702 Loop Checks & Functional Test 10 01MAR12 10MAR12 10 0 31
CN57020040 5702 Electrical Heaters Functional & Test 7 05MAR12 11MAR12 7 0 203
CN57020050 5702 Pumps (2) Run in with water 2 10MAR12 11MAR12 2 0 31
CN57020052 5702 Drum Drainage 2 12MAR12 13MAR12 2 0 31
CN57020005 5702 Closed Cold Drain Network: Air gross leak test 6 14MAR12 19MAR12 6 0 31
CN57020062 5702 Closed Cold Drain Network: Inerting 5 29MAR12 02APR12 5 0 17

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 13 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

CN5702RFSU 5702 Sub System RFSU - 5702 0 02APR12 0 0 17

62 - Diesel System
Diesel System
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO62000090 6200 Piping Hydrotest 39 16JUL11A 03MAR12 39 47 0
CO62000040 6200 Electrical cable laying 113 10SEP11A 03MAR12 39 91 13
CO62000100 6200 Electrical cable connections 40 09APR11A 17MAR12 53 33 13
CO62000080 6200 Instrument cable laying [Secondary] 113 24SEP11A 17MAR12 53 66 3
CO62000050 6200 Painting Works 10 19MAR11A 24MAR12 60 89 0
CO62000070 6200 Field Instrument installation 68 18JUN11A 24MAR12 60 78 3
CO62000060 6200 Insulation works 28 11MAR12 07APR12 28 0 0

6201 - Diesel System


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC62010070 6201 Piping Systems: Blowing/Reinst 68 15JUL11A 17MAR12 53 70 0
PC62010090 6201 Instrumentation 7 09SEP11A 17MAR12 53 1 12
PC62010050 6201 Pumps PA-62-01A 7 17DEC11A 17MAR12 53 15 13
PC62010052 6201 Pumps PA-62-01B 7 17DEC11A 17MAR12 53 15 13
PC62010060 6201 Filters MB-62-02A 7 17DEC11A 17MAR12 53 15 21
PC62010062 6201 Filters MA-62-01A/B; MB-62-02B 7 17DEC11A 17MAR12 53 15 13
PC62010020 6201 Tank RA-62-01 7 14JAN12A 17MAR12 53 90 14
PC62010080 6201 Electrical (Cables & Motors) 14 04MAR12 17MAR12 14 0 13
PC62010SMC 6201 Sub System MC - 6201 0 17MAR12 0 0 21
COMMISSIONING
CN62010030 6201 LV Ele Motors (2) no load test 1 28MAR12 28MAR12 1 0 3
CN62010032 6201 Pumps: final allignement and coupling 2 29MAR12 30MAR12 2 0 3
CN62010010 6201 Piping Network: leak test (21) 14 18MAR12 31MAR12 14 0 0
CN62010020 6201 Loop Checks & Functional Test 14 18MAR12 31MAR12 14 0 3
CN62010035 6201 Tank filling with diesel 4 01APR12 04APR12 4 0 0
CN62010040 6201 Pumps (2) Run in with diesel - Recycle mode 3 05APR12 07APR12 3 0 0
CN6201RFSU 6201 Sub System RFSU - 6201 0 07APR12 0 0 0

63 - Compressor Air System


Compressors Air Sub-Systems
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO63000070 6300 Piping & Supports erection 88 25DEC10A 29FEB12 36 90 0
CO63000050 6300 Instrument cable laying [Secondary] 58 24SEP11A 03MAR12 39 82 68
CO63000090 6300 Piping Hydrotests 58 26FEB11A 10MAR12 46 30 0
CO63000080 6300 Filed Instrument Installation 37 28SEP11A 17MAR12 53 42 61
CO63000110 6300 Painting works 21 09JUL11A 24MAR12 60 72 68

6301 - Air Compressor Diesel Motor Driven


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC63010080 6301 Electrical (Cables & Motors) 14 17SEP11A 07OCT11A 0 100
PC63010090 6301 Instrumentation 14 09SEP11A 25JAN12A 0 100
PC63010010 6301 Air Supply Packages HA-63-01F 7 24DEC11A 25FEB12 32 95 14
PC63010012 6301 Air Dryer Packages HA-63-02A 7 31DEC11A 25FEB12 32 95 14
PC63010013 6301 Air Dryer Packages HA-63-02B/C 7 31DEC11A 25FEB12 32 95 14
PC63010014 6301 Instrument & Air Receivers VL-63-01A/B; VL-63-02 7 07JAN12A 25FEB12 32 70 14
PC63010070 6301 Piping Systems: Blowing/Drying & Reinst 95 19JUL11A 10MAR12 46 64 0
PC63010SMC 6301 Sub System MC - 6301 0 10MAR12 0 0 0
COMMISSIONING
CN63010015 6301 Blower & Air cooler LV Ele Motor (3) load test 4 26DEC11A 25JAN12A 0 100
CN63010020 6301 Diesel Air Supply Package Commissioning 21 04MAR12 24MAR12 21 0 68
CN63010005 6301 Loop Checks & Functional Test 7 18MAR12 24MAR12 7 0 61
CN63010030 6301 Air Dryer Package (3) Commissioning 13 11MAR12 31MAR12 21 0 61
CN6301RFSU 6301 Sub System RFSU - 6301 0 31MAR12 0 0 61

6302 - Air Compressor Electric Motor Driven


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC63020080 6302 Electrical (Cables & Motors) 15 17SEP11A 07OCT11A 0 100
PC63020090 6302 Instrumentation 15 09SEP11A 25JAN12A 0 100
PC63020010 6302 Air Supply Packages HA-63-01A/B/C/D/E 7 24DEC11A 25FEB12 32 95 14
PC63020070 6302 Piping Systems: Blowing/Drying & Reinst 23 24JUL11A 10MAR12 46 88 0
PC63020SMC 6302 Sub System MC - 6302 0 10MAR12 0 0 0
COMMISSIONING
CN63020015 6302 MV Ele Motors (5) no load test 7 26DEC11A 25JAN12A 0 100
CN63020005 6302 Loop Checks & Functional Test 15 18MAR12 24MAR12 7 0 186
CN63020040 6302 Electrical Air Supply Package (5) Commissioning 25 08MAR12 28MAR12 21 0 186
CN63020020 6302 Blower & Air cooler LV Ele Motor (15) load test 7 22MAR12 28MAR12 7 0 186
CN6302RFSU 6302 Sub System RFSU - 6302 0 28MAR12 0 0 186

6303- Plant Air Distribution Network


Step 1A/1B: Up to TK1 Gas Turbine solo Run
COMMISSIONING
CN63030065 6303 Plant Air Network: service test 15 11MAR12 24MAR12 14 0 0
33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 14 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

CN63040060 6303 Instrument Air Network: service test 15 11MAR12 24MAR12 14 0 0


CN63030055 6303 Plant Air System: Start-UP 15 25MAR12 07APR12 14 0 0
CN63040050 6303 Instrument Air System: Start-UP 15 25MAR12 07APR12 14 0 0

64 - Inert Gas System


6401 - Nitrogen Package & Network
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO64010070 6401 Piping & Supports erection 10 26DEC10A 03MAR12 39 91 14
CO64010030 6401 Electrical Cable Connections 53 05MAR11A 17MAR12 53 47 28
CO64010090 6401 Piping Hydrotest 10 20AUG11A 17MAR12 53 25 7
CO64010050 6401 Instrument cable laying [Secondary] 42 16APR11A 31MAR12 67 71 183
CO64010080 6401 Field Instrument Installation 42 18JUN11A 31MAR12 67 45 0
CO64010060 6401 Painting works 58 12FEB11A 07APR12 74 75 7
PRE-COMMISSIONING
PC64010010 6401 Nitrogen Generator Package UN-64-01 14 24DEC11A 03MAR12 39 50 42
PC64010030 6401 Vessel & Drums VL-64-03; VL-64-01 10 07JAN12A 03MAR12 39 50 42
PC64010080 6401 Electrical (Cables) 15 14JAN12A 17MAR12 53 50 28
PC64010070 6401 Piping Systems: Blowing/Drying & Reinst 26 27AUG11A 24MAR12 60 30 0
PC64010090 6401 Instrumentation 15 09SEP11A 31MAR12 67 1 0
PC64010SMC 6401 Sub System MC - 6401 0 31MAR12 0 0 14
COMMISSIONING
CN64010035 6401 Nitrogen Generator Package Commissioning 7 04MAR12 10MAR12 7 0 204
CN64010025 6401 Piping Systems: leak test 7 22MAR12 28MAR12 7 0 3
CN64010055 6401 Nitrogen System service test 7 22MAR12 28MAR12 7 0 3
CN64010020 6401 Loop Checks & Functional Test 14 01APR12 14APR12 14 0 0
CN6401RFSU 6401 Sub System RFSU - 6401 0 14APR12 0 0 0

6402 - Nitrogen Snuffing Compressor


Step 2: Gas in Plant
PRE-COMMISSIONING
PC64020080 6402 Electrical (Cables & Motors) 20 01DEC11A 07JAN12A 0 100
PC64020070 6402 Piping Systems: Flushing/Blowing/Drying & Reinst 20 26NOV11A 17MAR12 53 25 7
PC64020090 6402 Instrumentation 20 09SEP11A 31MAR12 67 50 14
PC64020012 6402 Nitrogen Snuffing Compressor Package UK-64-01 14 18MAR12* 31MAR12 14 0 7
PC64020030 6402 Vessel & Drum VL-64-02 14 18MAR12 31MAR12 14 0 21
PC64020SMC 6402 Sub System MC - 6402 0 31MAR12 0 0 21
COMMISSIONING
CN64020030 6402 LV Ele Motors (1) no load test 2 26DEC11A 25JAN12A 0 100
CN64020025 6402 Piping Systems: leak test 7 18MAR12 21MAR12 4 0 24
CN64020020 6402 Loop Checks & Functional Test 21 18MAR12 07APR12 21 0 14
CN64020037 6402 Nitrogen Snuffing Compressor Package 14 25MAR12 07APR12 14 0 7
CN64020055 6402 Nitrogen System service test 14 08APR12 14APR12 7 0 7
CN6402RFSU 6402 Sub System RFSU - 6402 0 14APR12 0 0 7

70 - Fire and Gas Detection System


Fire & Gas Detection Sub-Systems
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO70000010 7000 Electrical Cable laying 14 09JUL11A 17MAR12 53 86 20
CO45000100 7000 F&G Detection Completion [Sys 45] 0 22MAR12 0 0 0
CO70000030 7000 F&G Detectors installation 1 15JAN11A 24MAR12 60 75 20
CO70000020 7000 Electrical Cable connenctions 1 13AUG11A 24MAR12 60 35 20
CO43000030 7000 F&G Detection Completion [Sys 43] 0 24MAR12 0 0 -2
CO27000130 7000 F&G Detection Completion [Sys 27] 0 31MAR12 0 0 -9
PRE-COMMISSIONING
PC70000010 7000 F&G Detection Completion [Sys. 27/ 43/ 45] 23 04MAR12 31MAR12 28 0 -9
PC70000020 7000 F&G Detection Compl. [27/ 43/45] - MC. 0 31MAR12 0 0 0
COMMISSIONING
CN70000010 7000 F&G Detection Competion [Sys. 27/ 43/ 45] 11 18MAR12 31MAR12 14 0 0
CN70000020 7000 F&G Detection Compl. [Sys 27/ 43/ 45] - RFSU 0 31MAR12 0 0 0

7001 - F&G Detection CPF Central Control Bld.


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC70010020 7001 F&G Cables 31 19JUL11A 12AUG11A 0 100
PC70010010 7001 F&G Detectors/Devises 27 23JUL11A 12AUG11A 0 100
PC70010040 7001 Main F&G Panel 17 02AUG11A 12AUG11A 0 100
PC70010030 7001 VESDA System 7 04MAR12 10MAR12 7 0 -9
PC70010SMC 7001 Sub-System MC - 7001 0 10MAR12 0 0 21
COMMISSIONING
CN70010010 7001 Main F&G Panel Commissioning 7 04MAR12* 10MAR12 7 0 -9
CN70010030 7001 F&G Loop Checks 28 06MAR12 02APR12 28 0 -9
CN70010040 7001 F&G Functional Tests and SAT 14 27MAR12 09APR12 14 0 -9
CN7001RFSU 7001 Sub-System RFSU - 7001 0 09APR12 0 0 -9

7002 - F&G Detection CPF Main Substation


Step 2: Gas in Plant
PRE-COMMISSIONING
PC70020010 7002 F&G Detectors/Devises 38 01FEB11A 10MAR11A 0 100
PC70020020 7002 F&G Cables 38 01FEB11A 10MAR11A 0 100

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 15 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

PC70020040 7002 Fire Alarm Control Panel (FACP) 14 25FEB11A 10MAR11A 0 100
PC70020030 7002 VESDA System 7 04MAR12* 10MAR12 7 0 7
PC70020SMC 7002 Sub-System MC - 7002 0 10MAR12 0 0 7
COMMISSIONING
CN70020010 7002 FACP Commissioning 6 10MAR11A 15MAR11A 0 100
CN70020030 7002 F&G Loop Checks 16 15MAR11A 24MAR11A 0 100
CN70020040 7002 F&G Functional Tests and SAT 10 21MAR11A 24MAR11A 0 100
CN70020050 7002 VESDA System 10 11MAR12 24MAR12 14 0 7
CN7002RFSU 7002 Sub-System RFSU - 7002 0 24MAR12 0 0 7

7003 - F&G Detection CPF Laboratory


Step 2: Gas in Plant
PRE-COMMISSIONING
Due to Materials Arrivals
PC70030010 7003 F&G Detectors/Devises 14 26FEB12* 10MAR12 14 0 28
PC70030020 7003 F&G Cables 7 04MAR12 10MAR12 7 0 55
PC70030SMC 7003 Sub-System MC - 7003 0 10MAR12 0 0 55
COMMISSIONING
CN70030030 7003 F&G Loop Checks 32 10MAR12 30MAR12 21 0 28
CN70030040 7003 F&G Functional Tests and SAT 16 24MAR12 06APR12 14 0 28
CN7003RFSU 7003 Sub-System RFSU - 7003 0 06APR12 0 0 28

7004 - F&G Detection S.G.C Satellite Substation


Step 2: Gas in Plant
PRE-COMMISSIONING
PC70040010 7004 F&G Detectors/Devises 30 07JUL11A 28FEB12 35 85 38
PC70040020 7004 F&G Cables 30 07JUL11A 28FEB12 35 85 38
PC70040040 7004 VESDA System 7 22FEB12 28FEB12 7 0 38
PC70040SMC 7004 Sub-System MC - 7004 0 28FEB12 0 0 66
COMMISSIONING
CN70040010 7004 VESDA System 7 29FEB12 06MAR12 7 0 38
CN70040030 7004 F&G Loop Checks 28 29FEB12 20MAR12 21 0 38
CN70040040 7004 F&G Functional Tests and SAT 14 14MAR12 27MAR12 14 0 38
CN7004RFSU 7004 Sub-System RFSU - 7004 0 27MAR12 0 0 38

7005 - F&G Detection Flare Satellite Substation


Step 2: Gas in Plant
PRE-COMMISSIONING
PC70050010 7005 F&G Detectors/Devises 18 07JAN12A 22FEB12 29 85 0
PC70050020 7005 F&G Cables 9 07JAN12A 22FEB12 29 85 0
PC70050SMC 7005 Sub-System MC - 7005 0 22FEB12 0 0 7
COMMISSIONING
CN70050030 7005 F&G Loop Checks 14 23FEB12 29FEB12 7 0 0
CN70050040 7005 F&G Functional Tests and SAT 14 23FEB12 29FEB12 7 0 0
CN7005RFSU 7005 Sub-System RFSU - 7005 0 29FEB12 0 0 0

7006 - F&G Detection Analyser House


Step 2: Gas in Plant
PRE-COMMISSIONING
PC70060010 7006 F&G Detectors/Devises 15 07JAN12A 24MAR12 60 80 20
PC70060020 7006 F&G Cables 7 07JAN12A 24MAR12 60 80 20
PC70060SMC 7006 Sub-System MC - 7006 0 24MAR12* 0 0 41
COMMISSIONING
CN70060030 7006 F&G Loop Checks 14 25MAR12 07APR12 14 0 20
CN70060040 7006 F&G Functional Tests and SAT 14 01APR12 14APR12 14 0 20
CN7006RFSU 7006 Sub-System RFSU - 7006 0 14APR12 0 0 20

7007 - F&G Detection Metering House


Step 2: Gas in Plant
PRE-COMMISSIONING
PC70070010 7007 F&G Detectors/Devises 15 07JAN12A 24MAR12 60 40 20
PC70070020 7007 F&G Cables 7 07JAN12A 24MAR12 60 40 20
PC70070SMC 7007 Sub-System MC - 7007 0 24MAR12 0 0 41
COMMISSIONING
CN70070030 7007 F&G Loop Checks 14 25MAR12 07APR12 14 0 20
CN70070040 7007 F&G Functional Tests and SAT 14 01APR12 14APR12 14 0 20
CN7007RFSU 7007 Sub-System RFSU - 7007 0 14APR12 0 0 20

7008 - F&G Detection CPF Field


Step 2: Gas in Plant
PRE-COMMISSIONING
PC70080010 7008 F&G Detectors/Devises 120 07JAN12A 24MAR12 60 40 20
PC70080020 7008 F&G Cables 120 07JAN12A 24MAR12 60 40 41
PC70080SMC 7008 Sub-System MC - 7008 0 24MAR12 0 0 41
COMMISSIONING
CN70080030 7008 F&G Loop Checks 42 04MAR12 14APR12 42 0 20
CN70080040 7008 F&G Functional Tests and SAT 106 04MAR12 14APR12 42 0 20
CN7008RFSU 7008 Sub-System RFSU - 7008 0 14APR12 0 0 20

7009 - F & G System for Storage and Export Areas


Step 2: Gas in Plant
COMMISSIONING
CN70090030 7009 F&G Loop Checks 80 01APR12 12MAY12 42 0 21
CN70090040 7009 F&G Functional Tests and SAT 80 08APR12 19MAY12 42 0 21

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 16 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

71 - Fire Water and Foam System


Fire Water and Foam Sub-Systems
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO71000060 7100 Pumps Installations 31 22JAN11A 25FEB12 32 92 6
CO71000065 7100 Steel Structures/Shelters erection 27 19FEB11A 03MAR12 39 100 37
CO71000070 7100 Piping & Supports erection 100 30OCT10A 17MAR12 53 97 17
CO71000090 7100 Sheds covering & Roofing/Cladding 22 01JUL11A 17MAR12 53 5 37
CO71000040 7100 Electrical cables laying 14 02JUL11A 24MAR12 60 80 37
CO71000045 7100 Electrical cable connections 30 21JUL11A 31MAR12 67 86 37
CO71000095 7100 Piping Hydrotest 100 23JUL11A 31MAR12 67 44 17
CO71000100 7100 Fire fighting equipments 1 21JUL11A 14APR12 81 8 49
CO71000075 7100 Electrical equipment installations 14 01APR12 14APR12 14 0 37
CO71000050 7100 Painting works 68 25DEC10A 19MAY12 116 86 7
CO71000055 7100 Field Instrument installations 30 04JUN11A 26MAY12 123 72 7
CO71000080 7100 Instrument cable laying [Secondary] 20 11JUN11A 26MAY12 123 78 7
CO71000110 7100 Insulation works 1 24AUG11A 16JUN12 144 5 7

7101 - Fire Water Pumps & Tanks (incl. FW Ring)


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC71010090 7101 Electrical (Cables, Motors) 7 17SEP11A 24SEP11A 0 100
PC71010099 7101 Instrumentation 10 09SEP11A 29FEB12 36 90 0
PC71010080 7101 Piping Systems: Flushing/Reinst 20 17SEP11A 29FEB12 36 33 44
PC71010030 7101 Pumps PA-71-01A/B; 02A/B; Electric Driven 14 12NOV11A 29FEB12 36 80 2
PC71010015 7101 Storage Tanks RB-71-01B 35 21JAN12A 29FEB12 36 90 17
PC71010040 7101 Dies. Emg. DD-71-01B , Driven Pump PA-71-03A/B 14 16FEB12 29FEB12 14 0 31
PC71010050 7101 Sub-System MC - 7101 [Partial] 0 29FEB12 0 0 31
COMMISSIONING
CN71010030 7101 Loop Checks & Functional Test 5 01MAR12 05MAR12 5 0 0
CN71010050 7101 LV Motors (2) no load test 3 03MAR12 05MAR12 3 0 0
CN71010090 7101 MV Motors (2) no load Test 6 01MAR12 06MAR12 6 0 5
CN71010060 7101 Pumps: final allignement and coupling 7 06MAR12 11MAR12 6 0 0
CN71010130 7101 Tanks filling with water 21 01MAR12 21MAR12 21 0 23
CN71010140 7101 FW Pumps (6) Run in - Recycle Mode 14 12MAR12 25MAR12 14 0 0
CN71010150 7101 FW Network: service test 14 18MAR12 31MAR12 14 0 0
CN7100RFSU 7101 Sub- System RFSU - 7101 [Partial] 0 31MAR12 0 0 0
Step 2: Gas in Plant
PRE-COMMISSIONING
PC71010045 7101 Dies. Emg. DD-71-01A 16 12NOV11A 17MAR12 53 80 27
PC71010010 7101 Storage Tanks RB-71-01A 35 31DEC11A 17MAR12 53 70 27
PC71010SMC 7101 Sub-System MC - 7101 [Final] 0 17MAR12 0 0 27
COMMISSIONING
CN7101RFSU 7101 Sub-System RFSU - 7101 - [Final] 0 31MAR12 0 0 13

7102 - Area 800


Step 2: Gas in Plant
PRE-COMMISSIONING
PC71020099 7102 Instrumentation 17 09SEP11A 24MAR12 60 20 11
PC71020070 7102 FW Hydrants, Hose Reels 21 04MAR12 24MAR12 21 0 27
PC71020090 7102 Electrical (Cables, Motors) 17 08MAR12 24MAR12 17 0 11
PC71020050 7102 Water Deluge Valve Skids 15 01APR12 15APR12 15 0 19
PC71020100 7102 Sub-System MC - 7102 0 15APR12 0 0 19
COMMISSIONING
CN71020030 7102 Loop Checks & Functional Test 15 25MAR12 08APR12 15 0 11
CN71020150 7102 FW Network: service test 15 09APR12 23APR12 15 0 11
CN7102RFSU 7102 Sub-System RFSU - 7102 0 23APR12 0 0 11

7103 - Fire Water Network Area K.O Drums+200/500


Step 2: Gas in Plant
PRE-COMMISSIONING
PC71030099 7103 Instrumentation 17 09SEP11A 31MAR12 67 20 18
PC71030090 7103 Electrical (Cables, Motors) 17 15MAR12 31MAR12 17 0 18
COMMISSIONING
CN71030150 7103 FW Network: service test 16 01APR12 16APR12 16 0 18
CN7103RFSU 7103 Sub-System RFSU - 7103 0 16APR12 0 0 18

7104 - Fire Water Network Area -100&400


Step 1A/1B: Up to TK1 Gas Turbine solo Run
COMMISSIONING
CN71040150 7104 FW Network: service test 11 04MAR12* 17MAR12 14 0 14
CN7104RFSU 7104 Sub-System RFSU - 7104 0 17MAR12 0 0 14

7105 - Storage Area


Step 3 : Balance
PRE-COMMISSIONING
PC71050099 7105 Instrumentation 31 09SEP11A 07APR12 74 45 18
PC71050090 7105 Electrical (Cables) 31 11MAR12 07APR12 28 0 18
PC71050080 7105 Piping Systems: Flushing/Reinst 17 26JUL11A 14APR12 81 45 46
PC71050050 7105 Water Deluge Valve Skids 20 25MAR12 14APR12 21 0 46
PC71050060 7105 Water Sprinkler Systems 20 25MAR12 14APR12 21 0 169

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 17 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

PC71050070 7105 FW Hydrants, Hose Reels 20 25MAR12 14APR12 21 0 46


PC71050SMC 7105 Sub-System MC - 7105 0 14APR12 0 0 46
COMMISSIONING
CN71050030 7105 Loop Checks & Functional Test 20 08APR12 28APR12 21 0 18
CN71050150 7105 FW Network: service test 11 29APR12 12MAY12 14 0 18
CN7105RFSU 7105 Sub-System RFSU - 7105 0 12MAY12 0 0 18

7106 - Fire Training Area


Step 3 : Balance
PRE-COMMISSIONING
PC71060080 7106 Piping Systems: Flushing/Reinst 56 25MAR12* 19MAY12 56 0 7
PC71060090 7106 Electrical (Cables) 12 08MAY12 19MAY12 12 0 14
PC71060099 7106 Instrumentation 12 07JAN12A 26MAY12 123 20 7
PC71060SMC 7106 Sub-System MC - 7106 0 26MAY12 0 0 7
COMMISSIONING
CN71060150 7106 FW Network: service test 10 27MAY12 16JUN12 21 0 7
CN7106RFSU 7106 Sub-System RFSU - 7106 0 16JUN12 0 0 7

7107 - Foam System


Step 2: Gas in Plant
PRE-COMMISSIONING
PC71070090 7107 Electrical (Cables, Motors) 15 24MAR12 07APR12 15 0 18
PC71070080 7107 Piping Systems: Flushing/Reinst 30 27AUG11A 21APR12 88 45 10
PC71070099 7107 Instrumentation 22 09SEP11A 21APR12 88 20 11
PC71070050 7107 Foam Deluge Valve Skids 47 06MAR12 21APR12 47 0 162
PC71070060 7107 Fixed Foam Systems (Tanks) 47 06MAR12 21APR12 47 0 162
PC71070070 7107 Foam Monitors 47 06MAR12 21APR12 47 0 162
PC71070010 7107 Foam Concentrate Storage Tank RA-71-02 8 14APR12 21APR12 8 0 162
PC71070030 7107 Pumps PA-71-04A/B 8 14APR12 21APR12 8 0 10
PC71070SMC 7107 Sub-System MC - 7107 0 21APR12 0 0 162
COMMISSIONING
CN71070050 7107 LV Ele Motors (2) no load test 6 16APR12 21APR12 6 0 10
CN71070060 7107 Pumps: final allignement and coupling 3 22APR12 24APR12 3 0 10
CN71070130 7107 Tanks filling with foam 20 25APR12 08MAY12 14 0 10
CN71070140 7107 Foam Pumps (2) Run in - Recycle Mode 6 09MAY12 15MAY12 7 0 10
CN71070030 7107 Loop Checks & Functional Test 20 22APR12 19MAY12 28 0 11
CN71070150 7107 Foam Network: Servicetest 32 14MAY12 20MAY12 7 0 10
CN7107RFSU 7107 Sub-System RFSU - 7107 0 20MAY12 0 0 10

72 - Inert Gas and CO2 System


7201 - CO2 System CPF Main Substation
Step 2: Gas in Plant
PRE-COMMISSIONING
PC72010010 7201 CO2 Skid 58 17SEP11A 03MAR12 39 95 14
PC72010020 7201 CO2 Distribution Network 58 17SEP11A 03MAR12 39 80 14
PC72010SMC 7201 Sub-System MC - 7201 0 03MAR12 0 0 14
COMMISSIONING
CN72010010 7201 CO2 System Commissioning 10 04MAR12 17MAR12 14 0 14
CN7201RFSU 7201 Sub-System RFSU - 7201 0 17MAR12 0 0 14

7202 - CO2 System CPF Satellite SS (TUCO)


Step 2: Gas in Plant
PRE-COMMISSIONING
PC72020010 7202 CO2 Skid 47 17SEP11A 03MAR12 39 95 15
PC72020020 7202 CO2 Distribution Network 47 17SEP11A 03MAR12 39 70 15
PC72020SMC 7202 Sub-System MC - 7202 0 03MAR12 0 2 15
COMMISSIONING
CN72020010 7202 CO2 System Commissioning 11 03MAR12 16MAR12 14 0 15
CN7202RFSU 7202 Sub-System RFSU - 7202 0 16MAR12 0 0 15

7203 - CO2 System CPF Central Control Bdlg


Step 2: Gas in Plant
PRE-COMMISSIONING
PC72030010 7203 CO2 Skid 47 17SEP11A 03MAR12 39 95 15
PC72030020 7203 CO2 Distribution Network 47 17SEP11A 03MAR12 39 70 15
PC72030SMC 7203 Sub-System MC - 7203 0 03MAR12 0 0 15
COMMISSIONING
CN72030010 7203 CO2 System Commissioning 11 03MAR12 16MAR12 14 0 15
CN7203RFSU 7203 Sub-System RFSU - 7203 0 16MAR12 0 0 15

77 - HVAC System
HVAC Sub-Systems
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO77000060 7700 Electrical cabel laying 160 05FEB11A 10MAR12 46 94 0
CO77000070 7700 Electrical cable connections 1 22OCT11A 17MAR12 53 82 0

7701 - HVAC Main Sub Station


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC77010010 7701 HVAC - Main SS 20 01JUN11A 20JUN11A 0 100
PC77010SMC 7701 Sub System MC - 7701 0 20JUN11A 0 100

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 18 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

7702 - HVAC TUCO Satellite SS


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC77020020 7702 HVAC - TUCO Satellite SS 20 01JUN11A 20JUN11A 0 100
PC77020SMC 7702 Sub System MC - 7702 0 20JUN11A 0 100
COMMISSIONING
CN77020020 7702 HVAC - TUCO Satellite SS Commissioning 20 20JUN11A 17MAR12 53 95 14
CN7702RFSU 7702 Sub System RFSU - 7702 0 17MAR12 0 0 14

7703 - HVAC Flare Satellite SS


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC77030030 7703 HVAC - FLARE Satellite SS 9 02JUL11A 25JUL11A 0 100
PC77030SMC 7703 Sub System MC - 7703 0 25JUL11A 0 100
COMMISSIONING
CN77030030 7703 HVAC - FLARE Satellite SS Commissioning 7 02JUL11A 17MAR12 53 90 14
CN7703RFSU 7703 Sub System RFSU - 7703 0 17MAR12 0 0 14

7704 - HVAC Central Control Building


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC77040040 7704 HVAC - Central Control Building 25 18JUL11A 11AUG11A 0 100
PC77040SMC 7704 Sub System MC - 7704 0 11AUG11A 0 100
COMMISSIONING
CN77040040 7704 HVAC - Central Control Building Commissioning 16 26SEP11A 29FEB12 36 90 31
CN7704RFSU 7704 Sub System RFSU - 7704 0 29FEB12 0 0 31

7705 - HVAC Laboratory Building


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC77050050 7705 HVAC - Laboratory Building 20 12NOV11A 17MAR12 53 22 0
PC77050SMC 7705 Sub System MC - 7705 0 17MAR12 0 0 14
COMMISSIONING
CN77050050 7705 HVAC - Laboratory Building Commissioning 11 18MAR12 31MAR12 14 0 0
CN7705RFSU 7705 Sub System RFSU - 7705 0 31MAR12 0 0 0

80 - Main Power Gener. & Distrib. (High Voltage)


8001- 60 KV OHL "A" & GIS
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC80010052 8001 60kV OHL - Electrical Tests 25 04NOV10A 28NOV10A 0 100
PC80010054 8001 60kV OHL - Telecoms Tests 25 04NOV10A 28NOV10A 0 100
PC80010030 8001 60kV MLN Tie-In - Tests prior to Energize 15 14NOV10A 28NOV10A 0 100
PC80010182 8001 60kV Switchyard - Electrical Tests 14 19NOV10A 02DEC10A 0 100
PC80010710 8001 60kV GIS EH-80-01: Check &Tests 62 13OCT10A 13DEC10A 0 100
PC80010720 8001 Protection Relays & Panels: Check & Tests 32 01JAN11A 01FEB11A 0 100
PC80010730 8001 Control Panels & Relays: Check & Tests 32 01JAN11A 01FEB11A 0 100
PC80010740 8001 Fiscal Metering Panel: Check & Tests 32 01JAN11A 01FEB11A 0 100
PC80010752 8001 Cables: Check & Tests 28 01FEB11A 28FEB11A 0 100
PC80010SMC 8001 Sub System MC - 8001 0 28FEB11A 0 100
COMMISSIONING
CN80010010 8001 60kV OHL- A - Energization 2 01MAR11A 02MAR11A 0 100
CN8001RFSU 8001 Sub System RFSU - 8001 0 24MAY11A 0 100
CN80010030 8001 60kV GIS - Energization & Tests 2 01MAY11A 23DEC11A 0 100

8002 - 60 KV OHL "B"


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC80020752 8002 Cables: Check & Tests 28 01FEB11A 28FEB11A 0 100
PC80020SMC 8002 Sub System MC - 8002 0 28FEB11A 0 100
COMMISSIONING
CN80020020 8002 60kV OHL- B - Energization 2 01MAR11A 02MAR11A 0 100
CN8002RFSU 8002 Sub System RFSU - 8002 0 02MAY11A 0 100
CN80020030 8002 60kV GIS - Energization & Tests 2 01MAY11A 23DEC11A 0 100

8003 - 60 KV Cables From GIS TO MV Panels


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC80030030 8003 Power Trafo 60/5,5Kv (ET-80-01A/B) -Check & Test 20 01MAR11A 20MAR11A 0 100
PC80030752 8003 Cables: Check & Tests 7 20MAR11A 25MAR11A 0 100
PC80030SMC 8003 Sub System MC - 8003 0 25MAR11A 0 100
COMMISSIONING
CN80030020 8003 60kV Cable Energization 2 28MAR11A 23DEC11A 0 100
CN80030030 8003 Trafo 60/5,5Kv (ET-80-01A/B) -Energization 3 26NOV11A 23DEC11A 0 100
CN8003RFSU 8003 Sub System RFSU - 8003 0 24DEC11A 0 100

81 - Main Power Gener. & Distrib. (Med. Voltage)


8101 - 5,5Kv Power Distrb Switc, Main Substation
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC81010814 8101 MV Earth.Switchgears (EY-81-01A/B) -Check &Tests 8 13MAR11A 20MAR11A 0 100
PC81010817 8101 MV Bus Ducts (EV-81-01A/B) -Check &Tests 8 20MAR11A 24MAR11A 0 100
PC81010SMC 8101 Sub-System MC - 8101 0 24MAR11A 0 100
PC81010813 8101 MV Switchgear (EM-81-01) -Check &Tests 21 10MAR11A 25MAR11A 0 100

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 19 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

COMMISSIONING
CN81010030 8101 MV Swichgear EM-81-01-Energization & Tests 2 09APR11A 23DEC11A 0 100
CN81010040 8101 MV Earth.Swgs EY-81-01A/B - Energization & Tests 2 09APR11A 23DEC11A 0 100
CN8101RFSU 8101 Sub System RFSU - 8101 0 24DEC11A 0 100

8102 - 5,5 Kv MV Distrib For Satellite S.Station


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC81020812 8102 Power Trafo 5,5/0,4 Kv (ET-82-05-A/B) Check&Test 30 01MAR11A 25MAR11A 0 100
PC81020827 8102 HV Electrical Cables Laying & Terminations 30 01MAR11A 25MAR11A 0 100
PC81020SMC 8102 Sub-System MC - 8102 0 25MAR11A 0 100
COMMISSIONING
CN81020010 8102 Trafo ET-82-05A Energization 2 26OCT11A 23DEC11A 0 100
CN81020020 8102 Trafo ET-82-05B Energization 2 26OCT11A 23DEC11A 0 100
CN8102RFSU 8102 Sub-System RFSU - 8102 0 24DEC11A 0 100

8103 - 5,5 Kv MV Distrib For Flare Ele S.Station


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC81030812 8103 Power Trafo 5,5/0,4 Kv (ET-82-04-A/B) Check&Test 17 15JUL11A 31JUL11A 0 100
PC81030827 8103 MV Electrical Cables Laying & Terminations 31 16JUL11A 12AUG11A 0 100
PC81030SMC 8103 Sub-System MC - 8103 0 12AUG11A 0 100
COMMISSIONING
CN81030010 8103 Trafo ET-82-04A Energization 2 26FEB12* 29FEB12 4 0 5
CN81030020 8103 Trafo ET-82-04B Energization 2 26FEB12 29FEB12 4 0 5
CN8103RFSU 8103 Sub-System RFSU - 8103 0 29FEB12 0 0 31

8104 - 5,5 Kv MV Distrib For CPF-EN-82-03


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC81040827 8104 MV Electrical Cables Laying & Terminations 31 01MAR11A 25MAR11A 0 100
PC81040812 8104 Power Trafo 5,5/0,4 Kv (ET-82-03-A/B) Check&Test 17 15MAR11A 25MAR11A 0 100
PC81040SMC 8104 Sub-System MC - 8104 0 25MAR11A 0 100
COMMISSIONING
CN81040010 8104 Trafo ET-82-03A Energization 2 26NOV11A 23DEC11A 0 100
CN81040020 8104 Trafo ET-82-03B Energization 3 26NOV11A 23DEC11A 0 100
CN8104RFSU 8104 Sub-System RFSU - 8104 0 24DEC11A 0 100

8105 - 5,5 Kv MV Distrib For CPF-EN-82-01


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC81050827 8105 MV Electrical Cables Laying & Terminations 31 01MAR11A 25MAR11A 0 100
PC81050812 8105 Power Trafo 5,5/0,4 Kv (ET-82-04-A/B) Check&Test 17 15MAR11A 25MAR11A 0 100
PC81050SMC 8105 Sub-System MC - 8105 0 25MAR11A 0 100
COMMISSIONING
CN81050010 8105 Trafo ET-82-01A Energization 2 26NOV11A 23DEC11A 0 100
CN81050020 8105 Trafo ET-82-01B Energization 2 26NOV11A 23DEC11A 0 100
CN8105RFSU 8105 Sub-System RFSU - 8105 0 24DEC11A 0 100

8106 - 5,5 Kv MV Distrib For CPF-EN-82-02


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC81060827 8106 MV Electrical Cables Laying & Terminations 31 01MAR11A 25MAR11A 0 100
PC81060812 8106 Power Trafo 5,5/0,4 Kv (ET-82-02-A/B) Check&Test 17 15MAR11A 25MAR11A 0 100
PC81060SMC 8106 Sub-System MC - 8106 0 25MAR11A 0 100
COMMISSIONING
CN81060010 8106 Trafo ET-82-02A Energization 2 26NOV11A 23DEC11A 0 100
CN81060020 8106 Trafo ET-82-02B Energization 2 26NOV11A 23DEC11A 0 100
CN8106RFSU 8106 Sub-System RFSU - 8106 0 24DEC11A 0 100

8119 - 5.5kV Capacitor Banks


Step 2: Gas in Plant
PRE-COMMISSIONING
PC81010815 8119 PF Correction Panels (ER-81-01A/B) -Check &Tests 8 13MAR11A 31MAY12 128 95 3
PC81010816 8119 PF Correction Panels (ER-81-02A/B) -Check &Tests 8 13MAR11A 31MAY12 128 95 3
PC81190SMC 8119 Sub-System MC - 8119 0 31MAY12 0 0 122
COMMISSIONING
CN81010060 8119 PF Panels ER-81-01A/B; 02A/B - Energiz & Tests 2 09APR11A 23JUN12 151 50 0
CN81190030 8119 Capacitory Banks Commissioning 5 19JUN12 23JUN12 5 0 0
CN8119RFSU 8119 Sub-System RFSU - 8119 0 23JUN12 0 0 0

82 - Main Power Gener. & Distrib. (Low Voltage)


82 - Main Power Gner. & Distrib./Light (Low Vol)
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO82000010 8200 Electrical cable laying 40 08JAN11A 03MAR12 39 85 51
CO82000040 8200 Electrical panels installation 40 25DEC10A 10MAR12 46 97 44
CO82000020 8200 Electrical cable connections 40 19FEB11A 10MAR12 46 67 51
CO82000030 8200 Electrical equipment installation 40 16APR11A 10MAR12 46 42 51
CO82000050 8200 Lighting installation (Poles, Foodlight, etc.) 60 06JUN10A 24MAR12 60 53 44

8201 - 400V - LV Switch. CPF-EN-82-01 (Main SS)


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82010937 8201 LV Switchgears -Check & Tests CPF-EN-82-01 30 01APR11A 30APR11A 0 100

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 20 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

PC82010SMC 8201 Sub-System MC - 8201 0 30APR11A 0 100


COMMISSIONING
CN82010030 8201 LV Switchgears EN-82-01- Energiz & Tests 4 01MAY11A 25JAN12A 0 100
CN8201RFSU 8201 Sub-System RFSU - 8201 0 25JAN12A 0 100

8202 - 400V - LV Switch. CPF-EN-82-02 (Main SS)


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82020937 8202 LV Switchgears -Check & Tests CPF-EN-82-02 30 01APR11A 30APR11A 0 100
PC82020SMC 8202 Sub-System MC - 8202 0 30APR11A 0 100
COMMISSIONING
CN82020030 8202 LV Switchgears EN-82-02 - Energization & Tests 4 01MAY11A 25JAN12A 0 100
CN8202RFSU 8202 Sub-System RFSU - 8202 0 25JAN12A 0 100

8203 - 400V - LV Switch. CPF-EN-82-03 (Main SS)


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82030937 8203 LV Switchgears -Check & Tests CPF-EN-82-03 30 01APR11A 30APR11A 0 100
PC82030SMC 8203 Sub-System MC - 8203 0 30APR11A 0 100
COMMISSIONING
CN82030030 8203 LV Switchgears EN-82-03 - Energization & Tests 4 01MAY11A 25JAN12A 0 100
CN8203RFSU 8203 Sub-System RFSU - 8203 0 25JAN12A 0 100

8204 - 400V - LV Switch. CPF-EN-82-04 (Flare SS)


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82040937 8204 LV Switchgears -Check & Tests CPF-EN-82-04 16 15JUL11A 25AUG11A 0 100
PC82040SMC 8204 Sub-System MC - 8204 0 25AUG11A 0 100
COMMISSIONING
CN82040030 8204 LV Switchgears EN-82-04 - Energization & Tests 6 01MAR12 06MAR12 6 0 5
CN8204RFSU 8204 Sub-System RFSU - 8204 0 06MAR12 0 0 5

8205 - 400V - LV Switch. CPF-EN-82-05 (TUCO SS)


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82050937 8205 LV Switchgears -Check & Tests CPF-EN-82-05 30 01APR11A 30APR11A 0 100
PC82050SMC 8205 Sub-System MC - 8205 0 30APR11A 0 100
COMMISSIONING
CN82050030 8205 LV Switchgears EN-82-05 - Energization & Tests 4 01MAY11A 25JAN12A 0 100
CN8205RFSU 8205 Sub-System RFSU - 8205 0 25JAN12A 0 100

8206 - Main Normal Ligh. Distribution (Main SS)


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82060901 8206 Trafo 0,4/0,4Kv Check & Test 6E0-ET-82-01 5 15JUL11A 25AUG11A 0 100
PC82060928 8206 Aux. Power Trafo 0,4/0,4Kv Check & Tests 3 15JUL11A 25AUG11A 0 100
PC82060937 8206 LV Switchgears -Check & Tests 6E0-EN-82-01/2/3 17 15JUL11A 25AUG11A 0 100
PC82060991 8206 LV Electrical Cable - Check & Tests 8 24JUL11A 25AUG11A 0 100
PC82060SMC 8206 Sub-System MC - 8206 0 25AUG11A 0 100
COMMISSIONING
CN82060010 8206 Trafos 6E0-ET-82-01 - Energization 3 22JAN12A 25JAN12A 0 100
CN82060030 8206 LV Switchgear 6E0-EN-82-01 - Energiz & Tests 2 23JAN12A 25JAN12A 0 100
CN8206RFSU 8206 Sub-System RFSU - 8206 0 25JAN12A 0 100

8247 - External Lighting Area 100


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82470010 8247 External Lighting System Area 100 59 09FEB12* 31MAR12 52 0 50
PC82470SMC 8247 Sub-System MC - 8247 0 31MAR12 0 0 50
COMMISSIONING
CN82470010 8247 External Lighting System Area 100 - Comm 4 31MAR12 03APR12 4 0 50
CN82470020 8247 External Lighting Sys Area 100 - Lux Measurement 8 03APR12 10APR12 8 0 50
CN8247RFSU 8247 Sub-System RFSU - 8247 0 10APR12 0 0 50

8248 - External Lighting Area 200


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82480010 8248 External Lighting System Area 200 20 09FEB12* 31MAR12 52 0 46
PC82480SMC 8248 Sub-System MC - 8248 0 31MAR12 0 0 46
COMMISSIONING
CN82480010 8248 External Lighting System Area 200 - Comm 5 31MAR12 04APR12 5 0 46
CN82480020 8248 External Lighting Sys Area 200 - Lux Measurement 11 04APR12 14APR12 11 0 46
CN8248RFSU 8248 Sub-System RFSU - 8248 0 14APR12 0 0 46

8249 - External Lighting Area 350


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82490010 8249 External Lighting System Area 350 39 09FEB12* 31MAR12 52 0 52
PC82490SMC 8249 Sub-System MC - 8249 0 31MAR12 0 0 52
COMMISSIONING
CN82490010 8249 External Lighting System Area 350 - Comm 3 31MAR12 02APR12 3 0 52
CN82490020 8249 External Lighting Sys Area 350 - Lux Measurement 7 02APR12 08APR12 7 0 52
CN8249RFSU 8249 Sub-System RFSU - 8249 0 08APR12 0 0 52

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 21 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

8250 - External Lighting Area 400


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82500010 8250 External Lighting System Area 400 10 04JAN12A 14JAN12A 0 100
PC82500SMC 8250 Sub-System MC - 8250 0 14JAN12A 0 100
COMMISSIONING
CN82500010 8250 External Lighting System Area 400 - Comm 4 15JAN12A 08APR12 75 75 20
CN82500020 8250 External Lighting Sys Area 400 - Lux Measurement 8 08APR12 15APR12 8 0 45
CN8250RFSU 8250 Sub-System RFSU - 8250 0 15APR12 0 0 45

8251 - External Lighting Area 450


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82510010 8251 External Lighting System Area 450 10 04JAN12A 14JAN12A 0 100
PC82510SMC 8251 Sub-System MC - 8251 0 14JAN12A 0 100
COMMISSIONING
CN82510010 8251 External Lighting System Area 450 - Comm 4 30APR12 03MAY12 4 0 20
CN82510020 8251 External Lighting Sys Area 450 - Lux Measurement 8 03MAY12 10MAY12 8 0 20
CN8251RFSU 8251 Sub-System RFSU - 8251 0 10MAY12 0 0 20

8252 - External Lighting Area 500


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82520010 8252 External Lighting System Area 500 - Precom. 8 04JAN12A 24MAR12 60 90 53
PC82520SMC 8252 Sub-System MC - 8252 0 24MAR12 0 0 53
COMMISSIONING
CN82520010 8252 External Lighting System Area 500 - Comm 9 24MAR12 01APR12 9 0 53
CN82520020 8252 External Lighting Sys Area 500 - Lux Measurement 7 01APR12 07APR12 7 0 53
CN8252RFSU 8252 Sub-System RFSU - 8252 0 07APR12 0 0 53

8253 - External Lighting Area 600


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82530010 8253 External Lighting System Area 600 - Precom. 11 09APR12 19APR12* 11 0 30
PC82530SMC 8253 Sub-System MC - 8253 0 19APR12 0 0 30
COMMISSIONING
CN82530010 8253 External Lighting System Area 600 - Comm 4 19APR12 22APR12 4 0 30
CN82530020 8253 External Lighting Sys Area 600 - Lux Measurement 9 22APR12 30APR12 9 0 30
CN8253RFSU 8253 Sub-System RFSU - 8253 0 30APR12 0 0 30

8254 - External Lighting Area 700


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82540010 8254 External Lighting System Area 700 - Precom. 13 25MAR12 06APR12* 13 0 44
PC82540SMC 8254 Sub-System MC - 8254 0 06APR12 0 0 44
COMMISSIONING
CN82540010 8254 External Lighting System Area 700 - Comm 5 06APR12 10APR12 5 0 44
CN82540020 8254 External Lighting Sys Area 700 - Lux Measurement 7 10APR12 16APR12 7 0 44
CN8254RFSU 8254 Sub-System RFSU - 8254 0 16APR12 0 0 44

8255 - External Lighting Area 800


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82550010 8255 External Lighting System Area 800 - Precom. 8 25MAR12 01APR12* 8 0 50
PC82550SMC 8255 Sub-System MC - 8255 0 01APR12 0 0 50
COMMISSIONING
CN82550010 8255 External Lighting System Area 800 - Comm 3 01APR12 03APR12 3 0 50
CN82550020 8255 External Lighting Sys Area 800 - Lux Measurement 8 03APR12 10APR12 8 0 50
CN8255RFSU 8255 Sub-System RFSU - 8255 0 10APR12 0 0 50

8256 - External Lighting Area CCB


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82560010 8256 External Lighting System CCB - Precom. 7 25MAR12 31MAR12 7 0 50
PC82560SMC 8256 Sub-System MC - 8256 0 31MAR12 0 0 50
COMMISSIONING
CN82560010 8256 External Lighting System CCB - Comm 4 31MAR12 03APR12 4 0 50
CN82560020 8256 External Lighting System CCB - Lux Measurement 8 03APR12 10APR12 8 0 50
CN8256RFSU 8256 Sub-System RFSU - 8256 0 10APR12 0 0 50

8257 - External Lighting Laboratory


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82570010 8257 External Lighting System Laboratory - Precom. 9 25MAR12 02APR12 9 0 48
PC82570SMC 8257 Sub-System MC - 8257 0 02APR12 0 0 48
COMMISSIONING
CN82570010 8257 External Lighting System Laboratory - Comm 4 02APR12 05APR12 4 0 48
CN82570020 8257 External Lighting System LAB - Lux Measurement 8 05APR12 12APR12 8 0 48
CN8257RFSU 8257 Sub-System RFSU - 8257 0 12APR12 0 0 48

8258 - Ext. Lighting Satellite Sub Station TUCO


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82580010 8258 External Lighting System Sat. SS TUCO - Precom. 10 04JAN12A 14JAN12A 0 100
PC82580SMC 8258 Sub-System MC - 8258 0 14JAN12A 0 100

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 22 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

COMMISSIONING
CN82580010 8258 External Lighting System Sat. SS TUCO - Comm 4 15JAN12A 25JAN12A 0 100
CN82580020 8258 Ext. Lighting Sys Sat. SS TUCO - Lux Measurement 8 08APR12 15APR12 8 0 45
CN8258RFSU 8258 Sub-System RFSU - 8258 0 15APR12 0 0 45

8259 - Ext. Lighting Satellite Sub Station Flare


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC82590010 8259 External Lighting System Sat. SS Flare - Precom. 8 30MAR12 06APR12 8 0 44
PC82590SMC 8259 Sub-System MC - 8259 0 06APR12 0 0 44
COMMISSIONING
CN82590010 8259 External Lighting System Sat. SS Flare - Comm 4 06APR12 09APR12 4 0 44
CN82590020 8259 Ext Lighting Sys Sat. SS Flare - Lux Measurement 8 09APR12 16APR12 8 0 44
CN8259RFSU 8259 Sub-System RFSU - 8259 0 16APR12 0 0 44

84 - Emergency Power (Low Voltage)


Emergency Power (LV)
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO84000040 8400 Electrical Cable Laying 10 19JAN11A 17MAR12 53 81 2
CO84000050 8400 Electricla Equipments installation 10 29DEC10A 24MAR12 60 96 2
CO84000030 8400 Electrical Cable Connections 10 19JAN11A 24MAR12 60 74 2

8401 - 400V LV Emerg. Switchgear Distrib For CPF


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC84010941 8401 Em. Switchgear -Check & Tests 15 24SEP11A 14OCT11A 0 100
PC84010951 8401 Emergency Gener. 6PO-EG-84-01 15 24SEP11A 14OCT11A 0 100
PC84010SMC 8401 Sub-System MC - 8401 0 14OCT11A 0 100
PC84010101 8401 LV Electrical Cables -Check & Tests 21 24SEP11A 09DEC11A 0 100
COMMISSIONING
CN84010020 8401 Em. Distrib. Boards/Panels - Energiz & Tests 16 09JAN12A 25JAN12A 0 100
CN84010010 8401 LV Switchgear EX-84-01 - Energiz & Tests 18 17SEP11A 29FEB12 36 95 31
CN84010040 8401 Emergency Gener. 6PO-EG-84-01 Load Tests 13 11JAN12A 29FEB12 36 95 31
CN8401RFSU 8401 Sub-System RFSU - 8401 0 29FEB12 0 0 31

8402 - Emerg. Lighting Sytem - CPF


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC84020010 8402 Emer. Lighting System Area 100 - Precom. 26 12NOV11A 25NOV11A 0 100
PC84020020 8402 Emer. Lighting System Area 200 - Precom. 26 12NOV11A 25NOV11A 0 100
PC84020030 8402 Emer. Lighting System Area 300 - Precom. 26 12NOV11A 25NOV11A 0 100
PC84020050 8402 Emer. Lighting System Area 400 - Precom. 26 11MAR12 31MAR12 21 0 30
PC84020070 8402 Emer. Lighting System Area 500 - Precom. 16 18MAR12 31MAR12 14 0 2
PC84020130 8402 Emer. Lighting System CCB - Precom. 16 18MAR12 31MAR12 14 0 30
PC84020140 8402 Emer. Lighting System LAB - Precom. 16 18MAR12 31MAR12 14 0 30
PC84020150 8402 Emer. Lighting System Sat. SS TUCO - Precom. 16 18MAR12 31MAR12 14 0 30
PC84020100 8402 Emer. Lighting System Area 700 - Precom. 16 01APR12 14APR12 14 0 2
PC84020110 8402 Emer. Lighting System Area 800 - Precom. 16 01APR12 14APR12 14 0 16
PC84020160 8402 Emer. Lighting System Sat. SS FLARE - Precom. 16 01APR12 14APR12 14 0 16
PC84020060 8402 Emer. Lighting System Area 450 - Precom. 26 15APR12 28APR12 14 0 2
PC84020090 8402 Emer. Lighting System Area 600 - Precom. 16 15APR12 28APR12 14 0 2
PC84020SMC 8402 Sub-System MC - 8402 0 28APR12 0 0 2
COMMISSIONING
CN84020010 8402 Emer. Lighting System CPF - Energization 15 29APR12 13MAY12 15 0 2
CN84020020 8402 Emer. Lighting System CPF - Lux Measurement 15 14MAY12 28MAY12 15 0 2
CN8402RFSU 8402 Sub-System RFSU - 8402 0 28MAY12 0 0 2

85 - Battery System and UPS


8501 - DC UPS Distribution CPF - Main S.S
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC85011031 8501 Main DC UPS 6E0-EF-8501 - Check & Tests 42 10JAN11A 20FEB11A 0 100
PC85011032 8501 Battery Banks -Check & Tests 42 10JAN11A 20FEB11A 0 100
PC85011033 8501 110VDC Aux. Switchboard -Check & Tests 40 20JAN11A 28FEB11A 0 100
PC85011037 8501 LV Electrical Cables -Check & Tests 40 20JAN11A 28FEB11A 0 100
PC85010SMC 8501 Sub-System MC - 8501 0 28FEB11A 0 100
COMMISSIONING
CN85010015 8501 Battery Banks - Commissioning 6 25FEB11A 02MAR11A 0 100
CN85010040 8501 110VDC Aux. Swg EE-85-01 - Energiz & Tests 6 25FEB11A 02MAR11A 0 100
CN85010010 8501 Main DC UPS 6E0-EF-85-01 - Commissioning 3 28FEB11A 02MAR11A 0 100
CN8501RFSU 8501 Sub-System RFSU - 8501 0 02MAR11A 0 100

8502 - AC UPS Distribution CPF - C.C.B


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC85020010 8502 CCB - Main AC UPS 5C0-EK-85-01 - Check & Tests 17 14JUL11A 30JUL11A 0 100
PC85020020 8502 CCB - Battery Banks -Check & Tests 17 14JUL11A 30JUL11A 0 100
PC85020030 8502 CCB - Distrib. Boards -Check & Tests 17 14JUL11A 30JUL11A 0 100
PC85020035 8502 CCB - LV Ele. Cables -Check & Tests 17 14JUL11A 30JUL11A 0 100
PC85020SMC 8502 Sub-System MC - 8502 0 30JUL11A 0 100

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 23 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

COMMISSIONING
CN85020020 8502 CCB - Battery Banks - Commissioning 15 25AUG11A 24SEP11A 0 100
CN85020030 8502 CCB - Distrib. Boards/Panels - Energiz & Tests 15 17SEP11A 24SEP11A 0 100
CN85020010 8502 CCB - Main AC UPS 5C0-EK-85-01 - 15 17SEP11A 25JAN12A 0 100
CN8502RFSU 8502 Sub-System RFSU - 8502 0 25JAN12A 0 100

86 - Telecom System
86CP - Telecomm Subsystems at CPF
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO86000010 8600 Electrical cable laying 1 07MAY11A 03MAR12 39 100 37
CO86000020 8600 Electrical cable connections 1 18MAY11A 10MAR12 46 69 37
CO86000030 8600 Laying of F.O. cables & Tele Cable Address 1 15JAN11A 17MAR12 53 96 37
CO86000050 8600 Batteries install. for Telec, Alarms, Radio link 1 08JUN11A 31MAR12 67 80 25
CO86000040 8600 TETRA Towers @ CPF 1 23MAR11A 14APR12 81 10 25
CO86000080 8600 CCTV System equipment installation 1 15JUN11A 25APR12 92 73 0
CO86000070 8600 Telecomm Equipments installation 1 20APR11A 30APR12 97 70 0
CO86000060 8600 Telecomm Cables connections 1 18AUG11A 30APR12 97 53 0
PRE-COMMISSIONING
PC86110020 8600 CPF - FO Backbone System - Precom. 15 01AUG11A 25NOV11A 0 100
PC86390120 8600 CPF - Hot Line System - Precom. 15 01AUG11A 09DEC11A 0 100
PC86450040 8600 CPF - LAN Core Switch - Precomm. 15 27NOV11A 10DEC11A 0 100
PC86400090 8600 CPF - LAN System - Precom. 15 24SEP11A 03MAR12 39 90 81
PC86260050 8600 CPF - PAGA Buildings System - Precom. 15 01MAR12* 14MAR12 14 0 70
PC86030030 8600 CPF - TETRA (UHF) System - Precom. 15 15APR12 28APR12 14 0 25
PC86280040 8600 CPF - Telephone System (PABX) - Precom. 15 24SEP11A 30APR12 97 50 23
PC86070080 8600 CPF - CCTV Security System - Precom. 15 26APR12 09MAY12 14 0 0
PC86270060 8600 CPF - PAGA Field System - Precom. 15 01MAY12 14MAY12 14 0 0
PC86060070 8600 CPF - CCTV Process System - Precom. 15 10MAY12 23MAY12 14 0 0
PC86100022 8600 CPF - VHF fixed radio System - Precom. 15 15MAY12 28MAY12 14 0 0
PC86CP0SMC 8600 Sub-System MC - 86CP [CPF] 0 28MAY12 0 0 2
COMMISSIONING
CN86450110 8600 CPF - LAN Core Switch - Comm. 14 11DEC11A 24DEC11A 0 100
CN86110020 8600 CPF - FO Backbone/SDH System - Comm. 15 01MAR12* 07MAR12 7 0 84
CN86390100 8600 CPF - Hot Line System - Comm. 15 04MAR12* 10MAR12 7 0 81
CN86400090 8600 CPF - LAN System - Comm. 15 04MAR12 10MAR12 7 0 81
CN86260050 8600 CPF - PAGA Buildings System - Comm. 15 15MAR12 21MAR12 7 0 70
CN86030030 8600 CPF - TETRA (UHF) System - Comm. 15 29APR12 05MAY12 7 0 25
CN86280040 8600 CPF - Telephone System (PABX) - Comm. 15 01MAY12 07MAY12 7 0 23
CN86070080 8600 CPF - CCTV Security System - Comm. 15 10MAY12 16MAY12 7 0 7
CN86270060 8600 CPF - PAGA Field System - Comm. 15 15MAY12 21MAY12 7 0 9
CN86060070 8600 CPF - CCTV Process System - Comm. 15 24MAY12 30MAY12 7 0 0
CN86110030 8600 CPF - VHF fixed radio System - Comm. 14 29MAY12 30MAY12 2 0 0
CN86CPRFSU 8600 Sub-System RFSU - 86CP [CPF] 0 30MAY12 0 0 0

87 - Instrument System
ICSS Sub-Systems
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO87000050 8700 Cable Laying and Connections [Multicables] 88 08JAN11A 29FEB12 36 98 51
CO87000070 8700 Instruments Cabinets installation 1 26FEB11A 29FEB12 36 99 51
CO87000030 8700 ELICS Server Panels & RTU installation 1 19FEB11A 24MAR12 60 95 18
CO87000040 8700 J-Box installation 1 05FEB11A 31MAR12 67 79 34
CO87000060 8700 Electrical connection execution 1 24SEP11A 31MAR12 67 14 34
COMMISSIONING
CNM0000200 8700 ICSS Ready for Loop Check 0 01JAN12A 0 100

8701 - DCS System CPF


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC87010010 8701 DCS Precom. 97 13JUL11A 31MAR12 67 90 34
PC87010SMC 8701 Sub-System MC - 8701 0 31MAR12 0 0 34
COMMISSIONING
CN87010010 8701 DCS - Commis. and SAT 195 26OCT11A 07APR12 74 10 27
CN8701RFSU 8701 Sub-System RFSU - 8701[Partial] 0 07APR12 0 0 27
Step 3 : Balance
COMMISSIONING
CN87010020 8701 DCS - Comm and SAT 247 26OCT11A 29JUN12 157 0 2
CN87010030 8701 Sub-System RFSU - 8701 [Final] 0 29JUN12 0 0 2

8702 - ESD System


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC87020010 8702 ESD System Precom. 62 12NOV11A 31MAR12 67 90 35
PC87020SMC 8702 Sub-System MC - 8702 0 31MAR12 0 0 35
COMMISSIONING
CN8702RFSU 8702 Sub-System RFSU - 8702 [Partial] 0 31MAR12 0 0 60
CN87020005 8702 ESD - Commis. and SAT 177 26DEC11A 07APR12 74 2 40

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 24 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

Step 3 : Balance
COMMISSIONING
CN87020010 8702 ESD Commiss. and SAT 186 26DEC11A 29JUN12 157 0 2
CN87020020 8702 SubSystem RFSU - 8702 [Fianl] 0 29JUN12 0 0 2

8712 - ELICS
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC87120030 8712 ELICS - Precom. 38 24SEP11A 31MAR12 67 90 18
PC87120040 8712 Sub-System MC - 8712 0 31MAR12 0 0 35
COMMISSIONING
CN87120010 8712 ELICS - Commis. 21 11MAR12 31MAR12 21 0 18
CN87120020 8712 ELICS - SAT 72 01APR12 12MAY12 42 0 18
CN8712RFSU 8712 Sub-System RFSU - 8712 0 12MAY12 0 0 18

88 - Earthing System
88 - Earthing System - CPF
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO88000010 8800 Earthing Systems erection 100 04APR10A 30APR12 97 90 5

8801 - Earting System - CPF


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC88010120 8801 Earthing System Main SS - Precom. 31 21JUL11A 31AUG11A 0 100
PC88010040 8801 Earthing System Area 350 - Precom. 5 08NOV11A 12NOV11A 0 100
PC88010060 8801 Earthing System Area 450 - Precom. 5 08NOV11A 12NOV11A 0 100
PC88010170 8801 Earthing System Tetra Shelter - Precom. 21 24SEP11A 14DEC11A 0 100
PC88010150 8801 Earthing System Sat. SS TUCO - Precom. 90 27FEB11A 23DEC11A 0 100
PC88010160 8801 Earthing System Sat. SS FLARE - Precom. 17 27JUL11A 30DEC11A 0 100
PC88010130 8801 Earthing System CCB - Precom. 31 21JUL11A 29FEB12 36 90 66
PC88010100 8801 Earthing System Area 700 - Precom. 50 14SEP11A 29FEB12 36 95 66
PC88010020 8801 Earthing System Area 200 - Precom. 50 24SEP11A 29FEB12 36 80 66
PC88010050 8801 Earthing System Area 400 - Precom. 30 14OCT11A 29FEB12 36 95 66
PC88010010 8801 Earthing System Area 100 - Precom. 14 30OCT11A 29FEB12 36 75 66
PC88010070 8801 Earthing System Area 500 - Precom. 50 25AUG11A 30MAR12 66 85 36
PC88010110 8801 Earthing System Area 800 - Precom. 15 19OCT11A 30MAR12 66 90 36
PC88010030 8801 Earthing System Area 300 - Precom. 5 13NOV11A 30MAR12 66 70 36
PC88010140 8801 Earthing System Laboratory - Precom. 31 24SEP11A 31MAR12 67 80 35
PC88010090 8801 Earthing System Area 600 - Precom. 75 30AUG11A 30APR12 97 70 5
PC88010080 8801 Earthing System Area 550 - Precom. 5 26APR12 30APR12* 5 0 5
PC88010SMC 8801 Sub-System MC - 8801 0 30APR12 0 0 5
COMMISSIONING
CN8801RFSU 8801 Sub-System RFSU - 8801 0 30APR12 0 0 30

90 - CIVIL WORK SYSTEM


9901- Fencing CPF Site
Step 1A/1B: Up to TK1 Gas Turbine solo Run
COMMISSIONING
CN8837060 9901 Subsystem MC 9901 0 31MAR12* 0 0 183

8F - Cathodic Protection System


8C - Cathodic Protection - CPF
Step 1A/1B: Up to TK1 Gas Turbine solo Run
CONSTRUCTION
CO8C000010 8C Electrical cables laying 1 03SEP11A 17MAR12 53 45 20
CO8C000020 8C Electrical cables connections 1 08OCT11A 24MAR12 60 13 20
PRE-COMMISSIONING
PC8C000010 8C CPF - CPTR-2/3/4 - Precom. 30 01MAR12 14MAR12 14 0 16
PC8C000020 8C CPF - Fire Fighting CP System- Precom. 20 08NOV11A 28MAR12 64 80 16
PC8C000040 8C CPF - Hot Oil CP System- Precom. 20 08NOV11A 28MAR12 64 80 16
PC8C000030 8C CPF - Hot Closed Drain CP System- Precom. 20 19NOV11A 28MAR12 64 80 16
PC8C000SMC 8C Sub-System MC - 8C 0 28MAR12 0 0 37
COMMISSIONING
CN8C010020 8C CPF - Fire Fighting CP System- Comm. 20 29MAR12 18APR12 21 0 16
CN8C010030 8C CPF - Hot Closed Drain CP System- Comm. 20 29MAR12 18APR12 21 0 16
CN8C010040 8C CPF - Hot Oil CP System- Comm. 20 29MAR12 18APR12 21 0 16
CN8C01RFSU 8C Sub-System RFSU - 8C 0 18APR12 0 0 16

20 - OFFPLOT
13 - Wellhead System (production)
1310 - Wellhead MLE-11
Step 2: Gas in Plant
PRE-COMMISSIONING
PC13100050 1310 8" Flowline 7 17SEP11A 24SEP11A 0 100
PC13100020 1310 Piping Systems: Flushing/Blowing/Reinst 10 17SEP11A 23DEC11A 0 100
PC13100030 1310 Electrical 10 08OCT11A 25JAN12A 0 100
PC13100040 1310 Instrumentation 10 07JAN12A 17MAR12 53 20 16
PC13100010 1310 Wellhead Control Panel 115-UW-13-11+Oil Flushing 6 11MAR12 24MAR12 14 0 16
PC13100SMC 1310 Sub System MC - 1310 0 24MAR12 0 0 61
COMMISSIONING
CN13100020 1310 Loop Checks & Functional Test 6 24MAR12 30MAR12 7 0 61

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 25 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

CN13100010 1310 Piping Systems: leak test 6 24DEC11A 31MAR12 67 10 70


CN13100025 1310 Wellhead Control Panel - Comm. & SAT 6 25MAR12 31MAR12 7 0 60
CN1310RFSU 1310 Sub System RFSU - 1310 0 31MAR12 0 0 60

15 - Wellhead System (chemical injection)


1510 - Chemical Injection MLE-11
Step 2: Gas in Plant
PRE-COMMISSIONING
PC15100020 1510 Piping Systems: Blowing/Reinst 6 08OCT11A 16DEC11A 0 100
PC15100030 1510 Electrical (Cables) 6 17SEP11A 25JAN12A 0 100
PC15100010 1510 Drum RA-15-11 6 05MAR12 10MAR12* 6 0 30
PC15100040 1510 Instrumentation 6 17SEP11A 17MAR12 53 70 19
PC15100060 1510 Chemical Pumps PB-15-11A/B 5 13MAR12 17MAR12 5 0 19
PC15100005 1510 Wellhead Corr. Inhibitor Inj. Package UZ-15-11 6 19MAR12 24MAR12 6 0 16
PC15100SMC 1510 Sub-System MC - 1510 0 24MAR12 0 0 16
COMMISSIONING
CN15100010 1510 Corr. Inhibitor Inj. Packages - Comm. 4 25MAR12 28MAR12 4 0 16
CN15100020 1510 Chemical Loading 4 25MAR12 28MAR12 4 0 17
CN15100030 1510 Pumps Loading Test 4 25MAR12 28MAR12 4 0 17
CN15100040 1510 Piping Systems: Leak Test 5 25MAR12 29MAR12 5 0 16
CN15100050 1510 Loop Checks & Functional Test 5 25MAR12 29MAR12 5 0 16
CN1510RFSU 1510 Sub System RFSU - 1510 0 29MAR12 0 0 16

1529 - Chemical Injection Manifold-M5


Step 2: Gas in Plant
PRE-COMMISSIONING
PC15290030 1529 Electrical (Cables) 23 15OCT11A 24DEC11A 0 100
PC15290020 1529 Piping Systems: Blowing/Reinst 37 26JAN12 03MAR12* 38 0 7
PC15290040 1529 Instrumentation 23 12FEB12 03MAR12 21 0 21
PC15290005 1529 Corr. Inhibitor Inj. Package UZ-15-29 5 04MAR12 10MAR12 7 0 7
PC15290010 1529 Drum RA-15-29 5 04MAR12 10MAR12 7 0 7
PC15290060 1529 Chemical Pumps PB-15-29A/B 5 11MAR12 17MAR12 7 0 7
PC15290SMC 1529 Sub-System MC - 1529 0 17MAR12 0 0 7
COMMISSIONING
CN15290040 1529 Piping Systems: Leak Test 4 04MAR12 10MAR12 7 0 28
CN15290030 1529 Pumps Loading Test 3 11MAR12 17MAR12 7 0 28
CN15290010 1529 Corr. Inhibitor Inj. Packages - Comm. 14 18MAR12 31MAR12 14 0 7
CN15290050 1529 Loop Checks & Functional Test 15 18MAR12 31MAR12 14 0 14
CN15290020 1529 Chemical Loading 7 01APR12 07APR12 7 0 7
CN1529RFSU 1529 Sub System RFSU - 1529 0 07APR12 0 0 7

18 - Manifold (production)
1801 - 24" Trunkline M5-CPF
Step 2: Gas in Plant
PRE-COMMISSIONING
PC18010020 1801 24" Trunkline M5-CPF 18 08OCT11A 31MAR12 67 90 35
PC18010SMC 1801 Sub-System MC - 1801 0 31MAR12 0 0 35
COMMISSIONING
CN1801RFSU 1801 Sub-System RFSU - 1801 0 31MAR12 0 0 104

1808 - Intermediate Fieled Manifold M5


Step 2: Gas in Plant
PRE-COMMISSIONING
PC18080060 1808 Electrical 23 15JUL11A 25JAN12A 0 100
PC18080050 1808 Piping Systems: Blowing & Reinst 11 15JUL11A 03MAR12 39 80 16
PC18080010 1808 Test Separator VA-18-07 5 17SEP11A 03MAR12 39 70 42
PC18080070 1808 Instrumentation 23 07JAN12A 03MAR12 39 40 21
PC18080SMC 1808 Sub-System MC - 1808 0 03MAR12 0 0 42
COMMISSIONING
CN18080020 1808 Loop Checks & Functional Test 20 10MAR12 29MAR12 20 0 16
CN18080010 1808 Piping Systems: leak test 15 15MAR12 29MAR12 15 0 16
CN1808RFSU 1808 Sub-System RFSU - 1808 0 29MAR12 0 0 16

81 - Main Power Gener. & Distrib. (Med. Voltage)


8107 - 5.5kV MV Distribution for LES-104

COMMISSIONING
CN81070030 8107 Pump Motor Panel Energization 3 07MAR12 08MAR12 2 0 5

8114 - 5,5 Kv MV Distribution - Manifold M5


Step 2: Gas in Plant
PRE-COMMISSIONING
PC81140010 8114 5,5Kv Cable - Check & Tests 3 02JUL11A 25JUL11A 0 100
PC81140020 8114 5,5Kv Panel 18-EM-81-05 12 02JUL11A 24SEP11A 0 100
PC81140030 8114 Trafo 5,5/0,4Kv 18-ET-82-05 3 02JUL11A 24SEP11A 0 100
PC81140SMC 8114 Sub-System MC - 8114 0 24JAN12 0 0 250
COMMISSIONING
CN81140030 8114 Trafo 5,5/0,4Kv 18-ET-82-05 2 26OCT11A 26JAN12 2 10 248
CN81140020 8114 5,5Kv Panel 18-EM-81-05 Tests 3 26OCT11A 27JAN12 3 10 247
CN81140010 8114 5,5Kv Cable - Test 5 26OCT11A 29JAN12 5 10 245
CN8114RFSU 8114 Sub-System RFSU - 8114 0 29JAN12 0 0 245

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 26 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

82 - Main Power Gener. & Distrib. (Low Voltage)


8230 - 400V LV Distribution Manifold M5
Step 2: Gas in Plant
PRE-COMMISSIONING
PC82300120 8230 400V Swgr18-EN-82-05 11 19NOV11A 25NOV11A 0 100
PC82300SMC 8230 Sub-System MC - 8230 0 24JAN12 0 0 250
COMMISSIONING
CN82300010 8230 400V Swgr 18-EN-82-05 3 25JAN12 27JAN12 3 0 247
CN8230RFSU 8230 Sub System RFSU - 8230 0 27JAN12 0 0 247

8235 - 400V LV Distribution MLE-11


Step 2: Gas in Plant
PRE-COMMISSIONING
PC82350120 8235 400V Swgr 115-ED-82-11 5 25JAN12 29JAN12 5 0 244
PC82350SMC 8235 Sub-System MC - 8235 0 29JAN12 0 0 245
COMMISSIONING
CN82350010 8235 400V Swgr 115-ED-82-11 2 29JAN12 30JAN12 2 0 244
CN8235RFSU 8235 Sub System RFSU - 8235 0 30JAN12 0 0 244

86 - Telecom System
86OP - Telecomm Subsystems - Off Plot
Step 2: Gas in Plant
PRE-COMMISSIONING
PC86150010 86OP Off-Plot - FO Backbone Manifolds&Wells - Precom. 15 02JUL11A 12AUG11A 0 100
PC86250030 86OP Off-Plot - FO Backbone LES 104 - Precomm. 0 17DEC11A 0 100
PC86050031 86OP Off-Plot - M6 - TETRA (UHF) System - Precom. 15 01APR12* 14APR12 14 0 13
PC86250020 86OP Off-Plot - FO Backbone Water Wells - Precom. 15 24SEP11A 28APR12 95 40 6
PC86OP0SMC 86OP Sub-System MC - 86OP [OFF-PLOT] 0 28APR12 0 0 6
COMMISSIONING
CN86150010 86OP Off-Plot - FO Backbone Manifolds & Wells - Comm. 14 04MAR12 10MAR12* 7 0 204
CN86050031 86OP Off-Plot - TETRA (UHF) System - Comm. 16 15APR12 21APR12 7 0 13
CN86250020 86OP Off-Plot - FO Backbone Water Wells - Comm. 16 22APR12 28APR12 7 0 6
CN86OPRFSU 86OP Sub-System RFSU - 86OP [OFF-PLOT] 0 28APR12 0 0 6

87 - Instrument System
8710 - SCADA System Manifold M5 & Wells
Step 2: Gas in Plant
PRE-COMMISSIONING
PC87100040 8710 RTU/PLC - Manifolds & Wells Precom. 45 26JAN12* 10MAR12 45 0 3
PC87100SMC 8710 Sub System MC - 8710 0 10MAR12 0 0 204
COMMISSIONING
CN87100030 8710 RTU/PLC - Manifolds & Wells Commis. 10 22MAR12 28MAR12 7 0 3
CN8710RFSU 8710 Sub System RFSU - 8710 0 28MAR12 0 0 3

88 - Earthing System
8810 - Earthing Off-Plot Manifold M5
Step 2: Gas in Plant
PRE-COMMISSIONING
PC88100010 8810 Earthing System Manifold M5 - Precom. 11 12NOV11A 25NOV11A 0 100
PC88100SMC 8810 Sub-System MC - 8810 0 25NOV11A 0 100
COMMISSIONING
CN8810RFSU 8810 Sub-System RFSU - 8810 0 25NOV11A 0 100

8821 - Earthing Off-Plot MLE-11


Step 2: Gas in Plant
PRE-COMMISSIONING
PC88210030 8821 Earthing System MLE-11 - Precom. 5 03DEC11A 25JAN12A 0 100
PC88210SMC 8821 Sub-System MC - 8821 0 25JAN12A 0 100
COMMISSIONING
CN8821RFSU 8821 Sub-System RFSU - 8821 0 25JAN12A 0 100

8F - Cathodic Protection System


8F07 - Cathodic Protection - Manifold M5
Step 2: Gas in Plant
PRE-COMMISSIONING
PC8F070080 8F07 Cathodic Protec - M5 - Precom. 11 07MAR12 20MAR12 14 0 71
PC8F070SMC 8F07 Sub-System MC - 8F07 0 20MAR12 0 0 71
COMMISSIONING
CN8F07RFSU 8F07 Sub-System RFSU - 8F07 0 20MAR12 0 0 71

30 - EXPORT PIPELINES
27 - Gas Handling
2702 - Gas Export Pipeline
Step 0 : 30" PL Gas in
PRE-COMMISSIONING
PC27020060 2702 Passive Shelter Installation (7Nos) 31 08JUL11A 24SEP11A 0 100
PC27020070 2702 Water Filiing on each passive Shelter 27 08JUL11A 24SEP11A 0 100
PC27020080 2702 Electrical panels + batteries 29 08JUL11A 24SEP11A 0 100
PC27020090 2702 TLC Panel + RTU 28 08JUL11A 24SEP11A 0 100
PC27020020 2702 30" Export Pipeline drying 27 10JUL11A 02DEC11A 0 100
PC27020030 2702 BVSs (6) - Precom 32 10JUL11A 02DEC11A 0 100
PC27020040 2702 Pig Launching Area @ CPF - Precom 6 27AUG11A 02DEC11A 0 100
PC27020050 2702 Pig Receiving Area @ GT - Precom 6 17SEP11A 02DEC11A 0 100
PC27020100 2702 Pig receiv @GT 6 17SEP11A 02DEC11A 0 100

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 27 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

PC27020110 2702 pig launch @CPF 6 17SEP11A 02DEC11A 0 100


PC27020SMC 2702 Sub-System MC - 2702 0 02DEC11A 0 100
COMMISSIONING
CN27020010 2702 BVSs (6) - Comm 13 26SEP11A 03MAR12 39 35 0
CN27020020 2702 SDV Open/Close Test With nitrogen 16 04MAR12 17MAR12 14 0 0
CN2702RFSU 2702 Sub-System RFSU - 2702 0 17MAR12 0 0 0

2703 - Gas Export at Gassi Touill Tie-in


Step 0 : 30" PL Gas in
PRE-COMMISSIONING
PC27030060 2703 Electrical 23 17JUL11A 24SEP11A 0 100
PC27030070 2703 Instrumentation 23 17JUL11A 02DEC11A 0 100
PC27030050 2703 Piping Systems: Blowing/Drying & Reinst 32 17SEP11A 02DEC11A 0 100
PC27030080 2703 Testing HIPPS Valves With Nitrogen 32 26NOV11A 02DEC11A 0 100
PC27030SMC 2703 Sub-System MC - 2703 0 02DEC11A 0 100
COMMISSIONING
CN27030050 2703 Piping Systems: Leak Test - Drying 15 26SEP11A 03MAR12 39 35 0
CN27030060 2703 Loop Checks & Functional Test 15 19FEB12 03MAR12 14 0 0
CN27030080 2703 Piping Systems: Inerting 15 04MAR12 17MAR12 14 0 0
CN2703RFSU 2703 Sub-System RFSU - 2703 0 17MAR12 0 0 0

33 - LPG Handling
3303 - LPG Export Pipeline
Step 3 : Balance
PRE-COMMISSIONING
PC33030030 3303 BVSs (6) - Precom 20 20JUL11A 06JAN12A 0 100
PC33030020 3303 12" Export Pipeline drying 10 20JUL11A 17MAR12 53 95 49
PC33030040 3303 Pig Launching Area @ CPF - Precom 10 27AUG11A 17MAR12 53 95 49
PC33030050 3303 Pig Receiving Area @ GT - Precom 10 17SEP11A 17MAR12 53 95 49
PC33030SMC 3303 Sub-System MC - 3303 0 17MAR12 0 0 49
COMMISSIONING
CN33030160 3303 BVSs (6) - Comm 23 18MAR12 09APR12 23 0 86
CN3330RFSU 3303 Sub-System RFSU - 3303 0 09APR12 0 0 86

3304 - LPG Export at Gassi Touill Tie-in


Step 3 : Balance
PRE-COMMISSIONING
PC33040030 3304 Electrical 17 20JUL11A 24SEP11A 0 100
PC33040040 3304 Instrumentation 17 20JUL11A 06JAN12A 0 100
PC33040020 3304 Piping Systems: Blowing/Drying & Reinst 17 20JUL11A 17MAR12 53 95 80
PC33040012 3304 Filters MB-33-01A/B 14 17SEP11A 17MAR12 53 70 197
PC33040SMC 3304 Sub-System MC - 3304 0 17MAR12 0 0 80
COMMISSIONING
CN33040050 3304 Piping Systems: Leak Test - Inerting 29 18MAR12 15APR12 29 0 80
CN33040060 3304 Loop Checks & Functional Test 29 18MAR12 15APR12 29 0 80
CN3304RFSU 3304 Sub-System RFSU - 3304 0 15APR12 0 0 80

86 - Telecom System
86EP - Telecomm - Export Pipelines
Step 2: Gas in Plant
PRE-COMMISSIONING
PC86140050 86EP EPL - FO Backbone P/L CPF - MLN - Precom. 15 20JUL11A 12AUG11A 0 100
PC86120040 86EP EPL - FO Backbone P/L CPF G.T. - Precom. 31 01JUL11A 25NOV11A 0 100
PC86290100 86EP EPL - PABX - P/L CPF - G.T. - Precomm. 31 12NOV11A 25NOV11A 0 100
PC86130010 86EP EPL - FO Backbone P/L CPF - H.B. - Precom. 15 20JUL11A 15MAR12 51 95 69
PC86300020 86EP EPL - PABX - P/L CPF - H.B. - Precom. 15 20JUL11A 15APR12 82 80 38
PC86010070 86EP EPL - UHF TETRA Radio - P/L CPF - G.T. - Precom. 15 16APR12 30APR12* 15 0 23
PC86020030 86EP EPL - UHF TETRA Radio - P/L CPF - H.B. - Precom. 15 01MAY12 15MAY12* 15 0 8
PC86EP0SMC 86EP Sub-System MC - 86EP [EXPORT P/LINES] 0 15MAY12 0 0 15
COMMISSIONING
CN86120040 86EP EPL - FO Backbone P/L CPF G.T. - Comm. 30 26OCT11A 25JAN12A 0 100
CN86140080 86EP EPL - FO Backbone P/L CPF - MLN - Comm. 7 26OCT11A 25JAN12A 0 100
CN86290010 86EP EPL - PABX - P/L CPF - G.T. - Comm. 30 26NOV11A 25JAN12A 0 100
CN86130060 86EP EPL - FO Backbone P/L CPF - H.B. - Comm. 7 16MAR12 22MAR12 7 0 69
CN86300040 86EP EPL - PABX - P/L CPF - H.B. - Comm. 7 16APR12 22APR12 7 0 38
CN86010070 86EP EPL - UHF TETRA Radio - P/L CPF - G.T. - Comm. 7 01MAY12 07MAY12 7 0 23
CN86020030 86EP EPL - UHF TETRA Radio - P/L CPF - H.B. - Comm. 7 16MAY12 22MAY12 7 0 8
CN86EPRFSU 86EP Sub-System RFSU - 86EP [EXPORT P/LINES] 0 22MAY12 0 0 8

87 - Instrument System
8704 - SCADA System For P/L CPF-GT
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC87040020 8704 RTU/PLC - EPL to GT Tie-in (1), BVSs(6) Precom. 31 15JUL11A 02DEC11A 0 100
PC87040SMC 8704 Sub System MC - 8704 0 02DEC11A 0 100
COMMISSIONING
CN87040010 8704 SCADA System - EPL to GT Commis. 7 26SEP11A 31MAR12 67 50 0
CN8704RFSU 8704 Sub System RFSU - 8704 0 31MAR12 0 0 0

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 28 of 29
2012 2013
Activity R Sub Activity Orig Early Early Rem % Total D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
ID Sys Description Dur Start Finish Dur Comp Float 33 34 35 36 37 38 39 40 41 42 43 44 45 4

88 - Earthing System
8836- Earthing BVS Export pipeline CPF-GT
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC8836010 8836 Earthing 21 05JUL11A 25JUL11A 0 100
PC88360SMC 8836 Sub-System MC - 8836 0 25JUL11A 0 100
COMMISSIONING
CN8836020 8836 Earthing system BVS RFSU 0 25JUL11A 0 100

8837- Earthing System GT


Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC8837030 8837 Earthing 30 26JUL11A 12AUG11A 0 100
PC8837040 8837 Subsystem MC 8837 0 12AUG11A 0 100
COMMISSIONING
CN8837050 8837 Earthing System GT RFSU 8837 0 12AUG11A 0 100

8F - Cathodic Protection System


8F01 - Cathodic Protection for P/L CPF - GT
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC8F010010 8F01 CP System from CPF - GT 31 02AUG11A 12AUG11A 0 100
PC8F010SMC 8F01 Sub System MC - 8F01 0 12AUG11A 0 100
COMMISSIONING
CN8F010010 8F01 CP System from CPF - GT 15 07MAR12 20MAR12 14 0 11
CN8F01RFSU 8F01 Sub System RFSU - 8F01 0 20MAR12 0 0 11

8P - Solar Panel System


8P01 - Solar Panel for P/L CPF - GT
Step 1A/1B: Up to TK1 Gas Turbine solo Run
PRE-COMMISSIONING
PC8P010110 8P01 Solar Packages (6+1) - Precom. 25 18JUL11A 07OCT11A 0 100
PC8P010SMC 8P01 Sub System MC - 8P01 0 07OCT11A 0 100
COMMISSIONING
CN8P010120 8P01 Solar Packages (6+1) - Comm. 21 26SEP11A 25JAN12A 0 100
CN8P01RFSU 8P01 Sub System RFSU - 8P01 0 25JAN12A 0 100

60 - COMMISSIONING/ START UP
MLE COMMISSIONING/ START UP
Commissioning/ Start-Up
Step 1A/1B: Up to TK1 Gas Turbine solo Run
COMMISSIONING/ START-UP
SU00000007 COSU 30" Gas P/L Gas-In (50-60 bar) 14 18MAR12* 31MAR12 14 0 0
SU00000010 COSU FG Syst. Gas-in (minimum 40 bar) 14 01APR12* 14APR12 14 0 0
SU00000020 COSU Flares (4) and Blow Down Syst. Start-Up 12 15APR12* 26APR12 12 0 0
SU00000030 COSU Close Drain Syst. & Burning Pit Start-Up 12 20APR12* 01MAY12 12 0 0
SU00000040 COSU Hot Oil Heaters (2) Dry-Out 12 22APR12* 03MAY12 12 0 0
SU00000050 COSU Hot Oil Syst. Start-Up 12 24APR12* 05MAY12 12 0 0
Ready For Start Up
SU00000060 COSU Gas Turbines (3) Solo Run (no load test) 14 24APR12* 07MAY12 14 0 0
Step 2: Gas in Plant
COMMISSIONING/ START-UP
SU00000070 COSU Gas Section - Leak Test with gas (20 bar) 17 05MAY12* 21MAY12 17 0 0
SU00000075 COSU Liquid Section - Leak Test with gas (20 bar) 17 06MAY12* 22MAY12 17 0 0
SU00000160 COSU Start Introduce Wet Gas in CPF 0 31MAY12 0 0 0
SU00000095 COSU Sales Gas Compr.s Trains Start-Up (Load test) 24 18MAY12* 10JUN12 24 0 0
SU00000097 COSU Inlet Process Section - Leak Test (70 bar) 21 23MAY12* 12JUN12 21 0 0
SU00000100 COSU Regeneration System Start-Up 7 08JUN12* 14JUN12 7 0 0
SU00000140 COSU Stabilizer Off Gas Compressor Start-Up 7 10JUN12* 16JUN12 7 0 0
SU00000110 COSU Dehydration System Start-Up 7 15JUN12* 21JUN12 7 0 0
SU00000139 COSU CO2 Removal System Start-Up 7 15JUN12* 21JUN12 7 0 0
SU00000150 COSU Gathering Syst. Start-Up (70 bar) - MLE11(M5) 37 31MAY12* 23JUN12 24 0 0
SU00000120 COSU Start Cooling Down by JT Valve 7 19JUN12* 25JUN12 7 0 0
TO BE CONFIRMED
SU00000130 COSU Turbo Expander Start-Up 7 22JUN12* 28JUN12 7 0 0
SU00000170 COSU Stabilizer Column/Reboiler Start-Up 7 24JUN12* 30JUN12 7 0 0
SU00000135 COSU Dehetanizer Column/Reboiler Start-Up 7 27JUN12* 03JUL12 7 0 0
SU00000138 COSU Process Gas Stable Condition Reached 0 03JUL12 0 0 89
SU00000180 COSU Debutanizer Column/Reboiler Start-Up 7 01JUL12* 07JUL12 7 0 0
SU00000185 COSU First Liquid Production (Off Spec) 0 07JUL12* 0 0 0
SU00000190 COSU Reach Plant On Spec Conditions (25% Turndown) 7 08JUL12* 14JUL12 7 0 0
SU00000210 COSU 30" Gas P/L Filling (Ready for Export) 27 24JUN12* 20JUL12 27 0 0
SU00000220 COSU Increase Feed up to Design Conditions 11 14JUL12* 24JUL12 11 0 0
Step 3 : Balance
COMMISSIONING/ START-UP
SU00000212 COSU 14" Condensate P/L Filling (Ready for Export) 20 27JUN12* 16JUL12 20 0 0
SU00000216 COSU 18" Oil P/L Filling (Ready for Export) 20 27JUN12* 16JUL12 20 0 0
SU00000214 COSU 12" LPG P/L Filling (Ready for Export) 14 05JUL12* 18JUL12 14 0 0
SU00000230 COSU Performance Test (Based on the No. wells avail.) 7 25JUL12* 31JUL12 7 0 0

33 34 35 36 37 38 39 40 41 42 43 44 45 4
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F
2012 2013

Sheet 29 of 29