You are on page 1of 52

Item Descripcin Und.

Metrado
01 ESTRUCTURA

01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

01.01.01 OBRAS PROVISIONALES

01.01.01.01 OFICINA DE RESIDENTE GLB 1.00

01.01.01.02 ALMACEN DE MATERIALES Y HERRAMIENTAS GLB 1.00

01.01.01.03 COMEDOR GLB 1.00

01.01.01.04 VESTUARIO GLB 1.00

01.01.01.05 SERVICIOS HIGINICOS GLB 1.00

01.01.01.06 CERCO DURANTE LA OBRA DE OBRA DE OBRA m 167.40

01.01.01.07 CARTEL DE IDENTIFICACION DE OBRA und 1.00

01.01.02 TRABAJOS PRELIMINARES

01.01.02.01 LIMPIEZA DE TERRENO MANUAL m2 1,734.20

01.01.02.02 TRAZOS, NIVELES Y REPLANTEO PRELIMINAR m2 224.41


01.01.03 MOVIMIENTO DE TIERRAS

01.01.03.01 RELLENO Y COMPACTADO C/EQUIPO LIVIANO C/MATERIAL DE PRESTAMO m3 221.84

01.01.03.02 EXCAVACIONES SIMPLES SOBRE TERRENO NATURAL m3 469.50

01.01.03.03 ELIMINACIN DE MATERIAL EXCEDENTE m3 309.58

01.01.04 DEMOLICION

01.01.04.01 DEMOLICION MASIVA C/ EQUIPOS LIVIANOS DE PISOS Y CONTRAPISO m2 173.98


EXISTENTE (e=0.50m)
01.01.04.02 DEMOLICION DE EDIFICACION EXISTENTE (MATERIAL RUSTICO) CON MAQUINARIA PESADA m2 395.38

01.02 CONCRETO SIMPLE


01.02.01 FALZA ZAPATAS

01.02.01.01 CONCRETO PARA FALZA ZAPATA f'c= 80 kg/cm2 m3 82.48

01.02.02 FALSOPISO (Concreto Ciclopeo C:H= 1 : 10 e = 0.10m) m2 464.26

01.02.03 CIMIENTOS CORRIDOS MEZCLA 1:10 C-H+30% PIEDRA m3 35.67

01.02.04 SOBRECIMIENTOS

01.02.04.01 CONCRETO EN SOBRECIMIENTO 1:8 C:H + 25% PM m3 17.52

01.02.04.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 233.65

01.03 CONCRETO ARMADO


01.03.01 ZAPATAS

01.03.01.01 CONCRETO PARA ZAPATAS f'c= 210 kg/cm2 m3 98.98

01.03.01.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA ZAPATAS m2 77.53

01.03.01.03 ACERO EN ZAPATA FY=4200KG/CM2. kg 2,517.90

01.03.02 VIGAS DE CIMENTACION

01.03.02.01 CONCRETO PARA VIGAS DE CIMENTACION f'c= 210 kg/cm2 m3 126.21


01.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA VIGAS DE CIMENTACION m2 207.38

01.03.02.03 ACERO EN VIGAS DE CIMENTACION FY=4200KG/CM2. kg 4,532.41

01.03.03 COLUMNAS

01.03.03.01 CONCRETO PARA COLUMNAS f'c= 280 kg/cm2 m3 117.60


01.03.03.02 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2 782.07

01.03.03.03 ACERO EN COLUMNAS FY= 4200KG/CM2 - GRADO 60 kg 24,637.42

01.03.04 MUROS DE CORTE

01.03.04.01 CONCRETO PARA MUROS DE CORTE f'c= 280 kg/cm2 m3 251.49

01.03.04.02 ENCOFRADO Y DESENCOFRADO PARA MUROS DE CORTE m2 2,011.78

01.03.04.03 ACERO EN MUROS DE CORTE FY= 4200KG/CM2 - GRADO 60 kg 40,496.51

01.03.05 VIGAS

01.03.05.01 CONCRETO PARA VIGAS f'c= 280 kg/cm2 m3 220.43

01.03.05.02 ENCOFRADO Y DESENCOFRADO PARA VIGAS m2 1,122.73

01.03.05.03 ACERO EN VIGAS FY= 4200KG/CM2 - GRADO 60 kg 49,071.17

01.03.06 LOSA NERVADA EN DOS DIRECCIONES e = 0.45 m

01.03.06.01 CONCRETO PARA LOSA f'c= 280 kg/cm2 E = 0.45 M m3 508.77

01.03.06.02 ENCOFRADO Y DESENCOFRADO PARA LOSA ALIEGRADA m2 2,890.74

01.03.06.03 ACERO SUPERIOR E INFERIOR EN LOSA NERVADA FY= 4200KG/CM2 - kg 36,664.90


GRADO 60
01.03.06.04 BOCEDILLA DE POLIESTIRENO 0.40X0.40X0.40 und 10,646.00

01.03.07 ESCALERAS

01.03.07.01 CONCRETO PARA ESCALERA f'c= 210 kg/cm2 m3 50.58

01.03.07.02 ENCOFRADO Y DESENCOFRADO PARA ESCALERA m2 291.10

01.03.07.03 ACERO EN ESCALERA FY= 4200KG/CM2 - GRADO 60 kg 3,997.78

01.03.08 CISTERNA

01.03.08.01 CONCRETO PARA CISTERNA f'c= 210 kg/cm2 m3 42.11

01.03.08.02 ENCOFRADO Y DESENCOFRADO PARA CISTERNA m2 173.57

01.03.08.03 ACERO EN CISTERNA FY= 4200KG/CM2 - GRADO 60 kg 888.51

01.03.09 OTROS

01.03.09.01 DISEO DE MEZCLAS PARA CONCRETO GLB 30.00

01.03.09.02 ROTURA DE CONCRETO und 30.00

02 ARQUITECTURA

02.01 MUROS Y TABIQUES DE ALBAILAERIA

02.01.01 MUROS DE LADRILLO KING KONG DE ARCILLA DE 18 HUECOS 9X14X24CM m2 1,584.97

02.02 REVOQUES Y REVESTIMIENTOS

02.02.01 TARRAJEO PRIMARIO O RAYADO

02.02.01.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 m2 3,483.12

02.02.02 TARRAJEO DE INTERIORES Y EXTERIORES

02.02.02.01 TARRAJEO MUROS INTERIORES MEZCLA C:A 1:5, E=1.5CM m2 2,342.12


02.02.02.02 TARRAJEO MUROS EXTERIORES MEZCLA C:A 1:5, E=1.5CM m2 1,141.00

02.02.03 TARRAJEO EN COLUMNAS

02.02.03.01 TARRAJEO EN COLUMNAS MEZCLA C:A 1:5, E=1.5CM m2 641.28

02.02.04 TARRAJEO EN VIGAS

02.02.04.01 TARRAJEO EN SUPERFICIE DE VIGAS CEMENTO - ARENA 1:5, E = 1.5 CM m2 932.55

02.02.05 TARRAJEO EN PARAPETOS

02.02.05.01 TARRAJEO EN PARAPETOS DE SOGA LADRILLO PANDERETA MEDIDAS m2 129.81


10X12X25 CM (1.5 cm)
02.02.06 TARRAJEO EN PLACAS
02.02.06.01 TARRAJEO EN PLACAS MEZCLA C:A 1:5, E=1.5CM m2 1,114.97

02.02.07 VESTIDURAS DE DERRAMES EN PUERTAS Y VENTANAS E=16CM

02.02.07.01 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS E=16CM m 934.65

02.02.08 TARRAJEO EN DUCTOS

02.02.08.01 TARRAJEO EN DUCTOS (Baja montantes y ducto de basura) m2 86.43

02.02.09 BRUAS

02.02.09.01 BRUAS EXTERIOR DE 1.0 CM m 761.50

02.02.09.02 BRUAS EN SS.HH DE 1.0 CM m 4,615.70

02.02.10 TARRAJEO EN ESCALERAS

02.02.10.01 TARRAJEO EN FONDO DE ESCALERA (ancho = 1.80) m2 202.68

02.02.10.02 TARRAJEO DE PASOS DE CONCRETO 1:5, E = 2.0 CM (ANCHO = 0.30 M ) m 378.00

02.02.10.03 TARRAJEO DE CONTRAPASOS DE CONCRETO 1:5, E = 2.0 CM (ALTURA = m 396.00


0.18 M )
02.02.10.04 TARRAJEO DE DESCANSOS DE CONCRETO 1:5, E = 2.0 CM (ANCHO = 1.80 m2 72.00
02.03 CIELORASOS

02.03.01 CIELORRASOS EN CASETONES CON MEZCLA C:A 1:5, E=1.5CM m2 2,885.25

02.04 PISOS Y PAVIMENTOS

02.04.01 CONTRAPISOS 1:5, 48 mm m2 3,058.77

02.04.02 PISOS

02.04.02.01 PISO TERMINADO VINILICO ALTO TRANSITO m2 1,124.04

02.04.02.02 CERAMICO 0.59x0.59m; Modelo:ONICE MARFIL PULIDO ; SAN LORENZO O m2 24.46

02.04.02.03 PISO: TERMINADO MICROCEMENTO m2 1,478.62

02.04.02.04 PISO: CONCRETO ESTAMPADO m2 151.29

02.04.02.05 Cermico Tipo:Matisse Negro 36x36 m2 280.37

02.04.03 SARDINEL; DE CA h = 0.60 M (E=0.13 m ) PARA JARDIN m 43.90

02.05 ZOCALOS Y CONTRAZOCALOS


02.05.01 ZOCALO DE CERAMICO 0.36X0.36M MATISSE NEGRO (1.50m) m2 629.60

02.05.02 CONTRAZOCALO DE MICROCEMENTO (0.08 m) m 1,167.33

02.06 CERAMICOS EN LAVADEROS

02.06.01 CERAMICO EN LAVADEROS m2 17.10

02.07 COBERTURAS

02.07.01 TARRAJEO CON IMPERMEABILIZANTES, MEZCLA 1:1, E=1.5CM m2 479.71

02.08 CARPINTERIA DE MADERA

02.08.01 PUERTA CONTRAPLACADA SEGUN DISEO m2 45.30

02.08.02 PUERTA APANELADA SEGUN DISEO m2 23.52

02.08.03 COLOCACION DE PUERTAS CONTRAPLACADAS und 24.00

02.08.04 COLOCACION DE PUERTAS APANELADAS und 7.00

02.09 CARPINTERA METLICA Y HERRERA

02.09.01 PUERTA METALICA SEGUN DISEO m2 42.38

02.09.02 VENTANAS DE ALUMINIO ; COLOR NEGRO;SEGN DISEO DE 6MM INC m2 125.60

ACCESORIOS

02.09.03 SEPARADOR DE MELAMINE PARA URINARIO m2 7.20

02.09.04 DIVISIN DE PLANCHA DE ACERO GALVANIZADO PARA SERVICIOS m2 74.52

HIGINICOS

02.09.05 COLOCACION DE PUERTAS METALICOS m2 42.38

02.09.06 COLOCACION DE VENTANA DE ALUMINIO CON VIDRIO TEMPLADO m2 125.60

02.09.07 BARANDAS

02.09.07.01 BARANDA METALICO EN CORREDOR H=0.95m m 273.75

02.09.07.02 BARANDA METALICO EN ESCALERA H=0.95m m 99.36

02.09.07.03 CANTONERAS EN PASOS PARA ESCALERAS DE 1 1/2X3MM m 475.20

02.10 CERRAJERIA

02.10.01 BISAGRAS

02.10.01.01 BISAGRA DE FIERRO DE 4" CON EJE DE 1/2" pza 282.00

02.10.01.02 BISAGRA ALTA ROTACION 1110 pza 63.00

02.10.02 CERRADURAS

02.10.02.01 CERRADURA BOTON INTERIOR Y LLAVE EXTERIOR pza 24.00

02.10.02.02 CERRADURA PARA PUERTAS (03 GOLPES) INCLUYE TIRADOR pza 2.00

02.10.02.03 CERRADURA PARA PUERTA CON PESTILLO SS.HH pza 36.00

02.10.02.04 MANIJA DE BRONCE DE 4" PARA PUERTAS und 27.00

02.11 VIDRIOS, CRISTALES Y SIMILARES

02.11.01 ESPEJOS EN BAOS E = 6MM m2 28.20

02.11.02 VIDRIOS 8MM SISTEMA DIRECTO m2 285.06

02.11.03 COLOCACION EN SISTEMA DIRECTO und 44.00

02.11.04 SUMINISTRO Y COLOCACION DE MURO CORTINA EXTERIOR m2 507.66

02.12 PINTURA

02.12.01 PINTURA EN EXTERIORES; ACABADO: FROTACHADO LISO Y PINTADO m2 1,141.00

SUPER MATE

02.12.02 PINTURA EN INTERIORES: ACABADO: FROTACHADO LISO Y PINTADO m2 2,342.12

02.12.03 PINTURA DE VIGAS; ACABADO: FROTACHADO LISO Y PINTADO m2 932.55

02.12.04 PINTURA DE COLUMNAS; ACABADO: FROTACHADO LISO Y PINTADO m2 641.28

02.12.05 PINTURA EN DERRAMES (0.15m); ACABADO: FROTACHADO LISO Y PINTADO m2 934.65

02.12.06 PINTURA DE CONTRAZOCALO Y BARANDAS

02.12.06.01 PINTURA DE CONTRAZOCALO (0.08 m ) m 1,167.33

02.12.06.02 PINTURA EN BARANDAS (0.95 m ) m 187.28

02.13 VARIOS, LIMPIEZA Y JARDINERA

02.13.01 BUTACAS INCLUIDO INSTALACION und 108.00

02.13.02 LIMPIEZA PERMANENTE DE OBRA glb 1.00

02.13.03 LIMPIEZA FINAL DE OBRA glb 1.00

02.13.04 LIMPIEZA DE VIDRIOS m2 462.38


02.13.05 JARDIN m2 59.93

03 INSTALACIONES SANITARIAS

03.01 APARATOS Y ACCESORIOS SANITARIOS

03.01.01 SUMINISTRO DE APARATOS SANITARIOS

03.01.01.01 URINARIO BAMBI COLOR BLANCO/TRBOL O SIMILAR und 24.00

03.01.01.02 INODORO BABY COLOR BLANCO/TRBOL O SIMILAR und 6.00

03.01.01.03 INODORO NOVARA FLUX COLOR BLANCO/TRBOL O SIMILAR und 36.00

03.01.01.04 OVALN CERALUX COLOR BLANCO/TRBOL O SIMILAR und 36.00

03.01.01.05 LAVATORIO FONTANA COLOR BLANCO/TREBOL O SIMILAR und 6.00

03.01.02 SUMINISTRO DE ACCESORIOS

03.01.02.01 DISPENSADOR DE PAPEL ADOSADO A PARED und 42.00

03.01.02.02 DISPENSADOR DE JABN LQUIDO ADOSADO EN PARED. und 18.00

03.01.02.03 PORTAPAPEL REDONDO CROMADO und 42.00

03.01.02.04 TACHO DE BASURA METLICO und 42.00

03.01.02.05 LLAVE DE 1/2" LAVATORIO TEMPORIZADA PICO LARGO und 42.00

03.01.03 INSTALACIN DE APARATOS SANITARIOS

03.01.03.01 INSTALACION DE URINARIO BAMBI COLOR BLANCO/TRBOL O SIMILAR und 24.00

03.01.03.02 INSTALACION DE INODORO BABY COLOR BLANCO/TRBOL O SIMILAR und 6.00

03.01.03.03 INSTALACION DE INODORO NOVARA FLUX COLOR BLANCO/TRBOL O und 36.00

03.01.03.04 INSTALACION DE OVALN CERALUX COLOR BLANCO/TRBOL O SIMILAR und 36.00

03.01.03.05 INSTALACION DE LAVATORIO FONTANA COLOR BLANCO/TREBOL O und 6.00

SIMILAR
03.01.04
INSTALACIN DE ACCESORIOS
03.01.04.01 INSTALACION DE DISPENSADOR DE PAPEL ADOSADO A PARED und 42.00

03.01.04.02 INSTALACION DE DISPENSADOR DE JABN LQUIDO ADOSADO EN und 18.00

03.01.04.03 INSTALACION DE PORTAPAPEL REDONDO CROMADO und 42.00

03.01.04.04 INSTALACION DE TACHO DE BASURA METLICO und 42.00

03.01.04.05 INSTALACION DE LLAVE DE 1/2" LAVATORIO TEMPORIZADA PICO LARGO und 42.00

03.02 SISTEMA DE AGUA FRIA

03.02.01 SALIDA DE AGUA FRIA

03.02.01.01 Salida de agua fria 1/2'' pto 48.00

03.02.01.02 Salida de agua fria 1'' pto 18.00

03.02.01.03 Salida de agua fria 1 1/4'' pto 42.00

03.02.02 REDES DE DISTRIBUCION

03.02.02.01 RED DE DISTRIBUCION TUBERIA DE 2 1/2" PVC-SAP m 60.21

03.02.02.02 RED DE DISTRIBUCION TUBERIA DE 1 1/2" PVC-SAP m 67.48

03.02.02.03 RED DE DISTRIBUCION TUBERIA DE 1 1/4" PVC-SAP m 54.21

03.02.02.04 RED DE DISTRIBUCION TUBERIA DE 1" PVC-SAP m 16.94

03.02.02.05 RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP m 53.22

03.02.02.06 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP m 31.28

03.02.02.07 RED DE ALIMENTACION TUBERIA DE 2 1/2" PVC-SAP m 37.88

03.02.03 REDES DE ALIMENTACION

03.02.03.01 RED DE ALIMENTACION TUBERIA DE 1 1/2" PVC-SAP m 2.67

03.02.03.02 RED DE ALIMENTACION TUBERIA DE 1" PVC-SAP m 2.92

03.02.04 ACCESORIOS DE REDES DE AGUA

03.02.04.01 CODO DE PVC SAP 2 1/2" pza 38.00

03.02.04.02 CODO DE PVC SAP 1 1/2" pza 67.00

03.02.04.03 CODO DE PVC SAP 1 1/4" pza 56.00

03.02.04.04 CODO DE PVC SAP 1" pza 24.00

03.02.04.05 CODO DE PVC SAP 3/4" pza 48.00

03.02.04.06 CODO DE PVC SAP 1/2" pza 47.00

03.02.04.07 TEE DE PVC SAP 2 1/2" pza 19.00


03.02.04.08 TEE DE PVC SAP 1 1/2" pza 52.00

03.02.04.09 TEE DE PVC SAP 1 1/4" pza 12.00

03.02.04.10 TEE DE PVC SAP 1" pza 6.00

03.02.04.11 TEE DE PVC SAP 3/4" pza 24.00

03.02.05 LLAVES Y VALVULAS

03.02.05.01 VALVULA COMPUERTA BRONCE DE 2 1/2" pz 20.00


a
03.02.05.02 VALVULA COMPUERTA BRONCE DE 1 1/2" pz 15.00
a
03.02.05.03 VALVULA COMPUERTA BRONCE DE 1 1/4" pz 6.00
a
03.02.05.04 VALVULA COMPUERTA BRONCE DE 4" un 12.00
d
03.02.06 ALMACENAMIENTO DE AGUA

03.02.06.01 CISTERNA CAP. = 39 m3 GL 1.00


B
03.02.06.02 CISTERNA CAP. = 45.42 m3 GL 1.00
B
03.02.07 EQUIPOS Y OTRAS INSTALACIONES

03.02.07.01 ELECTROBOMBA 7.5 HP un 3.00


d
03.03 SISTEMA DE AGUA CONTRA INCENDIOS

03.03.01 SALIDA DE AGUA CONTRAINCENDIO pt 12.00


o
03.03.02 RED DE ALIMENTACION

03.03.02.01 RED DE ALIMENTACION TUBERIA HDPE de 4" m 127.61

03.03.03 ACCESORIO REDES DE AGUA CONTRA INCENDIO

03.03.03.01 Codo de HDPE de 4 x 90 un 31.00


d
03.03.03.02 Tee de HDPE de 4" un 3.00
d
03.03.04 SUMINISTRO E INSTALACIN DE GABINETES CONTRA INCENDIO

03.03.04.01 GABNIETE CONTRA INCENDIO 2 1/2" un 10.00


d
03.03.05 VLVULAS DE SISTEMA CONTRA INCENDIO

03.03.05.01 VLVULA ANGULAR DE 1 1/2 " un 12.00


d
03.03.05.02 VLVULA ANGULAR DE 2 1/2 " un 12.00
d
03.03.05.03 VALVULA COMPUERTA BRONCE DE 4" un 8.00
d
03.03.05.04 VLVULA CHECK RANURADA 4" un 2.00
d
03.03.05.05 VALVULA DE ALIVIO DE 4" un 2.00
d
03.03.06 INSTALACIONES ESPECIALES

03.03.06.01 ELECTROBOMBA 60 HP un 1.00


d
03.04 DESAGUE Y VENTILACION

03.04.01 SALIDADE DE DESAGUE

03.04.01.01 SALIDA DE DESAGUE CON PVC 4" pt 42.00


o
03.04.01.02 SALIDA DE DESAGUE CON PVC 2" pt 66.00
o
03.04.02 REDES DE DERIVACION

03.04.02.01 RED DE DERIVACIN TUBERIA PVC SIMPLE PRESIN DE 2" m 242.10

03.04.02.02 RED DE DERIVACIN TUBERIA PVC SIMPLE PRESIN DE 3" m 12.50

03.04.02.03 RED DE DERIVACIN TUBERIA PVC SIMPLE PRESIN DE 4" m 147.95

03.04.02.04 MONTANTE DE DESAGE PVC SIMPLE PRESIN DE 3" m 22.50

03.04.02.05 MONTANTE DE DESAGE PVC SIMPLE PRESIN DE 4" m 45.00

03.04.02.06 TUBERA DE VENTILACIN PVC SIMPLE PRESIN DE 2" m 168.75

03.04.02.07 TUBERA DE VENTILACIN PVC SIMPLE PRESIN DE 3" m 18.75

03.04.02.08 TUBERA DE VENTILACIN PVC SIMPLE PRESIN DE 4" m 37.50

03.04.03 REDES COLECTORAS

03.04.03.01 RED COLECTORA TUBERIA PVC 160mm S-25 m 22.00

03.04.03.02 RED COLECTORA TUBERIA PVC C-10 3" m 5.00

03.04.04 ACCESORIOS DE REDES

03.04.04.01 YEE DE PVC DE 2" un 92.00


d
03.04.04.02 YEE DE PVC DE 4" un 18.00
d
03.04.04.03 YEE DE 3"PVC CON REDUCCIN A 2" un 1.00
d
03.04.04.04 YEE DE 4"PVC CON REDUCCIN A 3" un 9.00
d
03.04.04.05 YEE DE 4"PVC CON REDUCCIN A 2" un 12.00
d
03.04.04.06 REDUCCIN DE PVC DE 3" A 2" un 2.00
d
03.04.04.07 REDUCCIN DE PVC DE 4" A 2" un 22.00
d
03.04.04.08 CODO DE PVC DE 2" A 45 un 81.00
d
03.04.04.09 CODO DE PVC DE 4" A 45 un 18.00
d
03.04.04.10 CODO DE PVC DE 2" A 90 un 138.00
d
03.04.04.11 CODO DE PVC DE 3" A 90 un 20.00
d
03.04.04.12 CODO DE PVC DE 4" A 90 un 9.00
d
03.04.04.13 TEE DE PVC DE 2" und 12.00

03.04.04.14 TEE DE PVC DE 3" und 12.00

03.04.04.15 TEE DE PVC DE 4" und 53.00

03.04.04.16 TEE DE 4" CON REDUCCIN A 2" DE PVC und 19.00

03.04.04.17 TRAMPA "P" DE PVC DE 2" und 33.00

03.04.04.18 TRAMPA "P" DE PVC DE 3" und 11.00

03.04.04.19 REGISTRO ROSCADO DE BRONCE DE 2" und 34.00

03.04.04.20 REGISTRO ROSCADO DE BRONCE DE 4" und 21.00

03.04.04.21 SUMIDERO DE BRONCE DE 2" und 33.00

03.04.04.22 SUMIDERO DE BRONCE DE 3" und 11.00

03.04.05 CMARAS DE INSPECCIN

03.04.05.01 CAJA DE REGISTRO DE 12"X24" und 10.00

03.04.05.02 CAJA DE REGISTRO DE 1.00 m und 1.00

04 INSTALACIONES ELECTRICAS Y ELECTROMECANICAS

04.01 TRABAJOS PRELIMINARES

04.01.01 TRAZOS, NIVELES Y REPLANTEO PRELIMINAR m2 3,043.67

04.02 MOVIMIENTO DE TIERRAS

04.02.01 EXCAVACION DE ZANJA,TERRENO NORMAL m3 40.00

04.02.02 RELLENO Y COMPACTACION DE MATERIAL PROPIO m3 28.00

04.02.03 ELIMINACION MATERIAL EXCEDENTE m3 12.00

04.03 TUBERIAS Y DUCTO

04.03.01 TUBO PVC-SAP DE 20mmX 3m m 4,818.00

04.03.02 TUBO PVC-SAP DE 25mmX 3m m 129.00

04.03.03 TUBO PVC-SAP DE 50mmX 3m m 16.00

04.03.04 TUBO PVC-SAP DE 80mmX 3m m 35.00

04.04 CONDUCTORES Y/O CABLES

04.04.01 CONDUCTOR TIPO LSOH DE 2-1x4mm2 +2.5mm2 (TIERRA) m 883.00

04.04.02 CONDUCTOR TIPO LSOH DE 2 - 1x2.5mm2 + 2.5mm2 (TIERRA) m 2,695.00

04.04.03 CONDUCTOR N2XOH 3 - 1 X 70 mm2 m 35.00

04.04.04 CONDUCTOR N2XOH 3 - 1 X 25 mm2 m 16.00

04.04.05 CONDUCTOR N2XOH 3 - 1 x 10 mm2 m 45.00

04.04.06 CONDUCTOR N2XOH 3 - 1 x 10 mm2+ 1X 2.5mm2(TIERRA) m 29.00

04.04.07 CONDUCTOR N2XOH 3 - 1 X 4 mm2 + 1 X 2.5mm2(TIERRA) m 7.00

04.04.08 CONDUCTOR N2XOH 2 -1 X 6 mm2 + 1x 2.5mm2(TIERRA) m 65.00

04.04.09 CONDUCTOR N2XOH 2 - 1 X 4 mm2 + 1 X 2.5mm2(TIERRA) m 12.00

04.04.10 CONDUCTOR NYY 1 - 2 X 2.5 mm2 + 1 X 1.5mm2(TIERRA) m 31.00

04.05 CAJAS DE PASO Y BUZONES DE REGISTRO

04.05.01 CAJA DE INTERCONEXION DE 100X100X100mm und 53.00

04.05.02 BUZON DE CONCRETO ARMADO. GLB 6.00

04.05.03 RED SUBTERRNEA m 77.00

04.06 ARTEFACTOS DE ILUMINACION

04.06.01 FLUORESCENTE DE 3 X18W INC/EQUIPO Y PANTALLA CUADRADO CON und 92.00

04.06.02 FLUORESCENTE DE 2 X36W INC/EQUIPO Y PANTALLA RECTANGULAR und 31.00

04.06.03 SPOT LAIGHT CON FOCO LED 10W PARA EMPOTRAR TECHO und 118.00

04.06.04 DICROICO LEDS DE 10W LUZ BLANCA PARA EMPOTRAR und 346.00

04.06.05 LUMINARIA TIPO BOLLARD CON FOCO LEDS DE 6W und 12.00


04.06.06 LUMINARIA ESFERICA INC. LAMPARA (LED DE 10W) PARA PARED TIPO und 24.00

4.07 TABLEROS DE DISTRIBUCION

04.07.01 TABLERO ELECTRICO GAB.METALICO AUTOSOPORTADO P/DIST PARA und 1.00

5 CIRCUITOS TIPO TGD CON ANALIZADOR DE REDES

04.07.02 TABLERO ELECTRICO GAB.METALICO EMPOTRADO P/DIST PARA und 1.00

6 CIRCUITOS TIPO STGD TRIFASICO

04.07.03 TABLERO DISTRIBUCION CAJA METALICA EMPOTRADO P/DIST PARA und 1.00

8 CIRCUITOS TIPO TD1 MONOFASICO

04.07.04 TABLERO DISTRIBUCION CAJA METALICA EMPOTRADO P/DIST PARA und 1.00

10 CIRCUITOS TIPO TD2 MONOFASICO

04.07.05 TABLERO DISTRIBUCION CAJA METALICA EMPOTRADO P/DIST PARA 8 und 2.00

CIRCUITOS TIPO TD3 Y TD6 MONOFASICO

04.07.06 TABLERO DISTRIBUCION CAJA METALICA EMPOTRADO P/DIST PARA 9 und 2.00

CIRCUITOS TIPO TD4 Y TD5 MONOFASICO

04.07.07 TABLERO DISTRIBUCION CAJA METALICA TIPO T.SALA DE USOS und 1.00

MULTIPLES

04.07.08 TABLERO DISTRIBUCION CAJA METALICA TIPO T. LABORATORIO DE und 1.00

COMPUTO

04.07.09 TABLERO DE DISTRIBUCION CAJA METALICA TIPO T. ASCENSORES und 1.00

04.07.10 SUB TABLERO DISTRIBUCION CAJA METALICA TIPO STD-1 und 1.00

04.07.11 SUB TABLERO DISTRIBUCION CAJA METALICA TIPO STD-2 und 1.00

04.07.12 SUB TABLERO DISTRIBUCION CAJA METALICA TIPO und 4.00

04.08
ACCESORIOS DE INSTALACIONES ELECTRICAS INTERIORES Y EXTERIORES
04.08.01 SALIDA PARA CENTROS DE LUZ pto 623.00

04.08.02 SALIDA PARA INTERRUPTOR SIMPLE pto 41.00

04.08.03 SALIDA PARA INTERRUPTOR DOBLE pto 33.00

04.08.04 SALIDA PARA INTERRUPTOR DE CONMUTACION pto 27.00

04.08.05 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE C/TIERRA pto 96.00

04.08.06 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE C/TIERRA EN EL PISO pto 24.00

04.08.07 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE C/TIERRA A MEDIA pto 4.00

04.08.08 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE C/TIERRA EN TECHO pto 12.00

04.08.09 SALIDA DE FUERZA pto 3.00

04.09 PUESTA A TIERRA

04.09.01 PUESTA A TIERRA und 4.00

04.09.02 PARARRAYO DE PROTECCIN und 1.00

04.10 SISTEMAS DE LUCES DE EMERGENCIA

04.10.01 SALIDA PARA CONTROL DE LUZ DE EMERGENCIA pto 56.00

04.10.02 ARTEFACTO DE LUZ DE EMERGENCIA pto 56.00

04.11 EQUIPOS ELECTROMECANICOS

04.11.01 ASCENSOR DE 1,000kg PARA 13 PERSONAS , 1m/s, 220V. und 2.00

04.12 SUMISTRO E INSTALACION DE ASCENSOR

04.12.01 SUMINISTRO E INSTALACION DE ASCENSOR 1 TON und 2.00

04.13 SISTEMAS DE CONTINGENCIA

04.13.01 GRUPO ELECTROGENO ENCAPSULADO DE 50 KW TRIFSICO glb 1.00

04.13.02 TABLERO DE TRANSFERENCIA AUTOMATICO PARA GENERADOR DE 50 KW glb 1.00

TRIFSICO 220V
04.14
SUMINISTRO EN MEDIA TENSIN
04.14.01 INSTALACION DE NUEVO CIRCUITO EN SUB ESTACIN EXISTENTE glb 1.00

04.15 PRUEBAS ELECTRICAS FINALES

04.15.01 PRUEBA DE AISLAMIENTO und 16.00

04.15.02 PRUEBAS DE RESISTIVIDAD DE PUESTA A TIERRA und 4.00


04.15.03 PRUEBAS DE CONTINUIDAD DE INSTALACIONES INTERIORES und 16.00

04.15.04 PRUEBAS Y BALANCEO DE CARGAS und 16.00

05 SISTEMA DE DESAGUE PLUVIAL

05.01 RED DE RECOLECCIN

05.01.01 TUBERIA DE BAJADA PVC SAP DE 4" m 90.00

05.02 ACCESORIOS

05.02.01 CODO PVC SAL 4"X90 und 4.00

05.02.02 REGISTRO DE BRONCE DE BRONCE DE 4" und 24.00

05.02.03 Tee de PVC SAP 4" und 24.00

05.03 CONCRETO REFORZADO

05.03.01 CONCRETO F'C=175 Kg/CM2 COLUMNETAS m3 2.65

05.03.02 ACERO FY=4200 Kg/CM2 kg 155.68

05.03.03 ENCOFRADO Y DESENCOFRADO m2 88.30

06 SISTEMAS ELECTRONICOS

06.01 PLATAFORMA WEB Y DE SERVICIOS MULTIPLES

06.01.01 SUMINISTRO DE SERVIDOR DE DATOS und 1.00

06.01.02 SUMINISTRO DE ANTIVIRUS SERVER glb 6.00

06.01.03 INSTALACION DE PLATAFORMA WB glb 6.00

06.02 SISTEMA DE COMPUTO PARA LABORATORIOS Y AULAS

06.02.01 SUMINISTRO DE COMPUTADOR PERSONAL und 50.00

06.02.02 INSTALACION DEL SISTEMA DE COMPUTO PARA LAB Y AULAS glb 50.00

06.03 ADECUACION DE AMBIENTES MULTIMEDIAS

06.03.01 SISTEMA DE ADECUACION DE AMBIENTES

06.03.01.01 SUMINISTRO DE MODULO DE COMPUTO PARA DOCENTES und 6.00

06.03.01.02 SUMINISTRO DE SILLAS PARA MODULOS DE COMPUTO und 26.00

06.03.01.03 SUMINISTRO DE IMPRESORA LASER und 6.00

06.03.01.04 INSTALACION SISTEMA DE ADECUACION DE AMBIENTES glb 6.00

06.03.02 SISTEMA ELECTRONICOS

06.03.02.01 SALIDA PARA SENSORES DE ALARMA CONTRAINCENDIOS pto 28.00

06.03.02.02 SALIDA PARA PULSADOR DE ALARMA CONTRAINCENDIOS pto 6.00

06.03.02.03 SALIDA PARA CENTRAL DE ALARMA CONTRA INCENDIOS pto 6.00

06.03.02.04 SALIDA PARA SIRENA DE ALARMA INC. SIRENA pto 6.00

06.03.02.05 SALIDA PARA ALTOPARLANTE pto 52.00

06.03.02.06 TABLERO DE CONTROL DE SONIDO INCL. EQUIPO DE AMPLIFICACION DE pto 2.00

06.03.02.07 SALIDA PARA MICROFONO pto 2.00

06.03.02.08 SALIDA PARA CENTRAL DE COMPUTO pto 1.00

06.03.02.09 SALIDA PARA ACCES POINT 600 MW pto 3.00

06.03.02.10 SALIDA PARA RED DE DATOS - INTERNET pto 59.00

06.03.02.11 SALIDA PARA AUDIO pto 11.00

06.03.02.12 SALIDA PARA PROYECTOR MULTIMEDIA pto 12.00

06.03.02.13 TRANSFORMADOR DE CORRIENTE DE 7 KVA pto 1.00

06.03.02.14 ESTABILIZADOR DE 7KVA pto 1.00

06.04 SISTEMA ELECTRICO

06.04.01 TOMAS ELECTRICAS

06.04.01.01 Suministro de Tomacorriente doble con espiga a tierra 15A-250V und 15.00

06.04.01.02 Suministro de Placa de baquelita para tomacorriente doble con espiga a tierra und 15.00

06.05 RED DE DATOS

06.05.01 CANALETAS

06.05.01.01 Suministro de accesorios para tubo de PVC SAP GLB 10.00

06.05.01.02 Suministro de caja d/derivacin metalica c/tapa GLB 10.00

06.05.01.03 Suministro de Tubo de PVC 3/4" SAP und 10.00

06.05.01.04 Suministro de Tubo de PVC 1" SAP und 10.00

06.05.02 CONDUCTORES Y/O CABLES


06.05.02.01 CABLE DE SEAL PARA DETECTOR DE HUMO m 269.00

06.05.02.02 CABLE COAXIAL PARA SEAL DE AUDIO m 437.00

06.05.02.03 CABLE UTP PARA INTERNET m 669.00

06.05.03 ACCESORIOS Y EQUIPOS RED DE DATOS, VOZ Y WIRELESS

06.05.03.01 SUMINISTRO DE CAJA 2"X4"X1.45" EMPOTRABLE PARA DATOS Y VOZ und 13.00

06.05.03.02 Suministro de capuchas para plug RJ-45 azul und 61.00

06.05.03.03 Suministro de jack RJ-45 Cat 6 poncheo azul und 61.00

06.05.03.04 SUMINISTRO DE PACH PANEL CAT 6 24 PUERTOS TIPO 110 und 3.00

06.05.03.05 Organizador horizontal 1RU con tapa und 3.00

06.05.03.06 Suministro de Gabinete de comunicaciones de piso 120x60x80 cm und 5.00

06.05.03.07 Suministro de aire acondicionado 24000 BTU und 2.00

06.05.03.08 Suministro de un UPS potencia de salida 2200VA/1980 WATTS und 61.00

06.05.03.09 Suministro de Access Point Wireless Indoor und 4.00

06.05.03.10 Instalacin accesorios red de datos und 61.00

07 MOBILIARIO UNIVERSITARIO, ADMINISTRACION Y DOCENTE

07.01 MESAS

07.01.01 MDULO M-1 und 7.00

07.01.02 MDULO M-1A und 2.00

07.01.03 MDULO M-7 und 3.00

07.01.04 MDULO M-9 und 56.00

07.01.05 MDULO M-10 und 8.00

07.02 SILLAS

07.02.01 MDULO M-2 und 108.00

07.02.02 MDULO M-5 und 33.00

07.02.03 MDULO M-6 und 126.00

07.02.04 MDULO M-8 und 300.00

07.03 ARCHIVADOR Y MOSTRAR

07.03.01 MDULO M-3 und 11.00

07.03.02 MDULO M-4 und 12.00

07.03.03 MDULO M-11 und 17.00

08 DECLARACION DE IMPACTO AMBIENTAL Y PLAN DE SEGURIDAD Y SALUD EN OBRA

08.01 DECLARACION DE IMPACTO AMBIENTAL

08.01.01 NORMATIVIDAD AMBIENTAL

08.01.01.01 MONITOREO A LA APLICACION DE NORMAS DE COMPORTAMIENTO mes 8.00

08.01.01.02 SEGUIMEINTO Y CUMPLIMIENTO A LAS PAUTAS SOCIO AMBIENTALES mes 8.00

08.01.02 PLAN DE FORESTACION Y REFORESTACION

08.01.02.01 TRAZO Y REPLANTEO DE OBRA m2 150.00

08.01.02.02 ADQUISION Y TRANSPORTE DE PLANTONES FICUS und 40.00

08.01.02.03 ADQUISION Y TRANSPORTE DE PLANTAS DE GRAS sac 8.00

08.01.02.04 SIEMBRA DE PLANTONES und 40.00

08.01.02.05 SIEMBRA DE ESQUEJAS DE GRAS m2 150.00

08.01.03 SEALIZACION

08.01.03.01 LETREROS DE SEALIZACION AMBIENTAL und 40.00

08.01.04 MANEJO DE CAMPAMENTO

08.01.04.01 CONTENEDORES DE RESIDUOS SOLIDOS und 10.00

08.01.04.02 MICRORELLENO SANITARIO GLB 1.00

08.01.04.03 INSTALACION DE LETRINAS GLB 2.00

08.01.04.04 CLAUSURA DEL MICRO RRELENO SANITARIO GLB 1.00

08.01.04.05 CLAUSURA DE LETRINAS SANITARIAS und 2.00

08.01.04.06 IMPLEMENTACION DE BOTIQUIN und 4.00

08.01.05 MANEJO DE CANTERA

08.01.05.01 MANEJO DE AREA DE CANTERA DE AGREGADOS DE RIO GLB 2.00


08.01.05.02 MANEJO DE AREA DE CANTERA DE CERRO GLB 2.00

08.01.06 EDUCACION AMBIENTAL

08.01.06.01 CHARLA AL PERSONAL DE OBRA und 20.00

08.01.06.02 CHARLA A LA COMUNIDAD BENEFICIARIA und 20.00

08.01.06.03 CHARLA A LOS ESTUDIANTES und 20.00

08.01.06.04 AFICHES AMBIENTALES und 3,000.00

08.01.06.05 BOLETINES TECNICOS AMBIENTALES und 3,000.00

08.01.06.06 POLOS CON LOGOTIPO AMBIENTALES und 400.00

08.01.06.07 DIFUCION RADIAL und 1.00

08.01.07 PARTICIPACION CIUDADANA

08.01.07.01 COMFORMACION DE COMITE DE MANTENIMIENTO GLB 2.00

08.01.07.02 COORDINACION INTERINSTITUCIONAL AMBIENTAL GLB 2.00

08.01.08 PLAN DE ABANDONO Y CIERRE

08.01.08.01 PLAN DE ABANDONO Y CIERRE GLB 1.00

08.02 PLAN DE SEGURIDAD Y SALUD EN OBRA

08.02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE GLB 1.00

SEGURIDAD Y SALUD EN EL TRABAJO

08.02.02 EQUIPO DE PROTECCION INDIVIDUAL und 80.00

08.02.03 EQUIPO DE PROTECCION COLECTIVA GLB 1.00

08.02.04 SEALIZACION TEMPORAL DE SEGURIDAD GLB 1.00

08.02.05 CAPACITACION EN SEGURIDAD Y SALUD GLB 1.00

08.02.06 RECURSO PARA RESPUESTA ANTE EMERGENCIA EN SEGURIDAD Y SALUD GLB 1.00

08.02.07 CONO DE SEALIZACION DE 0.50M DE ALTO und 35.00


COSTO DIRECTO

GASTOS GENERALES FIJOS (2.71%)

GASTOS GENERALES VARIABLES (11.29%)

UTILIDAD (10.00%)

=================

SUB TOTAL DEL PRESUPUESTO

IGV (18%)

================

PRESUPUESTO DE OBRA

EXPEDIENTE TECNICO(1.50%)

SUPERVISION (4.00%)

================

PRESUPUESTO TOTAL
Precio S/. Parcial S/. Mes 1 Mes 2 Mes 3 Mes 4
2,506,599.95

65,838.50

17,794.00

1,500.00 1,500.00 1,500.00

1,500.00 1,500.00 1,500.00

750.00 750.00 750.00

750.00 750.00 750.00

750.00 750.00 750.00

60.00 10,044.00 10,044.00

2,500.00 2,500.00 2,500.00

2,595.37

1.34 2,323.83 2,323.83

1.21 271.54 271.54


33,765.07

14.65 3,249.96

44.62 20,949.09

30.90 9,566.02

11,684.06

45.00 7,829.10

9.75 3,854.96

104,610.26
27,338.00

331.45 27,338.00

107.14 49,740.82

242.76 8,659.25

18,872.19

392.50 6,876.60

51.34 11,995.59

2,336,151.19
59,422.50

443.75 43,922.38

40.14 3,112.05

4.92 12,388.07

86,629.38

443.75 56,005.69
40.14 8,324.23

4.92 22,299.46

237,779.75

543.75 63,945.00
53.42 41,778.18

5.36 132,056.57

453,602.86

511.62 128,667.31

53.42 107,469.29

5.37 217,466.26

376,001.44

463.56 102,182.53

52.45 58,887.19

4.38 214,931.72

1,021,371.25

445.53 226,672.30

51.26 148,179.33

5.11 187,357.64
43.13 459,161.98

58,653.97

475.92 24,072.03

48.62 14,153.28

5.11 20,428.66

31,590.04

475.92 20,040.99

40.38 7,008.76

5.11 4,540.29

11,100.00

350.00 10,500.00

20.00 600.00

1,741,209.97

92,451.30

58.33 92,451.30

343,492.66

68,025.33

19.53 68,025.33

74,369.93

20.11 47,100.03
23.90 27,269.90

21,008.33

32.76 21,008.33

36,061.71

38.67 36,061.71

2,610.48

20.11 2,610.48

43,115.89
38.67 43,115.89

25,029.93

26.78 25,029.93

1,738.11

20.11 1,738.11

40,094.01

8.04 6,122.46

7.36 33,971.55

31,438.94

27.76 5,626.40

37.33 14,110.74

23.69 9,381.24

32.23 2,320.56
173,605.49

60.17 92.09

318,890.62

31.06 95,005.40

221,798.65

49.27 55,381.45

85.30 2,086.44

92.09 136,166.12

64.26 9,721.90

65.78 18,442.74

47.53 2,086.57

151,167.67
82.43 51,897.93

85.04 99,269.74

1,573.54

92.02 1,573.54

18,118.65

37.77 18,118.65

16,848.64

257.43 11,661.58

153.24 3,604.20

51.06 1,225.44

51.06 357.42

131,902.29

232.13 9,837.67

198.00 24,868.80

194.55 1,400.76

194.55 14,497.87

33.94 1,438.38

26.06 3,273.14

76,585.67

145.51 39,833.36

185.76 18,457.11

38.50 18,295.20

11,511.86

7,281.93

18.43 5,197.26

33.09 2,084.67

4,229.93

58.21 1,397.04

47.50 95.00

58.21 2,095.56

23.79 642.33

322,656.51

64.33 1,814.11

344.05 98,074.89

51.14 2,250.16

434.38 220,517.35

71,172.03

8.62 9,835.42

8.62 20,189.07

10.90 10,164.80

8.89 5,700.98

9.99 9,337.15

15,944.61

3.38 3,945.58

64.07 11,999.03

87,818.71

580.94 62,741.52

4,911.88 4,911.88

10,000.00 10,000.00

17.39 8,040.79
35.45 2,124.52

225,890.84
30848.94 15081.74 13960.76
40,833.96

20,595.84

318.88 7,653.12 7,653.12

293.82 1,762.92 1,762.92

133.86 4,818.96 4,818.96

164.50 5,922.00 5,922.00

73.14 438.84 438.84

6,196.44

44.50 1,869.00 1,869.00

34.80 626.40 626.40

12.80 537.60 537.60

39.00 1,638.00 1,638.00

36.32 1,525.44 1,525.44

10,253.10

77.72 1,865.28 1,865.28

114.80 688.80 688.80

114.80 4,132.80 4,132.80

77.72 2,797.92 2,797.92

128.05 768.30 768.30

3,788.58

19.05 800.10 800.10

19.05 342.90 342.90

22.08 927.36 927.36

9.52 399.84 399.84

31.39 1,318.38 1,318.38

47,425.13

8,833.08

75.53 3,625.44 3,625.44

100.71 1,812.78 1,812.78

80.83 3,394.86 3,394.86

5,096.72

21.81 1,313.18 1,313.18

14.94 1,008.15 1,008.15

13.65 739.97 739.97

12.43 210.56 210.56

11.93 634.91 634.91

11.63 363.79 363.79

21.81 826.16 826.16

76.19

14.94 39.89 39.89

12.43 36.30 36.30

8,766.43

27.69 1,052.22 1,052.22

22.93 1,536.31 1,536.31

20.98 1,174.88 1,174.88

19.31 463.44 463.44

17.18 824.64 824.64

16.52 776.44

39.10 742.90
25.88 1,345.76

23.88 286.56

20.40 122.40

18.37 440.88

10,492.12

292.88 5,857.60

163.54 2,453.10

142.55 855.30

110.51 1,326.12

1,727.69

815.00 815.00

912.69 912.69

12,432.90

4,144.30 12,432.90

64,016.74

100.67 1,208.04

10,572.49

82.85 10,572.49

6,465.15

198.60 6,156.60

102.85 308.55

14,754.60

1,475.46 14,754.60

13,766.46

361.78 4,341.36

516.17 6,194.04

110.51 884.08

762.15 1,524.30

411.34 822.68

17,250.00

17,250.00 17,250.00

73,615.01

5,991.72

57.08 2,397.36

54.46 3,594.36

45,618.94

56.30 13,630.23

58.65 733.13

61.81 9,144.79

109.78 2,470.05

112.94 5,082.30

63.59 10,730.81

65.94 1,236.38

69.10 2,591.25

3,430.03

129.39 2,846.58

116.69 583.45

16,567.76

20.82 1,915.44

27.73 499.14

17.68 17.68

23.76 213.84

21.77 261.24
16.36 32.72

18.40 404.80

15.69 1,270.89

19.00 342.00

16.00 2,208.00

17.99 359.80

20.28 182.52

15.90 190.80

17.91 214.92

24.42 1,294.26

20.94 397.86

35.81 1,181.73

43.82 482.02

42.75 1,453.50

50.74 1,065.54

57.13 1,885.29

63.07 693.77

2,006.56

165.75 1,657.50

349.06 349.06

691,421.31
14719.54 10929.73 9559.44
3,682.84

1.21 3,682.84 613.81 613.81 613.81


2,823.04

43.70 1,748.00 1,748.00

27.80 778.40 778.40

24.72 296.64 296.64

31,341.85

6.15 29,630.70 4,938.45 4,938.45 4,938.45

6.62 853.98 853.98

10.02 160.32 160.32

19.91 696.85 696.85

38,209.95

6.09 5,377.47 5,377.47

5.58 15,038.10

147.38 5,158.30

87.38 1,398.08 1,398.08

57.98 2,609.10 2,609.10

60.08 1,742.32

66.08 462.56

64.48 4,191.20

60.88 730.56

48.46 1,502.26

4,633.09

15.33 812.49 812.49

280.00 1,680.00 1,680.00

27.80 2,140.60 2,140.60

84,748.82

112.07 10,310.44

106.98 3,316.38

235.36 27,772.48

106.98 37,015.08

191.87 2,302.44
168.00 4,032.00

15,311.94

3297.56 3297.56

1013.19 1013.19

934.02 934.02

925.05 925.05

780.98 1,561.96

914.87 1,829.74

827.61 827.61

1,025.93 1,025.93

1,623.15 1,623.15

725.72 725.72

665.73 665.73

220.57 882.28

18,342.45

14.05 8,753.15

35.91 1,472.31

50.47 1,665.51

40.10 1,082.70

41.29 3,963.84

24.10 578.40

24.10 96.40

41.29 495.48

78.22 234.66

11,301.00

1,342.20 5,368.80

5,932.20 5,932.20

5,407.92

26.21 1,467.76

70.36 3,940.16

302,849.92

151,424.96 302,849.92

84,745.76

42,372.88 84,745.76

80,652.06

58,141.68 58,141.68

22,510.38 22,510.38

2,397.47

2,397.47 2,397.47

4,973.20

157.08 2,513.28

86.90 347.60
66.01 1,056.16

66.01 1,056.16

13,277.15

1,148.40

12.76 1,148.40

2,032.84

33.31 133.24

48.67 1,168.08

30.48 731.52

10,095.91

492.90 1,306.19

53.42 8,316.43

5.36 473.29

965,616.54

37,542.20

12,118.46 12,118.46

2,542.37 15,254.22

1,694.92 10,169.52

183,962.00

2,831.78 141,589.00

847.46 42,373.00

64,815.69

21,033.90

508.47 3,050.82

296.61 7,711.86

1,288.14 7,728.84

423.73 2,542.38

43,781.79

64.96 1,818.88

63.26 379.56

828.40 4,970.40

132.95 797.70

120.88 6,285.76

1,963.45 3,926.90

133.59 267.18

2,896.14 2,896.14

649.89 1,949.67

46.55 2,746.45

198.49 2,183.39

296.92 3,563.04

7,515.31 7,515.31

4,481.41 4,481.41

419.40

419.40

25.42 381.30

2.54 38.10

678,877.25

25,906.80

2,542.37 25,423.70

38.14 381.40

4.24 42.40

5.93 59.30

11,217.37
8.06 2,168.14

9.18 4,011.66

7.53 5,037.57

641,753.08

2.89 37.57

0.36 21.96

8.94 545.34

268.13 804.39

33.90 101.70

1,228.81 6,144.05

320.00 640.00

1,864.41 113,729.01

694.92 2,779.68

8,474.58 516,949.38

212,140.00

39,600.00

800.00 5,600.00

800.00 1,600.00

2,000.00 6,000.00

400.00 22,400.00

500.00 4,000.00

149,040.00

650.00 70,200.00

180.00 5,940.00

150.00 18,900.00

180.00 54,000.00

23,500.00

800.00 8,800.00

800.00 9,600.00

300.00 5,100.00

106,816.24
67817.64 3842.11 3842.11 3842.11
47,638.31

1,680.00

110.00 880.00 88.00 88.00 88.00 88.00

100.00 800.00
80.00 80.00 80.00 80.00

1,369.60

1.65 247.50

15.00 600.00

3.50 28.00

3.09 123.60

2.47 370.50

4,632.40

115.81 4,632.40 4,632.40

6,456.31

168.84 1,688.40 1,688.40

425.57 425.57 425.57

1,039.37 2,078.74 2,078.74

241.80 241.80 241.80

210.90 421.80 421.80

400.00 1,600.00 160.00 160.00 160.00 160.00

1,800.00

450.00 900.00 900.00


450.00 900.00 900.00

27,250.00

250.00 5,000.00 500.00 500.00 500.00 500.00


250.00 5,000.00 500.00 500.00 500.00 500.00
250.00 5,000.00 500.00 500.00 500.00 500.00
0.80 2,400.00 240.00 240.00 240.00 240.00
0.50 1,500.00 150.00 150.00 150.00 150.00
20.00 8,000.00 1600.00 711.11 711.11 711.11
350.00 350.00 35.00 35.00 35.00 35.00
1,400.00

500.00 1,000.00 100.00 100.00 100.00 100.00


200.00 400.00 40.00 40.00 40.00 40.00
3,050.00

3,050.00 3,050.00

59,177.93

6,006.01 6,006.01 6,006.01

492.13 39,370.40 39,370.40

2,463.35 2,463.35 2,463.35

1,265.64 1,265.64 1,265.64

7,380.00 7,380.00 738.00 738.00 738.00 738.00


912.78 912.78 912.78

50.85 1779.75 1779.75


6,462,972.00

175,429.90

729,386.18

646,297.20

==============

8,014,085.28

1,442,535.35

==============

9,456,620.63

141,849.31

378,264.83

==============

9,976,734.77
Mes 5 Mes 6 Mes 7 Mes 8 Mes 9 Mes 10
14207.06 91807.56 59984.78

776.44

742.90
1,345.76

286.56

122.40

440.88

5,857.60

2,453.10

855.30

1,326.12

815.00

912.69

12,432.90

1,208.04

10,572.49

6,156.60

308.55

14,754.60

4,341.36

6,194.04

884.08

1,524.30

822.68

17,250.00

2,397.36

3,594.36

13,630.23

733.13

9,144.79

2,470.05

5,082.30

10,730.81

1,236.38

2,591.25

2,846.58

583.45

1,915.44

499.14

17.68

213.84

261.24
32.72

404.80

1,270.89

342.00

2,208.00

359.80

182.52

190.80

214.92

1,294.26

397.86

1,181.73

482.02

1,453.50

1,065.54

1,885.29

693.77

1,657.50

349.06

5552.26 37693.94 ###

613.81 613.81 613.81

4,938.45 4,938.45 4,938.45

15,038.10

5,158.30

1,742.32

462.56

4,191.20

730.56

1,502.26

10,310.44

3,316.38

27,772.48

37,015.08

2,302.44
4,032.00

3297.56

1013.19

934.02

925.05

1,561.96

1,829.74

827.61

1,025.93

1,623.15

725.72

665.73

882.28

8,753.15

1,472.31

1,665.51

1,082.70

3,963.84

578.40

96.40

495.48

234.66

5,368.80

5,932.20

1,467.76

3,940.16

302,849.92

84,745.76

58,141.68

22,510.38

2,397.47

2,513.28

347.60
1,056.16

1,056.16

3,181.24 10,095.91

1,148.40

133.24

1,168.08

731.52

1,306.19

8,316.43

473.29

43,135.40 880,108.14 42,373.00

12,118.46

15,254.22

10,169.52

141,589.00

42,373.00

3,050.82

7,711.86

7,728.84

2,542.38

1,818.88

379.56

4,970.40

797.70

6,285.76

3,926.90

267.18

2,896.14

1,949.67

2,746.45

2,183.39

3,563.04

7,515.31

4,481.41

381.30

38.10

25,423.70

381.40

42.40

59.30
2,168.14

4,011.66

5,037.57

37.57

21.96

545.34

804.39

101.70

6,144.05

640.00

113,729.01

2,779.68

516,949.38

212,140.00

5,600.00

1,600.00

6,000.00

22,400.00

4,000.00

70,200.00

5,940.00

18,900.00

54,000.00

8,800.00

9,600.00

5,100.00

3842.11 3842.11 3842.11 3842.11 3842.11 8261.71

88.00 88.00 88.00 88.00 88.00 88.00

80.00 80.00 80.00 80.00 80.00 80.00

247.50

600.00

28.00

123.60

370.50

160.00 160.00 160.00 160.00 160.00 160.00


500.00 500.00 500.00 500.00 500.00 500.00

500.00 500.00 500.00 500.00 500.00 500.00

500.00 500.00 500.00 500.00 500.00 500.00

240.00 240.00 240.00 240.00 240.00 240.00

150.00 150.00 150.00 150.00 150.00 150.00

711.11 711.11 711.11 711.11 711.11 711.11

35.00 35.00 35.00 35.00 35.00 35.00

100.00 100.00 100.00 100.00 100.00 100.00

40.00 40.00 40.00 40.00 40.00 40.00

3,050.00

738.00 738.00 738.00 738.00 738.00 738.00


02.03 CIELORRASOS 173,605.49
02.03.01 CIELORRASOS EN CASETONES CON MEZCLA C:A 1:5, E=1.5CM
02.04 PISOS Y PAVIMENTOS 318,890.62
02.04.01 CONTRAPISOS
02.04.02 1:5,
PISOS48 mm

02.04.02.01 PISO TERMINADO


VINILICO ALTO
02.04.02.02 CERAMICO
TRANSITO
02.04.02.03 0.59x0.59m;
PISO:
Modelo:ONICE
TERMINADO
02.04.02.04 MARFIL
PISO: PULIDO ;
CONCRETO
MICROCEMENTO
SAN LORENZO O
ESTAMPADO
02.04.02.05 Cermico
Tipo:Matisse Negro
02.04.03 SARDINEL;
36x36 DE
CA h = 0.60 M
02.05 ZOCALOS Y
(E=0.13 m ) PARA
CONTRAZOCALOS
JARDIN
173,605.49
2,885.25 60.17 92.09
318,890.62
m2 3,058.77 31.06 95,005.40
221,798.65

m2 1,124.04 49.27 55,381.45

m2 24.46 85.30 2,086.44


m2 1,478.62 92.09 136,166.12
m2 151.29 64.26 9,721.90

m2 280.37 65.78 18,442.74

m 43.90 47.53 2,086.57


151,167.67
Item Descripcin Und. Metrado
02.05.01 ZOCALO DE CERAMICO 0.36X0.36M MATISSE NEGRO (1.50m) m2 629.60

02.05.02 CONTRAZOCALO DE MICROCEMENTO (0.08 m) m 1,167.33


02.06 CERAMICOS EN LAVADEROS

02.06.01 CERAMICO EN LAVADEROS m2 17.10

02.07 COBERTURAS

02.07.01 TARRAJEO CON IMPERMEABILIZANTES, MEZCLA 1:1, E=1.5CM m2 479.71

02.08 CARPINTERIA DE MADERA

02.08.01 PUERTA CONTRAPLACADA SEGUN DISEO m2 45.30

02.08.02 PUERTA APANELADA SEGUN DISEO m2 23.52

02.08.03 COLOCACION DE PUERTAS CONTRAPLACADAS und 24.00

02.08.04 COLOCACION DE PUERTAS APANELADAS und 7.00

02.09 CARPINTERA METLICA Y HERRERA

02.09.01 PUERTA METALICA SEGUN DISEO m2 42.38

02.09.02 VENTANAS DE ALUMINIO ; COLOR NEGRO;SEGN DISEO DE 6MM INC m2 125.60


ACCESORIOS
02.09.03 SEPARADOR DE MELAMINE PARA URINARIO m2 7.20
02.09.04 DIVISIN DE PLANCHA DE ACERO GALVANIZADO PARA SERVICIOS m2 74.52
HIGINICOS
02.09.05 COLOCACION DE PUERTAS METALICOS m2 42.38
02.09.06 COLOCACION DE VENTANA DE ALUMINIO CON VIDRIO TEMPLADO m2 125.60

02.09.07 BARANDAS

02.09.07.01 BARANDA METALICO EN CORREDOR H=0.95m m 273.75

02.09.07.02 BARANDA METALICO EN ESCALERA H=0.95m m 99.36

02.09.07.03 CANTONERAS EN PASOS PARA ESCALERAS DE 1 1/2X3MM m 475.20

02.10 CERRAJERIA

02.10.01 BISAGRAS

02.10.01.01 BISAGRA DE FIERRO DE 4" CON EJE DE 1/2" pza 282.00

02.10.01.02 BISAGRA ALTA ROTACION 1110 pza 63.00


02.10.02 CERRADURAS

02.10.02.01 CERRADURA BOTON INTERIOR Y LLAVE EXTERIOR pza 24.00

02.10.02.02 CERRADURA PARA PUERTAS (03 GOLPES) INCLUYE TIRADOR pza 2.00

02.10.02.03 CERRADURA PARA PUERTA CON PESTILLO SS.HH pza 36.00

02.10.02.04 MANIJA DE BRONCE DE 4" PARA PUERTAS und 27.00

02.11 VIDRIOS, CRISTALES Y SIMILARES

02.11.01 ESPEJOS EN BAOS E = 6MM m2 28.20

02.11.02 VIDRIOS 8MM SISTEMA DIRECTO m2 285.06

02.11.03 COLOCACION EN SISTEMA DIRECTO und 44.00

02.11.04 SUMINISTRO Y COLOCACION DE MURO CORTINA EXTERIOR m2 507.66


02.12 PINTURA

02.12.01 PINTURA EN EXTERIORES; ACABADO: FROTACHADO LISO Y PINTADO m2 1,141.00


SUPER MATE
02.12.02 PINTURA EN INTERIORES: ACABADO: FROTACHADO LISO Y PINTADO m2 2,342.12
02.12.03 PINTURA DE VIGAS; ACABADO: FROTACHADO LISO Y PINTADO m2 932.55

02.12.04 PINTURA DE COLUMNAS; ACABADO: FROTACHADO LISO Y PINTADO m2 641.28

02.12.05 PINTURA EN DERRAMES (0.15m); ACABADO: FROTACHADO LISO Y PINTADO m2 934.65

02.12.06 PINTURA DE CONTRAZOCALO Y BARANDAS

02.12.06.01 PINTURA DE CONTRAZOCALO (0.08 m ) m 1,167.33

02.12.06.02 PINTURA EN BARANDAS (0.95 m ) m 187.28

02.13 VARIOS, LIMPIEZA Y JARDINERA

02.13.01 BUTACAS INCLUIDO INSTALACION und 108.00

02.13.02 LIMPIEZA PERMANENTE DE OBRA glb 1.00

02.13.03 LIMPIEZA FINAL DE OBRA glb 1.00

02.13.04 LIMPIEZA DE VIDRIOS m2 462.38

02.13.05 JARDIN m2 59.93

03 INSTALACIONES SANITARIAS

03.01 APARATOS Y ACCESORIOS SANITARIOS


Precio S/. Parcial S/.
82.43 51,897.93

85.04 99,269.74
1,573.54

92.02 1,573.54

18,118.65

37.77 18,118.65

16,848.64

257.43 11,661.58

153.24 3,604.20

51.06 1,225.44

51.06 357.42

131,902.29

232.13 9,837.67

198.00 24,868.80

194.55 1,400.76
194.55 14,497.87

33.94 1,438.38
26.06 3,273.14

76,585.67

145.51 39,833.36

185.76 18,457.11

38.50 18,295.20

11,511.86

7,281.93

18.43 5,197.26

33.09 2,084.67
4,229.93

58.21 1,397.04

47.50 95.00

58.21 2,095.56

23.79 642.33

322,656.51

64.33 1,814.11

344.05 98,074.89

51.14 2,250.16

434.38 220,517.35
71,172.03

8.62 9,835.42

8.62 20,189.07
10.90 10,164.80

8.89 5,700.98

9.99 9,337.15

15,944.61

3.38 3,945.58

64.07 11,999.03

87,818.71

580.94 62,741.52

4,911.88 4,911.88

10,000.00 10,000.00

17.39 8,040.79

35.45 2,124.52

225,890.84

40,833.96
Item Descripcin Und.
Metrado Precio S/. Parcial S/.

03.01.01 SUMISTRO DE APARATOS SANITARIOS 20,595.84

03.01.01.01 URINARIO BAMBI COLOR BLANCO/TRBOL O SIMILAR und


03.01.01.02 INODORO BABY COLOR BLANCO/TRBOL O SIMILAR und

03.01.01.03 INODORO NOVARA FLUX COLOR BLANCO/TRBOL O SIMILAR und

03.01.01.04 OVALN CERALUX COLOR BLANCO/TRBOL O SIMILAR und

03.01.01.05 LAVATORIO FONTANA COLOR BLANCO/TREBOL O SIMILAR und

03.01.02 SUMINISTRO DE ACCESORIOS

03.01.02.01 DISPENSADOR DE PAPEL ADOSADO A PARED und


03.01.02.02 DISPENSADOR DE JABN LQUIDO ADOSADO EN PARED. und

03.01.02.03 PORTAPAPEL REDONDO CROMADO und

03.01.02.04 TACHO DE BASURA METLICO und

03.01.02.05 LLAVE DE 1/2" LAVATORIO TEMPORIZADA PICO LARGO und

03.01.03 INSTALACIN DE APARATOS SANITARIOS

03.01.03.01 INSTALACION DE URINARIO BAMBI COLOR BLANCO/TRBOL O SIMILAR und

03.01.03.02 INSTALACION DE INODORO BABY COLOR BLANCO/TRBOL O SIMILAR und

03.01.03.03 INSTALACION DE INODORO NOVARA FLUX COLOR BLANCO/TRBOL O und


SIMILAR
03.01.03.04 INSTALACION DE OVALN CERALUX COLOR BLANCO/TRBOL O SIMILAR und
03.01.03.05 INSTALACION DE LAVATORIO FONTANA COLOR BLANCO/TREBOL O und
SIMILAR
03.01.04 INSTALACIN DE ACCESORIOS

03.01.04.01 INSTALACION DE DISPENSADOR DE PAPEL ADOSADO A PARED und

03.01.04.02 INSTALACION DE DISPENSADOR DE JABN LQUIDO ADOSADO EN und


PARED.
03.01.04.03 INSTALACION DE PORTAPAPEL REDONDO CROMADO und
03.01.04.04 INSTALACION DE TACHO DE BASURA METLICO und

03.01.04.05 INSTALACION DE LLAVE DE 1/2" LAVATORIO TEMPORIZADA PICO LARGO und

03.02 SISTEMA DE AGUA FRIA

03.02.01 SALIDA DE AGUA FRIA

03.02.01.01 Salida de agua fria 1/2'' pto

03.02.01.02 Salida de agua fria 1'' pto

03.02.01.03 Salida de agua fria 1 1/4'' pto

03.02.02 REDES DE DISTRIBUCION

03.02.02.01 RED DE DISTRIBUCION TUBERIA DE 2 1/2" PVC-SAP m

03.02.02.02 RED DE DISTRIBUCION TUBERIA DE 1 1/2" PVC-SAP m

03.02.02.03 RED DE DISTRIBUCION TUBERIA DE 1 1/4" PVC-SAP m

03.02.02.04 RED DE DISTRIBUCION TUBERIA DE 1" PVC-SAP m

03.02.02.05 RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP m

03.02.02.06 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP m

03.02.02.07 RED DE ALIMENTACION TUBERIA DE 2 1/2" PVC-SAP m

03.02.03 REDES DE ALIMENTACION

03.02.03.01 RED DE ALIMENTACION TUBERIA DE 1 1/2" PVC-SAP m

03.02.03.02 RED DE ALIMENTACION TUBERIA DE 1" PVC-SAP m


03.02.04 ACCESORIOS DE REDES DE AGUA

03.02.04.01 CODO DE PVC SAP 2 1/2" pza

03.02.04.02 CODO DE PVC SAP 1 1/2" pza

03.02.04.03 CODO DE PVC SAP 1 1/4" pza

03.02.04.04 CODO DE PVC SAP 1" pza

03.02.04.05 CODO DE PVC SAP 3/4" pza

03.02.04.06 CODO DE PVC SAP 1/2" pza

03.02.04.07 TEE DE PVC SAP 2 1/2" pza

03.02.04.08 TEE DE PVC SAP 1 1/2" pza

03.02.04.09 TEE DE PVC SAP 1 1/4" pza

03.02.04.10 TEE DE PVC SAP 1" pza


03.02.04.11 TEE DE PVC SAP 3/4" pza

03.02.05 LLAVES Y VALVULAS


03.01.01 SUMINISTRO DE APARATOS SANITARIOS
03.01.01.01 URINARIO BAMBI COLOR BLANCO/TRBOL O SIMILAR und

03.01.01.02 INODORO BABY COLOR BLANCO/TRBOL O SIMILAR und

03.01.01.03 INODORO NOVARA FLUX COLOR BLANCO/TRBOL O SIMILAR und

03.01.01.04 OVALN CERALUX COLOR BLANCO/TRBOL O SIMILAR und

03.01.01.05 LAVATORIO FONTANA COLOR BLANCO/TREBOL O SIMILAR und

03.01.02 SUMINISTRO DE ACCESORIOS

03.01.02.01 DISPENSADOR DE PAPEL ADOSADO A PARED und

03.01.02.02 DISPENSADOR DE JABN LQUIDO ADOSADO EN PARED. und

03.01.02.03 PORTAPAPEL REDONDO CROMADO und

03.01.02.04 TACHO DE BASURA METLICO und

03.01.02.05 LLAVE DE 1/2" LAVATORIO TEMPORIZADA PICO LARGO und

03.01.03 INSTALACIN DE APARATOS SANITARIOS

03.01.03.01 INSTALACION DE URINARIO BAMBI COLOR BLANCO/TRBOL O SIMILAR und

03.01.03.02 INSTALACION DE INODORO BABY COLOR BLANCO/TRBOL O SIMILAR und

03.01.03.03 INSTALACION DE INODORO NOVARA FLUX COLOR BLANCO/TRBOL O und

SIMILAR

03.01.03.04 INSTALACION DE OVALN CERALUX COLOR BLANCO/TRBOL O SIMILAR und

03.01.03.05 INSTALACION DE LAVATORIO FONTANA COLOR BLANCO/TREBOL O und

SIMILAR
03.01.04
INSTALACIN DE ACCESORIOS
03.01.04.01 INSTALACION DE DISPENSADOR DE PAPEL ADOSADO A PARED und

03.01.04.02 INSTALACION DE DISPENSADOR DE JABN LQUIDO ADOSADO EN und

PARED.

03.01.04.03 INSTALACION DE PORTAPAPEL REDONDO CROMADO und

03.01.04.04 INSTALACION DE TACHO DE BASURA METLICO und

03.01.04.05 INSTALACION DE LLAVE DE 1/2" LAVATORIO TEMPORIZADA PICO LARGO und

03.02 SISTEMA DE AGUA FRIA

03.02.01 SALIDA DE AGUA FRIA

03.02.01.01 Salida de agua fria 1/2'' pto

03.02.01.02 Salida de agua fria 1'' pto

03.02.01.03 Salida de agua fria 1 1/4'' pto

03.02.02 REDES DE DISTRIBUCION

03.02.02.01 RED DE DISTRIBUCION TUBERIA DE 2 1/2" PVC-SAP m

03.02.02.02 RED DE DISTRIBUCION TUBERIA DE 1 1/2" PVC-SAP m

03.02.02.03 RED DE DISTRIBUCION TUBERIA DE 1 1/4" PVC-SAP m

03.02.02.04 RED DE DISTRIBUCION TUBERIA DE 1" PVC-SAP m

03.02.02.05 RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP m

03.02.02.06 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP m

03.02.02.07 RED DE ALIMENTACION TUBERIA DE 2 1/2" PVC-SAP m

03.02.03 REDES DE ALIMENTACION

03.02.03.01 RED DE ALIMENTACION TUBERIA DE 1 1/2" PVC-SAP m

03.02.03.02 RED DE ALIMENTACION TUBERIA DE 1" PVC-SAP m

03.02.04 ACCESORIOS DE REDES DE AGUA

03.02.04.01 CODO DE PVC SAP 2 1/2" pza

03.02.04.02 CODO DE PVC SAP 1 1/2" pza

03.02.04.03 CODO DE PVC SAP 1 1/4" pza

03.02.04.04 CODO DE PVC SAP 1" pza

03.02.04.05 CODO DE PVC SAP 3/4" pza

03.02.04.06 CODO DE PVC SAP 1/2" pza

03.02.04.07 TEE DE PVC SAP 2 1/2" pza

03.02.04.08 TEE DE PVC SAP 1 1/2" pza

03.02.04.09 TEE DE PVC SAP 1 1/4" pza


03.02.04.10 TEE DE PVC SAP 1" pza

03.02.04.11 TEE DE PVC SAP 3/4" pza

03.02.05 LLAVES Y VALVULAS


20,595.84

24.00 318.88 7,653.12


6.00 293.82 1,762.92

36.00 133.86 4,818.96

36.00 164.50 5,922.00

6.00 73.14 438.84

6,196.44

42.00 44.50 1,869.00


18.00 34.80 626.40

42.00 12.80 537.60

42.00 39.00 1,638.00

42.00 36.32 1,525.44

10,253.10

24.00 77.72 1,865.28

6.00 114.80 688.80

36.00 114.80 4,132.80

36.00 77.72 2,797.92


6.00 128.05 768.30

3,788.58

42.00 19.05 800.10

18.00 19.05 342.90

42.00 22.08 927.36


42.00 9.52 399.84

42.00 31.39 1,318.38

47,425.13

8,833.08

48.00 75.53 3,625.44

18.00 100.71 1,812.78

42.00 80.83 3,394.86

5,096.72

60.21 21.81 1,313.18

67.48 14.94 1,008.15

54.21 13.65 739.97

16.94 12.43 210.56

53.22 11.93 634.91

31.28 11.63 363.79

37.88 21.81 826.16

76.19

2.67 14.94 39.89

2.92 12.43 36.30


8,766.43

38.00 27.69 1,052.22

67.00 22.93 1,536.31

56.00 20.98 1,174.88

24.00 19.31 463.44

48.00 17.18 824.64

47.00 16.52 776.44

19.00 39.10 742.90

52.00 25.88 1,345.76

12.00 23.88 286.56

6.00 20.40 122.40


24.00 18.37 440.88

10,492.12
20,595.84
24.00 318.88 7,653.12

6.00 293.82 1,762.92

36.00 133.86 4,818.96

36.00 164.50 5,922.00

6.00 73.14 438.84

6,196.44

42.00 44.50 1,869.00

18.00 34.80 626.40

42.00 12.80 537.60

42.00 39.00 1,638.00

42.00 36.32 1,525.44

10,253.10

24.00 77.72 1,865.28

6.00 114.80 688.80

36.00 114.80 4,132.80

36.00 77.72 2,797.92

6.00 128.05 768.30

3,788.58

42.00 19.05 800.10

18.00 19.05 342.90

42.00 22.08 927.36

42.00 9.52 399.84

42.00 31.39 1,318.38

47,425.13

8,833.08

48.00 75.53 3,625.44

18.00 100.71 1,812.78

42.00 80.83 3,394.86

5,096.72

60.21 21.81 1,313.18

67.48 14.94 1,008.15

54.21 13.65 739.97

16.94 12.43 210.56

53.22 11.93 634.91

31.28 11.63 363.79

37.88 21.81 826.16

76.19

2.67 14.94 39.89

2.92 12.43 36.30

8,766.43

38.00 27.69 1,052.22

67.00 22.93 1,536.31

56.00 20.98 1,174.88

24.00 19.31 463.44

48.00 17.18 824.64

47.00 16.52 776.44

19.00 39.10 742.90

52.00 25.88 1,345.76

12.00 23.88 286.56


6.00 20.40 122.40

24.00 18.37 440.88

10,492.12
Item Descripcin Und. Metrado
03. VALVULA p 20.00
02. COMPUE z
05.
03. RTA
VALVULA ap 15.00
01
02. BRONCE
COMPUE z
03.
05. DE 2 1/2"
VALVULA
RTA pa 6.00
02.
02 COMPUE
BRONCE z
03.
05. VALVULA
RTA ua 12.00
DE 1 1/2"
02.
03
03.02.06
COMPUE
BRONCE n
05. ALMACENAM
RTA d
DE 1 1/4"
04 IENTO DE
BRONCE
03. AGUACISTERN G 1.00
DE 4"
02. A CAP. = L
03.
06. CISTERN
39 m3 G
B 1.00
02.
01
03.02.07
A CAP. = L
06. EQUIPOS
45.42 Ym3 B
02 OTRAS
03. ELECTR
INSTALACIO u 3.00
02. NES OBOMBA n
03.
07. SISTEMA
7.5 HP DE d
03
01
03.03.01
AGUA
SALIDA
CONTRA DE p 12.00
03.03.02
AGUA
INCENDIOS t
RED DE
CONTRAINCE o
ALIMENTACI
NDIO
03. ON RED DE m 127.61
03.
03.03.03
ALIMENT
02. ACCESORIO
ACION
01 REDES DE
TUBERIA
03. AGUACodo de u 31.00
HDPE de
03. HDPE de
CONTRA n
03. 4" de
Tee ud 3.00
03. 4 x 90
INCENDIO
03.
01
03.03.04
HDPE de n
03. SUMINISTRO
4" d
02 E
03. GABNIET
INSTALACI u 10.00
03.
03.03.05 N DE E n
04. VLVULAS
CONTRA d
GABINETES
01 DE SISTEMA
INCENDI
03. CONTRA
VLVULA u 12.00
CONTRA
O 2 1/2"
03. INCENDIO
ANGULA n
INCENDIO
03.
05. VLVULA
R DE 1 ud 12.00
03.
01 ANGULA
1/2 " n
03.
05. VALVULA
R DE 2 ud 8.00
03.
02 COMPUE
1/2 " n
03.
05. VLVULA
RTA ud 2.00
03.
03 CHECK
BRONCE n
03.
05. VALVULA
RANURA ud 2.00
DE 4"
03.
04
03.03.06
DE
DA 4" n
05. INSTALACIO
ALIVIO d
05 NES DE 4"
03. ELECTR
ESPECIALES u 1.00
03. OBOMBA n
03.
06. DESAGUE
60 HP Y d
04
01
03.04.01
VENTILACIO
SALIDADE
N
DE
03. SALIDA
DESAGUE p 42.00
04. DE t
03.
01. SALIDA
DESAGU po 66.00
04.
01
03.04.02
DE
E CON t
01. REDES DE
DESAGU o
PVC 4"
02 DERIVACION
E CON
03. RED DE m 242.10
PVC 2"
04. DERIVAC
03.
02. RED
IN DE m 12.50
04.
01 DERIVAC
TUBERIA
03.
02. RED
IN DE m 147.95
PVC
04.
02 DERIVAC
TUBERIA
03. SIMPLE
MONTAN m 22.50
02. IN
PVC
04. PRESI
TE DE
03 TUBERIA
SIMPLE
03.
02. MONTAN
N DE 2"
DESAG m 45.00
PVC
PRESI
04.
04 TE DE
E PVC
03. SIMPLE
TUBERA
N DE 3" m 168.75
02. DESAG
SIMPLE
04. PRESI
DE
05 E PVC
PRESI
03.
02. TUBERA
N DE 4"
VENTILA m 18.75
SIMPLE
N DE 3"
04.
06 DE
CIN
03. PRESI
TUBERA m 37.50
02. VENTILA
PVC
04. N DE 4"
DE
07
03.04.03 CIN
SIMPLE
02. REDESVENTILA
PVC
PRESI
08 COLECTORA
CIN
03. SIMPLE
RED
N DE 2" m 22.00
S PVC
04. PRESI
COLECT
03. SIMPLE
RED
N DE 3" m 5.00
03. ORA
04. PRESI
COLECT
01
03.04.04 TUBERIA
03. ACCESORIO
N DE 4"
ORA
PVC
02 S DE TUBERIA
REDES
03. 160mm
YEE DE u 92.00
PVC
S-25 C-
04. PVC DE n
03. 10 3"
YEE
04. 2" DE ud 18.00
04.
01 PVC DE n
03.
04. YEE
4" DE ud 1.00
04.
02 3"PVC n
03.
04. YEE
CON DE ud 9.00
04.
03 4"PVC
REDUCC n
03.
04. YEE
CON DE ud 12.00
IN A
04.
04 4"PVC
REDUCC n
03. 2"
REDUCC ud 2.00
04. CON
IN A
04.
05 IN
REDUCCDE n
03. 3"
REDUCC ud 22.00
04. PVC
IN ADE
04.
06 IN
3" DE n
03. 2" A 2"
CODO ud 81.00
04. PVC DE
04.
07 DE PVC
4" A 2" n
03.
04. CODO
DE 2" A ud 18.00
04.
08 DE
45 PVC n
03.
04. CODO
DE 4" A ud 138.00
04.
09 DE
45 PVC n
03.
04. CODO
DE 2" A ud 20.00
04.
10 DE
90 PVC n
03.
04. CODO
DE 3" A ud 9.00
04.
11 DE
90 PVC n
04. DE 4" A d
12 90
03. TEE DE und 12.00
04. PVC DE
04.
03. 2"
TEE DE und 12.00
13
04. PVC DE
03.
04. TEE
3" DE und 53.00
04.
14 PVC DE
03.
04. TEE
4" DE und 19.00
04.
15 4" CON
03.
04. TRAMPA
REDUCC und 33.00
04.
16 "P"
INDEA
03.
04. TRAMPA
PVC DE und 11.00
2" DE
04.
17 "P"
2" DE
03. PVC
REGIST und 34.00
04. PVC DE
04.
18 RO
3"
03.
04. REGIST
ROSCAD und 21.00
04.
19 RO
O DE
03.
04. SUMIDE
ROSCAD und 33.00
BRONCE
04.
20 RO
O DEDE
03. DE 2"
SUMIDE und 11.00
04. BRONCE
BRONCE
04.
21 RO DE
DE 4"
2"
03.04.05
CMARAS DE
04. BRONCE
22 DE DE 3"
03. INSPECCIN CAJA DE und 10.00
04. REGIST
03.
05. CAJA
RO DEDE und 1.00
04.
01 REGIST
12"X24"
04
05. INSTALACIONES RO DE
02 ELECTRICAS 1.00Ym
04. TRABAJOS
ELECTROMECANI
01
04.01.01 CAS PRELIMINAR
TRAZOS,
ES m2 3,043.67
NIVELES Y
04. MOVIMIENTO
REPLANTEO
02
04.02.01
DE TIERRAS
PRELIMINAR
EXCAVACION m3 40.00
04.02.02
DE
RELLENO
ZANJA,TERRE Y m3 28.00
04.02.03
COMPACTACI
NO NORMAL
ELIMINACION
ON DE m3 12.00
MATERIAL
MATERIAL
04. TUBERIAS
EXCEDENTE Y
PROPIO
03
04.03.01
DUCTO
TUBO PVC- m 4,818.00
04.03.02
SAP DE
TUBO
20mmXPVC- 3m m 129.00
04.03.03
SAP DE
TUBO
25mmXPVC- 3m m 16.00
04.03.04
SAP DE
TUBO
50mmXPVC- 3m m 35.00
SAP DE
04. CONDUCTOR
80mmX 3m
04
04.04.01
ES Y/O
CONDUCTOR
CABLES m 883.00
04.04.02
TIPO LSOH DE
CONDUCTOR
2-1x4mm2 m 2,695.00
04.04.03
TIPO
+2.5mm2 LSOH DE
CONDUCTOR
2(TIERRA)
- 1x2.5mm2 + m 35.00
04.04.04
N2XOH
2.5mm2 3 - 1 X
CONDUCTOR
70 mm2 m 16.00
(TIERRA)
04.04.05
N2XOH 3 - 1 X
CONDUCTOR
25 mm2 m 45.00
04.04.06
N2XOH 3 - 1 x
CONDUCTOR
10 mm2 m 29.00
04.04.07
N2XOH 3 - 1 x
CONDUCTOR
10 mm2+ 1X m 7.00
04.04.08
N2XOH
2.5mm2(TIERR 3-1X
CONDUCTOR
4A)mm2 + 1 X m 65.00
04.04.09
N2XOH
2.5mm2(TIERR2 -1 X
CONDUCTOR
6A)mm2 + 1x m 12.00
04.04.10
N2XOH 2-1X
2.5mm2(TIERR
CONDUCTOR
4A)mm2 + 1 X m 31.00
NYY 1 - 2 X 2.5
2.5mm2(TIERR
04. CAJAS
mm2 DE
A) + 1 X
05
04.05.01
PASO Y
1.5mm2(TIERR
CAJA
BUZONES DE DE und 53.00
A)
04.05.02
INTERCONEXI
REGISTRO
BUZON
ON DE DE GLB 6.00
04.05.03
CONCRETO
100X100X100m
RED
ARMADO. m 77.00
m
SUBTERRNE
04. ARTEFACTO
A
06
04.06.01
S DE
FLUORESCENTE ILUMINACIO und 92.00
DE 3 X18W
REJILLA N
04.06.02
INC/EQUIPO Y
PANTALLA FLUORESCEN und 31.00
04.06.03 CUADRADO CON TE DE 2 X36W
SPOT LAIGHTY
INC/EQUIPO und 118.00
04.06.04
CON FOCO
PANTALLA
DICROICO
LED 10W und 346.00
RECTANGULA
LEDS DE 10W
04.06.05 PARA
R
LUMINARIA
LUZ BLANCA und 12.00
EMPOTRAR
TIPO
PARA
LUMINARIA TECHO
04.06.06

BOLLARD und 24.00


EMPOTRAR
ESFERICA INC. CON FOCO BRAQUET
LAMPARA (LED DE LEDS DE 6W
04.07 10W) PARA PARED DISTRIBUCION
TABLEROS DE 15,311.94
04.07.01
TIPO
04.07.02

04.07.03

04.07.04

TABLERO ELECTRICO GAB.METALICO AUTOSOPORTADO P/DIST PARA 5 CIRCUITOS TIPO TGD CON ANALIZADOR DE REDES
TABLERO ELECTRICO GAB.METALICO EMPOTRADO P/DIST PARA 6 CIRCUITOS TIPO STGD TRIFASICO
TABLERO DISTRIBUCION CAJA METALICA EMPOTRADO P/DIST PARA 8 CIRCUITOS TIPO TD1 MONOFASICO
TABLERO DISTRIBUCION CAJA METALICA EMPOTRADO P/DIST PARA 10 CIRCUITOS TIPO TD2 MONOFASICO
und und und
und
1.00 3,297.56 3,297.56
1.00 1,013.19 1,013.19
1.00 934.02 934.02
1.00 925.05 925.05
Precio S/. Parcial S/.
292.88 5,857.60

163.54 2,453.10
142.55 855.30

110.51 1,326.12

1,727.69

815.00 815.00

912.69 912.69

12,432.90

4,144.30 12,432.90

64,016.74

100.67 1,208.04

10,572.49

82.85 10,572.49

6,465.15

198.60 6,156.60

102.85 308.55

14,754.60

1,475.46 14,754.60

13,766.46

361.78 4,341.36

516.17 6,194.04

110.51 884.08
762.15 1,524.30

411.34 822.68

17,250.00

17,250.00 17,250.00

73,615.01

5,991.72

57.08 2,397.36

54.46 3,594.36

45,618.94

56.30 13,630.23
58.65 733.13

61.81 9,144.79

109.78 2,470.05

112.94 5,082.30

63.59 10,730.81

65.94 1,236.38

69.10 2,591.25

3,430.03

129.39 2,846.58

116.69 583.45

16,567.76

20.82 1,915.44

27.73 499.14

17.68 17.68

23.76 213.84

21.77 261.24

16.36 32.72

18.40 404.80

15.69 1,270.89

19.00 342.00

16.00 2,208.00
17.99 359.80

20.28 182.52
15.90 190.80

17.91 214.92

24.42 1,294.26

20.94 397.86

35.81 1,181.73

43.82 482.02

42.75 1,453.50

50.74 1,065.54

57.13 1,885.29

63.07 693.77
2,006.56

165.75 1,657.50

349.06 349.06

691,421.31

3,682.84

1.21 3,682.84

2,823.04

43.70 1,748.00

27.80 778.40

24.72 296.64
31,341.85

6.15 29,630.70

6.62 853.98

10.02 160.32

19.91 696.85

38,209.95

6.09 5,377.47

5.58 15,038.10

147.38 5,158.30

87.38 1,398.08

57.98 2,609.10
60.08 1,742.32

66.08 462.56

64.48 4,191.20

60.88 730.56

48.46 1,502.26

4,633.09

15.33 812.49
280.00 1,680.00

27.80 2,140.60

84,748.82

112.07 10,310.44

106.98 3,316.38
235.36 27,772.48

106.98 37,015.08

191.87 2,302.44

168.00 4,032.00

15,311.94
1.00 3,297.56 3,297.56

1.00 1,013.19 1,013.19

1.00 934.02 934.02

1.00 925.05 925.05


Item Descripcin Und.
Metrado Precio S/. Parcial S/.

04.07.05 TABLERO DISTRIBUCION CAJA METALICA EMPOTRADO P/DIST PARA 8 und 2.00
CIRCUITOS TIPO TD3 Y TD6 MONOFASICO
04.07.06 TABLERO DISTRIBUCION CAJA METALICA EMPOTRADO P/DIST PARA 9 und 2.00
CIRCUITOS TIPO TD4 Y TD5 MONOFASICO
04.07.07 TABLERO DISTRIBUCION CAJA METALICA TIPO T.SALA DE USOS und 1.00
MULTIPLES
04.07.08 TABLERO DISTRIBUCION CAJA METALICA TIPO T. LABORATORIO DE und 1.00
COMPUTO
04.07.09 TABLERO DE DISTRIBUCION CAJA METALICA TIPO T. ASCENSORES und 1.00
04.07.10 SUB TABLERO DISTRIBUCION CAJA METALICA TIPO STD-1 und 1.00
04.07.11 SUB TABLERO DISTRIBUCION CAJA METALICA TIPO STD-2 und 1.00

04.07.12 SUB TABLERO DISTRIBUCION CAJA METALICA TIPO und 4.00


STD-2.1,STD-2.2,STD-2.3 Y STD-2.4
04.08 ACCESORIOS DE INSTALACIONES ELECTRICAS INTERIORES Y EXTERIORES

04.08.01 SALIDA PARA CENTROS DE LUZ pto 623.00

04.08.02 SALIDA PARA INTERRUPTOR SIMPLE pto 41.00

04.08.03 SALIDA PARA INTERRUPTOR DOBLE pto 33.00

04.08.04 SALIDA PARA INTERRUPTOR DE CONMUTACION pto 27.00

04.08.05 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE C/TIERRA pto 96.00

04.08.06 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE C/TIERRA EN EL PISO pto 24.00
04.08.07 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE C/TIERRA A MEDIA pto 4.00
ALTURA
04.08.08 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE C/TIERRA EN TECHO pto 12.00
04.08.09 SALIDA DE FUERZA pto 3.00

04.09 PUESTA A TIERRA

04.09.01 PUESTA A TIERRA und 4.00

04.09.02 PARARRAYO DE PROTECCIN und 1.00

04.10 SISTEMAS DE LUCES DE EMERGENCIA

04.10.01 SALIDA PARA CONTROL DE LUZ DE EMERGENCIA pto 56.00

04.10.02 ARTEFACTO DE LUZ DE EMERGENCIA pto 56.00

04.11 EQUIPOS ELECTROMECANICOS

04.11.01 ASCENSOR DE 1,000kg PARA 13 PERSONAS , 1m/s, 220V. und 2.00

04.12 SUMISTRO E INSTALACION DE ASCENSOR

04.12.01 SUMINISTRO E INSTALACION DE ASCENSOR 1 TON und 2.00

04.13 SISTEMAS DE CONTINGENCIA

04.13.01 GRUPO ELECTROGENO ENCAPSULADO DE 50 KW TRIFSICO glb 1.00

04.13.02 TABLERO DE TRANSFERENCIA AUTOMATICO PARA GENERADOR DE 50 KW glb 1.00


TRIFSICO 220V
04.14 SUMINISTRO EN MEDIA TENSIN

04.14.01 INSTALACION DE NUEVO CIRCUITO EN SUB ESTACIN EXISTENTE glb 1.00


04.15 PRUEBAS ELECTRICAS FINALES

04.15.01 PRUEBA DE AISLAMIENTO und 16.00

04.15.02 PRUEBAS DE RESISTIVIDAD DE PUESTA A TIERRA und 4.00

04.15.03 PRUEBAS DE CONTINUIDAD DE INSTALACIONES INTERIORES und 16.00

04.15.04 PRUEBAS Y BALANCEO DE CARGAS und 16.00


05 SISTEMA DE DESAGUE PLUVIAL

05.01 RED DE RECOLECCIN

05.01.01 TUBERIA DE BAJADA PVC SAP DE 4" m 90.00

05.02 ACCESORIOS

05.02.01 CODO PVC SAL 4"X90 und 4.00

05.02.02 REGISTRO DE BRONCE DE BRONCE DE 4" und 24.00

05.02.03 Tee de PVC SAP 4" und 24.00

05.03 CONCRETO REFORZADO

05.03.01 CONCRETO F'C=175 Kg/CM2 COLUMNETAS m3 2.65

05.03.02 ACERO FY=4200 Kg/CM2 kg 155.68


05.03.03 ENCOFRADO Y DESENCOFRADO m2 88.30

06 SISTEMAS ELECTRONICOS

06.01 PLATAFORMA WEB Y DE SERVICIOS MULTIPLES


780.98 1,561.96

914.87 1,829.74

827.61 827.61

1,025.93 1,025.93

1,623.15 1,623.15
725.72 725.72
665.73 665.73

220.57 882.28

18,342.45

14.05 8,753.15

35.91 1,472.31

50.47 1,665.51

40.10 1,082.70

41.29 3,963.84

24.10 578.40
24.10 96.40

41.29 495.48
78.22 234.66

11,301.00

1,342.20 5,368.80

5,932.20 5,932.20

5,407.92

26.21 1,467.76

70.36 3,940.16

302,849.92

151,424.96 302,849.92

84,745.76

42,372.88 84,745.76

80,652.06

58,141.68 58,141.68

22,510.38 22,510.38

2,397.47

2,397.47 2,397.47
4,973.20

157.08 2,513.28

86.90 347.60

66.01 1,056.16

66.01 1,056.16
13,277.15

1,148.40

12.76 1,148.40

2,032.84

33.31 133.24

48.67 1,168.08

30.48 731.52

10,095.91

492.90 1,306.19

53.42 8,316.43
5.36 473.29

965,616.54

37,542.20
Item Descripcin Und. Metrado
06.01.01 SUMINISTRO DE SERVIDOR DE DATOS und 1.00

06.01.02 SUMINISTRO DE ANTIVIRUS SERVER glb 6.00


06.01.03 INSTALACION DE PLATAFORMA WB glb 6.00

06.02 SISTEMA DE COMPUTO PARA LABORATORIOS Y AULAS

06.02.01 SUMINISTRO DE COMPUTADOR PERSONAL und 50.00

06.02.02 INSTALACION DEL SISTEMA DE COMPUTO PARA LAB Y AULAS glb 50.00

06.03 ADECUACION DE AMBIENTES MULTIMEDIAS

06.03.01 SISTEMA DE ADECUACION DE AMBIENTES

06.03.01.01 SUMINISTRO DE MODULO DE COMPUTO PARA DOCENTES und 6.00

06.03.01.02 SUMINISTRO DE SILLAS PARA MODULOS DE COMPUTO und 26.00

06.03.01.03 SUMINISTRO DE IMPRESORA LASER und 6.00

06.03.01.04 INSTALACION SISTEMA DE ADECUACION DE AMBIENTES glb 6.00

06.03.02 SISTEMA ELECTRONICOS

06.03.02.01 SALIDA PARA SENSORES DE ALARMA CONTRAINCENDIOS pto 28.00

06.03.02.02 SALIDA PARA PULSADOR DE ALARMA CONTRAINCENDIOS pto 6.00

06.03.02.03 SALIDA PARA CENTRAL DE ALARMA CONTRA INCENDIOS pto 6.00

06.03.02.04 SALIDA PARA SIRENA DE ALARMA INC. SIRENA pto 6.00

06.03.02.05 SALIDA PARA ALTOPARLANTE pto 52.00

06.03.02.06 TABLERO DE CONTROL DE SONIDO INCL. EQUIPO DE AMPLIFICACION DE pto 2.00


2000W
06.03.02.07 SALIDA PARA MICROFONO pto 2.00
06.03.02.08 SALIDA PARA CENTRAL DE COMPUTO pto 1.00

06.03.02.09 SALIDA PARA ACCES POINT 600 MW pto 3.00

06.03.02.10 SALIDA PARA RED DE DATOS - INTERNET pto 59.00

06.03.02.11 SALIDA PARA AUDIO pto 11.00

06.03.02.12 SALIDA PARA PROYECTOR MULTIMEDIA pto 12.00


06.03.02.13 TRANSFORMADOR DE CORRIENTE DE 7 KVA pto 1.00

06.03.02.14 ESTABILIZADOR DE 7KVA pto 1.00

06.04 SISTEMA ELECTRICO

06.04.01 TOMAS ELECTRICAS

06.04.01.01 Suministro de Tomacorriente doble con espiga a tierra 15A-250V und 15.00

06.04.01.02 Suministro de Placa de baquelita para tomacorriente doble con espiga a tierra und 15.00

06.05 RED DE DATOS

06.05.01 CANALETAS

06.05.01.01 Suministro de accesorios para tubo de PVC SAP GLB 10.00

06.05.01.02 Suministro de caja d/derivacin metalica c/tapa GLB 10.00


06.05.01.03 Suministro de Tubo de PVC 3/4" SAP und 10.00

06.05.01.04 Suministro de Tubo de PVC 1" SAP und 10.00

06.05.02 CONDUCTORES Y/O CABLES

06.05.02.01 CABLE DE SEAL PARA DETECTOR DE HUMO m 269.00

06.05.02.02 CABLE COAXIAL PARA SEAL DE AUDIO m 437.00

06.05.02.03 CABLE UTP PARA INTERNET m 669.00

06.05.03 ACCESORIOS Y EQUIPOS RED DE DATOS, VOZ Y WIRELESS

06.05.03.01 SUMINISTRO DE CAJA 2"X4"X1.45" EMPOTRABLE PARA DATOS Y VOZ und 13.00

06.05.03.02 Suministro de capuchas para plug RJ-45 azul und 61.00

06.05.03.03 Suministro de jack RJ-45 Cat 6 poncheo azul und 61.00


06.05.03.04 SUMINISTRO DE PACH PANEL CAT 6 24 PUERTOS TIPO 110 und 3.00

06.05.03.05 Organizador horizontal 1RU con tapa und 3.00

06.05.03.06 Suministro de Gabinete de comunicaciones de piso 120x60x80 cm und 5.00

06.05.03.07 Suministro de aire acondicionado 24000 BTU und 2.00

06.05.03.08 Suministro de un UPS potencia de salida 2200VA/1980 WATTS und 61.00

06.05.03.09 Suministro de Access Point Wireless Indoor und 4.00

06.05.03.10 Instalacin accesorios red de datos und 61.00

07 MOBILIARIO UNIVERSITARIO, ADMINISTRACION Y DOCENTE

07.01 MESAS

07.01.01 MDULO M-1 und 7.00


07.01.02 MDULO M-1A und 2.00

07.01.03 MDULO M-7 und 3.00

07.01.04 MDULO M-9 und 56.00

07.01.05 MDULO M-10 und 8.00

07.02 SILLAS

07.02.01 MDULO M-2 und 108.00

07.02.02 MDULO M-5 und 33.00

07.02.03 MDULO M-6 und 126.00

07.02.04 MDULO M-8 und 300.00

07.03 ARCHIVADOR Y MOSTRAR

07.03.01 MDULO M-3 und 11.00

07.03.02 MDULO M-4 und 12.00

07.03.03 MDULO M-11 und 17.00

08 DECLARACION DE IMPACTO AMBIENTAL Y PLAN DE SEGURIDAD Y SALUD EN OBRA

08.01 DECLARACION DE IMPACTO AMBIENTAL


08.01.01 NORMATIVIDAD AMBIENTAL

08.01.01.01 MONITOREO A LA APLICACION DE NORMAS DE COMPORTAMIENTO mes 8.00

08.01.01.02 SEGUIMEINTO Y CUMPLIMIENTO A LAS PAUTAS SOCIO AMBIENTALES mes 8.00

08.01.02 PLAN DE FORESTACION Y REFORESTACION

08.01.02.01 TRAZO Y REPLANTEO DE OBRA m2 150.00

08.01.02.02 ADQUISION Y TRANSPORTE DE PLANTONES FICUS und 40.00

08.01.02.03 ADQUISION Y TRANSPORTE DE PLANTAS DE GRAS sac 8.00


08.01.02.04 SIEMBRA DE PLANTONES und 40.00

08.01.02.05 SIEMBRA DE ESQUEJAS DE GRAS m2 150.00

08.01.03 SEALIZACION

08.01.03.01 LETREROS DE SEALIZACION AMBIENTAL und 40.00

08.01.04 MANEJO DE CAMPAMENTO

08.01.04.01 CONTENEDORES DE RESIDUOS SOLIDOS und 10.00

08.01.04.02 MICRORELLENO SANITARIO GLB 1.00

08.01.04.03 INSTALACION DE LETRINAS GLB 2.00

08.01.04.04 CLAUSURA DEL MICRO RRELENO SANITARIO GLB 1.00

08.01.04.05 CLAUSURA DE LETRINAS SANITARIAS und 2.00


08.01.04.06 IMPLEMENTACION DE BOTIQUIN und 4.00

08.01.05 MANEJO DE CANTERA

08.01.05.01 MANEJO DE AREA DE CANTERA DE AGREGADOS DE RIO GLB 2.00

08.01.05.02 MANEJO DE AREA DE CANTERA DE CERRO GLB 2.00

08.01.06 EDUCACION AMBIENTAL

08.01.06.01 CHARLA AL PERSONAL DE OBRA und 20.00

08.01.06.02 CHARLA A LA COMUNIDAD BENEFICIARIA und 20.00

08.01.06.03 CHARLA A LOS ESTUDIANTES und 20.00

08.01.06.04 AFICHES AMBIENTALES und 3,000.00

08.01.06.05 BOLETINES TECNICOS AMBIENTALES und 3,000.00


08.01.06.06 POLOS CON LOGOTIPO AMBIENTALES und 400.00

08.01.06.07 DIFUCION RADIAL und 1.00

08.01.07 PARTICIPACION CIUDADANA

08.01.07.01 COMFORMACION DE COMITE DE MANTENIMIENTO GLB 2.00

08.01.07.02 COORDINACION INTERINSTITUCIONAL AMBIENTAL GLB 2.00

08.01.08 PLAN DE ABANDONO Y CIERRE

08.01.08.01 PLAN DE ABANDONO Y CIERRE GLB 1.00

08.02 PLAN DE SEGURIDAD Y SALUD EN OBRA

08.02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE GLB 1.00


SEGURIDAD Y SALUD EN EL TRABAJO
08.02.02 EQUIPO DE PROTECCION INDIVIDUAL und 80.00
08.02.03 EQUIPO DE PROTECCION COLECTIVA GLB 1.00

08.02.04 SEALIZACION TEMPORAL DE SEGURIDAD GLB 1.00


Precio S/. Parcial S/.
12,118.46 12,118.46

2,542.37 15,254.22
1,694.92 10,169.52

183,962.00

2,831.78 141,589.00

847.46 42,373.00

64,815.69

21,033.90

508.47 3,050.82

296.61 7,711.86

1,288.14 7,728.84

423.73 2,542.38

43,781.79

64.96 1,818.88

63.26 379.56

828.40 4,970.40

132.95 797.70

120.88 6,285.76

1,963.45 3,926.90

133.59 267.18
2,896.14 2,896.14

649.89 1,949.67

46.55 2,746.45

198.49 2,183.39

296.92 3,563.04
7,515.31 7,515.31

4,481.41 4,481.41

419.40

419.40

25.42 381.30

2.54 38.10

678,877.25

25,906.80

2,542.37 25,423.70

38.14 381.40
4.24 42.40

5.93 59.30

11,217.37

8.06 2,168.14

9.18 4,011.66

7.53 5,037.57

641,753.08

2.89 37.57

0.36 21.96

8.94 545.34
268.13 804.39

33.90 101.70

1,228.81 6,144.05

320.00 640.00

1,864.41 113,729.01

694.92 2,779.68

8,474.58 516,949.38

212,140.00

39,600.00

800.00 5,600.00
800.00 1,600.00

2,000.00 6,000.00

400.00 22,400.00

500.00 4,000.00

149,040.00

650.00 70,200.00

180.00 5,940.00

150.00 18,900.00

180.00 54,000.00

23,500.00

800.00 8,800.00

800.00 9,600.00

300.00 5,100.00

106,816.24

47,638.31
1,680.00

110.00 880.00

100.00 800.00

1,369.60

1.65 247.50

15.00 600.00

3.50 28.00
3.09 123.60

2.47 370.50

4,632.40

115.81 4,632.40

6,456.31

168.84 1,688.40

425.57 425.57

1,039.37 2,078.74

241.80 241.80

210.90 421.80
400.00 1,600.00

1,800.00

450.00 900.00

450.00 900.00

27,250.00

250.00 5,000.00

250.00 5,000.00

250.00 5,000.00

0.80 2,400.00

0.50 1,500.00
20.00 8,000.00

350.00 350.00

1,400.00

500.00 1,000.00

200.00 400.00

3,050.00

3,050.00 3,050.00

59,177.93

6,006.01 6,006.01

492.13 39,370.40
2,463.35 2,463.35

1,265.64 1,265.64
Item Descripcin Und. Metrado
08.02.05 CAPACITACI GLB 1.00
ON EN
08.02.06 SEGURIDAD
RECURSO GLB 1.00
Y SALUD
PARA
08.02.07
RESPUESTA
DURANTE EL TRABAJO ANTE
CONO DE SEALIZACION DE 0.50M DE ALTO EMERGENCI und
35.00 50.85 1,779.75A EN
SEGURIDAD
COSTO Y SALUD 6,462,972.00
DIRECT
GASTO 175,429.90
O
S
GASTO
GENER 729,386.18
S
ALES
UTILID
GENER 646,297.20
FIJOS
AD
ALES
(2.71%)
====== ==============
(10.00%
VARIAB
======
)LES
SUB
===== 8,014,085.28
(11.29%
TOTAL
)
IGV
DEL 1,442,535.35
(18%)
PRESU
====== ==============
PUEST
======
O
PRESU 9,456,620.63
====
PUEST
EXPEDI
O DE 141,849.31
ENTE
OBRA
SUPER
TECNIC 378,264.83
VISION
O(1.50
======
(4.00%) ==============
%)
======
PRESU
==== 9,976,734.77
PUEST
O
TOTAL
Precio S/. Parcial S/.
7,380.00 7,380.00

912.78 912.78