WeeklyMonitoringForm

Date 11/5/2017 ReportNo 27

Project HalfMoonOL Location HalfMoon,RoseHall

FieldOfficer ArkaliaWhite,KarlTodd

Engineer CarlJohnson/LenmourBell

PM PaulBurke

SummarytheworkprogressandIssues

GreatHouse
Pilecapsinthesecondthirdofthebuildingwerepoured.
Reinforementforthepilecapsinfinalthirdofthebuildingcontinuetobeinstalled
Slabreinforcementinthesecondthirdofthebuildingarebeinginstalled.
TheinstallationofU/Gsewerlines,electricalconduits,pilecapsandcolumnscontinuesintheGreatHouse
Villas
Villa4slabwaspouredandcontinuestobecured.Wallbarsarebeingerrectedforvilla4.Fourconcretecylindersamplesweretakentothelabtobetested.
Curingofvilla3slabendedthisweek.Splicelengthsforhorizontalwallbarsinvilla3werecorrected.
Wallbarsforvillas13havebeenerected.
Cottages
Installationoftheundergroundplumbingforcotteges4,3,2werecompletedthisweek.
MainResturauntBuilding
Excavationandinstallingofundergroundplumbingareongoing.
Fillingandcompactionforoutdoordininigpavillionareunderway.
Spa
TherenovationworksbytheSpacontinues.
Excavationforstarcasecompleted.
Workonplantersareongoing.
RetainingwallWCottages
Retainingwallbythecottageswaspoured.
RetainingWallEntertainmentPavillion
Reinforcementofretainingwallwasplacedandthenbaseofwallpoured.
SingleCellCulvert
Pipesweredivertedaroundtheareatoallowforexcavation.
Areawaspumpedtoremovethewaterthatseepedthroughtthedam
Fillingoftheareaiscurrentlytakingplace.
Compaction
CompactionandtestinginSectionAandCsouthofGreatHouseareongoing.Fillingforthe12thand8threspectivelyarealsoongoing.
CompactionandtestinginSectionB7greenareaareongoing.
Compactionandtestingofmainresturauntoutdoordinningpavillionongoing.

Attheendofweek26approximately62%oftheestimateledfillmaterialhasbeenplaced.

Intheweek28,fillworkandcompactiontestsareexpectedtocontinuesouthoftheGreatHouse,greenareasandalsoontheroadways.Theinstallationoftheundergroundplumbingformainrestaurantwillcontinue.Placementofreinforcement
willcontinueintheGreatHouseandisexpectedtocommenceforthecottages.ErectionofwallbarswillcontinueontheremainingGreatHousefoundation.Aconcretepourforthesecondthirdofthegreathousecanbeexpectedinthecoming
week.
ErectionofthewallbarsfortheEPretainingwallareexpectedtocontinueintoweek28.
Formworkforwallsareonsiteandsoerectionofformworkinthevillascanbeexpectedtocommence.

Meetings,DrawingsandOtherInformation

Comments

MeetingsandDiscussions N/A

Drawings/Sketches CD_OleanderCivilSetAddedendum2

ExtractSitePlanC3.01
Attachements
CompactionTestResults

Photos Sitephotographsattached

Ownerorrepresentativecausesofdelays N/A

Contractororrepresentativecausesof
N/A
delays

Fieldchange N/A

Dailysafetymeeting N/A

AccidentReport N/A

Works

Date Comments
CompactionoffillcontinuessouthofGreatHouse.
Installationofpilecaps,columncagesandtiebeamscontinueintheGreatHouse.

MSLcontinueswithinstallationofundergroundpipesforgrinderpumpsbythecottages.
Totalofsixgrinderpumpshavebeeninstalledtodate.

Theinstallationofconduitscontinueinthelaundrypod.
Monday(30102017)
TheinstallationofformworkcontinuefortheVilla4foundation.

Villa3wallbarscontinuetobeerected.

Excavationforthesinglecellculvertpauses.
Sewagelinebrokenduringexcavationforthesinglecellculvert.
Thediversionofpipescontinuesouthofthesinglecellculvertconstruction.
CompactingoffillcontinuessouthofGH.
Installationofpilecaps,columncagesandtiebeamscontinueintheGreatHouse.

MSLcontinueswiththeinstallationofU/GpipesforgrinderpumpsbytheCottages.

FoundationforVilla4hasbeenpoured.
ConcreteCylindersamplingwasdoneforVilla4foundation.

Atotalofsixgrinderpumpshavenowbeeninstalled.

Tuesday(31102017)
ErectionofVilla3wallbarscontinuetobeerected.

WorkonADSmanhole2hasbegan.

Sharpeningtheedgesoftheplantersatthespa.

Excavationforthesinglecellculvertcontinues.
Damagesewagelinebythesinglecellculverthasbeenrepaired

Thediversionofpipescontinuesouthofthesinglecellbridgeconstruction.

CompactingoffillcontinuessouthoftheGreatHousecontinues.
Installationofpilecaps,columncagesandtiebeamscontinueintheGreatHouse.
PilecapPC8alonggridlineEGHwaspoured

ErectionofwallbarsforVilla4hasbegun.

Atotalof7grinderpumpshavenowbeeninstalled.

CorrectiontothesplicelengthsonVilla3aretakingplace.

Wednesday(01112017)
WorkonADSmanhole2continues.

Workonplantersandthespacontinues.

SettingoutforMainResturantbuldingisongoing.
Excavationforplumbinginmainresturauntbuildinghasbegun.
CompactionfortheoutdoorDinningPavilioncontinues.

Fillingforthesinglecellculvertbegan.
Thediversionofpipescontinuesouthofthesinglecellbridgeconstruction.

CompactingoffillcontinuessouthofGHcontinues.
Installationofpilecaps,columncagesandtiebeamscontinueintheGreatHouse.

ErectionofwallbarsforVilla4continues.
CorrectiontothesplicelengthsonVilla3havebeencompleted.

CompactionfortheMainResturantoutdoordinningpavilioncontinues
CompactionTestswereconductedonasectionoftheMainresturantoutdoordinningpavillion.
SettingoutforMainResturantbuldingisongoing.
Thursday(02112017)
Excavationforplumbinginmainresturauntbuildingcontinues.

WorkonADSmanhole2continues.

PlacingofreinforcmentforEPretainingwallhasbegun.

Fillingforthesinglecellculvertisongoing.

Excavationatspaforstaircaseisongoing.

CompactingoffillcontinuessouthofGreatHousecontinues.
Installationofpilecaps,columncagesandtiebeamscontinueintheGreatHouse.
Pilecapsinthesecondthirdofthegreathousewerepoured.

ErectionofwallbarsforVilla4continues.

CompactionfortheMainResturantoutdoordinningpavilioncontinues.
Excavationforplumbinginmainresturauntbuildingcontinues.
InstallationofplumblingforMainResturantBuildingcontinues.
Friday(03112017)
Fillingformainresturauntoutdoordinninghallhasstarted.

FillingandcompactioninSectionBsouthofgreathousebegan.
FIllingandCompactionofSectionAandCisongoing.

PlacingofreinforcmentforEPretainingwallcontinues.

Fillingforthesinglecellculvertisongoing.
Trenchforsinglecellculvertisbeingpumpedout.

CompactingoffillcontinuessouthofGreatHousecontinues.
Installationofpilecaps,columncagesandtiebeamscontinueintheGreatHouse.
Slabreinforcementforthesecondthirdofthegreathouseisbeingplaced.

ErectionofwallbarsforVilla4continues.Slabalsocontinuestobecured.

FillingandcompactioninSectionBsouthofgreathousecontinues.
FillingandcompactioninSectionAandCsouthofgreathousecontinues.

Saturday(04112017)
Baseofretainingwallbyentertainmentpavillionwaspoured.

Fillingforthesinglecellculvertisongoing.
Trenchforsinglecellculvertisbeingpumpedout.

Excavationforplumbinginmainresturauntbuildingcontinues.
InstallationofplumblingforMainResturantBuildingcontinues.
Fillingformainresturauntoutdoordinninghallisongoing.
CompactionfortheMainResturantoutdoordinningpavilioncontinues.

GeneralSitemanagement

Item Comments

Health&Safety Workersonsitearegearedinclosedtoeshoes,safetyvestsandhardhat.

1..Dckneedstoensurethattrashcansareplacedandutilizedbythenorthernendofthesitetoreducetheaccumilationofwastenearthecoast.
EnvironmentalIssues
2.dckneedstoensurethatthetruckwashthatisbuilthasafiltersystemthatwillnotallowforoiltogetintothesea/canal.
ElectriciansneedstoensurethatconduitsbeinginstalledareinstalledaspernotesonS0.01.concretecoverforrebararebeingcompromisedduetoimproperinstallation.

Boxedoutbaseplatesarenotpreventingconcretefromcoveringthesteelandthereforewillstillneedtobedrilledfortheinstallationoftheactualbaseplates.

Manholesarenotbeingconstructedasperapproveddrawings.InconcsistentstructuraldetailsthatdifferfromthosesubmittedinSI068C.Dumpingdryconcretematerialintofloodedtrenchesraises
ConstructionIssues
concernsaboutthestrengthoftheconcretebeingused.

Termitetreatmentsarebeingcarriedoutwhenthegroundiswet

Concretepoursarebengdonewithoutnotice.Thismakesitimpossibletoperformqualitycontrolchecks.

ListofRecommendations/Instructions

1 dckhasbeeninstructedtodeliverdumpticketstotheIBEC'sofficeonaweeklybasis.

2 dckshouldhaveatruckwashstand/serviceareaforheavyequipmentandtrucksgoinginandoutofthesite.

3 dckhasbeenaskedtopaykeenattentiontotheGeneralNotesonStructuraldrawingsasitrelatestoconduitinstallation.

4 dckhasbeeninstructedtoensurethatthegroundisresonablydrybeforetermitetreatment
HM/OSiteIssues

Construction/EnvironmentalIssues DateAddressed DateResolved

Termitetreatmentisbeingappliedoverwetandheavilysaturatedfill
01/11/2017(Email)
materialatthebaseoftheconcreteslabs,henceresultinginalesseffective
solutionforthefoundation.

Theexistingstormdrainsshouldbemaintained,andwherethefillworksdo
19/09/2017(Email)
notallowthis,DCKshouldprovideprovisionsstormwaterflowstoavoid
floodingareassurroundthesite(theresort).

Manholesarenotbeingconstructedasperapproveddrawings. 01/11/2017(Email)
InconcsistentstructuraldetailsthatdifferfromthosesubmittedinSI068C.

Wehavenotreceiveddumpmaterialtickets.Thebuilding&environmental 19/09/2017(Email)
permitareissuedtoHalfMoon(notthecontractor)andtherefore

Thematerialisnotbeingplacedseparately,andthereforewearenotclear
19/09/2017(Email)
oncompactiontestingparameterstobeused.Shouldweusethehigher
value,compactiontestarenotlikelytoachievepassingresults.

Surveyinformationisnotbeingdeliveredinatimelymanner. 19/09/2017(Email)
StillawaitinginstalledasbuiltsforSDpipes.

dckneedstoensurethatthetruckwashisbuiltandthatithasafiltersystem 27/09/2017SiteMeeting
thatwillnotallowforoiltogetintothesea/canal.

dckhasnotbeenprovidingconcretepourdatesandsocylindersamplesare 04/11/2017(Email)
notbeingtakenforGreatHouseslabpoursamongotherslabs.

Pickershavebeenassignedtoremove
Fillmaterialgradationdoesnotnotmatchthespec.Wehaveobserved
19/09/2017(Email) bouldersbeforecompactionoffill
instancewherematerialbeinginstalledisoutsideoftheallowable
(WeekofOct9,2017)
parameter.

Fillmaterialgradationisaconcernattheupperlayers.Pipesarebeing 11/10/2017SiteMeeting
19/09/2017(Email)
installedinfillwithboulders/largerthan2.Thereisconcernofpotential (dcktodoonsitechecks)
damageofserviceswherethereisinadequatebeddingmaterial.

Spoketodckrepresentative dckhashiredaconcrete/steel
Electriciansneedstoensurethatconduitsbeinginstalledareinstalledasper 04/10/2017 supervisortoassistwithchecksbefore
notesonS0.01concretecoverforrebarsarebeingcompromiseddueto &25/10/2017 pours
improperinstallation&nospacingsareleftbetweenconduits.
CompactionTests

Date Building/Roadway Section/Grid Elevation Layer Compaction MC Depth


(m) (inch)
21/10/2017 SouthofGreatHouse SectionA 7th 96.6% 13.3% 6

95.3% 12.9% 6

96.0% 13.4% 6

91.7% 12.6% 6

95.3% 11.6% 6

96.1% 12.7% 6

95.2% 10.8% 6

23/10/2017 SouthofGreatHouse SectionC 4th 94.5% 10.9% 6

2.232 95.9% 11.5% 6

2.428 95.2% 10.3% 6

2.518 91.8% 13.1% 6

2.447 93.4% 12.3% 6

95.1% 12.3% 6

91.8% 13.5% 6

SectionA 8th 96.8% 12.0% 6

3.305 97.3% 12.2% 6

3.179 94.1% 12.1% 6

3.174 92.9% 12.3% 6

3.031 96.8% 9.8% 6

2.875 96.0% 11.7% 6

2.682 98.3% 11.2% 6

GreenArea WestPoolBar 2nd 95.6% 9.9% 6

95.3% 14.3%

93.8% 13.1%

95.4% 14.7%

SouthofGreatHouse SectionC RETEST 4th 98.7% 10.0% 6

97.4% 10.6%

96.3% 12.4%

97.2% 11.3%
SectionA RETEST 8th 112.2% 8.9% 6

92.6% 11.2%

100.2% 9.4%

24/10/2017 RetainingWall EntertainmentPav. 1st 92.2% 11.6% 6

93.3% 10.0%

94.0% 12.4%

SouthofGreatHouse SectionA 9th 101.3% 9.8% 6

101.1% 10.6% 6

99.4% 11.2% 6

94.6% 13.3% 6

96.2% 10.7% 6

93.8% 11.6% 6

94.5% 11.4% 6

25/10/2017 SouthofGreatHouse SectionA RETEST 9th 96.3% 11.5% 6

96.5% 11.1%

97.5% 9.6%

SectionC 5th 99.5% 9.7% 6

95.0% 12.0%

95.5% 10.9%

95.8% 12.6%

RetainingWall EntertainmentPav. 2nd 96.1% 10.4% 6

95.0% 11.4%

96.2% 12.7%

SouthofGreatHouse SectionA 10th 94.7% 13.0% 6

94.3% 13.1% 6

97.5% 11.6% 6

93.1% 13.3% 6

93.3% 14.3% 6

92.2% 15.0% 6
96.1% 12.3% 6

SouthofGreatHouse SectionC 6th 98.5% 12.3% 6

100.2% 11.5% 6

93.5% 14.6% 6

95.3% 14.0% 6

97.8% 13.4% 6

RETEST 95.4% 13.4% 6

2/11/2017 MainRestaurant SlabC 2nd 96.4% 14.3% 6

99.7% 12.4%

3/11/2017 GreenArea B7 1st 97.3% 13.6% 12

95.2% 13.0% 12

98.4% 12.8% 12

GreatHouse SectionC 7th 103.1% 10.1% 6

98.4% 12.7% 6

98.0% 14.0% 6

96.9% 14.0% 6

96.4% 13.4%

SectionA 11th 97.0% 12.0% 6

98.0% 12.9% 6

95.2% 14.5% 6

100.1% 12.5% 6

95.7% 14.2% 6
A
B
C

NOT FOR CONSTRUCTION


Site Pictures
4.11.2017

Figure 1: Villa 4 slab curing.

Figure 2: Compaction of fill in Section B south of Great House.


Figure 3: Section C south of Great House being filled

Figure 4: Base of retaining wall near entertainment pavilion poured.


Figure 5: Slab Reinforcement being placed in second third great house.
Aerial Photos
Figure 8: Compaction of Section A and C south of the Great House.