You are on page 1of 8

OTC 10894

OTC 10894

Deep Water Development Drilling from a Spar


C. P. Leach, Well Control & Systems Design Inc. and P. N. Stanton, Deep Oil Technology

Copyright 1999, Offshore Technology Conference

This paper was prepared for presentation at the 1999 Offshore Technology Conference held in Introduction
Houston, Texas, 36 May 1999.
Up until now, drilling operations in the ultra deep waters
This paper was selected for presentation by the OTC Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
of the Gulf of Mexico have generally been carried out
presented, have not been reviewed by the Offshore Technology Conference and are subject to using a conventional drilling system consisting of a
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Offshore Technology Conference or its officers. Electronic reproduction, seabed (subsea) BOP and a non-pressured marine
distribution, or storage of any part of this paper for commercial purposes without the written
consent of the Offshore Technology Conference is prohibited. Permission to reproduce in print
drilling riser. If a kick occurs, the seabed BOP is closed.
is restricted to an abstract of not more than 300 words; illustrations may not be copied. The The kill circulation path is through the drillstring to the bit,
abstract must contain conspicuous acknowledgment of where and by whom the paper was
presented. up the well annulus to the seabed and then through the
choke or kill line (or both) to the choke manifold located
on or close to the drilling rotary table.
Abstract
This paper describes the design of a well system for
(1) This type of system has its merits but also its drawbacks
development drilling from a Spar . In particular, the
which include:
paper gives results of realistic well control modeling
which has been used to confirm the design
1. Significant friction pressures which are transmitted
specifications for a system consisting of a surface BOP,
back through the well when circulating through the
pressured riser and partial seabed BOP (split BOP).
long choke and kill lines
Details of the pressures that would be expected from
2. Complex seabed equipment
typical Gulf of Mexico (GOM) deep water well kicks will
3. Potential high gas rates at the surface resultant from
be given. The results of the work show:
small undetected swabbed kicks (subsequently
circulated through the riser) when synthetic oil base
Most kicks that will be encountered can be dealt (2)
mud (SOBM) is in use
with using a pressured riser and a surface BOP if
this riser is rated to 3000 psi for surface holes and
The work described in this paper used a realistic well
6500 psi for deeper hole sections (3)
control simulator (RF Kick) and an underbalanced
A seabed choke and seabed BOP may be used drilling simulator (RF Dynaflodril)
(4)
to examine an
under certain circumstances to limit riser pressures alternative well system that could be used from a Spar
and that would:
The well control system as conceived also allows for:
eliminate (for the most part) the drawbacks of the
conventional system
More effective deep water drilling when compared
provide all required well control capabilities
to a conventional subsea drilling system casing
allow for cost effective drilling.
strings can be pushed further
A dual barrier such that failure of the riser during
Several key requirements had to be met. These were:
drilling does not result in a blow-out
1. Ability to deal with the pressures and other
Many areas for potential cost savings when conditions that are likely to occur
compared with a conventional subsea drilling 2. Ability to be able to deal with a catastrophic event
system (for example, evacuation of the wellbore following a
well flow that has gotten out of control)
The system is designed to fit the capabilities of a Spar. 3. Provision of a back up such that a single point failure
The paper also shows how the design of the well system does not cause the loss of the well
leads to some cost savings for the Spar system as a
whole. As is often the case when looking at realistic problems,
2 C. P. LEACH & P. N. STANTON OTC 10894

the complexities of the underlying systems must be during the kill circulation this assumption was made
examined and understood. For this work, both water simply because loss of circulation during well control
base mud (WBM) and synthetic oil base mud (SOBM) was not the focus of this work.
were considered. Methane gas was considered to be
the chief constituent of the influx. The solubility of this The riser base differential pressure is defined as the
gas within the SOBM had to be considered. More inside pressure at the base of the riser minus the sea
detailed work is required once a specific mud system water hydrostatic pressure (which acts on the outside of
has been chosen. It should also be understood that in the riser). In turn, the inside pressure at the base of the
many cases, well control will be much easier if the influx riser consists of the choke pressure plus the hydrostatic
is oil with some associated gas. pressure of the column in the riser that consists of a
mixture of gas and drilling mud.
Description of Well System
Figure 1 shows the overall well system layout and Note that for all of the runs the influx has consisted of
operation for this work. As well as the surface BOP, two gas (methane). This produces a worst case. If the
rams (not shown in detail) would be positioned at the influx consisted of a live oil (i.e with associated gas),
seabed. One would be equipped with a pipe/flex ram then the pressures and magnitudes of the effects seen
and one with a shear ram. An extra set of pipe/flex rams would be greatly reduced. It is beyond the scope of this
may be added for redundancy. work to discuss this topic, but it is fully feasible to take
such an effect into consideration when designing a well
A 19 ID riser was selected as the base riser case. An system for development drilling into a known reservoir.
alternative 13 ID riser was used for some of the runs at
deeper reservoir depths and with the smaller hole sizes. Table 1 shows the parameters used for each kick
This may be in the form of an inner (concentric) riser modeled.
(5)
such as that described by Herrmann et al.
Alternatively, the smaller ID riser may be installed as a 24 Hole Section @ 12000 ft (19 Riser). Figure 3
(1)
separate non-concentric riser. shows the maximum choke pressure and the maximum
riser base differential pressure that would be generated
Results Use of Surface BOP and Choke as each kick was circulated out for a range of kick sizes.
In this case only the surface BOP and choke were used
during shut in and kill operations. Each kick was For this section a 500 barrel kick generated a maximum
therefore circulated through the riser. A typical GOM choke pressure of 1320 psi and a maximum riser base
(3)
well was modeled using the RF Rogalands Kick differential pressure of 1460 psi.
simulator. Modeling runs were made at each casing
shoe setting depth (Total Depth of each hole section). 16 Hole Section @ 13500 ft (19 Riser). Figure 4
The total depth (TD) of the well was 25,000 ft and the shows the maximum choke pressure and the maximum
water depth was 8000 ft. Figure 2 provides a summary riser base differential pressure that would be generated
of the well pressure information. All the modeling runs as each kick was circulated out.
used the Drillers method, which relies on maintaining
bottom hole pressure constant just above the formation For this section a 530 barrel kick in OBM generated a
pressure and requires two circulations. maximum choke pressure of 1700 psi and a maximum
riser base differential pressure of 2360 psi. A 530 barrel
The results from each run give the maximum (surface) kick in WBM generated a maximum choke pressure of
choke pressure and the maximum differential pressure 1660 psi and a maximum riser base differential pressure
at the riser base that would be generated as each kick of 2500 psi.
was circulated out. These pressures at the top and
bottom ends of the riser give the extremes of internal 14.75 Hole Section @ 17000 ft (19 & 13 Riser)
pressure that the riser must withstand during a well Low and High Pressure Kicks. Figure 5 shows the
control operation. The riser can therefore be specified maximum choke pressure and the maximum riser base
based on these pressures. differential pressure that would be generated as each
kick (low pressure, 19 riser) was circulated out. For
In each case, the well was shut in using the surface these runs a 430 barrel kick generated a maximum
BOP. The circulation path was down the drillpipe, up the choke pressure of 2230 psi and a maximum riser base
well annulus to the seabed, up the riser annulus to the differential pressure of 3500 psi.
surface choke and then through the surface choke and
the surface processing equipment. The casing shoe and Figure 6 shows the maximum choke pressure and the
other exposed formations were assumed to be strong maximum riser base differential pressure that would be
enough to withstand wellbore pressure acting on them generated as each kick (high pressure, 19 riser) was
OTC 10894 DEEP WATER DEVELOPMENT DRILLING FROM A SPAR 3

circulated out. For these runs a 440 barrel kick conventional system with a subsea BOP and a 6
generated a maximum choke pressure of 4400 psi and a choke line (WBM)
maximum riser base differential pressure of 5600 psi.
A total of six runs were therefore made.
Figure 7 shows the maximum choke pressure and the
maximum riser base differential pressure that would be The top half of Figure 9 shows the maximum surface
generated as each kick (low pressure, 13 riser) was choke pressures for each of these (6) runs. In addition
circulated out. For these runs a 418 barrel kick the maximum pressure across the seabed choke is
generated a maximum choke pressure of 2230 psi and a shown for the two runs made with the seabed choke.
maximum riser base differential pressure of 3450 psi. This maximum pressure across the seabed choke is
added to the appropriate maximum surface choke
8.5 Hole Section @ 25000 ft (19/13 Riser). Figure pressure. The result is a bar graph that suggests that a
8 shows the maximum choke pressure and the certain total maximum choke pressure is required to kill
maximum riser base differential pressure that would be the well. This can either be applied solely at surface or
generated as each kick was circulated out. as a combination of surface and seabed choke pressure.

For this section a 209 barrel kick in the 19 riser The lower half of Figure 9 shows the maximum pressure
generated a maximum choke pressure of 3750 psi and a that would be exerted at the base of the riser and at the
maximum riser base differential pressure of 6350 psi. A surface choke. The bottom of the solid bar corresponds
230 barrel kick in the 13 riser generated a maximum to the maximum choke pressure and the top of the bar to
choke pressure of 3900 psi and a maximum riser base the maximum differential pressure at the base of the
differential pressure of 6600 psi. riser. The spread (or height) of the bar shows the range
of (maximum) differential pressures that would be
In each case, the maximum choke and riser base applied over the length of the riser.
differential pressures occurred at shut in and with the
influx below the seabed (within the 8 hole section). For the OBM case the absolute riser base pressure
(pressure inside of the riser and downstream of the
Results Use of a Seabed Choke seabed choke) was held at 6150 psi for the duration of
A system which includes a seabed choke could be used the kill. This resulted in a small seabed choke
to deal with very large kicks which are beyond the differential pressure of about 200 psi once all of the
capability of the equipment above the seabed (riser influx had been circulated above the seabed. This also
and/or surface BOP). The well control system is more resulted in a maximum riser base differential pressure of
complex for this situation. In essence there are two 2530 psi. The maximum surface choke pressure was
systems with two chokes that are interlinked. For 1800 psi. These pressures should be compared with a
modeling purposes, the system was split into two. The maximum riser base differential pressure of 6600 psi and
lower system consisted of the well from the seabed maximum choke pressure of 3900 psi for the same kick
downwards and the upper system (essentially the riser) when only a surface choke was used (see Figure 8).
from the seabed upwards.
The WBM case was more difficult to model. The
(3)
The lower system was modeled using the RF Kick required surface choke pressure was very low once the
simulator. The gas/mud mixture passing through the bulk of the gas had passed through and this made the
choke was then used as the input to the model for the simulation somewhat unstable. A constant surface
(4)
upper system. In this case the RF Dynaflodril choke pressure (1000 psi) was therefore selected as a
(underbalance drilling simulator) was used. potential operating point and the simulation of the riser
kill was then run successfully. Given these conditions,
A large kick from the 8 section (230 barrels with the the maximum riser base differential pressure was 3100
13 riser - see Table 1) was selected for this part of the psi. No equivalent surface only case was run for WBM,
work. Both OBM and WBM were simulated. The results but the comparable maximum riser base differential
of these runs using the split BOP were compared with: pressure would again be about 6600 psi.
The 230 barrel kick (surface BOP only) in OBM
shown in Figure 8 Figure 10 shows the maximum gas rates that would be
The same kick (surface BOP only) but with WBM seen at surface for these kills. Note the very high rate
The same 230 barrel kick circulated through a (28.8 mmscf/d) that would result from the combination of
conventional system with a subsea BOP and a 6 WBM and a low constant surface choke pressure of
choke line (OBM) 1000 psi. (further work is required to confirm this high gas rate)
The same 230 barrel kick circulated through a
Using a higher (constant) surface choke pressure (2200
4 C. P. LEACH & P. N. STANTON OTC 10894

psi) was also simulated. This resulted in a maximum table where the gas will come out of solution and may
(2)
gas rate of about 11 mmscf/d. However, this higher result in a significant gas flow . This event is routinely
choke pressure cannot be applied for the duration of the dealt with on land and jack-up rigs by circulating
kill as an overpressure would then be applied to the bottoms-up through the choke. The well system
complete wellbore during the latter stages of the kill. In described here allows for the same solution. In doing
this case, a viable approach may be to apply the so, not only is safety increased, but also there is the
constant (2200 psi) surface choke pressure at the start potential for drilling further below a casing shoe, possibly
of the kill and revert to a second constant choke even eliminating a casing string.
pressure once the bulk of the gas has passed through
the surface choke. Dealing with a Blow Out in Progress
Although this capabilty is unlikely to ever be needed, any
The different gas rates shown result from the different well system should be designed such that a blowing out
combinations of the gas volumes and transient mud and well can be shut in. This implies that the well equipment
gas voids upstream of the surface choke. (BOP, riser etc) should be capable of shutting in on a
pressure consisting of the fracture pressure of the
For both WBM and SOBM, use of the seabed choke formation at the casing shoe minus a column of gas
dramatically reduced the surface choke pressure and the back to the position of the equipment. For the case of
maximum riser base differential pressure. the seabed rams and choke, this implies that the seabed
BOP and the casing strings below the wellhead should
Significant further work is required to properly optimize be designed to this potentially high pressure. For the
the operation of such a system. This work shows that case of a surface BOP without any seabed BOP, the
such a 2-choke system is possible. riser must also be rated to this high pressure. For the
well given as an example in this paper, this implies a
Alternative Well Control Approaches maximum surface pressure of about 12,700 psi. (21,000 ft
Use of either the surface choke or the combined seabed x 15.5 ppg x 0.052 21,000 ft x 0.2 psi/ft).
and surface choke suggests a conventional approach
to well control and circulation of a kick. Bullheading This high pressure requirement would result in a very
provides an alternative to using the seabed choke for the thick riser wall and very heavy riser.
case where the pressures are too high to handle using a
surface choke/BOP. Bullheading has been used in Riser Specification Implied by Modeling Results
some deep water well control operations particularly After reviewing the results given in Figures 2 8, it is
wells where lost circulation has occurred. The downside concluded that most kicks that will be encountered can
of bullheading has been: be dealt with using a pressured riser and a surface
operations that have taken a week or more and system if the riser is rated to:
a high potential for loss of the BHA and open hole.
3000 psi (19 ID - for surface holes)
However, bullheading may be a viable back-up for this 6500 psi (13 ID - for deeper hole sections)
well system. The operation would run as follows after a
major kick had occurred/been detected: Note that the results presented in Figure 6 are well
Shut well in at seabed above the 3000 psi rating for a 19 ID riser. However,
Assess surface pressures and other pressures on the high pressure kicks modeled for these cases had a
riser system as being too great to handle using the shut in pressure of 2610 psi, which equates to a kick
surface choke/BOP intensity of 3 ppg. Given current technology, this high
Bullhead well through kill line kick intensity is unlikely on exploration wells and
unimaginable on development wells where formation
Bullheading may work better for smaller hole sizes and types and pressures are relatively well known.
when OBM/SOBM is in use. It should be noted that
further experimental work and field measurements are Well Control Procedures (Using Both Seabed and
required to fully understand the mechanisms and Surface Chokes)
limitations of this procedure such that it can be properly Well control procedures for the well system described
applied in all cases. here which includes the lower pressure rated riser and
both surface and seabed chokes will be very similar to
Dealing with Small (Swabbed) Kicks those established over many years for conventional
One of the problems of the conventional system when systems. A summary of the required steps is:
used with SOBM is that a small (undetected) swabbed Initial shut in using surface BOP unless a blow out
kick can be circulated up the riser to just below the rotary has occurred when shut in would be made using the
seabed ram
OTC 10894 DEEP WATER DEVELOPMENT DRILLING FROM A SPAR 5

Shut in on seabed ram following assessment that 7. Provision of the two ram seabed BOP provides for
potential circulating pressures will exceed maximum back up in the event of an out-of-control well or a
desirable riser pressure failure of the riser.
Adjust surface riser pressure to obtain the inside 8. Bullheading may be a viable option for regaining
riser base pressure selected control after taking a large kick that is beyond the
Bring pump up to speed capabilities of the riser and/or surface BOP
Maintain seabed choke pressure constant equipment. Note that further work is required to
and establish circulating pump pressure better understand bullheading operations such that a
Adjust surface choke to maintain required high success rate will be attained.
inside riser base pressure 9. The combination of a large kick, WBM, low surface
Maintain established circulating pump pressure pressure and large ID riser, (which is the case for
using the seabed choke one example in this paper) leads to a very high
Maintain required inside riser base pressure using surface gas rate. This gas rate will require surface
the surface choke separation equipment that is not generally currently
A second circulation would be made using either a pump available. It should be noted that this higher gas
pressure schedule or a constant seabed choke pressure rate may be lessened by selecting a higher surface
while kill weight mud was being pumped to the bit. choke pressure.

Constraints for Deep Water Drilling Imposed by GOM Acknowledgements


Conditions
A dual barrier is strongly suggested for deep water GOM The authors would like to express thanks to the
drilling. This is required because GOM reservoirs are mangements of their companies who gave permission
typically abnormally pressured and drilling is carried out for this work to be published and for the work of their
without a riser margin. If the riser fails and the column of peers in assisting with the work and with reviewing the
mud in the riser is lost (the pressure at the base of the content of the paper. Special thanks is due to Dave
riser becomes that of a column of seawater instead of a Schwartz of Well Control & Systems Design.
column of mud), then a blow out would occur from any
exposed reservoir section. Inclusion of the limited References
seabed BOP (1 pipe ram plus 1 shear ram) provides for
a back-up barrier for such an event and also provides (1) Stanton, P.N., Glanville, R.S., LeJune, J.L., and
the primary barrier in the event of a large well control Chao, J.C.-: Deep Water Drill Spar, The Deep
incident which is beyond the capability of the riser Offshore Technology Conference, New Orleans,
pressure rating and/or surface BOP and equipment. LA, 17-19 November, 1998
(2) Leach, C.P. and Roche, J.R.-: Avoiding Explosive
Other Spar Riser Design Issues Unloading of Gas in a Deepwater Riser, Offshore
It is beyond the scope of this paper to address other Magazine, January 1, 1998
Spar riser design issues. These are addressed (3) Hovland, F. and Rommetveit, R.-: Analysis of
elsewhere.
(6) Gas-Rise Velocities from Full-Scale Kick
Experiments, SPE Paper 24580 presented at the
th
Conclusions 67 Annual Tech. Conf. And Exhibition of the
1. Use of a pressured riser and surface BOP and SPE, Washington, DC, October 4-7, 1992
choke is viable and it should be possible to use this (4) Wang, Z., Vefring, E.H., Rommetveit, R.,
system for most GOM kicks Bieseman, T., Maglione, R., Lage, A.C.V.M and
2. A 13 riser would be better for smaller hole sizes Nakagawa, E.-: Underbalanced drilling model
than a 19 riser. The smaller riser may be run as a simulates dynamic well bore conditions, Oil &
liner or as a separate riser. Gas Journal., July 7, 1997
3. Provision of two seabed rams and a seabed choke (5) Herrmann, R.P., Shaughnessy, J.M. and Beynet,
allows the riser pressure rating to be significantly P.A.-: Concentric Drilling Risers for Ultra
reduced. Further work is required such that the Deepwater, SPE/IADC 39297, SPE/IADC Drilling
exact requirement and operation can be specified. Conference, Dallas, TX, 1998
4. The suggested rated working pressure for the 19 ID (6) Finn, L.-: Reliable Riser Systems for Spars,
th
riser is 3000 psi and for a 13 ID riser is 6500 psi. Proceedings of the 17 International Conference
5. Oil kicks will result in significantly less extreme on Offshore mechanics and Artic Engineering,
conditions than those shown in this work. ASME, Lisbon, Portugal, July 1998
6. Use of SOBM will typically simplify the kick
circulation operation.
6 C. P. LEACH & P. N. STANTON OTC 10894

Figure 1 : Overall Well System Layout Use


of Surface or Seabed and Surface
Chokes

Adjustable Adjustable
Choke Choke
Surface Surface
BOP BOP
Mud/Gas Mud/Gas
Separator Separator

Water
Depth Marine Riser
Marine Riser
13 or 19 ID
13 or 19 ID

Seabed BOP Seabed BOP


& Choke & Choke
Seabed

Potential
Producing Potential
Producing

Handling all but Handling Largest


Largest Kick - Kick - Seabed PLUS
Surface BOP/Choke Surface BOP/Choke
Only
OTC 10894 DEEP WATER DEVELOPMENT DRILLING FROM A SPAR 7

Figure 3: 24 Hole Section @ 12000 ft (19 Riser)

Figure 2: Well Pressure Summary


1600
0
1400 Riser Base Diff Press

Pressure (psi)
1200

1000
Choke Press
5000
800

600

Seabed - 8000 ft 400


Kick Size (bbl)
0 100 200 300 400 500
20 Casing
10000
Frac Grad 24 Hole

16 Liner
Mud Wt 16 Hole
13 3/8 Casing Figure 4: 16 Hole Section @ 13500 ft (19 Riser)
15000
14.75
Hole
11 3/4 Liner
2900
Depth (ft) 12 1/4 Hole Riser Base Diff Press
2400
20000

9 5/8 Casing 1900 Pressure (psi)


8 1/2 Hole 1400
Choke Press
Pressure (ppg) 900
25000
Kick Size (bbl)
8 10 12 14 16 18 400
0 100 200 300 400 500 600

Table 1. Inputs to Modeling


Hole TD/Csg Riser ID MW SIDPP Ref
Figure 5: 14.75 LP Hole Section @ 17000 ft (19 Riser)
Size Depth (in) (ppg) & (psi) Figure
(in) (ft) Type
24 12000 19 9.8 370 3 3600

10000 WBM 3100 Riser Base Diff Press


16 13500 19 10.9 400 4
12000 OBM 2600
Pressure (psi)

14.75 17000 19 11.5 400 5 2100


13500 OBM Choke Press
1600
14.75 17000 19 11.5 2610 6
13500 OBM 1100
14.75 17000 13 11.5 400 7 Kick Size (bbl)
600
13500 OBM 0 100 200 300 400 500
8.5 25000 13 15 600 8
21000 OBM 9
8 C. P. LEACH & P. N. STANTON OTC 10894

Figure 6: 14.75 HP Hole Section @ 17000 ft (19 Riser) Figure 9: Components of Total Choke Pressure (Top)
Riser Operating Pressure (Bottom)
(230 barrel Kick)

5300 Riser Base Diff Press Seabed Choke


6000 Surface Choke
4800

Pressure Across Choke (psi)


Pressure (psi)

4300 5000

3800 4000
Choke Press
3300 3000

2800
Kick Size (bbl)
2000
0 100 200 300 400 500

1000

0
Seabed + Surface Seabed + Surface Conventional Conventional
Surface only Surface only Subsea Subsea
Figure 7: 14.75 LP Hole Section @ 17000 ft (13 Riser) 8000
(OBM) (OBM) (WBM) (WBM) (OBM) (WBM)

Riser Operating Pressure (psi)


7000
6000
3600 5000

3100 4000
Riser Base Diff Press
3000 Choke Line
2600
2000
Pressure (psi)

2100
Choke Press 1000
1600 0

1100
Kick Size (bbl) Note: The higher operating pressure is always at the base of the riser.
600 The lower operating pressure is at the top of the riser (surface choke).
0 100 200 300 400 500

Figure 10 : Maximum Surface Gas Rate (mmscf/d)

Figure 8: 8.5 Hole Section @ 25000 ft (13 Riser) 35

30
Max Gas Rate (mmscf/d)

25
7000 20
6000 Riser Base Diff Press 15
Pressure (psi)

5000 10

4000 5

3000
0
Seabed + Surface Seabed + Surface Conventional Conventional
Choke Press Surface only Surface only Subsea Subsea
2000 (OBM) (OBM) (WBM) (WBM) (OBM) (WBM)
Kick Size (bbl)
1000
0 50 100 150 200 250

You might also like