Contract T216

Construction of Steven Station and Tunnels


for Thomson East coast Line

Presentation to BCA for TBM-4


(24/08/2017)

1
Currently TBM 3 has mined from R109 to R185

So far the TBM performance is very good and


successfully undercrossed 2 properties

Only a small over excavation was observed at R142


which happened after resuming mining after CHI. It was
compensated by TBM body grouting in the following
rings. 2 probe holes were carried out from surface to
prove no void exists and grouted

No sign of distress

Continuous body / backfill grouting

All the instrumentation readings are stable


2
3
4
Performance of TBM3 under mixed ground
Excavation parameters and body & backfill grout
Target
Face pressure Excavation Body Grout Backfill Grout
Ring Built Excavation Over Excavation
Avg (kPa) Volume in m3 Volume in m3 Volume in m3
Volume in m3

109 3.37 41.9 38.8 8% - 2.171

110 3.48 35.9 38.8 - - 4.809

111 3.54 40.9 40.9 - 3.095 4.665

112 3.64 40.08 40.9 - 2.005 4.500

113 3.41 37.3 39.4 - 4.405 4.472

114 3.47 39.7 39.4 1% - 4.500

115 3.47 41.8 40.9 2% 4.578 4.578

116 3.52 39.4 40.9 - 3.172 4.550

117 3.56 40.2 40.9 1.958 4.599

118 3.55 35.3 40.9 - 3.938 4.675

5
Performance of TBM3 under mixed ground
Excavation parameters and body & backfill grout
Target
Face pressure Excavation Body Grout Backfill Grout
Ring Built Excavation Over Excavation
Avg (kPa) Volume in m3 Volume in m3 Volume in m3
Volume in m3

119 3.57 39.1 40.9 - 2.404 4.500

120 3.35 25.1 40.9 - - 4.806

121 3.42 38.3 40.9 - - 4.712

122 3.42 41.7 40.9 2% - 4.869

123 3.42 37.9 40.9 - 2.756 4.631

124 3.29 40.9 40.9 - 3.788 4.714

125 3.38 40.1 36.9 8% 5.091 4.671

126 3.42 35.6 36.9 - 4.550 4.55

127 3.42 32.5 36.9 - 4.510 4.51

128 3.40 30.0 36.9 - 3.425 4.479

6
Performance of TBM3 under mixed ground
Excavation parameters and body & backfill grout
Target
Face pressure Excavation Body Grout Backfill Grout
Ring Built Excavation Over Excavation
Avg (kPa) Volume in m3 Volume in m3 Volume in m3
Volume in m3

129 3.40 25.0 36.9 - 3.215 4.549

130 3.40 23.5 36.9 - 2.277 4.466

131 3.41 20.5 35.2 - 4.977 4.490

132 3.45 31.9 35.2 - 2.560 4.429

133 3.45 30.1 35.2 - 2.547 4.447

134 3.45 29.6 35.2 - 1.626 4.524

135 3.44 26.8 29.3 - 1.330 4.518

136 3.42 25.2 29.3 - 1.295 4.558

137 3.45 24.4 29.3 - 0.847 4.452

138 3.43 25.6 29.3 - 1.075 4.311

7
Performance of TBM3 under mixed ground
Excavation parameters and body & backfill grout
Target
Face pressure Excavation Body Grout Backfill Grout
Ring Built Excavation Over Excavation
Avg (kPa) Volume in m3 Volume in m3 Volume in m3
Volume in m3

139 3.48 27.8 32.8 - 0.255 4.034

140 3.50 27.2 32.8 - 1.330 4.130

141 3.50 28.1 32.8 - 0.611 4.500

142 3.51 40.4 32.8 17% - 4.180

143 3.62 30.86 32.8 - 3.303 4.655

144 3.56 27.0 32.8 - 5.075 4.784

145 3.41 28.56 34.6 - 3.249 4.598

146 3.41 24.87 25.0 - 3.548 4.311

147 3.39 25.1 34.6 - 1.815 4.532

148 3.40 25.73 31.7 - 0.909 4.611

8
Performance of TBM3 under mixed ground
Excavation parameters and body & backfill grout
Target
Face pressure Excavation Body Grout Backfill Grout
Ring Built Excavation Over Excavation
Avg (kPa) Volume in m3 Volume in m3 Volume in m3
Volume in m3

149 3.40 21.2 30.0 - 0.869 4.274

150 3.39 22.9 31.1 - 0.202 4.46

151 3.39 19.6 31.7 - 1.855 4.503

152 3.39 23.4 32.2 - 2.109 4.497

153 3.40 21.8 32.7 - 0.341 4.252

154 3.38 21.9 31.1 - 0.757 4.465

155 3.39 24.4 31.7 - 1.093 4.45

156 3.40 26.3 32.6 - 0.139 4.322

157 3.39 27.4 35.1 - 0.675 4.619

158 3.39 21.7 30.1 - 0.000 4.465

9
Performance of TBM3 under mixed ground
Excavation parameters and body & backfill grout
Target
Face pressure Excavation Body Grout Backfill Grout
Ring Built Excavation Over Excavation
Avg (kPa) Volume in m3 Volume in m3 Volume in m3
Volume in m3

159 3.39 25.0 32.0 - 0.000 4.477

160 3.39 21.4 30.9 - 0.000 4.700

161 3.38 25.4 31.7 - 0.000 4.670

162 3.39 27.5 31.7 - 0.750 4.257

163 3.39 31.2 31.7 - 0.000 4.660

164 3.38 25.6 32.9 - 0.000 4.500

165 3.39 27.2 32.9 - 0.985 4.820

166 3.39 20.8 32.4 - 1.452 4.500

167 3.39 22.2 33.3 - 0.00 4.885

168 3.39 22.5 35.3 - 2.094 4.841

10
Performance of TBM3 under mixed ground
Excavation parameters and body & backfill grout
Target
Face pressure Excavation Body Grout Backfill Grout
Ring Built Excavation Over Excavation
Avg (kPa) Volume in m3 Volume in m3 Volume in m3
Volume in m3

169 3.39 31.0 31.4 - 2.730 4.450

170 3.37 35.4 32.9 4% 1.497 4.517

171 3.41 33.8 34.6 - 3.796 4.691

172 3.50 33.2 34.7 - 4.030 4.550

173 3.61 33.4 34.2 - 4.862 2.170

174 3.62 34.8 34.5 1% 1.940 4.480

175 3.61 34.7 34.4 1% 1.346 4.418

176 3.66 34.5 34.4 - 1.000 4.499

177 3.68 33.4 34.9 - 1.830 4.480

178 3.67 33.8 34.0 - 1.568 4.720

11
Performance of TBM3 under mixed ground
Excavation parameters and body & backfill grout
Target
Face pressure Excavation Body Grout Backfill Grout
Ring Built Excavation Over Excavation
Avg (kPa) Volume in m3 Volume in m3 Volume in m3
Volume in m3

179 3.62 32.1 35.9 - 2.020 4.570

180 3.64 33.0 33.5 - 2.507 4.510

181 3.61 30.7 34.4 - 2.400 4.360

182 3.60 36.0 35.3 2% 1.875 4.560

183 3.66 38.8 38.0 2% 2.850 4.334

184 3.67 39.7 37.7 5% 1.329 4.313

185 3.59 37.5 39.7 - 1.250 4.520

12
13
14
15
16
17
18
19
20
TBM-4. Undercrossing and adjacent structures

21
TBM-4. Undercrossing and adjacent structures

22
TBM-4. Undercrossing and adjacent structures
No. 83 Dalvey Road (Adjacent)

3.5m

BH-3

23
TBM-4. Undercrossing and adjacent structures
No. 83 Dalvey Road (Adjacent)

Soil Profile
R26 R47

Full Face Soil

Full Face Soil


Geophysical Survey
Result

24
TBM-4. Undercrossing and adjacent structures
No. 83 Dalvey Road (Adjacent)
Building Settlement Marker

25
TBM-4. Undercrossing and adjacent structures
No. 83 Dalvey Road (Adjacent)
Summary of Damage Impact Assessment
Overall
Maximum
Building Category of
Volume Loss Tensile Strain
Settlement Damage
(%)
(mm)
1% 13.22 0.0191 0
2% 28.62 0.0383 0

Requirement for Building in close proximity under Full Face Soil


PLC cut-off to stop the TBM when over excavation reaches 10%. Actions to be
taken include carrying out surface grouting and carrying out GPR to detect
voids.
QSS to inspect the houses twice a day and to certify its structural safety
throughout the period when tunnel crosses close to building.
Regardless of the magnitude of over-excavation %, if building settlement
markers installed on the building breach WSL of 15mm (for buildings on
piles), QPS and builder shall stop the TBM operation and notify BCA.
If QSS observe any building showing signs of distress during his inspection
(regardless of the magnitude of over-excavation %), decanting shall be
implemented. 26
TBM-4. Undercrossing and adjacent structures
No. 62A Dalvey Road (Undercrossing)

62A Dalvey Road

ST/5506

ST/2205A

ABH-310

27
TBM-4. Undercrossing and adjacent structures
No. 62A Dalvey Road (Undercrossing)

Soil Profile
R79 R90

Full Face Soil

Full Face Soil

Geophysical Survey
Result

28
TBM-4. Undercrossing and adjacent structures
No. 62A Dalvey Road (Undercrossing)
Building Settlement Marker

29
TBM-4. Undercrossing and adjacent structures
No. 62A Dalvey Road (Undercrossing)
Summary of Damage Impact Assessment
Overall
Maximum
Building Category of
Volume Loss Tensile Strain
Settlement Damage
(%)
(mm)
1% 16.96 0.0326 0
2% 22.76 0.0622 1
Requirement for Building undercrossing under Full Face Soil
Shield grouting for each ring during mining.
PLC cut-off to stop the TBM when over excavation reaches 10%. Actions to be
taken include carrying out surface grouting and carrying out GPR to detect
voids.
QSS to inspect the houses twice a day and to certify its structural safety
throughout the period when tunnel crosses underneath building.
Regardless of the magnitude of over-excavation %, if building settlement
markers installed on the building breach WSL of 15mm (for buildings on
piles), QPS and builder shall stop the TBM operation and notify BCA.
If QSS observe any building showing signs of distress during his inspection
(regardless of the magnitude of over-excavation %), decanting shall be
30
implemented.
TBM-4. Undercrossing and adjacent structures
No. 62 Dalvey Road (Undercrossing)

62 Dalvey Road BH-04

ABH-310

31
TBM-4. Undercrossing and adjacent structures
No. 62 Dalvey Road (Undercrossing)

Soil Profile
R90 R109

Mixed Face

Mixed Face

Geophysical Survey
Result

32
TBM-4. Undercrossing and adjacent structures
No. 62 Dalvey Road (Undercrossing)
Building Settlement Marker

33
TBM-4. Undercrossing and adjacent structures
No. 62 Dalvey Road (Undercrossing)
Summary of Damage Impact Assessment
Overall
Maximum
Building Category of
Volume Loss Tensile Strain
Settlement Damage
(%)
(mm)
1% 10.89 0.0106 0
2% 22.89 0.0262 0

34
TBM-4. Undercrossing and adjacent structures
No. 62 Dalvey Road (Undercrossing)
* This building will not have occupants during the period of tunneling.

Requirement for Building undercrossing under Mixed Face


Shield grouting for each ring during mining.
Standby rig to carry out surface grouting.
PLC cut-off to stop the TBM when over excavation reaches 10%. Actions to be taken
include carrying out surface grouting and carrying out GPR to detect voids.
QSS to inspect the houses twice a day and to certify its structural safety throughout the
period when tunnel crosses underneath building.
Regardless of the magnitude of over-excavation %, if building settlement markers
installed on the building breach WSL of 15mm (for buildings on piles), QPS and builder
shall stop the TBM operation and notify BCA.
If QSS observe any building showing signs of distress during his inspection (regardless
of the magnitude of over-excavation %), decanting shall be implemented.

35
TBM-4. Undercrossing and adjacent structures
No. 20 Stevens close (Undercrossing)

BH-04
ABH-311

20 Steven Close

36
TBM-4. Undercrossing and adjacent structures
No. 20 Stevens close (Undercrossing)

Soil Profile
R129 R140

Mixed Face

Mixed Face

Geophysical Survey
Result

37
TBM-4. Undercrossing and adjacent structures
No. 20 Stevens close (Undercrossing)
Building Settlement Marker

38
TBM-4. Undercrossing and adjacent structures
No. 20 Stevens close (Undercrossing)
Summary of Damage Impact Assessment

Overall Building Maximum Tensile Category of


Volume Loss Remarks
Settlement (mm) Strain (%) Damage

1% 19.14 0.0293 0 Piles remained


2% 29.98 0.0811 2 intact

1% 13.72 0.0318 0
Piles dislodged
2% 23.10 0.0583 2

39
TBM-4. Undercrossing and adjacent structures
No. 20 Stevens close (Undercrossing)
QPD and QPS will submit a letter with assessment report stating that the 3 following
measure do not need to be taken:

1. Adjusting the alignment to avoid mixed face condition


2. Carrying out ground improvement (such as grouting) underneath the building to form
homogeneous annuli surrounding the tunnel
3. Temporarily vacate the house

Requirement for Building undercrossing under Mixed Face


Shield grouting for each ring during mining.
Standby rig to carry out surface grouting.
PLC cut-off to stop the TBM when over excavation reaches 10%. Actions to be taken
include carrying out surface grouting and carrying out GPR to detect voids.
QSS to inspect the houses twice a day and to certify its structural safety throughout the
period when tunnel crosses underneath building.
Regardless of the magnitude of over-excavation %, if building settlement markers
installed on the building breach WSL of 25mm (for buildings on shallow foundation and
of 15mm for buildings on piles), QPS and builder shall stop the TBM operation and
notify BCA.
40
If QSS observe any building showing signs of distress during his inspection (regardless
of the magnitude of over-excavation %), decanting shall be implemented.
TBM-4. Undercrossing and adjacent structures
No. 60 Fernhill Road (Undercrossing)

60 Fernhill Road

ST/4613 ABH-11

ST/5508

41
TBM-4. Undercrossing and adjacent structures
No. 60 Fernhill Road (Undercrossing)

Soil Profile
R183 R200

Full Face Soil

Full Face Soil

Geophysical Survey
Result

42
TBM-4. Undercrossing and adjacent structures
No. 60 Fernhill Road (Undercrossing)
Building Settlement Marker

43
TBM-4. Undercrossing and adjacent structures
No. 60 Fernhill Road (Undercrossing)
Summary of Damage Impact Assessment
Overall Building Maximum Tensile Category of
Volume Loss Remarks
Settlement (mm) Strain (%) Damage
1% 6.50 0.0065 0 Piles remained
2% 14.80 0.0165 0 intact
1% 8.91 0.0096 0
Piles dislodged
2% 19.35 0.0223 0

Requirement for Building undercrossing under Full Face Soil


Shield grouting for each ring during mining.
PLC cut-off to stop the TBM when over excavation reaches 10%. Actions to be
taken include carrying out surface grouting and carrying out GPR to detect
voids.
QSS to inspect the houses twice a day and to certify its structural safety
throughout the period when tunnel crosses underneath building.
Regardless of the magnitude of over-excavation %, if building settlement
markers installed on the building breach WSL of 15mm (for buildings on
piles), QPS and builder shall stop the TBM operation and notify BCA.
If QSS observe any building showing signs of distress during his inspection
(regardless of the magnitude of over-excavation %), decanting shall be
44
implemented.
TBM-4. Undercrossing and adjacent structures
No. 30B Nassim Road (Adjacent)

30B Nassim Road

ABH-301
ABH-302

ST/4616
3.3m

ABH-312

45
TBM-4. Undercrossing and adjacent structures
No. 30B Nassim Road (Adjacent)

Soil Profile

R373 R380

Mixed Face

Full Face Soil


Geophysical Survey
Result

46
TBM-4. Undercrossing and adjacent structures
No. 30B Nassim Road (Adjacent)
Summary of Damage Impact Assessment
30B Nassim Road falls under damage category Negligible during damage impact
assessment stage 2, therefore stage 3 assessment is not required to be carried out.

Room of the building within 1D from the tunnel will be vacated and kept away from
personnel.

Requirement for Building undercrossing under Mixed Face


Shield grouting for each ring during mining.
Standby rig to carry out surface grouting.
PLC cut-off to stop the TBM when over excavation reaches 10%. Actions to be taken
include carrying out surface grouting and carrying out GPR to detect voids.
QPS to inspect the houses twice a day and to certify its structural safety throughout the
period when tunnel crosses underneath building.
Regardless of the magnitude of over-excavation %, if building settlement markers
installed on the building breach WSL of 25mm (for buildings on shallow foundation),
QPS and builder shall stop the TBM operation and notify BCA.
If QPS observe any building showing signs of distress during his inspection (regardless
47
of the magnitude of over-excavation %), decanting shall be implemented.
TBM-4. Undercrossing and adjacent structures
No. 28M Nassim Road (Adjacent)

28M Nassim Road

3.9m

ABH-303
ST/4619

48
TBM-4. Undercrossing and adjacent structures
No. 28M Nassim Road (Adjacent)

Soil Profile
R470 R480

Full Face Soil

Geophysical Survey
Result
Mixed Face
Seismic data show change
of impedance that are
associated with rock
Additional Borehole will
be done to verify the rock
head level at R475
49
TBM-4. Undercrossing and adjacent structures
No. 28M Nassim Road (Adjacent)
Summary of Damage Impact Assessment
28M Nassim Road falls under damage category Negligible during damage impact
assessment stage 2, therefore stage 3 assessment is not required to be carried out.

Requirement for Building in close proximity under Full Face Soil


PLC cut-off to stop the TBM when over excavation reaches 10%. Actions to be
taken include carrying out surface grouting and carrying out GPR to detect
voids.
QSS to inspect the houses twice a day and to certify its structural safety
throughout the period when tunnel crosses close to building.
Regardless of the magnitude of over-excavation %, if building settlement
markers installed on the building breach WSL of 15mm (for buildings on
piles), QPS and builder shall stop the TBM operation and notify BCA.
If QSS observe any building showing signs of distress during his inspection
(regardless of the magnitude of over-excavation %), decanting shall be
implemented.
50
TBM-4. Undercrossing and adjacent structures
No. 32 Nassim Road (Undercrossing)

ABH-304

ABH-305
ABH-306

ABH-08
ABH-19E

51
TBM-4. Undercrossing and adjacent structures
No. 32 Nassim Road (Undercrossing)

R606 R625
Soil Profile

Full Face Soil

Full Face Soil

Geophysical Survey
Result

TBM-4 Tunnel alignment


Rock Head Level
GV/GVI 52
TBM-4. Undercrossing and adjacent structures
No. 32 Nassim Road (Undercrossing)
Summary of Damage Impact Assessment
Overall Building Maximum
Category of
Volume Loss Settlement Tensile Strain
Damage
(mm) (%)

1% 34 0.0535 1
2% 39 0.0569 1

Requirement for Building undercrossing under Full Face Soil


Shield grouting for each ring during mining.
PLC cut-off to stop the TBM when over excavation reaches 10%. Actions to be taken
include carrying out surface grouting and carrying out GPR to detect voids.
QSS to inspect the houses twice a day and to certify its structural safety throughout
the period when tunnel crosses underneath building.
Regardless of the magnitude of over-excavation %, if building settlement markers
installed on the building breach WSL of 25mm (for buildings on shallow
foundation), QPS and builder shall stop the TBM operation and notify BCA.
If QSS observe any building showing signs of distress during his inspection
(regardless of the magnitude of over-excavation %), decanting shall be
implemented.
53
TBM-4. Undercrossing and adjacent structures
No. 1 Taman Serasi Botanic Gardens View (Undercrossing)

ABH-10
ABH-9 ABH-307

ST/5579

1 Taman
Serasi

54
TBM-4. Undercrossing and adjacent structures
No. 1 Taman Serasi Botanic Gardens View (Undercrossing)

R732 R747
Soil Profile

Mixed Face

Full Face Soil

Geophysical Survey
Result

TBM-4 Tunnel alignment


Rock Head Level
55
GV/GVI
TBM-4. Undercrossing and adjacent structures
No. 1 Taman Serasi Botanic Gardens View (Undercrossing)
Summary of Damage Impact Assessment
Overall Building Maximum
Category of
Volume Loss Settlement Tensile Strain
Damage
(mm) (%)

1% 20.46 0.0425 0
2% 29.89 0.0573 1

56
TBM-4. Undercrossing and adjacent structures
No. 1 Taman Serasi Botanic Gardens View (Undercrossing)
QPD and QPS will submit a letter with assessment report stating that the 3 following
measure do not need to be taken:

1. Adjusting the alignment to avoid mixed face condition


2. Carrying out ground improvement (such as grouting) underneath the building to form
homogeneous annuli surrounding the tunnel
3. Temporarily vacate the house

Requirement for Building undercrossing under Mixed Face


Shield grouting for each ring during mining.
Standby rig to carry out surface grouting.
PLC cut-off to stop the TBM when over excavation reaches 10%. Actions to be taken
include carrying out surface grouting and carrying out GPR to detect voids.
QSS to inspect the houses twice a day and to certify its structural safety throughout the
period when tunnel crosses underneath building.
Regardless of the magnitude of over-excavation %, if building settlement markers
installed on the building breach WSL of 25mm (for buildings on shallow foundation),
QPS and builder shall stop the TBM operation and notify BCA.
If QSS observe any building showing signs of distress during his inspection (regardless
of the magnitude of over-excavation %), decanting shall be implemented. 57
TBM-4. Undercrossing and adjacent structures
No. 9 Taman Serasi Botanic Gardens View (Adjacent)

9 Taman ABH-308

Serasi

ABH-10
1.6m ST/5579

58
TBM-4. Undercrossing and adjacent structures
No. 9 Taman Serasi Botanic Gardens View (Adjacent)

R752 R775

Soil Profile

Full Face Soil

Full Face Soil

Geophysical Survey
Result

TBM-4 Tunnel alignment


Rock Head Level
GV/GVI
59
TBM-4. Undercrossing and adjacent structures
No. 9 Taman Serasi Botanic Gardens View (Adjacent)
Summary of Damage Impact Assessment
Overall Building Maximum
Category of
Volume Loss Settlement Tensile Strain
Damage
(mm) (%)

1% 8.04 0.0083 0
2% 16.93 0.0181 0

Requirement for Building in close proximity under Full Face Soil


PLC cut-off to stop the TBM when over excavation reaches 10%. Actions to be
taken include carrying out surface grouting and carrying out GPR to detect
voids.
QSS to inspect the houses twice a day and to certify its structural safety
throughout the period when tunnel crosses underneath building.
Regardless of the magnitude of over-excavation %, if building settlement
markers installed on the building breach WSL of 15mm (for buildings on
piles), QPS and builder shall stop the TBM operation and notify BCA.
If QSS observe any building showing signs of distress during his inspection
(regardless of the magnitude of over-excavation %), decanting shall be
implemented. 60