PROGRAMA REGIONAL DE RIEGO Y DRENAJE - PRORR

OFICINA DE LIQUIDACION DE OBRAS


INFORME DE EQUIPO DE MAQUINARIA PESADA - P

"MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA DEL SIS


YOCARA, EN LA LOCALIDAD DE YOCARA, DISTRITOS DE JULIACA
PROVINCIA DE SAN ROMAN, REGION PUNO-CONSTRUCCION DEL CA

RESUMEN DE TOMO 21
PROPIETARIO: PRORR

EQUIPO MES HM
VOLQUETE - VOLVO FMX 440 PLACA: EGL - 122 Mar-15 53.00
VOLQUETE - VOLVO FMX 440 PLACA: EGL - 122 Apr-15 49.20
VOLQUETE - VOLVO FMX 440 PLACA: EGL - 122 May-15 130.12
TOTAL 232.32
VOLQUETE VOLVO F 12 PLACA: XU - 2885 Mar-15 12.00
VOLQUETE VOLVO F 12 PLACA: XU - 2885 Apr-15 57.80
TOTAL 69.80
RETROEXCAVADORA CAT 420 E Mar-15 58.95
RETROEXCAVADORA CAT 420 E Apr-15 100.77
TOTAL 159.72
RETROEXCAVADORA CAT 420 F Mar-15 66.20
RETROEXCAVADORA CAT 420 F Apr-15 121.55
TOTAL 187.75
RODILLO LISO VIBRATORIO CAT C5 533E Mar-15 8.05
RODILLO LISO VIBRATORIO CAT C5 533E Apr-15 6.00
TOTAL 14.05

PROPIETARIO: ALQUI
EQUIPO MES HM
CAMION CUSTER FORLAND PLACA: Z5Y-921 Mar-15 32.00
CAMION CUSTER FORLAND PLACA: Z5Y-921 Apr-15 176.00
TOTAL 208.00

PROGRAMA REGIONAL DE RIEGO Y DRENAJE - PRORR


OFICINA DE LIQUIDACION DE OBRAS
INFORME DE EQUIPO DE MAQUINARIA PESADA - P

"MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA DEL SIS


YOCARA, EN LA LOCALIDAD DE YOCARA, DISTRITOS DE JULIACA
PROVINCIA DE SAN ROMAN, REGION PUNO-CONSTRUCCION DEL CA

RESUMEN DE TOMO 22
PROPIETARIO: PRORR

EQUIPO MES HM
VOLQUETE - VOLVO FMX 440 - PLACA : EGL - 122 Jun-15 148.00
TOTAL 148.00
VOLQUETE VOLVO F 12 PLACA: XU - 2885 May-15 57.43
TOTAL 57.43
RETROEXCAVADORA CAT 420 E May-15 166.13
RETROEXCAVADORA CAT 420 E Jun-15 152.52
TOTAL 318.65
RETROEXCAVADORA CAT 420 F May-15 91.13
TOTAL 91.13
RODILLO LISO VIBRATORIO CAT C5 533E May-15 55.40
RODILLO LISO VIBRATORIO CAT C5 533E Jun-15 67.57
TOTAL 122.97

PROPIETARIO: ALQUI

EQUIPO MES HM
CAMION CUSTER FORLAND PLACA: Z5Y-921 May-15 200.00
CAMION CUSTER FORLAND PLACA: Z5Y-921 Jun-15 200.00
TOTAL 400.00
CAMION FUSO MITSUBISHI PLACA: Z5Q-710 Jun-15 200.00
TOTAL 200.00

PROPIETARIO: CONVENIO GOBIERNO


GR
EQUIPO MES HM
VOLQUETE MACK PLACA: Z1J 862 - GRP May-15 140.23
VOLQUETE MACK PLACA: Z1J 862 - GRP Jun-15 129.12
TOTAL 269.35
VOLQUETE MACK PLACA: Z1I 839 - GRP May-15 10.67
TOTAL 10.67
VOLQUETE INTERNATIONAL PLACA: Z1S 858 - GRP May-15 119.77
VOLQUETE INTERNATIONAL PLACA: Z1S 858 - GRP Jun-15 121.77
TOTAL 241.53
VOLQUETE INTERNATIONAL PLACA: Z1I 902 - GRP May-15 28.13
VOLQUETE INTERNATIONAL PLACA: Z1I 902 - GRP Jun-15 89.90
TOTAL 118.03
MOTONIVELADORA CAT 140 K - GRP May-15 86.08
MOTONIVELADORA CAT 140 K - GRP Jun-15 111.58
TOTAL 197.67
EXCAVADORA KOLBELCO CS 350 - GRP May-15 79.52
EXCAVADORA KOLBELCO CS 350 - GRP Jun-15 144.80
TOTAL 224.32

PROPIETARIO: CONVENIO

EQUIPO MES HM
CARGADOR FRONTAL VOLVO L150C Jun-15 57.77
TOTAL 57.77
VOLQUETE FMX 440 DOY-861 Jun-15 32.67
TOTAL 32.67
VOLQUETE FMX 440 V5B-789 Jun-15 31.55
TOTAL 31.55
EXCAVADORA CAT 325B Jun-15 7.92
TOTAL 7.92

PROGRAMA REGIONAL DE RIEGO Y DRENAJE - PRORR


OFICINA DE LIQUIDACION DE OBRAS
INFORME DE EQUIPO DE MAQUINARIA PESADA - P

"MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA DEL SIS


YOCARA, EN LA LOCALIDAD DE YOCARA, DISTRITOS DE JULIACA
PROVINCIA DE SAN ROMAN, REGION PUNO-CONSTRUCCION DEL CA

RESUMEN DE TOMO 23

PROPIETARIO: PRORR

EQUIPO MES HM
VOLQUETE - VOLVO FMX 440 PLACA: EGL - 122 Jul-15 135.02
VOLQUETE - VOLVO FMX 440 PLACA: EGL - 122 Aug-15 163.65
TOTAL 298.67
RETROEXCAVADORA CAT 420 E Jul-15 32.28
RETROEXCAVADORA CAT 420 E Aug-15 0.00
TOTAL 32.28
RODILLO LISO VIBRATORIO CAT C5 533E Jul-15 47.70
RODILLO LISO VIBRATORIO CAT C5 533E Aug-15 0.00
TOTAL 47.70
CAMIONETA HILUX PLACA: EGH 146 Jul-15 0.00
CAMIONETA HILUX PLACA: EGH 146 Aug-15 0.00
TOTAL 0.00

PROPIETARIO: CONVENIO GOBIERNO


GR
EQUIPO MES HM
VOLQUETE MACK PLACA: Z1J 862 - GRP Jul-15 122.33
VOLQUETE MACK PLACA: Z1J 862 - GRP Aug-15 116.23
TOTAL 238.57
VOLQUETE INTERNATIONAL PLACA: Z1S 858 - GRP Jul-15 125.88
VOLQUETE INTERNATIONAL PLACA: Z1S 858 - GRP Aug-15 118.73
TOTAL 244.62
VOLQUETE INTERNATIONAL PLACA: Z1I 902 - GRP Jul-15 124.00
VOLQUETE INTERNATIONAL PLACA: Z1I 902 - GRP Aug-15 132.00
TOTAL 256.00
MOTONIVELADORA CAT 140 K - GRP Jul-15 59.12
MOTONIVELADORA CAT 140 K - GRP Aug-15 108.35
TOTAL 167.47
EXCAVADORA KOLBELCO CS 350 - GRP Jul-15 56.40
EXCAVADORA KOLBELCO CS 350 - GRP Aug-15 104.53
TOTAL 160.93

PROPIETARIO: CONVENIO

EQUIPO MES HM
CARGADOR FRONTAL VOLVO L150C Jul-15 79.95
TOTAL 79.95
VOLQUETE FMX 440 DOY-861 Jul-15 55.83
TOTAL 55.83
VOLQUETE FMX 440 V5B-789 Jul-15 19.83
TOTAL 19.83
EXCAVADORA CAT 325B Jul-15 211.83
EXCAVADORA CAT 325B Aug-15 195.70
TOTAL 407.53
VOLQUETE VOLVO D70-702 Jul-15 111.97
VOLQUETE VOLVO D70-702 Aug-15 174.25
TOTAL 286.22
VOLQUETE VOLVO Z3P - 766 Jul-15 71.98
VOLQUETE VOLVO Z3P - 766 Aug-15 154.88
TOTAL 226.87
CARGADOR FRONTAL VOLVO L150E Jul-15 97.48
CARGADOR FRONTAL VOLVO L150E Aug-15 156.25
TOTAL 253.73
RODILLO LISO VIBRATORIO VM 115 Jul-15 6.70
RODILLO LISO VIBRATORIO VM 115 Aug-15 144.32
TOTAL 151.02
MOTONIVELADORA CAT 140H Jul-15 11.33
MOTONIVELADORA CAT 140H Aug-15 3.75
TOTAL 15.08
VOLQUETE MERCEDES BENZ XU - 3279 Jul-15 7.50
VOLQUETE MERCEDES BENZ XU - 3279 Aug-15 143.63
TOTAL 151.13
CISTERNA VOLVO F10 PLACA: Z2W - 810 Aug-15 118.77
TOTAL 118.77
PROPIETARIO: ALQUI

EQUIPO MES HM
CAMION CUSTER FORLAND PLACA: Z5Y-921 Jul-15 200.00
CAMION CUSTER FORLAND PLACA: Z5Y-921 Aug-15 216.00
TOTAL 416.00
CAMION FUSO MITSUBISHI PLACA: Z5Q-710 Jul-15 200.00
CAMION FUSO MITSUBISHI PLACA: Z5Q-710 Aug-15 216.00
TOTAL 416.00
CAMIONETA HILUX C3K - 804 SUPERVISION Aug-15 0.00
TOTAL 0.00

PROGRAMA REGIONAL DE RIEGO Y DRENAJE - PRORR


OFICINA DE LIQUIDACION DE OBRAS
INFORME DE EQUIPO DE MAQUINARIA PESADA - P

"MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA DEL SIS


YOCARA, EN LA LOCALIDAD DE YOCARA, DISTRITOS DE JULIACA
PROVINCIA DE SAN ROMAN, REGION PUNO-CONSTRUCCION DEL CA

RESUMEN DE TOMO 24
JE - PRORRIDRE
RAS
ESADA - POR MESES

UA DEL SISTEMA DE RIEGO


DE JULIACA Y CARACOTO,
ON DEL CANAL PRINCIPAL B"

PRORRIDRE

C.U. COSTO S/. COMBUSTIBLE FOLIOS


0.00 115.00 13.00
0.00 140.00 12.00
0.00 410.00 23.00
0.00 665.00 48.00
0.00 15.00 2.00
0.00 245.00 13.00
0.00 260.00 15.00
0.00 100.00 10.00
0.00 230.00 16.00
0.00 330.00 26.00
0.00 121.00 12.00
0.00 250.00 22.00
0.00 371.00 34.00
0.00 35.00 5.00
0.00 15.00 1.00
0.00 50.00 6.00

ALQUILADA
C.U. COSTO S/. COMBUSTIBLE FOLIOS
25.01 800.22 10.00 4.00
25.01 4,401.23 55.00 22.00
5,201.46 65.00 26.00

JE - PRORRIDRE
RAS
ESADA - POR MESES

UA DEL SISTEMA DE RIEGO


DE JULIACA Y CARACOTO,
ON DEL CANAL PRINCIPAL B"

PRORRIDRE

C.U. COSTO S/. COMBUSTIBLE FOLIOS


0.00 455.00 24.00
0.00 0.00 455.00 24.00
0.00 225.00 14.00
0.00 225.00 14.00
0.00 450.00 23.00
0.00 360.00 22.00
0.00 810.00 45.00
0.00 205.00 15.00
0.00 205.00 15.00
0.00 205.00 13.00
0.00 290.00 22.00
0.00 495.00 35.00

ALQUILADA

C.U. COSTO S/. COMBUSTIBLE FOLIOS


25.01 5,001.40 90.00 25.00
25.01 5,001.40 100.00 25.00
10,002.80 190.00 50.00
25.01 5,001.40 105.00 25.00
25.01 5,001.40 105.00 25.00

GOBIERNO REGIONAL DE PUNO -


GRP
C.U. COSTO S/. COMBUSTIBLE FOLIOS
0.00 365.00 25.00
0.00 415.00 23.00
0.00 780.00 48.00
0.00 55.00 3.00
0.00 55.00 3.00
0.00 355.00 25.00
0.00 395.00 22.00
0.00 750.00 47.00
0.00 90.00 6.00
0.00 320.00 19.00
0.00 410.00 25.00
150.00 12,912.50 505.00 15.00
150.00 16,737.50 495.00 23.00
29,650.00 1,000.00 38.00
0.00 735.00 12.00
0.00 1,250.00 24.00
0.00 1,985.00 36.00

CONVENIO AMDIL

C.U. COSTO S/. COMBUSTIBLE FOLIOS


130.00 7,509.67 295.00 9.00
7,509.67 295.00 9.00
100.00 3,266.67 120.00 6.00
3,266.67 120.00 6.00
100.00 3,155.00 110.00 7.00
3,155.00 110.00 7.00
220.00 1,741.67 60.00 1.00
1,741.67 60.00 1.00

JE - PRORRIDRE
RAS
ESADA - POR MESES

UA DEL SISTEMA DE RIEGO


DE JULIACA Y CARACOTO,
ON DEL CANAL PRINCIPAL B"

PRORRIDRE

C.U. COSTO S/. COMBUSTIBLE FOLIOS


0.00 455.00 22.00
0.00 545.00 26.00
0.00 1,000.00 48.00
0.00 105.00 5.00
0.00 50.00 3.00
0.00 155.00 8.00
0.00 185.00 13.00
0.00 7.00 1.00
0.00 192.00 14.00
0.00 60.00 6.00
0.00 85.00 21.00
0.00 145.00 27.00

GOBIERNO REGIONAL DE PUNO -


GRP
C.U. COSTO S/. COMBUSTIBLE FOLIOS
0.00 380.00 21.00
0.00 370.00 19.00
0.00 750.00 40.00
0.00 395.00 22.00
0.00 366.00 22.00
0.00 761.00 44.00
0.00 380.00 21.00
0.00 435.00 24.00
0.00 815.00 45.00
150.00 8,867.50 380.00 12.00
150.00 16,252.50 670.00 24.00
25,120.00 1,050.00 36.00
0.00 440.00 11.00
0.00 920.00 18.00
0.00 1,360.00 29.00

CONVENIO AMDIL

C.U. COSTO S/. COMBUSTIBLE FOLIOS


130.00 10,393.50 420.00 11.00
10,393.50 420.00 11.00
100.00 5,583.33 170.00 9.00
5,583.33 170.00 9.00
100.00 1,983.33 65.00 3.00
1,983.33 65.00 3.00
220.00 46,603.33 1,360.00 26.00
220.00 43,054.00 1,240.00 26.00
89,657.33 2,600.00 52.00
100.00 11,196.67 340.00 17.00
100.00 17,425.00 550.00 27.00
28,621.67 890.00 44.00
100.00 7,198.33 240.00 11.00
100.00 15,488.33 485.00 24.00
22,686.67 725.00 35.00
130.00 12,672.83 535.00 13.00
130.00 20,312.50 840.00 25.00
32,985.33 1,375.00 38.00
130.00 871.00 30.00 2.00
130.00 18,761.17 460.00 26.00
19,632.17 490.00 28.00
140.00 1,586.67 50.00 2.00
140.00 525.00 35.00 1.00
2,111.67 85.00 3.00
100.00 750.00 20.00 1.00
100.00 14,363.33 435.00 21.00
15,113.33 455.00 22.00
100.00 11,876.67 280.00 17.00
11,876.67 280.00 17.00
ALQUILADA

C.U. COSTO S/. COMBUSTIBLE FOLIOS


25.01 5,001.40 90.00 25.00
25.01 5,401.51 125.00 27.00
10,402.91 215.00 52.00
25.01 5,001.40 110.00 25.00
25.01 5,401.51 126.00 27.00
10,402.91 236.00 52.00
0.00 35.00 7.00
0.00 35.00 7.00

JE - PRORRIDRE
RAS
ESADA - POR MESES

UA DEL SISTEMA DE RIEGO


DE JULIACA Y CARACOTO,
ON DEL CANAL PRINCIPAL B"
GOBIERNO REGIONAL
Programa Regional de Riego y Drenaje
PRORRIDRE
OFICINA DE LIQUIDACION DE OBRAS
INFORME DE EQUIPO DE MAQUINARIA PESADA -
PROPIETARIO : PRORRIDRE

VOLQUETE - VOLVO FMX 440 PLACA: EGL - 122


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Mar-15 53.00 0.00 0.00 115.00 - 0.00 53.00 - 0.00 115.00 - 0.00
Apr-15 49.20 0.00 0.00 140.00 - 0.00 49.20 - 0.00 140.00 - 0.00
May-15 130.12 0.00 0.00 410.00 - 0.00 114.40 - 0.00 410.00 - 0.00
Jun-15 148.00 0.00 0.00 455.00 - 0.00 148.00 - 0.00 455.00 - 0.00
Jul-15 135.02 0.00 0.00 455.00 - 0.00 135.02 - 0.00 455.00 - 0.00
Aug-15 163.65 0.00 0.00 545.00 - 0.00 163.65 - 0.00 545.00 - 0.00
Sep-15 94.07 0.00 0.00 360.00 - 0.00 94.07 - 0.00 360.00 - 0.00
Oct-15 87.20 0.00 0.00 265.00 - 0.00 87.20 - 0.00 265.00 - 0.00
Nov-15 178.77 0.00 0.00 650.00 - 0.00 178.77 - 0.00 650.00 - 0.00
Dec-15 178.45 0.00 0.00 490.00 - 0.00 178.45 - 0.00 490.00 - 0.00
Jan-16 154.02 0.00 0.00 460.00 - 0.00 154.02 - 0.00 460.00 - 0.00
Feb-16 112.90 0.00 0.00 290.00 - 0.00 112.90 - 0.00 290.00 - 0.00
Mar-16 104.30 0.00 0.00 240.00 - 0.00 104.30 - 0.00 240.00 - 0.00
Apr-16 97.43 0.00 0.00 260.00 - 0.00 97.43 - 0.00 260.00 - 0.00
May-16 114.38 0.00 0.00 315.00 - 0.00 114.38 - 0.00 315.00 - 0.00
TOTAL . 1,800.50 0.00 5,450.00 0.00 1,784.78 0.00 5,450.00 0.00

VOLQUETE VOLVO F 12 PLACA: XU - 2885


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Mar-15 12.00 0.00 0.00 15.00 - 0.00 12.00 - 0.00 15.00 - 0.00
Apr-15 57.80 0.00 0.00 245.00 - 0.00 57.80 - 0.00 245.00 - 0.00
May-15 57.43 0.00 0.00 225.00 - 0.00 57.43 - 0.00 225.00 - 0.00
TOTAL . 127.23 0.00 485.00 0.00 127.23 0.00 485.00 0.00

RETROEXCAVADORA CAT 420 E


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Mar-15 58.95 0.00 0.00 100.00 - 0.00 58.95 - 0.00 100.00 - 0.00
Apr-15 100.77 0.00 0.00 230.00 - 0.00 100.77 - 0.00 230.00 - 0.00
May-15 166.13 0.00 0.00 450.00 - 0.00 166.13 - 0.00 450.00 - 0.00
Jun-15 152.52 0.00 0.00 360.00 - 0.00 152.52 - 0.00 380.00 - 0.00
Jul-15 32.28 0.00 0.00 105.00 - 0.00 32.28 - 0.00 105.00 - 0.00
Aug-15 0.00 0.00 0.00 50.00 - 0.00 0.00 - 0.00 50.00 - 0.00
Sep-15 0.00 0.00 0.00 0.00 - 0.00 0.00 - 0.00 0.00 - 0.00
Oct-15 0.00 0.00 0.00 0.00 - 0.00 0.00 - 0.00 0.00 - 0.00
Nov-15 0.00 0.00 0.00 0.00 - 0.00 0.00 - 0.00 0.00 - 0.00
Dec-15 85.55 0.00 0.00 280.00 - 0.00 85.55 - 0.00 280.00 - 0.00
Jan-16 147.95 0.00 0.00 410.00 - 0.00 147.95 - 0.00 410.00 - 0.00
Feb-16 135.37 0.00 0.00 345.00 - 0.00 135.37 - 0.00 345.00 - 0.00
Mar-16 92.27 0.00 0.00 235.00 - 0.00 92.27 - 0.00 235.00 - 0.00
Apr-16 86.33 0.00 0.00 230.00 - 0.00 86.33 - 0.00 230.00 - 0.00
May-16 108.55 0.00 0.00 295.00 - 0.00 108.55 - 0.00 295.00 - 0.00
TOTAL . 1,166.67 0.00 3,090.00 0.00 1,166.67 0.00 3,110.00 0.00

RETROEXCAVADORA CAT 420 F


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Mar-15 66.20 0.00 0.00 121.00 - 0.00 66.20 - 0.00 121.00 - 0.00
Apr-15 121.55 0.00 0.00 250.00 - 0.00 121.55 - 0.00 250.00 - 0.00
May-15 91.13 0.00 0.00 205.00 - 0.00 91.13 - 0.00 205.00 - 0.00
TOTAL . 278.88 0.00 576.00 0.00 278.88 0.00 576.00 0.00

RODILLO LISO VIBRATORIO CAT C5 533E


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Mar-15 8.05 0.00 0.00 35.00 - 0.00 8.38 - 0.00 35.00 - 0.00
Apr-15 6.00 0.00 0.00 15.00 - 0.00 6.00 - 0.00 15.00 - 0.00
May-15 55.40 0.00 0.00 205.00 - 0.00 55.40 - 0.00 205.00 - 0.00
Jun-15 67.57 0.00 0.00 290.00 - 0.00 67.57 - 0.00 290.00 - 0.00
Jul-15 47.70 0.00 0.00 185.00 - 0.00 47.70 - 0.00 185.00 - 0.00
Aug-15 0.00 0.00 0.00 7.00 - 0.00 0.00 - 0.00 7.00 - 0.00
Sep-15 11.53 0.00 0.00 60.00 - 0.00 13.65 - 0.00 60.00 - 0.00
Oct-15 0.00 0.00 0.00 0.00 - 0.00 0.00 - 0.00 0.00 - 0.00
Nov-15 28.85 0.00 0.00 95.00 - 0.00 28.85 - 0.00 95.00 - 0.00
Dec-15 133.32 0.00 0.00 373.00 - 0.00 133.32 - 0.00 373.00 - 0.00
Jan-16 125.97 0.00 0.00 335.00 - 0.00 125.97 - 0.00 335.00 - 0.00
Feb-16 0.00 0.00 0.00 5.00 - 0.00 0.00 - 0.00 5.00 - 0.00
Mar-16 49.22 0.00 0.00 115.00 - 0.00 49.22 - 0.00 115.00 - 0.00
Apr-16 68.63 0.00 0.00 190.00 - 0.00 68.63 - 0.00 190.00 - 0.00
May-16 72.82 0.00 0.00 200.00 - 0.00 72.82 - 0.00 200.00 - 0.00
TOTAL . 675.05 0.00 2,110.00 0.00 677.50 0.00 2,110.00 0.00

CAMIONETA HILUX PLACA: EGH 146


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Jul-15 0.00 0.00 0.00 60.00 - 0.00 0.00 - 0.00 65.00 - 0.00
Aug-15 0.00 0.00 0.00 85.00 - 0.00 0.00 - 0.00 85.00 - 0.00
Sep-15 0.00 0.00 0.00 80.00 - 0.00 0.00 - 0.00 80.00 - 0.00
Oct-15 0.00 0.00 0.00 65.00 - 0.00 0.00 - 0.00 65.00 - 0.00
Nov-15 0.00 0.00 0.00 85.00 - 0.00 0.00 - 0.00 85.00 - 0.00
Dec-15 0.00 0.00 0.00 85.00 - 0.00 0.00 - 0.00 85.00 - 0.00
Jan-16 0.00 0.00 0.00 60.00 - 0.00 0.00 - 0.00 60.00 - 0.00
Feb-16 0.00 0.00 0.00 80.00 - 0.00 0.00 - 0.00 80.00 - 0.00
Mar-16 0.00 0.00 0.00 45.00 - 0.00 0.00 - 0.00 45.00 - 0.00
Apr-16 0.00 0.00 0.00 60.00 - 0.00 0.00 - 0.00 70.00 - 0.00
May-16 0.00 0.00 0.00 86.00 - 0.00 0.00 - 0.00 86.00 - 0.00
TOTAL . 0.00 0.00 791.00 0.00 0.00 0.00 806.00 0.00

HORMIGONERA
INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Sep-15 0.00 0.00 0.00 10.00 - 0.00 0.00 - 0.00 10.00 - 0.00
Oct-15 0.00 0.00 0.00 0.00 - 0.00 0.00 - 0.00 0.00 - 0.00
TOTAL . 0.00 0.00 10.00 0.00 0.00 0.00 10.00 0.00
PESADA - POR MESES
DIFERENCIA
EQUIPOS COMBUSTIBLES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
15.72 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
15.72 0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 -20.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 -20.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
-0.33 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
-2.12 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
-2.45 0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 -5.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 -10.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 -15.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
MESES
OBSERVACIONES

En el informe de
preliquidacion no se
consider las horas
maquina de los dias 7
y 26. (8:00 y 7:72
respectivamente)
OBSERVACIONES

OBSERVACIONES

En el informe de
preliquidacion el
dia 15 indica 20
galones, este
dato no hay en
los partes
diarios.
OBSERVACIONES

OBSERVACIONES

En el informe de
preliquidacion el
dia 30
aumentaron 20
minutos.

En el informe de
preliquidacion el
dia 9 indica 2.12
horas. Este dato
no se encuentra
en los partes
diarios.
OBSERVACIONES

En el informe de
preliquidacion el dia
24 indica 5 galones.
Ese dato no se
encuentra en los
partes diarios.

En el informe de
preliquidacion el dia
29 indica 10
galones. Ese dato
no se encuentra en
los partes diarios.

OBSERVACIONES
GOBIERNO REGIONAL
Programa Regional de Riego y Drenaje
PRORRIDRE
OFICINA DE LIQUIDACION DE
OBRAS
INFORME DE EQUIPO DE MAQUINARIA PESADA

PROPIETARIO :
PRORRIDRE

EQUIPOS LIQUIDACION PRE LIQUIDACION


HM COSTO S/. HM
VOLQUETE - VOLVO FMX 440 PLACA: EGL - 122 1,800.50 0.00 1,784.78
VOLQUETE VOLVO F 12 PLACA: XU - 2885 127.23 0.00 127.23
RETROEXCAVADORA CAT 420 E 1,166.67 0.00 1,166.67
RETROEXCAVADORA CAT 420 F 278.88 0.00 278.88
RODILLO LISO VIBRATORIO CAT C5 533E 675.05 0.00 677.50
CAMIONETA HILUX PLACA: EGH 146 0.00 0.00 0.00
HORMIGONERA 0.00 0.00 0.00
TOTAL 4,048.33 0.00 4,035.07
GIONAL
Riego y Drenaje
RE
DACION DE
MAQUINARIA PESADA

PRE LIQUIDACION PRE LIQ. VS LIQUIDACION OBSERVACIONES


COSTO S/. HM COSTO S/.
0.00 15.72 0.00 No se consider las
horas maquina de los
0.00 0.00 0.00 dias 7 y 26. (8:00 y
0.00 0.00 0.00 7:72
0.00 0.00 0.00 respectivamente)
En marzo el dia 30
0.00 -2.45 0.00
incrementaron 30 min. En
0.00 0.00 0.00 Setiembre el dia 9
0.00 0.00 0.00 aumentaron 2.12 horas
0.00 13.27 0.00
GOBIERNO REGIONAL
Programa Regional de Riego y Drenaje
PRORRIDRE
OFICINA DE LIQUIDACION DE OBRAS

INFORME DE EQUIPO DE MAQUINARIA PESADA

PROPIETARIO : GOBIERNO REGIONAL PUNO


VOLQUETE MACK PLACA: Z1J 862 - GRP
INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
May-15 140.23 0.00 0.00 365.00 - 0.00 140.23 - 0.00 365.00 - 0.00
Jun-15 129.12 0.00 0.00 415.00 - 0.00 129.12 - 0.00 415.00 - 0.00
Jul-15 122.33 0.00 0.00 380.00 - 0.00 122.33 - 0.00 380.00 - 0.00
Aug-15 116.23 0.00 0.00 370.00 - 0.00 116.23 - 0.00 395.00 - 0.00
Sep-15 80.13 0.00 0.00 300.00 - 0.00 80.13 - 0.00 300.00 - 0.00
Oct-15 74.88 0.00 0.00 230.00 - 0.00 74.88 - 0.00 230.00 - 0.00
Nov-15 21.47 0.00 0.00 85.00 - 0.00 21.47 - 0.00 85.00 - 0.00
Dec-15 100.77 0.00 0.00 365.00 - 0.00 100.77 - 0.00 365.00 - 0.00
Jan-16 0.00 0.00 0.00 15.00 - 0.00 0.00 - 0.00 15.00 - 0.00
TOTAL . 785.17 0.00 2,525.00 0.00 785.17 0.00 2,550.00 0.00

VOLQUETE MACK PLACA: Z1I 839 - GRP


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
May-15 10.67 0.00 0.00 55.00 - 0.00 10.67 - 0.00 55.00 - 0.00
TOTAL . 10.67 0.00 55.00 0.00 10.67 0.00 55.00 0.00

VOLQUETE INTERNATIONAL PLACA: Z1S 858 - GRP


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
May-15 119.77 0.00 0.00 355.00 - 0.00 119.7667 - 0.00 355.00 - 0.00
Jun-15 121.77 0.00 0.00 395.00 - 0.00 121.7667 - 0.00 395.00 - 0.00
Jul-15 125.88 0.00 0.00 395.00 - 0.00 125.8833 - 0.00 395.00 - 0.00
Aug-15 118.73 0.00 0.00 366.00 - 0.00 118.7333 - 0.00 371.00 - 0.00
Sep-15 61.23 0.00 0.00 235.00 - 0.00 61.23333 - 0.00 235.00 - 0.00
Oct-15 83.07 0.00 0.00 225.00 - 0.00 83.07 - 0.00 225.00 - 0.00
Nov-15 16.43 0.00 0.00 45.00 - 0.00 16.43 - 0.00 45.00 - 0.00
Dec-15 105.75 0.00 0.00 365.00 - 0.00 105.75 - 0.00 365.00 - 0.00
Jan-16 0.00 0.00 0.00 15.00 - 0.00 0.00 - 0.00 15.00 - 0.00
TOTAL . 752.63 0.00 2,396.00 0.00 752.63 0.00 2,401.00 0.00
VOLQUETE INTERNATIONAL PLACA: Z1I 902 - GRP
INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
May-15 28.13 0.00 0.00 90.00 - 0.00 28.13333 - 0.00 90.00 - 0.00
Jun-15 89.90 0.00 0.00 320.00 - 0.00 89.9 - 0.00 320.00 - 0.00
Jul-15 124.00 0.00 0.00 380.00 - 0.00 124 - 0.00 380.00 - 0.00
Aug-15 132.00 0.00 0.00 435.00 - 0.00 132 - 0.00 435.00 - 0.00
Sep-15 49.12 0.00 0.00 210.00 - 0.00 49.11667 - 0.00 210.00 - 0.00
Oct-15 72.43 0.00 0.00 185.00 - 0.00 72.43 - 0.00 185.00 - 0.00
Nov-15 48.43 0.00 0.00 120.00 - 0.00 48.43 - 0.00 120.00 - 0.00
Dec-15 78.88 0.00 0.00 305.00 - 0.00 78.88 - 0.00 305.00 - 0.00
Jan-16 0.00 0.00 0.00 15.00 - 0.00 0.00 - 0.00 15.00 - 0.00
TOTAL . 622.90 0.00 2,060.00 0.00 622.90 0.00 2,060.00 0.00

MOTONIVELADORA CAT 140 K - GRP


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
May-15 86.08 150.00 12,912.50 505.00 - 0.00 86.08333 150.00 12,912.50 505.00 - 0.00
Jun-15 111.58 150.00 16,737.50 495.00 - 0.00 111.5833 150.00 16,737.50 495.00 - 0.00
Jul-15 59.12 150.00 8,867.50 380.00 - 0.00 59.11667 150.00 8,867.50 380.00 - 0.00
Aug-15 108.35 150.00 16,252.50 670.00 - 0.00 108.35 150.00 16,252.50 670.00 - 0.00
Sep-15 45.98 150.00 6,897.50 282.00 - 0.00 45.98333 150.00 6,897.50 282.00 - 0.00
Oct-15 21.02 150.00 3,152.50 120.00 - 0.00 21.02 150.00 3,152.50 120.00 - 0.00
Nov-15 11.40 150.00 1,710.00 20.00 - 0.00 11.40 150.00 1,710.00 50.00 - 0.00
Dec-15 91.78 150.00 13,767.50 435.00 - 0.00 91.78 150.00 13,767.50 435.00 - 0.00
Jan-16 96.48 150.00 14,472.50 430.00 - 0.00 96.48 150.00 14,472.50 430.00 - 0.00
Feb-16 13.08 150.00 1,962.50 45.00 - 0.00 13.08 150.00 1,962.50 45.00 - 0.00
TOTAL . 644.88 96,732.50 3,382.00 0.00 644.88 96,732.50 3,412.00 0.00

EXCAVADORA KOLBELCO CS 350 - GRP


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
May-15 79.52 0.00 0.00 735.00 - 0.00 79.51667 - 0.00 735.00 - 0.00
Jun-15 144.80 0.00 0.00 1,250.00 - 0.00 144.8 - 0.00 1,250.00 - 0.00
Jul-15 56.40 0.00 0.00 440.00 - 0.00 56.4 - 0.00 440.00 - 0.00
Aug-15 104.53 0.00 0.00 920.00 - 0.00 104.5333 - 0.00 950.00 - 0.00
Sep-15 101.92 0.00 0.00 900.00 - 0.00 101.9167 - 0.00 900.00 - 0.00
Oct-15 3.18 0.00 0.00 70.00 - 0.00 3.18 - 0.00 70.00 - 0.00
TOTAL . 490.35 0.00 4,315.00 0.00 490.35 0.00 4,345.00 0.00

CAMA BAJA
INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Sep-15 0.00 0.00 0.00 55.00 - 0.00 0.00 - 0.00 55.00 - 0.00
Oct-15 0.00 0.00 0.00 25.00 - 0.00 0.00 - 0.00 25.00 - 0.00
Nov-15 0.00 0.00 0.00 20.00 - 0.00 0.00 - 0.00 20.00 - 0.00
Dec-15 0.00 0.00 0.00 0.00 - 0.00 0.00 - 0.00 0.00 - 0.00
TOTAL . 0.00 0.00 100.00 0.00 0.00 0.00 100.00 0.00
A PESADA - POR MESES

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 En el informe de
0.00 0.00 0.00 0.00 preliquidacion el dia
0.00 0.00 -25.00 0.00 1 y 27 indica 15 y 10
0.00 0.00 0.00 0.00 galones
respectivamente.
Ese dato no se
encuentra en los
partes diarios.
En el informe de
preliquidacion el dia
1 y 27 indica 15 y 10
galones
respectivamente.
0.00 0.00 0.00 0.00 Ese dato no se
0.00 0.00 0.00 0.00 encuentra en los
0.00 0.00 0.00 0.00 partes diarios.
0.00 0.00 0.00 0.00
0.00 0.00 -25.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 En el informe de
0.00 0.00 0.00 0.00 preliquidacion el dia 17
0.00 0.00 -5.00 0.00 indica 5 galones. Ese
0.00 0.00 0.00 0.00 dato no se encuentra en
los partes diarios.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 -5.00 0.00
DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
En el informe de
0.00 0.00 0.00 0.00 preliquidacion el dia 16
0.00 0.00 -30.00 0.00 indica 30 galones. Este
0.00 0.00 0.00 0.00 dato no se encuentra
0.00 0.00 0.00 0.00 en los partes diarios.
preliquidacion el dia 16
indica 30 galones. Este
dato no se encuentra
en los partes diarios.
0.00 0.00 0.00 0.00
0.00 0.00 -30.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
En el informe de
0.00 0.00 0.00 0.00 preliquidacion el dia 15
0.00 0.00 -30.00 0.00 indica 30 galones, ese
0.00 0.00 0.00 0.00 dato no se encuentra
0.00 0.00 0.00 0.00 en los partes diarios.
0.00 0.00 -30.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
GOBIERNO REGIONAL
Programa Regional de Riego y Drenaje
PRORRIDRE
OFICINA DE LIQUIDACION DE
INFORME DE EQUIPO
OBRAS DE MAQUINARIA PESADA

PROPIETARIO : GOBIERNO REGIONAL PUNO

EQUIPOS LIQUIDACION PRE LIQUIDACION PRE LIQ. VS LIQUIDACION


HM COSTO S/. HM COSTO S/. HM
VOLQUETE MACK PLACA: Z1J 862 - GRP 785.17 0.00 785.17 0.00 0.00
VOLQUETE MACK PLACA: Z1I 839 - GRP 10.67 0.00 10.67 0.00 0.00
VOLQUETE INTERNATIONAL PLACA: Z1S 858 - 752.63 0.00 752.63 0.00 0.00
VOLQUETE INTERNATIONAL PLACA: Z1I 902 - 622.90 0.00 622.90 0.00 0.00
MOTONIVELADORA CAT 140 K - GRP 644.88 96,732.50 644.88 96,732.50 0.00
EXCAVADORA KOLBELCO CS 350 - GRP 490.35 0.00 490.35 0.00 0.00
CAMA BAJA 0.00 0.00 0.00 0.00 0.00
TOTAL 3,306.60 96,732.50 3,306.60 96,732.50 0.00
DA

VS LIQUIDACION OBSERVACIONES
COSTO S/.
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
GOBIERNO REGIONAL
Programa Regional de Riego y Drenaje
PRORRIDRE
OFICINA DE LIQUIDACION DE OBRAS
INFORME DE EQUIPO DE MAQUINARIA PESADA

PROPIETARIO :AMDIL

CARGADOR FRONTAL VOLVO L150C


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Jun-15 57.77 130.00 7,509.67 295.00 - 0.00 57.77 130.00 7,509.67 295.00 - 0.00
Jul-15 79.95 130.00 10,393.50 420.00 - 0.00 79.95 130.00 10,393.50 420.00 - 0.00
TOTAL . 137.72 17,903.17 715.00 0.00 137.72 17,903.17 715.00 0.00

VOLQUETE FMX 440 DOY-861


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Jun-15 32.67 100.00 3,266.67 120.00 - 0.00 32.67 100.00 3,266.67 120.00 - 0.00
Jul-15 55.83 100.00 5,583.33 170.00 - 0.00 55.83 100.00 5,583.33 170.00 - 0.00
TOTAL . 88.50 8,850.00 290.00 0.00 88.50 8,850.00 290.00 0.00

VOLQUETE FMX 440 V5B-789


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Jun-15 31.55 100.00 3,155.00 110.00 - 0.00 31.55 100.00 3,155.00 110.00 - 0.00
Jul-15 19.83 100.00 1,983.33 65.00 - 0.00 19.83 100.00 1,983.33 65.00 - 0.00
TOTAL . 51.38 5,138.33 175.00 0.00 51.38 5,138.33 175.00 0.00

EXCAVADORA CAT 325B


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Jun-15 7.92 220.00 1,741.67 60.00 - 0.00 7.92 220.00 1,741.67 60.00 - 0.00
Jul-15 211.83 220.00 46,603.33 1,360.00 - 0.00 211.83 220.00 46,603.33 1,360.00 - 0.00
Aug-15 195.70 220.00 43,054.00 1,240.00 - 0.00 195.70 220.00 43,054.00 1,240.00 - 0.00
Sep-15 122.78 220.00 27,012.33 815.00 - 0.00 122.78 220.00 27,012.33 815.00 - 0.00
Oct-15 70.32 220.00 15,469.67 690.00 - 0.00 70.32 220.00 15,469.67 690.00 - 0.00
Nov-15 142.92 220.00 31,441.67 850.00 - 0.00 142.92 220.00 31,441.67 850.00 - 0.00
Dec-15 35.72 220.00 7,857.67 215.00 - 0.00 35.72 220.00 7,857.67 215.00 - 0.00
TOTAL . 178.63 39,299.33 1,065.00 0.00 178.63 39,299.33 1,065.00 0.00

VOLQUETE VOLVO D70-702


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Jul-15 111.97 100.00 11,196.67 340.00 - 0.00 111.97 100.00 11,196.67 340.00 - 0.00
Aug-15 174.25 100.00 17,425.00 550.00 - 0.00 174.25 100.00 17,425.00 550.00 - 0.00
Sep-15 93.08 100.00 9,308.33 315.00 - 0.00 93.08 100.00 9,308.33 315.00 - 0.00
Oct-15 70.53 100.00 7,053.33 225.00 - 0.00 75.93 100.00 7,593.33 245.00 - 0.00
Nov-15 16.72 100.00 1,671.67 50.00 - 0.00 16.72 100.00 1,671.67 50.00 - 0.00
TOTAL . 466.55 46,655.00 1,480.00 0.00 471.95 47,195.00 1,500.00 0.00

VOLQUETE VOLVO Z3P - 766


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Jul-15 71.98 100.00 7,198.33 240.00 - 0.00 71.98 100.00 7,198.33 240.00 - 0.00
Aug-15 154.88 100.00 15,488.33 485.00 - 0.00 154.88 100.00 15,488.33 505.00 - 0.00
Sep-15 35.77 100.00 3,576.67 140.00 - 0.00 35.77 100.00 3,576.67 140.00 - 0.00
TOTAL . 262.63 26,263.33 865.00 0.00 262.63 26,263.33 885.00 0.00

CARGADOR FRONTAL VOLVO L150E


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Jul-15 97.48 130.00 12,672.83 535.00 - 0.00 97.48 130.00 12,672.83 535.00 - 0.00
Aug-15 156.25 130.00 20,312.50 840.00 - 0.00 156.25 130.00 20,312.50 840.00 - 0.00
Sep-15 111.33 130.00 14,473.33 570.00 - 0.00 111.33 130.00 14,473.33 570.00 - 0.00
Oct-15 74.87 130.00 9,732.67 660.00 - 0.00 74.87 130.00 9,732.67 660.00 - 0.00
TOTAL . 439.93 57,191.33 2,605.00 0.00 439.93 57,191.33 2,605.00 0.00

RODILLO LISO VIBRATORIO VM 115


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Jul-15 6.70 130.00 871.00 30.00 - 0.00 6.70 130.00 871.00 30.00 - 0.00
Aug-15 144.32 130.00 18,761.17 460.00 - 0.00 144.32 130.00 18,761.17 460.00 - 0.00
Sep-15 62.47 130.00 8,120.67 193.00 - 0.00 62.47 130.00 8,120.67 193.00 - 0.00
Oct-15 75.98 130.00 9,877.83 275.00 - 0.00 75.98 130.00 9,877.83 275.00 - 0.00
Nov-15 15.18 130.00 1,973.83 50.00 - 0.00 15.18 130.00 1,973.83 50.00 - 0.00
TOTAL . 304.65 39,604.50 1,008.00 0.00 304.65 39,604.50 1,008.00 0.00

MOTONIVELADORA CAT 140H


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Jul-15 11.33 140.00 1,586.67 50.00 - 0.00 11.33 140.00 1,586.67 50.00 - 0.00
Aug-15 3.75 140.00 525.00 35.00 - 0.00 3.75 140.00 525.00 35.00 - 0.00
TOTAL . 15.08 2,111.67 85.00 0.00 15.08 2,111.67 85.00 0.00

VOLQUETE MERCEDES BENZ XU - 3279


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Jul-15 7.50 100.00 750.00 20.00 - 0.00 7.50 100.00 750.00 20.00 - 0.00
Aug-15 143.63 100.00 14,363.33 435.00 - 0.00 143.63 100.00 14,363.33 445.00 - 0.00
Sep-15 72.22 100.00 7,221.67 220.00 - 0.00 72.22 100.00 7,221.67 220.00 - 0.00
TOTAL . 72.22 7,221.67 220.00 0.00 72.22 7,221.67 220.00 0.00

CISTERNA VOLVO F10 PLACA: Z2W - 810


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/.
Aug-15 118.77 100.00 11,876.67 280.00 - 0.00 118.77 100.00 11,876.67 280.00 - 0.00
Sep-15 146.30 100.00 14,630.00 240.00 - 0.00 146.30 100.00 14,630.00 240.00 - 0.00
Oct-15 67.67 100.00 6,766.67 180.00 - 0.00 67.67 100.00 6,766.67 180.00 - 0.00
Nov-15 49.97 100.00 4,996.67 135.00 - 0.00 49.97 100.00 4,996.67 135.00 - 0.00
Dec-15 57.88 100.00 5,788.33 145.00 - 0.00 57.88 100.00 5,788.33 145.00 - 0.00
TOTAL . 440.58 44,058.33 980.00 0.00 440.58 44,058.33 980.00 0.00
A PESADA - POR MESES

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00

DIFERENCIA OBSERVACIONES
EQUIPOS COMBUSTIBLES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00 En el informe de
0.00 0.00 0.00 0.00 preliquidacion el dia 2
0.00 0.00 0.00 0.00 indica 5.40 horas y 20
galones. Esos datos no
-5.40 -540.00 -20.00 0.00 se encuentran en los
0.00 0.00 0.00 0.00 partes diarios.
-5.40 -540.00 -20.00 0.00

DIFERENCIA OBSERVACIONES
EQUIPOS COMBUSTIBLES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00 En el informe de
0.00 0.00 -20.00 0.00 preliquidacion el dia 2
indica 20 galones. Ese
0.00 0.00 0.00 0.00 dato no se encuentra en
0.00 0.00 -20.00 0.00 el parte diario.

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00

DIFERENCIA
OBSERVACIONES
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00 En el informe de
0.00 0.00 -10.00 0.00 preliquidacion el dia 8 indica
0.00 0.00 0.00 0.00 10 galones, ese dato no
existe en los partes diarios.
0.00 0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
OBSERVACIONES
HM PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
GOBIERNO REGIONAL
Programa Regional de Riego y Drenaje
PRORRIDRE
OFICINA DE LIQUIDACION DE
INFORME DE EQUIPO DE MAQUINARIA PESADA
OBRAS

PROPIETARIO : AMDIL

EQUIPOS LIQUIDACION PRE LIQUIDACION


HM COSTO S/. HM COSTO S/.
CARGADOR FRONTAL VOLVO L150C 137.72 17,903.17 137.72 17,903.17
VOLQUETE FMX 440 DOY-861 88.50 8,850.00 88.50 8,850.00
VOLQUETE FMX 440 V5B-789 51.38 5,138.33 51.38 5,138.33
EXCAVADORA CAT 325B 178.63 39,299.33 178.63 39,299.33
VOLQUETE VOLVO D70-702 466.55 46,655.00 471.95 47,195.00
VOLQUETE VOLVO Z3P - 766 262.63 26,263.33 262.63 26,263.33
CARGADOR FRONTAL VOLVO L150E 439.93 57,191.33 439.93 57,191.33
RODILLO LISO VIBRATORIO VM 115 304.65 39,604.50 304.65 39,604.50
MOTONIVELADORA CAT 140H 15.08 2,111.67 15.08 2,111.67
VOLQUETE MERCEDES BENZ XU - 3279 72.22 7,221.67 72.22 7,221.67
CISTERNA VOLVO F10 PLACA: Z2W - 810 440.58 44,058.33 440.58 44,058.33
TOTAL 2,457.88 294,296.67 1,190.82 144,649.17
GIONAL
iego y Drenaje
RE
DACION DE
INARIA PESADA

PRE LIQ. VS LIQUIDACION OBSERVACIONES


HM COSTO S/.
0.00 0.00
0.00 0.00 En el mes de
0.00 0.00 octubre indica
5.40 horas,
0.00 0.00
Esos datos no
-5.40 -540.00 se encuentran
0.00 0.00 en los partes
0.00 0.00 diarios.
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
1,267.07 ###
GOBIERNO REGIONAL
Programa Regional de Riego y Drenaje
PRORRIDRE
OFICINA DE LIQUIDACION DE OBRAS

INFORME DE EQUIPO DE MAQUINARIA PE

PROPIETARIO : ALQUILADO

CAMION CUSTER FORLAND PLACA: Z5Y-921


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD
Mar-15 32.00 25.01 800.22 10.00 - 0.00 48.00 25.01 1,200.34 10.00
Apr-15 176.00 25.01 4,401.23 55.00 - 0.00 176.00 25.01 4,401.23 55.00
May-15 200.00 25.01 5,001.40 90.00 - 0.00 200.00 25.01 5,001.40 90.00
Jun-15 200.00 25.01 5,001.40 100.00 - 0.00 200.00 25.01 5,001.40 100.00
Jul-15 200.00 25.01 5,001.40 90.00 - 0.00 200.00 25.01 5,001.40 100.00
Aug-15 216.00 25.01 5,401.51 125.00 - 0.00 216.00 25.01 5,401.51 125.00
Sep-15 208.00 25.01 5,201.46 115.00 - 0.00 208.00 25.01 5,201.46 115.00
Oct-15 208.00 25.01 5,201.46 135.00 - 0.00 208.00 25.01 5,201.46 135.00
Nov-15 192.00 25.01 4,801.34 0.00 - 0.00 192.00 25.01 4,801.34 0.00
Dec-15 194.23 25.01 4,857.19 0.00 - 0.00 194.23 25.01 4,857.19 0.00
Jan-16 200.78 25.01 5,020.99 0.00 - 0.00 200.78 25.01 5,020.99 0.00
Apr-16 78.93 25.01 1,973.89 0.00 - 0.00 78.93 25.01 1,973.89 0.00
May-16 94.02 25.01 2,351.17 0.00 - 0.00 94.02 25.01 2,351.17 0.00
TOTAL . 2,199.97 55,014.66 720.00 0.00 2,215.97 55,414.77 730.00

CAMION FUSO MITSUBISHI PLACA: Z5Q-710


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD
Jun-15 200.00 25.01 5,001.40 105.00 - 0.00 200.00 25.01 5,001.40 105.00
Jul-15 200.00 25.01 5,001.40 110.00 - 0.00 200.00 25.01 5,001.40 132.00
Aug-15 216.00 25.01 5,401.51 126.00 - 0.00 216.00 25.01 5,401.51 126.00
Sep-15 208.00 25.01 5,201.46 115.00 - 0.00 208.00 25.01 5,201.46 115.00
Oct-15 208.00 25.01 5,201.46 140.00 - 0.00 208.00 25.01 5,201.46 140.00
Nov-15 192.00 25.01 4,801.34 0.00 - 0.00 192.00 25.01 4,801.34 0.00
Dec-15 194.75 25.01 4,870.11 0.00 - 0.00 194.88 25.01 4,873.45 0.00
Jan-16 199.77 25.01 4,995.57 0.00 - 0.00 199.77 25.01 4,995.57 0.00
Apr-16 80.32 25.01 2,008.48 0.00 - 0.00 80.32 25.01 2,008.48 0.00
TOTAL . 1,698.83 42,482.73 596.00 0.00 1,698.97 42,486.06 618.00

CAMIONETA HILUX C3K - 804 SUPERVISION


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD
Aug-15 0.00 0.00 0.00 35.00 - 0.00 0.00 - 0.00 35.00
Sep-15 0.00 0.00 0.00 135.00 - 0.00 0.00 - 0.00 135.00
Oct-15 0.00 0.00 0.00 105.00 - 0.00 0.00 - 0.00 105.00
Nov-15 0.00 0.00 0.00 80.00 - 0.00 0.00 - 0.00 100.00
Dec-15 0.00 0.00 0.00 90.00 - 0.00 0.00 - 0.00 90.00
Jan-16 0.00 0.00 0.00 30.00 - 0.00 0.00 - 0.00 30.00
TOTAL . 0.00 0.00 475.00 0.00 0.00 0.00 495.00

CAMION HYUNDAI HD 65 PLACA: Z4M-847


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD
Nov-15 192.00 25.01 4,801.34 0.00 - 0.00 192.00 25.01 4,801.34 0.00
Dec-15 188.48 25.01 4,713.40 0.00 - 0.00 188.48 25.01 4,713.40 0.00
Jan-16 156.78 25.01 3,920.68 0.00 - 0.00 156.78 25.01 3,920.68 0.00
TOTAL . 537.27 13,435.43 0.00 0.00 537.27 13,435.43 0.00

CAMION BAW INCAPOWER B40 PLACA: Z4D-839


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD
Nov-15 192.00 25.01 4,801.34 0.00 - 0.00 192.00 25.01 4,801.34 0.00
Dec-15 187.43 25.01 4,687.15 0.00 - 0.00 187.43 25.01 4,687.15 0.00
Jan-16 157.63 25.01 3,941.94 0.00 - 0.00 157.63 25.01 3,941.94 0.00
TOTAL . 537.07 13,430.43 0.00 0.00 537.07 13,430.43 0.00

CISTERNA VOLVO N1O PLACA: V3R-804


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD
Dec-15 54.38 98.00 5,329.57 135.00 - 0.00 54.38 98.00 5,329.57 135.00
Jan-16 145.38 98.00 14,247.57 315.00 - 0.00 145.38 98.00 14,247.57 330.00
Feb-16 39.23 98.00 3,844.87 95.00 - 0.00 39.23 98.00 3,844.87 95.00
TOTAL . 239.00 23,422.00 545.00 0.00 239.00 23,422.00 560.00

CAMIONETA HILUX AHM-904 SUPERVISION


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD
Jan-16 0.00 0.00 0.00 50.00 - 0.00 0.00 - 0.00 50.00
Feb-16 0.00 0.00 0.00 60.00 - 0.00 0.00 - 0.00 60.00
TOTAL . 0.00 0.00 110.00 0.00 0.00 0.00 110.00

CISTERNA N3 CITOTRUX PLACA: COX - 764


INFORME LIQUIDACION INFORME PRE-LIQUIDACION
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD
Mar-16 156.77 108.80 17,056.21 350.00 - 0.00 156.77 108.80 17,056.21 350.00
Apr-16 114.00 108.80 12,403.20 265.00 - 0.00 114.00 108.80 12,403.20 265.00
TOTAL . 270.77 29,459.41 615.00 0.00 270.77 29,459.41 615.00
NAL
y Drenaje

N DE OBRAS

INARIA PESADA - POR MESES

LIQUIDACION DIFERENCIA
COMBUSTIBLES EQUIPOS COMBUSTIBLES OBSERVACIONES
C.U. PARCIAL S/. HM PARCIAL S/. CANTIDAD PARCIAL S/.
- 0.00 -16.00 -400.11 0.00 0.00 En el informe de
- 0.00 0.00 0.00 0.00 0.00 preliquidacion el resultado
- 0.00 0.00 0.00 0.00 0.00 de las horas maquina esta
- 0.00 0.00 0.00 0.00 0.00 incrementado 16 horas.
- 0.00 0.00 0.00 -10.00 0.00 En el informe de
- 0.00 0.00 0.00 0.00 0.00 preliquidacion los dias
- 0.00 0.00 0.00 0.00 0.00 21, 30, 31 indican 5,5,5
galones
respectivamente, ese
dato no se encuentra en
los partes diarios. El dia
En el informe de
preliquidacion los dias
21, 30, 31 indican 5,5,5
galones
- 0.00 0.00 0.00 0.00 0.00
respectivamente, ese
- 0.00 0.00 0.00 0.00 0.00 dato no se encuentra en
- 0.00 0.00 0.00 0.00 0.00 los partes diarios. El dia
- 0.00 0.00 0.00 0.00 0.00 15 no se considero 5
- 0.00 0.00 0.00 0.00 0.00 galones.
- 0.00 0.00 0.00 0.00 0.00
0.00 -16.00 -400.11 -10.00 0.00

LIQUIDACION DIFERENCIA
COMBUSTIBLES EQUIPOS COMBUSTIBLES OBSERVACIONES
C.U. PARCIAL S/. HM PARCIAL S/. CANTIDAD PARCIAL S/.
- 0.00 0.00 0.00 0.00 0.00 En el informe de
- 0.00 0.00 0.00 -22.00 0.00 preliquidacion se incremento
- 0.00 0.00 0.00 0.00 0.00 el dia 9 con 5 galones, de
- 0.00 0.00 0.00 0.00 0.00 los dias 27, 30, 31 no existen
en el parte diario 7, 5, 5
- 0.00 0.00 0.00 0.00 0.00 galones respectivamente.
- 0.00 0.00 0.00 0.00 0.00
- 0.00 -0.13 -3.33 0.00 0.00 En el informe de
- 0.00 0.00 0.00 0.00 0.00 preliquidacion el dia 24 se
incremento 0.13 horas.
- 0.00 0.00 0.00 0.00 0.00
0.00 -0.13 -3.33 -22.00 0.00

LIQUIDACION DIFERENCIA
COMBUSTIBLES EQUIPOS COMBUSTIBLES OBSERVACIONES
C.U. PARCIAL S/. HM PARCIAL S/. CANTIDAD PARCIAL S/.
- 0.00 0.00 0.00 0.00 0.00
En el informe de
- 0.00 0.00 0.00 0.00 0.00
preliquidacion los dias
27 y 30 se aument 10
y 10 galones
respectivamente.
En el informe de
preliquidacion los dias
- 0.00 0.00 0.00 0.00 0.00 27 y 30 se aument 10
- 0.00 0.00 0.00 -20.00 0.00 y 10 galones
- 0.00 0.00 0.00 0.00 0.00 respectivamente.
- 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 -20.00 0.00

LIQUIDACION DIFERENCIA
COMBUSTIBLES EQUIPOS COMBUSTIBLES OBSERVACIONES
C.U. PARCIAL S/. HM PARCIAL S/. CANTIDAD PARCIAL S/.
- 0.00 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00

LIQUIDACION DIFERENCIA
COMBUSTIBLES EQUIPOS COMBUSTIBLES OBSERVACIONES
C.U. PARCIAL S/. HM PARCIAL S/. CANTIDAD PARCIAL S/.
- 0.00 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00

LIQUIDACION DIFERENCIA
COMBUSTIBLES EQUIPOS COMBUSTIBLES OBSERVACIONES
C.U. PARCIAL S/. HM PARCIAL S/. CANTIDAD PARCIAL S/.
- 0.00 0.00 0.00 0.00 0.00 En el informe de
preliquidacion el dia 30
indica 15 galones. Ese dato
no existe en el parte diario.
En el informe de
- 0.00 0.00 0.00 -15.00 0.00 preliquidacion el dia 30
- 0.00 0.00 0.00 0.00 0.00 indica 15 galones. Ese dato
0.00 0.00 0.00 -15.00 0.00 no existe en el parte diario.

LIQUIDACION DIFERENCIA
COMBUSTIBLES EQUIPOS COMBUSTIBLES OBSERVACIONES
C.U. PARCIAL S/. HM PARCIAL S/. CANTIDAD PARCIAL S/.
- 0.00 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00

LIQUIDACION DIFERENCIA
COMBUSTIBLES EQUIPOS COMBUSTIBLES OBSERVACIONES
C.U. PARCIAL S/. HM PARCIAL S/. CANTIDAD PARCIAL S/.
- 0.00 0.00 0.00 0.00 0.00
- 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
GOBIERNO REGIONAL
Programa Regional de Riego y Drenaje
PRORRIDRE
OFICINA DE LIQUIDACION DE OBR
INFORME DE EQUIPO DE MAQUINARIA PES

PROPIETARIO : ALQUILADO

EQUIPOS LIQUIDACION PRE LIQUIDACION


HM COSTO S/. HM
CAMION CUSTER FORLAND PLACA: Z5Y-921 2,199.97 55,014.66 2,215.97
CAMION FUSO MITSUBISHI PLACA: Z5Q-710 1,698.83 42,482.73 1,698.97
CAMIONETA HILUX C3K - 804 SUPERVISION 0.00 0.00 0.00
CAMION HYUNDAI HD 65 PLACA: Z4M-847 537.27 13,435.43 537.27
CAMION BAW INCAPOWER B40 PLACA: Z4D-83 537.07 13,430.43 537.07
CISTERNA VOLVO N1O PLACA: V3R-804 239.00 23,422.00 239.00
CAMIONETA HILUX AHM-904 SUPERVISION 0.00 0.00 0.00
CISTERNA N3 CITOTRUX PLACA: COX - 764 270.77 29,459.41 270.77
TOTAL 5,482.90 177,244.65 5,499.04
O REGIONAL
l de Riego y Drenaje
RIDRE
IDACION DE OBRAS
IPO DE MAQUINARIA PESADA

PRE LIQUIDACION PRE LIQ. VS LIQUIDACION OBSERVACIONES


COSTO S/. HM COSTO S/.
55,414.77 -16.00 -400.11 En marzo 2015 del informe de
42,486.06 -0.13 -3.33 preliquidacion el resultado de
0.00 0.00 0.00 las horas maquina esta
13,435.43 0.00 0.00 incrementado 16 horas.
13,430.43 0.00 0.00 En dic 2015 del informe
23,422.00 0.00 0.00 de preliquidacion el dia 24
0.00 0.00 0.00 se incremento 0.13 horas.
29,459.41 0.00 0.00
177,648.10 -16.13 -403.45
GOBIERNO REGIONAL
Programa Regional de Riego y Drenaje
PRORRIDRE
OFICINA DE LIQUIDACION DE OBRAS

INFORME DE EQUIPO DE MAQUINARIA PESADA - POR M

PROPIETARIO :POR LICITACION

MOTONIVELADORA CAT 140H


INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Sep-15 51.07 194.76 9,945.97 0.00 - 0.00 51.07 194.76 9,945.97 0.00 - 0.00 0.00
Oct-15 188.07 194.76 36,628.69 0.00 - 0.00 188.07 194.76 36,628.69 0.00 - 0.00 0.00
Nov-15 160.37 194.76 31,233.72 0.00 - 0.00 160.28 194.76 31,217.49 0.00 - 0.00 0.08
Dec-15 78.09 194.76 15,209.31 0.00 - 0.00 78.09 194.76 15,209.31 0.00 - 0.00 0.00
May-16 24.83 194.76 4,836.65 0.00 - 0.00 24.83 194.76 4,836.65 0.00 - 0.00 0.00
TOTAL . 502.42 97,854.34 0.00 0.00 502.34 97,838.11 0.00 0.00 0.08
CARGADOR FRONTAL LONKING CDM856E
INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Oct-15 8.15 185.00 1,507.75 0.00 - 0.00 8.15 185.00 1,507.75 0.00 - 0.00 0.00
Nov-15 56.38 185.00 10,430.92 0.00 - 0.00 56.38 185.00 10,430.92 0.00 - 0.00 0.00
Dec-15 21.48 185.00 3,974.42 0.00 - 0.00 21.48 185.00 3,974.42 0.00 - 0.00 0.00
TOTAL . 86.02 15,913.08 0.00 0.00 86.02 15,913.08 0.00 0.00 0.00

VOLQUETE VOLVO PLACA: D6C-734


INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Dec-15 195.78 126.50 24,766.59 0.00 - 0.00 195.78 126.50 24,766.59 0.00 - 0.00 0.00
Jan-16 151.67 126.50 19,185.83 0.00 - 0.00 151.67 126.50 19,185.83 0.00 - 0.00 0.00
Feb-16 25.50 126.50 3,225.75 0.00 - 0.00 25.50 126.50 3,225.75 0.00 - 0.00 0.00
Apr-16 63.52 126.50 8,034.86 0.00 - 0.00 63.52 126.50 8,034.86 0.00 - 0.00 0.00
TOTAL . 436.47 55,213.03 0.00 0.00 436.47 55,213.03 0.00 0.00 0.00
VOLQUETE VOLVO PLACA: B5Z - 708
INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Dec-15 197.93 126.50 25,038.57 0.00 - 0.00 197.93 126.50 25,038.57 0.00 - 0.00 0.00
Jan-16 153.32 126.50 19,394.56 0.00 - 0.00 153.32 126.50 19,394.56 0.00 - 0.00 0.00
Feb-16 21.07 126.50 2,664.93 0.00 - 0.00 21.07 126.50 2,664.93 0.00 - 0.00 0.00
Apr-16 69.35 126.50 8,772.78 0.00 - 0.00 69.35 126.50 8,772.78 0.00 - 0.00 0.00
TOTAL . 441.67 55,870.83 0.00 0.00 441.67 55,870.83 0.00 0.00 0.00

VOLQUETE VOLVO PLACA: C4D-931


INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Dec-15 196.48 126.50 24,855.14 0.00 - 0.00 195.98 126.50 24,791.89 0.00 - 0.00 0.50
Jan-16 152.72 126.50 19,318.66 0.00 - 0.00 152.72 126.50 19,318.66 0.00 - 0.00 0.00
Feb-16 2.52 126.50 318.36 0.00 - 0.00 2.52 126.50 318.36 0.00 - 0.00 0.00
Mar-16 59.07 126.50 7,471.93 0.00 - 0.00 0.00 126.50 0.00 0.00 - 0.00 59.07
Apr-16 68.90 126.50 8,715.85 0.00 - 0.00 68.90 126.50 8,715.85 0.00 - 0.00 0.00
TOTAL . 479.68 60,679.94 0.00 0.00 420.12 53,144.76 0.00 0.00 59.57

VOLQUETE VOLVO PLACA: C7C-894


INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Dec-15 196.48 126.50 24,855.14 0.00 - 0.00 196.48 126.50 24,855.14 0.00 - 0.00 0.00
Jan-16 154.00 126.50 19,481.00 0.00 - 0.00 154.00 126.50 19,481.00 0.00 - 0.00 0.00
Feb-16 22.60 126.50 2,858.90 0.00 - 0.00 22.60 126.50 2,858.90 0.00 - 0.00 0.00
Mar-16 23.62 126.50 2,987.51 0.00 - 0.00 23.62 126.50 2,987.51 0.00 - 0.00 0.00
Apr-16 68.64 126.50 8,682.93 0.00 - 0.00 68.64 126.50 8,682.93 0.00 - 0.00 0.00
TOTAL . 465.34 58,865.48 0.00 0.00 465.34 58,865.48 0.00 0.00 0.00

VOLQUETE VOLVO PLACA: DOU-778


INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Dec-15 195.70 126.50 24,756.05 0.00 - 0.00 195.70 126.50 24,756.05 0.00 - 0.00 0.00
TOTAL . 195.70 24,756.05 0.00 0.00 195.70 24,756.05 0.00 0.00 0.00

VOLQUETE VOLVO PLACA V2S - 799


INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Dec-15 196.28 126.50 24,829.84 0.00 - 0.00 196.28 126.50 24,829.84 0.00 - 0.00 0.00
Jan-16 155.28 126.50 19,643.34 0.00 - 0.00 155.28 126.50 19,643.34 0.00 - 0.00 0.00
TOTAL . 351.57 44,473.18 0.00 0.00 351.57 44,473.18 0.00 0.00 0.00

VOLQUETE VOLVO PLACA Z5I - 730


INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Dec-15 198.17 126.50 25,068.08 0.00 - 0.00 198.17 126.50 25,068.08 0.00 - 0.00 0.00
TOTAL . 198.17 25,068.08 0.00 0.00 198.17 25,068.08 0.00 0.00 0.00

VOLQUETE VOLVO PLACA - YP 1209


INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Dec-15 197.87 126.50 25,030.13 0.00 - 0.00 197.87 126.50 25,030.13 0.00 - 0.00 0.00
TOTAL . 197.87 25,030.13 0.00 0.00 197.87 25,030.13 0.00 0.00 0.00

VOLQUETE VOLVO FM - PLACA V2Z 752


INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Dec-15 199.03 126.50 25,177.72 0.00 - 0.00 199.03 126.50 25,177.72 0.00 - 0.00 0.00
TOTAL . 199.03 25,177.72 0.00 0.00 199.03 25,177.72 0.00 0.00 0.00

EXCAVADORA HIDRAULICA SOBRE ORUGAS - CAT 329 DL


INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Dec-15 122.88 261.00 32,072.55 0.00 - 0.00 122.88 261.00 32,072.55 0.00 - 0.00 0.00
Jan-16 153.48 261.00 40,059.15 0.00 - 0.00 153.48 261.00 40,059.15 0.00 - 0.00 0.00
Feb-16 53.67 261.00 14,007.00 0.00 - 0.00 53.67 261.00 14,007.00 0.00 - 0.00 0.00
Mar-16 67.87 261.00 17,713.20 0.00 - 0.00 67.87 261.00 17,713.20 0.00 - 0.00 0.00
Apr-16 36.63 261.00 9,561.30 0.00 - 0.00 36.63 261.00 9,561.30 0.00 - 0.00 0.00
May-16 5.00 261.00 1,305.00 0.00 - 0.00 5.00 261.00 1,305.00 0.00 - 0.00 0.00
TOTAL . 439.53 114,718.20 0.00 0.00 439.53 114,718.20 0.00 0.00 0.00

EXCAVADORA HIDRAULICA SOBRE ORUGAS - VOLVO EC240


INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Dec-15 115.32 261.00 30,097.65 0.00 - 0.00 120.57 261.00 31,467.90 0.00 - 0.00 -5.25
Jan-16 155.20 261.00 40,507.20 0.00 - 0.00 155.20 261.00 40,507.20 0.00 - 0.00 0.00
TOTAL . 270.52 70,604.85 0.00 0.00 275.77 71,975.10 0.00 0.00 -5.25

EXCAVADORA HIDRAULICA SOBRE ORUGAS - CAT 330 DL


INFORME LIQUIDACION INFORME PRE-LIQUIDACION DIF
EQUIPOS COMBUSTIBLES EQUIPOS COMBUSTIBLES EQUIPOS
MESES HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM C.U. PARCIAL S/. CANTIDAD C.U. PARCIAL S/. HM
Dec-15 120.45 261.00 31,437.45 0.00 - 0.00 120.45 261.00 31,437.45 0.00 - 0.00 0.00
Jan-16 155.25 261.00 40,520.25 0.00 - 0.00 155.25 261.00 40,520.25 0.00 - 0.00 0.00
TOTAL . 275.70 71,957.70 0.00 0.00 275.70 71,957.70 0.00 0.00 0.00
A - POR MESES

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00 En el informe de
0.00 0.00 0.00 preliquidacion el
16.23 0.00 0.00 dia 5 indica 7.72
0.00 0.00 0.00 horas, lo que en
realidad es 7.80
0.00 0.00 0.00
horas.
16.23 0.00 0.00
DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
63.25 0.00 0.00
En el informe de
0.00 0.00 0.00 preliquidacion no
0.00 0.00 0.00 se ha sumado el
7,471.93 0.00 0.00 total de horas
0.00 0.00 0.00 maquina.
7,535.18 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00
0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00
0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00
0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00
0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
El dia 19 indica 5.25
-1,370.25 0.00 0.00 HM, este dato no
0.00 0.00 0.00 existe en los partes
diarios.
El dia 19 indica 5.25
HM, este dato no
existe en los partes
-1,370.25 0.00 0.00 diarios.

DIFERENCIA
EQUIPOS COMBUSTIBLES OBSERVACIONES
PARCIAL S/. CANTIDAD PARCIAL S/.
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
GOBIERNO REGIONAL
Programa Regional de Riego y Drenaje
PRORRIDRE
OFICINA DE LIQUIDACION DE
INFORME DE EQUIPO
OBRAS DE MAQUINARIA PESADA

PROPIETARIO : POR LICITACION

EQUIPOS LIQUIDACION PRE LIQUIDACION


HM COSTO S/. HM COSTO S/.
MOTONIVELADORA CAT 140H 502.42 97,854.34 502.34 97,838.11
CARGADOR FRONTAL LONKING CDM856 86.02 15,913.08 86.02 15,913.08
VOLQUETE VOLVO PLACA: D6C-734 436.47 55,213.03 436.47 55,213.03
VOLQUETE VOLVO PLACA: B5Z - 708 441.67 55,870.83 441.67 55,870.83
VOLQUETE VOLVO PLACA: C4D-931 479.68 60,679.94 420.12 53,144.76
VOLQUETE VOLVO PLACA: C7C-894 465.34 58,865.48 465.34 58,865.48
VOLQUETE VOLVO PLACA: DOU-778 195.70 24,756.05 195.70 24,756.05
VOLQUETE VOLVO PLACA V2S - 799 351.57 44,473.18 351.57 44,473.18
VOLQUETE VOLVO PLACA Z5I - 730 198.17 25,068.08 198.17 25,068.08
VOLQUETE VOLVO PLACA - YP 1209 197.87 25,030.13 197.87 25,030.13
VOLQUETE VOLVO FM - PLACA V2Z 752 199.03 25,177.72 199.03 25,177.72
EXCAVADORA HIDRAULICA SOBRE ORUGA439.53 114,718.20 439.53 114,718.20
EXCAVADORA HIDRAULICA SOBRE ORUG 270.52 70,604.85 275.77 71,975.10
EXCAVADORA HIDRAULICA SOBRE ORUGA275.70 71,957.70 275.70 71,957.70
TOTAL 4,539.68 746,182.62 4,485.28 740,001.46
EGIONAL
Riego y Drenaje
DRE
UIDACION DE
ESMAQUINARIA PESADA

PRE LIQ. VS LIQUIDACION OBSERVACIONES


HM COSTO S/.
0.08 16.23 En noviembre en el informe
0.00 0.00 de preliquidacion el dia 5
0.00 0.00 indica 7.72 horas, lo que en
0.00 0.00 realidad es 7.80 horas.
59.57 7,535.18 En marzo 2016 en el informe
0.00 0.00 de preliquidacion no se ha
0.00 0.00 sumado el total de horas
0.00 0.00 maquina.
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
En dic el dia 19 indica 5.25
-5.25 -1,370.25 HM, este dato no existe en
0.00 0.00 los partes diarios.
54.40 6,181.16
LIQUIDACION PRE LIQ. - LIQUIDACION
UNIDAD EMPRESA EQUIPO
HM PARCIAL S/. HM PARCIAL S/.
VOLQUETE - VOLVO FMX 440 PLACA: EGL - 122 1,800.50 0.00 1,784.78 0.00
PRORRIDRE
VOLQUETE VOLVO F 12 PLACA: XU - 2885 127.23 0.00 127.23 0.00
VOLQUETE MACK PLACA: Z1J 862 - GRP 785.17 0.00 785.17 0.00
VOLQUETE MACK PLACA: Z1I 839 - GRP 10.67 0.00 10.67 0.00
GRP
VOLQUETE INTERNATIONAL PLACA: Z1S 858 - 752.63 0.00 752.63 0.00
VOLQUETE INTERNATIONAL PLACA: Z1I 902 - G 622.90 0.00 622.90 0.00
VOLQUETE FMX 440 DOY-861 88.50 8,850.00 88.50 8,850.00
VOLQUETE FMX 440 V5B-789 51.38 5,138.33 51.38 5,138.33
AMDIL VOLQUETE VOLVO D70-702 466.55 46,655.00 471.95 47,195.00
VOLQUETE VOLVO Z3P - 766 262.63 26,263.33 262.63 26,263.33
VOLQUETE
VOLQUETE MERCEDES BENZ XU - 3279 72.22 7,221.67 72.22 7,221.67
VOLQUETE VOLVO PLACA: D6C-734 436.47 55,213.03 436.47 55,213.03
VOLQUETE VOLVO PLACA: B5Z - 708 441.67 55,870.83 441.67 55,870.83
VOLQUETE VOLVO PLACA: C4D-931 479.68 60,679.94 420.12 53,144.76
VOLQUETE VOLVO PLACA: C7C-894 465.34 58,865.48 465.34 58,865.48
LICITACION VOLQUETE VOLVO PLACA: DOU-778 195.70 24,756.05 195.70 24,756.05
VOLQUETE VOLVO PLACA V2S - 799 351.57 44,473.18 351.57 44,473.18
VOLQUETE VOLVO PLACA Z5I - 730 198.17 25,068.08 198.17 25,068.08
VOLQUETE VOLVO PLACA - YP 1209 197.87 25,030.13 197.87 25,030.13
VOLQUETE VOLVO FM - PLACA V2Z 752 199.03 25,177.72 199.03 25,177.72
TOTAL (HM Y VALORIZADO EN S/.) 8,005.87 469,262.78 7,935.99 462,267.60
RETROEXCAVADORA CAT 420 E 1,166.67 0.00 1,166.67 0.00
RETROEXCAVADORA PRORRIDRE
RETROEXCAVADORA CAT 420 F 278.88 0.00 278.88 0.00
TOTAL (HM Y VALORIZADO EN S/.) 1,445.55 0.00 1,445.55 0.00
PRORRIDRE RODILLO LISO VIBRATORIO CAT C5 533E 675.05 0.00 677.50 0.00
RODILLO
AMDIL RODILLO LISO VIBRATORIO VM 115 304.65 39,604.50 304.65 39,604.50
TOTAL (HM Y VALORIZADO EN S/.) 979.70 39,604.50 982.15 39,604.50
PRORRIDRE CAMIONETA HILUX PLACA: EGH 146 0.00 0.00 0.00 0.00
CAMIONETA CAMIONETA HILUX C3K - 804 SUPERVISION 0.00 0.00 0.00 0.00
ALQUILADA
CAMIONETA HILUX AHM-904 SUPERVISION 0.00 0.00 0.00 0.00
TOTAL (HM Y VALORIZADO EN S/.) 0.00 0.00 0.00 0.00
GRP MOTONIVELADORA CAT 140 K - GRP 644.88 96,732.50 644.88 96,732.50
MOTONIVELADORA AMDIL MOTONIVELADORA CAT 140H 15.08 2,111.67 15.08 2,111.67
LICITACION MOTONIVELADORA CAT 140H 502.42 97,854.34 502.34 97,838.11
TOTAL (HM Y VALORIZADO EN S/.) 1,162.39 196,698.51 1,162.31 196,682.28
GRP EXCAVADORA KOLBELCO CS 350 - GRP 490.35 0.00 490.35 0.00
AMDIL EXCAVADORA CAT 325B 178.63 39,299.33 178.63 39,299.33
EXCAVADORA EXCAVADORA HIDRAULICA SOBRE ORUGAS - CA 439.53 114,718.20 439.53 114,718.20
LICITACION EXCAVADORA HIDRAULICA SOBRE ORUGAS - V 270.52 70,604.85 275.77 71,975.10
EXCAVADORA HIDRAULICA SOBRE ORUGAS - CA 275.70 71,957.70 275.70 71,957.70
TOTAL (HM Y VALORIZADO EN S/.) 1,654.73 296,580.08 1,659.98 297,950.33
OBSERVACIONES
PROGRAMA REGIONAL DE RIEGO Y DRENAJE - PRORRIDRE
OFICINA DE LIQUIDACION DE OBRAS
INFORME DE EQUIPO DE MAQUINARIA PESADA - RESUMEN POR

OBRA:
"MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA DEL SISTEMA DE RIEGO YOCARA
DISTRITOS DE JULIACA Y CARACOTO, PROVINCIA DE SAN ROMAN, REGION PUNO-CONSTRUC

COMPARATIVO
EXPEDIENTE TECNICO LIQUIDACION PRE - LIQUIDACION
EQUIPO EXP. VS LIQUIDACION EXP VS PRELIQUIDACION
HM PARCIAL S/. HM PARCIAL S/. HM PARCIAL S/. HM PARCIAL S/. HM
VOLQUETE 7,361.57 140.00 8,005.87 469,262.78 7,935.99 462,267.60 -644.30 -469,122.78 -574.42
RETROEXCAVADORA 533.76 140.00 1,445.55 0.00 1,445.55 0.00 -911.79 140.00 -911.79
RODILLO 1,352.36 200.00 979.70 39,604.50 982.15 39,604.50 372.66 -39,404.50 370.21
CAMIONETA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
MOTONIVELADORA 1,082.94 200.00 1,162.39 196,698.51 1,162.31 196,682.28 -79.45 -196,498.51 -79.36
EXCAVADORA 16.14 320.00 1,654.73 296,580.08 1,659.98 297,950.33 -1,638.60 -296,260.08 -1,643.85
CARGADOR FRONTAL 2,334.74 200.00 663.67 91,007.58 663.67 91,007.58 1,671.07 -90,807.58 1,671.07
CISTERNA 1,561.26 135.00 950.35 96,939.75 950.35 96,939.75 610.91 -96,804.75 610.91
CAMION 1,000.40 25.00 4,973.14 124,363.24 4,989.27 124,766.68 -3,972.74 -124,338.24 -3,988.87
HORMIGONERA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
CAMA BAJA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TOTAL 15,243.18 1,360.00 19,835.40 1,314,456.44 19,789.27 1,309,218.72 -4,592.22 -1,313,096.44 -4,546.09
E - PRORRIDRE
BRAS
- RESUMEN POR HM

MA DE RIEGO YOCARA, EN LA LOCALIDAD DE YOCARA,


ON PUNO-CONSTRUCCION DEL CANAL PRONCIPAL "B"

COMPARATIVO
OBSERVACIONES
EXP VS PRELIQUIDACION LIQ. VS PRELIQUIDACION
PARCIAL S/. HM PARCIAL S/.
-462,127.60 69.88 6,995.18
140.00 0.00 0.00
-39,404.50 -2.45 0.00
0.00 0.00 0.00
-196,482.28 0.08 16.23
-297,630.33 -5.25 -1,370.25
-90,807.58 0.00 0.00
-96,804.75 0.00 0.00
-124,741.68 -16.13 -403.45
LAS MAQUINAS
0.00 0.00 0.00 NO EXISTEN EN
0.00 0.00 0.00 EL EXPEDIENTE
-1,307,858.72 -46.13 -5,237.72 TECNICO
PROGRAMA REGIONAL DE RIEGO Y DRENAJE - PRORRIDRE
OFICINA DE LIQUIDACION DE OBRAS
INFORME DE EQUIPO DE MAQUINARIA PESADA POR HM
"MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA DEL SISTEMA DE
RIEGO YOCARA, EN LA LOCALIDAD DE YOCARA, DISTRITOS DE JULIACA Y
CARACOTO, PROVINCIA DE SAN ROMAN, REGION PUNO-CONSTRUCCION DEL
CANAL PRINCIPAL "B"

LIQUIDACION
ENTIDAD HM PARCIAL S/.
PRORRIDRE 4,048.33 0.00
GRP 3,306.60 96,732.50
AMDIL 2,457.88 294,296.67
ALQUILADO 5,482.90 177,244.65
LICITACION 4,539.68 746,182.62
TOTAL 19,835.40 1,314,456.44

COMPARATIVO 19,835.40 1,314,456.44


DIFERENCIA 0.00 0.00