M E T R A D O G E N E R A L MODULO SSHH

SISTEMA DE SANEAMIENTO BASICO


PROYECTO : INSTALACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL RURAL EN LA COMUNIDAD DE VAQUERIA
DEPART. : CUSCO
PROVINCIA : LA CONVENCION
DISTRITO : OCOBAMBA
LUGAR : COMUNIDAD DE VAQUERIA
FECHA : MARZO DEL 2013

N N Dimensiones
Item NOMRE DE PARTIDAS Unid. F Parcial Total
BENEF. Vec. Largo Ancho Altura rea/Volm
10 OBRAS PROVISIONALES
10.01 TRAZO Y REPLANTEO PRELIMINAR M2 29.00 1.00 2.35 3.80 8.93 8.93 258.97
10.02 EXPLANACION DEL TERRENO (e=0.10m) M3 29.00 1.00 2.35 3.80 0.10 0.89 0.89 25.90
10.03 ELIMINACION DE MATERIAL EXCEDENTE M3 29.00 1.00 3.80 2.35 0.89 1.10 0.98 28.49
11 MOVIMIENTO DE TIERRAS
11.01 CIMENTACION SSHH
11.01.01 EXCAVACION MANUAL EN MATERIAL SUELTO M3 29.00 1.00 6.80 0.35 0.40 0.95 1.00 0.95 27.61
11.01.02 ELIMINACION DE MATERIAL EXCEDENTE M3 29.00 1.00 6.80 0.35 0.40 0.95 1.10 1.05 30.37
11.01.03 RELLENO CON MATERIAL PROPIO SELECCIONADO M3 29.00 25.90
INTERIOR MODULO SSHH Y POR DEBAJO DE PISO 1.00 3.80 2.35 0.10 0.89 0.89
11.02 SISTEMA DE DESAGUE
11.02.01 EXCAVACIONEN MANUAL ZANJA DE h=0.50, a=0.40 m ML 29.00 290.00
DE LA PILETA AL POZO PERCOLADOR DE PILETA 1.00 4.00 4.00
DEL INODORO TURCO AL POZO PERCOLADOR DE INODORO TURCO 1.00 6.00 6.00
11.03 SISTEMA DE AGUA
11.03.01 EXCAVACIONEN MANUAL ZANJA DE h=0.50, a=0.40 m ML 29.00 1.00 5.00 5.00 145.00
12 CIMIENTOS Y SOBRECIMIENTOS
12.01 CIMIENTOS
12.01.01 CIMIENTOS DE CONCRETO F'C=140 KG/CM2 + 30% PM M3 29.00 1.00 6.80 0.35 0.40 0.95 0.95 27.61
12.02 SOBRECIMIENTOS
12.02.01 SOBRECIMIENTOS DE CONCRETO F'C=140 KG/CM2 + 30% PM M3 29.00 1.00 6.60 0.15 0.40 0.40 0.40 11.48
12.02.02 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS M2 29.00 1.00 13.85 0.40 5.54 5.54 160.66
13 ALBAILERIA
13.01 MURO DE SOGA CON BLOQUETAS DE CONCRETO M2 29.00 348.58
Muro frente 1.00 2.30 1.60 3.68 3.68
Restar area de la puerta -1.00 0.70 1.60 1.12 -1.12
Muro posterior 1.00 2.30 2.00 4.60 4.60
Muro lateral 2.00 1.35 1.80 2.43 4.86
14 TARRAJEO DE MUROS
14.01 TARRAJEO INTERIOR C/IMPERM. E=1.5CM MEZCLA 1:2 M2 29.00 347.20
Muro frente + sobrecimiento 1.00 2.00 1.80 3.60 3.60
Restar area de la puerta -1.00 0.70 1.80 1.26 -1.26
Muro posterior + sobrecimiento 1.00 2.00 2.15 4.30 4.30
Muro lateral + sobrecimiento 2.00 1.35 1.98 2.67 5.33
14.02 TARRAJEO EXTERIOR E=1.5CM MEZCLA 1:2 M2 29.00 381.57
Muro frente + sobrecimiento 1.00 2.30 1.80 4.14 4.14
Restar area de la puerta -1.00 0.70 1.80 1.26 -1.26
Muro posterior + sobrecimiento 1.00 2.30 2.15 4.95 4.95
Muro lateral + sobrecimiento 2.00 1.35 1.98 2.67 5.33
15 PISOS Y VEREDAS
15.01 PISO DE CONCRETO FROTACHADO e=5.0cm M2 29.00 81.35
Interior bao (incluye confeccin in suto del inodoro turco) 1.00 2.00 1.35 2.70 2.70
Derrame puerta 1.00 0.70 0.15 0.11 0.11
15.02 VEREDA FROTACHADO Y BRUADO e=5.0cm M2 29.00 135.87
- ADYACENTE A PUERTA. 1.00 3.80 0.70 2.66 2.66
- ADYACENTE A PILETAS 1.00 1.65 0.90 1.49 1.49
- PISO DEBAJO DE LAS PILETAS 1.00 0.90 0.60 0.54 0.54
16 PINTURA
16.01 PINTADO DE MUROS M2 29.00 381.57
Muro frente + sobrecimiento 1.00 2.30 1.80 4.14 4.14
Restar area de la puerta -1.00 0.70 1.80 1.26 -1.26
Muro posterior + sobrecimiento 1.00 2.30 2.15 4.95 4.95
Muro lateral + sobrecimiento 2.00 1.35 1.98 2.67 5.33
17 COBERTURA DE SSHH
17.01 COBERTURA DE CALAMINA M2 29.00 1.00 2.80 2.40 6.72 6.720 194.88
17.02 PINTURA EN CUBIERTAS M2 29.00 1.00 2.80 2.40 6.72 6.720 194.88
18 CARPINTERIA DE MADERA
18.01 COLOCADO DE PUERTA DE MADERA 0.70m X 1.70m UND 29.00 1.00 1.00 29.00
19 SUMINISTRO E INSTALACION TUBERIAS Y ACCESORIOS PARA AGUA
19.01 INSTALACION DE TUBERIA PVC SAP C-10 1/2" ML 29.00 171.10
- Para Ducha. 1.00 1.65 1.65 1.65
- Para Pileta. 1.00 4.25 4.25 4.25
20 SUMINISTRO Y COLOCACION DE ACCESORIOS
20.01 SUMINISTRO DE ACCESORIOS UND 29.00 29.00
- Para Pileta.
codo 1/2" 90 und 5.00 5.00
valvula esferica de 1/2" und 1.00 1.00
Niple de FG 1/2"x1" und 2.00 2.00
Adapatador PVC 1/2" und 2.00 2.00
Unio Universal FG 1/2" und 2.00 2.00
Codo FG 1/2"X90 und 1.00 1.00
Llave jardinero 1/2" und 1.00 1.00

- Para Ducha.
codo pvc 1/2" 90 und 1.00 1.00
Tee 1/2" und 1.00 1.00
valvula esferica de 1/2" und 1.00 1.00
M E T R A D O G E N E R A L MODULO SSHH
SISTEMA DE SANEAMIENTO BASICO
PROYECTO : INSTALACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL RURAL EN LA COMUNIDAD DE VAQUERIA
DEPART. : CUSCO
PROVINCIA : LA CONVENCION
DISTRITO : OCOBAMBA
LUGAR : COMUNIDAD DE VAQUERIA
FECHA : MARZO DEL 2013

N N Dimensiones
Item NOMRE DE PARTIDAS Unid. F Parcial Total
BENEF. Vec. Largo Ancho Altura rea/Volm
Niple de FG 1/2"x1" und 2.00 2.00
Adapatador PVC 1/2" und 2.00 2.00
Unio Universal FG 1/2" und 2.00 2.00
Codo FG 1/2" und 1.00 1.00
Regadera PVC para ducha UND 1.00 1.00

20.02 COLOCACION DE ACCESORIOS y TUBERIA JGO 58.00


Pto de pileta PTO 1.00 1.00
Pto de ducha PTO 1.00 1.00

21 SUMINISTRO E INSTALACION TUBERIAS Y ACCESORIOS PARA DESAGE.


21.01 SUM. E INSTALACION DE TUBERIA PVC SAL 2" . ML 29.00 9.00 261.00
- Tuberia para Ducha. (Tramo ducha-pileta) 1.00 1.00 1.00 1.00
- Tuberia para Pileta (Tuberia de sumidero) 1.00 1.00 1.00 1.00
- Tramo pileta al pozo percolador 1.00 4.50 4.50 4.50
- Tuberia de ventilacion inodoro turco 1.00 2.50 2.50 2.50
21.02 SUM. E INSTALACION DE TUBERIA PVC SAL 4" ML 29.00 261.00
- Del inodoro Turco a la caja de registro 1.00 3.00 3.00 3.00
- De la Caja de registro al Pozo percolador 1.00 6.00 6.00 6.00
22 SUMINISTRO Y COLOCACION DE ACCESORIOS
22.01 SUMINISTRO DE ACCESORIOS UND 29.00 29.00
- Para inodoro Turco
TEE PVC SAL 4"X4" UND 1.00 1.00
Reduccin PVC SAL 4"X2" UND 1.00 1.00
Codo 4" 45 (entrega al pozo percolador) UND 1.00 1.00
Trampa del inodoro turco PVC SAL 4" UND 1.00 1.00
- Para ventilacion
Codo PVC SAL 2" 90 (para ventilacin) UNID 1.00 1.00
Sombrero de ventilacin 2" UNID 1.00 1.00
- Para Ducha.
Trampa PVC SAL 2" UND 1.00 1.00
Codo PVC SAL 2"X 45 UND 1.00 1.00
Sumidero de bronce de 2" UND 1.00 1.00
- Para Pileta.
Codo PVC SAL 2" 45 UND 2.00 2.00
YEE PVC SAL 2"X2" UND 1.00 1.00
Sumidero de bronce de 2" UND 1.00 1.00
22.02 COLOCACION DE ACCESORIOS Y TUBERIA JGO 116.00
Pto de pileta PTO 1.00 1.00
Pto de ducha PTO 1.00 1.00
Pto de inodoro turco PTO 1.00 1.00
Pto de salida de ventilacion PTO 1.00 1.00

23 POZO SEPTICO
23.01 TRAZO Y REPLANTEO M2 29.00 1.00 2.00 3.14 3.14 91.11
23.02 EXCAVACION MANUAL EN MATERIAL SUELTO M3 29.00 1.00 1.60 2.00 4.02 4.02 116.62
23.03 TAPA DE CONCRETO ARMADO DEL POZO SEPTICO (F'c=175Kg/cm2) M3 29.00 1.00 2.40 0.10 0.45 0.45 13.12
23.04 FILTRO DE GRAVA EN FONDO DE POZO SEPTICO M3 29.00 1.00 1.20 0.30 0.34 1.20 0.41 11.81
23.05 BROCAL DE SOPORTE (CONCRETO 1:10+30% PG) M3 29.00 1.00 6.75 0.30 0.20 0.41 0.41 11.75
23.06 ELIMINACION DE MATERIAL EXCEDENTE M3 29.00 1.00 1.60 2.00 4.02 1.3 5.23 151.60
24 CAJA DE REGISTRO
24.01 TRAZO Y REPLANTEO M2 29.00 1.00 0.80 0.50 0.40 0.40 11.60
24.02 EXCAVACION MANUAL EN MATERIAL SUELTO M3 29.00 1.00 0.80 0.50 0.50 0.20 0.20 5.80
24.03 RELLENO CON MATERIAL PROPIO M3 29.00 3.19
Volumen de la excavacion 1.00 0.80 0.50 0.50 0.20 0.20
Restar volumen de caja de registro -1.00 0.60 0.30 0.50 0.09 -0.09
24.04 CONCRETO FC= 175 Kg/cm2 M3 29.00 0.06 1.71
costados 1.00 1.80 0.05 0.50 0.05 0.05
tapa 1.00 0.60 0.30 0.05 0.01 0.01
fondo 1.00 0.50 0.20 0.05 0.01 0.01
24.05 ENCOFRADO DESENCOFRADO PARA ESTRUCTURAS M2 29.00 44.37
Pared exterior 29.00 1.00 1.80 0.50 0.90 0.90
Pared interior 29.00 1.00 1.40 0.45 0.63 0.63
24.06 TARRAJEO EXTERIOR e = 1.0cm mezcla: 1:5 M2 29.00 1.00 26.10
Pared exterior 1.00 1.00 1.80 0.50 0.90 0.90
24.07 TARRAJEO INTERIOR e = 1.0cm mezcla: 1:5 M2 29.00 1.00 21.17
Pared interior 1.00 1.00 1.40 0.45 0.63 0.63
fondo 1.00 1.00 0.50 0.20 0.10 0.10
25 PILETA Y POZO PERCOLADOR DE PILETA Y DUCHA.
25.01 CONSTRUCION DE PILETA TIPO II
25.01.01 TRAZO Y REPLANTEO M2 29.00 1.00 1.65 0.60 0.99 0.99 28.71
25.01.02 EXCAVACION MANUAL EN MATERIAL SUELTO M3 29.00 1.00 2.09
Para cimiento de muros de pileta 3.00 0.60 0.20 0.20 0.02 0.07
25.01.03 CONCRETO CICLOPEO MEZCLA 1:10 M3 29.00 8.92
Pileta 0.31
Soportes de lavatorio 1.00 0.60 0.25 0.95 0.14 0.14
Soportes de lavatorio 2.00 0.60 0.25 0.55 0.08 0.17
M E T R A D O G E N E R A L MODULO SSHH
SISTEMA DE SANEAMIENTO BASICO
PROYECTO : INSTALACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL RURAL EN LA COMUNIDAD DE VAQUERIA
DEPART. : CUSCO
PROVINCIA : LA CONVENCION
DISTRITO : OCOBAMBA
LUGAR : COMUNIDAD DE VAQUERIA
FECHA : MARZO DEL 2013

N N Dimensiones
Item NOMRE DE PARTIDAS Unid. F Parcial Total
BENEF. Vec. Largo Ancho Altura rea/Volm

25.01.04 CONCRETO F'c = 175 kg/cm2 M3 29.00 0.12 3.42


Losa del fregadero 1.00 0.75 0.45 0.05 0.02 0.02
Losa del lavatorio 1.00 0.80 0.45 0.05 0.02 0.02
Muro delante 1.00 0.90 0.05 0.45 0.02 0.02
Muro lateral labatorio 2.00 0.45 0.05 0.45 0.01 0.01
Muro postrerior: e=0.10m 1.00 0.90 0.10 0.45 0.04 0.04
Muro postrerior zona de pieltas: e=0.10m 1.00 0.35 0.10 0.35 0.01 0.01

25.01.05 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS M2 29.00 3.47 100.63


Losa del fregadero 1.00 0.50 0.60 0.30 0.30
Losa del lavatorio 1.00 0.40 0.60 0.24 0.24
Muro delante 1.00 1.65 0.75 1.24 1.24
Restar are adebajo de la losa de fregadero -1.00 0.50 0.75 0.38 -0.38
Restar are adebajo de la losa de la pielta -1.00 0.40 0.35 0.14 -0.14
Muro Interior pileta 1.00 2.50 0.35 0.88 0.88
Muro posterior de pileta - parte superior 1.00 0.55 0.35 0.19 0.19
Muros de apoyo - lado exterior 2.00 0.60 0.80 0.48 0.48
Muros de apoyo - lado interior h=0.35 2.00 0.60 0.35 0.21 0.21
Muros de apoyo - lado interior h=0.75 2.00 0.60 0.75 0.45 0.45
25.01.06 ACERO DE REFUERZO F'y=4200 kg/cm2(1/4") KG 29.00 171.97
Nota: ver hoja de metrado de acero de pileta 5.93
25.01.07 TARRAJEO EXTERIOR e=1.0cm MEZCLA: 1:5 M2 29.00 1.95 56.41
Muro delante 1.00 1.65 0.80 1.32 1.32
Restar are adebajo de la losa de fregadero -1.00 0.50 0.75 0.38 -0.38
Restar are adebajo de la losa de la pielta -1.00 0.40 0.35 0.14 -0.14
Muros de apoyo - lado exterior 2.00 0.60 0.80 0.48 0.48
Muros de apoyo - lado interior h=0.35 2.00 0.60 0.35 0.21 0.21
Muros de apoyo - lado interior h=0.75 2.00 0.60 0.75 0.45 0.45
25.01.08 TARRAJEO INTERIOR C/IMPERMEABILIZANTE e=1.0cm MEZCLA: 1:5 M2 29.00 1.00 2.03 58.90
Interior lavatorio 1.00 2.50 0.35 0.88 0.88
Losa del fregadero 1.00 0.80 0.60 0.48 0.48
Losa del lavatorio 1.00 0.80 0.45 0.36 0.36
Muro posterior superior 1.00 0.35 0.35 0.12 0.12
derrames muros de ppzo de pileta. 1.00 1.35 0.05 0.07 0.07
derrames muro posterior 1.00 1.26 0.10 0.13 0.13

25.02. POZO PERCOLADOR DE PILETA Y DUCHA UND 29.00


25.02.01 TRAZO Y REPLANTEO M2 29.00 1.00 1.50 1.77 1.77 51.25
25.02.02 EXACAVACION MANUAL EN MATERIAL SUELTO M3 29.00 1.00 1.10 1.50 1.43 1.43 41.34
25.02.03 RELLENO DE GRAVA CON PIEDRA MEDIANA M3 29.00 1.00 1.10 1.50 1.43 1.20 1.71 49.61
25.02.04 ELIMINACION DE MATERIAL EXCEDENTE M4 29.00 1.00 1.10 1.50 1.43 1.30 1.85 53.74

26 EDUCACION SANITARIA.
26.01 PROGRAMA DE EDUCACION SANITARIA
26.02.01 ELABORACION DE MANUALES AFICHES Y TRIPTICOS GLB 1.00 1.00 1.00 1.00
26.02.02 ELABORACION DE UN PLAN DE EDUCACION UND 1.00 1.00 1.00 1.00
26.02.03 CHARLAS DE SENSIBILIZACION A LA POBACION UND 3.00 1.00 3.00 3.00

27 EDUCACION EN MANTENIMIENTO Y CONSERVACION AMBIENTAL


27.01 CHARLA AMBIENTAL A LA COMUNIDAD BENEFICIARIA UND 3.00 1.00 3.00 3.00
27.02 BOLETINES INFORMATIVOS UND 29.00 1.00 29.00 29.00

28 MEDIDAS DE MITIGACION
28.01 LIMPIEZA GENERAL DEL AREA AFECTADA M2 1.00 548.00 548.00
28.02 REFORESTACION EN ZONAS INTERVENIDAS Y ZONAS DESLIZABLES HA 1.00 0.50 0.50
28.03 CULTIVO DE PLANTAS RASTRERAS M2 1.00 548.00 548.00

29 MEDIDAS DE CONTROL
29.01 LETRINAS SANITARIAS UND 1.00 2.00 2.00
29.02 CLAUSURA DE LETRINAS Y CONTENEDORES M2 1.00 20.00 20.00
29.03 CONTENEDORES DE RESIDUOS SOLIDOS UND 1.00 4.00 4.00

30 SEALIZACION
30.01 SEALIZACIONES EN OBRA M 1.00 300.00 300.00
30.02 POSTE PARA SEALIZACION UND 1.00 30.00 30.00

31 FLETE
31.01 FLETE TERRESTRE GLB
1.00 1.00 1.00

31.02 FLETE RURAL GLB


1.00 1.00 1.00