You are on page 1of 2

000000Page 1 000000Evantage Energy Inc.

CANDIDATE SCREENING FORM


Evaluating UBD, MPD, AIR/MIST/AERATED/FOAM DRILLING TECHNIQUES

Well ID
Area/BU
Drlg Eng
Proj Manager
Click either 'Yes' or 'No' Columns or Give Description/Value in the next column
# Item Yes No Comments / Values / Other
1 MAIN DRIVER

a Formation Damage

b ROP Enhancement

c Loss Circulation (Please Give Value if any)

d Reservoir Production Enhancement

e Preventing HP Kicks (Gas or Water) from a given formation

f Reduction of Mud Weight

f Elimination of Casing String (Intermediate or Production)

g Hard Rock Drilling

h Wellbore stability problem

2 TOP HOLE ROCKS & RESERVOIR PROPERTIES


a Formation Name

b Lithology of the formation

c Is it Top Hole or Reservoir section drilling

d Probability of Gas or Water kick in Top/Surface Hole

e Reservoir Pressure (kpa or psi)

f Is it Fractured

g Fracture Orientation (parallel, perpendicular)

h Which is Dominated K (Matrix or Fracture Perms)

i Is the reservoir Water Wet or Oil Wet

j Any presence of Shale or Streaks of Shale

k If Yes, What % of Shale is present

l Are there any "COAL SEAMS"

m If Yes, how big are these Coal Seams

n Are there any "Channels" here

o If YES, What formations are Channeled

p Porosity () - %

q Insitu Permeability (k) - md

r Kv / Kh ratio

s Temperature, Deg C

t Please provide "STRIP LOGS" if available

3 RESERVOIR FLUIDS CHARACTERESTICS

a Type of Reservoir Fluid (Gas or Oil)

b Is It a Sweet or Sour Reservoir

c Water Saturation (Sw) - %

e GOR (m3/m3)

f OWR (m3/m3)

g if Sour, What % of H2S is there

h Any upper Sour zones where drilling would take place

i Density of the reservoir fluid (API or SG)

j Is there a Gas Cap?

k Drive Mechanism here (Solution Gas, Water Drive, Gas Cap)

l Any GOC or WOC or GWC. What is the Depth

m Distance to water layer beneath the productive Zone

n Type of rock b/w bottom of reservoir & water zone if any

4 COMPLETIONS

a Type of Completion - Tub w/Pack/ECP/Slotted Liners/other

b Usage of ESP, Sucker Rods

c Any Dual Completion in the area

d No of zones that are usually completed

e Skin due to completion (Please Give Value if any)

5 PRODUCTION HISTORY

a Is Fraccing the usual way of flowing these wells

b Please provide the Skin Value (From Transient Analysis)

c Min Production Rate Seen - Unstimulated (m3/day)

d Max Production Rate Seen - Unstimulated (m3/day)

e Min Production Rate Seen - Stimulated (m3/day)

f Max Production Rate Seen - Stimulated (m3/day)

g Formation Name which is contributing to the Flow

h Extended Flow Rate (m3/d) or the Flow during Cleanup

i Stabilised Flow Rate (m3/d)

j Value of C MMscfd/psi^2 OR m3/day/kPa^2 (*1E-03)

k Value of n (0.1 < n 1.0)

l Flowing WellHead Pressure (kPa) or Line Pressure

m Maximum Drawdown Delta P @ Sandface (kPa)

n Production Test Type (Isochronal/Multirate/Single Point)

000000Author: Hassan Malik 00000012/06/201716:23:38


000000Page 2 000000Evantage Energy Inc.

CANDIDATE SCREENING FORM


Evaluating UBD, MPD, AIR/MIST/AERATED/FOAM DRILLING TECHNIQUES

Well ID
Area/BU
Drlg Eng
Proj Manager
Click either 'Yes' or 'No' Columns or Give Description/Value in the next column
# Item Yes No Comments / Values / Other
6 WELL & DRILLSTRING DESIGN DATA (Drilling Engineer)

a Last Casing OD (in/mm) or Provide Well Stick

b Is it Vertical, Deviated or Deviated with Hz Leg at end

c Total Depth: MD (m) and TVD (m)

d Hole Size where drilling would take place

e Drill Pipe - Size (in/mm) & Wt (Kg/m)

f Drill Collars - Size (in/mm) & Wt (Kg/m)

g BHA Size (in/mm)

h Mud Type and MW (Kg/m3) to be used

i Is it a polymer mud which may breakdown downhole?

j Value for MACP/MASP (Max Allowable Casing Pressure)

k LOT value (if any)


l FIT Value and corresponding Depth in mTVD

m Type and Size of Motor Used

n No of Bit Nozzles

o Pressure Drop across the Motor (if any)

p Pressure Drop across the MWD (if any)

7 RIG SPECIFICATIONS

a BOP Specification (Level I, II, III). Is it 5K or 10K

b Clearance below the Rotary b/w Annular and RT (m)

c Rig Crew Experience in UDT (1 to 5), Level 1 - Green Hands

d Rig Pumps Capacity (Minimum and Maximum)

e DAQ system Available (Pason, TRUVU, Rig Manager) etc)

f Can Standpipe handle pressure more than 14000 kPa

Notes
1 Fill in as much information as possible
2 Information which is not relevant leave it blank
3 Any back up information will be useful to create a technology mapping

FOR EVALUATION PURPOSE (DO NOT WRITE IN THIS SPACE)

CDE Project #

UDT Ranking / Reasons


A 1 HIGH PREFERENCE
MD 2 MEDIUM PREFERENCE
AMD 3 LOW PREFERENCE
N2 4+ DO NOT CONSIDER
F
MPD
UBD

SURGERY
1 MAIN DRIVER 4 COMPLETIONS

2 TOP HOLE ROCKS & RESERVOIR CHARACTERISTICS 5 PRODUCTION HISTORY

3 RESERVOIR FLUIDS CHARACTERISTICS 7 RIG SPECIFICATIONS

CONCLUSION & RECOMMENDATIONS

GO AHEAD REJECTED
PPT PPT

Well Design Well Design

Flow Models Report

Timeline Asset Review

High Prof Rep Reasons

000000Author: Hassan Malik 00000012/06/201716:23:38