You are on page 1of 4

SECTION 500 TEMPORARY STRUCTURES

501 PRELIMINARY DESIGN the temporary structure need to be considered


when determining the structure waterway
During the preliminary design stage, the grade opening. Scour depths for the 5 year storm
and the alignment of the temporary structure shall be calculated and must be accounted for
must be established and shown on the Site in the design of the temporary bridge.
Plan. The roadway width, hydraulic design,
clearance requirements, and all other design
parameters must also be determined in The designer shall show the water surface
conjunction with the development of the elevation and velocity of the 5 year storm on
preliminary design. When the temporary the temporary structure plans. The temporary
structure can adequately be shown on the Site bridge superstructure shall clear the 5 year
Plan for the permanent bridge, a Site Plan for storm.
the temporary structure is not required. The
required Site Plan information shall be as
detailed in Section 200. A preliminary design Culvert pipes may be used in lieu of a bridge
submittal is required and the submission shall structure provided controls specified in
be made concurrently with the permanent Section 1006 of the ODOT Location and
structure preliminary design submittal. Design Manual are not exceeded for the 5 year
storm.
Provisions for pedestrian traffic on the
temporary structure shall be considered. If
warranted, sidewalks on temporary structures 502 DETAIL DESIGN
generally should be a minimum of 1200 mm
wide. Roadway width for two way traffic on
the temporary bridge is normally not less than The temporary structure detail plans shall be
7000 mm face to face of guardrail or toe to toe complete and independent of the permanent
of parapet. structure plans. The temporary structure detail
plans shall include a general elevation plan,
general notes, a table of estimated quantities,
501.1 HYDRAULICS a reinforcing steel bar list and all necessary
detail plan sheets. Provide a detailed list of
the estimated quantities with individual pay
The temporary bridge shall be designed to items for the temporary structure. Final bid
accommodate the 5 year storm. Upstream item shall be temporary structure Lump Sum.
flooding and stream velocities produced by

5-1
SECTION 500 TEMPORARY STRUCTURES - METRIC SEPTEMBER 1998

Temporary bridge structures shall be designed C. The nominal thickness of wood plank or
to withstand the same loads as the permanent strip floor shall be 75 mm minimum.
structure as defined in the current AASHTO
Standard Specifications for Highway Bridges D. Timber floors shall be securely fastened
and this Manual. These loads and forces shall to the stringers and stringers shall be
include, but not be limited to, dead load, securely fastened to the pier and
MS18 live load with impact, wind, thermal abutment caps.
effects, centrifugal effect, earth pressure,
buoyancy, ice pressure, stream current, E. When circumstances permit, all or part
longitudinal and transverse forces and erection of the existing bridge may be used for
stresses. the run-around.

For ice pressure loads, the thickness of ice F. Guardrail, posts and anchorages shall be
shall be assumed to be 150 mm, with a 1.4 designed to resist loads specified in
MPa effective ice strength. The force shall be AASHTO. Post spacing shall not exceed
assumed to act at the 5 year highwater level. 1905 mm center to center. In lieu of
guardrail, precast concrete barriers
The temporary bridge plans shall show all the (Standard Drawing PCB-91M) may be
yield and/or allowable stresses used in the used provided they are anchored
design. An increase of the allowable stresses properly to the structure.
over AASHTO requirements or this Manual is
not permitted. G. Field welded connections shall require
nondestructive testing as per 513/863.
Generally a temporary structure should be Bolted connections are preferred and
designed to be easily constructed and removed generally are more economical.
with minimal cost. The following items
should be considered when designing a H. Designs which minimize debris
temporary bridge: accumulation should be considered.

I. Shop drawings are not required.


A. Timber decks, H pile bents, and simple Adequate plan details need to be
spans are commonly used. provided.

B. Locally available lumber should be


specified. The allowable design unit 503 GENERAL NOTES
stresses of the lumber used in the design
shall be specified in the plans. State
whether timber sizes are full sawn or The designer should provide plan note(s) with
standard dressed sizes. the Temporary Structure plans similar to the
following:

5-2
SECTION 500 TEMPORARY STRUCTURES - METRIC SEPTEMBER 1998

The Contractor may substitute used or


alternate members for the members shown When 511 Class "C" is specified in the plans
on the Temporary Structure Plans, CMS 511.15 shall be waived.
provided that the members structural
adequacy is equal to or greater than the
original member. Waterway opening size The following notes shall be included in the
and required clearances are to be Structure General Notes. In the roadway plans
maintained. The Contractor shall submit the pay item description "614 Maintenance of
to the Department calculations by a Traffic" shall include an "as per Plan."
registered professional engineer showing Coordination with the roadway plans for this
the substituted member qualifies for the item is required.
substitution. Only new bolts shall be
used.
MAINTENANCE: The Contractor shall
Structural steel need not be painted. maintain all portions of the temporary
structure in good condition with regard to
For each individual project the general notes strength, safety and ridability. This shall be
and the pay item descriptions shall be included as incidental to 614 Maintenance
developed. The following instructions are of Traffic. The waterway opening shown on
provided to assist in developing the necessary the plans shall be maintained at all times. If
general notes. debris accumulates within the waterway
opening or on any part of the structure the
When 513/863 Structural Steel is specified in debris shall be promptly removed by the
the plans, only the following CMS Contractor. Removal of debris will be
descriptions shall apply: compensated for as per CMS 109.04.

Straightening 513.06/863.12 CLOSING OF THE TEMPORARY


STRUCTURE: If for any reason or at any
Holes for High-Strength and Bearing time the temporary structures ability to
Bolts 513.14/863.20 safely carry traffic is in question, the
Contractor shall be responsible for
High Strength Steel Bolts, Nuts and immediately taking the actions necessary to
Washers 513.15/863.21 protect traffic, repairing and reopening the
temporary structure. When a Contractor
Welding 513.17/863.23 closes a temporary structure he shall
immediately notify the Engineer and the
Nondestructive Testing 513.21/863.27 appropriate law enforcement agency. Water
elevations exceeding the 5 year highwater
Shipping, Storage and Erection elevation or an excessive accumulation of
513.22/863.28 debris within the waterway opening shall

5-3
SECTION 500 TEMPORARY STRUCTURES - METRIC SEPTEMBER 1998

be sufficient reasons to close the temporary


structure. The 5 year highwater elevation
shall be painted with fluorescent paint on
the temporary structure, at a visible location.
This shall be included as incidental to 614
Maintenance of Traffic, as per plan.

5-4

You might also like