Professional Documents
Culture Documents
assurance o"
ther examination shows a pile with an apparent defect to be subse-
quently sound.
Therefore, after implementing a QA programme of integrity testing
on up to 100% of the working piles, using an integrity testing system
sore~ ~i e that may be less than 100'!. reliable at detecting defective and non-
defective piles, how confident can a foundation designer be in the con-
struction quality of the entire piling system, and thereby the final
piled foundation? Also, what is the minimum proportion of piles that
should be tested on a project, under certain conditions, to achieve an
"ounce ai;ions acceptable level of quality assurance?
This paper shows how the use of statistics and probability theory
may help answer such questions. Through the use of a statistical
approach, a foundation designer may be able to quantify their level of
By Gordon Cameron, PhD research student, confidence in the foundation quality, in addition to deciding on an effi-
Napier University and Tim Chapman, associate cient QA programme of integrity testing. Previously developed statis-
tical approaches have not taken into account the inaccuracy of the
director, Arup Geotechnics. integrity testing process and the likelihood that a wrong diagnosis
could be made regarding the true pile quality. This paper presents and
discusses the results of analyses performed using a more detailed sta-
The performance of a bored piled foundation is affected by the con- tistical sampling approach, which considers the reliability of the
struction quality of the individual piles comprising the piling system. integrity testing system.
For the purposes of quality assurance, a programme of non-destruc-
tive integrity testing (NDT) is usually implemented on a specified per- Bored piling and the occurrence of defects
centage of the working piles. Traditionally, the proportion of piles to In general, piling contractors produce bored cast insitu piles to the best
be tested is decided upon by the foundation designer based on site-spe- of their ability, following industry best practice to reduce the likeli-
cific knowledge, engineering judgement and his prior experiences of hood of faults. Nevertheless faults can still occur both during and after
NDT. This paper shows how the use of statistics and probability theo- construction in a small proportion of a pile population, with the fac-
ry may help influence this decision. tors in Table 1 influencing the number of piles affected on a given site.
Thorburn and Thorburn (1977) and Fleming et al (1985) provide a com-
Introduction prehensive review of the numerous types of piling fault that can occur
Bored cast insitu piling is regularly specified in the UK to support the in bored piles along with their variety of causes.
ever-taller structures that are being built in urban locations. However The presence of a piling fault does not necessarily imply that a pile
the high degree of contractor workmanship, experience and supervi- cannot be used for its intended purpose. Once constructed, there must be
sion necessary in construction, coupled with the naturally variable a belief that each and every pile satisfies three general design criteria:
soil and groundwater conditions on site, makes bored cast insitu piles ~ Meet serviceability limit state requirements and support a proposed
particularly vulnerable to structural faults and variable in construc- working load without settling by more than is permissible.
tion quality (Thorburn and Thorburn, 1977). ~ Meet ultimate limit state requirements and carry a specified load
The subterranean nature of their formation makes direct, visual with an adequate factor of safety against failure.
inspection of the final product impossible in most cases. Faced with ~ Remain durable throughout the design life of the structure, such
uncertain quality, it is unknown whether the piles will be suitable for that the pile is not affected by time dependent activities like corrosion
their intended operational function. Therefore to verify satisfactory of the steel reinforcement or chemical attack of the concrete, which
construction and detect any defective piles that may exist, non-destruc- would affect its ability to continue satisfying the first two criteria.
tive integrity testing is usually implemented on a specified percentage Some faults that occur will be more serious than others, given the
of the pile population. site specific operating conditions of a particular foundation. However,
Blanket inspection of every pile is the most conservative yet widely any fault that is likely to adversely affect performance, safety or dura-
adopted quality assurance (QA) strategy in the UK and internationally. bility of a pile, in either the short or long term, should be considered a
However, when this is impossible, sampling inspection (eg testing less defect, with a pile containing one or more defects being classified as
than 100% of the piles) is conducted. Due to a lack of codified recom- defective.
mendations or quantitative guidance, the number of piles tested in Some information on the frequency of defective bored piles, identi-
such a case is traditionally decided upon by the foundation designer. At fied through NDT inspection, can be taken from the results of surveys
its best, this decision is based on detailed construction observations, published in the technical literature. Davis and Dunn (1974) report
site-specific knowledge and engineering judgement; at its worst, this 9.7% defective out of a total 717 piles tested on five projects; Fleming et
may be little more than a token number of piles chosen purely to satis- al (1985) found 1.5% defective out of a total 5,000 piles tested and 1.9%
fy contractual QA obligations. defective out of a further 4,550 piles tested; Ellway (1987) reports 4.2%
Furthermore, due to the indirect nature of their examination, few defective of a total 4,400 piles tested; Thasnanipan et al (1988) state 3.3'!a
methods of integrity testing are infallible. A misclassification of the defective of a total 8,689 piles tested; Lew et al (2002) report 7'!a defec-
true pile quality caused by an inaccurate integrity test or an inaccu- tive within a population of 380 piles tested and 1.5% defective of a total
rate interpretation of a test result can either lead to a defective pile 5,000 piles tested. Preiss and Shapiro (1981) suggest that approximately
going undetected (false-negative result) and being mistakenly incorpo- 5% to 10% of the piles on a project could be defective.
rated into the foundation or a sound pile being wrongly condemned Obviously, there are numerous factors influencing the quality of
(false-positive result) and subjected to unnecessary inspection or reme- the piling work in each case, some of which may be noted in Table 1,
dial work.
Incorporating defective piles WNe1:Fscheeewf csehieeeecethegNOINrefpuegosspwecelsrceo
into the foundation system may
adversely affect its performance,
safety or durability, and depend- ~ L::
~ fhe em~ay of glwNNI =::: ==::=swese NNI snc RNI wNh Nepal
~
~ rseaaee
Of the eiennme NNNWN CSSNNNNW gehWg fiWN ~ ihgelhNI SNO meeeaaen"
ing on the redundancy offered by
the piling layout and the robust-
ness of the superstructure, result
~
Chgl Seg Seem eence Wgh S ghNNI PNS InNI Seger Sheger efsaanaaei ennnnmnm
~ SNPPlr Of aamam Of CWIOCIIPNNIr
~ IPoa eoi aatmaeee Of enemas mnaam PIOCONINOS fere PWNMISr SON WNI os eiaeaanaam CeednhNN
W
in failure with consequential ~ IOCOI ef WWIONSSchlP Seg Sne eiaisea eaenan IINAIg aeneas eennae
remedial costs or even loss of life. ~ as~ay Of in eoe meaam arseasies OS NIS Pghgl WWh
Alternatively, implementing ~ gflOCIS Of gleeed nnseeaaimam SINI SNONSINC NWhgl ennea>eases INh aammae
unnecessary inspection or reme- ~ Npgaeiaa mac NWNNNI Seg CWO hl a maimag pge INNNI IO NNSI CNION hNNI
dial work on sound piles may
of the piling system. Figure 1 shows the layout of a typical piled foun- 0 0 0 0 0 0 0 0 0 0
dation. The pile population comprises 100 piles, with five piles forming
each pile group and 20 pile groups forming the piling system. Normally, 00 0+
0 0 0 0 0+
0 0 00
a project team's requirements of a piled foundation are that it must be
constructed as quickly as possible, as cheaply as possible and perform
adequately in operation (Chapman and Marcetteau, 2004).
In the UK piling industry the use of single large diameter bored
00 0 0 0 0 0 0 0+
0 0 0 0+
piles is now often favoured to support a column instead of several
0+
0 0 0 0 0+
0 0 0 0
smaller piles in a group. In many cases the direct piling costs
associated with this type of layout are greater than that for a pile
group, but the substructure costs attributed to a system of single
piles are generally less, due to pile caps being unnecessary. The main
reason for choosing single piles is that the substructure tends to be
constructed more rapidly so long as the rate of concrete supply to
the site is not a constraining factor. However as shown in Table 2, the
consequence of a defect in any individual pile depends on the a non-redundant group as one for which failure of a single pile
redundancy offered by the piling layout. Larger pile groups are will adversely affect the structural column its supports, with limited
inherently more redundant than smaller groups or single pile groups or no ability of other piles supporting the same column to mitigate
due to the reserve capacity offered by neighbouring piles and the its effects.
ability to redistribute load through the soil and pile cap (Zhang et al, Defects are particularly critical for single large diameter piles
2001; Paikowsky, 2003). because if such a non-redundant pile is unable to support its working
Table 2 illustrates the likely consequences of a defect causing a loss load this may lead to excessive settlement of the column it supports,
of pile capacity, when single and multiple piles are favoured for the thereby causing significant distortions in the superstructure. Thus, as
foundation layout. Some pile groups may tolerate the presence of the level of redundancy offered by a pile group diminishes, it becomes
a defective pile without being significantly adversely affected, due to a more crucial to assure the construction quality of every pile to avoid
higher level of redundancy being offered. Paikowsky (2003) defines foundation problems.
~&i !lg'A 1 .' ', '' =i. '' ~f'' ' aat 5 A~~.. 'i 'o .w,~aquas ~af'i tite~
Pile testing
There are two fundamentally dif-
ferent uncertainties associated
with foundation piles that tend to
""+ n'=;-t.s.u ~ 't., - 'tsi-s-.' as'~-;I be investigated through testing:
Pile capacity: Will the pile satis-
factorily withstand a specified
loading?
Pile integrity: Is the pile of the
correct dimensions and structur-
al quality?
Bored pile capacity is tradi-
tionally determined through stat-
':l.'I'f) "t I::-":4"-';i'~'ttg)P:4~'~if~<~~ "".S4~'tiSQ""I'6W~a nit $.:-" W'~"'W=':~~'4'~fbsg<j'"-i ic load testing. The load test
~-,.*4>,"j;,*.,'.,':t'6'nt:.'--, j, "':,'::,'y~~@kj4p@~;:u:,i~>~~'~~~"Wet@t, *'W~:,t"..>';i!inn~A'~~<>at''in".L".~
I',;;,"'i
directly examines pile perfor-
mance and establishes whether
there is enough strength provid-
ed by the pile and enough resis-
tance provided by the surround-
ing ground to support an applied
load with an acceptable amount
't'tltttf" 4 silt"pit i't'it 8 -" i'.~ )I I)itjeintN ~')gqi ettft'w+P%~ of settlement (Fleming et al,
1985).
I'!! Pile integrity is traditionally
,
CljiiNaeilgigtgteI4(4tugS'eel)fr,,
~ggRtaeymaye~'~f)
,'otal
izr Tolerable number of defechve piles: TD = (ND -nD) + ud = (ND nD) + (nD ddl = ND dd
Unselected defective piles
(ND nDi
* Defectrve piles
r'efectwe
r Defechve piles correctly
inthe population Defective detechon classified defective
(ND) reliability Detected defecdves
r (( - Eil
piles in the number of piles
selected sample c(ass!bed def ectwe
Defectwe piles incorrectly
! x x False-negatnie c(assr(red nondefectrve
(nDt)
t
r
classrhed nondefectwe
Nondefectwe piles nDt)
(N) ln
Non defechve correctly
detection reliabihty c(assrhed nondefechve
r
(i - Eio)
r e)g,t-.~v4<~bWirr 'WQ zmlthv Nondefective piles r
(xxl
r
PA.",'~ksT'='"vnaaH.W straw in the selected sample i
ln nD) False-positive incorrecdy
inspection error classified defective
Norrdefechve piles
(Ein ) f
(p)
in the population
(N NDI
Unselected i
nondefective piles r
(N-ND-n+ nD) !
='-;;w~'1;I'~<,',v4vglvrdcxt ';.P r<Arlm)) 4'~!;"'rue
Known state
state of nature
~r I
Testing process
r~
I
Observed state based
on teshng process
ber of defective piles remaining, and thus incorporated into the final same for each type of integrity test, then to achieve a predetermined
piling system, after the implementation of a programme of integrity level of quality assurance, the more reliable the test is the more effec-
testing and subsequent repair. tive and efficient the testing programme due to the smaller sample of
As shown in Table 2, it may be possible for a foundation to tolerate a piles to be tested.
number of defective piles without being significantly adversely affect- However in reality, the cost and time to test a pile varies with the dif-
ed, due to the redundancy offered by the piling layout. Therefore, to ferent NDT methods. For example, testing a pile using a SE or TDR
assure foundation quality through a programme of non-destructive method may only take a few minutes (10 to 20 piles tested per hour with
testing, at least all but a tolerable number of defective piles must be good access (FPS, 1999)) and cost typically f3 to y5 per pile in addition
detected. The degree of confidence in satisfying this QA criterion (level to a site mobilisation fee and minimum testing charge, while a CSL test
of quality assurance achieved) can be quantified through the use of a may take up to an hour to perform and cost hundreds of pounds
statistical procedure. Referring to Figure 3, the statistical analysis depending on the length of the pile and the number of pre-installed
answers the question: access tubes.
Accounting for such factors in achieving a predetermined level of
What is the probability of detecting at least all but a tolerable number quality assurance, increasing the reliability of the integrity testing
of defective piles amongst the (nDt) apparently defective piles detected system improves the testing effectiveness, as a smaller sample of piles
and subsequently repaired within a sample of (n) piles tested at random must be tested. However the testing efficiency does not necessarily
using an integrity test with a defective and non-defective detection relia- improve due to the increased time and cost of testing each pile with a
blllty of I-Efn and I-Efp respectively, given that a total of 1VD defective more reliable test method.
piles are assumed to initially exist within a population of (N) piles prior Most foundation designers like to believe that they are achieving
to the programme of inspection and repair? high levels of confidence during integrity testing. However, even when
a NDT programme is carried out on an entire pile population, a foun-
This degree of confidence is given symbolically as: Pr[dd~ (ND TD)]. dation designer can rarely guarantee that there will be absolutely no
defective piles incorporated into the final foundation.
Discussion of results In fact, the results show that even if blanket inspection of every pile
The results of statistical analyses, for a range of likely practical val- is performed, in the hope of achieving total quality (ie TD = 0), the inac-
ues, are given in Figure 4. Each graph shows the number of piles test- curacy in the integrity testing system only allows for low levels of con-
ed versus degree of confidence, within a population of 100 piles for a fidence to be achieved. For example, assume that the population con-
given number of defective piles in the population, testing reliability tains 5'zo defectives and the integrity testing system used is 80'ro reli-
and tolerable number of defective piles. able. If a programme of 100'Zo inspection is carried out under these
Assume that the pile population contains 5'/o defectives. If the foun- conditions, the likelihood of detecting all the defective piles in the test-
dation can tolerate up to four defective piles (TD = 4) and the integrity ed sample is only 32'to. Thus, on the basis of these data, foundation
testing system used is 100 zo reliable at detecting defective piles, then a designers need to allow for either accepting:
totally competent testing specialist would be 90'!o confident in detect- ~ lower levels of confidence in assuring total quality of the founda-
ing at least one defective by testing 37 piles. However if the test is only tion;
60cvo reliable then the same testing sPecialist would be only 71 "o confi- ~ that the piled foundation should tolerate a number of undetected
dent. Furthermore, to achieve the same 90 yo level of confidence, with a defective piles.
60g" reliable test, 62 piles should be inspected. Thus, to achieve the Furthermore, for a given level of confidence, the more defective piles
same level of quality assurance with the less reliable integrity test, that can be tolerated, then the less integrity testing is required. Thus,
almost twice as many piles should be tested. Therefore, the results the amount of in built redundancy offered by the piling system (tolera-
show that: ble proportion defective) may influence the decision as to how many
~ for a given number of piles tested, a greater degree of quality assur- piles should be integrity tested.
ance will be achieved with a more reliable integrity testing system It is the general recommendation of many (Turner, 1997; Paikowsky,
Used; 2003) that every pile on a given site should be post construction tested
~ a more reliable integrity testing system requires a smaller sample of for defects. However, in practice it is often difficult to test 100'Io of the
piles to be tested to achieve a pre-determined level of quality assur- working piles due a number of factors including cost, time and access.
ance. As foundation construction is usually on a project's critical path, any
A programme of integrity testing is effective if the QA criteria are delays that may occur during pile testing can adversely affect the
satisfied with an acceptable level of confidence and efficient if these progress of all follow-on activities, the direct cost of which may exceed
objectives are accomplished with as little effort as possible. the value of the entire piling contract (Chapman and Marcetteau, 2004).
If it is assumed that the cost and time required to test a pile is the As such, there is a significant advantage in terms of cost and pro-
~
Number of piles tested
lihood that suspected piles will
have already been identified
prior to integrity testing. The
findings of this paper reinforce
gramme if some piles could be omitted from testing. these well-accepted principles.
Consider a programme of inspection carried out on a population of
100 piles, assumed to contain 5% defectives, using an integrity test that Acknowledgefnents
is 80% reliable. Under these conditions, Figure 5 shows the increase in The authors gratefully acknowledge the comments given during the
confidence (quality assurance) gained for every additional 10 piles preparation of this paper by Dr Allen Davis, Dr Mike Duncan, Mr
integrity tested. It is shown that where the foundation can tolerate up Bernie Hertlein, Mr Tom Pelnik, Dr Hugh St John, Prof Kenneth Preiss
to four defective piles, most benefit comes from the initial piles tested. and Mr Aaron Zdinak.
However, where the foundation cannot tolerate any defective piles with-
in it, most benefit comes from testing the final piles. Therefore, the
greater the reliance on each individual pile in a population, the more Cameron G, Wamuziri SC. Smith IGN and Chapman TJP (2002) Statistical sampling
schemes for integrity testing of piled foundations, Proceedings of United Engineering
important it is to check the integrity of every single pile, even when Foundation International Conference on Probabilistics in Geotechnics: Technical and
performing 1009o testing may be disruptive to the construction pro- economic risk estimation, Graz. Austria, 15-19 September 2002, p129.136.
gramme. Chapman TJP and Marcetteau A (2004) Achieving economy and reliability in geotechni-
Figure 5 shows that in some cases the added value gained by the last cal design for a building project. The Structural Engineer. in print.
Davis AG (1999) Assessing the reliability of drilled shaft integrity testing,
piles tested could be judged by the foundation designer not to be worth Transportation Research Record 1633, TRB, National Research Council, Washington DC,
the time and money involved in the testing. This is particularly true on p108-116.
large projects with a rapid construction programme, where the con- Davis AG and Dunn CS (1974) From theory to field experience with the non-destructive
vibration testing of piles, Proceedings of the Institution of Civil Engineers, Vol. 57, Part
struction manager wants the groundwork contractor to follow on 2, p571-593.
directly as the piling contractor leaves site. EIIway K (1987) Practical guidance on the use of integrity tests for quality control of cast
Often on these projects, there is immense pressure not to integrity insitu piles, Proceedings of the first international conference on foundations and tun-
test the final say 20 to of the piles to allow an earlier package handover. nels, London, p228-234.
Eurocode 7 (1997) Geotechnical Design Part I - General rules, DDFNV 1997-1:1995,
The analysis shows that such an omission may be possible only if the European Committee for Standardisation.
tolerable proportion of defective piles is high. Hence, there could be pro- Federation of Piling Specialists (1999)The essential guide to the ICE specification for pil.
gramme advantages in selecting a more redundant foundation system. ing and embedded retaining walls, The Institution of Civil Engineers, Thomas Telford
Limited, London.
Fleming WGK, Weltman AJ, Randolph MF and Elson WK (1985) Piling engineering,
Conclusion Surrey University Press.
Many engineers like to perform 100% inspection in the hope of detect- Hertlein BH (1998) Integrity testing friend or foe?, Proceedings of the 23rd Annual
ing all the defective piles that may exist on a site. However, the results Members Conference of the Deep Foundations Institute, Geosystems for future trans.
portation systems, Seattle, Washington.
of statistical analyses have shown that even if every pile is tested, the ICE (1988a) Specification for piling. The Institution of Civil Engineers, Thomas Telford
inaccuracy of the integrity testing system used does not allow for high Limited, London.
levels of confidence to be achieved. ICE (1988b) Specification for piling Contract documentation and measurement, The
Institution of Civil Engineers, Thomas Telford. London.
Furthermore, in some cases testing slightly less than 100% of the ICE (1996) Specification for piling and embedded retaining walls. The Institution of Civil
piles may be a viable option, with little reduction in the level of quali- Engineers, Thomas Telford, London.
ty assurance occurring but with potential benefit in terms of cost and Lew M, Zadoorian CJ and Carpenter LD (2002) Integrity testing of drilled piles for tall
buildings, Structure Magazine, National Council of Structural Engineers and the ASCE,
programme savings. Nevertheless, it must be highlighted that the only October 2002.
way that this can happen is by selecting a more redundant foundation National Research Council (1995) Probabilistic methods in geotechnical engineering, US
design. National Academy Press.
Hence, the redundancy offered by supporting columns on a layout of Paikowsky SG (2003) Load and resistance factor design for deep foundations, Report
NCHRP 24-17, National Cooperative Highway Research Program, Transportation
pile groups, as opposed to single large diameter piles, may serve as a Research Board, National Research Council in 2003.
major reason for a decrease in the amount of integrity testing neces- Preiss K and Shapiro J (1979) Statistical estimation of the number of piles to be tested on
sary for quality assurance of a bored pile foundation. a project, RILEM Commission on Non-Destructive Testing, Stockholm.
As in any modelling activity, assumptions and simplifications have Preiss K and Shapiro J (1981) Statistical considerations in pile testing, Congress on the
Mechanics of Soils, Stockholm, p799-802.
been made to the real life pile construction and integrity testing Thasnanipan N, Maung AW and Baskaran G (1988) Sonic integrity test on piles founded
sequence to model the problem in a statistical manner. in Bangkok subsoil signal characteristics and their interpretations, Proceedings of the
Notwithstanding, the use of these statistical results, supplementing Fourth International Conference on Case Histories in Geotechnical Engineering, St
Louis, Missouri, 9-12 March, p1086-1092.
experience and sound engineering judgement, may provide a more Thorburn S and Thorburn JQ (1977) Review of the problems associated with the con-
rational basis for deciding on a suitable level of integrity testing, there- struction of cast in place concrete piles, DoE and CIRIA Piling Developnient Group,
by helping to improve foundation safety and construction efficiency. Report PG2.
The paper highlights the folly of absolute reliance on the results of Turner MJ (1997) Integrity testing in piling practice, Construction Industry Research
and Information Association, CIRIA Report 144.
integrity testing as the sole arbiter of quality in bored pile founda- Weltman AJ (1980) Pile load testing procedures, DoE and CIRIA Piling Development
tions. While integrity tests have a valuable role to play in the detection Group, Report PG7.
of defects, statistical analysis accounting for inaccuracies in the tech- Weltman AJ (1977) Integrity testing of piles: a review, DoE and CIRIA Piling
Development Group, Report PG4.
niques, indicates that a high level of dependence should not be attrib- Zhang L, Tang W and Ng CWW (2001) Reliability of axially loaded driven pile groups,
uted to the results of integrity tests alone. Moreover, the best approach Journal of Geotechnlcal and Geoenvl ronmental Engineering, vol. 127, No. 12, p1051-1060.
in ensuring quality of piled foundations is to follow the basic princi-